PROJECT MANAGEMENT

THE MANAGERIAL PROCESS 7E

ERIK W. LARSON CLIFFORD F. GRAY

Connect Insight® Connect Insight is Connect’s new one-of-a-kind visual analytics dashboard—now available for both instructors and students—that provides at-a-glance information regarding student performance, which is immediately actionable. By presenting assignment, assessment, and topical performance results together with a time metric that is easily visible for aggregate or individual results, Connect Insight gives the user the ability to take a just-in-time approach to teaching and learning, which was never before available. Connect Insight presents data that empowers students and helps instructors improve class performance in a way that is efficient and effective.

McGraw-Hill Connect® Learn Without Limits Connect is a teaching and learning platform that is proven to deliver better results for students and instructors.

Connect empowers students by continually adapting to deliver precisely what they need, when they need it, and how they need it, so your class time is more engaging and effective.

Mobile

73% of instructors who use Connect require it; instructor satisfaction increases

by 28% when Connect is required.

Students can view their results for any

Connect course.

Analytics

Connect’s new, intuitive mobile interface gives students and instructors flexible and convenient, anytime–anywhere access to all components of the Connect platform.

Required=Results

®

©Getty Images/iStockphoto

Using Connect improves retention rates by 19.8%, passing rates by 12.7%, and exam scores by 9.1%.

SmartBook® Proven to help students improve grades and study more efficiently, SmartBook contains the same content within the print book, but actively tailors that content to the needs of the individual. SmartBook’s adaptive technology provides precise, personalized instruction on what the student should do next, guiding the student to master and remember key concepts, targeting gaps in knowledge and offering customized feedback, and driving the student toward comprehension and retention of the subject matter. Available on tablets, SmartBook puts learning at the student’s fingertips—anywhere, anytime.

Adaptive

Over 8 billion questions have been answered, making McGraw-Hill

Education products more intelligent, reliable, and precise.

THE ADAPTIVE READING EXPERIENCE DESIGNED TO TRANSFORM THE WAY STUDENTS READ

More students earn A’s and B’s when they use McGraw-Hill Education Adaptive products.

www.mheducation.com

The McGraw-Hill Series Operations and Decision Sciences

OPERATIONS MANAGEMENT Beckman and Rosenfield, Operations, Strategy: Competing in the 21st Century, First Edition

Benton, Purchasing and Supply Chain Management, Second Edition

Bowersox, Closs, Cooper, and Bowersox, Supply Chain Logistics Management, Fourth Edition

Brown and Hyer, Managing Projects: A Team-Based Approach, First Edition

Burt, Petcavage, and Pinkerton, Supply Management, Eighth Edition

Cachon and Terwiesch, Operations Management First Edition

Cachon and Terwiesch, Matching Supply with Demand: An Introduction to Operations Management, Third Edition

Cooper and Schindler, Business Research Methods, Twelfth Edition

Finch, Interactive Models for Operations and Supply Chain Management, First Edition

Fitzsimmons, Fitzsimmons, and Bordoloi, Service Management: Operations, Strategy, Information Technology, Eighth Edition

Gehrlein, Operations Management Cases, First Edition

Harrison and Samson, Technology Management, First Edition

Hayen, SAP R/3 Enterprise Software: An Introduction, First Edition

Hill, Manufacturing Strategy: Text & Cases, Third Edition

Hopp, Supply Chain Science, First Edition

Hopp and Spearman, Factory Physics, Third Edition

Jacobs, Berry, Whybark, and Vollmann, Manufacturing Planning & Control for Supply Chain Management, Sixth Edition

Jacobs and Chase, Operations and Supply Management: The Core, Fourth Edition

Jacobs and Chase, Operations and Supply Management, Fifteenth Edition

Jacobs and Whybark, Why ERP? First Edition

Larson and Gray, Project Management: The Managerial Process, Seventh Edition

Leenders, Johnson, and Flynn, Purchasing and Supply Management, Fourteenth Edition

Nahmias, Production and Operations Analysis, Sixth Edition

Olson, Introduction to Information Systems Project Management, Second Edition

Schroeder, Goldstein, Rungtusanatham, Operations Management: Contemporary Concepts and Cases, Seventh Edition

Seppanen, Kumar, and Chandra, Process Analysis and Improvement, First Edition

Simchi-Levi, Kaminsky, and Simchi-Levi, Designing and Managing the Supply Chain: Concepts, Strategies, Case Studies, Third Edition

Sterman, Business Dynamics: Systems Thinking and Modeling for Complex World, First Edition

Stevenson, Operations Management, Thirteenth Edition

Swink, Melnyk, Cooper, and Hartley, Managing Operations Across the Supply Chain, Third Edition

Thomke, Managing Product and Service Development: Text and Cases, First Edition

Ulrich and Eppinger, Product Design and Development, Fourth Edition

Zipkin, Foundations of Inventory Management, First Edition

QUANTITATIVE METHODS AND MANAGEMENT SCIENCE Hillier and Hillier, Introduction to Management Science: A Modeling and Case Studies Approach with Spreadsheets, Fifth Edition

Stevenson and Ozgur, Introduction to Management Science with Spreadsheets, First Edition

Project Management:

The Managerial Process Seventh Edition

Erik W. Larson

Clifford F. Gray Oregon State University

PROJECT MANAGEMENT: THE MANAGERIAL PROCESS, SEVENTH EDITION

Published by McGraw-Hill Education, 2 Penn Plaza, New York, NY 10121. Copyright © 2018 by McGraw-Hill Education. All rights reserved. Printed in the United States of America. Previous editions © 2014 and 2011. No part of this publication may be reproduced or distributed in any form or by any means, or stored in a database or retrieval system, without the prior written consent of McGraw-Hill Education, including, but not limited to, in any network or other electronic storage or transmission, or broadcast for distance learning.

Some ancillaries, including electronic and print components, may not be available to customers outside the United States.

This book is printed on acid-free paper.

1 2 3 4 5 6 7 8 9 LWI 21 20 19 18 17 

ISBN 978-1-259-66609-4 MHID 1-259-66609-3

Chief Product Officer, SVP Products & Markets: G. Scott Virkler Vice President, General Manager, Products & Markets: Marty Lange Managing Director: James Heine Brand Manager: Dolly Womack Product Developer: Christina Holt Marketing Manager: Britney Hermsen Director, Content Design & Delivery: Linda Avenarius Program Manager: Mark Christianson Content Project Managers: Melissa M. Leick, Bruce Gin, Karen Jozefowicz Buyer: Jennifer Pickel Design: Egzon Shaqiri Content Licensing Specialists: Melissa Homer, Beth Thole Cover Design: Jessica Cuevas Cover Image: © Getty Images/Georgijevic Compositor: Aptara®, Inc. Printer: LSC Communications

All credits appearing on page or at the end of the book are considered to be an extension of the copyright page.

Library of Congress Cataloging-in-Publication Data

Names: Gray, Clifford F., author. | Larson, Erik W., 1952 author. Title: Project management : the managerial process / Erik W. Larson, Oregon State University, Clifford F. Gray, Oregon State University. Description: Seventh edition. | New York, NY : McGraw-Hill Education, [2018] | Clifford F. Gray is the first named author on the earlier editions. Identifiers: LCCN 2016040029 | ISBN 9781259666094 | ISBN 1259666093 (alk. paper) Subjects: LCSH: Project management. | Time management. | Risk management. Classification: LCC HD69.P75 G72 2018 | DDC 658.4/04—dc23 LC record available at https://lccn.loc.gov/

2016040029

The Internet addresses listed in the text were accurate at the time of publication. The inclusion of a website does not indicate an endorsement by the authors or McGraw-Hill Education, and McGraw-Hill Education does not guarantee the accuracy of the information presented at these sites.

mheducation.com/highered

Erik W. Larson ERIK W. LARSON is professor of project management at the College of Business, Oregon State University. He teaches executive, graduate, and undergraduate courses on project management and leadership. His research and consulting activities focus on project management. He has published numerous articles on matrix management, product development, and project partnering. He has been honored with teaching awards from both the Oregon State University MBA program and the University of Oregon Executive MBA program. He has been a member of the Portland, Oregon, chapter of the Project Management Institute since 1984. In 1995 he worked as a Ful- bright scholar with faculty at the Krakow Academy of Economics on modernizing Polish business education. He was a visiting professor at Chulalongkorn University in Bangkok, Thailand, and at Baden-Wuerttemberg Cooperative State University in Bad Mergentheim, Germany. He received a B.A. in psychology from Claremont McKenna College and a Ph.D. in management from State University of New York at Buffalo. He is a certified project management professional (PMP) and Scrum Master.

Clifford F. Gray CLIFFORD F. GRAY is professor emeritus of management at the College of Busi- ness, Oregon State University. He has personally taught more than 100 executive development seminars and workshops. Cliff has been a member of the Project Man- agement Institute since 1976 and was one of the founders of the Portland, Oregon, chapter. He was a visiting professor at Kasetsart University in Bangkok, Thailand, in 2005. He was the president of Project Management International, Inc. (a training and consulting firm specializing in project management) 1977–2005. He received his B.A. in economics and management from Millikin University, M.B.A. from Indiana Univer- sity, and doctorate in operations management from the College of Business, University of Oregon. He is certified Scrum Master.

About the Authors

vii

“Man’s mind, once stretched by a new idea, never regains its original dimensions.”

Oliver Wendell Holmes, Jr.

To my family, who have always encircled me with love and encouragement—my parents (Samuel and Charlotte), my wife (Mary), my sons and their wives (Kevin and Dawn, Robert and Sally) and their children (Ryan, Carly, Connor and Lauren).

C.F.G.

“We must not cease from exploration and the end of all exploring will be to arrive where we began and to know the place for the first time.”

T. S. Eliot

To Ann, whose love and support have brought out the best in me. To our girls Mary, Rachel, and Tor-Tor for the joy and pride they give me. And to our grandkids, Mr. B, Livvy, and Xmo, whose future depends upon effective project management. Finally, to my muse, Neil—Walk on!

E.W.L

viii

Our motivation in writing this text continues to be to provide a realistic, socio-technical view of project management. In the past, textbooks on project management focused almost exclusively on the tools and processes used to manage projects and not the human dimension. This baffled us since people not tools complete projects! While we firmly believe that mastering tools and processes is essential to successful project management, we also believe that the effectiveness of these tools and methods is shaped and determined by the prevailing culture of the organization and interpersonal dynamics of the people involved. Thus, we try to provide a holistic view that focuses on both of these dimensions and how they interact to determine the fate of projects. The role of projects in organizations is receiving increasing attention. Projects are the major tool for implementing and achieving the strategic goals of the organization. In the face of intense, worldwide competition, many organizations have reorganized around a philosophy of innovation, renewal, and organizational learning to survive. This philosophy suggests an organization that is flexible and project driven. Project management has developed to the point where it is a professional discipline having its own body of knowledge and skills. Today it is nearly impossible to imagine anyone at any level in the organization who would not benefit from some degree of expertise in the process of managing projects.

Audience

This text is written for a wide audience. It covers concepts and skills that are used by managers to propose, plan, secure resources, budget, and lead project teams to suc- cessful completions of their projects. The text should prove useful to students and prospective project managers in helping them understand why organizations have developed a formal project management process to gain a competitive advantage. Readers will find the concepts and techniques discussed in enough detail to be imme- diately useful in new-project situations. Practicing project managers will find the text to be a valuable guide and reference when dealing with typical problems that arise in the course of a project. Managers will also find the text useful in understanding the role of projects in the missions of their organizations. Analysts will find the text useful in helping to explain the data needed for project implementation as well as the opera- tions of inherited or purchased software. Members of the Project Management Insti- tute will find the text is well structured to meet the needs of those wishing to prepare for PMP (Project Management Professional) or CAPM (Certified Associate in Project Management) certification exams. The text has in-depth coverage of the most critical topics found in PMI’s Project Management Body of Knowledge (PMBOK). People at all levels in the organization assigned to work on projects will find the text useful not only in providing them with a rationale for the use of project management processes but also because of the insights they will gain on how to enhance their contributions to project success. Our emphasis is not only on how the management process works, but more impor- tantly, on why it works. The concepts, principles, and techniques are universally

Preface

ix

x Preface

applicable. That is, the text does not specialize by industry type or project scope. Instead, the text is written for the individual who will be required to manage a variety of projects in a variety of different organizational settings. In the case of some small projects, a few of the steps of the techniques can be omitted, but the conceptual frame- work applies to all organizations in which projects are important to survival. The approach can be used in pure project organizations such as construction, research orga- nizations, and engineering consultancy firms. At the same time, this approach will benefit organizations that carry out many small projects while the daily effort of deliv- ering products or services continues.

Content

In this and other editions we continue to try to resist the forces that engender scope creep and focus only on essential tools and concepts that are being used in the real world. We have been guided by feedback from practitioners, teachers, and students. Some changes are minor and incremental, designed to clarify and reduce confusion. Other changes are significant. They represent new developments in the field or better ways of teaching project management principles. Below are major changes to the seventh edition. ∙ Learning objectives have been established for each chapter and the corresponding

segment has been marked in the text. ∙ Chapter 16 Oversight has been eliminated and critical information on project matu-

rity models is now part of Chapter 14. ∙ Chapter 18 Project Management Career Paths has been eliminated and essential

information from this chapter is now in Chapter 1. ∙ A new set of network exercises have been developed for Chapter 6. ∙ A new set of crashing exercises have been developed for Chapter 9 which introduce

crashing concepts in a developmental way. ∙ The Chapter 2 Appendix on Request for Proposal is now part of Chapter 12. ∙ Terms and concepts have been updated to be consistent with the sixth edition of the

Project Management Body of Knowledge (2015). ∙ New student exercises and cases have been added to chapters. ∙ The Snapshot from Practice boxes feature a number of new examples of project

management in action as well as new Research Highlights that continue to promote practical application of project management.

∙ The Instructor’s Manual contains a listing of current YouTube videos that corre- spond to key concepts and Snapshots from Practice.

Overall the text addresses the major questions and challenges the authors have encountered over their 60 combined years of teaching project management and con- sulting with practicing project managers in domestic and foreign environments. These questions include:  What is the strategic role of projects in contemporary organiza- tions? How are projects prioritized? What organizational and managerial styles will improve chances of project success? How do project managers orchestrate the complex network of relationships involving vendors, subcontractors, project team members, senior management, functional managers, and customers that affect project success? What factors contribute to the development of a high-performance project team? What project management system can be set up to gain some measure of control? How do managers prepare for a new international project in a foreign culture? 

Preface xi

Project managers must deal with all these concerns to be effective. All of these issues and problems represent linkages to an integrative project management view. The chapter content of the text has been placed within an overall framework that inte- grates these topics in a holistic manner. Cases and snapshots are included from the experiences of practicing managers. The future for project managers appears to be promising. Careers will be determined by success in managing projects.

Student Learning Aids

Student resources include study outlines, online quizzes, PowerPoint slides, videos, Microsoft Project Video Tutorials and web links. These can be found in Connect.

Acknowledgments

We would like to thank Scott Bailey for building the end-of-chapter exercises for Connect and Tracie Lee for reviewing them; Pinyarat Sirisomboonsuk for revising the PowerPoint slides; Oliver F. Lehmann for providing access to PMBOK study questions; Ronny Richardson for updating the Instructor’s Manual; Angelo Serra for updating the Test Bank; and Pinyarat Sirisomboonsuk for providing new Snapshot from Practice questions. Next, it is important to note that the text includes contributions from numerous stu- dents, colleagues, friends, and managers gleaned from professional conversations. We want them to know we sincerely appreciate their counsel and suggestions. Almost every exercise, case, and example in the text is drawn from a real-world project. Special thanks to managers who graciously shared their current project as ideas for exercises, subjects for cases, and examples for the text. Shlomo Cohen, John A. Drexler, Jim Moran, John Sloan, Pat Taylor, and John Wold, whose work is printed, are gratefully acknowledged. Special gratitude is due Robert Breitbarth of Interact Management, who shared invaluable insights on prioritizing projects. University stu- dents and managers deserve special accolades for identifying problems with earlier drafts of the text and exercises. We are indebted to the reviewers of past editions who shared our commitment to elevating the instruction of project management. The reviewers include Paul S. Allen, Rice University; Denis F. Cioffi, George Washington University; Joseph D. DeVoss, DeVry University; Edward J. Glantz, Pennsylvania State University; Michael Godfrey, University of Wisconsin–Oshkosh; Robert Key, University of Phoenix; Dennis Krum- wiede, Idaho State University; Nicholas C. Petruzzi, University of Illinois–Urbana/ Champaign; William R. Sherrard, San Diego State University; S. Narayan Bodapati, Southern Illinois University at Edwardsville; Warren J. Boe, University of Iowa; Burton Dean, San Jose State University; Kwasi Amoako-Gyampah, University of North Carolina–Greensboro; Owen P. Hall, Pepperdine University; Bruce C. Hartman, University of Arizona; Richard Irving, York University; Robert T. Jones, DePaul University; Richard L. Luebbe, Miami University of Ohio; William Moylan, Lawrence Technological College of Business; Edward Pascal, University of Ottawa; James H. Patterson, Indiana University; Art Rogers, City University; Christy Strbiak, U.S. Air Force Academy; David A. Vaughan, City University; and Ronald W. Witzel, Keller Graduate School of Management. Nabil Bedewi, Georgetown University; Scott Bailey, Troy University; Michael Ensby, Clarkson University; Eldon Larsen, Marshall University; Steve Machon, DeVry University–Tinley Park; William Matthews, William Patterson

xii Preface

University; Erin Sims, DeVry University–Pomona; Kenneth Solheim, DeVry University–Federal Way; and Oya Tukel, Cleveland State University. Gregory Anderson, Weber State University; Dana Bachman, Colorado Christian University; Alan Cannon, University of Texas, Arlington; Susan Cholette, San Francisco State; Michael Ensby, Clarkson University; Charles Franz, University of Missouri, Columbia; Raouf Ghattas, DeVry University; Robert Groff, Westwood College; Raffael Guidone, New York City College of Technology; George Kenyon, Lamar University; Elias Konwufine, Keiser University; Rafael Landaeta, Old Dominion University; Muhammad Obeidat, Southern Polytechnic State University; Linda Rose, Westwood College; Oya Tukel, Cleveland State University; and Mahmoud Watad, William Paterson University. Victor Allen, Lawrence Technological University; Mark Angolia, East Carolina University; Alan Cannon, University of Texas at Arlington; Robert Cope, Southeastern Louisiana University; Kenneth DaRin, Clarkson University; Ron Darnell, Amberton University; Jay Goldberg, Marquette University; Mark Huber, University of Georgia; Marshall Issen, Clarkson University; Charles Lesko, East Carolina University; Lacey McNeely, Oregon State University; Donald Smith, Texas A&M University; Peter Sutanto, Prairie View A&M University; Jon Tomlinson, University of Northwestern Ohio. We thank you for your many thoughtful suggestions and for making our book better. Of course we accept responsibility for the final version of the text. In addition, we would like to thank our colleagues in the College of Business at Oregon State University for their support and help in completing this project. In par- ticular, we recognize Lacey McNeely, Prem Mathew, Keith Leavitt and Pauline Schlip- zand for their helpful advice and suggestions. We also wish to thank the many students who helped us at different stages of this project, most notably Neil Young, Saajan Patel, Katherine Knox, Dat Nguyen, and David Dempsey. Mary Gray deserves special credit for editing and working under tight deadlines on earlier editions. Special thanks go to Pinyarat (“Minkster”) Sirisomboonsuk for her help in preparing the last four editions. Finally, we want to extend our thanks to all the people at McGraw-Hill Education for their efforts and support. First, we would like to thank Dolly Womack, and Christina Holt, for providing editorial direction, guidance, and management of the book’s devel- opment for the seventh edition. And we would also like to thank Melissa Leick, Jennifer Pickel, Egzon Shaqiri, Bruce Gin, and Karen Jozefowicz for managing the final production, design, supplement, and media phases of the seventh edition.

Erik W. Larson

Clifford F. Gray

xiii

Guided Tour Established Learning Objectives Learning objectives have been added to this edition to help stu- dents target key areas of learning. Learning objectives are listed both at the beginning of each chapter and are called out as mar- ginal elements throughout the narrative in each chapter.

End-of-Chapter Content Both static and algorithmic end-of-chapter content, including Review Questions and Exercises, are now assignable in Connect.

SmartBook The SmartBook has been updated with new highlights and probes for optimal student learning.

Snapshots The Snapshot from Practice boxes have been updated to include a number of new exam- ples of project management in action. New questions based on the Snapshots are also now assignable in Connect.

New and Updated Cases Included at the end of each chapter are between one and five cases which demonstrate key ideas from the text and help students understand how Project Management comes into play in the real world. New cases have been added across several chapters in the 7th edition.

26

Organization Strategy and Project Selection2

LEARNING OBJECTIVES After reading this chapter you should be able to:

2-1 Explain why it is important for project managers to understand their organization’s strategy.

2-2 Identify the significant role projects contribute to the strategic direction of the organization.

2-3 Understand the need for a project priority system.

2-4 Apply financial and nonfinancial criteria to assess the value of projects.

2-5 Understand how multi-criteria models can be used to select projects.

2-6 Apply an objective priority system to project selection.

2-7 Understand the need to manage the project portfolio.

OUTLINE 2.1 The Strategic Management Process: An

Overview

2.2 The Need for a Project Priority System

2.3 A Portfolio Management System

2.4 Selection Criteria

2.5 Applying a Selection Model

2.6 Managing the Portfolio System

Summary

C H A P T E R T W O

Lar66093_ch02_026-065.indd 26 10/4/16 4:52 PM

28 Chapter 2 Organization Strategy and Project Selection

alignment even more essential for success. Ensuring a strong link between the strategic plan and projects is a difficult task that demands constant attention from top and mid- dle management. The larger and more diverse an organization, the more difficult it is to create and maintain this strong link. Companies today are under enormous pressure to manage a process that clearly aligns projects to organization strategy. Ample evidence still sug- gests that many organizations have not developed a process that clearly aligns project selection to the strategic plan. The result is poor utilization of the organization’s resources—people, money, equipment, and core competencies. Conversely, organiza- tions that have a coherent link of projects to strategy have more cooperation across the organization, perform better on projects, and have fewer projects. How can an organization ensure this link and alignment? The answer requires inte- gration of projects with the strategic plan. Integration assumes the existence of a stra- tegic plan and a process for prioritizing projects by their contribution to the plan. A crucial factor to ensure the success of integrating the plan with projects lies in the creation of a process that is open and transparent for all participants to review. This chapter presents an overview of the importance of strategic planning and the process for developing a strategic plan. Typical problems encountered when strategy and proj- ects are not linked are noted. A generic methodology that ensures integration by creat- ing very strong linkages of project selection and priority to the strategic plan is then discussed. The intended outcomes are clear organization focus, best use of scarce orga- nization resources (people, equipment, capital), and improved communication across projects and departments.

Why Project Managers Need to Understand Strategy Project management historically has been preoccupied solely with the planning and exe- cution of projects. Strategy was considered to be under the purview of senior manage- ment. This is old-school thinking. New-school thinking recognizes that project management is at the apex of strategy and operations. Aaron Shenhar speaks to this issue when he states, “. . . it is time to expand the traditional role of the project manager from an operational to a more strategic perspective. In the modern evolving organization, proj- ect managers will be focused on business aspects, and their role will expand from getting the job done to achieving the business results and winning in the marketplace.”1 There are two main reasons why project managers need to understand their organiza- tion’s mission and strategy. The first reason is so they can make appropriate decisions and adjustments. For example, how a project manager would respond to a suggestion to modify the design of a product to enhance performance will vary depending upon whether his company strives to be a product leader through innovation or to achieve operational excellence through low cost solutions. Similarly, how a project manager would respond to delays may vary depending upon strategic concerns. A project man- ager will authorize overtime if her firm places a premium on getting to the market first. Another project manager will accept the delay if speed is not essential. The second reason project managers need to understand their organization’s strat- egy is so they can be effective project advocates. Project managers have to be able to demonstrate to senior management how their project contributes to their firm’s mis- sion. Protection and continued support come from being aligned with corporate objec- tives. Project managers also need to be able to explain to team members and other

Explain why it is impor- tant for project managers to understand their orga- nization’s strategy.

2-1LO

1 Shenhar, A., and Dov Dvie, Reinventing Project Management (Harvard Business School, 2007), p. 5.

Lar66093_ch02_026-065.indd 28 10/4/16 4:52 PM

84 Chapter 3 Organization: Structure and Culture

In 2016 Google Inc. topped Fortune magazine’s list of best companies to work at for the seventh time in the past ten years. When one enters the 24-hour Googleplex located in

Mountain View, California, you feel that you are walking through a new-age college campus rather than the corporate office of a billion-dollar business. The collection of interconnected low-rise buildings with colorful, glass-encased offices feature upscale trappings—free gourmet meals three times a day, free use of an outdoor wave pool, indoor gym and large child care facility, private shuttle bus service to and from San Francisco and other residential areas— that are the envy of workers across the Bay area. These perks and others reflect Google’s culture of keeping people happy and thinking in unconven- tional ways. The importance of corporate culture is no more evi- dent than in the fact that the head of Human Resources, Stacy Savides Sullivan, also has the title of Chief Cul- ture Officer. Her task is to try to preserve the innovative culture of a start-up as Google quickly evolves into a mammoth international corporation. Sullivan character- izes Google culture as “team-oriented, very collabora- tive and encouraging people to think nontraditionally, different from where they ever worked before—work with integrity and for the good of the company and for the good of the world, which is tied to our overall mis- sion of making information accessible to the world.” Google goes to great lengths to screen new employees to not only make sure that they have outstanding tech- nical capabilities but also that they are going to fit Google’s culture. Sullivan goes on to define a Google-y employee as somebody who is “flexible, adaptable, and not focusing on titles and hierarchy, and just gets stuff done.” Google’s culture is rich with customs and traditions not found in corporate America. For example, project

S N A P S H O T F R O M P R A C T I C E 3 . 4 Google-y*

teams typically have daily “stand-up” meetings seven min- utes after the hour. Why seven minutes after the hour? Because Google cofounder Sergey Brin once estimated that it took seven minutes to walk across the Google cam- pus. Everybody stands to make sure no one gets too com- fortable and no time is wasted during the rapid-fire update. As one manager noted, “The whole concept of the stand-up is to talk through what everyone’s doing, so if someone is working on what you’re working on, you can discover and collaborate not duplicate.” Another custom is “dogfooding.” This is when a project team releases the functional prototype of a future product to Google employees for them to test drive. There is a strong norm within Google to test new products and provide feedback to the developers. The project team receives feedback from thousands of Google-ys. The internal focus group can log bugs or simply comment on design or functionality. Fellow Google-ys do not hold back on their feedback and are quick to point out things they don’t like. This often leads to significant product improvements.

© Caiaimage/Glow Images

simply rely on what people report about their culture. The physical environment in which people work, as well as how people act and respond to different events that occur, must be examined. Figure 3.6 contains a worksheet for diagnosing the culture of an organization. Although by no means exhaustive, the checklist often yields clues about the norms, customs, and values of an organization: 1. Study the physical characteristics of an organization. What does the external

architecture look like? What image does it convey? Is it unique? Are the buildings

* Walters, H., “How Google Got Its New Look,” BusinessWeek, May 10, 2010; Goo, S. K., “Building a ‘Googley’ Workforce,“ Washington Post, October 21, 2006; Mills, E., “Meet Google’s Culture Czar,” CNET News.com, April 27, 2007.

Lar66093_ch03_066-099.indd 84 10/4/16 5:10 PM

xiv

Note to Student You will find the content of this text highly practical, relevant, and current. The con- cepts discussed are relatively simple and intuitive. As you study each chapter we sug- gest you try to grasp not only how things work, but why things work. You are encouraged to use the text as a handbook as you move through the three levels of competency:

I know. I can do. I can adapt to new situations.

Project management is both people and technical oriented. Project management involves understanding the cause-effect relationships and interactions among the sociotechnical dimensions of projects. Improved competency in these dimensions will greatly enhance your competitive edge as a project manager. The field of project management is growing in importance and at an exponential rate. It is nearly impossible to imagine a future management career that does not include management of projects. Résumés of managers will soon be primarily a description of the individual’s participation in and contributions to projects. Good luck on your journey through the text and on your future projects.

Chapter-by-Chapter Revisions for the Seventh Edition Chapter 1: Modern Project Management

∙ New Snapshot: Project Management in Action 2016. ∙ Information updated. ∙ New Snapshot: Ron Parker replaced Research Highlight: Works well with others. ∙ New case: The Hokie Lunch Group.

Chapter 2: Organization Strategy and Project Selection

∙ New Snapshot: Project Code Names replaced HP’s Strategy Revision.

Chapter 3: Organization: Structure and Culture

∙ Learning objectives established. ∙ Snapshot: Google-y updated. ∙ Snapshot: Skunk Works at Lockheed Martin updated.

Chapter 4: Defining the Project

∙ Learning objectives established. ∙ New case: Home Improvement Project.

Note to Student xv

Chapter 5: Estimating Project Times and Costs

∙ Learning objectives established. ∙ New Snapshot: London 2012 Olympics: Avoiding White Elephant curse. ∙ Expanded discussion of Mega Projects including the emergence of white

elephants.

Chapter 6: Developing a Project Schedule

∙ Learning objectives established. ∙ New Exercises 2-15 and Lag Exercises 18-21. ∙ Shoreline Stadium case replaces Greendale Stadium case.

Chapter 7: Managing Risk

∙ Learning objectives established.

Chapter 8 Appendix 1: The Critical-Chain Approach

∙ Learning objectives established.

Chapter 9: Reducing Project Duration

∙ Learning objectives established. ∙ Snapshot: Smartphone Wars updated. ∙ New exercises 1-7.

Chapter 10: Leadership: Being an Effective Project Manager

∙ Learning objectives established. ∙ New Research Highlight: Give and Take. ∙ Ethics discussion expanded.

Chapter 11: Managing Project Teams

∙ Learning objectives established. ∙ Expanded discussion on project vision.

Chapter 12: Outsourcing: Managing Interorganizational Relations

∙ Learning objectives established. ∙ Discussion of RFP process. ∙ New Snapshot: U.S. Department of Defense’s Value Engineering Awards 2015.

Chapter 13 Progress and Performance Measurement and Evaluation

∙ Learning Objectives established. ∙ Discussion of milestone schedules. ∙ New Snapshot: Guidelines for Setting Milestones. ∙ Discussion of Management Reserve Index. ∙ New case: Shoreline Stadium Status Report.

xvi Note to Student

Chapter 14: Project Closure

∙ Major Revision of chapter with more attention to project audit and closing activities.

∙ New Snapshot: The Wake. ∙ New Snapshot: 2015 PMO of the Year. ∙ New Snapshot: Operation Eagle Claw. ∙ Project Management Maturity model introduced.

Chapter 15: International Projects

∙ Learning Objectives established.

