Adopt a pet" web application
activity list and attributes.doc
Activity List and Attributes
Date
Project Name:
WBS Item Number:
WBS Item Name:
Predecessors:
Successors:
Logical Relationships:
Leads and Lags:
Resource Requirements:
Constraints:
Imposed Dates:
Assumptions:
activity resource requirements.doc
Activity Resource Requirements
Date
Project Name:
WBS Item Number:
WBS Item Name:
Description:
assumption log.xlsx
Sheet1
| Assumption Log | ||||||
| ID | Assumption Description | Category | Owner | Due Date | Status | Actions |
breakeven.xlsx
Profit Analysis
| Units Sold | Revenue | Expense | ||||||
| 0 | $0 | $25,000 | ||||||
| 500 | 6,000 | 29,000 | ||||||
| 1,000 | 12,000 | 33,000 | ||||||
| 1,500 | 18,000 | 37,000 | ||||||
| 2,000 | 24,000 | 41,000 | ||||||
| 2,500 | 30,000 | 45,000 | ||||||
| 3,000 | 36,000 | 49,000 | ||||||
| 3,500 | 42,000 | 53,000 | ||||||
| 4,000 | 48,000 | 57,000 | ||||||
| 4,500 | 54,000 | 61,000 | ||||||
| 5,000 | 60,000 | 65,000 | ||||||
| 5,500 | 66,000 | 69,000 | ||||||
| Sales Price per Unit: | $12 | 6,000 | 72,000 | 73,000 | ||||
| 6,500 | 78,000 | 77,000 | ||||||
| 7,000 | 84,000 | 81,000 | ||||||
| Manufacturing Cost per Unit: | $8 | 7,500 | 90,000 | 85,000 | ||||
| 8,000 | 96,000 | 89,000 | ||||||
| 8,500 | 102,000 | 93,000 | ||||||
| Fixed Monthly Expense: | $25,000 | 9,000 | 108,000 | 97,000 | ||||
| 9,500 | 114,000 | 101,000 | ||||||
| 10,000 | 120,000 | 105,000 | ||||||
| Break-Even Point (Units Sold): | 6,250 | 10,500 | 126,000 | 109,000 | ||||
| Revenue at Break-Even Point: | $75,000 | 11,000 | 132,000 | 113,000 | ||||
| 11,500 | 138,000 | 117,000 | ||||||
| 12,000 | 144,000 | 121,000 | ||||||
| 12,500 | 150,000 | 125,000 | ||||||
| 13,000 | 156,000 | 129,000 | ||||||
| 13,500 | 162,000 | 133,000 | ||||||
| 14,000 | 168,000 | 137,000 | ||||||
| 14,500 | 174,000 | 141,000 | ||||||
| 15,000 | 180,000 | 145,000 | ||||||
| 15,500 | 186,000 | 149,000 | ||||||
| 16,000 | 192,000 | 153,000 | ||||||
| 16,500 | 198,000 | 157,000 | ||||||
| 17,000 | 204,000 | 161,000 | ||||||
| 17,500 | 210,000 | 165,000 | ||||||
| 18,000 | 216,000 | 169,000 | ||||||
| 18,500 | 222,000 | 173,000 | ||||||
| 19,000 | 228,000 | 177,000 | ||||||
| 19,500 | 234,000 | 181,000 | ||||||
| 20,000 | 240,000 | 185,000 |
Profit Analysis
Revenue 0 500 1000 1500 2000 2500 3000 3500 4000 4500 5000 5500 6000 6500 7000 7500 8000 8500 9000 9500 10000 10500 11000 11500 12000 12500 13000 13500 14000 14500 15000 15500 16000 16500 17000 17500 18000 18500 19000 19500 20000 0 6000 12000 18000 24000 30000 36000 42000 48000 54000 60000 66000 72000 78000 84000 90000 96000 102000 108000 114000 120000 126000 132000 138000 144000 150000 156000 162000 168000 174000 180000 186000 192000 198000 204000 210000 216000 222000 228000 234000 240000 Expense 0 500 1000 1500 2000 2500 3000 3500 4000 4500 5000 5500 6000 6500 7000 7500 8000 8500 9000 9500 10000 10500 11000 11500 12000 12500 13000 13500 14000 14500 15000 15500 16000 16500 17000 17500 18000 18500 19000 19500 20000 25000 29000 33000 37000 41000 45000 49000 53000 57000 61000 65000 69000 73000 77000 81000 85000 89000 93000 97000 101000 105000 109000 113000 117000 121000 125000 129000 133000 137000 141000 145000 149000 153000 157000 161000 165000 169000 173000 177000 181000 185000 Break-Even6250 75000
Units Sold
burndownchart.xlsx
Sheet1
| Days | Tasks Done | Remaining | Ideal Done Per Day | Ideal Velocity | |
| Initial Value | 0 | 0 | 200 | 10 | 200 |
| 1 | 0 | 200 | 10 | 190 | |
| 2 | 5 | 195 | 10 | 180 | |
| 3 | 3 | 192 | 10 | 170 | |
| 4 | 12 | 180 | 10 | 160 | |
| 5 | 17 | 163 | 10 | 150 | |
| 6 | 9 | 154 | 10 | 140 | |
| 7 | 8 | 146 | 10 | 130 | |
| 8 | 13 | 133 | 10 | 120 | |
| 9 | 15 | 118 | 10 | 110 | |
| 10 | 6 | 112 | 10 | 100 | |
| 11 | 18 | 94 | 10 | 90 | |
| 12 | 15 | 79 | 10 | 80 | |
| 13 | 16 | 63 | 10 | 70 | |
| 14 | 11 | 52 | 10 | 60 | |
| 15 | 8 | 44 | 10 | 50 | |
| 16 | 13 | 31 | 10 | 40 | |
| 17 | 9 | 22 | 10 | 30 | |
| 18 | 6 | 16 | 10 | 20 | |
| 19 | 10 | 6 | 10 | 10 | |
| 20 | 6 | 0 | 10 | 0 |
Sprint 1 Burndown Chart
Remaining Initial Value 200 200 195 192 180 163 154 146 133 118 112 94 79 63 52 44 31 22 16 6 0 Ideal Velocity Initial Value 200 190 180 170 160 150 140 130 120 110 100 90 80 70 60 50 40 30 20 10 0Sheet2
