HF week's
Copyright 2012 John Wiley & Sons, Inc.
Chapter 7
Budgeting: Estimating Costs and Risks
*
7-*
Estimating Project Budgets
- Like any forecast, this includes some uncertainty
- There is uncertainty regarding usage and price
Especially true for material and labor
- The more standardized the project and components, the lower the uncertainty
- The more experienced the cost estimator, the lower the uncertainty
7-*
Rules of Thumb
- Some estimates are prepared by rules of thumb
Construction cost by square feet
Printing cost by number of pages
Lawn care cost by square feet of lawn
- These rules of thumb may be adjusted for special conditions
- However, this is still easier than starting the estimate from scratch
7-*
Estimating Budgets is Difficult
- There may not be as much historical data or none at all
- Even with similar projects, there may be significant differences
- Many people have input to the budget
7-*
Estimating Budgets is Difficult Continued
- Multiple people have some control over the budget
- There is more “flexibility” regarding the estimates of inputs (material and labor)
- The accounting system may not be set up to track project data
- Usage of labor and material is very lumpy over time
7-*
Types of Budgeting
- Top-down
- Bottom-up
- Negotiated
7-*
Top-Down Budgeting
- Top managers estimate/decide on the overall budget for the project
- These trickle down through the organization where the estimates are broken down into greater detail at each lower level
- The process continues to the bottom level
7-*
Advantages
- Overall project budgets can be set/controlled very accurately
A few elements may have significant error
- Management has more control over budgets
- Small tasks need not be identified individually
7-*
Disadvantages
- More difficult to get buy in
- Leads to low level competition for larger shares of budget
7-*
Bottom-Up Budgeting
- Project is broken down into work packages
- Low level managers price out each work package
- Overhead and profits are added to develop the budget
7-*
Advantages
- Greater buy in by low level managers
- More likely to catch unusual expenses
7-*
Disadvantages
- People tend to overstate their budget requirements
- Management tends to cut the budget
7-*
Work Element Costing
- Labor rates include overhead and personal time
The book uses estimates of 84% and 12%, respectively, in one example
- Direct costs usually do not include overhead
- General and administrative (G&A) charge
7-*
An Iterative Budgeting Process–Negotiation-in-Action
- Most projects use some combination of top-down and bottom-up budgeting
- Both are prepared and compared
- Any differences are negotiated
7-*
Project Budget by Task & Month
Table 7-2
7-*
Improving The Process of Cost Estimation
- Inputs from a lot of areas are required to estimate a project
- May have a professional cost estimator to do the job
- Project manager will work closely with cost estimator when planning a project
- We are primarily interested in estimating direct costs
- Indirect costs are not a major concern
7-*
Problems
- Even with careful planning, estimates are wrong
- Most firms add 5-10 percent for contingencies
7-*
Learning Curves
- Human performance usually improves when a task is repeated
- This happens by a fixed percent each time the production doubles
- Percentage is called the learning rate
7-*
Learning Curve Calculations
Tn = Time for nth unit
T1 = Time for first unit
n = Number of units
r = log decimal rate/log 2
7-*
Making Better Estimates
- Projects are known for being over budget
It is unlikely that this is due to deliberate underestimating
- There are two types of errors
Random
Bias
- There is nothing we can do about random errors
Tend to cancel each other
- Eliminate systematic errors
*
7-*
Risk Estimation
- Duration of project activities varies
- Amounts of various resources needed varies
- Value of accomplishing a project varies
- Can reduce but not eliminate ambiguity
- Want to describe uncertainties in a way that provides useful insight to their nature
7-*
Applying Risk Analysis
- Must make assumptions about probability distributions
Key parameters
Variables
- Estimate the risk profiles of the outcomes of the decision
Also know as probability distributions
- Simulation is often used
7-*
General Simulation Analysis
- Simulation combined with sensitivity analysis is useful for evaluating projects
- Would support project if NPV is positive and is the best use of funds
- Should avoid full-cost philosophy
Some overheads are not affected by changes
- Analysis gives a picture in terms of costs and times that will be affected
- Project is then reviewed using simulation
å
=
=
=
=
N
n
r
r
n
n
T
rate
r
n
T
T
1
1
2
1
time
Total
)
(
log