$60 fixed draft due in 6hrs ..final paper in 12hrs 3000 words
Project Management 1
Project Management
Contents
4Abstract
6 Aim
7 PMP
16 Functional and Non-functional requirements
18 Conclusion
19 References
21 Appendix
List of Figures
11Figure 1: Gantt chart of Website designing
17 Figure 2: Use case diagram of Website design
22 Figure 1: Gantt chart of Website designing
23 Figure 2: Use case diagram of Website design
Abstract
The main purpose of this report was created to the design website and web page for ICPS (Indian Courier and Packing Supply). With the help of this project, the ICPS (Indian Courier and Packing Supply) company can be easily managed the information of customers and it will also provide the help to the locate the customer's address by using the GPS system or technology and company can easily track the orders. GPS and mobile & computer technology were utilized tothe design website and web page for ICPS (Indian Courier and Packing Supply) company. With the help of GPS and mobile & computer technology, the ICPS Company was controlling the tracking information of parcels (goods) from one place to another place in the nation. The web designing was completed for the ICPS (Indian Courier and Packing Supply) company within the 24 days and the project budget was AUD $6000. It was enhancing the order tracking capacity of the company from one place to another place in the nation. With the help of the web design, the ICPS Company should tie up with the numbers of big companies for expanding business in the future and the company can also enhance the revenue in the future.
Introduction
In this assignment report, the design website and web page are designing for the ICPS (Indian Courier and Packing Supply) company to expand business in different areas. ICPS (Indian Courier and Packing Supply) is a small company and it delivers goods in a small town and nearby areas.The location tracking functionality is adding in this project to track the exact address location of the customers. So, the ICPS (Indian Courier and Packing Supply) company can easily go online and track the address location of the customers from one place to another place in the nation. The ICPS Company can easily tie up with the numbers of big companies for expanding a business. The website will easy to use and it has small numbers of pages and this website can easily maintain and update. It will provide the 24 hours services in all day and it will enhance the profit level of the company. The designing of the website will complete within 24 days and estimate the budget of the project is AUD $6000.
The whole project is dividing into different phases such as the first phase is describing details of the project charter such as objectives, success criteria, deliverables, benefits, dependencies, assumptions, constraints, timeframe, cost estimation, and completion date. The second phase will describe the project WBS and project schedule in the form of different types of activities. The project risks are managing with the help of risk management technique. The next phase is describing the information of different types of required documents such as user requirements, system requirement, domain requirements, no-functional & functional requirements, and use case diagram of the designed website.
Aim
The main aim of this project is to design the web page and website for the for ICPS (Indian Courier and Packing Supply) to track the exact location of the customer order and web page design will also help to expand the business. With the help of this project, mobile and computer technology can use with the same experience. So, the ICPS Company can easily reduce the delivery timing of the parcels and goods. All the data information will be centralized with the help of the website design and GPS tracking technology. The website design will enhance the security of company information and customer information that is the main objective of this website design.
PMP
Project Charter |
|
|
Project Name – Website Design |
Project Manager – Amanjot Singh |
|
Background/Rationale – ICPS (Indian Courier and Packing Supply) is a small company delivering goods in small town and nearby areas. |
|
|
Objective/s · Creating a webpage for company to expand business · Adding a location tracker to know exact location of client
|
Success Criteria – · Client Involvement, active communication, consultation and listening to all parties. · Ongoing training and orientation to the employees · Security and updates on required periods |
|
Deliverables - The main deliverable of this project will be designing a website so that company can go online and can start taking orders from local people as to drop and parcel goods from one place to other nationally and with this they can tie up with big companies to expand business. |
|
|