Sheet3
business case financials.xls
Sheet1
| Financial Analysis for Project Name | ||||||
| Created by: | Date: | |||||
| Note: Change the inputs, such as discount rate, number of years, costs, and benefits. Be sure to double-check the formulas based on the inputs. The discount factor is not rounded. | ||||||
| Discount rate | 8% | |||||
| Assume the project is completed in Year 0 | Year | |||||
| 0 | 1 | 2 | 3 | Total | ||
| Costs | 100 | 100 | 100 | 100 | ||
| Discount factor | 1.00 | 0.93 | 0.86 | 0.79 | ||
| Discounted costs | 100 | 93 | 86 | 79 | 358 | |
| Benefits | 0 | 200 | 200 | 200 | ||
| Discount factor | 1.00 | 0.93 | 0.86 | 0.79 | ||
| Discounted benefits | 0 | 185 | 171 | 159 | 515 | |
| Discounted benefits - costs | (100) | 93 | 86 | 79 | 158 | NPV |
| Cumulative benefits - costs | (100) | (7) | 78 | 158 | ||
| ROI | 44% | |||||
| Payback in Year X | ||||||
| Assumptions | ||||||
| Enter assumptions here |
Sheet2
Sheet3
business case.doc
Business Case for Project Name
Date
Project Name:
|
1.0 Introduction/ Background
|
|
2.0 Business Objective
|
|
3.0 Current Situation and Problem/Opportunity Statement
|
|
4.0 Critical Assumption and Constraints . |
|
5.0 Analysis of Options and Recommendation
|
|
6.0 Preliminary Project Requirements
|
|
7.0 Budget Estimate and Financial Analysis
|
|
8.0 Schedule Estimate
|
|
9.0 Potential Risks
|
|
10.0 Exhibits Exhibit A: Financial Analysis
|
cause and effect diagram.ppt
Cause and Effect Diagram
Date
Problem: Low
course ratings
Potential causes
Effect
Content
Interactivity
Speed
Graphics/fonts
Not enough examples
Too simple
Fonts too small
Too little interaction
Slow between screens
Assessment
results very slow
No online support
Colors too wild
Note: Change the text in the diagram based on your project.
change request.doc
Change Request
Date
Project Name:
Date Request Submitted:
Title of Change Request:
Change Order Number:
Submitted by:
Change Category: (Scope (Schedule (Cost (Technology (Other
Description of change requested:
Events that made this change necessary or desirable:
Justification for the change/why it is needed/desired to continue/complete the project:
Impact of the proposed change on:
Scope:
Schedule:
Cost:
Staffing:
Risk:
Other:
Suggested implementation if the change request is approved:
Required approvals:
|
Name/Title |
Date |
Approve/Reject |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
charter.doc
Project Charter
Date
|
Project Title: |
|||
|
Project Start Date: Projected Finish Date: |
|||
|
Budget Information:
|
|||
|
Project Manager: Name, phone, e-mail |
|||
|
Project Objectives:
|
|||
|
Success Criteria:
|
|||
|
Approach:
|
|||
|
Roles and Responsibilities |
|||
|
Name and Signature |
Role |
Position |
Contact Information |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|||
|
Comments: (Handwritten or typed comments from above stakeholders, if applicable)
|
communication management plan.doc
Communication Management Plan Version 1.0
Date
Project Name:
1. Stakeholder communications requirements:
2. Communications summary:
|
Stakeholders |
Communications Name |
Delivery Method/Format |
Producer |
Due/Frequency |
|
Project steering committee |
Weekly status report |
Hard copy and short meeting |
Kristin Maur |
Wed. mornings at 9 AM |
|
Sponsor and champion |
Monthly status report |
Hard copy and short meeting |
Kristin Maur |
First Thursday of month at 10 AM |
|
Affected employees |
Project announcement |
Memo, e-mail, intranet site, and announcement at department meetings |
Lucy Camerena and Mike Sundby |
July 1, 2007 |
|
Project team |
Weekly status report |
Short meeting |
All team members |
Tues. afternoons at 2:00. |
3. Comments/Guidelines:
4. Escalation procedures for resolving issues:
5. Revision procedures for this document:
6. Glossary of common terminology:
contract closure notice.doc
Contract Closure Notice
Date
As described in our contract/service agreement (XXXXX-X), this letter provides formal notice that the work you were contracted to perform for __________________ (the Buyer) has been completed. Payment is being processed based on __________________.
