business mgt

profilehelpmeout11
20170917234900group_4___project_quality_professionals___itp_3___it_system_wbs__1_1.pdf

ID Task

Mode

Task Name Duration Start Finish Predecessors

0 IT System Project 126.88 days?Wed 9/6/17 Thu 3/1/18

1 1 Conduct Kick-off Meeting on Implementing IT System Project 2 days Wed 9/6/17 Thu 9/7/17

2 1.1 Conduct meeting to confirm scope and identify project goals 2 days Wed 9/6/17 Thu 9/7/17

3 2 Plan Project Management Roadmap 8 days Fri 9/8/17 Tue 9/19/17

4 2.1 Establish project management meetings plan (Weekly

Assessment Report schedule, Project Team meetings)

2 days Fri 9/8/17 Mon 9/11/17 2

5 2.2 Establish team project process plan 3 days Tue 9/12/17 Thu 9/14/17 4

6 2.3 Determine team work schedules 2 days Tue 9/12/17 Wed 9/13/17

7 2.3.1 Establish schedule based on deliverables 2 days Tue 9/12/17 Wed 9/13/17 5SS

8 2.3.2 Establish schedules based on milestones and timeline 1 day Tue 9/12/17 Tue 9/12/17 5SS

9 2.4 Establish team collaboration strategies 4 days Tue 9/12/17 Fri 9/15/17

10 2.4.1 Identify project team skills and responsibilities 4 days Tue 9/12/17 Fri 9/15/17 5SS

11 2.5 Comprise stakeholder meeting schedule 1 day Tue 9/12/17 Tue 9/12/17 2,4

12 2.6 Discuss market sustainability, growth potential and initial

profitability the new IT system

7 days Mon

9/11/17

Tue 9/19/17

13 2.6.1 Forecast financial returns 1 day Wed 9/13/17Wed 9/13/17 11

14 2.6.2 Summarize operating expenses and financial projections 1 day Thu 9/14/17 Thu 9/14/17 13

15 2.6.3 Assess market size and stability 2 days Wed 9/13/17Thu 9/14/17 11

16 2.6.4 Create market analysis plan 2 days Mon 9/11/17Wed 9/13/17 15SF

17 2.6.5 Identify operating cost elements 3 days Wed 9/13/17Fri 9/15/17 16

18 2.6.6 Identify target market niche 1 day Mon 9/18/17Mon 9/18/17 17

19 2.6.7 Develop sales and marketing strategy 1 day Tue 9/19/17 Tue 9/19/17 18

20 3 Create Budget 16.5 days Wed 9/20/17Thu 10/12/17

21 3.1 Develop project budget and resource plan 4 days Wed 9/20/17Mon 9/25/17

M

Sep 3, '17

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Critical

Critical Split

Progress

Manual Progress

Page 1

Project: IT System Project

Date: Sun 9/17/17

ID Task

Mode

Task Name Duration Start Finish Predecessors

22 3.1.1 Determine financial requirements 3 days Wed 9/20/17Fri 9/22/17

23 3.1.1.1 Establish pricing strategy 1 day Wed 9/20/17Wed 9/20/17 14,19

24 3.1.1.2 Develop cash-flow projection 2 days Thu 9/21/17 Fri 9/22/17 23

25 3.1.2 Identify needed raw materials 1 day Mon 9/25/17Mon 9/25/17 24

26 3.2 Outline project resource requirements based on budget 3.5 days Mon 9/25/17Thu 9/28/17

27 3.2.1 Identify indirect labor cost 4 hrs Mon 9/25/17Mon 9/25/17 22SS,25SS

28 3.2.2 Identify direct labor cost 1 day Mon 9/25/17Tue 9/26/17 27

29 3.2.3 Identify general and administrative cost 3 days Mon 9/25/17Thu 9/28/17 13SF,17SS,28SS

30 3.3 Outline new IT System 13 days Mon 9/25/17Thu 10/12/17

31 3.3.1 Identify major hardware and software purchases 10 days Mon 9/25/17Mon 10/9/17

32 3.3.1.1 Compare hardware and software platforms for best

pricing

2 wks Mon

9/25/17

Mon 10/9/17 29SS

33 3.3.2 Identify systems dependencies 2 days Mon 10/9/17Wed 10/11/17 10,32

34 3.3.3 Design the Information system database 5 days Mon 10/2/17Mon 10/9/17 33SF

35 3.3.4 Discuss operating cost of new IT System implementation 3 days Mon 10/9/17Thu 10/12/17 34