Chapter 16: An Introduction to Agile Project Management

∙ Learning Objectives established. ∙ New Snapshot: Kanban.

xvii

Preface ix

1. Modern Project Management 2

2. Organization Strategy and Project Selection 26

3. Organization: Structure and Culture 66

4. Defining the Project 100

5. Estimating Project Times and Costs 128

6. Developing a Project Plan 162

7. Managing Risk 206

8. Scheduling Resources and Costs 250

9. Reducing Project Duration 304

10. Being an Effective Project Manager 338

11. Managing Project Teams 374

12. Outsourcing: Managing Interorganizational Relations 418

Brief Contents 13. Progress and Performance Measurement

and Evaluation 458

14. Project Closure 514

15. International Projects 544

16. An Introduction to Agile Project Management 578

APPENDIX One Solutions to Selected Exercises 603 Two Computer Project Exercises 616

GLOSSARY 633 ACRONYMS 640 PROJECT MANAGEMENT EQUATIONS 641 CROSS REFERENCE OF PROJECT MANAGEMENT 642 SOCIO-TECHNICAL APPROACH TO PROJECT MANAGEMENT 643 INDEX 644

xviii

Contents Preface ix

Chapter 1 Modern Project Management 2 1.1 What Is a Project? 6

What a Project Is Not 7 Program versus Project 7 The Project Life Cycle 8 The Project Manager 9 Being Part of a Project Team 11

1.2 Current Drivers of Project Management 12 Compression of the Product Life Cycle 12 Knowledge Explosion 12 Triple Bottom Line (Planet, People, Profit) 12 Increased Customer Focus 12 Small Projects Represent Big Problems 15

1.3 Project Governance 15 Alignment of Projects with Organizational Strategy 16

1.4 Project Management Today: A Socio-Technical Approach 17

Summary 18

Chapter 2 Organization Strategy and Project Selection 26 2.1 The Strategic Management Process:

An Overview 29 Four Activities of the Strategic Management Process 29

2.2 The Need for a Project Priority System 34 Problem 1: The Implementation Gap 34 Problem 2: Organization Politics 35 Problem 3: Resource Conflicts and Multitasking 36

2.3 A Portfolio Management System 37 Classification of the Project 37

2.4 Selection Criteria 38 Financial Criteria 38 Nonfinancial Criteria 40

2.5 Applying a Selection Model 43 Project Classification 43 Sources and Solicitation of Project Proposals 44 Ranking Proposals and Selection of Projects 46

2.6 Managing the Portfolio System 48 Senior Management Input 48 The Governance Team Responsibilities 49 Balancing the Portfolio for Risks and Types of Projects 50

Summary 51

Chapter 3 Organization: Structure and Culture 66 3.1 Project Management Structures 68

Organizing Projects within the Functional Organization 68 Organizing Projects as Dedicated Teams 71 Organizing Projects within a Matrix Arrangement 75 Different Matrix Forms 76

3.2 What Is the Right Project Management Structure? 79 Organization Considerations 79 Project Considerations 79

3.3 Organizational Culture 81 What Is Organizational Culture? 81 Identifying Cultural Characteristics 83

3.4 Implications of Organizational Culture for Organizing Projects 86

Summary 89

Chapter 4 Defining the Project 100 4.1 Step 1: Defining the Project Scope 102

Employing a Project Scope Checklist 103 4.2 Step 2: Establishing Project Priorities 106 4.3 Step 3: Creating the Work Breakdown

Structure 108 Major Groupings Found in a WBS 108 How WBS Helps the Project Manager 108 A Simple WBS Development 109

4.4 Step 4: Integrating the WBS with the Organization 113

4.5 Step 5: Coding the WBS for the Information System 113

4.6 Process Breakdown Structure 116

Contents xix

4.7 Responsibility Matrices 117 4.8 Project Communication Plan 119 Summary 121

Chapter 5 Estimating Project Times and Costs 128 5.1 Factors Influencing the Quality of

Estimates 130 Planning Horizon 130 Project Complexity 130 People 131 Project Structure and Organization 131 Padding Estimates 131 Organization Culture 131 Other Factors 131

5.2 Estimating Guidelines for Times, Costs, and Resources 132

5.3 Top-Down versus Bottom-Up Estimating 134

5.4 Methods for Estimating Project Times and Costs 136 Top-Down Approaches for Estimating Project Times and Costs 136 Bottom-Up Approaches for Estimating Project Times and Costs 140 A Hybrid: Phase Estimating 141

5.5 Level of Detail 143 5.6 Types of Costs 144

Direct Costs 145 Direct Project Overhead Costs 145 General and Administrative (G&A) Overhead Costs 145

5.7 Refining Estimates 146 5.8 Creating a Database for Estimating 148 5.9 Mega Projects: A Special Case 149 Summary 151 Appendix 5.1: Learning Curves for Estimating 157

Chapter 6 Developing a Project Plan 162 6.1 Developing the Project Network 163 6.2 From Work Package to Network 164 6.3 Constructing a Project Network 166

Terminology 166 Basic Rules to Follow in Developing Project Networks 166

6.4 Activity-on-Node (AON) Fundamentals 167 6.5 Network Computation Process 171

Forward Pass—Earliest Times 171 Backward Pass—Latest Times 173 Determining Slack (or Float) 175

6.6 Using the Forward and Backward Pass Information 177

6.7 Level of Detail for Activities 178 6.8 Practical Considerations 178

Network Logic Errors 178 Activity Numbering 179 Use of Computers to Develop Networks 179 Calendar Dates 182 Multiple Starts and Multiple Projects 182

6.9 Extended Network Techniques to Come Closer to Reality 182 Laddering 182 Use of Lags to Reduce Schedule Detail and Project Duration 183 An Example Using Lag Relationships—The Forward and Backward Pass 186 Hammock Activities 188

Summary 189

Chapter 7 Managing Risk 206 7.1 Risk Management Process 208 7.2 Step 1: Risk Identification 210 7.3 Step 2: Risk Assessment 212

Probability Analysis 215 7.4 Step 3: Risk Response Development 216

Mitigating Risk 216 Avoiding Risk 217 Transferring Risk 217 Accept Risk 218

7.5 Contingency Planning 219 Technical Risks 220 Schedule Risks 222 Cost Risks 222 Funding Risks 222

7.6 Opportunity Management 223 7.7 Contingency Funding and Time Buffers 223

Budget Reserves 224 Management Reserves 224 Time Buffers 225

7.8 Step 4: Risk Response Control 225 7.9 Change Control Management 226 Summary 230 Appendix 7.1: PERT and PERT Simulation 240

xx Contents

Chapter 8 Scheduling Resources and Costs 250 8.1 Overview of the Resource Scheduling

Problem 252 8.2 Types of Resource Constraints 254 8.3 Classification of a Scheduling

Problem 255 8.4 Resource Allocation Methods 255

Assumptions 255 Time-Constrained Project: Smoothing Resource Demand 256 Resource-Constrained Projects 257

8.5 Computer Demonstration of Resource- Constrained Scheduling 262 The Impacts of Resource-Constrained Scheduling 266

8.6 Splitting Activities 269 8.7 Benefits of Scheduling Resources 270 8.8 Assigning Project Work 271 8.9 Multiproject Resource Schedules 272 8.10 Using the Resource Schedule to Develop a

Project Cost Baseline 273 Why a Time-Phased Budget Baseline Is Needed 273 Creating a Time-Phased Budget 274

Summary 279 Appendix 8.1: The Critical-Chain Approach 294

Chapter 9 Reducing Project Duration 304 9.1 Rationale for Reducing Project

Duration 306 9.2 Options for Accelerating Project

Completion 307 Options When Resources Are Not Constrained 308 Options When Resources Are Constrained 310

9.3 Project Cost–Duration Graph 313 Explanation of Project Costs 313

9.4 Constructing a Project Cost–Duration Graph 314 Determining the Activities to Shorten 314 A Simplified Example 316

9.5 Practical Considerations 318 Using the Project Cost–Duration Graph 318 Crash Times 319 Linearity Assumption 319 Choice of Activities to Crash Revisited 319 Time Reduction Decisions and Sensitivity 320

9.6 What If Cost, Not Time, Is the Issue? 321 Reduce Project Scope 322 Have Owner Take on More Responsibility 322 Outsourcing Project Activities or Even the Entire Project 322 Brainstorming Cost Savings Options 322

Summary 323

Chapter 10 Being an Effective Project Manager 338 10.1 Managing versus Leading a Project 340 10.2 Managing Project Stakeholders 341 10.3 Influence as Exchange 345

Task-Related Currencies 345 Position-Related Currencies 346 Inspiration-Related Currencies 347 Relationship-Related Currencies 347 Personal-Related Currencies 348

10.4 Social Network Building 348 Mapping Stakeholder Dependencies 348 Management by Wandering Around (MBWA) 350 Managing Upward Relations 351 Leading by Example 353

10.5 Ethics and Project Management 356 10.6 Building Trust: The Key to Exercising

Influence 357 10.7 Qualities of an Effective Project Manager 359 Summary 362

Chapter 11 Managing Project Teams 374 11.1 The Five-Stage Team Development Model 377 11.2 Situational Factors Affecting Team

Development 379 11.3 Building High-Performance Project Teams 381

Recruiting Project Members 381 Conducting Project Meetings 383 Establishing Team Norms 385 Establishing a Team Identity 387 Creating a Shared Vision 388 Managing Project Reward Systems 391 Orchestrating the Decision-Making Process 392 Managing Conflict within the Project 394 Rejuvenating the Project Team 398

11.4 Managing Virtual Project Teams 399 11.5 Project Team Pitfalls 403

Groupthink 403 Bureaucratic Bypass Syndrome 404

Contents xxi

Team Spirit Becomes Team Infatuation 404 Going Native 404

Summary 405

Chapter 12 Outsourcing: Managing Interorganizational Relations 418 12.1 Outsourcing Project Work 420 12.2 Request for Proposal (RFP) 424

Selection of Contractor from Bid Proposals 425 12.3 Best Practices in Outsourcing Project Work 426

Well-Defined Requirements and Procedures 426 Extensive Training and Team-Building Activities 428 Well-Established Conflict Management Processes in Place 429 Frequent Review and Status Updates 431 Co-Location When Needed 432 Fair and Incentive-Laden Contracts 432 Long-Term Outsourcing Relationships 433

12.4 The Art of Negotiating 434 1. Separate the People from the Problem 435 2. Focus on Interests, Not Positions 436 3. Invent Options for Mutual Gain 437 4. When Possible, Use Objective Criteria 138 Dealing with Unreasonable People 438

12.5 A Note on Managing Customer Relations 439 Summary 442 Appendix 12.1: Contract Management 451

Chapter 13 Progress and Performance Measurement and Evaluation 458 13.1 Structure of a Project Monitoring Information

System 460 What Data Are Collected? 460 Collecting Data and Analysis 460 Reports and Reporting 460

13.2 The Project Control Process 461 Step 1: Setting a Baseline Plan 461 Step 2: Measuring Progress and Performance 461 Step 3: Comparing Plan against Actual 462 Step 4: Taking Action 462

13.3 Monitoring Time Performance 462 Tracking Gantt Chart 463 Control Chart 463 Milestone Schedules 464

13.4 Development of an Earned Value Cost/Schedule System 467

Percent Complete Rule 467 What Costs Are Included in Baselines? 467 Methods of Variance Analysis 468

13.5 Developing a Status Report: A Hypothetical Example 470 Assumptions 470 Baseline Development 470 Development of the Status Report 471

13.6 Indexes to Monitor Progress 475 Performance Indexes 477 Project Percent Complete Indexes 474 Software for Project Cost/Schedule Systems 477 Additional Earned Value Rules 478

13.7 Forecasting Final Project Cost 476 13.8 Other Control Issues 481

Technical Performance Measurement 481 Scope Creep 483 Baseline Changes 483 The Costs and Problems of Data Acquisition 485

Summary 486 Appendix 13.1: The Application of Additional Earned Value Rules 505 Appendix 13.2: Obtaining Project Performance Information from MS Project 2010 or 2015 511

Chapter 14 Project Closure 514 14.1 Types of Project Closure 516 14.2 Wrap-up Closure Activities 518 14.3 Project Audits 521

The Project Audit Process 522 Project Retrospectives 525 Project Audits: The Bigger Picture 529

14.4 Post-Implementation Evaluation 532 Team Evaluation 532 Individual, Team Member, and Project Manager Performance Reviews 534

Summary 537 Appendix 14.1: Project Closeout Checklist 539 Appendix 14.2: Euro Conversion—Project Closure Checklist 541

Chapter 15 International Projects 544 15.1 Environmental Factors 546

Legal/Political 546 Security 547 Geography 548

xxii Contents

Economic 549 Infrastructure 550 Culture 551

15.2 Project Site Selection 553 15.3 Cross-Cultural Considerations:

A Closer Look 554 Adjustments 555 Working in Mexico 556 Working in France 559 Working in Saudi Arabia 560 Working in China 562 Working in the United States 563 Summary Comments about Working in Different Cultures 565 Culture Shock 565 Coping with Culture Shock 567

15.4 Selection and Training for International Projects 568

Summary 571

Chapter 16 An Introduction to Agile Project Management 578 16.1 Traditional versus Agile Methods 580 16.2 Agile PM 582

16.3 Agile PM in Action: Scrum 585 Roles and Responsibilities 586 Scrum Meetings 587 Product and Sprint Backlogs 588 Sprint and Release Burndown Charts 589

16.4 Applying Agile PM to Large Projects 592 16.5 Limitations and Concerns 593 Summary 595

Appendix One: Solutions to Selected Exercise 603

Appendix Two: Computer Project Exercises 616

Glossary 633 Acronyms 640 Project Management Equations 641 Cross Reference of Project Management 642 Socio-Technical Approach to Project Management 643 Index 644

Project Management:

The Managerial Process

2

Modern Project Management1 LEARNING OBJECTIVES After reading this chapter you should be able to:

1-1 Understand why project management is crucial in today’s world.

1-2 Distinguish a project from routine operations.

1-3 Identify the different stages of project life cycle.

1-4 Understand the importance of projects in implementing organization strategy.

1-5 Understand that managing projects involves balancing the technical and sociocultural dimensions of the project.

OUTLINE 1.1 What Is a Project?

1.2 Current Drivers of Project Management

1.3 Project Governance

1.4 Project Management Today—A Socio-Technical Approach

Summary

Text Overview

C H A P T E R O N E

3

All of mankind’s greatest accomplishments—from building the great pyra- mids to discovering a cure for polio to putting a man on the moon—began as a project.

This is a good time to be reading a book about project management. Business leaders and experts have proclaimed that project management is critical to sustainable eco- nomic growth. New jobs and competitive advantage are achieved by constant innova- tion, developing new products and services, and improving both productivity and quality of work. This is the world of project management. Project management pro- vides people with a powerful set of tools that improves their ability to plan, implement, and manage activities to accomplish specific objectives. But project management is more than just a set of tools; it is a results-oriented management style that places a premium on building collaborative relationships among a diverse cast of characters. Exciting opportunities await people skilled in project management. The project approach has long been the style of doing business in the construction industry, U.S. Department of Defense contracts, and Hollywood, as well as big con- sulting firms. Now project management has spread to all avenues of work. Today,

Understand why project management is crucial in today’s world.

1-1LO

Project networks

6

Managing risk 7

Monitoring progress

13

Teams 11

Outsourcing 12

Project manager

10

Strategy 2

Introduction 1

Organization 3

Schedule resources & costs

8

Intern ation

al

proje cts

15

Agile PM 16

Project closure

14

Estimate 5

Reducing duration

9

Define project

4

4 Chapter 1 Modern Project Management

project teams carry out everything from port expansions to hospital restructuring to upgrading information systems. They are creating next-generation fuel-efficient vehi- cles, developing sustainable sources of energy, and exploring the farthest reaches of outer space. The impact of project management is most profound in the electronics industry, where the new folk heroes are young professionals whose Herculean efforts lead to the constant flow of new hardware and software products. Project management is not limited to the private sector. Project management is also a vehicle for doing good deeds and solving social problems. Endeavors such as provid- ing emergency aid to areas hit by natural disasters, devising a strategy for reducing crime and drug abuse within a city, or organizing a community effort to renovate a public playground would and do benefit from the application of modern project man- agement skills and techniques. Perhaps the best indicator of demand for project management can be seen in the rapid expansion of the Project Management Institute (PMI), a professional organiza- tion for project managers. PMI membership has grown from 93,000 in 2002 to more than 478,000 currently. See Snapshot from Practice 1.1 for information regarding pro- fessional certification in project management. It’s nearly impossible to pick up a newspaper or business periodical and not find something about projects. This is no surprise! Approximately $2.5 trillion (about 25 per- cent of the U.S. gross national product) is spent on projects each year in the United States alone. Other countries are increasingly spending more on projects. Millions of people around the world consider project management the major task in their profession. Most of the people who excel at managing projects never have the title of project manager. They include accountants, lawyers, administrators, scientists, contractors, pub- lic health officials, teachers, and community advocates whose success depends upon being able to lead and manage project work. For some, the very nature of their work is project driven. Projects may be cases for lawyers, audits for accountants, events for

The Project Management Institute (PMI) was founded in 1969 as an international society for project managers. Today PMI has members from more than 180 coun- tries and more than 478,500 members.

PMI professionals come from virtually every major indus- try, including aerospace, automotive, business manage- ment, construction, engineering, financial services, information technology, pharmaceuticals, health care, and telecommunications. PMI provides certification as a Project Management Professional (PMP)—someone who has documented sufficient project experience, agreed to follow the PMI code of professional conduct, and demonstrated mas- tery of the field of project management by passing a comprehensive examination. The number of people earning PMP status has grown dramatically in recent years. In 1996 there were fewer than 3,000 certified project management professionals. By 2016 there were more than 695,000 Professional credential holders.

S N A P S H O T F R O M P R A C T I C E 1 . 1 The Project Management Institute*

Just as the CPA exam is a standard for accountants, passing the PMP exam may become the standard for project managers. Some companies are requiring that all their project managers be PMP certified. Moreover, many job postings are restricted to PMPs. Job seekers, in general, are finding that being PMP certified is an advantage in the marketplace. PMI added a certification as a Certified Associate in Project Management (CAPM). CAPM is designed for project team members and entry-level project manag- ers, as well as qualified undergraduate and graduate students who want a credential to recognize their mas- tery of the project management body of knowledge. CAPM does not require the extensive project manage- ment experience associated with the PMP. For more details on PMP and CAPM, google PMI to find the cur- rent website for the Project Management Institute.

*PMI Today, March 2016, p. 4.

Chapter 1 Modern Project Management 5

artists, and renovations for contractors. For others, projects may be a small, but critical part of their work. For example, a high school teacher who teaches four classes a day is responsible for coaching a group of students to compete in a national debate competition. A store manager who oversees daily operations is charged with developing an employee retention program. A sales account executive is given the additional assignment of team lead to launch daily deals into a new city. A public health official who manages a clinic is also responsible for organizing a Homeless Youth Connect event. For these and others, project management is not a title, but a critical job requirement. It is hard to think of a profession or a career path that would not benefit from being good at managing projects. Not only is project management critical to most careers, the skill set is transferable across most businesses and professions. At its core, project management fundamentals are universal. The same project management methodology that is used to develop a new prod- uct can be adapted to create new services, organize events, refurbish aging operations, and so forth. In a world where it is estimated that each person is likely to experience three to four career changes, managing projects is a talent worthy of development. The significance of project management can also be seen in the classroom. Twenty years ago major universities offered one or two classes in project management, primarily for engineers. Today, most universities offer multiple sections of project man- agement classes, with the core group of engineers being supplemented by business stu- dents majoring in marketing, management information systems (MIS), and finance, as well as students from other disciplines such as oceanography, health sciences, computer sciences, and liberal arts. These students are finding that their exposure to project man- agement is providing them with distinct advantages when it comes time to look for jobs. More and more employers are looking for graduates with project management skills.

1. Business information: Join a proj- ect team charged with installing new data security system.

2. Physical education: Design and develop a new fitness program for

senior citizens that combines principles of yoga and aerobics.

3. Marketing: Execute a sales program for new home air purifier.

4. Industrial engineering: Manage a team to create a value chain report for every aspect of key product from design to customer delivery.

5. Chemistry: Develop a quality control program for organization’s drug production facilities.

6. Management: Implement a new store layout design.

7. Pre-med neurology student: Join project team link- ing mind mapping to an imbedded prosthetic that will allow blind people to function near normally.

8. Sports communication: Join Olympic project team that will promote women’s sports products for the 2016 Games in Rio de Janeiro, Brazil.

""9. Systems engineer: Become a project team member of a project to develop data mining of medical pa- pers and studies related to drug efficacy.

10. Accounting: Work on an audit of a major client.

11. Public health: Research and design a medical mari- juana educational program.

12. English: Create a web-based user manual for new electronics product.

S N A P S H O T F R O M P R A C T I C E 1 . 2 A Dozen Examples of Projects Given to Recent College Graduates

© John Fedele/Blend Images LLC, RF

6 Chapter 1 Modern Project Management

See the nearby Snapshot from Practice 1.2 for examples of projects given to recent col- lege graduates. The logical starting point for developing these skills is understanding the uniqueness of a project and of project managers.

1.1 What Is a Project? What do the following headlines have in common?

Millions watch Olympic Opening Ceremony Citywide WiFi System Set to Go Live Hospitals Respond to New Healthcare Reforms Apple’s New iPhone Hits the Market City Receives Stimulus Funds to Expand Light Rail System

All of these events represent projects.

© McGraw-Hill Education

The Project Management Institute provides the following definition of a project: A project is a temporary endeavor undertaken to create a unique product, service, or result.

Like most organizational efforts, the major goal of a project is to satisfy a customer’s need. Beyond this fundamental similarity, the characteristics of a project help

Distinguish a project from routine operations.

1-2LO

Chapter 1 Modern Project Management 7

differentiate it from other endeavors of the organization. The major characteristics of a project are as follows: 1. An established objective. 2. A defined life span with a beginning and an end. 3. Usually, the involvement of several departments and professionals. 4. Typically, doing something that has never been done before. 5. Specific time, cost, and performance requirements. First, projects have a defined objective—whether it is constructing a 12-story apart- ment complex by January 1 or releasing version 2.0 of a specific software package as quickly as possible. This singular purpose is often lacking in daily organizational life in which workers perform repetitive operations each day. Second, because there is a specified objective, projects have a defined endpoint, which is contrary to the ongoing duties and responsibilities of traditional jobs. In many cases, individuals move from one project to the next as opposed to staying in one job. After helping to install a security system, an IT engineer may be assigned to develop a database for a different client. Third, unlike much organizational work that is segmented according to functional specialty, projects typically require the combined efforts of a variety of specialists. Instead of working in separate offices under separate managers, project participants, whether they be engineers, financial analysts, marketing professionals, or quality con- trol specialists, work closely together under the guidance of a project manager to com- plete a project. The fourth characteristic of a project is that it is nonroutine and has some unique elements. This is not an either/or issue but a matter of degree. Obviously, accomplish- ing something that has never been done before, such as building an electric automobile or landing two mechanical rovers on Mars, requires solving previously unsolved prob- lems and using breakthrough technology. On the other hand, even basic construction projects that involve established sets of routines and procedures require some degree of customization that makes them unique. Finally, specific time, cost, and performance requirements bind projects. Projects are evaluated according to accomplishment, cost, and time spent. These triple con- straints impose a higher degree of accountability than you typically find in most jobs. These three also highlight one of the primary functions of project management, which is balancing the trade-offs among time, cost, and performance while ultimately satisfy- ing the customer.

What a Project Is Not Projects should not be confused with everyday work. A project is not routine, repeti- tive work! Ordinary daily work typically requires doing the same or similar work over and over, while a project is done only once; a new product or service exists when the project is completed. Examine the list in Table 1.1 that compares routine, repetitive work and projects. Recognizing the difference is important because too often resources can be used up on daily operations which may not contribute to longer range organiza- tion strategies that require innovative new products.

Program versus Project In practice the terms project and program cause confusion. They are often used syn- onymously. A program is a group of related projects designed to accomplish a

8 Chapter 1 Modern Project Management

common goal over an extended period of time. Each project within a program has a project manager. The major differences lie in scale and time span. Program management is the process of managing a group of ongoing, interdepen- dent, related projects in a coordinated way to achieve strategic objectives. For example, a pharmaceutical organization could have a program for curing cancer. The cancer pro- gram includes and coordinates all cancer projects that continue over an extended time horizon (Gray, 2011). Coordinating all cancer projects under the oversight of a cancer team provides benefits not available from managing them individually. This cancer team also oversees the selection and prioritizing of cancer projects that are included in their special “Cancer” portfolio. Although each project retains its own goals and scope, the project manager and team are also motivated by the higher program goal. Program goals are closely related to broad strategic organization goals.

The Project Life Cycle Another way of illustrating the unique nature of project work is in terms of the project life cycle. Some project managers find it useful to use the project life cycle as the cor- nerstone for managing projects. The life cycle recognizes that projects have a limited life span and that there are predictable changes in level of effort and focus over the life of the project. There are a number of different life-cycle models in project management literature. Many are unique to a specific industry or type of project. For example, a new software development project may consist of five phases: definition, design, code, inte- gration/test, and maintenance. A generic cycle is depicted in Figure 1.1. The project life cycle typically passes sequentially through four stages: defining, planning, executing, and delivering. The starting point begins the moment the project is given the go-ahead. Project effort starts slowly, builds to a peak, and then declines to delivery of the project to the customer. 1. Defining stage: Specifications of the project are defined; project objectives are

established; teams are formed; major responsibilities are assigned. 2. Planning stage: The level of effort increases, and plans are developed to determine

what the project will entail, when it will be scheduled, whom it will benefit, what quality level should be maintained, and what the budget will be.

3. Executing stage: A major portion of the project work takes place—both physical and mental. The physical product is produced (a bridge, a report, a software pro- gram). Time, cost, and specification measures are used for control. Is the project on schedule, on budget, and meeting specifications? What are the forecasts of each of these measures? What revisions/changes are necessary?

4. Closing stage: Closing includes three activities: delivering the project product to the customer, redeploying project resources, and post-project review. Delivery of

Identify the different stages of project life cycle.

1-3LO

TABLE 1.1 Comparison of Routine Work with Projects

Routine, Repetitive Work Projects Taking class notes Writing a term paper Daily entering sales receipts into the Setting up a sales kiosk for a professional accounting accounting ledger meeting Responding to a supply-chain request Developing a supply-chain information system Practicing scales on the piano Writing a new piano piece Routine manufacture of an Apple iPod Designing an iPod that is approximately 2 × 4 inches,

interfaces with PC, and stores 10,000 songs Attaching tags on a manufactured product Wire-tag projects for GE and Walmart

Chapter 1 Modern Project Management 9

the project might include customer training and transferring documents. Redeploy- ment usually involves releasing project equipment/materials to other projects and finding new assignments for team members. Post-project reviews include not only assessing performance but also capturing lessons learned.

In practice, the project life cycle is used by some project groups to depict the timing of major tasks over the life of the project. For example, the design team might plan a major commitment of resources in the defining stage, while the quality team would expect their major effort to increase in the latter stages of the project life cycle. Because most organizations have a portfolio of projects going on concurrently, each at a differ- ent stage of each project’s life cycle, careful planning and management at the organiza- tion and project levels are imperative.

The Project Manager At first glance project managers perform the same functions as other managers. That is, they plan, schedule, motivate, and control. However, what makes them unique is that they manage temporary, nonrepetitive activities, to complete a fixed life project. Unlike functional managers, who take over existing operations, project managers cre- ate a project team and organization where none existed before. They must decide what and how things should be done instead of simply managing set processes. They must meet the challenges of each phase of the project life cycle, and even oversee the dis- solution of their operation when the project is completed. Project managers must work with a diverse troupe of characters to complete proj- ects. They are typically the direct link to the customer and must manage the tension between customer expectations and what is feasible and reasonable. Project managers provide direction, coordination, and integration to the project team, which is often made up of part-time participants loyal to their functional departments. They often must work with a cadre of outsiders—vendors, suppliers, subcontractors—who do not necessarily share their project allegience.

Le ve

l o f e

ff or

t

1. Goals 2. Specifications 3. Tasks 4. Responsibilities

1. Schedules 2. Budgets 3. Resources 4. Risks 5. Staffing

1. Status reports 2. Changes 3. Quality 4. Forecasts

1. Train customer 2. Transfer documents 3. Release resources 4. Evaluation 5. Lessons learned

Defining

Defining

Start Time End

Planning

Planning

Executing

Executing

Closing

Closing

FIGURE 1.1 Project Life Cycle

10 Chapter 1 Modern Project Management

Project managers are ultimately responsible for performance (frequently with too little authority). They must ensure that appropriate trade-offs are made among the time, cost, and performance requirements of the project. At the same time, unlike their functional counterparts, project managers generally possess only rudimentary techni- cal knowledge to make such decisions. Instead, they must orchestrate the completion of the project by inducing the right people, at the right time, to address the right issues and make the right decisions. While project management is not for the timid, working on projects can be an extremely rewarding experience. Life on projects is rarely boring; each day is different from the last. Since most projects are directed at solving some tangible problem or pursuing some useful opportunity, project managers find their work personally mean- ingful and satisfying. They enjoy the act of creating something new and innovative. Project managers and team members can feel immense pride in their accomplishment, whether it is a new bridge, a new product, or needed service. Project managers are often stars in their organization and well compensated. Good project managers are always in demand. Every industry is looking for effective people who can get the right things done on time. See Snapshot from Practice 1.3: Ron Parker for an example of a former student who leveraged his ability to manage

1986 B.S. Business Administration–Oregon State University

1986–1990 Food Products Manufacturing

1990–1994 Wood Products Manufacturing 1994–Current Glass Products Manufacturing

Upon completion of my business degree at OSU, I was recruited by a Fortune 100 food products company for a first line production supervisor position. In that role, an opportunity came up for me to manage a project that involved rolling out a new statistical package-weight- control program throughout the factory. Successfully completing that project was instrumental in accelerating my career within the company, advancing from supervi- sor to product manager in less than three years. After four years in food products I accepted an offer to join a wood products manufacturing company. Initially my role in this company was Human Resources Manager. My HR responsibilities included managing several projects to improve safety and employee retention. Successful com- pletion of these projects led to a promotion to Plant Man- ager. In the Plant Manager role, I was tasked with building and managing a new wood door manufacturing factory. After successfully taking that factory to full production, I was promoted again to Corporate Manager of Continuous Improvement. This “culture change” project involved

S N A P S H O T F R O M P R A C T I C E 1 . 3 Ron Parker

implementing Total Quality Management throughout 13 different manufacturing factories as well as all the indirect and support functions within the corporation. Shortly after we successfully ingrained this new culture in the company, the owner passed away, leading me to look for other employment. I was able to leverage my previous experience and success to convince the owner of a struggling glass fab- rication company to hire me. In this new role as General Manager, I was tasked with turning the company around. This was my largest project yet. Turning a com- pany around involves a myriad of smaller improvement projects spanning from facilities and equipment improvements to product line additions and deletions to sales and marketing strategy and everything in between. In four years, we successfully turned the com- pany around to the extent that the owner was able to sell the company and comfortably retire. Successfully turning that glass company around got the attention of a much larger competitor of ours, resulting in an offer of employment. This new offer involved the start-up of a $30M high-tech glass manufacturing facility in another state. We were able to take that facility from a dirt field to the highest volume manufacturing facility of its kind in the world in just three years. After building and operating this factory at a world-class benchmark level for eight years, I came across a new and exciting opportunity to help expand a strong glass fabrication company in

Chapter 1 Modern Project Management 11

Canada. I spent four years successfully transitioning this Canadian company from a medium-size glass fabrication facility to one of the largest and most successful of its kind in North America. After tiring of the “Great White North,” I found an opportunity to tackle the largest and most impactful project of my career. I’m currently VP of Operations in a venture-funded high-tech start-up company. In this role, I’m overseeing the construction and start-up of the first full-scale, high-volume electrochromic glass fabrication factory in the world. This new project

involves building a company from the ground up and taking an exciting new technology from the lab to full- scale commercialization. Success in this role, although still far from being certain, will eventually revolutionize the glass industry through the introduction of a product that dramatically improves the energy efficiency and occupant comfort of buildings around the world. Looking back on my career, it is apparent that my degree of success has largely been the result of taking on and successfully completing successively larger and increasingly impactful projects. There’s a saying that’s always resonated with me: “If your only tool is a hammer, all your problems look like nails.” Good tools are hard to come by and heavy to carry around. I like my tool bag filled with generalist tools; things like communication skills, leadership, common sense, judgment, reasoning, logic and a strong sense of urgency. I often wonder how much more I could have accomplished had I actually studied project management and had more of that toolset in my bag. With a bag full of strong generalist tools, you can tackle any problem in any business. Project man- agement is clearly one of those skills where the better you are at it, the higher your chances of success in any business environment. Having the tools is only part of the equation though. To be successful, you must also be willing to run at problems/opportunities when every- one else is running away from them.

projects to build a successful career in the glass products industry. Clearly, project man- agement is a challenging and exciting profession. This text is intended to provide the necessary knowledge, perspective, and tools to enable students to accept the challenge.

