Final Exam: Earned Value Problem (total value of 50 points towards the final exam score)

Answer the following questions based upon the budget, cost ledger & percentage complete calculations on the following page. Assume the project is now at the end of the fifth week. Create the following status report for the end of week 5.

Status report: Ending week 5

Task

% Complete

EV

AC

PV

CV

SV

CPI

SPI

Design System

Finished

Draft Forms

Finished

Establish codes

Finished

Solicit

Bids

Finished

Collect Data

Finished

Setup Accounts

Finished

Program System

Finished

Merge Data

30%

Test System

0

Delivery Solution

0

Cumulative Total

Is the project performing better or worse than expected? Explain your answer

Material to use during your calculations and analysis:

12345678

Design system251510

Draft Forms1055

Establish Codes1515

Solicit Bids55

Collect Data30101010

Set-up Accounts1010

Program System50202010

Merge Data1515

Test Sytem2525

Deliver Solution2020

Total2051535354020152520

155085125145160185205

12345678

Design system22121000

Draft Forms808000

Establish Codes17012500

Solicit Bids606000

Collect Data4100101120

Set-up Accounts10000100

Program System5800232510

Merge Data800008

Test Sytem000000

Deliver Solution000000

Total1701236384638

124886132170

12345678

Design system2550%100%100%100%100%

Draft Forms100%100%100%100%100%

Establish Codes150%75%100%100%100%

Solicit Bids50%100%100%100%100%

Collect Data300%0%30%60%100%

Set-up Accounts100%0%0%100%100%

Program System500%0%35%75%100%

Merge Data150%0%0%0%30%

Test Sytem250%0%0%0%0%

Deliver Solution200%0%0%0%0%

Budget

Actual Costs

TasksBudget

Week

Cumulative

Week

TasksBudget

TasksCost

Week

Cumulative

Percentage Complete