36 4 Outline Project Plan 32.75 days? Thu 10/12/17Tue 11/28/17

37 4.1 Establish requirements based on customer objectives 6 days Thu 10/12/17Fri 10/20/17

38 4.1.1 Establish project metrics 1 day Thu 10/12/17Fri 10/13/17 35

39 4.1.2 Devise Project Implementation Plan 5 days Fri 10/13/17Fri 10/20/17

40 4.1.2.1 Consider your options 5 days Fri 10/13/17Fri 10/20/17

41 4.1.2.1.1 Hardware requirements 2 days Fri 10/13/17 Tue 10/17/17 31,38

42 4.1.2.1.2 Software requirements 1 day Fri 10/13/17 Mon 10/16/17 31SS,41SS

43 4.1.2.1.3 Network requirements 4 days Mon 10/16/17Fri 10/20/17 31,42

44 4.2 Establish Project process plan 3 days? Fri 10/13/17Wed 10/18/17

M

Sep 3, '17

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Critical

Critical Split

Progress

Manual Progress

Page 2

Project: IT System Project

Date: Sun 9/17/17

ID Task

Mode

Task Name Duration Start Finish Predecessors

45 4.2.1 Establish team efforts 1 day Fri 10/13/17 Mon 10/16/17 5,38

46 4.2.2 Create team interactions matrixes 1 day Mon 10/16/17Tue 10/17/17 45

47 4.2.3 Delineate team participation requirements 1 day? Mon 10/16/17Tue 10/17/17 46SS

48 4.2.4 Establish project documentations processes 1 day Tue 10/17/17Wed 10/18/17 47

49 4.3 Create project Charter 11 days Mon 10/16/17Tue 10/31/17

50 4.3.1 Identify key stakeholders 1 day Mon 10/16/17Tue 10/17/17 48SF

51 4.3.2 Define project objective 3 days Tue 10/17/17Fri 10/20/17 50

52 4.3.3 Define project Scope 1 day Fri 10/20/17 Mon 10/23/17 51

53 4.3.4 Define project milestones 1 day Mon 10/23/17Tue 10/24/17 52

54 4.3.5 Define personnel roles 2 days Fri 10/20/17Tue 10/24/17

55 4.3.5.1 Outline management staff roles 1 day Fri 10/20/17 Mon 10/23/17 5,53SF

56 4.3.5.2 Outline general staffing (cashiers, bakers, deli

workers, etc.) roles

1 day Mon

10/23/17

Tue 10/24/17 55

57 4.3.6 Identify unit and systems impact 5 days Tue 10/24/17Tue 10/31/17

58 4.3.6.1 Create project schedule 5 days Tue 10/24/17Tue 10/31/17

59 4.3.6.1.1 Identify requirements to produce deliverables 2 days Tue 10/24/17Thu 10/26/17 56

60 4.3.6.1.2 Identify system dependencies 1 day Thu 10/26/17Fri 10/27/17 59

61 4.3.6.1.3 Decide on hardware and software platforms 1 day Fri 10/27/17 Mon 10/30/17 60

62 4.3.6.1.4 Design the Information system databases 1 day Mon 10/30/17Tue 10/31/17 61

63 4.4 Create Work Breakdown Schedule 15 days Mon 10/23/17Mon 11/13/17

64 4.4.1 Determine what are the expected outcomes/benefits 1 day Mon 10/30/17Tue 10/31/17 62SS

65 4.4.2 Develop communication plan, to include frequency 1 day Mon 10/30/17Tue 10/31/17 64SS

66 4.4.3 Devise risk management plan 1 day Tue 10/31/17Wed 11/1/17

67 4.4.3.1 Identify strengths, weaknesses, assets and threats 1 day Tue 10/31/17Wed 11/1/17 65

M

Sep 3, '17

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Critical

Critical Split

Progress

Manual Progress

Page 3

Project: IT System Project

Date: Sun 9/17/17

ID Task

Mode

Task Name Duration Start Finish Predecessors

68 4.4.4 Develop project phase management plan 14 days Mon 10/23/17Fri 11/10/17

69 4.4.4.1 Plan Analysis phase 6 days Mon 10/23/17Tue 10/31/17 33SF,38SF,67SF

70 4.4.4.2 Plan system design 3 days Tue 10/31/17Fri 11/3/17 69

71 4.4.4.3 Plan system build 5 days Fri 11/3/17 Fri 11/10/17 70

72 4.4.4.4 Plan system testing 1 day Thu 11/9/17 Fri 11/10/17 71FF

73 4.4.5 Develop resource management plan 1 day Fri 11/10/17Mon 11/13/17

74 4.4.5.1 Identify needed materials and supplies 1 day Fri 11/10/17 Mon 11/13/17 72