Being Part of a Project Team Most people’s first exposure to project management occurs while working as part of a team assigned to complete a specific project. Sometimes this work is full-time, but in most cases, people work part-time on one or more projects. They must learn how to juggle their day-to- day commitments with additional project responsibilities. They may join a team with a long history of working together, in which case roles and norms are firmly established. Alternatively, their team may consist of strangers from different departments and organiza- tions. As such, they endure the growing pains of a group evolving into a team. They need to be a positive force in helping the team coalesce into an effective project team. Not only are there people issues, but project members are also expected to use proj- ect management tools and concepts. They develop or are given a project charter or scope statement that defines the objectives and parameters of the project. They work with others to create a project schedule and budget that will guide project execution. They need to understand project priorities so they can make independent decisions.

Courtesy of Ron Parker

12 Chapter 1 Modern Project Management

They must know how to monitor and report project progress. Although much of this book is written from the perspective of a project manager, the tools, concepts, and methods are critical to everyone working on a project. Project members need to know how to avoid the dangers of scope creep, manage the critical path, engage in timely risk management, negotiate, and utilize virtual tools to communicate.

1.2 Current Drivers of Project Management Project management is no longer a special-need management. It is rapidly becoming a standard way of doing business. See Snapshot from Practice 1.4: Project Management in Action: 2016. An increasing percentage of the typical firm’s effort is being devoted to projects. The future promises an increase in the importance and the role of projects in contributing to the strategic direction of organizations. Several reasons why this is the case are briefly discussed below.

Compression of the Product Life Cycle One of the most significant driving forces behind the demand for project management is the shortening of the product life cycle. For example, today in high-tech industries the product life cycle is averaging six months to three years. Only 30 years ago, life cycles of 10 to 15 years were not uncommon. Time to market for new products with short life cycles has become increasingly important. A common rule of thumb in the world of high-tech product development is that a six-month project delay can result in a 33 percent loss in product revenue share. Speed, therefore, becomes a competitive advantage; more and more organizations are relying on cross-functional project teams to get new products and services to the market as quickly as possible.

Knowledge Explosion The growth in new knowledge has increased the complexity of projects because proj- ects encompass the latest advances. For example, building a road 30 years ago was a somewhat simple process. Today, each area has increased in complexity, including materials, specifications, codes, aesthetics, equipment, and required specialists. Simi- larly, in today’s digital, electronic age it is becoming hard to find a new product that does not contain at least one microchip. Product complexity has increased the need to integrate divergent technologies. Project management has emerged as an important discipline for achieving this task.

Triple Bottom Line (Planet, People, Profit) The threat of global warming has brought sustainable business practices to the fore- front. Businesses can no longer simply focus on maximizing profit to the detriment of the environment and society. Efforts to reduce carbon imprint and utilize renewable resources are realized through effective project management. The impact of this move- ment toward sustainability can be seen in changes in the objectives and techniques used to complete projects. See Snapshot from Practice 1.5: Dell Children’s Becomes World’s First “Green” Hospital.

Increased Customer Focus Increased competition has placed a premium on customer satisfaction. Customers no longer simply settle for generic products and services. They want customized products

Understand the impor- tance of projects in im- plementing organization strategy.

1-4LO

Chapter 1 Modern Project Management 13

Businesses thrive and survive based on their ability to manage projects that produce pro-

ducts and services that meet mar- ket needs. Below is a small sample of projects that are important to their company’s future.

Panama: The Third Set of Locks Project The expansion of the Panama Canal is scheduled to be operational in 2016. The project doubles the capac- ity of the Panama Canal by creating a new lane of traffic and allowing more and larger ships, the new Panamax size, which are about one and a half times bigger than the current size and can carry over twice as much cargo. With the third sets of locks, the canal will be able to manage traffic demand beyond 2025 with a predicted inflationary adjusted revenue of over $6.2 billion per year.

Molinski, D., “Panama Canal, Consortium Reach Deal to Complete Work,” The Wall Street Journal, February 28, 2014.

Google: Autonomous-Vehicle Project Google has contracted Roush Enterprises of Detroit, Michigan, to build 150 self-driving car prototypes. With more than 90 percent of U.S. road collisions caused by human error, self-driving cars could prevent over $190 billion in annual damages and health costs as well as greatly reduce fuel consumption.

Parsi, N., “No Driver Necessary,” PM Network, August 2015, pp. 7–9.

Studio Roosegaarde: Smog Free Tower The Smog Free tower, which stands 23 feet tall, sucks and cleans 1 million cubic feet of polluted air an hour. Innovator Daan Roosegaarde began working on out- door air purification after a particularly smoggy 2013 trip to China.

Karif, O., “Innovation: Smog Eater,” Bloomberg Business- Week, October 15, 2015, p. 22.

Facebook: Oculus Rift Virtual Reality Project Facebook paid over $2 billion for virtual-reality start-up Oculus, which will release its Rift virtual reality headset

in 2016. Video games will spur early sales of Rift, but mass adoption is likely to depend upon Hollywood. Lions Gate Entertainment and 21st Century Fox have agreed to sell movies via Oculus’s online store and Netflix will make its streaming service available on VR headsets.

Shaw, L., “Virtual Reality Goes to the Movies,” Bloom- berg BusinessWeek, Special Issue: Year Ahead 2016, p. 74.

CogniToys: Dino Project Rather than repeating catchphrases, as “talking” toys have done in the past, this dinosaur taps IBM’s Watson technology to engage kids ages 5 to 9 in a more mean- ingful way. The wi-fi-enabled figurine talks back and learns from kids’ responses, helping them hone their math skills by asking harder questions. The trick, according to CogniToys CEO Donald Coolidge, is to make education seem like a “cool, fun experience.”

“The Toy That Talks Back,” Time, November 30/Decem- ber 7, 2015, p. 81.

Coca-Cola Co.: Replenish Africa Initiative (RAIN) The global beverage company aims to provide at least 2 million people with safe water by the end of 2020. The firm is investing over $30 million in community- based water projects across Africa. Greg Koch, senior director of global water stewardship says, “We know that to do business we need water. And when commu- nities have access to safe water, you have the founda- tion of a thriving community, which is a better place for everyone to do business.”

“Water Works,” PMNetwork, September, 2015, p. 53.

S N A P S H O T F R O M P R A C T I C E 1 . 4 Project Management in Action: 2016

© Asif Islam/Shutterstock

14 Chapter 1 Modern Project Management

Dateline 1/7/2009, Austin Texas: Dell Children’s Medical Center becomes the first hospital in the world to receive platinum LEED (Leadership in Energy & Environmental Design) certi-

fication. Platinum certification is the highest award granted by the U.S. Green Building Council. Dell Children’s occupies nearly one-half-million square feet on 32 acres that were once part of Austin’s old Mueller Airport. Its environmentally sensitive design not only conserves water and electricity, but positively impacts the hospital’s clinical environment by improv- ing air quality, making natural sunlight readily avail- able, and reducing a wide range of pollutants. In order to receive LEED certification, buildings are rated in five key areas: sustainable site development, water savings, energy efficiency, materials selection, and environmental quality. Listed below are some of the accomplishments in each LEED category:

Sustainable Site

47,000 tons of Mueller Airport runway material was reused on site.

About 40 percent fly ash instead of Portland cement in concrete yields a drop in carbon dioxide emissions equivalent to taking 450 cars off the road.

925 tons of construction waste was recycled on site.

Water Efficiency and Water Conservation

Reclaimed water is used for irrigation; xeriscaped landscaping uses native plants, which require less water.

Low-flow plumbing fixtures.

S N A P S H O T F R O M P R A C T I C E 1 . 5 Dell Children’s Becomes World’s First “Green” Hospital*

Energy Efficiency and Energy Conservation

An on-site natural gas turbine supplies all electric- ity, which is 75 percent more efficient than coal- fired plants.

Converted steam energy from a heating/cooling plant supplies all chilled water needs.

Indoor Environment Quality and Lighting

Most interior spaces are within 32 feet of a window.

Motion and natural light sensors shut off unneeded lights.

Conservation of Materials and Resources

Use of local and regional materials saves fuel for shipping.

Special paints and flooring emit low levels of vola- tile organic compounds (VOCs).

“Even before the first plans were drawn up, we set our sight on creating a world-class children’s hospital, and becoming the first LEED Platinum hospital in the world was definitely part of that,” said Robert Bonar, presi- dent and CEO, Dell Children’s Medical Center of Central Texas. “Our motivation to pursue LEED Platinum was not just environmental. Being a ‘green’ hospital has a profound, measurable effect on healing. What’s good for the environment and good for our neighbors is also good for our patients.”

and services that cater to their specific needs. This mandate requires a much closer working relationship between the provider and the receiver. Account executives and sales representatives are assuming more of a project manager’s role as they work with their organization to satisfy the unique needs and requests of clients. Increased customer attention has also prompted the development of customized products and services. For example, 15 years ago buying a set of golf clubs was a rela- tively simple process: You picked out a set based on price and feel. Today, there are golf clubs for tall players and short players, clubs for players who tend to slice the ball and clubs for those who hook the ball, high-tech clubs with the latest metallurgic dis- covery guaranteed to add distance, and so forth. Project management is critical both to development of customized products and services and to sustaining lucrative relation- ships with customers.

*Austin Business Journal, January 11, 2009, www.dellchildrens.net/about_us/news/2009/01/08.

Chapter 1 Modern Project Management 15

Small Projects Represent Big Problems The velocity of change required to remain competitive or simply keep up has created an organizational climate in which hundreds of projects are implemented concurrently. This climate has created a multiproject environment and a plethora of new problems. Sharing and prioritizing resources across a portfolio of projects is a major challenge for senior management. Many firms have no idea of the problems involved with inefficient man- agement of small projects. Small projects typically carry the same or more risk as do large projects. Small projects are perceived as having little impact on the bottom line because they do not demand large amounts of scarce resources and/or money. Because so many small projects are going on concurrently and because the perception of the inef- ficiency impact is small, measuring inefficiency is usually nonexistent. Unfortunately, many small projects soon add up to large sums of money. Many customers and millions of dollars are lost each year on small projects in product and service organizations. Small projects can represent hidden costs not measured in the accounting system. Organizations with many small projects going on concurrently face the most diffi- cult project management problems. A key question becomes one of how to create an organizational environment that supports multiproject management. A process is needed to prioritize and develop a portfolio of small projects that supports the mission of the organization. In summary, there are a variety of environmental forces interacting in today’s busi- ness world that contribute to the increased demand for good project management across all industries and sectors. Project management appears to be ideally suited for a business environment requiring accountability, flexibility, innovation, speed, and con- tinuous improvement. These environmental and other factors have created the neces- sity for major oversight of all organization projects.

1.3 Project Governance Competing in a global market influenced by rapid change, innovation, and time to market means organizations manage more and more projects. Some means for coordi- nating and managing projects in this changing environment is needed. Centralization of project management processes and practices has been the practical outcome. For example, Google, Apple, General Electric, and Sony all have over 1,000 projects being implemented concurrently every day of the year across borders and differing cultures. Questions: How do these organizations oversee the management of all these projects? How were these projects selected? How do they ensure performance measurement and accountability? How can project management continually improve? Centralization entails governance of all project processes and practices to improve project management. Governance is designed to improve project management in the whole organization over the long haul. The rationale for integration of project management was to provide senior management with: ∙ An overview of all project management activities; ∙ A big picture of how organizational resources are being used; ∙ An assessment of the risk their portfolio of projects represents; ∙ A rough metric for measuring the improvement of managing projects relative to

others in the industry; ∙ Linkages of senior management with actual project execution management.

16 Chapter 1 Modern Project Management

Full insight of all components of the organization is crucial for aligning internal busi- ness resources with the requirements of the changing environment. Governance enables management to have greater flexibility and better control of all project man- agement activities. Operationally, what does project management integration mean? It necessitates combining all of the major dimensions of project management under one umbrella. Each dimension is connected in one seamless, integrated domain. Governance means applying a set of knowledge, skills, tools, and techniques to a collection of projects in order to move the organization toward its strategic goals. This integrative movement represents a major thrust of project-driven organizations across all industries. See Fig- ure 1.2, Integrated Management of Projects.

Alignment of Projects with Organizational Strategy Today, projects are the modus operandi for implementing strategy. Yet in some organizations, selection and management of projects often fail to support the strate- gic plan of the organization. Strategic plans are written by one group of managers, projects selected by another group, and projects implemented by another. These independent decisions by different groups of managers create a set of conditions leading to conflict, confusion, and frequently an unsatisfied customer. Under these conditions, resources of the organization are wasted in non-value-added activities/ projects. Since projects are the modus operandi, strategic alignment of projects is of major importance to conserving and effective use of organization resources. Selection crite- ria need to ensure each project is prioritized and contributes to strategic goals. Any- thing less is a waste of scarce organizational resources—people, capital, and equipment. Ensuring alignment requires a selection process that is systematic, open, consistent, and balanced. All of the projects selected become part of a project portfolio that balances the total risk for the organization. Management of the project portfolio ensures that only the most valuable projects are approved and managed across the entire organization.

Organizational Culture Environment

Strategic Alignment

Portfolio Management

Project Management

FIGURE 1.2 Integrated Management of Projects

Chapter 1 Modern Project Management 17

1.4 Project Management Today: A Socio-Technical Approach Senior management is often involved in selecting projects but seldom involved in implementing them. Implementing the project is the challenge. Managing a project is a multidimensional process (see Figure 1.3, A Socio-Technical Approach to Project Management). The first dimension is the technical side of the management process, which consists of the formal, disciplined, purely logical parts of the process. This technical dimension includes planning, scheduling, and controlling projects. Clear project scope statements are written to link the project and customer and to facilitate planning and control. Creation of the deliverables and work break- down structures facilitates planning and monitoring the progress of the project. The work breakdown structure serves as a database that links all levels in the organization, major deliverables, and all work—right down to the tasks in a work package. Effects of project changes are documented and traceable. Thus, any change in one part of the project is traceable to the source by the integrated linkages of the system. This inte- grated information approach can provide all project managers and the customer with decision information appropriate to their level and needs. A successful project man- ager will be well trained in the technical side of managing projects. The second and opposing dimension is the sociocultural side of project manage- ment. In contrast to the orderly world of project planning, this dimension involves the much messier, often contradictory and paradoxical world of implementation. It centers on creating a temporary social system within a larger organizational environment that combines the talents of a divergent set of professionals working to complete the proj- ect. Project managers must shape a project culture that stimulates teamwork and high levels of personal motivation as well as a capacity to quickly identify and resolve prob- lems that threaten project work. Things rarely go as planned and project managers must be able to steer the project back on track or alter directions when necessary. The sociocultural dimension also involves managing the interface between the proj- ect and external environment. Project managers have to assuage and shape

Understand that manag- ing projects involves bal- ancing the technical and sociocultural dimensions of the project.

1-5LO

FIGURE 1.3 A Socio-Technical Approach to Project Management

Technical

Scope WBS Schedules Resource allocation Baseline budgets Status reports

Sociocultural

Leadership Problem solving Teamwork Negotiation Politics Customer expectations

18 Chapter 1 Modern Project Management

expectations of customers, sustain the political support of top management, negotiate with their functional counterparts, monitor subcontractors, and so on. Overall, the manager must build a cooperative social network among a divergent set of allies with different standards, commitments, and perspectives. Some suggest that the technical dimension represents the “science” of project manage- ment while the sociocultural dimension represents the “art” of managing a project. To be successful, a manager must be a master of both. Unfortunately, some project managers become preoccupied with the planning and technical dimension of project management. Often their first real exposure to project management is through project management soft- ware, and they become infatuated with network charts, Gantt diagrams, and performance variances; they attempt to manage a project from a distance. Conversely, there are other managers who manage projects by the “seat of their pants,” relying heavily on team dynam- ics and organizational politics to complete a project. Good project managers balance their attention to both the technical and sociocultural aspects of project management.

Summary Project management is a critical skill set in today’s world. A project is defined as a non- routine, one-time effort limited by time, resources, and performance specifications de- signed to meet customer needs. One of the distinguishing characteristics of project management is that it has both a beginning and an end and typically consists of four phases: defining, planning, executing, and closing. Effective project management begins with selecting and prioritizing projects that support the firm’s mission and strategy. Suc- cessful implementation requires both technical and social skills. Project managers have to plan and budget projects as well as orchestrate the contributions of others.

Text Overview This text is written to provide the reader with a comprehensive, integrative under- standing of the project management process. The text focuses both on the science of project management and the art of managing projects. Following this introductory chapter, Chapter 2 focuses on how organizations go about evaluating and selecting projects. Special attention is devoted to the importance of aligning project selection to the mission and strategy of the firm. The organizational environment in which projects are implemented is the focus of Chapter 3. The discussion of matrix management and other organizational forms is augmented by a discussion of the role the culture of an organization plays in the implementation of projects. The next six chapters focus on developing a plan for the project; after all, project success begins with a good plan. Chapter 4 deals with defining the scope of the project and developing a work breakdown structure (WBS). The challenge of formulating cost and time estimates is the subject of Chapter 5. Chapter 6 focuses on utilizing the infor- mation from the WBS to create a project plan in the form of a timed and sequenced network of activities. Risks are a potential threat to every project, and Chapter 7 examines how organiza- tions and managers identify and manage risks associated with project work. Resource allocation is added to the plan in Chapter 8 with special attention devoted to how re- source limitations impact the project schedule. After a resource schedule is estab- lished, a project time-phased budget is developed. Finally, Chapter 9 examines strategies for reducing (“crashing”) project time either prior to the initiation of the project or in response to problems or new demands placed on the project. Chapters 10 through 12 focus on project implementation and the sociocultural side of project management, beginning with Chapter 10, which focuses on the role of the

Chapter 1 Modern Project Management 19

project manager as a leader and stresses the importance of managing project stake- holders within the organization. Chapter 11 focuses on the core project team; it com- bines the latest information on team dynamics with leadership skills/techniques for developing a high-performance project team. Chapter 12 continues the theme of man- aging project stakeholders by discussing how to outsource project work and negotiate with contractors, customers, and suppliers. Chapter 13 focuses on the kinds of information managers use to monitor project prog- ress, with special attention devoted to the key concept of earned value. The project life cycle is completed with Chapter 14, which covers closing out a project and the important assess- ment of performance and lessons learned. Two “supplemental” chapters are included to augment the project management core. Working on international projects across cultures is the focus of Chapter 15. Agile project management, a more flexible approach to managing projects where requirements cannot be clearly defined, is the subject of Chapter 16. Throughout this text you will be exposed to the major aspects of the project man- agement system. However, a true understanding of project management comes not from knowing what a scope statement is, or the critical path, or partnering with con- tractors, but from comprehending how the different elements of the project manage- ment system interact to determine the fate of a project. If, by the end of this text, you come to appreciate and begin to master both the technical and sociocultural dimen- sions of project management, you should have a distinct competitive advantage over others aspiring to work in the field of project management.

Key Terms Program, 7 Project, 6 Project life cycle, 8

Project Management Professional (PMP), 4

1. Define a project. What are five characteristics that help differentiate projects from other functions carried out in the daily operations of the organization?

2. What are some of the key environmental forces that have changed the way projects are managed? What has been the effect of these forces on the management of projects?

3. Why is the implementation of projects important to strategic planning and the proj- ect manager?

4. The technical and sociocultural dimensions of project management are two sides to the same coin. Explain.

5. What is the impact of governance on managing an individual project? Why is this approach important in today’s environment?

Review Questions

1. Review the front page of your local newspaper, and try to identify all the projects contained in the articles. How many were you able to find?

2. Individually, identify what you consider to be the greatest achievements of mankind in the last five decades. Now share your list with three to five other students in the class, and come up with an expanded list. Review these great achievements in terms of the definition of a project. What does your review suggest about the importance of project management?

3. Individually, identify projects assigned in previous terms. Were both sociocultural and technical elements factors in the success or difficulties in the projects?

Exercises

4. Check out the Project Management Institute’s home page at www.pmi.org. a. Review general information about PMI as well as membership information. b. See if there is a PMI chapter in your state. If not, where is the closest one? c. Use the search function at the PMI home page to find information on Project

Management Body of Knowledge (PMBOK). What are the major knowledge areas of PMBOK?

d. Explore other links that PMI provides. What do these links tell you about the nature and future of project management?

Note: If you have any difficulty accessing any of the Web addresses listed here or else- where in the text, you can find up-to-date addresses on the home page of Dr. Erik Larson, coauthor of this text: http://business.oregonstate.edu/faculty-and-staff-bios/erik-larson

Benko, C., and F. W. McFarlan, Connecting the Dots (Boston: HBS Press, 2003). Cohen, D. J., and R. J. Graham, The Project Manager’s MBA (San Francisco: Jossey-Bass, 2001). Darnell, R., “The Emerging Role of the Project Manager,” PM Network, vol. 11, no. 7 (1997). Derby, Charles, and Ofer Zwikael, “The Secret of (Defining) Success,” PM Network, vol. 26, no. 8 (August 2012), pp. 20–22. Gray, Clifford, “Program Management, A Primer,” PM World Today, vol. 13, no. 8 (August 2011), pp. 1–7. Jonas, D., “Empowering Project Portfolio Managers: How Management Involvement Impacts Project Management Performance,” International Journal of Project Man- agement, vol. 28, no. 8 (2010), pp. 818–831. Koh, Aileen, and Lynn Crawford, “Portfolio Management: The Australian Experience,” Project Management Journal, vol. 43, no. 6 (2012), pp. 33–41. Peters, T., PM Network, January 2004, vol. 18, no. 1, p. 19. Project Management Institute, Leadership in Project Management Annual (Newton Square, PA: PMI Publishing, 2006). Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK), (Newton Square, PA: PMI Publishing, 2013). Project Management Institute, PMI Today, July 2011, p. 11. The Standish Group, CHAOS Summary 2009, pp. 1–4. Stewart, T. A., “The Corporate Jungle Spawns a New Species: The Project Manager,” Fortune, September 1996, pp. 14–15.

References

Case 1.1

A Day in the Life Rachel, the project manager of a large information systems project, arrives at her office early to get caught up with work before her co-workers and project team arrive. However, as she enters the office she meets Neil, one of her fellow project managers,

20 Chapter 1 Modern Project Management

Chapter 1 Modern Project Management 21

who also wants to get an early start on the day. Neil has just completed a project over- seas. They spend 10 minutes socializing and catching up on personal news. It takes Rachel 10 minutes to get to her office and settle in. She then checks her voice mail and turns on her computer. She was at her client’s site the day before until 7:30 p.m. and has not checked her e-mail or voice mail since 3:30 p.m. the previous day. There are 7 phone messages, 16 e-mails, and 4 notes left on her desk. She spends 15 minutes reviewing her schedule and “to do” lists for the day before responding to messages that require immediate attention. Rachel spends the next 25 minutes going over project reports and preparing for the weekly status meeting. Her boss, who just arrived at the office, interrupts her. They spend 20 minutes discussing the project. He shares a rumor that a team member is using stimulants on the job. She tells him that she has not seen anything suspicious but will keep an eye on the team member. The 9:00 a.m. project status meeting starts 15 minutes late because two of the team members have to finish a job for a client. Several people go to the cafeteria to get cof- fee and doughnuts while others discuss last night’s baseball game. The team members arrive, and the remaining 45 minutes of the progress review meeting surface project issues that have to be addressed and assigned for action. After the meeting Rachel goes down the hallway to meet with Victoria, another IS project manager. They spend 30 minutes reviewing project assignments since the two of them share personnel. Victoria’s project is behind schedule and in need of help. They broker a deal that should get Victoria’s project back on track. She returns to her office and makes several phone calls and returns several e-mails before walking downstairs to visit with members of her project team. Her intent is to follow up on an issue that had surfaced in the status report meeting. However, her simple, “Hi guys, how are things going?” elicits a stream of disgruntled responses from the “troops.” After listening patiently for over 20 minutes, she realizes that among other things several of the client’s managers are beginning to request features that were not in the original project scope statement. She tells her people that she will get on this right away. Returning to her office she tries to call her counterpart John at the client firm but is told that he is not expected back from lunch for another hour. At this time, Eddie drops by and says, “How about lunch?” Eddie works in the finance office and they spend the next half hour in the company cafeteria gossiping about internal politics. She is sur- prised to hear that Jonah Johnson, the director of systems projects, may join another firm. Jonah has always been a powerful ally. She returns to her office, answers a few more e-mails, and finally gets through to John. They spend 30 minutes going over the problem. The conversation ends with John promising to do some investigating and to get back to her as soon as possible. Rachel puts a “Do not disturb” sign on her door, and lies down in her office. She listens to the third and fourth movement of Ravel’s string quartet in F on headphones. Rachel then takes the elevator down to the third floor and talks to the purchasing agent assigned to her project. They spend the next 30 minutes exploring ways of get- ting necessary equipment to the project site earlier than planned. She finally authorizes express delivery. When she returns to her office, her calendar reminds her that she is scheduled to participate in a conference call at 2:30. It takes 15 minutes for everyone to get online. During this time, Rachel catches up on some e-mail. The next hour is spent exchang- ing information about the technical requirements associated with a new version of a software package they are using on systems projects like hers. Rachel decides to stretch her legs and goes on a walk down the hallway where she engages in brief conversations with various co-workers. She goes out of her way to thank

22 Chapter 1 Modern Project Management

Chandra for his thoughtful analysis at the status report meeting. She returns to find that John has left a message for her to call him back ASAP. She contacts John, who informs her that, according to his people, her firm’s marketing rep had made certain promises about specific features her system would provide. He doesn’t know how this communication breakdown occurred, but his people are pretty upset over the situation. Rachel thanks John for the information and immediately takes the stairs to where the marketing group resides. She asks to see Mary, a senior marketing manager. She waits 10 minutes before being invited into her office. After a heated discussion, she leaves 40 minutes later with Mary agreeing to talk to her people about what was promised and what was not promised. She goes downstairs to her people to give them an update on what is happening. They spend 30 minutes reviewing the impact the client’s requests could have on the project schedule. She also shares with them the schedule changes she and Victoria had agreed to. After she says good night to her team, she heads upstairs to her boss’s office and spends 20 minutes updating him on key events of the day. She returns to her office and spends 30 minutes reviewing e-mails and project documents. She logs on to the MS project schedule of her project and spends the next 30 minutes working with “what-if” scenarios. She reviews tomorrow’s schedule and writes some personal reminders before starting off on her 30-minute commute home. 1. How effectively do you think Rachel spent her day? 2. What does the case tell you about what it is like to be a project manager?

Case 1.2

The Hokies Lunch Group1

PART A Fatma settled down for lunch at the Yank Sing Chinese restaurant. She was early and took the time to catch up on her e-mail. Soon she would be joined by Jasper and Viktoria, two fellow 2014 grads from Virginia Tech in Blacksburg, Virginia. Jasper worked as a software engineer for a start-up company that wanted to expand the boundaries of sharing economy. Viktoria was an electrical engineer who worked for a German healthcare company in San Francisco. They had met each other at a Silicon Val- ley alumni reception hosted by Virginia Tech. Each of them felt a bit like a fish out of water on the West Coast, so they decided to have lunch together each month. The lunch evolved into a professional support group. A major part of each of their jobs was manag- ing projects, and they found it useful to share issues and seek advice from each other. Fatma worked for a very successful Internet company whose founders believed that everyone in the firm should devote three days a year to community service projects. The company was partnering with several companies in the construction industry to renovate abandoned buildings for low income families. The next project was the reno- vation of an empty warehouse into eight two-bedroom apartments. Fatma was part of the core team in charge of scheduling and managing work assignments. Viktoria and Jasper entered the restaurant together. Viktoria was the first to move to the Bay area. She was currently working on the next-generation neural

1 Hokies is the name associated with Virginia Tech athletic teams.

Chapter 1 Modern Project Management 23

stimulator (“PAX 2”). Neural stimulators are electronic devices that doctors implant in patients with wires connected to sources of pain in the patient’s spine. In the past, patients would have to have an operation to replace the stimulator bat- tery every 10 years. PAX 2 was being designed to take advantage of new battery technologies and use a rechargeable battery. In concept, this battery system would eliminate the need for replacement surgeries and allow the implanted battery to be recharged externally. Viktoria’s team had just completed the second prototype and was entering a critical testing phase. It had been tricky trying to predict the life span of the new rechargeable battery without testing it in real time. She was anx- ious to begin seeing the test results. Jasper was working for a start-up company after doing contract work for his first nine months in San Francisco. He was sworn to secrecy about the project and all Fatma and Viktoria knew was that the project had something to do with sharing economy. He was working with a small development team that included colleagues from Bangalore, India, and Malmo, Sweden. After ordering and chit-chatting a bit, Fatma started the discussion. “I will be glad when this week is over,” she said. “We’ve been struggling defining the scope of the project. At first glance our project seems relatively simple, build eight two-bedroom apartments in an old warehouse. But there are a lot of unanswered questions. What kind of community space do we want to have? How efficient should the energy system be? What kind of furniture? Everybody wants to do a good job, but when does low income housing morph into middle income housing?” Viktoria offered, “Scope defining is one of the things my company does very well. Before a project is authorized, a detailed scope statement is developed that clearly defines the project objectives, priorities, budget, requirements, limits, and exclusions. All of the key stakeholders sign off on it. It is really important to identify priorities up front. I know on the PAX 2 project that scope is the number one priority. I know no matter how long it takes it is imperative that my work is done right.” Fatma responded, “That’s exactly what my Project manager is preparing for Friday’s meeting. I guess that is one of the things you have to do as a project manager is end discussions. He is going to make the tough calls and finalize the project scope so we can begin planning.” Jasper interjected, “You guys are so lucky, for the most part your scope remains the same. In my work the scope is constantly changing. You show the founders a feature they wanted, and they say well if you can do that, can you do this? You know it’s going to happen, but you really can’t plan for it.” Jasper went on to say, “We do know what our number one priority is: time. There are a lot of players trying to move in to the ‘space’ we are working on. We have to demon- strate we are ahead of the pack if we are going to continue to get VC funding.”2 Jasper said that despite the pressure, his project had been a lot of fun. He especially liked working with his Swedish and Indian counterparts, Axel and Raja. They worked like a global tag team on their part of the project. Jasper would code and then pass his work onto Raja who would work on it and pass it on to Axel, who would eventually hand it off to Jasper. Given the time zones, they were able to have at least one person working on the code around the clock. Jasper said it was hard at first working with someone you never met personally other than on a video screen. Trust was an issue. Everyone was trying to prove them- selves. Eventually a friendly competition arose across the team. The programmers

2 New Venture Capital funding.

24 Chapter 1 Modern Project Management

exchanged funny cartoons and YouTube videos. He showed Fatma and Viktoria a You- Tube video about scope creep that got a chuckle from everyone. They made plans to meet next at the New Peruvian restaurant on SE 8th Street.

PART B The Peruvian cilantro/lime ceviche was a big hit at the next lunch. Viktoria began their discussion by reporting, “I have good and bad news. The bad news is that our first prototype failed its tests miserably. The good news is that I have a smart project man- ager. She knew this could happen, so she mitigated the risk by having us working on two alternative battery technologies. The alternative technology is passing all of the tests. Instead of falling behind months we are only days behind schedule.” This precipitated a discussion of risk management. Fatma reported that there had been a two-day session on risk management for the renovation project. They spent the first day brainstorming what could go wrong, and the second day coming up with strat- egies for dealing with risks. A big help was the risk report that was generated after the last project. The report detailed all of the problems that had occurred on the last reno- vation project as well as recommendations. Fatma said, “I couldn’t believe how much time and attention was devoted to safety, but as my project manager said, ‘all it takes is one bad accident to shut down a project for weeks, even months.’ ” Jasper reported that on his project they spent very little time on risk management. His project was driven by a build-test mentality. “Everybody assumes that daily testing eliminates problems, but when it’s time to integrate different features, that’s when the real bugs will emerge,” Jasper said. Jasper went on to say that things were not going well at work. They had missed their second straight milestone, and everyone was feeling the pressure to show results. “I even slept by my cubicle three nights ago,” Jasper confessed. Fatma asked, “How many hours are you working?” “I don’t know, at least 70, maybe 80 hours,” Jasper answered. He went on to say, “This is a high stakes project, with a BIG upside if suc- cessful. I am doing some of my best programming and we’ll just have to see what happens.” Jasper showed them a cartoon that was being circulated across his team. The cap- tion read: “When did you want it done? Yesterday.” Fatma turned to her friends and said, “I need some advice. As you know I’m respon- sible for scheduling work assignments. Well, some of my colleagues have been pretty aggressive lobbying for choice assignments. Everyone wants to work alongside Bruno or Ryan. Suddenly I am everyone’s friends, and certain people are going way out of their way to do favors for me. I am sure they think it will influence my decisions. It’s getting awkward and I am not sure what to do.” “Quid pro quo,” answered Jasper, “that’s how the business world works. You scratch my back and I’ll scratch yours. Within reason, I don’t have a problem with someone taking advantage of their position to garner favors and build relationships.” Viktoria said, “I disagree. You don’t want to be seen as someone whose influence can be bought. You need to think what’s best for the company. You need to ask your- self what would Bruno and Ryan want you to do? And if you don’t know, ask them.” After much discussion, Fatma left the restaurant leaning towards Viktoria’s advice, but she wasn’t sure what the guidelines should be.

