PP 1: Display Stock/Requirements List

Exercise Use the SAP Easy Access Menu to display the Stock/Requirements List. Time 5 min

Task Review the material status of your Deluxe Touring bike (finished good) in the Dallas plant using the Stock/Requirements list.

Name (Position) Lars Iseler (Production Order Worker)

The Stock/Requirements list contains up-to-date information on the current status of inventory on hand, requirements, and receipts. It is a dynamic list that allows you to view changes made to material status.

Stock/Requirements List

1. To review the material status, follow the SAP Easy Access menu path:

Logistics ► Production ► Production Planning ► Demand Management ► Environment ► Stock/Requirements List

The following screen will appear.

Menu path

image2.png

2. First of all, you need to find the material number(s) for your Deluxe Touring bikes. In order to do so, click in the Material field and press F4 (or click on the search icon image3.png next to the field). This will produce the following search screen.

F4

image4.png

3. Make sure that you are on the Material by Material Type tab. If not, you can use the image5.png icon (in the top-right corner) to display a list of all search tabs available.

4. In the Material Type field, select Finished Product (FERT). In order to display your Deluxe Touring bikes only, you need to define two more search criteria. First, in the Material Description field type Deluxe*. Second, in the Material field (which is the field for the unique material number) type *###. Remember to replace ### with your three-digit number, e.g. *014 if your number is 014.

Finished Product

Deluxe*

*###

5. Before pressing Enter or clicking on image6.png to start the search compare your entries with the screen below.

image7.png

The result of this search should give you a list of:

a) all finished goods,

b) which name (short description) starts with Deluxe,

c) which material number end with your number (###).

image8.png

6. You should get a list of three different Deluxe Touring bikes – black, red and silver (please note that the material numbers in your screen will be different). Double-click on your red Touring bike which will copy its unique material number (DXTR3###) into the Material field.

DXTR3###

7. In addition to the material number, in the Plant field select GBI’s manufacturing facility in Dallas (DL00). Then, press Enter or click on image9.png. You should be displayed a screen similar to the one shown below.

DL00

image10.png

As you can see, GBI has currently no red Deluxe Touring bikes on stock. Repeat the same procedure for the other two deluxe bikes (black and silver).

8. Click on image11.png to return to the SAP Easy Access Menu.

image12

image13

PP 2: Display Bill of Material

Exercise Use the SAP Easy Access Menu to display a bill of material. Time 5 min

Task Review the components of your black Deluxe Touring bike and the components of the Touring Aluminum Wheel Assembly within the finished bike bill of material.

Name (Position) Jun Lee (Production Supervisor)

A bill of material (BOM) is a list of the components that are needed to create a given product. The list contains the description, the quantity, and unit of measure. The BOM can contain items of different item categories such as stock items, non-stock items, document items, and text items.

Bill of Material (BOM)

1. To review a bill of material, follow the menu path:

Logistics ► Production ► Master Data ► Bills of Material ► Bill of Material ► Material BOM ► Display

This will produce the following screen.

Menu path

image14.png

2. The system should have already defaulted in the material number (DXTR1###) and the plant (DL00) from the previous exercise. It also assumes that you would like to display the BOM valid today (note Valid From and Valid to dates). In addition, the system requests the usage of this BOM. Click in the BOM Usage field and use F4 to display possible usage types. Select usage type 1 for plant DL00. Then, press Enter to display the BOM of your black Deluxe Touring bike

DXTR1###

DL00

F4

1

image15.png

The assembly indicator (column Asm; see the circled area above) marks the item with components that have their own BOM. In this case, it is the Touring Aluminum Wheel Assembly.

3. Double-click on this checkbox (indicator for Wheel Assembly TRWA1###). This will produce the following screen.

TRWA1###

image16.png

4. In the Display assembly screen, click on image17.png . This will display the materials that make up the assembly of TRWA1###.

5. Repeat the procedure for your red and the silver Deluxe Touring bike to identify the differences in their bills of materials. You may open another (parallel) session to compare the BOMs in separate screens (use the image18.png icon in the system tool bar).

6. Click on image19.png twice to return to the SAP Easy Access Menu.

image20

image21

PP 3: Display Multi-Level Bill of Materials

Exercise Use the SAP Easy Access Menu to display a multi-level BOM. Time 5 min

Task Review the BOM for your black Deluxe Touring bike from a multi-level hierarchy level.

Name (Position) Jun Lee (Production Supervisor)

1. To display a multi-level BOM, follow the menu path:

Logistics ► Production ► Master Data ► Bills of Material ► Reporting ► BOM Explosion ► Material BOM ► Multilevel BOM

Menu path

2. In the following screen, enter (or find) Material DXTR1### (replace ### with your number), Plant DL00, and BOM Application PP01 (Production-General). Then, click on image22.png to display the BOM structure for your bike valid today. If the system requests a quantity, enter 1.

DXTR1##

DL00

PP01

1

image23.png

3. Click on image24.png to go back to the initial screen. There, you click on image25.png (View). On the following screen, in the Display field group select Variable list and click on image26.png.

Variable list

image27.png

4. After reviewing the components of your Finished Bike, find and select the following item in the system menu:

Goto ► Graphic

This should produce the following BOM hierarchy graphic.

image28.png

You can use the Zoom in and Zoom out buttons to resize the graphic.

5. Click on image29.png to exit the graphic screen. Then, click on image30.png again to return to the SAP Easy Access Menu.

image31

image32

PP 4: Display Routing

Exercise Use the SAP Easy Access Menu to display a routing. Time 10 min

Task Review the routing for your black Deluxe Touring bike.

Name (Position) Jun Lee (Production Supervisor)

A routing is a series of sequential operations carried out to produce an end product. Routings contain information on where work is to be performed, steps that need to be completed, and time lines assigned for each operation.