75 4.5 Create Project Testing Plan 5.75 days Mon 11/13/17Tue 11/21/17

76 4.5.1 Determine test plan requirements 3 days Mon 11/13/17Thu 11/16/17 74

77 4.5.2 Get test plan approval 2 days Thu 11/16/17Mon 11/20/17 50,76

78 4.5.3 Establish Test Plan resumption criteria 6 hrs Mon 11/20/17Tue 11/21/17 77

79 4.6 Establish System Training Plan 1 day Tue 11/21/17Wed 11/22/17 78

80 4.7 Establish Project Transition Plan 3 days Wed 11/22/17Mon 11/27/17

81 4.7.1 Outline transition plan 1 day Wed 11/22/17Thu 11/23/17 79

82 4.7.2 Outline resource transition plan 2 days Thu 11/23/17Mon 11/27/17

83 4.7.2.1 Software 2 days Thu 11/23/17Mon 11/27/17 81

84 4.7.2.2 Hardware 2 days Thu 11/23/17Mon 11/27/17 83SS

85 4.7.2.3 Personnel (if applicable) 2 days Thu 11/23/17Mon 11/27/17 84SS

86 4.7.2.4 Facilities 1 day Thu 11/23/17Fri 11/24/17 85SS

87 4.7.2.5 Other applicable resources 1 day Fri 11/24/17 Mon 11/27/17 86

88 4.8 Establish project closeout procedures 1 day Mon 11/27/17Tue 11/28/17 87

89 5 Execution Phase - System Build 49 days Tue 11/28/17Mon 2/5/18

90 5.1 Install System and Network 10 days Tue 11/28/17Tue 12/12/17

M

Sep 3, '17

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Critical

Critical Split

Progress

Manual Progress

Page 4

Project: IT System Project

Date: Sun 9/17/17

ID Task

Mode

Task Name Duration Start Finish Predecessors

91 5.1.1 Allocate funds to purchase IT systems requirements 1 day Tue 11/28/17Wed 11/29/17 79,88

92 5.1.2 Purchase hardware systems 7 days Wed 11/29/17Fri 12/8/17

93 5.1.2.1 Order hardware 3 days Wed 11/29/17Mon 12/4/17 91

94 5.1.2.2 Receive Hardware 7 days Wed 11/29/17Fri 12/8/17 91,38

95 5.1.3 Purchase software system requirements 2 days Fri 12/8/17 Tue 12/12/17

96 5.1.3.1 Order software 1 day Fri 12/8/17 Mon 12/11/17 94

97 5.1.3.2 Receive software 1 day Mon 12/11/17Tue 12/12/17 96

98 5.2 Wireless Network Capabilities and Set Up Network

Infrastructure

14 days Wed

11/29/17

Tue 12/19/17

99 5.2.1 Purchase network systems requirements 14 days Wed 11/29/17Tue 12/19/17

100 5.2.1.1 Order network components 3 days Wed 11/29/17Mon 12/4/17 91

101 5.2.1.2 Receive network components 10 days Mon 12/4/17Mon 12/18/17 100

102 5.2.1.3 Deliver network components 1 day Mon 12/18/17Tue 12/19/17 101

103 5.3 Install Computer System with Network 10 days Mon 12/18/17Mon 1/1/18

104 5.3.1 Install hardware 4 days Mon 12/18/17Fri 12/22/17 91FF,94SF,102SS

105 5.3.2 Install software 3 days Fri 12/22/17 Wed 12/27/17 104

106 5.3.3 Install networking 3 days Wed 12/27/17Mon 1/1/18 105

107 5.4 Test systems functionalities and capabilities 17 days Wed 12/27/17Fri 1/19/18

108 5.4.1 Complete performance testing 1 wk Wed 12/27/17Wed 1/3/18 105

109 5.4.2 Complete regression testing 2 days Mon 1/1/18 Wed 1/3/18 108FF

110 5.4.3 Complete stress testing 3 days Wed 1/3/18 Mon 1/8/18 109

111 5.4.4 Comprise draft of test results 10 days Fri 1/5/18 Fri 1/19/18

112 5.4.4.1 Assess system failures with test team 1 day Fri 1/5/18 Mon 1/8/18 110FF

