Chapter 5: Project Scope Management

Information Technology Project Management, Ninth Edition

Note: See the text itself for full citations

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

1

Learning Objectives (1 of 2)

List key reasons why good project scope management is important

Describe the process of planning scope management

Discuss methods for collecting and documenting requirements to meet stakeholder needs and expectations

Explain the scope definition process and describe the contents of a project scope statement

Discuss the process for creating a work breakdown structure using the analogy, top-down, bottom-up, and mind-mapping approaches

Explain the importance of validating scope and how it relates to defining and controlling scope

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

2

Learning Objectives (2 of 2)

Given an information technology (IT) project situation, show how recommended approaches for controlling scope can improve the potential for project success

Describe how software can assist in project scope management

Discuss considerations for agile/adaptive environments

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

What is Project Scope Management?

Scope refers to all the work involved in creating the products of the project and the processes used to create them

A deliverable is a product produced as part of a project, such as hardware or software, planning documents, or meeting minutes

Project scope management includes the processes involved in defining and controlling what is or is not included In a project

Ensures that the project team and stakeholders have the same understanding of what products the project will produce and what processes the project team will use to produce them

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

Project Scope Management Processes (1 of 2)

Main processes

Planning scope management: determining how the project’s scope and requirements will be managed

Collecting requirements: defining and documenting the features and functions of the products produced during the project as well as the processes used for creating them

Defining scope: reviewing the project charter, requirements documents, and organizational process assets to create a scope statement

Creating the WBS: subdividing the major project deliverables into smaller, more manageable components

Validating scope: formalizing acceptance of the project deliverables

Controlling scope: controlling changes to project scope throughout the life of the project

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

Project Scope Management Processes (2 of 2)

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

6

Planning Scope Management (1 of 2)

The project team uses expert judgment, data analysis, and meetings to develop two important outputs

Scope management plan (subsidiary part of the project management plan)

Requirements management plan

Scope management plan contents

Prepare a detailed project scope statement

Create a WBS

Maintain and approve the WBS

Obtain formal acceptance of the completed project deliverables

Control requests for changes to the project scope

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

Planning Scope Management (2 of 2)

Requirements Management Plan

The PMBOK® Guide, Sixth Edition, describes a requirement as ““a condition or capability that is necessary to be present in a product, service, or result to satisfy a business need”

The requirements management plan documents how project requirements will be analyzed, documented, and managed

How to plan, track, and report requirements activities

How to perform configuration management activities

How to prioritize requirements

How to use product metrics

How to trace and capture attributes of requirements

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

What Went Right?

U.S. Bureau of Labor Statistics projected the number of jobs for business analysts to increase 19 percent by 2022

49 percent of survey respondents had the resources in place to do requirements management properly

53 percent failed to use a formal process to validate requirements

There are several certification programs available for business analysis to help meet this need

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

Collecting Requirements (1 of 3)

Several ways to collect requirements

Interviewing stakeholders

Holding focus groups and facilitated workshops

Using group creativity and decision-making techniques

Utilizing questionnaires and surveys

Conducting observation studies

Generating ideas by comparing specific project practices or product characteristics (i.e., benchmarking)

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

Collecting Requirements (2 of 3)

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

11

Collecting Requirements (3 of 3)

Requirements traceability matrix (RTM): a table that lists requirements, various attributes of each requirement, and the status of the requirements to ensure that all requirements are addressed

Requirement No. Name Category Source Status
R32 Laptop memory Hardware Project charter and corporate laptop specifications Complete. Laptops ordered meet memory requirement.

Table 5-1 Sample entry in a requirements traceability matrix

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

Best Practice

Book called How Google Tests Software describes how Google changed their culture as quality rests on the shoulders of those writing the code

Do not rely on testers to ensure quality

Do not believe in fads or buzzwords

Including Agile

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

Defining Scope (1 of 2)

Important elements of a project scope statement

Product scope description

Product user acceptance criteria

Detailed information on all project deliverables

It is also helpful to document other scope-related information

Project boundaries, constraints, and assumptions

Supporting document references (e.g., product specifications)

As time progresses, the scope of a project should become more clear and specific

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

Defining Scope (2 of 2)