PART C It took two months for the Hokie lunch group to get together again. Jasper had canceled the last meeting because of work, so Viktoria and Fatma saw a movie together instead.

Chapter 1 Modern Project Management 25

Jasper was the last person to arrive and it was clear from the look on his face that things were not going well. He sat down, avoided eye contact, before blurting, “I’m out of work.” “What do you mean?” Fatma and Viktoria cried. Jasper explained after months and months of work they had been unable to demonstrate a functional product. Jasper went on to say, “Despite our best efforts we couldn’t deliver. The founders couldn’t get an ounce of second round venture funding, so they decided to cut their losses and kill the project. I just spent the best six months of my programming life for nothing.” Fatma and Viktoria tried to comfort their friend. Fatma asked Jasper how the others were taking the news. Jasper said the Swedish programmer, Axel, took the news very hard. He went on to say, “I think he was burning a lot of bridges at home with the long work hours and now he has nothing to show for it. He started blaming us for mistakes we never made.” Raja, his Indian counterpart, was a different story. “Raja seemed to shrug his shoulders.” Jasper added, “He said, I know I am a good programmer. There are lots of opportunities here in Bangalore.” Fatma broke the silence that followed by saying to Jasper, “Send me your resume. My company is always looking for top notch programmers and it is a really great com- pany. Can you believe it, the two founders, Bruno and Ryan, are working side by side with everyone on renovating the warehouse? In fact, people were amazed at how good Bruno was with sheet rock. A big part of my job now is scheduling their time so they can work with as many different people as possible. They really want to use the project to get to know their employees. This hasn’t been easy. I have had to juggle their calen- dars, their abilities, and work opportunities.” Viktoria interjected, “You’re using Microsoft Project to do this?” “Not really,” responded Fatma. “At first I tried scheduling their work in Project, but it was too cum- bersome and time consuming. Now I just use the Project master schedule and each of their calendars to schedule their work. This seems to work best.” Viktoria added, “Yeah, Microsoft Project is a great program, but you can get lost trying to get it to do everything. Sometimes all you need is an Excel sheet and common sense.” Viktoria felt awkward, given what had happened to Jasper. She was just wrapping up the successful PAX 2 project. She was also getting ready for a well-deserved holi- day in Vietnam paid for by her project bonus. “I hate closing out a project,” Viktoria said. “It’s so boring. Document, document, document! I keep kicking myself for not tracking things when they happened. I am spending most of my time scouring my computer for files. I can’t wait to take off to Vietnam.” Viktoria went on to say, “The only thing I liked doing was the project retrospective.” Jasper asked, “What’s a project retrospective?” Viktoria answered, “It’s when the project team gets together and reviews what went well, what didn’t, and identifies lessons learned that we can apply to future projects. For example, one of the things we learned was that we needed to bring the manufacturing people on board a lot sooner in the design process. We focused on designing the very best product possible, regardless of cost. We found out later that there were ways for reducing production costs without compromising quality.” Fatma added, “We do that too at the end of our projects, but we call it an audit.” Fatma asked Viktoria, “Do you know what your next assignment will be?” “No,” she replied, “I will probably go back to my department and do some testing. I’m not worried. I did good work. I am sure someone will want me for their project.” Jasper chimed in, “I sure hope someone wants me for their next project.” Fatma and Viktoria immediately went into action trying to lift their friend’s spirits. A little while later, they walked out of the Tapa restaurant and gave each other hugs. Fatma reminded Jasper to send her his latest resume. 1. For each part (A, B, C), what phase of the project life cycle is each project in? Explain. 2. What are two important things you learned about working on projects from the

case? Why are they important?

26

Organization Strategy and Project Selection2

LEARNING OBJECTIVES After reading this chapter you should be able to:

2-1 Explain why it is important for project managers to understand their organization’s strategy.

2-2 Identify the significant role projects contribute to the strategic direction of the organization.

2-3 Understand the need for a project priority system.

2-4 Apply financial and nonfinancial criteria to assess the value of projects.

2-5 Understand how multi-criteria models can be used to select projects.

2-6 Apply an objective priority system to project selection.

2-7 Understand the need to manage the project portfolio.

OUTLINE 2.1 The Strategic Management Process: An

Overview

2.2 The Need for a Project Priority System

2.3 A Portfolio Management System

2.4 Selection Criteria

2.5 Applying a Selection Model

2.6 Managing the Portfolio System

Summary

C H A P T E R T W O

27

Strategy is implemented through projects. Every significant project should have a clear link to the organization’s strategy.

Strategy is fundamentally deciding how the organization will compete. Organizations use projects to convert strategy into new products, services, and processes needed for success. For example, Intel’s major strategy is one of differentiation. Its projects target innovation and time to market. Currently, Intel is directing its strategy toward specialty chips for products other than computers, such as autos, security, cell phones, and air controls. Another goal is to reduce project cycle times. Procter and Gamble, NEC, General Electric, and AT&T have reduced their cycle times by 20–50 percent. For example, Toyota and other auto manufacturers are now able to design and develop new cars in two to three years instead of five to seven. Projects and project management play the key role in supporting strategic goals. It is vital for project managers to think and act strategically. Aligning projects with the strategic goals of the organization is crucial for business success. Today’s economic climate is unprecedented by rapid changes in technology, global competition, and financial uncertainty. These conditions make strategy/project

Project networks

6

Managing risk 7

Monitoring progress

13

Teams 11

Outsourcing 12

Project manager

10

Strategy 2

Introduction 1

Organization 3

Schedule resources/costs

8

Intern ation

al

proje cts

15

Agile PM 16

Project closure

14

Estimate 5

Reducing project duration

9

Define project

4

28 Chapter 2 Organization Strategy and Project Selection

alignment even more essential for success. Ensuring a strong link between the strategic plan and projects is a difficult task that demands constant attention from top and mid- dle management. The larger and more diverse an organization, the more difficult it is to create and maintain this strong link. Companies today are under enormous pressure to manage a process that clearly aligns projects to organization strategy. Ample evidence still sug- gests that many organizations have not developed a process that clearly aligns project selection to the strategic plan. The result is poor utilization of the organization’s resources—people, money, equipment, and core competencies. Conversely, organiza- tions that have a coherent link of projects to strategy have more cooperation across the organization, perform better on projects, and have fewer projects. How can an organization ensure this link and alignment? The answer requires inte- gration of projects with the strategic plan. Integration assumes the existence of a stra- tegic plan and a process for prioritizing projects by their contribution to the plan. A crucial factor to ensure the success of integrating the plan with projects lies in the creation of a process that is open and transparent for all participants to review. This chapter presents an overview of the importance of strategic planning and the process for developing a strategic plan. Typical problems encountered when strategy and proj- ects are not linked are noted. A generic methodology that ensures integration by creat- ing very strong linkages of project selection and priority to the strategic plan is then discussed. The intended outcomes are clear organization focus, best use of scarce orga- nization resources (people, equipment, capital), and improved communication across projects and departments.

Why Project Managers Need to Understand Strategy Project management historically has been preoccupied solely with the planning and exe- cution of projects. Strategy was considered to be under the purview of senior manage- ment. This is old-school thinking. New-school thinking recognizes that project management is at the apex of strategy and operations. Aaron Shenhar speaks to this issue when he states, “. . . it is time to expand the traditional role of the project manager from an operational to a more strategic perspective. In the modern evolving organization, proj- ect managers will be focused on business aspects, and their role will expand from getting the job done to achieving the business results and winning in the marketplace.”1 There are two main reasons why project managers need to understand their organiza- tion’s mission and strategy. The first reason is so they can make appropriate decisions and adjustments. For example, how a project manager would respond to a suggestion to modify the design of a product to enhance performance will vary depending upon whether his company strives to be a product leader through innovation or to achieve operational excellence through low cost solutions. Similarly, how a project manager would respond to delays may vary depending upon strategic concerns. A project man- ager will authorize overtime if her firm places a premium on getting to the market first. Another project manager will accept the delay if speed is not essential. The second reason project managers need to understand their organization’s strat- egy is so they can be effective project advocates. Project managers have to be able to demonstrate to senior management how their project contributes to their firm’s mis- sion. Protection and continued support come from being aligned with corporate objec- tives. Project managers also need to be able to explain to team members and other

Explain why it is impor- tant for project managers to understand their orga- nization’s strategy.

2-1LO

1 Shenhar, A., and Dov Dvie, Reinventing Project Management (Harvard Business School, 2007), p. 5.

Chapter 2 Organization Strategy and Project Selection 29

stakeholders why certain project objectives and priorities are critical. This is essential for getting buy-in on contentious trade-off decisions. For these reasons project managers will find it valuable to have a keen understand- ing of strategic management and project selection processes, which are discussed next.

2.1 The Strategic Management Process: An Overview Strategic management is the process of assessing “what we are” and deciding and imple- menting “what we intend to be and how we are going to get there.” Strategy describes how an organization intends to compete with the resources available in the existing and perceived future environment.

Two major dimensions of strategic management are responding to changes in the external environment and allocating scarce resources of the firm to improve its com- petitive position. Constant scanning of the external environment for changes is a major requirement for survival in a dynamic competitive environment. The second dimen- sion is the internal responses to new action programs aimed at enhancing the competi- tive position of the firm. The nature of the responses depends on the type of business, environment volatility, competition, and the organizational culture. Strategic management provides the theme and focus of the future direction of the organization. It supports consistency of action at every level of the organization. It encourages integration because effort and resources are committed to common goals and strategies. See Snapshot from Practice 2.1: Does IBM’s Watson’s Jeopardy Project Represent a Change in Strategy? It is a continuous, iterative process aimed at develop- ing an integrated and coordinated long-term plan of action. Strategic management posi- tions the organization to meet the needs and requirements of its customers for the long term. With the long-term position identified, objectives are set, and strategies are devel- oped to achieve objectives and then translated into actions by implementing projects. Strategy can decide the survival of an organization. Most organizations are successful in formulating strategies for what course(s) they should pursue. However, the problem in many organizations is implementing strategies—that is, making them happen. Inte- gration of strategy formulation and implementation often does not exist. The components of strategic management are closely linked, and all are directed toward the future success of the organization. Strategic management requires strong links among mission, goals, objectives, strategy, and implementation. The mission gives the general purpose of the organization. Goals give global targets within the mis- sion. Objectives give specific targets to goals. Objectives give rise to formulation of strategies to reach objectives. Finally, strategies require actions and tasks to be imple- mented. In most cases the actions to be taken represent projects. Figure 2.1 shows a schematic of the strategic management process and major activities required.

Four Activities of the Strategic Management Process The typical sequence of activities of the strategic management process is outlined here; a description of each activity then follows: 1. Review and define the organizational mission. 2. Analyze and formulate strategies. 3. Set objectives to achieve strategy. 4. Implement strategies through projects.

Identify the significant role projects contribute to the strategic direction of the organization.

2-2LO

30 Chapter 2 Organization Strategy and Project Selection

IBM’s investment in artificial intelligence paid off. In February 2010, millions of people were glued to their television sets to watch IBM’s Watson outclass two former champion contestants on

the Jeopardy quiz show. Watson performed at human expert levels in terms of precision, confidence, and speed during the Jeopardy quiz show. Does Watson represent a new strategic direction for IBM? Not really. The Watson project is simply a man- ifestation of the move from computer hardware to a service strategy over a decade ago.

WATSON PROJECT DESCRIPTION Artificial intelligence has advanced significantly in recent years. Watson goes beyond IBM’s chess-playing supercomputer of the late 1990s. Chess is finite, logical, and reduced easily to mathematics. Watson’s space is ill-defined and involves dealing with abstraction and the circumstantial nature of language. Since Watson’s sys- tem can understand natural language, it can extend the way people interact with computers. The IBM Watson project took three intense years of research and development by a core team of about 20. Eight university teams working on specific challenge areas augmented these researchers. Watson depends on over 200 million pages of structured and unstructured data and a program capable of running trillions of operations per second. With this information backup, it attacks a Jeopardy question by parsing the question into small pieces. With the question parsed, the program then searches for relevant data. Using hundreds of decision rules, the program generates possible answers. These answers are assigned a confidence score to decide if Watson should risk offering an answer and how much to bet.

WHAT’S NEXT? Now that the hype is over, IBM is pursuing their service strategy and applying the knowledge gained from the Watson project to real business applications. Watson’s artificial intelligence design is flexible and suggests a wide variety of opportunities in industries such as

S N A P S H O T F R O M P R A C T I C E 2 . 1 Does IBM’s Watson’s Jeopardy Project Represent a Change in Strategy?*

finance, medicine, law enforcement, and defense. Fur- ther extensions to handheld mobile applications that tap into Watson’s servers also hold great potential. IBM identified the obvious lowest hanging apples on the tree as providing healthcare solutions and has begun design of such a program. To create a “doctor’s consultant” program would likely follow a design platform similar to Watson’s. For example, it would be able to:

knowledge base.

data.

- nostic options.

Creating a doctor’s consultant solution will not replace doctors. Although the system holds tremendous poten- tial, it is man-made and depends on the database, data analytics, and decision rules to select options. Given the doctor’s consultant input, a trained doctor makes the final patient diagnosis to supplement physical examination and experience. The Watson project provides IBM with a flexible com- ponent to continue their decade-old strategy, moving IBM from computer hardware to service products.

© Sean Gallup/Getty

*Ferrucci et al., “Building Watson,” AI Magazine, vol. 31, no. 3 (Fall 2010).

Chapter 2 Organization Strategy and Project Selection 31

Review and Define the Organizational Mission The mission identifies “what we want to become,” or the raison d’être. Mission state- ments identify the scope of the organization in terms of its product or service. A writ- ten mission statement provides focus for decision making when shared by organizational managers and employees. Everyone in the organization should be keenly aware of the organization’s mission. For example, at one large consulting firm, partners who fail to recite the mission statement on demand are required to buy lunch. The mission statement communicates and identifies the purpose of the organization to all stakeholders. Mission statements can be used for evaluating organization performance. Traditional components found in mission statements are major products and ser- vices, target customers and markets, and geographical domain. In addition, statements frequently include organizational philosophy, key technologies, public image, and con- tribution to society. Including such factors in mission statements relates directly to business success.

FIGURE 2.1 Strategic Management Process

Projects

1

2

3

4

What are we now?

What do we intend to be?

How are we going to get there?

Internal environment— strengths and weaknesses

Review/revise mission

Review/revise mission

External environment— opportunities and threats

Set strategy and objectives

Portfolio of strategic choices

Strategy implementation

Project selection

32 Chapter 2 Organization Strategy and Project Selection

Mission statements change infrequently. However, when the nature of the business changes or shifts, revised mission and strategy statements may be required. More specific mission statements tend to give better results because of a tighter focus. Mission statements decrease the chance of false directions by stakeholders. For example, compare the phrasing of the following mission statements:

Provide hospital design services. Provide data mining and analysis services. Provide information technology services. Provide high-value products to our customer.

Clearly, the first two statements leave less chance for misinterpretation than the others. A rule-of-thumb test for a mission statement is, if the statement can be anybody’s mis- sion statement, it will not provide the guidance and focus intended. The mission sets the parameters for developing objectives.

Analyze and Formulate Strategies Formulating strategy answers the question of what needs to be done to reach objec- tives. Strategy formulation includes determining and evaluating alternatives that sup- port the organization’s objectives and selecting the best alternative. The first step is a realistic evaluation of the past and current position of the enterprise. This step typi- cally includes an analysis of “who are the customers” and “what are their needs as they (the customers) see them.” The next step is an assessment of the internal and external environments. What are the internal strengths and weaknesses of the enterprise? Examples of internal strengths or weaknesses could be core competencies, such as technology, product quality, man- agement talent, low debt, and dealer networks. Managers can alter internal strengths and weaknesses. Opportunities and threats usually represent external forces for change such as technology, industry structure, and competition. Competitive benchmarking tools are sometimes used here to assess current and future directions. Opportunities and threats are the flip sides of each other. That is, a threat can be perceived as an opportu- nity, or vice versa. Examples of perceived external threats could be a slowing of the economy, a maturing life cycle, exchange rates, or government regulation. Typical opportunities are increasing demand, emerging markets, and demographics. Managers or individual firms have limited opportunities to influence such external environmental factors; however, in recent years notable exceptions have been new technologies such as Apple using the iPod to create a market to sell music. The keys are to attempt to forecast fundamental industry changes and stay in a proactive mode rather than a reactive one. This assessment of the external and internal environments is known as the SWOT anal- ysis (strengths, weaknesses, opportunities, and threats). From this analysis, critical issues and strategic alternatives are identified. Critical analysis of the strategies includes asking questions: Does the strategy take advantage of our core competencies? Does the strategy exploit our competitive advantage? Does the strategy maximize meeting customers’ needs? Does the strategy fit within our acceptable risk range? These strategic alternatives are winnowed down to a critical few that support the basic mission. Strategy formulation ends with cascading objectives or projects assigned to lower divisions, departments, or individuals. Formulating strategy might range around 20 percent of management’s effort, while determining how strategy will be imple- mented might consume 80 percent.

Chapter 2 Organization Strategy and Project Selection 33

Set Objectives to Achieve Strategies Objectives translate the organization strategy into specific, concrete, measurable terms. Organizational objectives set targets for all levels of the organization. Objec- tives pinpoint the direction managers believe the organization should move toward. Objectives answer in detail where a firm is headed and when it is going to get there. Typically, objectives for the organization cover markets, products, innovation, pro- ductivity, quality, finance, profitability, employees, and consumers. In every case, objectives should be as operational as possible. That is, objectives should include a time frame, be measurable, be an identifiable state, and be realistic. Doran created the memory device shown in Exhibit 2.1, which is useful when writing objectives.2 Each level below the organizational objectives should support the higher-level objectives in more detail; this is frequently called cascading of objectives. For exam- ple, if a firm making leather luggage sets an objective of achieving a 40 percent increase in sales through a research and development strategy, this charge is passed to the marketing, production, and R&D departments. The R&D department accepts the firm’s strategy as their objective, and their strategy becomes the design and develop- ment of a new “pull-type luggage with hidden retractable wheels.” At this point the objective becomes a project to be implemented—to develop the retractable wheel lug- gage for market within six months within a budget of $200,000. In summary, organi- zational objectives drive your projects.

Implement Strategies through Projects Implementation answers the question of how strategies will be realized, given avail- able resources. The conceptual framework for strategy implementation lacks the struc- ture and discipline found in strategy formulation. Implementation requires action and completing tasks; the latter frequently means mission-critical projects. Therefore, implementation must include attention to several key areas. First, completing tasks requires allocation of resources. Resources typically repre- sent funds, people, management talents, technological skills, and equipment. Fre- quently, implementation of projects is treated as an “addendum” rather than an integral part of the strategic management process. However, multiple objectives place conflict- ing demands on organizational resources. Second, implementation requires a formal and informal organization that complements and supports strategy and projects. Authority, responsibility, and performance all depend on organization structure and culture. Third, planning and control systems must be in place to be certain project activities necessary to ensure strategies are effectively performed. Fourth, motivating project contributors will be a major factor for achieving project success. Finally, areas receiving more attention in recent years are portfolio management and prioritizing

EXHIBIT 2.1 Characteristics of Objectives

S Specific Be specific in targeting an objective M Measurable Establish a measurable indicator(s) of progress A Assignable Make the objective assignable to one person for completion R Realistic State what can realistically be done with available resources T Time related State when the objective can be achieved, that is, duration

2 Doran, G. T., “There’s a Smart Way to Write Management Goals and Objectives,” Management Review, November 1981, pp. 35–36.

34 Chapter 2 Organization Strategy and Project Selection

projects. Although the strategy implementation process is not as clear as strategy for- mulation, all managers realize that, without implementation, success is impossible. Although the four major steps of the strategic management process have not been altered significantly over the years, the view of the time horizon in the strategy formu- lation process has been altered radically in the last two decades. Global competition and rapid innovation require being highly adaptive to short-run changes while being consistent in the longer run.

2.2 The Need for a Project Priority System Implementation of projects without a strong priority system linked to strategy creates problems. Three of the most obvious problems are discussed below. A priority driven project portfolio system can go a long way to reduce, or even eliminate, the impact of these problems.

Problem 1: The Implementation Gap In organizations with short product life cycles, it is interesting to note that frequently participation in strategic planning and implementation includes participants from all levels within the organization. However, in perhaps 80 percent of the remaining product and service organizations, top management pretty much formulates strategy and leaves strategy implementation to functional managers. Within these broad constraints, more detailed strategies and objectives are developed by the functional managers. The fact that these objectives and strategies are made independently at different levels by func- tional groups within the organization hierarchy causes manifold problems. Some symptoms of organizations struggling with strategy disconnect and unclear priorities are presented here. ∙ Conflicts frequently occur among functional managers and cause lack of trust. ∙ Frequent meetings are called to establish or renegotiate priorities. ∙ People frequently shift from one project to another, depending on current priority.

Employees are confused about which projects are important. ∙ People are working on multiple projects and feel inefficient. ∙ Resources are not adequate. Because clear linkages do not exist, the organizational environment becomes dysfunc- tional, confused, and ripe for ineffective implementation of organization strategy and, thus, of projects. The implementation gap refers to the lack of understanding and con- sensus of organization strategy among top and middle-level managers. A scenario the authors have seen repeated several times follows. Top management picks their top 20 projects for the next planning period, without priorities. Each functional department—marketing, finance, operations, engineering, information technology, and human resources—selects projects from the list. Unfortunately, independent department priorities across projects are not homogenous. A project that rates first in the IT department can rate 10th in the finance department. Imple- mentation of the projects represents conflicts of interest with animosities developing over organization resources. If this condition exists, how is it possible to effectively implement strategy? The problem is serious. One study found that only about 25 percent of Fortune 500 execu- tives believe there is a strong linkage, consistency, and/or agreement between the

Understand the need for a project priority system.

2-3LO

Chapter 2 Organization Strategy and Project Selection 35

strategies they formulate and implementation. In another study of Deloitte Consulting, Jeff MacIntyre reports, “Only 23 percent of nearly 150 global executives considered their project portfolios aligned with the core business.”3  Middle managers considered organizational strategy to be under the purview of oth- ers or not in their realm of influence. It is the responsibility of senior management to set policies that show a distinct link between organizational strategy and objectives and projects that implement those strategies. The research of Fusco suggests the imple- mentation gap and prioritizing projects are still overlooked by many organizations. He surveyed 280 project managers and found that 24 percent of their organizations did not even publish or circulate their objectives; in addition, 40 percent of the respondents reported that priorities among competing projects were not clear, while only 17 per- cent reported clear priorities.4

Problem 2: Organization Politics Politics exist in every organization and can have a significant influence on which proj- ects receive funding and high priority. This is especially true when the criteria and process for selecting projects are ill-defined and not aligned with the mission of the firm. Project selection may be based not so much on facts and sound reasoning as on the persuasiveness and power of people advocating projects. The term “sacred cow” is often used to denote a project that a powerful, high- ranking official is advocating. Case in point, a marketing consultant confided that he was once hired by the marketing director of a large firm to conduct an independent, external market analysis for a new product the firm was interested in developing. His extensive research indicated that there was insufficient demand to warrant the financ- ing of this new product. The marketing director chose to bury the report and made the consultant promise never to share this information with anyone. The director explained that this new product was the “pet idea” of the new CEO, who saw it as his legacy to the firm. He went on to describe the CEO’s irrational obsession with the project and how he referred to it as his “new baby.” Like a parent fiercely protecting his child, the marketing director believed that he would lose his job if such critical information ever became known. Project sponsors play a significant role in the selection and successful implemen- tation of product innovation projects. Project sponsors are typically high-ranking man- agers who endorse and lend political support for the completion of a specific project. They are instrumental in winning approval of the project and in protecting the project during the critical development stage. The importance of project sponsors should not be taken lightly. For example, a PMI global survey of over 1,000 project practitioners and leaders over a variety of industries found those organizations having active spon- sors on at least 80 percent of their projects/programs have a success rate of 75 percent, 11 percentage points above the survey average of 64 percent. Many promising projects have failed to succeed due to lack of strong sponsorship.5 The significance of corporate politics can be seen in the ill-fated ALTO computer project at Xerox during the mid-1970s.6 The project was a tremendous technological

3 MacIntyre, J., PM Network, vol. 20, no. 11 (November 2006), pp. 32–35. 4 Fusco, J. C., “Better Policies Provide the Key to Implementing Project Management,” Project Management Journal, vol. 28, no. 3 (1997), pp. 38–41. 5 PMI, “PMI’s Pulse of the Profession,” Project Management Institute, March 2012, p. 7. 6 Smith, D. K., and R. C. Alexander, Fumbling the Future: How Xerox Invented, Then Ignored the First Personal Computer (New York: Macmillan, 1988).

36 Chapter 2 Organization Strategy and Project Selection

success; it developed the first workable mouse, the first laser printer, the first user- friendly software, and the first local area network. All of these developments were five years ahead of their nearest competitor. Over the next five years this opportunity to dominate the nascent personal computer market was squandered because of internal in-fighting at Xerox and the absence of a strong project sponsor. (Apple’s MacIntosh computer was inspired by many of these developments.) Politics can play a role not only in project selection but also in the aspirations behind projects. Individuals can enhance their power within an organization by managing extraordinary and critical projects. Power and status naturally accrue to successful inno- vators and risk takers rather than to steady producers. Many ambitious managers pursue high-profile projects as a means for moving quickly up the corporate ladder. Many would argue that politics and project management should not mix. A more proactive response is that projects and politics invariably mix and that effective project managers recognize that any significant project has political ramifications. Likewise, top management needs to develop a system for identifying and selecting projects that reduces the impact of internal politics and fosters the selection of the best projects for achieving the mission and strategy of the firm.

Problem 3: Resource Conflicts and Multitasking Most project organizations exist in a multiproject environment. This environment cre- ates the problems of project interdependency and the need to share resources. For example, what would be the impact on the labor resource pool of a construction com- pany if it should win a contract it would like to bid on? Will existing labor be adequate to deal with the new project—given the completion date? Will current projects be delayed? Will subcontracting help? Which projects will have priority? Competition among project managers can be contentious. All project managers seek to have the best people for their projects. The problems of sharing resources and scheduling resources across projects grow exponentially as the number of projects rises. In multiproject envi- ronments the stakes are higher and the benefits or penalties for good or bad resource scheduling become even more significant than in most single projects. Resource sharing also leads to multitasking. Multitasking involves starting and stopping work on one task to go and work on another project, and then returning to the work on the original task. People working on several tasks concurrently are far less efficient, especially where conceptual or physical shutdown and start-up are signifi- cant. Multitasking adds to delays and costs. Changing priorities exacerbate the multi- tasking problems even more. Likewise, multitasking is more evident in organizations that have too many projects for the resources they command. The number of small and large projects in a portfolio almost always exceeds the available resources (typically by a factor of three to four times the available resources). This capacity overload inevitably leads to confusion and inefficient use of scarce orga- nizational resources. The presence of an implementation gap, of power politics, and of multitasking adds to the problem of which projects are allocated resources first. Employee morale and confidence suffer because it is difficult to make sense of an ambiguous system. A multiproject organization environment faces major problems without a priority system that is clearly linked to the strategic plan. In essence, to this point we have suggested that many organizations have no mean- ingful process for addressing the problems we have described. The first and most important change that will go a long way in addressing these and other problems is the development and use of a meaningful project priority process for project selection.

Chapter 2 Organization Strategy and Project Selection 37

How can the implementation gap be narrowed so that understanding and consensus of organizational strategies run through all levels of management? How can power politics be minimized? Can a process be developed in which projects are consistently prioritized to support organizational strategies? Can the prioritized projects be used to allocate scarce organizational resources—for example, people, equipment? Can the process encourage bottom-up initiation of projects that support clear organizational targets? What is needed is a set of integrative criteria and a process for evaluating and select- ing projects that support higher-level strategies and objectives. A single-project prior- ity system that ranks projects by their contribution to the strategic plan would make life easier. Easily said, but difficult to accomplish in practice. Organizations that man- aged independent projects and allocated resources ad hoc have shifted focus to select- ing the right portfolio of projects to achieve their strategic objectives. This is a quickening trend. The advantages of successful project portfolio systems are becoming well recognized in project-driven organizations. See Exhibit 2.2, which lists a few key benefits; the list could easily be extended. A project portfolio system is discussed next with emphasis on selection criteria, which is where the power of the portfolio system is established.

2.3 A Portfolio Management System Succinctly put, the aim of portfolio management is to ensure that projects are aligned with strategic goals and prioritized appropriately. As Foti points out, portfolio manage- ment asks “What is strategic to our organization?” (2002). Portfolio management pro- vides information that allows people to make better business decisions. Since projects clamoring for funding and people usually outnumber available resources, it is important to follow a logical and defined process for selecting the projects to implement. Design of a project portfolio system should include classification of a project, selec- tion criteria depending upon classification, sources of proposals, evaluating proposals, and managing the portfolio of projects.

Classification of the Project Many organizations find they have three basic kinds of projects in their portfolio: com- pliance (emergency—must do), operational, and strategic projects. (See Figure 2.2.) Compliance projects are typically those needed to meet regulatory conditions required to operate in a region; hence, they are called “must do” projects. Emergency projects, such as building an auto parts factory destroyed by tsunami, or recovering a crashed network, are examples of must do projects. Compliance and emergency projects usu- ally have penalties if they are not implemented. Operational projects are those that are needed to support current operations. These projects are designed to improve

EXHIBIT 2.2 Benefits of Project Portfolio Management

38 Chapter 2 Organization Strategy and Project Selection

efficiency of delivery systems, reduce product costs, and improve performance. Some of these projects, given their limited scope and cost, require only immediate manager approval, while bigger, more expensive projects need extensive review. Choosing to install a new piece of equipment would be an example of the latter while modifying a production process would be an example of the former. Total quality management (TQM) projects are examples of operational projects. Finally, strategic projects are those that directly support the organization’s long-run mission. They frequently are directed toward increasing revenue or market share. Examples of strategic projects are new products, research, and development. For a good, complete discussion on classifi- cation schemes found in practice, see Crawford, Hobbs, and Turne (2006). Frequently, these three classifications are further decomposed by product type, organization divisions, and functions that will require different criteria for project selection. For example, the same criteria for the finance or legal division would not apply to the IT (information technology) department. This often requires different project selection criteria within the basic three classifications of strategic, operational, and compliance projects.

2.4 Selection Criteria Although there are many criteria for selecting projects, selection criteria are typically identified as financial and nonfinancial. A short description of each is given next, fol- lowed by a discussion of their use in practice.

Financial Criteria Financial Models    For most managers financial criteria are the preferred method to evaluate projects. These models are appropriate when there is a high level of confidence associated with estimates of future cash flows. Two models and examples are demonstrated here— payback and net present value (NPV).

Project A has an initial investment of $700,000 and projected cash inflows of $225,000 for 5 years. Project B has an initial investment of $400,000 and projected cash inflows of $110,000 for 5 years. 1. The payback model measures the time it will take to recover the project invest-

ment. Shorter paybacks are more desirable. Payback is the simplest and most widely

Apply financial and nonfinancial criteria to assess the value of projects.

