CASE STUDY RESEARCH PAPER- REPORT ( 48 Hours - A+ Score Required)

profilejhayes
2.CONE-Presentation.pptx

Ibrahim Alsaeed #32

CONE-430

Summer2017

Professor Hossein Hemati

Pendry Hotel

General Contractor: Davis Reed Owner: Robert Green Company Project Cost: $105 million Project Duration: 27 months Start Date: October 8th 2017 Finish Date: March 2019

Building Features

Pendry Hotel San Diego will feature:

317 guest rooms, including 36 suites

A rooftop pool

Two uniquely-designed restaurants

A regional micro-brew beer hall

6,200-square-foot state-of-the-art spa/fitness facility

Over 30,000 square feet of meeting space

Subterranean parking in three stories below grade

Site Logistics and Layout

The project is located in the Gaslamp Quarter of downtown San Diego

The project sits on a 1 ½ acre site, this area also includes the pedestrian sidewalk which was annexed into the project

The Gaslamp Quarter Association only allows construction to occur from the hours of 7 am to 5 pm

Location of project outlined in red

Site Layout Continued

Site Layout 4/22/18

Site Layout Diagram

Comat pc 300 Excavator Cycle Time Data

Cycle Time:

load bucket 6 Seconds

Actual load 6*0.35= 2.1 seconds

Swing time load 4 Seconds

Actual Swing 4*1.67= 6.7 Seconds

Empty bucket 3 Seconds

Swing time empty 4 Seconds

Actual Swing empty 4*1.67= 6.7 Seconds

Theoretical Cycle time 18.5 Seconds

Actual Total Cycle Time = 18.7 Seconds

Estimated Productivity:

Probably production: 338 bcy/hr

Time period of the excavation:

Hours of excavating: 680 hr.

Days for operation: 680 hr./10 hr/day = 68 days

Machine: KomatSu Pc 300lc Angle of Swing: 100 Degrees

Depth of Excavation: 3 ft FIll Factor 100%

Cat 450 E Cycle Time Data

Machines : Two Cat 450 E Angle of Swing: 100 Degrees

Depth of Excavation: 3 ft FIll Factor 100%

Cycle Time:

load bucket 5.5 Seconds

Actual load 6*0.35= N/A

Swing time load 3 Seconds

Actual Swing 4*1.67= N/A

Empty bucket 2 Seconds

Swing time empty 3 Seconds

Actual Swing empty 4*1.67= N/A

Theoretical Cycle time 15.9 Seconds

Actual Total Cycle Time = N/A

Estimated Productivity: Bucket size 1.75 yd^3

Probably production: 440 bcy/hr

Time period of the excavation:

Hours of excavating: 552 hr.

Days for operation: 552 hr./10 hr/day = 55.2 days

Equipment Analysis

Cat 450 E

If two smaller excavators, the Cat 450 E were used then a cost and time saving could be achieved.

+

Comat pc 300

The single Comat pc 300 offers good excavation production rate but not as good as two cat 450 E.

VS

55.2 Days vs 68 Days

12.8 Days of Savings

Cost Savings

$107,946 per month x (2.1 / 5 ) = $5,000 saved in General Conditions Alone

* 2.1 weeks saved

* 5 weeks in a month

Summary

Based on the cycle times and my calculations Davis Reed would be better off using two smaller Cat 450 Es which would result in an accelerated excavation of the foundation and underground parking garage. By accelerating the schedule for the excavation and equipment alike, the cost would be less than the cost for the operation while taking less time.