By: __Name, Title, Company____
Date __ ______________________
contract statement of work.doc
Contract Statement of Work
Date
Project Name:
Contract Name:
Scope of Work:
Location of Work:
Period of Performance:
Deliverables Schedule:
Applicable Standards:
Acceptance Criteria:
Special Requirements:
contract.doc
Company Name
Contract/Service Agreement
Date
Title of Work:
This is an Agreement made as of __________ by _______________________________ (the “Seller”), and __________________________________ (the “Buyer”).
THE SELLER AND THE BUYER AGREE THAT:
1. The Work: The Seller will create the Work as set forth in Exhibit A hereto. The Buyer will provide the Seller with the format and specifications in which each element of the Work is to be submitted. The Seller agrees to conform to such format and specifications.
2. Delivery of the Work: The Seller agrees to deliver to the Buyer the Work in form and content acceptable to the Buyer on or before the dates outlined in Exhibit B of this Agreement, time being of the essence to the Buyer.
3. Right to Terminate: If the Seller materially departs from the agreed-upon schedule or if the Work is not satisfactory to the Buyer (based on reviews of drafts, market conditions, and/or other criteria as determined by the Buyer), the Buyer may at its option:
A. Allow the Seller to finish, correct, or improve the Work by a date specified by the Buyer;
B. Terminate this Agreement by giving written notice to the Seller.
4. Payments: The Buyer will pay the Seller _________________ upon accepted completion of the Work.
5. Exhibit: The following Exhibit is hereby incorporated by reference into this Agreement:
Exhibit A: Statement of Work
Exhibit B: Schedule
IN WITNESS WHEREOF, THE PARTIES HERETO HAVE EXECUTED THIS Agreement as a sealed instrument as of the date first above written.
Buyer Seller
By: ________________________ ____________________________
Date: ________________________ ____________________________
cost baseline.xls
Sheet1
| Cost Estimate | |||||||||||||
| Project Name: | Date: | ||||||||||||
| Note: Enter your WBS and costs each month. Add/delete rows and columns as needed and check all formulas (bolded below). | |||||||||||||
| Month | |||||||||||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | Total Cost | |
| WBS Categories | |||||||||||||
| 1. Initiating | 13,000 | $ 13,000 | |||||||||||
| 2. Planning | 6,000 | 16,000 | 8,000 | 1,000 | 1,000 | 1,000 | 1,000 | 1,000 | 1,000 | $ 36,000 | |||
| 3. Executing | - 0 | - 0 | - 0 | $ - 0 | |||||||||
| 3.1 Course design and development | - 0 | - 0 | - 0 | $ - 0 | |||||||||
| 3.1.1 Supplier management training | 5,000 | 73,667 | 73,667 | 73,667 | $ 226,000 | ||||||||
| 3.1.2 Negotiating skills training | 5,000 | 35,500 | 35,500 | 35,500 | $ 111,500 | ||||||||
| 3.1.3 Project management training | 5,000 | 43,000 | 43,000 | 43,000 | $ 134,000 | ||||||||
| 3.1.4 Software applications training | 5,000 | 43,000 | 43,000 | 43,000 | $ 134,000 | ||||||||
| 3.2 Course administration | 17,000 | 53,333 | 53,333 | 53,333 | $ 177,000 | ||||||||
| 3.3.Course evaluation | 3,000 | 3,000 | 3,000 | 7,500 | $ 16,500 | ||||||||
| 3.4 Stakeholder communications | 1,500 | 1,500 | 1,500 | 1,500 | 1,500 | 1,500 | 1,500 | 1,500 | 1,500 | 1,500 | 1,500 | $ 16,500 | |
| 4. Monitoring and Controlling | 1,000 | 2,000 | 2,000 | 2,000 | 3,000 | 3,500 | 3,000 | 3,000 | 2,000 | 3,000 | 2,000 | 1,000 | $ 27,500 |
| 5. Closing | 8,000 | 3,000 | $ 11,000 | ||||||||||
| Subtotal | $ 903,000 | ||||||||||||
| Reserves* | - 0 | - 0 | - 0 | 90,300 | $ 90,300 | ||||||||
| Total | 20,000 | 19,500 | 31,500 | 199,667 | 200,667 | 218,167 | 61,833 | 61,833 | 60,833 | 12,000 | 11,500 | 95,800 | 993,300 |
| *Reserves are all entered in month 12 |
Sheet2
Sheet3
cost estimate.xls
Sheet1
| Cost Estimate | |||||||||
| Project Name: | Date: | ||||||||
| Note: Enter your WBS, hours, labor rates, etc. Add/delete rows and columns as needed and check all formulas (bolded below). | |||||||||
| Internal | $/hour | Internal | External | $/hour | External | Total | Non-labor $ | Total Cost | |
| WBS Categories | Labor | $ Total | Labor | $ Total | Labor | ||||
| 1. Initiating | 200 | $ 65 | $ 13,000 | $ - 0 | $ 13,000 | $ 13,000 | |||
| 2. Planning | 600 | $ 60 | $ 36,000 | $ - 0 | $ 36,000 | $ 36,000 | |||
| 3. Executing | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| 3.1 Course design and development | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| 3.1.1 Supplier management training | 600 | $ 60 | $ 36,000 | 600 | $ 150 | $ 90,000 | $ 126,000 | $ 100,000 | $ 226,000 |
| 3.1.2 Negotiating skills training | 300 | $ 55 | $ 16,500 | 300 | $ 150 | $ 45,000 | $ 61,500 | $ 50,000 | $ 111,500 |
