Chapter 6: Project Schedule Management

Information Technology Project Management, Ninth Edition

Note: See the text itself for full citations

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

1

Learning Objectives (1 of 2)

Illustrate the importance that project schedules and good project schedule management can have in helping to make projects successful

Discuss the process of planning schedule management

Define activities as the basis for developing project schedules

Describe how project managers use network diagrams and dependencies to assist in activity sequencing

Explain how various tools and techniques help project managers perform activity duration estimates

Use a Gantt chart for planning and tracking schedule information, find the critical path for a project, and describe how critical chain scheduling and the Program Evaluation and Review Technique (PERT) affect schedule development

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

2

Learning Objectives (2 of 2)

Compare how schedule management is addressed using Agile vs. more predictive project approaches

Discuss how reality checks and discipline are involved in controlling and managing changes to the project schedule

Describe how project management software can assist in project schedule management and review words of caution before using this software

Discuss considerations for agile/adaptive environments

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

The Importance of Project Schedules (1 of 3)

Managers often cite delivering projects on time as one of their biggest challenges

Time has the least amount of flexibility; it passes no matter what happens on a project

Individual work styles and cultural differences may also cause schedule conflicts

Different cultures and even entire countries have different attitudes about schedules

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

Media Snapshot

In contrast to the 2002 Salt Lake City Winter Olympic Games (see Chapter 4’s Media Snapshot), planning and scheduling was very different for the 2004 Athens Summer Olympic Games and the 2014 Sochi Winter Olympic Games

Many articles were written before the opening ceremonies in Athens predicting that the facilities would not be ready in time

The Greeks even made fun of critics by having construction workers pretend to still be working as the ceremonies began, but the games cost more than twice the planned budget

The 2014 Winter Olympic Games in Sochi, Russia, suffered even greater financial loss

Originally budgeted at $12 billion, final costs reached over $51 billion, making it the most expensive games in history

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

The Importance of Project Schedules (2 of 3)

Project time management processes

Planning schedule management

Defining activities

Sequencing activities

Estimating activity resources

Estimating activity durations

Developing the schedule

Controlling the schedule

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

The Importance of Project Schedules (3 of 3)

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

7

Planning Schedule Management

Elements of a schedule management plan

Project schedule model development

Scheduling methodology

Level of accuracy and units of measure

Control thresholds

Rules of performance measurement

Reporting formats

Process descriptions

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

Defining Activities (1 of 2)

Defining activities involves identifying the specific actions that will produce the project deliverables in enough detail to determine resource and schedule estimates

Activity list: a tabulation of activities to be included on a project schedule

Activity name, activity identifier or number, and brief description of the activity

Activity attributes provide more information

Predecessors, successors, logical relationships, leads and lags, resource requirements, constraints, imposed dates, and assumptions related to the activity

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

Defining Activities (2 of 2)

A milestone is a significant event that normally has no duration

It often takes several activities and a lot of work to complete a milestone

They’re useful tools for setting schedule goals and monitoring progress

Examples: obtaining customer sign-off on key documents or completion of specific products

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

What Went Wrong?

At the U.S. Federal Bureau of Investigation (FBI), poor time management was one of the reasons behind the failure of Trilogy

System was supposed to integrate intelligence within the Bureau

In May 2006, the Government Accounting Agency said that the Trilogy project failed at its core mission of improving the FBI’s investigative abilities and was plagued with missed milestones and escalating costs

Sentinel replaced Trilogy in 2007

During a test exercise in 2011, Sentinel experienced two outages, and the FBI determined that the current hardware structure was inadequate

In 2014, the system still wasn’t working well

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

Sequencing Activities (1 of 6)

Sequencing process involves evaluating the reasons for dependencies and the different types of dependencies

A dependency or relationship is the sequencing of project activities or tasks

Mandatory dependencies: inherent in the nature of the work being performed on a project, sometimes referred to as hard logic

Discretionary dependencies: defined by the project team, sometimes referred to as soft logic. and should be used with care since they may limit later scheduling options

External dependencies: involve relationships between project and non-project activities

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

Sequencing Activities (2 of 6)

Network diagrams are the preferred technique for showing activity sequencing

Schematic display of the logical relationships among, or sequencing of, project activities

Two main formats are the arrow and precedence diagramming methods

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

Sequencing Activities (3 of 6)

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

14

Sequencing Activities (4 of 6)

Arrow diagramming method (ADM) (i.e., activity-on-arrow network diagrams)