Benefits Expected – · User-Centered · a smaller number of pages, easy to use · A mobile first design strategy will help to use on mobiles and computer with same experience · Easy to update and maintain · 24/7 services
|
Dependencies · a strong network connection · a good number of computers · GPS or location trackers
|
|
Assumptions – this project is based on the following assumptions · the company is committed to designing a webpage that is user centered · Help to locate the customer address using GPS. |
Constraints · Project team: we have complete confidence in the project team but also realize that the individuals on the team have other demands on their time that might be the risk · Timing of user testing: Getting user to participate in user testing can be difficult. |
|
Timeframe: Time frame the whole project is 24 days |
Cost Estimate/Budget: AUD $6000 |
|
Dated Approvals/Sign-offs - 29/03/2019 AMANJOT SINGH |
Project Manager Sign-off & Date –29/03/2019 KARTIKEY RAJPAL |
(Milosevic and Martinelli, 2016)
Work Breakdown Structure
Table 1: Work Breakdown Structure Table
|
S. No. |
Tasks ID |
Activities of the Project |
Total Duration |
Starting Date |
Ending Date |
Predecessor |
|
1. |
0 |
Website design of ICPS (Indian Courier and Packing Supply) |
24 days |
3/29/2019 |
5/1/2019 |
|
|
2. |
1. |
Creating the project charter |
2 days |
3/29/2019 |
4/1/2019 |
|
|
3. |
2. |
Get the project Signed |
1 day |
4/2/2019 |
4/2/2019 |
1 |
|
4. |
3. |
Identify needs of website |
1 day |
4/3/2019 |
4/3/2019 |
2,1 |
|
5. |
4. |
Analysis the needs of website |
1 day |
4/4/2019 |
4/4/2019 |
3,2 |
|
6. |
5. |
Understand the project purpose |
1 day |
4/5/2019 |
4/5/2019 |
4 |
|
7. |
6. |
Decide the hosting name |
1 day |
4/8/2019 |
4/8/2019 |
5 |
|
8. |
7. |
Register domain name |
1 day |
4/9/2019 8:00 |
4/9/2019 |
6,5 |
|
9. |
8. |
Design website look |
1 day |
4/10/2019 |
4/10/2019 |
7 |
|
10. |
9. |
Design home page |
2 days |
4/11/2019 |
4/12/2019 |
8 |
|
11. |
10. |
Design interior page |
2 days |
4/15/2019 |
4/16/2019 |
9,8 |
|
12. |
11. |
Develop web content structure |
2 days |
4/17/2019 |
4/18/2019 |
10 |
|
13. |
12. |
Research and write content |
2 days |
4/19/2019 |
4/22/2019 |
11,10 |
|
14. |
13. |
Build pages |
2 days |
4/23/2019 |
4/24/2019 |
12 |
|
15. |
14. |
Run the usability test |
2 days |
4/25/2019 |
4/26/2019 |
13 |
|
16. |
15. |
Resolve all issues |
2 days |
4/29/2019 |
4/30/2019 |
14,13 |
|
17. |
16. |
Sign off the project |
1 day |
5/1/2019 |
5/1/2019 |
15 |
(Andersen, 2016)
The work breakdown structure is organizing the development or design of the website for the ICPS (Indian Courier and Packing Supply) company in a specific manner. The WBS is designing for the “Website design of the ICPS (Indian Courier and Packing Supply) company” and it is delivering the different types of details such as name of project, activities, end and star date, task ids, predecessors and senior numbers and these details are using to complete the development of the website on the time. The project has started on 29 March 2019 and it has completed on 1 May 2019.
Project Schedule
The project scheduling is utilized to manage all the project activities in a specific manner and project scheduling is a proposed plan and this plan will implement when the website will design for theICPS (Indian Courier and Packing Supply) company. Project scheduling is very helpful to know which activity will perform next and which activity has completed (Heldman, 2018). In this website designing, different types of activities are scheduling which are started from a particular date and it will complete on a particular date. The designing of the website has started from 29 March 2019 and it will be finished on 1 May 2019. Different types of resources are working on this project.
1. Project Manager
2. Web Developer
3. Software engineer
4. Testing Engineer
5. Data Analyst
6. Business Analyst
7. Admin Staff.
Figure 1: Gantt chart of Website designing
The above Gantt chart is representing different types of activities in the graphical format and Gantt chart is also showing that many activities are performing at the same time such as “Get the project Signed” and “Identify needs of website activities” are performing at the same time. The designing of the website is completing in the 24 days and website designing is AUD $6000. It is representing the predecessor and starts& end date of each activity and it will help to schedule project work in an efficient manner.
Risk Management
Risk is the effect of uncertainty on objectives, whether is a positive or negative. It can be related to time, cost, scope, or quality related effects. A risk can have one or more causes and similarly have one or more impacts (Choi et al. 2016).
The techniques use of to minimize or terminate the risk or its impact on project or daily life is known as risk management.