| 3.1.3 Project management training | 400 | $ 60 | $ 24,000 | 400 | $ 150 | $ 60,000 | $ 84,000 | $ 50,000 | $ 134,000 |
| 3.1.4 Software applications training | 400 | $ 60 | $ 24,000 | 400 | $ 150 | $ 60,000 | $ 84,000 | $ 50,000 | $ 134,000 |
| 3.2 Course administration | 400 | $ 55 | $ 22,000 | 300 | $ 250 | $ 75,000 | $ 97,000 | $ 80,000 | $ 177,000 |
| 3.3.Course evaluation | 300 | $ 55 | $ 16,500 | $ - 0 | $ 16,500 | $ 16,500 | |||
| 3.4 Stakeholder communications | 300 | $ 55 | $ 16,500 | $ - 0 | $ 16,500 | $ 16,500 | |||
| 4. Monitoring and Controlling | 500 | $ 55 | $ 27,500 | $ - 0 | $ 27,500 | $ 27,500 | |||
| 5. Closing | 200 | $ 55 | $ 11,000 | $ - 0 | $ 11,000 | $ 11,000 | |||
| Subtotal | $ 903,000 | ||||||||
| Reserves | $ - 0 | $ - 0 | $ - 0 | 90,300.0 | |||||
| Total | 4,200 | 243,000 | 2,000 | 850 | 330,000 | 573,000 | 330,000 | $ 993,300 | |
| Assumptions |
Sheet2
Sheet3
customer acceptance form.doc
Customer Acceptance/Project Completion Form
Date
Project Name: ____________________________________
Project Manager: ____________________________________
I (We), the undersigned, acknowledge and accept delivery of the work completed for this project on behalf of our organization. My (Our) signature(s) attest(s) to my (our) agreement that this project has been completed. No further work should be done on this project.
|
Name |
Title |
Signature |
Date |
|
|
|
|
|
|
|
|
|
|
1. Was this project completed to your satisfaction? ____ Yes _____ No
2. Please provide the main reasons for your satisfaction or dissatisfaction with this project..
3. Please provide suggestions on how our organization could improve its project delivery capability in the future.
Thank you for your inputs.
deliverable acceptance form.doc
Deliverable Acceptance Form
Date
Project Name:
Deliverable Name:
Project Manager:
Project Sponsor:
(We), the undersigned, acknowledge and accept delivery of the work completed for this deliverable on behalf of our organization. My (Our) signature(s) attest(s) to my (our) agreement that this deliverable has been completed. No further work should be done on this deliverable. If the deliverable is not acceptable, reasons are stated and corrective actions are described.
|
Name |
Title |
Signature |
Date |
|
|
|
|
|
|
|
|
|
|
1. Was this deliverable completed to your satisfaction? Yes No ___
2. Please provide the main reasons for your satisfaction or dissatisfaction with this deliverable.
3. If the deliverable is not acceptable, describe in detail what additional work must be done to complete it.
Contact’s signature for resubmission of deliverable if found unacceptable: ____ ______________
earned value chart.xls
Sheet1
| Earned Value Chart | |||||||||||||
| Date | |||||||||||||
| Be sure to enter your own data and check your formulas. | |||||||||||||
| Month | |||||||||||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | Total Cost | |
| WBS Categories | |||||||||||||
| 1. Initiating | 13,000 | $ 13,000 | |||||||||||
| 2. Planning | 6,000 | 16,000 | 8,000 | 1,000 | 1,000 | 1,000 | 1,000 | 1,000 | 1,000 | $ 36,000 | |||
| 3. Executing | - 0 | - 0 | - 0 | $ - 0 | |||||||||
| 3.1 Course design and development | - 0 | - 0 | - 0 | $ - 0 | |||||||||
| 3.1.1 Supplier management training | 5,000 | 73,667 | 73,667 | 73,667 | $ 226,000 | ||||||||
| 3.1.2 Negotiating skills training | 5,000 | 35,500 | 35,500 | 35,500 | $ 111,500 | ||||||||
| 3.1.3 Project management training | 5,000 | 43,000 | 43,000 | 43,000 | $ 134,000 | ||||||||
| 3.1.4 Software applications training | 5,000 | 43,000 | 43,000 | 43,000 | $ 134,000 | ||||||||
| 3.2 Course administration | 17,000 | 53,333 | 53,333 | 53,333 | $ 177,000 | ||||||||
| 3.3.Course evaluation | 3,000 | 3,000 | 3,000 | 7,500 | $ 16,500 | ||||||||
| 3.4 Stakeholder communications | 1,500 | 1,500 | 1,500 | 1,500 | 1,500 | 1,500 | 1,500 | 1,500 | 1,500 | 1,500 | 1,500 | $ 16,500 | |
| 4. Monitoring and Controlling | 1,000 | 2,000 | 2,000 | 2,000 | 3,000 | 3,500 | 3,000 | 3,000 | 2,000 | 3,000 | 2,000 | 1,000 | $ 27,500 |
| 5. Closing | 8,000 | 3,000 | $ 11,000 | ||||||||||
| Subtotal | $ 903,000 | ||||||||||||
| Reserves | - 0 | - 0 | - 0 | 90,300 | $ 90,300 | ||||||||
| Total | 20,000 | 19,500 | 31,500 | 199,667 | 200,667 | 218,167 | 61,833 | 61,833 | 60,833 | 12,000 | 11,500 | 95,800 | 993,300 |
| $ 689,500 | |||||||||||||
| Monthly Planned Value (PV) | 20,000 | 19,500 | 31,500 | 199,667 | 200,667 | 218,167 | 61,833 | 61,833 | 60,833 | 12,000 | 11,500 | 95,800 | |
| Cumulative Planned Value (PV) | 20,000 | 39,500 | 71,000 | 270,667 | 471,333 | 689,500 | 751,333 | 813,167 | 874,000 | 886,000 | 897,500 | 993,300 | |
| Monthly Actual Cost (AC) | 20,000 | 20,000 | 35,000 | 210,000 | 220,000 | 245,000 | |||||||