Activities are represented by arrows

Nodes or circles are the starting and ending points of activities

Only show finish-to-start dependencies

Refer to the text for the step-by-step process of creating AOA diagrams

Precedence diagramming method (PDM)

Network diagramming technique in which boxes represent activities

Types of dependencies or relationships between activities

Finish-to-start

Start-to-start

Finish-to-finish

Start-to-finish

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

Sequencing Activities (5 of 6)

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

16

Sequencing Activities (6 of 6)

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

17

Estimating Activity Durations

Duration includes the actual amount of time worked on an activity plus elapsed time

Effort is the number of workdays or work hours required to complete a task and does not normally equal duration

People doing the work should help create estimates

An expert should review them

A three-point estimate is an estimate that includes an optimistic, most likely, and pessimistic estimate

Three-point estimates are needed for PERT and Monte Carlo simulations

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

Advice for Young Professionals

Some people find estimating to be challenging, especially for their own work

It is very important to develop this skill

Practice estimating how long it takes you to do different activities and then take actual measurements

Define the activity in detail to help make better estimates

If you realize that an activity estimate might not be a good one, let your team know as soon as possible so that adjustments can be made early in the project

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

Developing the Schedule

Uses results of the other time management processes to determine the start and end date of the project

Ultimate goal is to create a realistic project schedule that provides a basis for monitoring project progress for the time dimension of the project

Important tools and techniques

Gantt charts

Critical path analysis

Critical chain scheduling

PERT analysis

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

Gantt Charts (1 of 5)

Provide a standard format for displaying project schedule information by listing project activities and corresponding start and finish dates in a calendar form

Symbols

Black diamond: milestones

Thick black bars: summary tasks

Light gray horizontal bars: durations of tasks

Arrows: dependencies between tasks

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

Gantt Charts (2 of 5)

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

22

Gantt Charts (3 of 5)

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

23

Gantt Charts (4 of 5)

Adding milestones to Gantt charts

Many people like to focus on meeting milestones, especially for large projects

Milestones emphasize important events or accomplishments on projects

SMART Criteria for milestones

Specific

Measurable

Assignable

Realistic

Time-framed

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

Best Practice

Shawn Anchor suggests the 20-second rule in his book, The Happiness Advantage

People prefer the path of least resistance

For example, if you have to wait in line 20 seconds to get a second scoop of ice cream, you might resist it

Anchor recommends making it more difficult for yourself to be distracted at work by keeping email or websites closed while you are working

Save time by adding time to the distracting behaviors at work

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

Gantt Charts (5 of 5)

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

26

Critical Path Method (CPM) (1 of 2)

Network diagramming technique used to predict total project duration

Critical path: series of activities that determine the earliest time by which the project can be completed

The longest path through the network diagram and has the least amount of slack or float; amount of time an activity may be delayed without delaying a succeeding activity or the project finish date

Calculating the critical path

Develop a good network diagram and add the duration estimates for all activities on each path through the network diagram

Longest path is the critical path

If one or more of the activities on the critical path takes longer than planned, the whole project schedule will slip unless the project manager takes corrective action

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

Critical Path Method (CPM) (2 of 2)

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

28

Growing Grass Can Be on the Critical Path

The fact that its name includes the word critical does not mean that it includes all critical activities

Only accounts for time

Example: growing grass for Disney’s Animal Kingdom

There can be more than one critical path if the lengths of two or more paths are the same

Project managers should closely monitor performance of activities on the critical path to avoid late project completion

Critical path can change as the project progresses

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

Using Critical Path Analysis to Make Schedule Trade-Offs (1 of 3)

Free slack or free float

Amount of time an activity can be delayed without delaying the early start of any immediately following activities

Total slack or total float

Amount of time an activity may be delayed from its early start without delaying the planned project finish date

Forward pass

Determines the early start and finish dates

Backward pass

Determines the late start and finish dates

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

Using Critical Path Analysis to Make Schedule Trade-Offs (2 of 3)

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

31

Using Critical Path Analysis to Make Schedule Trade-Offs (3 of 3)

Task Name Start Finish Late Start Late Finish Free Slack Total Slack
A 8/3/15 8/3/15 8/5/15 8/5/15 0d 2d
B 8/3/15 8/4/15 8/3/15 8/4/15 0d 0d
C 8/3/15 8/5/15 8/5/15 8/7/15 0d 2d
D 8/4/15 8/7/15 8/6/15 8/11/15 2d 2d
E 8/5/15 8/11/15 8/5/15 8/11/15 0d 0d
F 8/5/15 8/10/15 8/14/15 8/17/15 7d 7d
G 8/6/15 8/13/15 8/10/15 8/17/15 0d 2d
H 8/12/15 8/19/15 8/12/15 8/19/15 0d 0d
I 8/14/15 8/17/15 8/18/15 8/19/15 2d 2d
J 8/20/15 8/24/15 8/20/15 8/24/15 0d 0d