2-4LO

Compliance (must do) projects

Operational projects

Strategic projects

FIGURE 2.2 Portfolio of Projects by Type

Chapter 2 Organization Strategy and Project Selection 39

used model. Payback emphasizes cash flows, a key factor in business. Some managers use the payback model to eliminate unusually risky projects (those with lengthy pay- back periods). The major limitations of payback are that it ignores the time value of money, assumes cash inflows for the investment period (and not beyond), and does not consider profitability. The payback formula is

Payback period (yrs) = Estimated Project Cost/Annual Savings Exhibit 2.3 compares the payback for Project A and Project B. The payback for Project A is 3.1 years and for Project B is 3.6 years. Using the payback method, both projects are acceptable since both return the initial investment in less than five years and have returns on the investment of 32.1 and 27.5 percent. Payback provides especially useful information for firms concerned with liquidity and having sufficient resources to man- age their financial obligations. Exhibit 2.3A presents the payback method.

2. The net present value (NPV) model uses management’s minimum desired rate- of-return (discount rate, for example, 20 percent) to compute the present value of all net cash inflows. If the result is positive (the project meets the minimum desired rate

EXHIBIT 2.3B Example Comparing Two Projects Using Net Present Value Method

EXHIBIT 2.3A Example Comparing Two Projects Using Payback Method

40 Chapter 2 Organization Strategy and Project Selection

of return), it is eligible for further consideration. If the result is negative, the project is rejected. Thus, higher positive NPVs are desirable. Excel uses this formula:

Project NPV = I0 + ∑ n

t=1

Ft (1 + k)t

where I0 = Initial investment (since it is an outflow, the number will be negative) Ft = Net cash inflow for period t k = Required rate of return

Exhibit 2.3B presents the NPV model using Microsoft Excel software. The NPV model accepts Project A, which has a positive NPV of $54,235. Project B is rejected since the NPV is negative $31,263. Compare the NPV results with the payback results. The NPV model is more realistic because it considers the time value of money, cash flows, and profitability. When using the NPV model, the discount rate (return on investment hurdle rate) can differ for different projects. For example, the expected ROI on strategic projects is frequently set higher than operational projects. Similarly, ROIs can differ for riskier versus safer projects. The criteria for setting the ROI hurdle rate should be clear and applied consistently. Unfortunately, pure financial models fail to include many projects where financial return is impossible to measure and/or other factors are vital to the accept or reject decision. One research study by Foti showed that companies using predominantly financial models to prioritize projects yielded unbalanced portfolios and projects that aren’t strategically oriented (2003). Nonfinancial Criteria Financial return, while important, does not always reflect strategic importance. The past saw firms become overextended by diversifying too much. Now the prevailing thinking is that long-term survival is dependent upon developing and maintaining core competencies. Companies have to be disciplined in saying no to potentially profitable projects that are outside the realm of their core mission. This requires other criteria be considered beyond direct financial return. For example, a firm may support projects that do not have high profit margins for other strategic reasons including:

To capture larger market share To make it difficult for competitors to enter the market To develop an enabler product, which by its introduction will increase sales in more profitable products To develop core technology that will be used in next-generation products To reduce dependency on unreliable suppliers To prevent government intervention and regulation

Less tangible criteria may also apply. Organizations may support projects to restore corporate image or enhance brand recognition. Many organizations are committed to corporate citizenship and support community development projects. Two Multi-Criteria Selection Models Since no single criterion can reflect strategic significance, portfolio management requires multi-criteria screening models. Two models, the checklist and multi- weighted scoring models, are described next.

Chapter 2 Organization Strategy and Project Selection 41

Checklist Models The most frequently used method in selecting projects has been the checklist. This approach basically uses a list of questions to review potential proj- ects and to determine their acceptance or rejection. Several of the typical questions found in practice are listed in Exhibit 2.4. One large, multiproject organization has 250 different questions! A justification of checklist models is that they allow great flexibility in selecting among many different types of projects and are easily used across different divisions and locations. Although many projects are selected using some variation of the check- list approach, this approach has serious shortcomings. Major shortcomings of this approach are that it fails to answer the relative importance or value of a potential proj- ect to the organization and fails to allow for comparison with other potential projects. Each potential project will have a different set of positive and negative answers. How do you compare? Ranking and prioritizing projects by their importance is difficult, if not impossible. This approach also leaves the door open to the potential opportunity for power plays, politics, and other forms of manipulation. To overcome these serious shortcomings experts recommend the use of a multi-weighted scoring model to select projects, which is examined next.

Multi-Weighted Scoring Models A weighted scoring model typically uses several weighted selection criteria to evaluate project proposals. Weighted scoring models will generally include qualitative and/or quantitative criteria. Each selection criterion is assigned a weight. Scores are assigned to each criterion for the project, based on its importance to the project being evaluated. The weights and scores are multiplied to get a total weighted score for the project. Using these multiple screening criteria, projects can then be compared using the weighted score. Projects with higher weighted scores are considered better. Selection criteria need to mirror the critical success factors of an organization. For example, 3M set a target that 25 percent of the company’s sales would come from products fewer than four years old versus the old target of 20 percent. Their priority

Understand how multi- criteria models can be used to select projects.

2-5LO

EXHIBIT 2.4 Sample Selection Questions Used in Practice

Topic Question Strategy/alignment What specific organization strategy does this project align with? Driver What business problem does the project solve? Sponsorship Who is the project sponsor? Risk What is the impact of not doing this project? Risk What is the project risk to our organization? Benefits, value, ROI What is the value of the project to this organization? Benefits, value, ROI When will the project show results? Objectives What are the project objectives? Organization culture Is our organization culture right for this type of project? Resources Will internal resources be available for this project? Approach Will we build or buy? Schedule How long will this project take? Schedule Is the time line realistic? Training/resources Will staff training be required? Finance/portfolio What is the estimated cost of the project? Portfolio Is this a new initiative or part of an existing initiative? Portfolio How does this project interact with current projects? Technology Is the technology available or new?

42 Chapter 2 Organization Strategy and Project Selection

system for project selection strongly reflects this new target. On the other hand, failure to pick the right factors will render the screening process “useless” in short order. See Snapshot from Practice 2.2: Crisis IT. Figure 2.3 represents a project scoring matrix using some of the factors found in practice. The screening criteria selected are shown across the top of the matrix (e.g., stay within core competencies . . . ROI of 18 percent plus). Management weights each criterion (a value of 0 to a high of, say, 3) by its relative importance to the organiza- tion’s objectives and strategic plan. Project proposals are then submitted to a project priority team or project office. Each project proposal is then evaluated by its relative contribution/value added to the selected criteria. Values of 0 to a high of 10 are assigned to each criterion for each project. This value represents the project’s fit to the specific criterion. For example, project 1 appears to fit well with the strategy of the organization since it is given a value of 8. Conversely, project 1 does nothing to support reducing defects (its value is 0). Finally, this model applies the management weights to each criterion by impor- tance using a value of 1 to 3. For example, ROI and strategic fit have a weight of 3, while urgency and core competencies have weights of 2. Applying the weight to each

In May 2007, Frontier Airlines Hold- ings hired Gerry Coady as chief infor- mation officer (CIO). Nearly a year later the airline filed for bankruptcy under Chapter 11. In an interview Coady

describes how he managed IT projects during the bank- ruptcy and recession crisis of 2008–2009. Fundamentally, Coady faced a situation of too many projects and too few resources. Coady used a strategy of focusing on reducing the number of proj- ects in the portfolio. He put together a steering com- mittee of senior management that reviewed several hundred projects. The end result was a reduction to less than 30 projects remaining in the portfolio.

How Can You Get to a Backlog of over 100 Projects? “There are never enough resources to get everything done.” Backlogs build over time. Sacred cow projects get included in the selection system. Projects proposed from people who have left the airline still reside in the project portfolio. Non-value-added projects somehow make their way into the project portfolio. Soon the queue gets longer. With everyone in IT working on too many projects concurrently, project completion and productivity are slow.

Which Projects Remain? To cut the number of projects, the steering committee used a weighting scheme that reflected the airline’s pri- orities, which were: fly safe, generate revenue, reduce

S N A P S H O T F R O M P R A C T I C E 2 . 2 Crisis IT

costs, and customer service. The weighting scheme eas- ily weeded out the fluff. Coady noted that “by the time you get to the 20s the margin of differentiation gets nar- rower and narrower.” Of the remaining projects, project sponsors had to have solid justification why their project is important. Reduction of the number of projects places emphasis on high value projects.

What Advice Does Coady Have for Crisis Management? In times of crisis, it is easier to take bold steps to make changes. But you need to have a clear vision of what you should be focusing on with the resources available. Coady suggests, “It comes back to really having a good idea of what the initial business case for a project is and what resources it is consuming, both people and otherwise.”

Source: Worthen, B., “Crisis IT,” The Wall Street Journal, April 20, 2009, p. 6.

© PRNewsFoto/Genesis, Inc.

Chapter 2 Organization Strategy and Project Selection 43

criterion, the priority team derives the weighted total points for each project. For example, project 5 has the highest value of 102 [(2 × 1) + (3 × 10) + (2 × 5) + (2.5 × 10) + (1 × 0) + (1 × 8) + (3 × 9) = 102] and project 2 has a low value of 27. If the resources available create a cutoff threshold of 50 points, the priority team would elimi- nate projects 2 and 4. (Note: Project 4 appears to have some urgency, but it is not clas- sified as a “must” project. Therefore, it is screened with all other proposals.) Project 5 would receive first priority, project n second, and so on. In rare cases where resources are severely limited and project proposals are similar in weighted rank, it is prudent to pick the project placing less demand on resources. Weighted multiple criteria models similar to this one are rapidly becoming the dominant choice for prioritizing projects. At this point in the discussion it is wise to stop and put things into perspective. While selection models like the one above may yield numerical solutions to project selection decisions, models should not make the final decisions—the people using the models should. No model, no matter how sophisticated, can capture the total reality it is meant to represent. Models are tools for guiding the evaluation process so that the decision makers will consider relevant issues and reach a meeting of the minds as to which projects should be supported and not supported. This is a much more subjective process than calculations suggest.

2.5 Applying a Selection Model

Project Classification    It is not necessary to have exactly the same criteria for the different types of projects discussed above (strategic and operations). However, experience shows most organiza- tions use similar criteria across all types of projects, with perhaps one or two criteria specific to the type of project—e.g., strategic breakthrough versus operational.

Apply an objective prior- ity system to project selection.

2-6LO

Project 1

CriteriaW eight

Project 2

Project 3

Project 4

Project 5

Project 6 ...

Project n

1

3

9

3

1

6

5

8

3

5

0

10

5

5

2

2

2

10

5

0

7

6

0

0

0

10

2

0

0

0

2

0

0

0

10

6

5

2

6

8

2

10

5

1

5

0

9

7

8

66

2.0

Sta y w

ith in

co re

co mp

ete nc

ies

Ur ge

nc y

25 %

of sa

les

fro m

ne w

pr od

uc ts

Re du

ce

de fec

ts to

les s t

ha n 1

% Im

pr ov

e

cu sto

me r

loy alt

y RO

I o f 18

%

plu s

We igh

ted

tot al

Str ate

gic

fit

3.0 2.0 2.5 1.0 1.0 3.0

27

56

32

102

55

83

FIGURE 2.3 Project Screening Matrix

44 Chapter 2 Organization Strategy and Project Selection

Regardless of criteria differences among different types of projects, the most important criterion for selection is the project’s fit to the organization strategy. Therefore, this criterion should be consistent across all types of projects and carry a high priority relative to other criteria. This uniformity across all priority models used can keep departments from suboptimizing the use of organization resources. Project proposals should be classified by type, so the appropriate criteria can be used to evaluate them.

Selecting a Model In the past, financial criteria were used almost to the exclusion of other criteria. However, in the last two decades we have witnessed a dramatic shift to include multiple criteria in project selection. Concisely put, profitability alone is simply not an adequate measure of contribution; however, it is still an important criterion, especially for projects that enhance revenue and market share such as breakthrough R&D projects. Today, senior management is interested in identifying the potential mix of projects that will yield the best use of human and capital resources to maximize return on investment in the long run. Factors such as researching new technology, public image, ethical position, protection of the environment, core competencies, and strategic fit might be important criteria for selecting projects. Weighted scoring criteria seem the best alternative to meet this need. Weighted scoring models result in bringing projects to closer alignment with stra- tegic goals. If the scoring model is published and available to everyone in the organi- zation, some discipline and credibility are attached to the selection of projects. The number of wasteful projects using resources is reduced. Politics and “sacred cow” projects are exposed. Project goals are more easily identified and communicated using the selection criteria as corroboration. Finally, using a weighted scoring approach helps project managers understand how their project was selected, how their project contributes to organization goals, and how it compares with other projects. Project selection is one of the most important decisions guiding the future success of an organization. Criteria for project selection are the area where the power of your portfolio starts to manifest itself. New projects are aligned with the strategic goals of the organization. With a clear method for selecting projects in place, project proposals can be solicited.

Sources and Solicitation of Project Proposals As you would guess, projects should come from anyone who believes his or her project will add value to the organization. However, many organizations restrict proposals from specific levels or groups within the organization. This could be an opportunity lost. Good ideas are not limited to certain types or classes of organiza- tion stakeholders. Encourage and keep solicitations open to all sources—internal and external sponsors. Figure 2.4A provides an example of a proposal form for an automatic vehicular tracking (Automatic Vehicle Location) public transportation project. Figure 2.4B pres- ents a preliminary risk analysis for a 500-acre wind farm. Many organizations use risk analysis templates to gain a quick insight of a project’s inherent risks. Risk factors depend on the organization and type of projects. This information is useful in balanc- ing the project portfolio and identifying major risks when executing the project. Proj- ect risk analysis is the subject of Chapter 7.

Chapter 2 Organization Strategy and Project Selection 45

In some cases organizations will solicit ideas for projects when the knowledge requirements for the project are not available in the organization. Typically, the organi- zation will issue an RFP (Request for Proposal) to contractors/vendors with adequate experience to implement the project. In one example, a hospital published an RFP that asked for a bid to design and build a new operating room that uses the latest technol- ogy. Several architecture firms submitted bids to the hospital. The bids for the project were evaluated internally against other potential projects. When the project was accepted as a go, other criteria were used to select the best qualified bidder.

Project Proposal Form

Project classification?

What business problem does the project solve?

Increase customer satisfaction through kiosk and Web site for bus, streetcar, and fast rail Enhance driver and traveler safety

Strategic Infrastructure Compliance

Date: Proposal # SponsorJan 22, 2xxx 11

X

J. Moran

Hyperlink to: AVL.tri-met.org

Increase customer ridership through better passenger travel planning & scheduling decisions Faster response to accidents

How does this project align with our organization strategy?

What are the major deliverables of the project?

What is the impact of not doing this project?

What are the three major risks for this project?

Increased ridership Customer satisfaction Meeting budget and schedule

How will we measure success?

What is the estimated cost of the project?

How long will this project take?

Oversight action:

Signature

Accept

XXXXXX Date: Feb. 7, 2xxx

Return

22 Weeks

$10 million

Will this project require internal resources? Available?

Yes No Yes

Not meeting ridership goals

Cost overruns Hacking system

Integration of fast rail, bus, and streetcar systems

GPS vehicle tracking system, Internet access, schedule screen

No

X

X X

FIGURE 2.4A A Proposal Form for an Automatic Vehicular Tracking (AVL) Public Transportation Project

46 Chapter 2 Organization Strategy and Project Selection

Ranking Proposals and Selection of Projects Culling through so many proposals to identify those that add the most value requires a structured process. Figure 2.5 shows a flow chart of a screening process beginning with the creation of an idea for a project. See Figure 12.3 for a template for evaluating contractors. Data and information are collected to assess the value of the proposed project to the organization and for future backup. If the sponsor decides to pursue the project on the basis of the collected data, it is forwarded to the project priority team (or the project office). Note that the sponsor knows which criteria will be used to accept or reject the project. Given the selection criteria and current portfolio of projects, the priority team rejects or accepts the project. If the project is accepted, the priority team sets imple- mentation in motion. Figure 2.6 is a partial example of an evaluation form used by a large company to pri- oritize and select new projects. The form distinguishes between must and want objec- tives. If a project does not meet designated “must” objectives, it is not considered and is removed from consideration. Organization (or division) objectives have been ranked and weighted by their relative importance—for example, “Improve external customer ser- vice” carries a relative weight of 83 when compared to other want objectives. The want objectives are directly linked to objectives found in the strategic plan.

FIGURE 2.4B Risk Analysis for a 500-Acre Wind Farm

Brief Risk Assessment

Risk Intensity Rating

Purpose: To draw attention to apparent project risks that will need management attention.

Rank risks above by “probability” and “impact” on the chart below by High, Medium or Low.

What are the four major risks of this project?

1.

2.

3.

Government incentives curtailed

Land use injunction

Energy price decrease

4. New import tax

Risk Probability Impact

1.

2.

3.

Government incentives curtailed

Land use injunction

Energy price decrease

4. New import tax

High

Medium

Medium

Low

High

High

Medium

High

Check other project risk factors: Complexity

Resource skills

Technology

Low

Good

Low

Average

Okay

Average

High

Lacking

High

Reviewed by Date

X

Rachel April 1, 2xxx

X

X

Chapter 2 Organization Strategy and Project Selection 47

Impact definitions represent a further refinement to the screening system. They are developed to gauge the predicted impact a specific project would have on meeting a particular objective. A numeric scheme is created and anchored by defining criteria. To illustrate how this works, let’s examine the $5 million in new sales objective. A “0” is assigned if the project will have no impact on sales or less than $100,000, a “1” is given if predicted sales are more than $100,000 but less than $500,000, a “2” if greater than $500,000. These impact assessments are combined with the relative importance of each objective to determine the predicted overall contribution of a project to strategic objec- tives. For example, project 26 creates an opportunity to fix field problems, has no effect on sales, and will have major impact on customer service. On these three objectives, project 26 would receive a score of 265 [99 + 0 + (2 × 83)]. Individual weighted scores are totaled for each project and are used to prioritize projects.

Responsibility for Prioritizing Prioritizing can be an uncomfortable exercise for managers. But prioritizing projects is a major responsibility for senior management. Prioritizing means discipline, account- ability, responsibility, constraints, reduced flexibility, and loss of power. Top manage- ment commitment means more than giving a blessing to the priority system; it means management will have to rank and weigh, in concrete terms, the objectives and strate- gies they believe to be most critical to the organization. This public declaration of commitment can be risky if the ranked objectives later prove to be poor choices, but setting the course for the organization is top management’s job. The good news is, if management is truly trying to direct the organization to a strong future position, a good project priority system supports their efforts and develops a culture in which everyone is contributing to the goals of the organization.

Periodic reassessment

of priorities

Return for more

information

Abandon

Reject Accept

Pursue

Project proposal

idea

Data collection

and backup

Self-evaluation of project by criteria

Priority team evaluates proposal

and reviews portfolio for risk balance

Need strategic fit

ROI/payback risk

Assign priority Assign resources

Assign project manager

Evaluate progress

Hold for resources

FIGURE 2.5 Project Screening Process

48 Chapter 2 Organization Strategy and Project Selection

2.6 Managing the Portfolio System Managing the portfolio takes the selection system one step higher in that the merits of a particular project are assessed within the context of existing projects. At the same time it involves monitoring and adjusting selection criteria to reflect the strategic focus of the organization. This requires constant effort. The priority system can be managed by a small group of key employees in a small organization. Or, in larger organizations, the priority system can be managed by the project office or a governance team of senior managers.

Senior Management Input Management of a portfolio system requires two major inputs from senior management. First, senior management must provide guidance in establishing selection criteria that

Understand the need to manage the project portfolio.

2-7LO

Must objectives

All activities meet current legal, safety, and environmental standards

All new products will have a complete market analysis

Want objectives Single projectimpact definitions

Provides immediate response to field problems

Relative Importance

1-100

Weighted score

Weighted score

Weighted score

Weighted score

99

88

83

99

yes

n/a

0

166

0 Does not address 1 = Opportunity to fix 2 Urgent problem

0 < $100,000 1 = $100,000–500,000 2 > $500,000

0 Minor impact 1 = Significant impact 2 Major impact

Create $5 million in new sales by 20xx

Total weighted score

Priority

Improve external customer service

Yes-Meets objective No-Does not meet obj N/A-No impact

Yes-Meets objective No-Does not meet obj N/A-No impact

Must meet if impacts ...26 27 28 29

Project number FIGURE 2.6 Priority Screening Analysis

Chapter 2 Organization Strategy and Project Selection 49

strongly align with the current organization strategies. Second, senior management must annually decide how they wish to balance the available organizational resources (people and capital) among the different types of projects. A preliminary decision of balance must be made by top management (e.g., 20 percent compliance, 50 percent strategic, and 30 percent operational) before project selection takes place, although the balance may be changed when the projects submitted are reviewed. Given these inputs the priority team or project office can carry out its many responsibilities, which include supporting project sponsors and representing the interests of the total organization.

The Governance Team Responsibilities The governance team, or project office, is responsible for publishing the priority of every project and ensuring the process is open and free of power politics. For example, most organizations using a governance team or project office use an electronic bulletin board to disperse the current portfolio of projects, the current status of each project, and current issues. This open communication discourages power plays. Over time the governance team evaluates the progress of the projects in the portfolio. If this whole process is managed well, it can have a profound impact on the success of an organization. See Snapshot from Prac- tice 2.3: Project Code Names for the rationale behind titles given to projects.

What do Yangtze, Operation Iceberg, and Get Blue have in common? They are all code names given to projects. Project code names are used for sev- eral reasons:

organization.

Apple Corporation used to name major releases of MAC OS X after big cats such as Jaguar, Tiger, Panther, and Leopard, but now name them after national parks (i.e., Yosemite).

against rival concerns.

Oxcart was used by U.S. Department of Defense during the height of the cold war for the secret de- velopment of super sonic fighter jet.

- ect objectives

Operation Just Cause was the name given by U.S. government for the 1989 invasion of Panama, which ousted corrupt leader Manual Noriega.

Revolution was used by Nintendo for groundbreak- ing Wii video game console.

Often on small projects names convey a playful sense of humor. For example, a set of interrelated software projects were all named after Smurf Characters (Papa Smurf, Handy Smurf, Dreamy Smurf,…). Other times the project name reflects an inside joke, for example, one software project was named ALINA, which was an acronym for At Least It Is Not Access.

S N A P S H O T F R O M P R A C T I C E 2 . 3 Project Code Names*

© McGraw-Hill Education/Jill Braaten, photographer

*Sieminski, G. C., “The Art of Naming Operations,” Parame- ters, Autumn 1995, pp. 81-98; “Operation Know-It-All: The Indispensable Guide to Choosing Good Project Names,” articulatemarketing.com, accessed December 20, 2015.

50 Chapter 2 Organization Strategy and Project Selection

Constant scanning of the external environment to determine if organizational focus and/or selection criteria need to be changed is imperative! Periodic priority review and changes need to keep current with the changing environment and keep a unified vision of organization focus. Regardless of the criteria used for selection, each project should be evaluated by the same criteria. If projects are classified by must do, operation, and strategic, each project in its class should be evaluated by the same criteria. Enforcing the project priority system is crucial. Keeping the whole system open and aboveboard is important to maintaining the integrity of the system and keeping new, young execu- tives from going around the system. For example, communicating which projects are approved, project ranks, current status of in-process projects, and any changes in prior- ity criteria will discourage people from bypassing the system.

Balancing the Portfolio for Risks and Types of Projects A major responsibility of the priority team is to balance projects by type, risk, and resource demand. This requires a total organization perspective. Hence, a proposed project that ranks high on most criteria may not be selected because the organization portfolio already includes too many projects with the same characteristics—e.g., proj- ect risk level, use of key resources, high cost, nonrevenue producing, long durations. Balancing the portfolio of projects is as important as project selection. Organizations need to evaluate each new project in terms of what it adds to the project mix. Short- term needs need to be balanced with long-term potential. Resource usage needs to be optimized across all projects, not just the most important project. Two types of risk are associated with projects. First are risks associated with the total portfolio of projects, which should reflect the organization’s risk profile. Second are specific project risks that can inhibit the execution of a project, such as schedule, cost, and technical. In this chapter we look only to balancing the organizational risks inherent in the project portfolio, such as market risk, ability to execute, time to market, and technology advances. Project-specific risks will be covered in detail in Chapter 7. David and Jim Matheson studied R&D organizations and developed a classification scheme that could be used for assessing a project portfolio.7 They separated projects in terms of degree of difficulty and commercial value and came up with four basic types of projects:

Bread-and-butter projects are relatively easy to accomplish and produce modest commercial value. They typically involve evolutionary improvements to current products and services. Examples include software upgrades and manufacturing cost reduction efforts. Pearls are low risk development projects with high commercial payoffs. They represent revolutionary commercial advances using proven technology. Examples include next-generation integrated circuit chip and subsurface imaging to locate oil and gas. Oysters are high risk, high value projects. These projects involve technological breakthroughs with tremendous commercial potential. Examples include embry- onic DNA treatments and new kinds of metal alloys. White elephants are projects that at one time showed promise but are no longer viable. Examples include products for a saturated market or a potent energy source with toxic side-effects.

7 Matheson, D., and J. Matheson, The Smart Organization (Boston: Harvard Business School Press, 1998), pp. 203–209.

Chapter 2 Organization Strategy and Project Selection 51

The Mathesons report that organizations often have too many white elephants and too few pearls and oysters. To maintain strategic advantage they recommend that organiza- tions capitalize on pearls, eliminate or reposition white elephants, and balance resources devoted to bread-and-butter and oyster projects to achieve alignment with overall strategy. Although their research centers on R&D organizations, their observa- tions appear to hold true for all types of project organizations.

Summary Multiple competing projects, limited skilled resources, dispersed virtual teams, time to market pressures, and limited capital serve as forces for the emergence of project port- folio management that provides the infrastructure for managing multiple projects and linking business strategy with project selection. The most important element of this system is the creation of a ranking system that utilizes multiple criteria that reflect the mission and strategy of the firm. It is critical to communicate priority criteria to all organizational stakeholders so that the criteria can be the source of inspiration for new project ideas. Every significant project selected should be ranked and the results published. Se- nior management must take an active role in setting priorities and supporting the prior- ity system. Going around the priority system will destroy its effectiveness. The project governance team needs to consist of seasoned managers who are capable of asking tough questions and distinguishing facts from fiction. Resources (people, equipment, and capital) for major projects must be clearly allocated and not conflict with daily operations or become an overload task. The governance team needs to scrutinize significant projects in terms of not only their strategic value but also their fit with the portfolio of projects currently being im- plemented. Highly ranked projects may be deferred or even turned down if they upset the current balance among risks, resources, and strategic initiatives. Project selection must be based not only on the merits of the specific project but also on what it contrib- utes to the current project portfolio mix. This requires a holistic approach to aligning projects with organizational strategy and resources. The importance of aligning projects with organization strategy cannot be over- stated. We have discussed two types of models found in practice. Checklist models are easy to develop and are justified primarily on the basis of flexibility across different divisions and locations. Unfortunately, questionnaire checklist models do not allow comparison of the relative value (rank) of alternative projects in contributing toward organization strategy. The latter is the major reason the authors prefer multi-weighted scoring models. These models keep project selection highly focused on alignment with organization strategy. Weighted scoring models require major effort in establishing the criteria and weights.

Key Terms Implementation gap, 34 Net present value (NVP), 38 Organization politics, 35

Payback, 38 Priority system, 34 Priority team, 42 Project portfolio, 34

Project sponsor, 35 Sacred cow, 35 Strategic management, 29

52 Chapter 2 Organization Strategy and Project Selection

1. Describe the major components of the strategic management process. 2. Explain the role projects play in the strategic management process. 3. How are projects linked to the strategic plan? 4. The portfolio of projects is typically represented by compliance, strategic, and oper-

ations projects. What impact can this classification have on project selection? 5. Why does the priority system described in this chapter require that it be open and

published? Does the process encourage bottom-up initiation of projects? Does it discourage some projects? Why?

6. Why should an organization not rely only on ROI to select projects? 7. Discuss the pros and cons of the checklist versus the weighted factor method of

selecting projects.

1. You manage a hotel resort located on the South Beach on the Island of Kauai in Hawaii. You are shifting the focus of your resort from a traditional fun-in-the-sun destination to eco-tourism. (Eco-tourism focuses on environmental awareness and education.) How would you classify the following projects in terms of compliance, strategic, and operational? a. Convert the pool heating system from electrical to solar power. b. Build a four-mile nature hiking trail. c. Renovate the horse barn. d. Launch a new promotional campaign with Hawaii Airlines. e. Convert 12 adjacent acres into a wildlife preserve. f. Update all the bathrooms in condos that are 10 years old or older. g. Change hotel brochures to reflect eco-tourism image. h. Test and revise disaster response plan. i. Introduce wireless Internet service in café and lounge areas.

How easy was it to classify these projects? What made some projects more difficult than others? What do you think you now know that would be useful for managing projects at the hotel?

2.* Two new software projects are proposed to a young, start-up company. The Alpha project will cost $150,000 to develop and is expected to have annual net cash flow of $40,000. The Beta project will cost $200,000 to develop and is expected to have annual net cash flow of $50,000. The company is very concerned about their cash flow. Using the payback period, which project is better from a cash flow standpoint? Why?

3. A five-year project has a projected net cash flow of $15,000, $25,000, $30,000, $20,000, and $15,000 in the next five years. It will cost $50,000 to implement the project. If the required rate of return is 20 percent, conduct a discounted cash flow calculation to determine the NPV.

4. You work for the 3T company, which expects to earn at least 18 percent on its investments. You have to choose between two similar projects. The following chart shows the cash information for each project. Which of the two projects would you fund if the decision is based only on financial information? Why?

Exercises

Review Questions

*The solution to these exercises can be found in Appendix One.

Chapter 2 Organization Strategy and Project Selection 53

Omega Alpha Year Inflow Outflow Netflow Year Inflow Outflow Netflow Y0              0 $225,000 −225,000 Y0              0 $300,000 −300,000 Y1              0  190,000 −190,000 Y1   $ 50,000   100,000   −50,000 Y2 $ 150,000            0   150,000 Y2    150,000             0    150,000 Y3    220,000    30,000   190,000 Y3    250,000    50,000    200,000 Y4    215,000            0   215,000 Y4    250,000            0    250,000 Y5    205,000    30,000   175,000 Y5    200,000    50,000    150,000 Y6   197,000            0   197,000 Y6    180,000             0    180,000 Y7    100,000    30,000     70,000 Y7    120,000    30,000      90,000 Total 1,087,000  505,000   582,000 Total 1,200,000   530,000    670,000

5.* You are the head of the project selection team at SIMSOX. Your team is consider- ing three different projects. Based on past history, SIMSOX expects at least a rate of return of 20 percent.

Given the following information for each project, which one should be SIMSOX’s first priority? Should SIMSOX fund any of the other projects? If so, what should be the order of priority based on return on investment?

Project: Dust Devils

Year Investment Revenue Stream 0 $500,000 0 1 50,000 2 250,000 3 350,000

Project: Osprey

Year Investment Revenue Stream 0 $250,000 0 1 75,000 2 75,000 3 75,000 4 50,000

Project: Voyagers

Year Investment Revenue Stream 0 $75,000 0 1 15,000 2 25,000 3 50,000 4 50,000 5 150,000

*The solution to these exercises can be found in Appendix One.

54 Chapter 2 Organization Strategy and Project Selection

6. You are the head of the project selection team at Broken Arrow records. Your team is considering three different recording projects. Based on past history, Broken Arrow expects at least a rate of return of 20 percent.

Given the following information for each project, which one should be Broken Arrow’s first priority? Should Broken Arrow fund any of the other projects? If so, what should be the order of priority based on return on investment?