| Cumulative Actual Cost (AC) | 20000 | 40,000 | 75,000 | 285,000 | 505,000 | 750,000 | |||||||
| Monthly Earned Value (EV) | 20,000 | 20,000 | 30,000 | 190,000 | 200,000 | 240,000 | |||||||
| Cumulative Earned Value (EV) | 20,000 | 40,000 | 70,000 | 260,000 | 460,000 | 700,000 | |||||||
| Project EV as of May 31 | 700,000 | ||||||||||||
| Project PV as of May 31 | 689,500 | ||||||||||||
| Project AC as of May 31 | $ 750,000 | ||||||||||||
| CV=EV-AC | $ (50,000) | ||||||||||||
| SV=EV-PV | $ 10,500 | ||||||||||||
| CPI=EV/AC | 93.33% | ||||||||||||
| SPI=EV/PV | 101.52% | ||||||||||||
| Estimate at Completion (EAC) | $ 1,071,429 | ||||||||||||
| Estimated time to complete | 11.82 |
Sheet1
Sheet2
Sheet3
Excel_draft_schedule.xls
draft schedule template
| Team Project Draft Schedule | |||||||||||||||
| Note: Add/delete rows and columns as needed. Enter your team member names for A, B, C, D, and E. Focus on getting a good list of Executing tasks and estimating hours. | |||||||||||||||
| Only enter hours for the lowest level tasks (verb phrases, indented farthest right). Have draft schedule ready for PR1 and update info and use to create your Gantt chart for PR 2. | |||||||||||||||
| PR=Progress Report | |||||||||||||||
| Total hours-> | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
| Major tasks | Start Date | End Date | Responsible | Estimated Hours per person | Total | Actual Hours | Total | ||||||||
| A | B | C | D | E | Est. Hours | A | B | C | D | E | Act. Hours | ||||
| 1.1 Initiating | |||||||||||||||
| 1.1.1 Project charter (PR1) | |||||||||||||||
| 1.1.2 Kick-off meeting (PR1) | |||||||||||||||
| 1.1.3 Team MBTI summary (PR1) | |||||||||||||||
| 1.1.4 Sponsor feedback (PR1) | |||||||||||||||
| 1.1.5 Google site initial set-up (PR1) | |||||||||||||||
| 1.2 Planning | |||||||||||||||
| 1.2.1 Draft scope statement (PR1) | |||||||||||||||
| 1.2.2 Team contract (PR1) | |||||||||||||||
| 1.2.3 Excel draft schedule (PR1) | |||||||||||||||
| 1.2.4 Gantt chart (PR2) | |||||||||||||||
| 1.2.6 Updated scope statement (PR2) | |||||||||||||||
| 1.2.5 Additional sponsor feedback (PR2) | |||||||||||||||
| 1.3 Executing | |||||||||||||||
| 1.3.1 Communications | |||||||||||||||
| 1.3.1.1 Document team meetings | |||||||||||||||
| 1.3.1.2 Document sponsor meetings/feedback | |||||||||||||||
| 1.3.1.3 Update Google site | |||||||||||||||
| 1.3.2 Main deliverable 2 | |||||||||||||||
| Task 1 | |||||||||||||||
| Task 2 | |||||||||||||||
| Task 3 | |||||||||||||||
| 1.3.3 Main deliverable 3 | |||||||||||||||
| Task 1 | |||||||||||||||
| Task 2 | |||||||||||||||
| Task 3 | |||||||||||||||
| etc. | |||||||||||||||
| 1.4 Monitoring and Controlling | |||||||||||||||
| 1.4.1 Progress report 1 (PR1) | |||||||||||||||
| 1.4.1.1 Fill out progress report template | |||||||||||||||
| 1.4.1.2 Assemble all documents for PR1 | |||||||||||||||
| 1.4.1.3 Prepare and practice presentation | |||||||||||||||
| 1.4.1.5 Post all info online | |||||||||||||||
| 1.4.2 Progress report 2 (PR2) | |||||||||||||||
| 1.4.2.1 Fill out progress report template | |||||||||||||||
| 1.4.2.2 Prepare est. vs. actual hours summary | |||||||||||||||
| 1.4.2.3 Assemble all documents for PR2 | |||||||||||||||
| 1.4.2.4 Prepare and practice presentation | |||||||||||||||
| 1.2.2.5 Post all info online | |||||||||||||||
| 1.4.3 Other monitoring and controlling | |||||||||||||||
| 1.5 Closing | |||||||||||||||
| 1.5.1 Project notebook | |||||||||||||||
| 1.5.1.1 Assemble all documents for notebook | |||||||||||||||
| 1.5.1.2 Receive project completion form from sponsor | |||||||||||||||
| 1.5.1.3 Prepare final report | |||||||||||||||
| 1.5.1.4 Prepare and practice final presentation | |||||||||||||||
| 1.5.1.5 Post all info online | |||||||||||||||
| 1.5.1.6 Final presentation completed (milestone) |
Comments
| Remember that a WBS is a deliverable-oriented grouping of ALL the work you will do for your project. |
| For class projects, only the executing section should be different from this template. Decide what the |
| main deliverables are for your project under executing, the break them down into specific tasks. |
| The Planning section is for project planning. If one of your deliverables is some other type of plan, put it under Executing |
Sheet3
final project report table of contents.doc
Final Project Report Table of Contents
Date
Project Name:
1. Project Objectives
2. Summary of Project Results
3. Original and Actual Schedule
4. Original and Actual Budget
5. Project Assessment
6. Transition Plan
Attachments:
A. Key Project Management Documentation
B. Product-Related Documentation
flow chart.ppt
Flow Chart
Date
Deliverable
Acceptance
Request
Route to
appropriate
decision
makers
Accepted?