113 5.4.4.2 Implement edits and critiques from draft test plan 1 day Mon 1/8/18 Tue 1/9/18 112

M

Sep 3, '17

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Critical

Critical Split

Progress

Manual Progress

Page 5

Project: IT System Project

Date: Sun 9/17/17

ID Task

Mode

Task Name Duration Start Finish Predecessors

114 5.4.4.3 Resume test plan activities 1 day Tue 1/9/18 Wed 1/10/18 113

115 5.4.4.4 Complete final test of IT system 7 days Wed 1/10/18Fri 1/19/18

116 5.4.4.4.1 Continue progress evaluation 7 days Wed 1/10/18Fri 1/19/18 108,114

117 5.5 Monitor systems deployments 6 days Fri 1/19/18 Mon 1/29/18

118 5.5.1 Ensure systems requirements are met 2 days Fri 1/19/18 Tue 1/23/18 116

119 5.5.2 Ensure Network requirements are met 1 day Tue 1/23/18 Wed 1/24/18 118

120 5.5.3 Confirm network system efficiency 2 days Wed 1/24/18Fri 1/26/18 119,106

121 5.5.4 Validate that all project scope requirements are met 1 day Fri 1/26/18 Mon 1/29/18 108,120

122 5.6 Complete project final phase checkup 5 days Mon 1/29/18Mon 2/5/18

123 5.6.1 Complete final reassessment of systems capabilities 1 day Mon 1/29/18Tue 1/30/18 121

124 5.6.2 Test all equipment to prepare for normal use 5 days Mon 1/29/18Mon 2/5/18 110SS,120SS,123SS

125 6 Train employees on new IT system 10 days Mon 2/5/18 Mon 2/19/18

126 6.1 Show hardware and software 3 days Mon 2/5/18 Thu 2/8/18 124

127 6.2 Teach systems dependencies 2 days Mon 2/5/18 Wed 2/7/18 126SS

128 6.3 Train to use new system databases 5 days Mon 2/5/18 Mon 2/12/18 127SS

129 6.4 Provide overall instructions on system usage to organization5 days Mon 2/12/18Mon 2/19/18

130 6.4.1 Show how to use diverse applications 1 day Mon 2/12/18Tue 2/13/18

131 6.4.1.1 Provide instructions for data entry in systems 1 day Mon 2/12/18Tue 2/13/18 128

132 6.4.2 Provide basic system maintenance techniques to entire

organization

2 days Mon

2/12/18

Wed 2/14/18

133 6.4.2.1 Provide helpdesk support as outlined in scope of work 2 days Mon 2/12/18Wed 2/14/18 131SS

134 6.4.3 Provide basic system maintenance training to employees 3 days Wed 2/14/18Mon 2/19/18 133

135 7 Transition project to customer for approval 9 days Wed 2/14/18Tue 2/27/18

136 7.1 Test systems functionalities 2 days Wed 2/14/18Fri 2/16/18 134SS

M

Sep 3, '17

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Critical

Critical Split

Progress

Manual Progress

Page 6

Project: IT System Project

Date: Sun 9/17/17

ID Task

Mode

Task Name Duration Start Finish Predecessors

137 7.2 Conduct walk-thru - present to sponsor the new IT system

environment

7 days Fri 2/16/18 Tue 2/27/18 136

138 7.3 Get confirmation and acceptance from client 4 days Fri 2/16/18 Thu 2/22/18 121SF,137SS

139 7.4 Provide onsite support for first day of operations 3 days Thu 2/22/18 Tue 2/27/18 138

140 8 Perform closeout procedures 126.88 days Wed 9/6/17 Thu 3/1/18

141 8.1 Verify acceptance of final project deliverables 5 hrs Tue 2/27/18 Tue 2/27/18 139

142 8.2 Conduct Post-Project Assessment 2 days Tue 2/27/18 Thu 3/1/18

143 8.2.1 Evaluate market share against realistic initial market

sustainability, growth potential projections and profitability

2 days Tue 2/27/18 Thu 3/1/18 141

144 8.3 Conduct lessons learned session 1 day Mon 2/26/18Tue 2/27/18 143SF

145 8.4 Complete contract closure and audit requirements 3 days Mon 2/26/18Thu 3/1/18

