Project Plan

profileamericaneagle
13.11.22STRBCKS_BA.pdf

ID Task Mode

Task Name Duration Start Finish Predecessors

1 Starbucks_BA 2 1.0 Social media listening 7 days Sun 11/13/22 Mon 11/21/22 3 1.1 Establish an objective 2 days Sun 11/13/22 Mon 11/14/22 4 1.2 Monitor social media channels2 days Mon 11/14/22 Tue 11/15/22 3 5 1.3 Analyze the information 2 days Tue 11/15/22 Wed 11/16/22 4 6 1.4 Create response 4 days Wed 11/16/22 Mon 11/21/22 5 7 2.0 Survey 7 days Mon 11/14/22 Tue 11/22/22 8 2.1 Set the objectives of the survey1 day Sun 11/13/22 Sun 11/13/22 9 2.2 Define the targeted population1 day Mon 11/14/22 Mon 11/14/22 8

10 2.3 Decide the type of survey 1 day Tue 11/15/22 Tue 11/15/22 9 11 2.4 Design the survey questions 2 days Wed 11/16/22 Thu 11/17/22 10 12 2.5 Distribute the Survey 2 days Fri 11/18/22 Mon 11/21/22 11 13 2.6 Collect responses and write

up the survey findings 1 day Mon 11/21/22 Mon 11/21/22 12

14 2.7 Analyze the results 1 day Tue 11/22/22 Tue 11/22/22 13 15 3.0 Starbucks report analysis 7 days? Sun 11/13/22 Mon 11/21/22 7 16 3.1 Analyze Starbucks’ Global

Environmental & Sustainability report and Synthesize goals for 2030

1 day Sun 11/13/22 Sun 11/13/22

17 3.2 Synthesize progress towards that goal

2 days Sun 11/13/22 Mon 11/14/22 16

18 3.2.1 Determine progress made2 days Sun 11/13/22 Mon 11/14/22 19 3.2.2 Determine remaining

progress needed 1 day Mon 11/14/22 Mon 11/14/22 18

20 3.3 Synthesize strategies for change3 days Wed 11/16/22 Fri 11/18/22 17

Oct Nov Dec Jan Qtr 4, 2022

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 1

Project: Starbucks Date: Sun 11/13/22

ID Task Mode

Task Name Duration Start Finish Predecessors

21 3.4 Analyze the degree to which the product adheres to current goals and strategies

1 day Sat 11/19/22 Sat 11/19/22 20

22 3.5 Determine the degree to which the product addresses Starbucks business needs

1 day Sat 11/19/22 Sat 11/19/22 21

23 3.6 Convert data into requirements2 days Sat 11/19/22 Mon 11/21/22 22 24 3.7 Approve final requirements 2 days Sat 11/19/22 Mon 11/21/22 23 25 4.0 Cost benefit analysis 7 days Sun 11/13/22 Mon 11/21/22 15 26 4.1 Establishement of

framework for the analysis 2 days Sun 11/13/22 Mon 11/14/22

27 4.2 Identifcation of direct and indirect cost and its benefits

4 days Mon 11/14/22 Thu 11/17/22 26

28 4.3 Value of each costs and its benefits

2 days Fri 11/18/22 Mon 11/21/22 27

29 4.4 Tally the total value of beneifts and cost in order to compare

0 days Mon 11/21/22 Mon 11/21/22 28

30 5.0 Evaluate solution requirements15 days Tue 11/22/22 Mon 12/12/22 25

11/21

Oct Nov Dec Jan Qtr 4, 2022

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 2

Project: Starbucks Date: Sun 11/13/22