Sign
approval
section
Notify
requestor
and log in
system
Document
required
additional
work
YES
NO
Be sure to enter your own data.
histogram.xls
Sheet1
| Histogram | |||
| Date | |||
| Month | # Complaints | Be sure to enter your own data and check your formulas. | |
| July | 77 | ||
| August | 94 | ||
| September | 75 | ||
| October | 78 | ||
| November | 88 | ||
| December | 62 |
Sheet1
Sheet2
Sheet3
issue log.xls
Sheet1
| Issue Log | |||||||||
| Date | |||||||||
| Issue # | Issue Description | Impact on Project | Date Reported | Reported By | Assigned To | Priority(M/H/L) | Due Date | Status | Comments |
| 1 | |||||||||
| 2 | |||||||||
| 3 |
Sheet2
Sheet3
kick- off meeting agenda.doc
Kick-Off Meeting
Date
Project Name:
Meeting Objective: Get the project off to an effective start by introducing key stakeholders, reviewing project goals, and discussing future plans
Agenda:
· Introductions of attendees
· Review of project background
· Review of project-related documents (i.e. business case, project charter)
· Discussion of project organizational structure
· Discussion of project scope, time, and cost goals
· Discussion of other important topics
· List of action items from meeting
|
Action Item |
Assigned To |
Due Date |
|
|
|
|
|
|
|
|
|
|
|
|
Date and time of next meeting:
lessons learned register.xlsx
Sheet1
| Lessons Learned Register | ||||||
| ID | Date Identified | Owner | Name | Category | Situation | Recommendation |
lessons-learned report.doc
Lessons-Learned Report
Date
|
Project Name: Project Sponsor: Project Manager: Project Dates: Final Budget: |
|
1. Did the project meet scope, time, and cost goals? 2. What was the success criteria listed in the project scope statement? 3. Reflect on whether or not you met the project success criteria. 4. What were the main lessons your team learned from this project? 5. Describe one example of what went right on this project. 6. Describe one example of what went wrong on this project. 7. What will you do differently on the next project based on your experience working on this project?
|
make-or-buy analysis.doc
Make-Or-Buy Analysis
Date
Project Name:
Decision Being Analyzed:
Option 1: Make:
Total Cost:
Option 2: Buy:
Total Cost:
Cost Difference:
Recommendation:
milestone list.doc
Milestone List
Date
Project Name:
Milestone Estimated Completion Date
milestone report.doc
Project Milestone Report
Date
|
Milestone |
Date |
Status |
Responsible |
Issues/Comments |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
pareto chart.xls
Sheet1
| Pareto Chart | |||
| Date | |||
| Be sure to enter your own data and check your formulas. | |||
| Problem | Count | % | Cumulative % |
| A | 50 | 50% | 50% |
| B | 30 | 30% | 80% |
| C | 15 | 15% | 95% |
| D | 5 | 5% | 100% |
| Total | 100 |
Sheet1
Sheet2
Sheet3
payback period chart.xls
Sheet1
| Payback Period Chart for Project Name | ||||
| Created by: | Date: | |||
| Note: Enter the discounted costs and benefits for your project below. | ||||
| Add and delete rows as needed. | ||||
| Year | Costs | Benefits | Cum Costs | Cum Benefits |
| 0 | 140,000 | 0 | 140,000 | 0 |
| 1 | 37,200 | 186,000 | 177,200 | 186,000 |
| 2 | 34,400 | 172,000 | 211,600 | 358,000 |
| 3 | 31,600 | 158,000 | 243,200 | 516,000 |
Sheet1
Sheet2
Sheet3
performance report.doc
Progress Report
Date
Project Name:
Reporting Period:
Work completed this reporting period:
Work to complete next reporting period:
What’s going well and why:
What’s not going well and why:
Suggestions/Issues:
Project changes:
potential project.doc
Potential Project Proposal
Student Name: Date:
Potential Project Name:
Project Sponsor’s Name, Organization, and Contact Information:
Justification or Reason for the Project:
Main Project Deliverables:
Required Team Skills:
Main Team Tasks/Roles:
My Desired Role and Why:
Project Sales Pitch:
(You must convince at two and up to four of your classmates to work on this project with you. Write a short sales pitch to read in class.)