146 8.4.1 Archive final project records 1 day Tue 2/27/18 Wed 2/28/18 144

147 8.4.2 Clear payment engagements 2 days Mon 2/26/18Wed 2/28/18 146FF

148 8.4.3 Sign closeout documents 1 day Wed 2/28/18Thu 3/1/18 147

149 8.5 End Project Review and Evaluation 0 days Wed 9/6/17 Wed 9/6/17

150 8.5.1 Promise to obey IT system support agreement 0 days Wed 9/6/17 Wed 9/6/17

9/6

9/6

M

Sep 3, '17

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Critical

Critical Split

Progress

Manual Progress

Page 7

Project: IT System Project

Date: Sun 9/17/17

T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S

Sep 3, '17 Sep 10, '17 Sep 17, '17 Sep 24, '17 Oct 1, '17 Oct 8, '17 Oct 15, '17

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Critical

Critical Split

Progress

Manual Progress

Page 8

Project: IT System Project

Date: Sun 9/17/17

T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S

Sep 3, '17 Sep 10, '17 Sep 17, '17 Sep 24, '17 Oct 1, '17 Oct 8, '17 Oct 15, '17

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Critical

Critical Split

Progress

Manual Progress

Page 9

Project: IT System Project

Date: Sun 9/17/17

T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S

Sep 3, '17 Sep 10, '17 Sep 17, '17 Sep 24, '17 Oct 1, '17 Oct 8, '17 Oct 15, '17

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Critical

Critical Split

Progress

Manual Progress

Page 10

Project: IT System Project

Date: Sun 9/17/17

T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S

Sep 3, '17 Sep 10, '17 Sep 17, '17 Sep 24, '17 Oct 1, '17 Oct 8, '17 Oct 15, '17

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Critical

Critical Split

Progress

Manual Progress

Page 11

Project: IT System Project

Date: Sun 9/17/17

T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S

Sep 3, '17 Sep 10, '17 Sep 17, '17 Sep 24, '17 Oct 1, '17 Oct 8, '17 Oct 15, '17

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Critical

Critical Split

Progress

Manual Progress

Page 12

Project: IT System Project

Date: Sun 9/17/17

T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S

Sep 3, '17 Sep 10, '17 Sep 17, '17 Sep 24, '17 Oct 1, '17 Oct 8, '17 Oct 15, '17

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Critical

Critical Split

Progress

Manual Progress

Page 13

Project: IT System Project

Date: Sun 9/17/17

9/6

9/6

T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S

Sep 3, '17 Sep 10, '17 Sep 17, '17 Sep 24, '17 Oct 1, '17 Oct 8, '17 Oct 15, '17

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Critical

Critical Split

Progress

Manual Progress

Page 14

Project: IT System Project

Date: Sun 9/17/17

S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W

Oct 15, '17 Oct 22, '17 Oct 29, '17 Nov 5, '17 Nov 12, '17 Nov 19, '17 Nov 26, '17 Dec 3, '17

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Critical

Critical Split

Progress

Manual Progress

Page 15

Project: IT System Project

Date: Sun 9/17/17

S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W

Oct 15, '17 Oct 22, '17 Oct 29, '17 Nov 5, '17 Nov 12, '17 Nov 19, '17 Nov 26, '17 Dec 3, '17

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Critical

Critical Split

Progress

Manual Progress

Page 16

Project: IT System Project

Date: Sun 9/17/17

S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W

Oct 15, '17 Oct 22, '17 Oct 29, '17 Nov 5, '17 Nov 12, '17 Nov 19, '17 Nov 26, '17 Dec 3, '17

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Critical

Critical Split

Progress

Manual Progress

Page 17

Project: IT System Project

Date: Sun 9/17/17

S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W

Oct 15, '17 Oct 22, '17 Oct 29, '17 Nov 5, '17 Nov 12, '17 Nov 19, '17 Nov 26, '17 Dec 3, '17

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Critical

Critical Split

Progress

Manual Progress

Page 18

Project: IT System Project

Date: Sun 9/17/17

S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W

Oct 15, '17 Oct 22, '17 Oct 29, '17 Nov 5, '17 Nov 12, '17 Nov 19, '17 Nov 26, '17 Dec 3, '17

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Critical

Critical Split

Progress

Manual Progress

Page 19

Project: IT System Project

Date: Sun 9/17/17

S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W

Oct 15, '17 Oct 22, '17 Oct 29, '17 Nov 5, '17 Nov 12, '17 Nov 19, '17 Nov 26, '17 Dec 3, '17

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Critical

Critical Split

Progress

Manual Progress

Page 20

Project: IT System Project

Date: Sun 9/17/17

9/6

9/6

S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W

Oct 15, '17 Oct 22, '17 Oct 29, '17 Nov 5, '17 Nov 12, '17 Nov 19, '17 Nov 26, '17 Dec 3, '17