Recording Project: Time Fades Away

Year Investment Revenue Stream 0 $600,000 0 1 600,000 2 75,000 3 20,000 4 15,000 5 10,000

Recording Project: On the Beach

Year Investment Revenue Stream 0 $400,000 0 1 400,000 2 100,000 3 25,000 4 20,000 5 10,000

Recording Project: Tonight’s the Night

Year Investment Revenue Stream 0 $200,000 0 1 200,000            2 125,000            3 75,000          4 20,000          5 10,000        

7. The Custom Bike Company has set up a weighted scoring matrix for evaluation of potential projects. Below are five projects under consideration.

a. Using the scoring matrix in the following chart, which project would you rate highest? Lowest?

b. If the weight for “Strong Sponsor” is changed from 2.0 to 5.0, will the project selection change? What are the three highest weighted project scores with this new weight?

c. Why is it important that the weights mirror critical strategic factors?

Chapter 2 Organization Strategy and Project Selection 55

Project Screening Matrix

Project 1

CriteriaW eight

Project 2

Project 3

Project 4

Project 5

9

3

6

1

3

5

7

8

0

10

2

2

2

5

10

0

0

3

10

1

2

5

6

6

8

5

1

8

9

0

2.0

Str on

g

sp on

so r

Ur ge

nc y

10 %

of

sa les

fro m

ne w

pro du

cts

Co mp

eti tio

n

Fil l m

ark et

ga pSu

pp ort

s

bu sin

es s

str ate

gy

5.0 4.0 3.0 1.0 3.0

We igh

ted

tot al

Adler, P. S., et al., “Getting the Most Out of Your Product Development Process,” Harvard Business Review, vol. 74, no. 2, pp. 134–52. Benko, C., and F. W. McFarlan, Connecting the Dots: Aligning Projects With Objec- tives in Unpredictable Times (Boston: Harvard Business School Press, 2003). Bigelow, D., “Want to Ensure Quality? Think Project Portfolio Management,” PM Network, vol. 16, no. 1 (April 2002), pp. 16–17. Bloomberg Businessweek, “IBM Wants to Put Watson in Your Pocket,” September 17–23, 2012, pp. 41–42. Boyer, C., “Make Profit Your Priority,” PM Network, vol. 15, no. 10 (October 2003), pp. 37–42. Cohen, D., and R. Graham, The Project Manager’s MBA (San Francisco: Jossey- Bass, 2001), pp. 58–59. Crawford, L., B. Hobbs, and J. R. Turne, “Aligning Capability with Strategy: Catego- rizing of Projects to Do the Right Projects and Do Them Right,” Project Management Journal, vol. 37, no. 2 (June 2006), pp. 38–50. Descamps, J. P., “Mastering the Dance of Change: Innovation as a Way of Life,” Prism, Second Quarter, 1999, pp. 61–67. Doran, G. T., “There’s a Smart Way to Write Management Goals and Objectives,” Management Review, November 1981, pp. 35–36. Floyd, S. W., and B. Woolridge, “Managing Strategic Consensus: The Foundation of Effectiveness Implementation,” Academy of Management Executives, vol. 6, no. 4  (1992), pp. 27–39.

References

56 Chapter 2 Organization Strategy and Project Selection

Foti, R., “Louder Than Words,” PM Network, December 2002, pp. 22–29. Also see Foti, R., “Make Your Case, Not All Projects Are Equal,” PM Network, vol. 31, no. 7 (2003), pp. 35–43. Frank, L., “On Demand,” PM Network, vol. 18, no. 4 (April 2004), pp. 58–62. Friedman, Thomas L., Hot, Flat, and Crowded (New York: Farrar, Straus, and Giroux, 2008). Fusco, J. C., “Better Policies Provide the Key to Implementing Project Management,” Project Management Journal, vol. 28. no. 3 (1997), pp. 38–41. Helm, J., and K. Remington, “Effective Project Sponsorship: An Evaluation of the Executive Sponsor in Complex Infrastructure Projects by Senior Project Managers,” Project Management Journal, vol. 36, no. 1 (September 2005), pp. 51–61. Hutchens, G., “Doing the Numbers,” PM Network, vol. 16, no. 4 (March 2002), p. 20. Johnson, R. E., “Scrap Capital Project Evaluations,” Chief Financial Officer, May 1998, p. 14. Kaplan, R. S., and D. P. Norton, “The Balanced Scorecard—Measures That Drive Performance,” Harvard Business Review, January–February 1992, pp. 73–79. Also see Kaplan, Robert, http;//balancedscorecard.org. Kenny, J., “Effective Project Management for Strategic Innovation and Change in an Organizational Context,” Project Management Journal, vol. 34, no. 1 (2003), pp. 45–53. Kharbanda, O. P., and J. K. Pinto, What Made Gertie Gallop: Learning from Project Failures (New York: Van Nostrand Reinhold, 1996), pp. 106–11, 263–83. Korte, R. F., and T. J. Chermack, “Changing Organizational Culture with Scenario Planning,” Futures, vol. 39, no. 6 (August 2007), pp. 645–56. Leifer, R., C. M. McDermott, G. C. O’Connor, L. S. Peters, M. Price, and R. W. Veryzer, Radical Innovation: How Mature Companies Can Outsmart Upstarts (Boston: Harvard Business School Press, 2000). MacIntyre, J., PM Network, vol. 20, no. 11 (November 2006), pp. 32–35. Magretta, Joan, Understanding Michael Porter: The Essential Guide to Competition and Strategy (Boston: Harvard Business Press Book, 2011). Matheson, D., and J. Matheson, The Smart Organization (Boston: Harvard Business School Press, 1998), pp. 203–9. Milosevic, D. Z., and S. Srivannaboon, “A Theoretical Framework for Aligning Proj- ect Management with Business Strategy,” Project Management Journal, vol. 37, no. 3 (August 2006), pp. 98–110. Morris, P. W., and A. Jamieson, “Moving from Corporate Strategy to Project Strategy,” Project Management Journal, vol. 36, no. 4 (December 2005), pp. 5–18. Motta, Silva, and Rogério Hermida Quintella, “Assessment of Non-Financial Criteria in the Selection of Investment Projects for Seed Capital Funding: The Contribution of Scientometrics and Patentometrics,” Journal of Technology Management Innovation, vol. 7, no. 3 (2012). PMI, “PMI’s Pulse of the Profession,” March 2012, Project Management Institute, p. 7.

Chapter 2 Organization Strategy and Project Selection 57

Raskin, P., et al., Great Transitions: The Promise and Lure of the Times Ahead, retrieved June 3, 2008, www.gtinitiative.org/documents/Great_Transitions.pdf Schwartz, Peter, and Doug Randall, “An Abrupt Climate Change Scenario and its Implications for United States National Security,” Global Business Network, Inc., October 2003. Shenhar, A., “Strategic Project Leadership: Focusing Your Project on Business Success,” Proceedings of the Project Management Institute Annual Seminars & Symposium, San Antonio, Texas, October 3–10, 2002, CD. Also see Shenhar, Aaron, Reinventing Project Management (Harvard Business School, 2007). Sieminski, G. C., “The Art of Naming Operations,” Parameters, Autumn 1995, pp. 81–98. Smith, D. K., and R. C. Alexander, Fumbling the Future: How Xerox Invented, Then Ignored the First Personal Computer (New York: Macmillan, 1988). Swanson, S., “All Things Considered,” PM Network, vol. 25, no. 2 (February 2011), pp. 36–40. Woodward, H., “Winning in a World of Limited Project Spending,” Proceedings of the Project Management Institute Global Congress North America, Baltimore, Maryland, September 18–12, 2003, CD.

Case 2.1

Hector Gaming Company Hector Gaming Company (HGC) is an educational gaming company specializing in young children’s educational games. HGC has just completed their fourth year of oper- ation. This year was a banner year for HGC. The company received a large influx of capital for growth by issuing stock privately through an investment banking firm. It appears the return on investment for this past year will be just over 25 percent with zero debt! The growth rate for the last two years has been approximately 80 percent each year. Parents and grandparents of young children have been buying HGC’s prod- ucts almost as fast as they are developed. Every member of the 56-person firm is enthusiastic and looking forward to helping the firm grow to be the largest and best educational gaming company in the world. The founder of the firm, Sally Peters, has been written up in Young Entrepreneurs as “the young entrepreneur to watch.” She has been able to develop an organization culture in which all stakeholders are committed to innovation, continuous improvement, and organization learning. Last year, 10 top managers of HGC worked with McKinley Consulting to develop the organization’s strategic plan. This year the same 10 managers had a retreat in Aruba to formulate next year’s strategic plan using the same process suggested by McKinley Consulting. Most executives seem to have a consensus of where the firm should go in the intermediate and long term. But there is little consensus on how this should be accomplished. Peters, now president of HGC, feels she may be losing con- trol. The frequency of conflicts seems to be increasing. Some individuals are always requested for any new project created. When resource conflicts occur among projects, each project manager believes his or her project is most important. More projects are

58 Chapter 2 Organization Strategy and Project Selection

not meeting deadlines and are coming in over budget. Yesterday’s management meet- ing revealed some top HGC talent have been working on an international business game for college students. This project does not fit the organization vision or market niche. At times it seems everyone is marching to his or her own drummer. Somehow more focus is needed to ensure everyone agrees on how strategy should be imple- mented, given the resources available to the organization. Yesterday’s meeting alarmed Peters. These emerging problems are coming at a bad time. Next week HGC is ramping up the size of the organization, number of new prod- ucts per year, and marketing efforts. Fifteen new people will join HGC next month. Peters is concerned that policies be in place that will ensure the new people are used most productively. An additional potential problem looms on the horizon. Other gam- ing companies have noticed the success HGC is having in their niche market; one com- pany tried to hire a key product development employee away from HGC. Peters wants HGC to be ready to meet any potential competition head on and to discourage any new entries into their market. Peters knows HGC is project driven; however, she is not as confident that she has a good handle on how such an organization should be managed— especially with such a fast growth rate and potential competition closer to becoming a reality. The magnitude of emerging problems demands quick attention and resolution. Peters has hired you as a consultant. She has suggested the following format for your consulting contract. You are free to use another format if it will improve the effectiveness of the consulting engagement. What is our major problem? Identify some symptoms of the problem. What is the major cause of the problem? Provide a detailed action plan that attacks the problem. Be specific and provide exam- ples that relate to HGC.

Case 2.2

Film Prioritization The purpose of this case is to give you experience in using a project priority system that ranks proposed projects by their contribution to the organization’s objectives and strategic plan.

COMPANY PROFILE The company is the film division for a large entertainment conglomerate. The main office is located in Anaheim, California. In addition to the feature film division, the conglomerate includes theme parks, home videos, a television channel, interactive games, and theatrical productions. The company has been enjoying steady growth over the past 10 years. Last year total revenues increased by 12 percent to $21.2 billion. The company is engaged in negotiations to expand its theme park empire to mainland China and Poland. The film division generated $274 million in revenues, which was an increase of 7 percent over the past year. Profit margin was down 3 percent to 16 per- cent because of the poor response to three of the five major film releases for the year.

Chapter 2 Organization Strategy and Project Selection 59

COMPANY MISSION The mission for the firm:

Our overriding objective is to create shareholder value by continuing to be the world’s pre- mier entertainment company from a creative, strategic, and financial standpoint.

The film division supports this mission by producing four to six high-quality, family entertainment films for mass distribution each year. In recent years, the CEO of the company has advocated that the firm take a leadership position in championing envi- ronmental concerns.

COMPANY “MUST” OBJECTIVES Every project must meet the must objectives as determined by executive management. It is important that selected film projects not violate such objectives of high strategic priority. There are three must objectives: 1. All projects meet current legal, safety, and environmental standards. 2. All film projects should receive a PG or lower advisory rating. 3. All projects should not have an adverse effect on current or planned operations

within the larger company.

COMPANY “WANT” OBJECTIVES Want objectives are assigned weights for their relative importance. Top management is responsible for formulating, ranking, and weighting objectives to ensure that projects support the company’s strategy and mission. The following is a list of the company’s want objectives: 1. Be nominated for and win an academy award for Best Animated Feature or Best

Picture of the Year. 2. Generate additional merchandise revenue (action figures, dolls, interactive games,

music CDs). 3. Raise public consciousness about environmental issues and concerns. 4. Generate profit in excess of 18 percent. 5. Advance the state of the art in film animation, and preserve the firm’s reputation. 6. Provide the basis for the development of a new ride at a company-owned theme park.

ASSIGNMENT You are a member of the priority team in charge of evaluating and selecting film pro- posals. Use the provided evaluation form to formally evaluate and rank each proposal. Be prepared to report your rankings and justify your decisions. Assume that all of the projects have passed the estimated hurdle rate of 14 percent ROI. In addition to the brief film synopsis, the proposals include the following finan- cial projections of theater and video sales: 80 percent chance of ROI, 50 percent chance of ROI, and 20 percent chance of ROI. For example, for proposal #1 (Dalai Lama) there is an 80 percent chance that it will earn at least 8 percent return on investment (ROI), a 50-50 chance the ROI will be 18 percent, and a 20 percent chance that the ROI will be 24 percent.

60 Chapter 2 Organization Strategy and Project Selection

FILM PROPOSALS PROJECT PROPOSAL 1: MY LIFE WITH DALAI LAMA An animated, biographical account of the Dalai Lama’s childhood in Tibet based on the popular children’s book Tales from Nepal. The Lama’s life is told through the eyes of “Guoda,” a field snake, and other local animals who befriend the Dalai and help him understand the principles of Buddhism.

Probability 80% 50% 20%

ROI   8% 18% 24%

PROJECT PROPOSAL 2: HEIDI  A remake of the classic children’s story with music written by award-winning compos- ers Syskle and Obert. The big-budget film will feature top-name stars and breathtaking scenery of the Swiss Alps.

Probability 80% 50% 20%

ROI   2% 20% 30%

PROJECT PROPOSAL 3: THE YEAR OF THE ECHO A low-budget documentary that celebrates the career of one of the most influential bands in rock-and-roll history. The film will be directed by new-wave director Elliot Cznerzy and will combine concert footage and behind-the-scenes interviews spanning the 25-year history of the rock band the Echos. In addition to great music, the film will focus on the death of one of the founding members from a heroin overdose and reveal the underworld of sex, lies, and drugs in the music industry.

Probability 80% 50% 20%

ROI 12% 14% 18%

PROJECT PROPOSAL 4: ESCAPE FROM RIO JAPUNI An animated feature set in the Amazon rainforest. The story centers around Pablo, a young jaguar who attempts to convince warring jungle animals that they must unite and escape the devastation of local clear cutting.

Probability 80% 50% 20%

ROI 15% 20% 24%

PROJECT PROPOSAL 5: NADIA!  The story of Nadia Comaneci, the famous Romanian gymnast who won three gold medals at the 1976 Summer Olympic Games. The low-budget film will document her life as a small child in Romania and how she was chosen by Romanian authorities to join their elite, state-run, athletic program. The film will highlight how Nadia main- tained her independent spirit and love for gymnastics despite a harsh, regimented training program.

Probability 80% 50% 20%

ROI 8% 15% 20%

Chapter 2 Organization Strategy and Project Selection 61

Must objectives

Meets all safety and environmental standards

No adverse effect on other operations

PG or G rating

Want objectives

Single project impact definitions

Win Best Picture of the Year

Relative Importance

1–100

Weighted Score

Weighted Score

Weighted Score

Weighted Score

Weighted Score

Weighted Score

Weighted Score

70

60

55

70

40

10

0 = No potential 1 = Low potential 2 = High potential

0 = No potential 1 = Low potential 2 = High potential

10 0 = No potential 1 = Low potential 2 = High potential

0 = No potential 1 = Low potential 2 = High potential

0 < 18% 1 = 18–22% 2 > 22%

0 = No impact 1 = Some impact 2 = Great impact

0 = No potential 1 = Low potential 2 = High potential

Total weighted score

Priority

Win Best Animated Feature Film

Generate additional merchandise

Raise environmental concerns

Generate profit greater than 18%

Y = yes N = no N/A = not applicable Y = yes N = no N/A = not applicable

Y = yes N = no N/A = not applicable

Must meet if impacts

1 2 3 4 5 6 7

Advance state of film animation

Provide basis for new theme ride

Project Priority Evaluation Form

PROJECT PROPOSAL 6: KEIKO—ONE WHALE OF A STORY The story of Keiko, the famous killer whale, will be told by an imaginary offspring Seiko, who in the distant future is telling her children about their famous grandfather. The big-budget film will integrate actual footage of the whale within a realistic ani- mated environment using state-of-the-art computer imagery. The story will reveal how Keiko responded to his treatment by humans.

Probability 80% 50% 20%

ROI   6% 18% 25%

62 Chapter 2 Organization Strategy and Project Selection

PROJECT PROPOSAL 7: GRAND ISLAND  The true story of a group of junior-high biology students who discover that a fertilizer plant is dumping toxic wastes into a nearby river. The moderate-budget film depicts how students organize a grassroots campaign to fight local bureaucracy and ultimately force the fertilizer plant to restore the local ecosystem.

Probability 80% 50% 20%

ROI   9% 15% 20%

Case 2.3

Fund Raising Project Selection case The purpose of this “case exercise” is to provide you with experience in using a project selection process that ranks proposed projects by their contribution to an organiza- tion’s mission and strategy.

FUND RAISING PROJECT Assume you are a member of a class on project management. Each student will join a team of 5–7 students who will be responsible for creating, planning, and executing a fund raising project for a designated charity. The fund raising project has two goals: (1) raise money for a worthy cause and (2) provide an opportunity for all team mem- bers to practice project management skills and techniques. In addition to completing the project a number of deliverables are required to com- plete this assignment. These deliverables include: a. Project Proposal b. Implementation Plan c. Risk Management Plan d. Status Report e. Project Reflections Presentation f. Project Retrospective/Audit Approved projects will receive $250 seed money to be reimbursed upon completion of the project.

“MUST” OBJECTIVES Every project must meet the “must” objectives as determined by the instructor. There are four must objectives: 1. All projects must be safe, legal and comply with university policies. 2. All projects must be capable of earning at least $500. 3. All projects must be able to be completed within nine weeks. 4. All projects must provide an opportunity for every member of the project team to

experience and learn about project management. Among the factors to consider for the last objective would be the extent there is mean- ingful work for every member of the team, the degree of coordination required, the

Chapter 2 Organization Strategy and Project Selection 63

extent the team will have to work with external stakeholders, and the complexity of the project.

“WANT” OBJECTIVES In addition to the must objectives, there are “want” objectives that the instructor would like to achieve. The following is a list of these objectives: 1. Earn more than $500 for a charity 2. Increase public awareness of the charity 3. Provide a resume worthy experience for students 4. Be featured on local TV news 5. Be fun to do

ASSIGNMENT You are a member of the class priority team in charge of evaluating and approving fund raising projects. Use the provided proposal evaluation form to formally evaluate and rank each proposal. Be prepared to report your rankings and justify your decision. You should assume that these projects would be held at your university or college.

FUND RAISING PROPOSALS PROJECT PROPOSAL 1: HOOPS FOR HOPE The project is a three-on-three basketball tournament to raise money for the Down Syndrome Association. The tournament will consist of three brackets: Co-ed, Male, and Female teams. There will be a $40 entry fee per team and additional funds will be derived from the sale of commemorative T-shirts ($10). Winning teams will receive gift baskets consisting of donations from local businesses and restaurants. The event will be held at the university recreational center.

PROJECT PROPOSAL 2: SINGING FOR SMILES The project will hold a karaoke competition with celebrity judges at a popular campus night spot. Funds will be raised by $5 admission at the door and a raffle for prizes donated by local businesses. Funds will be donated to Smile Train, an international organization that performs cleft lip surgery at a cost of $250 per child. The event will feature pictures of children born with cleft lips and with every $50 earned a piece of a picture puzzle will be added until the original picture is covered with a smiling face.

PROJECT PROPOSAL 3: HALO FOR HEROES The project will be a Halo video game competition to be held over the weekend utiliz- ing the College’s big screen electronic classrooms. Teams of 4 players will play each other in a single elimination tournament with the grand prize being a Sony Play Sta- tion 3 donated by a local video game store. Entry fee is 24$ per team and individual players will be able to play in a loser’s bracket for 5$. All proceeds will go to the National Military Family Association.

PROJECT PROPOSAL 4: RAFFLE FOR LIFE Organize a raffle contest. Raffle tickets will be sold for 3$ apiece with the winning ticket worth $300. Each of the six team members will be responsible for selling 50 raffle tickets. All profits will go to the American Cancer Society.

64 Chapter 2 Organization Strategy and Project Selection

PROJECT PROPOSAL 5: HOLD’EM FOR HUNGER  Organize a Texas Hold’em poker tournament at a campus dining facility. It will cost $20 to enter the tournament with a $15 buy-in in fee. Prizes include $300, $150, and $50 gift certificates to a large department store. Gift certificates purchased from entry fees. All players will be eligible to win two donated tickets to Men and Women basketball games. Funds raised will go to local county food shelter. PROJECT PROPOSAL 6: BUILD YOUR OWN BOX The purpose of this project is to raise awareness of plight of homeless. Students will donate 10 dollars to participate in building and living in a cardboard city on the univer- sity quad for one night. Building materials will be provided by local recycling centers and hardware stores. Hot soup will be provided by the team at midnight to all partici- pants. Proceeds go to the local homeless shelter.

Must objectives

Be safe, legal, & comply with University Policies

Can be completed within 9 weeks

Earn at least $500

Want objectives

Single project impact definitions

Earning potential

Relative Importance

1–100

90

30

40

40

0: 500–750 1 : 750–1500 2: >$1500 3: >$2000 0: None 1 : Some fun 2: A lot of fun

30 0: No potential 1 : Low potential 2: High potential

0: No potential 1 : Low potential 2: High potential

0: No potential 1 : Low potential 2: High potential

Total weighted score

Priority

Fun

Increase awareness of charity

Resume worthy

Be featured on local TV news

Y = yes N = no

Y = yes N = no

Y = yes N = no

Opportunity to learn Project Management

Y = yes N = no

Must meet if impacts

1 2 3 4 5 6 7

Project Priority Evaluation Form

66

Organization: Structure and Culture3

LEARNING OBJECTIVES After reading this chapter you should be able to:

3-1 Identify different project management structures and understand their strengths and weaknesses.

3-2 Distinguish three different types of matrix structures and understand their strengths and weaknesses.

3-3 Understand organizational and project consider- ations that should be considered in choosing an appropriate project management structure.

3-4 Appreciate the significant role that organizational culture plays in managing projects.

3-5 Interpret the culture of an organization.

3-6 Understand the interaction between project management structure and the culture of an organization.

OUTLINE 3.1 Project Management Structures

3.2 What Is the Right Project Management Structure?

3.3 Organizational Culture

3.4 Implications of Organizational Culture for Organizing Projects

Summary

C H A P T E R T H R E E

67

Matrix management works, but it sure is difficult at times. All matrix man- agers must keep up their health and take Stress-Tabs. —A Project Manager

Once management approves a project, then the question becomes, how will the project be implemented? This chapter examines three different project management structures used by firms to implement projects: functional organization, dedicated project teams, and matrix structure. Although not exhaustive, these structures and their variant forms represent the major approaches for organizing projects. The advantages and disadvan- tages of each of these structures are discussed as well as some of the critical factors that might lead a firm to choose one form over others. Whether a firm chooses to complete projects within the traditional functional organiza- tion or through some form of matrix arrangement is only part of the story. Anyone who has worked for more than one organization realizes that there are often considerable dif- ferences in how projects are managed within certain firms even with similar structures. Working in a matrix system at AT&T is different from working in a matrix environment at Hewlett-Packard. Many researchers attribute these differences to the organizational

Project networks

6

Managing risk 7

Monitoring progress

13

Teams 11

Outsourcing 12

Project manager

10

Strategy 2

Introduction 1

Organization 3

Schedule resources & costs

8

Intern ation

al

proje cts

15

Agile PM 16

Project closure

14

Estimate 5

Reducing duration

9

Define project

4

68 Chapter 3 Organization: Structure and Culture

culture at AT&T and Hewlett-Packard. A simple explanation of organizational culture is that it reflects the “personality” of an organization. Just as each individual has a unique personality, so each organization has a unique culture. Toward the end of this chapter, we examine in more detail what organizational culture is and the impact that the culture of the parent organization has on organizing and managing projects. Both the project management structure and the culture of the organization constitute major elements of the enterprise environment in which projects are implemented. It is important for project managers and participants to know the “lay of the land” so that they can avoid obstacles and take advantage of pathways to complete their projects.

3.1 Project Management Structures A project management system provides a framework for launching and implementing project activities within a parent organization. A good system appropriately balances the needs of both the parent organization and the project by defining the interface between the project and parent organization in terms of authority, allocation of resources, and eventual integration of project outcomes into mainstream operations. With this in mind, we will start the discussion of project management structures.

Organizing Projects within the Functional Organization One approach to organizing projects is to simply manage them within the existing func- tional hierarchy of the organization. Once management decides to implement a project, the different segments of the project are delegated to the respective functional units with each unit responsible for completing its segment of the project (see Figure 3.1). Coordi- nation is maintained through normal management channels. For example, a tool manu- facturing firm decides to differentiate its product line by offering a series of tools specially designed for left-handed individuals. Top management decides to implement the project, and different segments of the project are distributed to appropriate areas. The industrial design department is responsible for modifying specifications to conform

Identify different project management structures and understand their strengths and weaknesses.

3-1LO

Manufacturing Procurement

Purchasing Receiving andinspection

Fabrication Assembly Testing Productionscheduling

Delta Manufacturing, Inc. President

Human resources

Project coordination

Marketing Engineering

Electronics engineering

Software engineering

Mechanical engineering

Customer service

Domestic sales

International sales

Design

Finance and administration

Manufacturing Procurement

Purchasing Receiving andinspection

Fabrication Assembly Testing Productionscheduling

Delta Manufacturing, Inc. President

Human resources

Project coordination

Marketing Engineering

Electronics engineering

Software engineering

Mechanical engineering

Customer service

Domestic sales

International sales

Design

Finance and administration

FIGURE 3.1 Functional Organizations

Chapter 3 Organization: Structure and Culture 69

to the needs of left-handed users. The production department is responsible for devising the means for producing new tools according to these new design specifications. The marketing department is responsible for gauging demand and price as well as identify- ing distribution outlets. The overall project will be managed within the normal hierar- chy, with the project being part of the working agenda of top management. The functional organization is also commonly used when, given the nature of the project, one functional area plays a dominant role in completing the project or has a dominant interest in the success of the project. Under these circumstances, a high- ranking manager in that area is given the responsibility of coordinating the project. For example, the transfer of equipment and personnel to a new office would be managed by a top-ranking manager in the firm’s facilities department. Likewise, a project involving the upgrading of the management information system would be managed by the information systems department. In both cases, most of the project work would be done within the specified department and coordination with other departments would occur through normal channels. There are advantages and disadvantages for using the existing functional organiza- tion to administer and complete projects (Larson, 2004). The major advantages are the following: 1. No Change. Projects are completed within the basic functional structure of the par-

ent organization. There is no radical alteration in the design and operation of the parent organization.

2. Flexibility. There is maximum flexibility in the use of staff. Appropriate specialists in different functional units can temporarily be assigned to work on the project and then return to their normal work. With a broad base of technical personnel available within each functional department, people can be switched among different projects with relative ease.

3. In-Depth Expertise. If the scope of the project is narrow and the proper functional unit is assigned primary responsibility, then in-depth expertise can be brought to bear on the most crucial aspects of the project.

Manufacturing Procurement

Purchasing Receiving andinspection

Fabrication Assembly Testing Productionscheduling

Delta Manufacturing, Inc. President

Human resources

Project coordination

Marketing Engineering

Electronics engineering

Software engineering

Mechanical engineering

Customer service

Domestic sales

International sales

Design

Finance and administration

Manufacturing Procurement

Purchasing Receiving andinspection

Fabrication Assembly Testing Productionscheduling

Delta Manufacturing, Inc. President

Human resources

Project coordination

Marketing Engineering

Electronics engineering

Software engineering

Mechanical engineering

Customer service

Domestic sales

International sales

Design

Finance and administration

70 Chapter 3 Organization: Structure and Culture

4. Easy Post-Project Transition. Normal career paths within a functional division are maintained. While specialists can make significant contributions to projects, their functional field is their professional home and the focus of their professional growth and advancement.

Just as there are advantages for organizing projects within the existing functional orga- nization, there are also disadvantages. These disadvantages are particularly pro- nounced when the scope of the project is broad and one functional department does not take the dominant technological and managerial lead on the project: 1. Lack of Focus. Each functional unit has its own core routine work to do; sometimes

project responsibilities get pushed aside to meet primary obligations. This difficulty is compounded when the project has different priorities for different units. For example, the marketing department may consider the project urgent while the oper- ations people consider it only of secondary importance. Imagine the tension if the marketing people have to wait for the operations people to complete their segment of the project before they proceed.

2. Poor Integration. There may be poor integration across functional units. Func- tional specialists tend to be concerned only with their segment of the project and not with what is best for the total project.

3. Slow. It generally takes longer to complete projects through this functional arrange- ment. This is in part attributable to slow response time—project information and

FIGURE 3.2 Dedicated Project Team

Zeus Electronics, Inc. President

Human resources

Finance and administration

Marketing Manufacturing

Project manager

Project team

ProcurementEngineering

Zeus Electronics, Inc. President

Human resources

Finance and administration

Marketing Manufacturing

Project manager

Project team

ProcurementEngineering

Chapter 3 Organization: Structure and Culture 71

decisions have to be circulated through normal management channels. Furthermore, the lack of horizontal, direct communication among functional groups contributes to rework as specialists realize the implications of others’ actions after the fact.

4. Lack of Ownership. The motivation of people assigned to the project can be weak. The project may be seen as an additional burden that is not directly linked to their professional development or advancement. Furthermore, because they are working on only a segment of the project, professionals do not identify with the project.

Organizing Projects as Dedicated Teams At the other end of the structural spectrum is the creation of a dedicated project team. These teams operate as separate units from the rest of the parent organization. Usually a full-time project manager is designated to pull together a core group of specialists who work full time on the project. The project manager recruits necessary personnel from both within and outside the parent company. The subsequent team is physically separated from the parent organization and given marching orders to complete the proj- ect (see Figure 3.2). The interface between the parent organization and the project teams will vary. In some cases, the parent organization maintains a tight rein through financial controls. In other cases, firms grant the project manager maximum freedom to get the project done as he

Zeus Electronics, Inc. President

Human resources

Finance and administration

Marketing Manufacturing

Project manager

Project team

ProcurementEngineering

Zeus Electronics, Inc. President

Human resources

Finance and administration

Marketing Manufacturing

Project manager

Project team

ProcurementEngineering

72 Chapter 3 Organization: Structure and Culture

sees fit. Lockheed Martin has used this approach to develop next-generation jet airplanes. See Snapshot from Practice 3.1: Skunk Works. In the case of firms where projects are the dominant form of business, such as a con- struction firm or a consulting firm, the entire organization is designed to support project teams. Instead of one or two special projects, the organization consists of sets of quasi- independent teams working on specific projects. The main responsibility of traditional functional departments is to assist and support these project teams. For example, the marketing department is directed at generating new business that will lead to more proj- ects, while the human resource department is responsible for managing a variety of personnel issues as well as recruiting and training new employees. This type of organi- zation is referred to in the literature as a projectized organization and is graphically portrayed in Figure 3.3. It is important to note that not all projects are dedicated project teams; personnel can work part-time on several projects. As in the case of functional organization, the dedicated project team approach has strengths and weaknesses (Larson, 2004). The following are recognized as strengths: 1. Simple. Other than taking away resources in the form of specialists assigned to the

project, the functional organization remains intact with the project team operating independently.

2. Fast. Projects tend to get done more quickly when participants devote their full attention to the project and are not distracted by other obligations and duties. Fur- thermore, response time tends to be quicker under this arrangement because most decisions are made within the team and are not deferred up the hierarchy.