probability impact matrix.ppt
Probability/Impact Matrix
Date
Impact
Probability
low
medium
high
low
medium
high
risk 1
risk 4
risk 6
risk 9
risk 2
risk 5
risk 11
risk 3
risk 7
risk 8
risk 10
risk 12
procurement management plan.doc
Procurement Management Plan
Date
Project Name:
Guidelines on Types of Contracts:
Standard procurement documents or templates:
Guidelines for creating procurement documents:
Roles and responsibilities:
project management plan.doc
Project Management Plan Version 1.0
Date
Project Name:
Introduction/Overview of Project
Project Organization
Management and Technical Processes
Management Processes:
Technical Processes:
Work to Be Performed
Schedule Information
Budget Information
References to Other Project Planning Documents
project organizational chart.ppt
Project Name Organizational Chart
Date
Project Sponsor
Project Manager
Team Leads
Supplier
Project Managers
Team 1
Team 2
Team 3
Team 4
Project Champion
Project Steering
Committee
project schedule.mpp
qualified sellers list.doc
Qualified Sellers List
Date
Project Name:
|
Seller Name/ Web Site |
Areas of Expertise |
Full-Time Staff |
Reputation |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
quality checklist.doc
Quality Checklist
Date
Project Name:
Checklist Purpose:
quality management plan.doc
Quality Management Plan
Date
Project Name:
Introduction
Quality Standards
Metrics
Problem Reporting and Corrective Action Process
Supplier Quality and Control
quality metrics.doc
Quality Metrics
Date
Project Name:
The following quality metrics apply to this project:
RACI chart.xls
Sheet1
| Project Name RACI Chart | ||||
| Date | ||||
| Task | Name 1 | Name 2 | Name 3 | Name 4 |
| R: Responsible | ||||
| A: Accountable | ||||
| C: Consulted | ||||
| I: Informed |
Sheet2
Sheet3
request for proposal.doc
Request for Proposal
Date
Project Name:
RFP Name:
Purpose of RFP
Background Information
Basic Requirements
RFP Process
Statement of Work and Schedule Information
Appendices
requirements management plan.doc
Requirements Management Plan Version X.X
Date
Project Name:
Planning, tracking, and reporting requirements:
Performing configuration management activities:
Prioritizing requirements:
Using product metrics:
Tracing requirements:
requirements traceability matrix.doc
Requirements Traceability Matrix for Project Name
Prepared by: Date:
|
Requirement No. |
Name |
Category |
Source |
Status |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
resource histogram.xls
Sheet1
| Project Name Resource Histogram | ||||||||||||
| Date: | ||||||||||||
| Enter resource names, months, and number of resources for your project. | ||||||||||||
| Resource | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
| A | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 |
| B | 2 | 2 | 2 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 |
| C | 1 | 1 | 4 | 4 | 4 | 6 | 6 | 1 | 1 | 1 | 0 | 0 |
| D | 0 | 0 | 0 | 1 | 1 | 2 | 2 | 2 | 1 | 0.5 | 0.5 | 0 |
Sheet1
Sheet2
Sheet3
risk management plan.doc
Risk Management Plan
Date
Project Name:
1. Methodology
2. Roles and Responsibilities
3. Budget and Schedule
4. Risk Categories
5. Risk Probability and Impact
6. Risk Documentation
risk register.xls
Sheet1
| Risk Register for Project Name | |||||||||||
| Date | |||||||||||
| Project Name: | |||||||||||
| ID No. | Rank | Risk | Description | Category | Root Cause | Triggers | Potential Responses | Risk Owner | Probability | Impact | Status |
Sheet2
Sheet3
run chart.xls
Sheet1
| Run Chart | |||
| Date | |||
| Be sure to enter your own data and check your formulas. | |||
| Defect 1 | Defect 2 | Defect 3 | |
| Jan | 5 | 10 | 3 |
| Feb | 4 | 9 | 5 |
| Mar | 5 | 9 | 2 |
| Apr | 5 | 8 | 7 |
| May | 4 | 7 | 1 |
| Jun | 7 | 7 | 5 |
| Jul | 8 | 7 | 6 |
| Aug | 10 | 6 | 3 |
| Sep | 11 | 6 | 8 |
| Oct | 11 | 6 | 4 |
| Nov | 12 | 6 | 7 |
| Dec | 13 | 6 | 5 |
Sheet1
Sheet2
Sheet3
scatter diagram.xls
Sheet1
| Scatter Diagram | |||
| Date | |||
| Be sure to enter your own data and check your formulas. | |||
| Rating | Age | ||
| 3 | 40 | ||
| 4 | 27 | ||
| 3.5 | 43 | ||
| 5 | 26 | ||
| 5 | 31 | ||
| 3 | 33 | ||
| 4.5 | 23 | ||
| 4 | 33 | ||
| 3 | 35 | ||
| 2.5 | 52 | ||
| 5 | 29 | ||
| 2 | 54 | ||
| 4.5 | 31 |
Sheet1
Sheet2
Sheet3
scope management plan.doc
Scope Management Plan
Date
Project Name:
Introduction
Preparing the Scope Statement
Creating the Work Breakdown Structure (WBS)
Verifying Completion of Project Deliverables
Managing Requests for Changes to Project Scope
scope statement.doc
Scope Statement (Version xx)
|
Project Title: Date: Prepared by: |
|
Project Justification: . |
|
Product Characteristics and Requirements:
|
|
Product User Acceptance Criteria: Summary of Project Deliverables Project management-related deliverables: business case, charter, team contract, scope statement, WBS, schedule, cost baseline, status reports, final project presentation, final project report, lessons-learned report, and any other documents required to manage the project. Product-related deliverables: research reports, design documents, software code, hardware, etc.