Project Charter: Upgrades may affect servers . . . (listed under Project Objectives)
Project Scope Statement, Version 1: Servers: If additional servers are required to support this project, they must be compatible with existing servers. If it is more economical to enhance existing servers, a detailed description of enhancements must be submitted to the CIO for approval. See current server specifications provided in Attachment 6. The CEO must approve a detailed plan describing the servers and their location at least two weeks before installation.
Project Scope Statement, Version 2: Servers: This project will require purchasing 10 new servers to support Web, network, database, application, and printing functions. Virtualization will be used to maximize efficiency. Detailed descriptions of the servers are provided in a product brochure in Attachment 8, along with a plan describing where they will be located.

Table 5-3 Further defining project scope

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

Media Snapshot

Inaccurate requirements gathering continues to be one of the main causes of project failure

For every dollar spent on projects and programs, 5.1 percent is wasted due to poor requirements management

Organizations need to develop people, processes, and culture to improve requirements management

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

Creating the Work Breakdown Structure (1 of 9)

Work Breakdown Structure (WBS) is a deliverable-oriented grouping of the work involved in a project that defines the total scope of the project

Foundation document that provides the basis for planning and managing project schedules, costs, resources, and changes

Decomposition is the main tool or technique for creating a WBS

Subdividing project deliverables into smaller pieces

A work package is a task at the lowest level of the WBS

Outputs of creating the WBS are the scope baseline and project documents updates

Scope baseline includes the approved project scope statement and its associated WBS and WBS dictionary

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

Creating the Work Breakdown Structure (2 of 9)

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

18

Creating the Work Breakdown Structure (3 of 9)

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

19

Creating the Work Breakdown Structure (4 of 9)

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

20

Creating the Work Breakdown Structure (5 of 9)

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

21

Creating the Work Breakdown Structure (6 of 9)

1.0 Software Product Release 5.0
1.1 Project Management
1.1.1 Planning
1.1.2 Meetings
1.1.3 Administration
1.2 Product Requirements
1.2.1 Software
1.2.2 User Documentation
1.2.3 Training Program Materials
1.3 Detail Design
1.3.1 Software
1.3.2 User Documentation
1.3.2 User Documentation
1.4 Construct
1.4.1 Software
1.4.2 User Documentation
1.4.3 Training Program Materials
1.5 Integration and Test
1.5.1 Software
1.5.2 User Documentation
1.5.3 Training Program Materials

Table 5-4 Tabular form of WBS

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

Creating the Work Breakdown Structure (7 of 9)

Approaches to developing work breakdown structures

Using guidelines: some organizations, like the U.S. Department of Defense (DOD), provide guidelines for preparing WBSs

Analogy approach: review WBSs of similar projects and tailor to your project

Top-down approach: start with the largest items of the project and break them down

Bottom-up approach: start with the specific tasks

Mind mapping: uses branches radiating out from a core idea to structure thoughts and ideas

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

Creating the Work Breakdown Structure (8 of 9)

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

24

Creating the Work Breakdown Structure (9 of 9)

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

25

Advice for Young Professionals

It is very difficult to create a good WBS

Attend meetings in your organization where teams work together

Ask to see WBSs for projects that have been completed or are in process

Conduct your own research to find examples of different WBSs

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

The WBS Dictionary (1 of 3)

Many WBS tasks are vague

WBS dictionary is a document that describes detailed information about each WBS item

Format of the WBS dictionary can vary based on project needs

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

The WBS Dictionary (2 of 3)

WBS Dictionary Entry March 20
Project Title: Information Technology (IT) Upgrade Project
WBS Item Number: 2.2
WBS Item Name: Database Update
Description: The IT department maintains an online database of hardware and software on the corporate intranet. We need to make sure that we know exactly what hardware and software employees are currently using and if they have any unique needs before we decide what to order for the upgrade. This task will involve reviewing information from the current database, producing reports that list each department’s employees and location, and updating the data after performing the physical inventory and receiving inputs from department managers. Our project sponsor will send a notice to all department managers to communicate the importance of this project and this particular task. In addition to general hardware and software upgrades, the project sponsors will ask the department managers to provide information for any unique requirements they might have that could affect the upgrades. This task also includes updating the inventory data for network hardware and software. After updating the inventory database, we will send an e-mail to each department manager to verify the information and make changes online as needed. Department managers will be responsible for ensuring that their people are available and cooperative during the physical inventory. Completing this task is dependent on WBS Item Number 2.1, Physical Inventory, and must precede WBS Item Number 3.0, Hardware and Software Acquisition.