Table 6-1 Free and Total Float or Slack for Project X

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

Using the Critical Path to Shorten a Project Schedule

Main techniques for shortening schedules

Shortening durations of critical activities/tasks by adding more resources or changing their scope

Crashing activities by obtaining the greatest amount of schedule compression for the least incremental cost

Fast tracking activities by doing them in parallel or overlapping them

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

Importance of Updating Critical Path Data

It is important to update the schedule with actual data

Note actual activity durations as they are completed

Revise estimates for activities in progress

Monitor changes to make informed decisions

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

Critical Chain Scheduling (1 of 4)

Considers limited resources when creating a project schedule and includes buffers to protect the project completion date

Uses the Theory of Constraints (TOC): management philosophy developed by Eliyahu M. Goldratt; attempts to minimize multitasking when a resource works on more than one task at a time

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

Critical Chain Scheduling (2 of 4)

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

36

Critical Chain Scheduling (3 of 4)

Additional concepts

Buffer: additional time to complete a task

Murphy’s Law: if something can go wrong, it will

Parkinson’s Law: work expands to fill the time allowed

Project buffer: additional time added before the project’s due date

Feeding buffers: additional time added before tasks on the critical path

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

Critical Chain Scheduling (4 of 4)

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

38

What Went Right?

Scheduling at healthcare clinic’s can be more efficient by using critical chain scheduling

National University Hospital in Singapore decreased patient admission times by more than 50 percent

Improved scheduling lowered average wait times, which went from six to eight hours to less than three hours

63 percent of patients were admitted in less than 1.5 hours

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

Program Evaluation and Review Technique (PERT)

Network analysis technique used to estimate project duration when there is a high degree of uncertainty about the individual activity duration estimates

Uses probabilistic time estimates: duration estimates based on using optimistic, most likely, and pessimistic estimates of activity durations

By using the PERT weighted average for each activity duration estimate, total project duration estimate takes into account the risk or uncertainty in the individual activity estimates

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

Agile and Schedule Management

Core values of the Manifesto for Agile Software Development

Customer collaboration over contract negotiation

Responding to change over following a plan

Example: product owner defines and prioritizes the work to be done within a sprint

Collaboration and time management are designed into the process

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

Controlling the Schedule

Goals of schedule control

Know the status of the schedule

Influence the factors that cause schedule changes

Determine that the schedule has changed

Manage changes when they occur

Main inputs to schedule control

Project management plan

Project documents

Work performance data

Organizational process assets

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

Reality Checks on Scheduling and the Need for Discipline

Important activities

Review the draft schedule or estimated completion date in the project charter

Prepare a more detailed schedule with the project team

Make sure the schedule is realistic and followed

Alert top management well in advance if there are schedule problems

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

Using Software to Assist in Project Schedule Management

Software for facilitating communications helps people exchange schedule-related information

Decision support models help analyze trade-offs that can be made to address schedule issues

Project management software can help in various time management areas

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

Global Issues

Microsoft tells the customer story of Mexico’s Secretary of Economy, who wanted to ensure that IT initiatives aligned with business goals and improved project management efficiency

After implementing new software, their IT team could handle four times the number of concurrent projects without adding more staff

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

Words of Caution on Using Project Management Software

Many people misuse project management software because they don’t understand important concepts and have not had training

Example: dependencies must be entered to have dates adjust automatically and to determine the critical path

Many project management software programs come with templates or sample files

It is very easy to use these files without considering unique project needs

Project managers and their teams should be careful not to rely too much on templates or sample files and ignore the unique concerns of their particular projects

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

Considerations for Agile/Adaptive Environments

Schedule management is radically different using Agile and Scrum

Projects that rely heavily on the critical path method consider meeting the project’s estimated completion date as a crucial component of success

Agile projects may not even need to estimate activity durations or project schedules at all; overall project completion time is not important

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

Chapter Summary

Project time management is often cited as the main source of conflict on projects

Most IT projects exceed time estimates

Main processes

Plan schedule management

Define activities

Sequence activities

Estimate activity resources

Estimate activity durations

Develop schedule

Control schedule