· Protect scope statement
· Website is too complex to use by end user or by organization itself
· Staff or stakeholder does not like the website for e.g. they are not happy with graphics work, coding or it does not meet their expectations
· Website firewall is no good defends from bugs, contain lots bugs
· Hardware to slow does not meet with new system
· Communication Management Plan
· Wrong user requirements
|
RISK MANAGEMENT LOG |
|
|
|
|
|
|
|
|
|
|
Project Name: |
|
Website Design for the ICPS (Indian Courier and Packing Supply) company |
|||||||
|
Project Manager Name: |
|
Amanjot Singh |
|||||||
|
Project Description: |
|
Design website for ICPS company to expand the business and track the actual location of customer address |
|||||||
|
ID |
Current Status |
Risk Category |
Risk Description |
Risk Impact |
Probability of Occurrence |
Risk Rating |
Risk Response Strategy |
Response Strategy |
Assigned To |
|
WDICPS11 |
Open |
Technical Obsolescence |
The website firewall may not defend the website from virus, lots of bugs, bugs, and hackers. |
High |
Medium |
High |
Mitigation |
Set the firewall setting according to the website design and LINUX platform. |
The testing engineer and software engineer will responsible to mitigate this risk. |
|
WDICPS12 |
Open |
Project Resources |
It can be possible that proper resources will not available to complete the website design for the ICPS (Indian Courier and Packing Supply) company |
Low |
Medium |
Low |
Avoidance |
The availability of resources must check on a daily basis such as LINUX software, website design, etc. |
To avoid this risk, the project manager will responsible and the project manager must check the availability of internal resources. |
|
WDICPS13 |
Open |
Security |
It can be possible that the essential information of customers can be stolen. |
High |
Medium |
High |
Mitigation |
The proper security technique must use to secure the essential information of customers such as two-way authentication. |
The Software engineer will responsible to integrate security technique with website design. |
|
WDICPS14 |
Open |
Data/Information |
The designing of the website can be affected due to the less communication between stakeholders and team members |
High |
High |
High |
Mitigation |
The proper communication plan must be developed to communicate all information between stakeholders and team members |
The project manager will responsible to mitigate this risk. |
|
WDICPS15 |
Open |
Project Management |
If proper motivation will not provide to each team member then this type of risk can occur |
Medium |
Low |
Medium |
Mitigation |
The proper motivation will provide to each team member to complete the internal process of website designing |
The project manager will responsible to mitigate this risk. |
Requirements Document
User Requirements
User requirement describes the expectation of users and how users will interact with the website design. The different types of user requirements are given below:
· The website design must user-friendly so users can easily use.
· Loading timing of website should be less as possible as.
· The tracking information of customers must be done in a proper manner (Coleyconsulting, 2018).
· The essential information of customers should be secured from hackers, bugs, virus, etc.
· Response time of the website should minimum as compared to other websites.
· The website should accept customer orders.
System requirements
For designing the website, the different types of software and hardware resources are needed and these resources are known as the system requirements that are given below:
· Design website should be compatible with the different types of the version of operating systems such as Microsoft Windows XP, 98, mobile phone, etc.
· The LINUX Kernel should support the new operating systems.
· The website design should support to each web browser such as default browser must install on the system (Usability, 2018).
· The website design must have a strong network or internet connection.
Domain Requirements
The domain name is used to represent the Internet Protocol in the website designing of the ICPS (Indian Courier and Packing Supply) company. To register the domain name, the key requirements are needed to connect the specific search with a domain (Websitebuilderexpert, 2016). The different types of domain requirements are given below:
· Administrative contact to manage the domain name.
· Technical contact to manage the name servers of the website domain.
· Billing contact to manage billing invoices information and pay applicable fees.
Functional and Non-functional requirements
The functional requirements of website designing describe that what website or software should perform functions (New2HTML, 2016). So the functional requirements of website designing are:
· The web application should able to produce monthly and weekly reports of delivery.
· Set the firewall setting according to the website design and LINUX platform.
· The GPS system must track the customer address details in the proper manner.
· The web application should available for 24 hours.
The non-functional requirement doesn’t describe the system’s functions. The non-functional requirements include the reliability and response timing of the system(New2HTML, 2016). So non-functional requirements of website designing are:
· Response time of the website should minimum as compared to other websites.
· The web application should available in different types of languages.
· The reliability of web application should be good.
Use case diagram
Figure 2: Use case diagram of Website design
Source: (Wikitechy, 2018)
The use case is the simplest way to show the interaction between the system and users. The use case diagram of the website design is describing the functionality of the new system (Lovelycoding, 2018) such as first of all, company admin will login the website after that admin will view the details of the item. The customers can also view the details of the item. After that, an admin will add the delivery boy details then tracks the customers address details and users can check the delivery details. After that, an admin will check the status of users then delivery boy delivers the products that status will update at the website.