Table 5-5 Sample WBS dictionary entry

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

The WBS Dictionary (3 of 3)

Advice for creating a WBS and WBS dictionary

Unit of work should appear at only one place in the WBS

Work content of a WBS item is the sum of the WBS items below it

WBS item is the responsibility of only one individual, even though many people may be working on it

WBS must be consistent with the way in which work is actually going to be performed; it should serve the project team first, and other purposes only if practical

Project team members should be involved in developing the WBS to ensure consistency and buy-in

Each WBS item must be documented in a WBS dictionary to ensure accurate understanding of the scope of work included and not included

WBS must be a flexible tool to accommodate inevitable changes while properly maintaining control of the work content in the project according to the scope statement

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

Validating Scope

It is difficult to create a good project scope statement and WBS for a project

Even more difficult, especially on IT projects, to verify the project scope and minimize scope changes

Even when the project scope is fairly well defined, many IT projects suffer from scope creep

Tendency for project scope to keep getting bigger and bigger

Scope validation involves formal acceptance of the completed project deliverables

Acceptance is often achieved by a customer inspection and then sign-off on key deliverables

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

What Went Wrong?

A project scope that is too broad and grandiose can cause severe problems

Scope creep and an overemphasis on technology for technology’s sake resulted in the bankruptcy of a large pharmaceutical firm, Texas-based FoxMeyer Drug

In 2001, McDonald’s fast-food chain initiated a project to create an intranet that would connect its headquarters with all of its restaurants to provide detailed operational information in real time

After spending $170 million on consultants and initial implementation planning, McDonald’s realized that the project was too much to handle and terminated it

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

Global Issues

Many countries have had difficulties controlling the scope of large projects

Especially those that involve advanced technologies and many different users

For example, the state government of Victoria, Australia, has a website for its public transportation smart card; there were many problems in developing and implementing the smart card

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

Controlling Scope (1 of 3)

Scope control involves controlling changes to the project scope

Keeping project goals and business strategy in mind

Goals of scope control

Influence the factors that cause scope changes

Ensure changes are processed according to procedures developed as part of integrated change control

Manage changes when they occur

Variance is the difference between planned and actual performance

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

Controlling Scope (2 of 3)

Suggestions for improving user input

Develop a good project selection process and insist that sponsors are from the user organization

Place users on the project team

Conduct regular meetings with defined agendas

Deliver something to users and sponsors on a regular basis

Do not promise to deliver what the team cannot deliver in a particular time frame

Locate users with the developers

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

Controlling Scope (3 of 3)

Suggestions for reducing incomplete and changing requirements

Develop and follow a requirements management process

Employ techniques such as prototyping, use case modeling, and JAD to get more user involvement

Put requirements in writing and keep them current

Create a requirements management database for documenting and controlling requirements

Provide adequate testing and conduct it throughout the project life cycle

Review changes from a systems perspective

Emphasize completion dates to help focus on what’s most important

Allocate resources specifically for handling change requests

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

Using Software to Assist in Project Scope Management

Word-processing software helps create several scope-related documents

Spreadsheets or presentation software to develop various charts, graphs, and matrixes related to scope management

Mind-mapping software can be useful in developing a WBS

Communication software like e-mail and web-based applications can transmit project scope management information

Project management software helps in creating a WBS; basis for creating a Gantt chart

Specialized software is available to assist in project scope management

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

Considerations for Agile/Adaptive Environments

Stakeholders define and approve the detailed scope before the start of an iteration with an adaptive or agile product life cycle, producing a usable product at the end of each iteration

Detailed scope develops over time

Agile approach provides several usable products during the project

Information Technology Project Management, Ninth Edition. © 2019 Cengage. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.

Chapter Summary

Project scope management includes the processes required to ensure that the project addresses all the work required, and only the work required, to complete the project successfully

Main processes

Define scope management

Collect requirements

Define scope

Create WBS

Validate scope

Control scope