Routing

1. To review a routing, follow the menu path:

Logistics ► Production ► Master Data ► Routings ► Routings ► Standard Routings ► Display (CA03)

Menu path

Enter Material DXTR1### and Plant DL00. If group number is populated with some value, please remove that value (i.e., make this blank).

image33.png

Then, click on image34.png to display the following list of operations.

DXTR1###

DL00

image35.png

2. Select image36.png to display the list of components (BOM data). None of them is assigned to any specific operation (note that column Oper./Act. is empty which means that all components are used from the first operation)

image37.png

3. Select image38.png to go back to the operation overview. Then, click on image39.png.

This will display the following operation graphic (this example is simple and every operation is sequential. However, a network structure is possible)

image40.png

4. Click on image41.png to go back to the operation overview. Then, find the following system menu item:

Extras ► Scheduling ► Schedule

This should produce the following screen.

image42.png

5. Enter Scheduling type 1 and Lot size 10. Click on image43.png. In the following screen, find and enter overview variant 000000000001 (Operation segments). Confirm your entry with image44.png (You’re setting the setting basic information for scheduling operations).

1

10

000000000001

6. In order to view the schedule in a Gantt chart, click on image45.png. Find the following system menu item:

Time unit ► Minute

Also, display the legend by clicking on image46.png .

image47.png

7. Click on image48.png and on Yes to quit the Gantt chart. Then, click on image49.png to return to the SAP Easy Access Menu.

Yes

image50

image51

PP 5: Display Routing/BOM in Engineering Workbench

Exercise Use the Engineering Workbench to display a routing and a BOM. Time 10 min

Task Review the BOM and routing simultaneously.

Name (Position) Jun Lee (Production Supervisor)

The Engineering Workbench (EWB) provides an environment where you have the ability to create, change, and delete BOM and routings. More importantly, it gives us the ability to create work lists and work on specific parts of a BOM or routing without locking the entire object.

Engineering Workbench (EWB)

1. To review BOMs and routings simultaneously, follow the menu path:

Logistics ► Production ► Master Data ► Engineering Workbench

Menu path

2. In the following window, find and select Current Working Area FK (Test Work Area) using the F4 help and click on image52.png.

FK

3. In the EWB: Selection Criteria for BOM Headers screen, enter (or find) Material DXTR1### (replace ### with your number) and Plant DL00. Then, click on image53.png . If the system requests a Change number in a separate screen, leave it blank and click on image54.png.

DXTR1###

DL00

4. In the EWB: BOM Headers Overview screen, if the image55.png icon is not grayed out, click on it to activate the browser. If the system requests an Application, enter PP01 and click on image56.png.

PP01

5. In order to see the icons image57.png and image58.png, use the mouse to widen the browser window (as shown below).

image59.png image60.png

6. Click on image61.png (left) to select the line DXTR1###, DL00, Deluxe Touring Bike (black). Then, click on image62.png to expand the tree completely. This might take a few seconds and will result in the following screen. This operation may not work in some clients. In this case, you can expand the node by clicking on▼.

image63.png

The subtree marked with image64.png comprises the entire BOM for your Deluxe Touring Bike, the subtree marked with image65.png lists all routing operations.

7. Double-click on operation 0020 (Attach seat to frame) to call up specific information. Here, you could change the routing details for this operation if necessary.

0020

8. Click on image66.png and on Yes to return to the SAP Easy Access Menu.

Yes

image67

PP 6: Display Work Center

Exercise Use the SAP Easy Access Menu to display a work center. Time 15 min

Task Review a work center in GBI’s plant in Dallas.

Name (Position) Jun Lee (Production Supervisor)

A work center is a location where operations are carried out for an order. Capacities (setup, machine, and labor) are assigned to work centers so that they can be allocated and consumed within an order in a controlled and predictable manner. The work center capacity is created in and assigned to a single work center.

Work center

1. To review a work center and the capacity assigned to it, follow the menu path:

Logistics ► Production ► Master Data ► Work Centers ► Work Center ► Display

Menu path

2. Enter Plant DL00. In the Work center field, use the F4 help to display all three work centers in Dallas. In the search results, double-click on the DL Assembly work center to select it which should copy its number (ASSY1000). Click on image68.png. Note that if you cannot see work centers and get the message, “No object found”, first click the OK button in the message, click icon

image69.png (Search Other Criteria), and select Work Center among the list.

image70.emf

DL00

F4

ASSY1000

3. On the Basic Data tab, find out who is the person responsible.

4. On the Default Values tab, click in the Control key field (ASSY) and select F4. On the following screen, single-click on the ASSY. Then, select image71.png, which will indicate what is required when ASSY is used.

ASSY

F4

image72.png

5. Select image73.png. Click on the Scheduling tab.

6. On the Scheduling tab, click in the Processing formula field and select image74.png (Display formula). After acknowledging the formula, press image75.png to continue.

7. After selecting image76.png (Test formula), enter Operation Quantity 100 EA, Base Quantity 1, No. of Splits 2, Setup 7 MIN, and Labor 7 MIN. Then, select image77.png (Calculate). The following screen will appear.

100 EA

1

2

7 MIN

7 MIN

image78.png

8. Click on image79.png to continue. Did the Processing formula work correctly?

image80.png (((7 * 100) / 1) / 2) = 350

9. Select image81.png to go back.

10. Capture the screen (schedule tab).

On the Costing tab, what Controlling Area and Cost Center are defined?

11. Click on image82.png to return to the SAP Easy Access Menu.

Please capture this screen (after 9. Select “End Formula Test”). Please upload this image (e.g., image file or Word document) to the blackboard