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Critical

Critical Split

Progress

Manual Progress

Page 21

Project: IT System Project

Date: Sun 9/17/17

W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S

Dec 3, '17 Dec 10, '17 Dec 17, '17 Dec 24, '17 Dec 31, '17 Jan 7, '18 Jan 14, '18 Jan 21, '18

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Critical

Critical Split

Progress

Manual Progress

Page 22

Project: IT System Project

Date: Sun 9/17/17

W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S

Dec 3, '17 Dec 10, '17 Dec 17, '17 Dec 24, '17 Dec 31, '17 Jan 7, '18 Jan 14, '18 Jan 21, '18

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Critical

Critical Split

Progress

Manual Progress

Page 23

Project: IT System Project

Date: Sun 9/17/17

W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S

Dec 3, '17 Dec 10, '17 Dec 17, '17 Dec 24, '17 Dec 31, '17 Jan 7, '18 Jan 14, '18 Jan 21, '18

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Critical

Critical Split

Progress

Manual Progress

Page 24

Project: IT System Project

Date: Sun 9/17/17

W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S

Dec 3, '17 Dec 10, '17 Dec 17, '17 Dec 24, '17 Dec 31, '17 Jan 7, '18 Jan 14, '18 Jan 21, '18

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Critical

Critical Split

Progress

Manual Progress

Page 25

Project: IT System Project

Date: Sun 9/17/17

W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S

Dec 3, '17 Dec 10, '17 Dec 17, '17 Dec 24, '17 Dec 31, '17 Jan 7, '18 Jan 14, '18 Jan 21, '18

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Critical

Critical Split

Progress

Manual Progress

Page 26

Project: IT System Project

Date: Sun 9/17/17

W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S

Dec 3, '17 Dec 10, '17 Dec 17, '17 Dec 24, '17 Dec 31, '17 Jan 7, '18 Jan 14, '18 Jan 21, '18

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Critical

Critical Split

Progress

Manual Progress

Page 27

Project: IT System Project

Date: Sun 9/17/17

W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S

Dec 3, '17 Dec 10, '17 Dec 17, '17 Dec 24, '17 Dec 31, '17 Jan 7, '18 Jan 14, '18 Jan 21, '18

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Critical

Critical Split

Progress

Manual Progress

Page 28

Project: IT System Project

Date: Sun 9/17/17

S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T

Jan 21, '18 Jan 28, '18 Feb 4, '18 Feb 11, '18 Feb 18, '18 Feb 25, '18 Mar 4, '18

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Critical

Critical Split

Progress

Manual Progress

Page 29

Project: IT System Project

Date: Sun 9/17/17

S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T

Jan 21, '18 Jan 28, '18 Feb 4, '18 Feb 11, '18 Feb 18, '18 Feb 25, '18 Mar 4, '18

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Critical

Critical Split

Progress

Manual Progress

Page 30

Project: IT System Project

Date: Sun 9/17/17

S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T

Jan 21, '18 Jan 28, '18 Feb 4, '18 Feb 11, '18 Feb 18, '18 Feb 25, '18 Mar 4, '18

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Critical

Critical Split

Progress

Manual Progress

Page 31

Project: IT System Project

Date: Sun 9/17/17

S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T

Jan 21, '18 Jan 28, '18 Feb 4, '18 Feb 11, '18 Feb 18, '18 Feb 25, '18 Mar 4, '18

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Critical

Critical Split

Progress

Manual Progress

Page 32

Project: IT System Project

Date: Sun 9/17/17

S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T

Jan 21, '18 Jan 28, '18 Feb 4, '18 Feb 11, '18 Feb 18, '18 Feb 25, '18 Mar 4, '18

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Critical

Critical Split

Progress

Manual Progress

Page 33

Project: IT System Project

Date: Sun 9/17/17

S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T

Jan 21, '18 Jan 28, '18 Feb 4, '18 Feb 11, '18 Feb 18, '18 Feb 25, '18 Mar 4, '18

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Critical

Critical Split

Progress

Manual Progress

Page 34

Project: IT System Project

Date: Sun 9/17/17

S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T

Jan 21, '18 Jan 28, '18 Feb 4, '18 Feb 11, '18 Feb 18, '18 Feb 25, '18 Mar 4, '18

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Critical

Critical Split

Progress

Manual Progress

Page 35

Project: IT System Project

Date: Sun 9/17/17