In project management folklore, skunk works is code for a small, dedicated team assigned to a breakthrough proj- ect. The first skunk works was created more than a half a century ago by

Clarence L. “Kelly” Johnson at Lockheed Aerospace Corporation. Kelly’s project had two objectives: (1) to create a jet fighter, the Shooting Star, and (2) to do it as fast as possible. Kelly and a small band of engineering mavericks operated as a dedicated team unencum- bered by red tape and the bureaucratic delays of the normal R&D process. The name was coined by team member Irvin Culver after the moonshine brewery deep in the forest in the popular cartoon strip Lil’Abner. The homemade whisky was euphemistically called kickapoo joy juice. The project was a spectacular success. In just 43 days, Johnson’s team of 23 engineers and teams of support personnel put together the first American fighter to fly at more than 500 miles per hour. Lockheed has continued to use skunk works to develop a string of high speed jets, including the F117 Nighthawk Stealth Fighter as well as jet drone prototypes. Lockheed Mar- tin has an official Skunk Works Division. Their charter is:

S N A P S H O T F R O M P R A C T I C E 3 . 1

The Skunk Works is a concentration of a few good people solving problems far in advance—and at a fraction of the cost—by applying the simplest, most straightforward methods possible to develop and produce new products.

© Monty Rakusen/Getty Images

Skunk Works at Lockheed Martin*

*J. Miller, Lockheed Martin’s Skunk Works (New York: Special- ity Publications, 1996); “Lockheed Martin Skunk Works,” www.lockheedmartin.com/us/aeronautics/skunkworks.html, accessed 1/22/2015.

Chapter 3 Organization: Structure and Culture 73

3. Cohesive. A high level of motivation and cohesiveness often emerges within the project team. Participants share a common goal and personal responsibility toward the project and the team.

4. Cross-Functional Integration. Specialists from different areas work closely together and, with proper guidance, become committed to optimizing the project, not their respective areas of expertise.

In many cases, the project team approach is the optimum approach for completing a project when you view it solely from the standpoint of what is best for completing the project. Its weaknesses become more evident when the needs of the parent organiza- tion are taken into account: 1. Expensive. Not only have you created a new management position (project man-

ager), but resources are also assigned on a full-time basis. This can result in dupli- cation of efforts across projects and a loss of economies of scale.

2. Internal Strife. Sometimes dedicated project teams become an entity in their own right and conflict emerges between the team and the remainder of the organization (see Snapshot from Practice 3.2: The Birth of the Mac). This divisiveness can undermine not only the integration of the eventual outcomes of the project into mainstream operations but also the assimilation of project team members back into their functional units once the project is completed.

3. Limited Technological Expertise. Creating self-contained teams inhibits maxi- mum technological expertise being brought to bear on problems. Technical

FIGURE 3.3 Projectized Organization Structure

Central Engineering Systems, Inc. President

Marketing

Alpha Project Project Manager

ManufacturingEngineering Procurement Engineering Subcontractors

Other projects

Other projects

Manufacturing Procurement

Systems Hardware Software

Assembly Test

Electrical Mechanical Software

Fabrication Assembly Test

Subcontractor X Subcontractor Y Subcontractor Z

Beta Project Project Manager

Human resources

Finance and administration Legal

74 Chapter 3 Organization: Structure and Culture

One of the advantages of creating ded- icated project teams is that project par- ticipants from different functional areas can develop into a highly cohesive work team that is strongly committed

to completing the project. While such teams often pro- duce Herculean efforts in pursuit of project completion, there is a negative dimension to this commitment that is often referred to in the literature as projectitis. A we– they attitude can emerge between project team mem- bers and the rest of the organization. The project team succumbs to hubris and develops a holier-than-thou atti- tude that antagonizes the parent organization. People not assigned to the project become jealous of the atten- tion and prestige being showered on the project team, especially when they believe that it is their hard work that is financing the endeavor. The tendency to assign project teams exotic titles such as “Silver Bullets” and “Tiger Teams,” as well as give them special perks, tends to intensify the gap between the project team and the parent organization. Such appears to have been the case with Apple’s highly successful Macintosh development team. Steve Jobs, who at the time was both the chairman of Apple and the project manager for the Mac team, pampered his team with perks including at-the-desk massages, coolers stocked with freshly squeezed orange juice, a Bosendorfer grand piano, and first-class plane tickets. No other employees at Apple got to travel first class. Jobs considered his team to be the elite of Apple and had a tendency to refer to everyone else as “Bozos” who “didn’t get it.” Engineers from the Apple II division, which was the bread and butter of Apple’s sales, became incensed with the special treatment their col- leagues were getting. One evening at Ely McFly’s, a local watering hole, the tensions between Apple II engineers seated at one table and those of a Mac team at another boiled over. Aaron Goldberg, a long-time industry consultant, watched from his barstool as the squabbling escalated. “The Mac guys were screaming, ‘We’re the future!’ The Apple II guys were screaming, ‘We’re the money!’ Then

S N A P S H O T F R O M P R A C T I C E 3 . 2

there was a geek brawl. Pocket protectors and pens were flying. I was waiting for a notebook to drop, so they would stop and pick up the papers.” Although comical from a distance, the discord between the Apple II and Mac groups severely hampered Apple’s performance during the 1980s. John Sculley, who replaced Steve Jobs as chairman of Apple, observed that Apple had evolved into two “warring companies” and referred to the street between the Apple II and Macintosh buildings as “the DMZ” (demilitarized zone).

© McGraw-Hill Education/Jill Braaten

expertise is limited somewhat to the talents and experience of the specialists assigned to the project. While nothing prevents specialists from consulting with others in the functional division, the we–they syndrome and the fact that such help is not formally sanctioned by the organization discourage this from happening.

The Birth of the Mac*

*J. Carlton, Apple: The Inside Story of Intrigue, Egomania, and Business Blunders (New York: Random House, 1997), pp. 13–14; J. Sculley, Odyssey: Pepsi to Apple . . . A Journey of Adventure, Ideas, and the Future (New York: Harper & Row, 1987), pp. 270–79.

Chapter 3 Organization: Structure and Culture 75

4. Difficult Post-Project Transition. Assigning full-time personnel to a project cre- ates the dilemma of what to do with personnel after the project is completed. If other project work is not available, then the transition back to their original func- tional departments may be difficult because of their prolonged absence and the need to catch up with recent developments in their functional area.

Organizing Projects within a Matrix Arrangement One of the biggest management innovations to emerge in the past 40 years has been the matrix organization. Matrix management is a hybrid organizational form in which a horizontal project management structure is “overlaid” on the normal functional hier- archy. In a matrix system, there are usually two chains of command, one along func- tional lines and the other along project lines. Instead of delegating segments of a project to different units or creating an autonomous team, project participants report simultaneously to both functional and project managers. Companies apply this matrix arrangement in a variety of different ways. Some orga- nizations set up temporary matrix systems to deal with specific projects, while “matrix” may be a permanent fixture in other organizations. Let us first look at its general application and then proceed to a more detailed discussion of finer points. Consider Figure 3.4. There are three projects currently under way: A, B, and C. All three project managers (PM A-C) report to a director of project management, who supervises all projects. Each project has an administrative assistant, although the one for project C is only part time. Project A involves the design and expansion of an existing production line to accommodate new metal alloys. To accomplish this objective, project A has assigned to it 3.5 people from manufacturing and 6 people from engineering. These individuals are assigned to the project on a part-time or full-time basis, depending on the project’s needs during various phases of the project. Project B involves the development of a new product that requires the heavy representation of engineering, manufacturing, and marketing. Project C involves forecasting changing needs of an existing customer base. While these three projects, as well as others, are being completed, the functional divi- sions continue performing their basic, core activities. The matrix structure is designed to optimally utilize resources by having individu- als work on multiple projects as well as being capable of performing normal func- tional duties. At the same time, the matrix approach attempts to achieve greater integration by creating and legitimizing the authority of a project manager. In theory, the matrix approach provides a dual focus between functional/technical expertise and project requirements that is missing in either the project team or functional approach to project management. This focus can most easily be seen in the relative input of functional managers and project managers over key project decisions (see Table 3.1).

TABLE 3.1 Division of Project Manager and Functional Manager Responsibilities in a Matrix Structure

Project Manager Negotiated Issues Functional Manager

What has to be done? Who will do the task? How will it be done? When should the task Where will the task be done? be done? How much money is available Why will the task be How will the project involvement to do the task? done? impact normal functional activities? How well has the total project Is the task satisfactorily How well has the functional input been done? completed? been integrated?

76 Chapter 3 Organization: Structure and Culture

Different Matrix Forms In practice there are really different kinds of matrix systems, depending on the relative authority of the project and functional managers (Larson & Gobeli, 1987; Bowen et al., 1994). Here is a thumbnail sketch of the three kinds of matrices: ∙ Weak matrix—This form is very similar to a functional approach with the excep-

tion that there is a formally designated project manager responsible for coordinating project activities. Functional managers are responsible for managing their segment of the project. The project manager basically acts as a staff assistant who draws the schedules and checklists, collects information on status of work, and facilitates project completion. The project manager has indirect authority to expedite and monitor the project. Functional managers call most of the shots and decide who does what and when the work is completed.

∙ Balanced matrix—This is the classic matrix in which the project manager is responsible for defining what needs to be accomplished while the functional man- agers are concerned with how it will be accomplished. More specifically, the proj- ect manager establishes the overall plan for completing the project, integrates the contribution of the different disciplines, sets schedules, and monitors progress. The functional managers are responsible for assigning personnel and executing their segment of the project according to the standards and schedules set by the project manager. The merger of “what and how” requires both parties to work closely together and jointly approve technical and operational decisions.

Distinguish three differ- ent types of matrix struc- tures and understand their strengths and weaknesses.

3-2LO

FIGURE 3.4 Matrix Organization Structure

Testing

1/2

1

Domestic sales

2

2

Human resources Finance

Director of projects Engineering

Project A project

manager Project A team

Project B team

Project C team

Project administration

Manufacturing Marketing

Project B project

manager

Project C project

manager

Design engineering

2

3

1

1

1

1/2

Electronics engineering

1

1

Software engineering

1

Mechanical engineering

2

1

Technical documentation

1

1

Assembly

2

1

Quality

1

1

Customer service

1

1/2

International sales

1

2

Zeta Manufacturing, Inc. President

Chapter 3 Organization: Structure and Culture 77

∙ Strong matrix—This form attempts to create the “feel” of a project team within a matrix environment. The project manager controls most aspects of the project, includ- ing scope trade-offs and assignment of functional personnel. The project manager con- trols when and what specialists do and has final say on major project decisions. The functional manager has title over her people and is consulted on a need basis. In some situations a functional manager’s department may serve as a “subcontractor” for the project, in which case they have more control over specialized work. For example, the development of a new series of laptop computers may require a team of experts from different disciplines working on the basic design and performance requirements within a project matrix arrangement. Once the specifications have been determined, final design and production of certain components (i.e., power source) may be assigned to respective functional groups to complete.

Matrix management both in general and in its specific forms has unique strengths and weaknesses (Larson & Gobeli, 1987). The advantages and disadvantages of matrix organizations in general are noted below, while only briefly highlighting specifics con- cerning different forms: 1. Efficient. Resources can be shared across multiple projects as well as within func-

tional divisions. Individuals can divide their energy across multiple projects on an as-needed basis. This reduces duplication required in a projectized structure.

2. Strong Project Focus. A stronger project focus is provided by having a formally designated project manager who is responsible for coordinating and integrating

Testing

1/2

1

Domestic sales

2

2

Human resources Finance

Director of projects Engineering

Project A project

manager Project A team

Project B team

Project C team

Project administration

Manufacturing Marketing

Project B project

manager

Project C project

manager

Design engineering

2

3

1

1

1

1/2

Electronics engineering

1

1

Software engineering

1

Mechanical engineering

2

1

Technical documentation

1

1

Assembly

2

1

Quality

1

1

Customer service

1

1/2

International sales

1

2

Zeta Manufacturing, Inc. President

Testing

1/2

1

Domestic sales

2

2

Human resources Finance

Director of projects Engineering

Project A project

manager Project A team

Project B team

Project C team

Project administration

Manufacturing Marketing

Project B project

manager

Project C project

manager

Design engineering

2

3

1

1

1

1/2

Electronics engineering

1

1

Software engineering

1

Mechanical engineering

2

1

Technical documentation

1

1

Assembly

2

1

Quality

1

1

Customer service

1

1/2

International sales

1

2

Zeta Manufacturing, Inc. President

78 Chapter 3 Organization: Structure and Culture

contributions of different units. This helps sustain a holistic approach to problem solving that is often missing in the functional organization.

3. Easier Post-Project Transition. Because the project organization is overlaid on the functional divisions, specialists maintain ties with their functional group, so they have a homeport to return to once the project is completed.

4. Flexible. Matrix arrangements provide for flexible utilization of resources and expertise within the firm. In some cases functional units may provide individuals who are managed by the project manager. In other cases the contributions are moni- tored by the functional manager.

The strengths of the matrix structure are considerable. Unfortunately, so are the poten- tial weaknesses. This is due in large part to the fact that a matrix structure is more complicated and the creation of multiple bosses represents a radical departure from the traditional hierarchical authority system. Furthermore, one does not install a matrix structure overnight. Experts argue that it takes 3–5 years for a matrix system to fully mature. So many of the problems described below represent growing pains.

1. Dysfunctional Conflict. The matrix approach is predicated on tension between func- tional managers and project managers who bring critical expertise and perspectives to the project. Such tension is viewed as a necessary mechanism for achieving an appro- priate balance between complex technical issues and unique project requirements. While the intent is noble, the effect is sometimes analogous to opening Pandora’s box. Legitimate conflict can spill over to a more personal level, resulting from conflicting agendas and accountabilities. Worthy discussions can degenerate into heated argu- ments that engender animosity among the managers involved.

2. Infighting. Any situation in which equipment, resources, and people are being shared across projects and functional activities lends itself to conflict and competi- tion for scarce resources. Infighting can occur among project managers, who are primarily interested in what is best for their project.

3. Stressful. Matrix management violates the management principle of unity of com- mand. Project participants have at least two bosses—their functional head and one or more project managers. Working in a matrix environment can be extremely stressful. Imagine what it would be like to work in an environment in which you are being told to do three conflicting things by three different managers.

4. Slow. In theory, the presence of a project manager to coordinate the project should accelerate the completion of the project. In practice, decision making can get bogged down as agreements have to be forged across multiple functional groups. This is especially true for the balanced matrix.

When the three variant forms of the matrix approach are considered, we can see that advantages and disadvantages are not necessarily true for all three forms of matrix. The Strong matrix is likely to enhance project integration, diminish internal power struggles, and ultimately improve control of project activities and costs. On the downside, technical quality may suffer because functional areas have less control over their contributions. Finally, projectitis may emerge as the members develop a strong team identity. The Weak matrix is likely to improve technical quality as well as provide a better system for managing conflict across projects because the functional manager assigns personnel to different projects. The problem is that functional control is often main- tained at the expense of poor project integration. The Balanced matrix can achieve

Chapter 3 Organization: Structure and Culture 79

better balance between technical and project requirements, but it is a very delicate system to manage and is more likely to succumb to many of the problems associated with the matrix approach.

3.2 What Is the Right Project Management Structure? There is empirical evidence that project success is directly linked to the amount of autonomy and authority project managers have over their projects (Gray et al., 1990; Larson & Gobeli, 1988; Larson & Gobeli, 1987). However, most of this research is based on what is best for managing specific projects. It is important to remember what was stated in the beginning of the chapter—that the best system balances the needs of the project with those of the parent organization. So what project structure should an organization use? This is a complicated question with no precise answers. A number of issues need to be considered at both the organization and project level.

Organization Considerations At the organization level, the first question that needs to be asked is how important is project management to the success of the firm? What percentage of core work involves projects? If over 75 percent of work involves projects, then an organization should consider a fully projectized organization. If an organization has both standard products and projects, then a matrix arrangement would appear to be appropriate. If an organi- zation has very few projects, then a less formal arrangement is probably all that is required. Dedicated teams could be created on an as-needed basis and the organization could outsource project work. A second key question is resource availability. Remember, matrix evolved out of the necessity to share resources across multiple projects and functional domains while at the same time creating legitimate project leadership. For organizations that cannot afford to tie up critical personnel on individual projects, a matrix system would appear to be appropriate. An alternative would be to create a dedicated team but outsource project work when resources are not available internally. Within the context of the first two questions, an organization needs to assess current practices and what changes are needed to more effectively manage projects. A strong project matrix is not installed overnight. The shift toward a greater emphasis on proj- ects has a host of political implications that need to be worked through, requiring time and strong leadership. For example, we have observed many companies that make the transition from a functional organization to a matrix organization begin with a weak functional matrix. This is due in part to resistance by functional and department man- agers toward transferring authority to project managers. With time, these matrix struc- tures eventually evolve into a project matrix. Many organizations have created Project Management Offices to support project management efforts. See Snapshot from Prac- tice 3.3: POs: Project Offices.

Project Considerations At the project level, the question is how much autonomy the project needs in order to be successfully completed. Hobbs and Ménard (1993) identify seven factors that should influence the choice of project management structure: ∙ Size of project. ∙ Strategic importance.

Understand organiza- tional and project con- siderations that should be considered in choos- ing an appropriate proj- ect management structure.

3-3LO

80 Chapter 3 Organization: Structure and Culture

Project offices (POs) were originally developed as a response to the poor track record many companies had in completing projects on time, within budget, and according to plan. They

were often established to help matrix systems mature into more effective project delivery platforms. Today, POs come in many different shapes and forms. One interesting way of classifying POs was set forth by Casey and Peck, who describe certain POs in terms of being (1) a weather station, (2) a control tower, or (3) a resource pool. Each of these models performs a very different function for its organization.

Weather Station. The primary function of the weather station PO is to track and monitor project performance. It is typically created to satisfy top management’s need to stay on top of the portfolio of projects under way in the firm. Staff provides an independent forecast of project performance. The questions answered for specific projects include:

How are our projects progressing? Which ones are on track? Which ones are not?

S N A P S H O T F R O M P R A C T I C E 3 . 3 POs: Project Offices*

How are we doing in terms of cost? Which proj- ects are over or under budget?

What are the major problems confronting proj- ects? Are contingency plans in place? What can the organization do to help the project?

Control Tower. The primary function of the control tower PO is to improve project execution. It consid- ers project management as a profession to be pro- tected and advanced. Staff at the PO identify best practices and standards for project management ex- cellence. They work as consultants and trainers to support project managers and their teams.

Resource Pool. The goal of the resource pool PO is to provide the organization with a cadre of trained project managers and professionals. It operates like an academy for continually upgrading the skills of a firm’s project professionals. In addition to training, this kind of PO also serves to elevate the stature of project management within the organization.

* W. Casey and W. Peck, “Choosing the Right PMO Setup,” PM Network, vol. 15, no. 2 (2001), pp. 40–47.

∙ Novelty and need for innovation. ∙ Need for integration (number of departments involved). ∙ Environmental complexity (number of external interfaces). ∙ Budget and time constraints. ∙ Stability of resource requirements. The higher the levels of these seven factors, the more autonomy and authority the project manager and project team need to be successful.1 This translates into using either a dedi- cated project team or a project matrix structure. For example, these structures should be used for large projects that are strategically critical and are new to the company, thus requiring much innovation. These structures would also be appropriate for complex, multidisciplinary projects that require input from many departments, as well as for proj- ects that require constant contact with customers to assess their expectations. Dedicated project teams should also be used for urgent projects in which the nature of the work requires people working steadily from beginning to end. Many firms that are heavily involved in project management have created a flexible management system that organizes projects according to project requirements. For example, Chaparral Steel, a mini-mill that produces steel bars and beams from scrap

1 For a more sophisticated discussion of contingency factors related to managing specific projects see: A. J. Shenhar and D. Dvir, Reinventing Project Management: The Diamond Approach to Successful Growth and Innovation (Boston: Harvard Press, 2007).

Chapter 3 Organization: Structure and Culture 81

metal, classifies projects into three categories: advanced development, platform, and incremental. Advanced development projects are high-risk endeavors involving the creation of a breakthrough product or process. Platform projects are medium-risk proj- ects involving system upgrades that yield new products and processes. Incremental projects are low-risk, short-term projects that involve minor adjustments in existing products and processes. At any point in time, Chaparral might have 40–50 projects under way, of which only one or two are advanced, three to five are platform projects, and the remainder are small, incremental projects. The incremental projects are almost all done within a weak matrix with the project manager coordinating the work of func- tional subgroups. A strong matrix is used to complete the platform projects, while dedicated project teams are typically created to complete the advanced development projects. More and more companies are using this “mix and match” approach to managing projects.

3.3 Organizational Culture The decision for combining a discussion of project management structures and orga- nizational cultures in this chapter can be traced to a conversation we, the authors, had with two project managers who work for a medium-sized information technology firm. The managers were developing a new operating platform that would be critical to the future success of their company. When they tried to describe how this project was organized, one manager began to sketch out on a napkin a complicated structure involving 52 different teams, each with a project leader and a technical leader! In response to our further probing to understand how this system worked, the manager stopped short and proclaimed, “The key to making this structure work is the culture in our company. This approach would never work at company Y, where I worked before. But because of our culture here we are able to pull it off.” This comment, our observations of other firms, and research suggest there is a strong connection between project management structure, organizational culture, and project success.2 We have observed organizations successfully manage projects within the traditional functional organization because the culture encouraged cross-functional integration. Conversely we have seen matrix structures break down because the culture of the organization did not support the division of authority between project managers and functional managers. We have also observed companies relying on independent project teams because the dominant culture would not support the innovation and speed necessary for success.

What Is Organizational Culture? Organizational culture refers to a system of shared norms, beliefs, values, and assumptions which binds people together, thereby creating shared meanings (Deal & Kennedy, 1982). This system is manifested by customs and habits that exemplify the values and beliefs of the organization. For example, egalitarianism may be expressed in the informal dress worn at a high-tech firm. Conversely, mandated uniforms at a department store reinforce respect for the hierarchy.

Appreciate the signifi- cant role that organiza- tional culture plays in managing projects.

3-4LO

Interpret the culture of an organization.

3-5LO

2 See, for example: Kerzner, H., In Search of Excellence in Project Management (New York: Von Nostrand Reinhold, 1997); Yazici, H. “The Role of Project Management Maturity and Organizational Culture in Perceived Performance”, Project Man- agement Journal, 2009.

82 Chapter 3 Organization: Structure and Culture

Culture reflects the personality of the organization and, similar to an individual’s personality, can enable us to predict attitudes and behaviors of organizational mem- bers. Culture is also one of the defining aspects of an organization that sets it apart from other organizations even in the same industry. Research suggests that there are 10 primary characteristics which, in aggregate, capture the essence of an organization’s culture:3

1. Member identity—the degree to which employees identify with the organization as a whole rather than with their type of job or field of professional expertise.

2. Team emphasis—the degree to which work activities are organized around groups rather than individuals.

3. Management focus—the degree to which management decisions take into account the effect of outcomes on people within the organization.

4. Unit integration—the degree to which units within the organization are encour- aged to operate in a coordinated or interdependent manner.

5. Control—the degree to which rules, policies, and direct supervision are used to oversee and control employee behavior.

6. Risk tolerance—the degree to which employees are encouraged to be aggressive, innovative, and risk seeking.

7. Reward criteria—the degree to which rewards such as promotion and salary increases are allocated according to employee performance rather than seniority, favoritism, or other nonperformance factors.

8. Conflict tolerance—the degree to which employees are encouraged to air con- flicts and criticisms openly.

9. Means versus end orientation—the degree to which management focuses on out- comes rather than on techniques and processes used to achieve those results.

10. Open-systems focus—the degree to which the organization monitors and responds to changes in the external environment.

As shown in Figure 3.5, each of these dimensions exists on a continuum. Assessing an organization according to these 10 dimensions provides a composite picture of the organization’s culture. This picture becomes the basis for feelings of shared under- standing that the members have about the organization, how things are done, and the way members are supposed to behave. Culture performs several important functions in organizations. An organization’s culture provides a sense of identity for its members. The more clearly an organiza- tion’s shared perceptions and values are stated, the more strongly people can iden- tify with their organization and feel a vital part of it. Identity generates commitment to the organization and reasons for members to devote energy and loyalty to the organization. A second important function is that culture helps legitimize the management sys- tem of the organization. Culture helps clarify authority relationships. It provides reasons why people are in a position of authority and why their authority should be respected.

3 Harrison, M. T., and J. M. Beyer, The Culture of Organizations (Englewood Cliffs, NJ: Prentice Hall, 1993); O’Reilly, C. A., J. Chatman, and D. F. Caldwell, “People and Organizational Culture: A Profile Comparison Approach to Assessing Person- Organization Fit,” Academy of Management Journal, vol. 34, no. 3 (September 1991), pp. 487–516; and Schein, E., Organi- zational Culture and Leadership: A Dynamic View (San Francisco, CA: Jossey-Bass, 2010).

Chapter 3 Organization: Structure and Culture 83

Most importantly, organizational culture clarifies and reinforces standards of behavior. Culture helps define what is permissible and inappropriate behavior. These standards span a wide range of behavior from dress code and working hours to chal- lenging the judgment of superiors and collaborating with other departments. Ulti- mately, culture helps create social order within an organization. Imagine what it would be like if members didn’t share similar beliefs, values, and assumptions—chaos! The customs, norms, and ideals conveyed by the culture of an organization provide the stability and predictability in behavior that is essential for an effective organization. See Snapshot from Practice 3.4: Google-y for an example of this. Although our discussion of organizational culture may appear to suggest one cul- ture dominates the entire organization, in reality this is rarely the case. “Strong” or “thick” are adjectives used to denote a culture in which the organization’s core values and customs are widely shared within the entire organization. Conversely, a “thin” or “weak” culture is one that is not widely shared or practiced within a firm. Even within a strong organizational culture, there are likely to be subcultures often aligned within specific departments or specialty areas. As noted earlier in our discus- sion of project management structures, it is not uncommon for norms, values, and customs to develop within a specific field or profession such as marketing, finance, or operations. People working in the marketing department may have a different set of norms and values than those working in finance. Countercultures sometimes emerge within organizations that embody a different set of values, beliefs, and customs—often in direct contradiction with the culture espoused by top management. How pervasive these subcultures and countercultures are affects the strength of the culture of the organization and the extent to which culture influ- ences members’ actions and responses.

Identifying Cultural Characteristics Deciphering an organization’s culture is a highly interpretative, subjective process that requires assessment of both current and past history. The student of culture cannot

Job

Individual

Task

Independent

Loose

Low

Performance

Low

Means

Internal

1. Member identity

2. Team emphasis

3. Management focus

4. Unit integration

5. Control

6. Risk tolerance

7. Reward criteria

8. Conflict tolerance

9. Means-ends orientation

10. Open-system focus

Organization

Group

People

Interdependent

Tight

High

Other

High

Ends

External

FIGURE 3.5 Key Dimensions Defining an Organization’s Culture

84 Chapter 3 Organization: Structure and Culture

In 2016 Google Inc. topped Fortune magazine’s list of best companies to work at for the seventh time in the past ten years. When one enters the 24-hour Googleplex located in

Mountain View, California, you feel that you are walking through a new-age college campus rather than the corporate office of a billion-dollar business. The collection of interconnected low-rise buildings with colorful, glass-encased offices feature upscale trappings—free gourmet meals three times a day, free use of an outdoor wave pool, indoor gym and large child care facility, private shuttle bus service to and from San Francisco and other residential areas— that are the envy of workers across the Bay area. These perks and others reflect Google’s culture of keeping people happy and thinking in unconven- tional ways. The importance of corporate culture is no more evi- dent than in the fact that the head of Human Resources, Stacy Savides Sullivan, also has the title of Chief Cul- ture Officer. Her task is to try to preserve the innovative culture of a start-up as Google quickly evolves into a mammoth international corporation. Sullivan character- izes Google culture as “team-oriented, very collabora- tive and encouraging people to think nontraditionally, different from where they ever worked before—work with integrity and for the good of the company and for the good of the world, which is tied to our overall mis- sion of making information accessible to the world.” Google goes to great lengths to screen new employees to not only make sure that they have outstanding tech- nical capabilities but also that they are going to fit Google’s culture. Sullivan goes on to define a Google-y employee as somebody who is “flexible, adaptable, and not focusing on titles and hierarchy, and just gets stuff done.” Google’s culture is rich with customs and traditions not found in corporate America. For example, project

S N A P S H O T F R O M P R A C T I C E 3 . 4 Google-y*

teams typically have daily “stand-up” meetings seven min- utes after the hour. Why seven minutes after the hour? Because Google cofounder Sergey Brin once estimated that it took seven minutes to walk across the Google cam- pus. Everybody stands to make sure no one gets too com- fortable and no time is wasted during the rapid-fire update. As one manager noted, “The whole concept of the stand-up is to talk through what everyone’s doing, so if someone is working on what you’re working on, you can discover and collaborate not duplicate.” Another custom is “dogfooding.” This is when a project team releases the functional prototype of a future product to Google employees for them to test drive. There is a strong norm within Google to test new products and provide feedback to the developers. The project team receives feedback from thousands of Google-ys. The internal focus group can log bugs or simply comment on design or functionality. Fellow Google-ys do not hold back on their feedback and are quick to point out things they don’t like. This often leads to significant product improvements.

© Caiaimage/Glow Images

simply rely on what people report about their culture. The physical environment in which people work, as well as how people act and respond to different events that occur, must be examined. Figure 3.6 contains a worksheet for diagnosing the culture of an organization. Although by no means exhaustive, the checklist often yields clues about the norms, customs, and values of an organization: 1. Study the physical characteristics of an organization. What does the external

architecture look like? What image does it convey? Is it unique? Are the buildings

* Walters, H., “How Google Got Its New Look,” BusinessWeek, May 10, 2010; Goo, S. K., “Building a ‘Googley’ Workforce,“ Washington Post, October 21, 2006; Mills, E., “Meet Google’s Culture Czar,” CNET News.com, April 27, 2007.

Chapter 3 Organization: Structure and Culture 85

and offices the same quality for all employees? Or are modern buildings and fancier offices reserved for senior executives or managers from a specific department? What are the customs concerning dress? What symbols does the organization use to signal authority and status within the organization? These physical characteristics can shed light on who has real power within the organization, the extent to which the organization is internally differentiated, and how formal the organization is in its business dealings.

2. Read about the organization. Examine annual reports, mission statements, press releases, and internal newsletters. What do they describe? What principles are espoused in these documents? Do the reports emphasize the people who work for the organization and what they do or the financial performance of the firm? Each emphasis reflects a different culture. The first demonstrates concern for the people who make up the company. The second may suggest a concern for results and the bottom line.

3. Observe how people interact within the organization. What is their pace—is it slow and methodical or urgent and spontaneous? What rituals exist within the orga- nization? What values do they express? Meetings can often yield insightful infor- mation. Who are the people at the meetings? Who does the talking? To whom do they talk? How candid is the conversation? Do people speak for the organization or for the individual department? What is the focus of the meetings? How much time is spent on various issues? Issues that are discussed repeatedly and at length are clues about the values of the organization’s culture.

FIGURE 3.6 Organizational Culture Diagnosis Worksheet

Power Corp.

I. Physical Characteristics: Architecture, office layout, décor, attire

Corporate HQ is 20 story modern building—president on top floor. Offices are bigger in the top floors than lower floors. Formal business attire (white shirts, ties, power suits, . . . ). Power appears to increase the higher up you are.

II. Public Documents: Annual reports, internal newsletters, vision statements

At the heart of the Power Corp. way is our vision . . . to be the global energy company most admired for its people, partnership, and performance.

Integrity. We are honest with others and ourselves. We meet the highest ethical standards in all busi- ness dealings. We do what we say we will do.

III. Behavior: Pace, language, meetings, issues discussed, decision-making style, communication patterns, rituals

Hierarchical decision making, pace brisk but orderly, meetings start on time and end on time, subordi- nates choose their words very carefully when talking to superiors, people rarely work past 6:00 p.m., president takes top performing unit on a boat cruise each year . . .

IV. Folklore: Stories, anecdotes, heroines, heroes, villains

Young project manager was fired after going over his boss’s head to ask for additional funds.

Stephanie C. considered a hero for taking complete responsibility for a technical error.

Jack S. was labeled a traitor for joining chief competitor after working for Power Corp. for 15 years.