Conclusion
It has concluded from this report that web application has designed for the ICPS (Indian Courier and Packing Supply) company. With the help of this website, the ICPS Company has expanded its business in different areas.ICPS is a small company and it is delivering goods in a small town and nearby areas. The location tracking functionality has added in this project to track the exact address location of the customers. For designing website, the project charter, WBS and project schedule has prepared and different types of risks have controlled with the help of a risk management plan. The different types of document requirements have also prepared in the website designing such as users requirement, system, and domain requirement, etc.
References
Milosevic, D.Z. and Martinelli, R.J. (2016) Project management toolbox: tools and techniques for the practicing project manager. John Wiley & Sons.
Andersen, E.S. (2016) Do project managers have different perspectives on project management?. International Journal of Project Management, 34(1), pp.58-65.
Heldman, K. (2018) PMP: project management professional exam study guide. John Wiley & Sons.
Choi, T.M., Wallace, S.W. and Wang, Y. (2016) Risk management and coordination in service supply chains: information, logistics and outsourcing. Journal of the Operational Research Society, 67(2), pp.159-164.
Coleyconsulting. (2018) User Requirements - three areas to include and one to avoid.. [Online] Available at: https://www.coleyconsulting.co.uk/require.htm [Accessed: 7 May 2019].
Website builder expert.(2016) What You Need to Build a Website - The Definitive Website Checklist. [Online] Available at: https://www.websitebuilderexpert.com/building-websites/what-you-need-to-build-a-website-checklist/ [Accessed: 7 May 2019].
Usability.(2018) Website Requirements | Usability.gov. [Online] Available at: https://www.usability.gov/how-to-and-tools/methods/requirements.html [Accessed: 7 May 2019].
New2HTML. (2016) Developing Website Requirements - (Functional vs. Non-Functional) - New2HTML. [Online] Available at: http://www.new2html.com/website/developing-website-requirements-functional-vs-non-functional/ [Accessed: 7 May 2019].
Wikitechy.(2018) Courier Service System - Use Case Diagram. [Online] Available at: https://www.wikitechy.com/final-year-project/java/courier-service-system/use-case-diagram [Accessed: 7 May 2019].
Lovelycoding. (2018) Courier management System For Final Year ( PHP, Java, Andriod). [Online] Available at: http://services.lovelycoding.org/courier-management-system/ [Accessed: 7 May 2019].
Appendix
Work Breakdown Structure
Table 1: Work Breakdown Structure Table
|
S. No. |
Tasks ID |
Activities of the Project |
Total Duration |
Starting Date |
Ending Date |
Predecessor |
|
18. |
0 |
Website design of ICPS (Indian Courier and Packing Supply) |
24 days |
3/29/2019 |
5/1/2019 |
|
|
19. |
17. |
Creating the project charter |
2 days |
3/29/2019 |
4/1/2019 |
|
|
20. |
18. |
Get the project Signed |
1 day |
4/2/2019 |
4/2/2019 |
1 |
|
21. |
19. |
Identify needs of website |
1 day |
4/3/2019 |
4/3/2019 |
2,1 |
|
22. |
20. |
Analysis the needs of website |
1 day |
4/4/2019 |
4/4/2019 |
3,2 |
|
23. |
21. |
Understand the project purpose |
1 day |
4/5/2019 |
4/5/2019 |
4 |
|
24. |
22. |
Decide the hosting name |
1 day |
4/8/2019 |
4/8/2019 |
5 |
|
25. |
23. |
Register domain name |
1 day |
4/9/2019 8:00 |
4/9/2019 |
6,5 |
|
26. |
24. |
Design website look |
1 day |
4/10/2019 |
4/10/2019 |
7 |
|
27. |
25. |
Design home page |
2 days |
4/11/2019 |
4/12/2019 |
8 |
|
28. |
26. |
Design interior page |
2 days |
4/15/2019 |
4/16/2019 |
9,8 |
|
29. |
27. |
Develop web content structure |
2 days |
4/17/2019 |
4/18/2019 |
10 |
|
30. |
28. |
Research and write content |
2 days |
4/19/2019 |
4/22/2019 |
11,10 |
|
31. |
29. |
Build pages |
2 days |
4/23/2019 |
4/24/2019 |
12 |
|
32. |
30. |
Run the usability test |
2 days |
4/25/2019 |
4/26/2019 |
13 |
|
33. |
31. |
Resolve all issues |
2 days |
4/29/2019 |
4/30/2019 |
14,13 |
|
34. |
32. |
Sign off the project |
1 day |
5/1/2019 |
5/1/2019 |
15 |
Figure 1: Gantt chart of Website designing
Figure 2: Use case diagram of Website design