|
staffing management plan.doc
Staffing Management Plan
Date
Project Name:
Introduction
Staffing Requirements
This project will require the following internal staff:
Staff Assignments
Training, Rewards, and Reassignment
stakeholder management strategy.doc
Stakeholder Management Strategy for Project Name
Prepared by: Date:
|
Name |
Level of Interest |
Level of Influence |
Potential Management Strategies |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
stakeholder register.doc
Stakeholder Register for Project Name
Prepared by: Date:
|
Name |
Position |
Internal/External |
Project Role |
Contact Information |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
supplier evaluation matrix.xls
Sheet1
| Supplier Evaluation Matrix | |||||
| Date | |||||
| Note: Enter your criteria, weights, and scores in the template below. | |||||
| Add and delete rows and columns as needed. Formulas are bolded. | |||||
| Proposal 1 | Proposal 2 | ||||
| Criteria | Weight | Rating | Score | Rating | Score |
| A | 15% | 100 | 15 | 80 | 12 |
| B | 15% | 70 | 10.5 | 80 | 12 |
| C | 20% | 80 | 16 | 90 | 18 |
| D | 20% | 80 | 16 | 100 | 20 |
| E | 10% | 90 | 9 | 90 | 9 |
| F | 20% | 100 | 20 | 100 | 20 |
| Weighted Project Scores | 100% | 86.5 | 91 |
Sheet2
Sheet3
team charter.doc
Team Contract
Date
Project Name:
Project Team Members’ Names and Sign-off:
|
Name |
Date |
|
|
|
|
|
|
|
|
|
|
|
|
Code of Conduct: As a project team, we will:
Participation: We will:
Communication: We will:
Problem Solving: We will:
Meeting Guidelines: We will:
team performance assessment.doc
Team Performance Assessment
Date
Project Name:
Individual Name: ________________ Project Manager: __________________________
Date: __________________
1. Using a scale of 0-100, assess how you think the project team is performing: ________
2. Explain the rationale behind the above score.
3. Using a scale of 0-100, assess how you think you are performing on this project: ______
4. Explain the rationale behind the above score. What are your roles and responsibilities, and how well have you performed them?
5. Briefly assess each team member’s performance. If you had to give each person a score between 0-100, what would it be?
6. To compare individual contributions, if you had 100 points to allocate to your team, how would you allocate them?
7. What suggestions do you have for improving team performance?
team roster.doc
Team Roster
Date
Project Name:
|
Name |
Role on Project |
Position |
|
Phone |
Location |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
transition plan.doc
Transition Plan
Date
Project Name:
Introduction
Assumptions
Organization
Work Required
The main work required to support the products/services developed from this project includes:
Schedule
wbs dictionary entry.doc
WBS Dictionary Entry
Date
Project Name:
WBS Item Number:
WBS Item Name:
Description:
wbs.doc
Work Breakdown Structure (WBS)
Date
Project Name:
1.0 Main category 1
1.1 Subcategory
1.2 Subcategory
1.2.1 Sub-subcategory
1.2.2 Sub-subcategory
1.3 Subcategory
1.4 Subcategory
2.0 Main category 2
2.1 Subcategory
2.2 Subcategory
2.2.1 Sub-subcategory
2.2.2 Sub-subcategory
2.3 Subcategory
2.4 Subcategory
3.0 Main category 3
3.1 Subcategory
3.2 Subcategory
3.2.1 Sub-subcategory
3.2.2 Sub-subcategory
3.3 Subcategory
3.4 Subcategory
4.0 Main category 4
4.1 Subcategory
4.2 Subcategory
4.2.1 Sub-subcategory
4.2.2 Sub-subcategory
4.3 Subcategory
4.4 Subcategory
weighted scoring model.xls
Sheet1
| Weighted Scoring Model for Project Name | |||||
| Created by: | Date: | ||||
| Note: Enter your criteria, weights, and scores in the template below. | |||||
| Insert or clear rows and columns as needed. Double check formulas and results. | |||||
| Criteria | Weight | Project 1 | Project 2 | Project 3 | Project 4 |
| A | 25% | 90 | 90 | 50 | 20 |
| B | 15% | 70 | 90 | 50 | 20 |
| C | 15% | 50 | 90 | 50 | 20 |
| D | 10% | 25 | 90 | 50 | 70 |
| E | 5% | 20 | 20 | 50 | 90 |
| F | 20% | 50 | 70 | 50 | 50 |
| G | 10% | 20 | 50 | 50 | 90 |
| Weighted Project Scores | 100% | 56 | 78.5 | 50 | 41.5 |