86 Chapter 3 Organization: Structure and Culture

4. Interpret stories and folklore surrounding the organization. Look for similari- ties among stories told by different people. The subjects highlighted in recurring stories often reflect what is important to an organization’s culture. For example, many of the stories that are repeated at Versatec, a Xerox subsidiary that makes graphic plotters for computers, involve their flamboyant cofounder, Renn Zaphi- ropoulos. According to company folklore, one of the very first things Renn did when the company was formed was to assemble the top management team at his home. They then devoted the weekend to handmaking a beautiful teak conference table around which all future decisions would be made. This table came to symbol- ize the importance of teamwork and maintaining high standards of performance, two essential qualities of the culture at Versatec. Try to identify who the heroes and villains are in company folklore. What do they suggest about the culture’s ideals? Returning to the Versatec story, when the company was eventually purchased by Xerox many employees expressed concern that Versatec’s informal, play hard/ work hard culture would be overwhelmed by the bureaucracy at Xerox. Renn rallied the employees to superior levels of performance by arguing that if they exceeded Xerox’s expectations they would be left alone. Autonomy has remained a fixture of Versatec’s culture long after Renn’s retirement.

It is also important to pay close attention to the basis for promotions and rewards. What do people see as the keys to getting ahead within the organization? What con- tributes to downfalls? These last two questions can yield important insights into the qualities and behaviors which the organization honors as well as the cultural taboos and behavioral land mines that can derail a career. For example, one project man- ager confided that a former colleague was sent to project management purgatory soon after publicly questioning the validity of a marketing report. From that point on, the project manager was extra careful to privately consult the marketing depart- ment whenever she had questions about their data.

With practice an observer can assess how strong the dominant culture of an organiza- tion is and the significance of subcultures and countercultures. Furthermore, learners can discern and identify where the culture of an organization stands on the 10 cultural dimensions presented earlier and, in essence, begin to build a cultural profile for a firm. Based on this profile, conclusions can be drawn about specific customs and norms that need to be adhered to as well as those behaviors and actions that violate the norms of a firm.

3.4 Implications of Organizational Culture for Organizing Projects Project managers have to be able to operate in several, potentially diverse, organiza- tional cultures. First, they have to interact with the culture of their parent organization as well as the subcultures of various departments (e.g., marketing, accounting). Sec- ond, they have to interact with the project’s client or customer organizations. Finally, they have to interact in varying degrees with a host of other organizations connected to the project. These organizations include suppliers and vendors, subcontractors, con- sulting firms, government and regulatory agencies, and, in many cases, community groups. Many of these organizations are likely to have very different cultures. Project managers have to be able to read and speak the culture they are working in to develop strategies, plans, and responses that are likely to be understood and accepted. Still, the emphasis of this chapter is on the relationship between organizational culture and proj- ect management structure, and it is necessary to defer further discussion of these

Understand the interac- tion between project management structure and the culture of an organization.

3-6LO

Chapter 3 Organization: Structure and Culture 87

implications until Chapters 10–12, which focus on leadership, team building, and outsourcing. Earlier we stated that we believe there are strong relationships among project man- agement structure, organizational culture, and successful project management. To explore these relationships further, let us return to the dimensions that can be used to characterize the culture of an organization. When examining these dimensions we could hypothesize that certain aspects of the culture of an organization would support successful project management while other aspects would deter or interfere with effec- tive management. Figure 3.7 attempts to identify which cultural characteristics create an environment conducive to completing most complex projects involving people from different disciplines. Note that, in many cases, the ideal culture is not at either extreme. For example, a fertile project culture would likely be one in which management balances its focus on the needs of both the task and the people. An optimal culture would balance con- cern with output (ends) and processes to achieve those outcomes (means). In other cases, the ideal culture would be on one end of a dimension or the other. For exam- ple, because most projects require collaboration across disciplines, it would be desir- able that the culture of the organization emphasize working in teams and identifying with the organization, not just the professional domain. Likewise, it is important that the culture support a certain degree of risk taking and a tolerance for constructive conflict. One organization that appears to fit this ideal profile is 3M. 3M has received acclaim for creating an entrepreneurial culture within a large corporate framework. The essence of its culture is captured in phrases that have been chanted often by 3Mers throughout its history: “Encourage experimental doodling.” “Hire good people and leave them alone.” “If you put fences around people, you get sheep. Give people the room they need.” Freedom and autonomy to experiment are reflected in the “15 per- cent rule,” which encourages technical people to spend up to 15 percent of their time on projects of their own choosing and initiative. This fertile culture has contributed to

Job

Individual

Task

Independent

Loose

Low

Performance

Low

Means

Internal

1. Member identity

2. Team emphasis

3. People focus

4. Unit integration

5. Control

6. Risk tolerance

7. Reward criteria

8. Conflict tolerance

9. Means-ends orientation

10. Open-system focus

Organization

Group

People

Interdependent

Tight

High

Other

High

Ends

External

FIGURE 3.7 Cultural Dimensions of an Organization Supportive of Project Management

88 Chapter 3 Organization: Structure and Culture

3M’s branching out into more than 60,000 products and 35 separate business units (Collins & Porras, 1994). The metaphor we choose to describe the relationship between organizational culture and project management is that of a riverboat trip. Culture is the river and the project is the boat. Organizing and completing projects within an organization in which the culture is conducive to project management is like paddling downstream: much less effort is required. In many cases, the current can be so strong that steering is all that is required. Such is the case for projects that operate in a project-friendly environment where teamwork and cross-functional cooperation are the norms, where there is a deep commitment to excellence, and where healthy conflict is voiced and dealt with quickly and effectively. Conversely, trying to complete a project in a toxic culture is like paddling upstream: much more time, effort, and attention are needed to reach the destination. This would be the situation in cultures that discourage teamwork and cooperation, that have a low tolerance for conflict, and where getting ahead is based less on performance and more on cultivating favorable relationships with superiors. In such cases, the project man- ager and her people not only have to overcome the natural obstacles of the project but also have to overcome the prevailing negative forces inherent in the culture of the organization. The implications of this metaphor are important. Greater project authority and time are necessary to complete projects that encounter a strong, negative cultural current. Conversely, less formal authority and fewer dedicated resources are needed to com- plete projects in which the cultural currents generate behavior and cooperation essen- tial to project success. The key issue is the degree of interdependency between the parent organization and the project team. In cases where the prevalent organizational culture supports the behaviors essential to project completion, a weaker, more flexible project management structure can be effective. For example, one of the major reasons Chaparral Steel is able to use a functional matrix to successfully complete incremental projects is that its culture contains strong norms for cooperation (Bowen et al., 1994). See Research Highlight 3.1: The Secret of Success for another example of how culture supports suc- cessful project management. When the dominant organizational culture inhibits collaboration and innovation, it is advisable to insulate the project team from the dominant culture. Here it becomes necessary to create a self-sufficient project team. If a dedicated project team is impossible because of resource constraints, then at least a project matrix should be used where the project manager has dominant control over the project. In both cases, the managerial strategy is to create a distinct team subculture in which a new set of norms, customs, and values evolves that will be conducive to project completion. Under extreme circumstances this project culture could even represent a countercul- ture in that many of the norms and values are the antithesis of the dominant, parent culture. Such was the case when IBM decided to develop their personal computer quickly in 1980 (Smith & Reinertsen, 1995). They knew that the project could get bogged down by the overabundance of computer knowledge and bureaucracy in the company. They also realized that they would have to work closely with suppliers and make use of many non-IBM parts if they were to get to the market quickly. This was not the IBM way at the time, so IBM established the PC project team in a warehouse in Boca Raton, Florida, far from corporate headquarters and other corporate develop- ment facilities that existed within the organization.

In The Secret of Success: The Dou- ble Helix of Formal and Informal Structures in an R&D Laboratory Polly Rizova revealed the results of a year-long investigation into the in-

ner workings of a Fortune 500 R&D Lab. Through interviews with key participants and analysis of social networking data, Rizova assessed the efficacy of six high-tech development projects. Four critical success factors emerged from her research. One element that is crucial to success is a heavy reliance on open and unrestricted patterns of communication, coupled with a low degree of formal reporting. In other words, team members freely interacted with each other regardless of title, experience, or discipline. A second key is having individuals on the project who are highly respected across the laboratory for their exceptional technical skills and experience. Similarly, it is also vital to have individuals involved in the project who are highly respected for their organizational expertise and experience. Having both “technical stars” and “organizational stars” on the project team was es- sential to success. The final factor is a strong and sustained support for the project from the compa- ny’s corporate management. What’s more, her analysis revealed the interactive nature of the four conditions, namely, that no one condition was likely to produce successful outcomes on its own, but only when put together in a way in which they reinforce each other. Here the culture of the labo- ratory was seen as the key catalyst. Rizova describes a matrix system in which peo- ple work on multiple projects simultaneously but

with a different wrinkle. Individuals occupy differ- ent positions and play different roles depending upon the project. For example, it is common for a senior engineer to be the manager of one project and a researcher on another that is led by his or her subordinate. In essence one must “boss” his or her own boss. At first glance this formal structure should create destructive tensions. However, Rizova argues that the organizational culture of the lab is the glue that keeps things running smoothly. She describes a culture in which the social norms of cooperation, respect, and civility are up- held and reproduced. It is a culture characterized by trust and a strong drive toward superior individ- ual and organizational learning and achievement. The culture is captured in the comments of researchers:

That is one of the nicest things around here. Your opinions are listened to. Superiors consider our advice. You will find that most of the projects here are a team effort.

What I like most is the positive thinking and the “whatever it takes” attitude. Per- sonality conflicts can be devastating. Here everyone helps you and supports you. There is no “I” in the word team.

Very friendly environment. . . . I met new people and learned a lot from them. They do not mind sharing their expertise.

Research Highlight 3.1 The Secret of Success*

* Polly S. Rizova, The Secret of Success: The Double Helix of Formal and Informal Structures in an R&D Laboratory (Stan- ford, CA: Stanford University Press, 2007).

Summary This chapter examined two major characteristics of the parent organization that affect the implementation and completion of projects. The first is the formal structure of the organization and how it chooses to organize and manage projects. Although the indi- vidual project manager may have very little say as to how the firm chooses to manage projects, he or she must be able to recognize the options available as well as the inher- ent strengths and weaknesses of different approaches. Three basic project management structures were described and assessed as to their weaknesses and strengths. Only under unique circumstances can a case be made for managing a project within the normal functional hierarchy. When thinking only in terms of what is best for the project, the creation of an independent project team is clearly favored. However, the most effective project management system appropriately balances the needs of the project with those of the parent organization. Matrix

89

90 Chapter 3 Organization: Structure and Culture

structures emerged out of the parent organization’s need to share personnel and re- sources across multiple projects and operations while creating legitimate project focus. The matrix approach is a hybrid organizational form that combines elements of both the functional and project team forms in an attempt to realize the advantages of both. The second major characteristic of the parent organization that was discussed in this chapter is the concept of organizational culture. Organizational culture is the pattern of beliefs and expectations shared by an organization’s members. Culture includes the be- havioral norms, customs, shared values, and the “rules of the game” for getting along and getting ahead within the organization. It is important for project managers to be “culture sensitive” so that they can develop appropriate strategies and responses and avoid violat- ing key norms that would jeopardize their effectiveness within the organization. The interaction between project management structure and organizational culture is a complicated one. We have suggested that in certain organizations, culture encourages the implementation of projects. In this environment the project management structure used plays a less decisive role in the success of the project. Conversely, for other orga- nizations in which the culture stresses internal competition and differentiation, just the opposite may be true. The prevailing norms, customs, and attitudes inhibit effective project management, and the project management structure plays a more decisive role in the successful implementation of projects. At a minimum, under adverse cultural conditions, the project manager needs to have significant authority over the project team; under more extreme conditions firms should physically relocate dedicated proj- ect teams to complete critical projects. In both cases, the managerial strategy should be insulate project work from the dominant culture so that a more positive “subculture” can emerge among project participants. The project management structure of the organization and the culture of the organi- zation are major elements of the environment in which a project is initiated. Subse- quent chapters will examine how project managers and professionals work within this environment to successfully complete projects.

Key Terms Balanced matrix, 76 Dedicated project team, 71 Matrix, 75

Organizational culture, 81 Projectitis, 74 Projectized organization, 72

Project office, 80 Strong matrix, 77 Weak matrix, 76

1. What are the relative advantages and disadvantages of the functional, matrix, and dedicated team approaches to managing projects?

2. What distinguishes a weak matrix from a strong matrix? 3. Under what conditions would it be advisable to use a strong matrix instead of a

dedicated project team? 4. How can project management offices (POs) support effective project

management? 5. Why is it important to assess the culture of an organization before deciding what

project management structure should be used to complete a project? 6. Other than culture, what other organizational factors should be used to determine

which project management structure should be used? 7. What do you believe is more important for successfully completing a project—the

formal project management structure or the culture of the parent organization?

Review Questions

Chapter 3 Organization: Structure and Culture 91

1. Going to college is analogous to working in a matrix environment in that most stu- dents take more than one class and must distribute their time across multiple classes. What problems does this situation create for you? How does it affect your performance? How could the system be better managed to make your life less dif- ficult and more productive?

2. You work for LL Company, which manufactures high-end optical scopes for hunt- ing rifles. LL Company has been the market leader for the past 20 years and has decided to diversify by applying its technology to develop a top-quality binocular. What kind of project management structure would you recommend they use for this project? What information would you like to have to make this recommendation, and why?

3. You work for Barbata Electronics. Your R&D people believe they have come up with an affordable technology that will double the capacity of existing MP3 players and use audio format that is superior to MP3. The project is code named KYSO (Knock Your Socks Off). What kind of project management structure would you recommend they use for the KYSO project? What information would you like to have to make this recommendation and why?

4. This chapter discussed the role of values and beliefs in forming an organization’s culture. The topic of organizational culture is big business on the Internet. Many companies use their Web pages to describe their mission, vision, and corporate values and beliefs. There also are many consulting firms that advertise how they help organizations to change their culture. The purpose of this exercise is for you to obtain information pertaining to the organizational culture for two different compa- nies. You can go about this task by very simply searching on the key words “orga- nizational culture” or “corporate vision and values.” This search will identify numerous companies for you to use to answer the following questions. You may want to select companies that you would like to work for in the future.

a. What are the espoused values and beliefs of the companies? b. Use the worksheet in Figure 3.6 to assess the Web page. What does the Web

page reveal about the culture of this organization? Would this culture be condu- cive to effective project management?

5. Use the cultural dimensions listed in Figure 3.5 to assess the culture of your school. Instead of employees, consider students, and instead of management, use faculty. For example, member identity refers to the degree to which students identify with the school as a whole rather than their major or option. Either as individuals or in small groups rate the culture of your school on the 10 dimensions.

a. What dimensions were easy to evaluate and which ones were not? b. How strong is the culture of your school? c. What functions does the culture serve for your school? d. Do you think the culture of your school is best suited to maximizing your learn-

ing? Why or why not? e. What kind of projects would be easy to implement in your school and what kind

of projects would be difficult given the structure and culture of your school? Explain your answer.

6. You work as an analyst in the marketing department for Springfield International (SI). SI uses a weak matrix to develop new services. Management has created an extremely competitive organizational culture that places an emphasis upon achieving results above everything else. One of the project managers that you have been assigned to

Exercises

92 Chapter 3 Organization: Structure and Culture

help has been pressuring you to make his project your number one priority. He also wants you to expand the scope of your work on his project beyond what your market- ing manager believes is necessary or appropriate. The project manager is widely per- ceived as a rising star within SI. Up to now you have been resisting the project manager’s pressure and complying with your marketing manager’s directives. How- ever, your most recent interchange with the project manager ended by his saying, “I’m not happy with the level of help I am getting from you and I will remember this when I become VP of Marketing.” How would you respond and why?

Block, T. R., and J. D. Frame, The Project Office—A Key to Managing Projects Effectively (Menlo Park, CA: Crisp Publications, 1998). Block, T. R., and J. D. Frame, “Today’s Project Office: Gauging Attitudes,” PM Net- work, August 2001. Bowen, H. K., K. B. Clark, C. A. Holloway, and S. C. Wheelwright, The Perpetual Enterprise Machine (New York: Oxford University Press, 1994). Brown, S., and K. R. Eisenhardt, “Product Development: Past Research, Present Findings, and Future Directions,” Academy of Management Review, vol. 20, no. 2 (1995), pp. 343–78. Cameron, K. S., and R. E. Quinn, Diagnosing and Changing Organizational Culture: Based on the Competing Values Framework (Upper Saddle River, NJ: Prentice Hall, 2011). Carlton, J., Apple: The Inside Story of Intrigue, Egomania, and Business Blunders (New York: Random House, 1997), pp. 13–14. Casey, W., and W. Peck, “Choosing the Right PMO Setup,” PM Network, vol. 15, no. 2 (2001), pp. 40–47. Collins, J. C., and J. I. Porras, Built to Last: The Successful Habits of Visionary Com- panies (New York: HarperCollins, 1994), pp. 150–58. Deal, T. E., and A. A. Kennedy, Corporate Cultures: The Rites and Rituals of Corpo- rate Life (Reading, MA: Addison-Wesley, 1982). De Laat, P. B., “Matrix Management of Projects and Power Struggles: A Case Study of an R&D Laboratory,” IEEE Engineering Management Review, Winter 1995. Filipczak, B., “Beyond the Gates of Microsoft,” Training, September 1992, pp. 37–44. Gallagher, R. S., The Soul of an Organization: Understanding the Values That Drive Successful Corporate Cultures (Chicago: Dearborn Trade Publishing, 2002). Graham, R. J., and R. L. Englund, Creating an Environment for Successful Projects: The Quest to Manage Project Management (San Francisco: Jossey-Bass, 1997). Gray, C., S. Dworatschek, D. H. Gobeli, H. Knoepfel, and E. W. Larson, “International Comparison of Project Organization Structures: Use and Effectiveness,” International Journal of Project Management, vol. 8, no. 1 (February 1990), pp. 26–32. Harrison, M. T., and J. M. Beyer, The Culture of Organizations (Englewood Cliffs, NJ: Prentice Hall, 1993).

References

Hobbs, B., and P. Ménard, “Organizational Choices for Project Management,” in Paul Dinsmore (ed.), The AMA Handbook of Project Management (New York: AMACOM, 1993). Hobday, M., “The Project-Based Organization: An Ideal Form for Managing Com- plex Products and Systems?” Research Policy, vol. 29, no. 17 (2000). Jassawalla, A. R., and H. C. Sashittal, “Cultures that Support Product-Innovation Pro- cesses,” Academy of Management Executive, vol. 15, no. 3 (2002), pp. 42–54. Johnson, C. L., M. Smith, and L. K. Geary, More Than My Share in All (Washington, D.C.: Smithsonian Institute Publications, 1990). Kerzner, H., In Search of Excellence in Project Management (New York: Von Nostrand Reinhold, 1997). Kerzner, H., “Strategic Planning for the Project Office,” Project Management Jour- nal, vol. 34, no. 2 (2003), pp. 13–25. Larson, E. W., “Project Management Structures” in The Wiley Handbook for Manag- ing Projects, P. Morris & J. Pinto (eds.) (New York: Wiley, 2004), pp. 48–66. Larson, E. W., and D. H. Gobeli, “Matrix Management: Contradictions and Insights,” California Management Review, vol. 29, no. 4 (Summer 1987), p. 137. Larson, E. W., and D. H. Gobeli, “Organizing for Product Development Projects,” Journal of Product Innovation Management, vol. 5 (1988), pp. 180–90. Larsson, U. (ed.), Cultures of Creativity: The Centennial Exhibition of the Nobel Prize (Canton, MA: Science History Publications, 2001). Laslo, Z., and A. I. Goldberg, “Matrix Structures and Performance: The Search for Optimal Adjustments to Organizational Objectives?” IEEE Transactions in Engineer- ing Management, vol. 48, no. 12 (2001). Lawrence, P. R., and J. W. Lorsch, Organization and Environment (Homewood, IL: Irwin, 1969). Majchrzak, A., and Q. Wang, “Breaking the Functional Mind-Set in Process Organi- zations,” Harvard Business Review, September–October 1996, pp. 93–99. Miller, J., Lockheed Martin’s Skunk Works (New York: Speciality Publications, 1996). Olson, E. M., O. C. Walker, Jr., and R. W. Ruekert, “Organizing for Effective New Product Development: The Moderating Role of Product Innovativeness,” Journal of Marketing, vol. 59 (January 1995), pp. 48–62. O’Reilly, C. A., J. Chatman, and D. F. Caldwell, “People and Organizational Culture: A Profile Comparison Approach to Assessing Person-Organization Fit,” Academy of Management Journal, vol. 34, no. 3 (September 1991), pp. 487–516. Pettegrew, A. M., “On Studying Organizational Culture,” Administrative Science Quarterly, vol. 24, no. 4 (1979), pp. 570–81. Powell, M., and J. Young, “The Project Management Support Office” in The Wiley Handbook for Managing Projects, P. Morris and J. Pinto (eds.) (New York: Wiley, 2004), pp. 937–69. Rebello, K., “Inside Microsoft,” Business Weekly, July 15, 1996, pp. 56–67.

Chapter 3 Organization: Structure and Culture 93

Rizova, P., The Secret of Success: The Double Helix of Formal and Informal Struc- tures in an R&D Laboratory (Stanford, CA: Stanford University Press, 2007). Schein, E., Organizational Culture and Leadership: A Dynamic View (San Francisco, CA: Jossey-Bass, 2010). Sculley, J., Odyssey: Pepsi to Apple . . . A Journey of Adventure, Ideas, and the Future (New York: Harper & Row, 1987), pp. 270–79. Shenhar, A. J., “From Theory to Practice: Toward a Typology of Project Management Styles,” IEEE Transactions in Engineering Management, vol. 41, no. 1 (1998), pp. 33–48. Shenhar, A. J., D. Dvir, T. Lechler, and M. Poli, “One Size Does Not Fit All—True for Projects, True for Frameworks,” Frontiers of Project Management Research and Application, Proceedings of PMI Research Conference, Seattle, 2002, pp. 99–106. Smith, P. G., and D. G. Reinertsen, Developing Products in Half the Time (New York: Van Nostrand Reinhold, 1995). Stuckenbruck, L. C., Implementation of Project Management (Upper Darby, PA: Project Management Institute, 1981). Yazici, H., “The Role of Project Management Maturity and Organizational Culture in Perceived Performance,” Project Management Journal, vol. 40, no. 3 (2009), pp. 14–33. Youker, R., “Organizational Alternatives for Project Management,” Project Manage- ment Quarterly, vol. 8 (March 1977), pp. 24–33.

Case 3.1

Moss and McAdams Accounting Firm Bruce Palmer had worked for Moss and McAdams (M&M) for six years and was just promoted to account manager. His first assignment was to lead an audit of Johnson- ville Trucks. He was quite pleased with the five accountants who had been assigned to his team, especially Zeke Olds. Olds was an Army vet who returned to school to get a double major in accounting and computer sciences. He was on top of the latest devel- opments in financial information systems and had a reputation for coming up with innovative solutions to problems. M&M was a well-established regional accounting firm with 160 employees located across six offices in Minnesota and Wisconsin. The main office, where Palmer worked, was in Green Bay, Wisconsin. In fact, one of the founding members, Seth Moss, played briefly for the hometown NFL Packers during the late 1950s. M&M’s primary ser- vices were corporate audits and tax preparation. Over the last two years the partners decided to move more aggressively into the consulting business. M&M projected that consulting would represent 40 percent of their growth over the next five years. M&M operated within a matrix structure. As new clients were recruited, a manager was assigned to the account. A manager might be assigned to several accounts, depend- ing on the size and scope of the work. This was especially true in the case of tax

94 Chapter 3 Organization: Structure and Culture

Chapter 3 Organization: Structure and Culture 95

preparation projects, where it was not uncommon for a manager to be assigned to 8 to 12 clients. Likewise, senior and staff accountants were assigned to multiple account teams. Ruby Sands was the office manager responsible for assigning personnel to dif- ferent accounts at the Green Bay office. She did her best to assign staff to multiple projects under the same manager. This wasn’t always possible, and sometimes accoun- tants had to work on projects led by different managers. M&M, like most accounting firms, had a tiered promotion system. New CPAs entered as junior or staff accountants. Within two years, their performance was reviewed and they were either asked to leave or promoted to senior accountant. Sometime during their fifth or sixth year, a decision was made to promote them to account manager. Finally, after 10 to 12 years with the firm, the manager was considered for promotion to partner. This was a very competitive position. During the last five years, only 20 per- cent of account managers at M&M had been promoted to partner. However, once a partner, they were virtually guaranteed the position for life and enjoyed significant increases in salary, benefits, and prestige. M&M had a reputation for being a results- driven organization; partner promotions were based on meeting deadlines, retaining clients, and generating revenue. The promotion team based its decision on the relative performance of the account manager in comparison to his or her cohorts. One week into the Johnsonville audit, Palmer received a call from Sands to visit her office. There he was introduced to Ken Crosby, who recently joined M&M after work- ing nine years for a Big 5 accounting firm. Crosby was recruited to manage special consulting projects. Sands reported that Crosby had just secured a major consulting project with Springfield Metals. This was a major coup for the firm: M&M had com- peted against two Big 5 accounting firms for the project. Sands went on to explain that she was working with Crosby to put together his team. Crosby insisted that Zeke Olds be assigned to his team. Sands told him that this would be impossible because Olds was already assigned to work on the Johnsonville audit. Crosby persisted, arguing that Olds’s expertise was essential to the Springfield project. Sands decided to work out a compromise and have Olds split time across both projects. At this time Crosby turned to Palmer and said, “I believe in keeping things simple. Why don’t we agree that Olds works for me in the mornings and you in the afternoons. I’m sure we can work out any problems that come up. After all, we both work for the same firm.”

SIX WEEKS LATER Palmer could scream whenever he remembered Crosby’s words, “After all, we both work for the same firm.” The first sign of trouble came during the first week of the new arrangement when Crosby called, begging to have Olds work all of Thursday on his project. They were conducting an extensive client visit, and Olds was critical to the assessment. After Palmer reluctantly agreed, Crosby said he owed him one. The next week when Palmer called Crosby to request that he return the favor, Crosby flatly refused and said any other time but not this week. Palmer tried again a week later and got the same response. At first Olds showed up promptly at 1:00 p.m. at Palmer’s office to work on the audit. Soon it became a habit to show up 30 to 60 minutes late. There was always a good rea- son. He was in a meeting in Springfield and couldn’t just leave, or an urgent task took longer than planned. One time it was because Crosby took his entire team out to lunch at the new Thai restaurant—Olds was over an hour late because of slow service. In the beginning Olds would usually make up the time by working after hours, but Palmer could tell from conversations he overheard that this was creating tension at home.

96 Chapter 3 Organization: Structure and Culture

What probably bothered Palmer the most were the e-mails and telephone calls Olds received from Crosby and his team members during the afternoons when he was sup- posed to be working for Palmer. A couple of times Palmer could have sworn that Olds was working on Crosby’s project in his (Palmer’s) office. Palmer met with Crosby to talk about the problem and voice his complaints. Crosby acted surprised and even a little bit hurt. He promised things would change, but the pattern continued. Palmer was becoming paranoid about Crosby. He knew that Crosby played golf with Olds on the weekends and could just imagine him badmouthing the Johnsonville project and pointing out how boring auditing work was. The sad fact was that there probably was some truth to what he was saying. The Johnsonville project was getting bogged down, and the team was slipping behind schedule. One of the contributing factors was Olds’s performance. His work was not up to its usual standards. Palmer approached Olds about this, and Olds became defensive. Olds later apologized and confided that he found it dif- ficult switching his thinking from consulting to auditing and then back to consulting. He promised to do better, and there was a slight improvement in his performance. The last straw came when Olds asked to leave work early on Friday so that he could take his wife and kids to a Milwaukee Brewers baseball game. It turned out Springfield Metals had given Crosby their corporate tickets, and he decided to treat his team with box seats right behind the Brewers dugout. Palmer hated to do it, but he had to refuse the request. He felt guilty when he overheard Olds explaining to his son on the tele- phone why they couldn’t go to the game. Palmer finally decided to pick up the phone and request an urgent meeting with Sands to resolve the problem. He got up enough nerve and put in the call only to be told that Sands wouldn’t be back in the office until next week. As he put the receiver down, he thought maybe things would get better.

TWO WEEKS LATER Sands showed up unexpectedly at Palmer’s office and said they needed to talk about Olds. Palmer was delighted, thinking that now he could tell her what had been going on. But before he had a chance to speak, Sands told him that Olds had come to see her yesterday. She told him that Olds confessed that he was having a hard time working on both Crosby’s and Palmer’s projects. He was having difficulty concentrating on the auditing work in the afternoon because he was thinking about some of the consulting issues that had emerged during the morning. He was putting in extra hours to try to meet both of the projects’ dead- lines, and this was creating problems at home. The bottom line was that he was stressed out and couldn’t deal with the situation. He asked that he be assigned full-time to Crosby’s project. Sands went on to say that Olds didn’t blame Palmer, in fact he had a lot of nice things to say about him. He just enjoyed the consulting work more and found it more chal- lenging. Sands concluded by saying, “I told him I understood, and I would talk to you about the situation and see what could be done. Frankly, I think we should pull him from your project and have him work full-time on Crosby’s project. What do you think?” 1. If you were Palmer at the end of the case, how would you respond? 2. What, if anything, could Palmer have done to avoid losing Olds? 3. What advantages and disadvantages of a matrix type organization are apparent from

this case? 4. What could the management at M&M do to more effectively manage situations

like this?

Chapter 3 Organization: Structure and Culture 97

Case 3.2

Horizon Consulting Patti Smith looked up at the bright blue Carolina sky before she entered the offices of Horizon Consulting. Today was Friday, which meant she needed to prepare for the weekly status report meeting. Horizon Consulting is a custom software development company that offers fully integrated mobile application services for iPhoneTM, AndroidTM, Windows Mobile® and BlackBerry® platforms. Horizon was founded by James Thrasher, a former marketing executive, who quickly saw the potential for digi- tal marketing via smartphones. Horizon enjoyed initial success in sports marketing, but quickly expanded to other industries. A key to their success was the decline in cost for developing smartphone applications, which expanded the client base. The decline in cost was primarily due to learning curve and ability to build customized solutions on established platforms. Patti Smith was a late bloomer who went back to college after working in the res- taurant business for nine years. She and her former husband had tried unsuccessfully to operate a vegetarian restaurant in Golden, Colorado. After her divorce, she returned to University of Colorado where she majored in Management Information Systems with a minor in Marketing. While she enjoyed her marketing classes much more than her MIS classes, she felt the IT know-how acquired would give her an advantage in the job market. This turned out to be true as Horizon hired her to be an Account Manager soon after graduation. Patti Smith was hired to replace Stephen Stills who had started the restaurant side of the business at Horizon. Stephen was “let go” according to one Account Manager for being a prima donna and hoarding resources. Patti’s clients ranged from high-end restaurants to hole-in-wall mom and pop shops. She helped develop smartphone apps that let users make reservations, browse menus, receive alerts on daily specials, pro- vide customer feedback, order take-out, and in some cases order delivery. As an Account Manager she worked with clients to assess their needs, develop a plan, and create customized smartphone apps. Horizon appeared to be a good fit for Patti. She had enough technical training to be able to work with software engineers and help guide them to produce client-ready products. At the same time she could relate to the restaurateurs and enjoyed working with them on web design and digital marketing. Horizon was organized into three departments: Sales, Software Development, and Graphics, with Account Managers acting as project managers. Account Managers gen- erally came from Sales, and would divide their time between projects and making sales pitches to potential new clients. Horizon employed a core group of software engineers and designers, supplemented by contracted programmers when needed. The first step in developing a smartphone application involved the Account Manager meeting with the client to define the requirements and vision for the application. The Account Manager would then work with a Graphic User Interface (GUI) designer to come up with a preliminary story board of how the application would function and look. Once the initial concept and requirements were approved the Account Manager was assigned two pairs of software engineers. The first pair (app engineers) would work on the smartphone side of the application while the second pair would work on the client side of the application. Horizon preferred to have software engineers work in tandem so they could check each other’s work. The two app engineers would typically work full

98 Chapter 3 Organization: Structure and Culture

time on the application until it was completed while the other engineers would work on multiple projects as needed. Likewise, GUI designers would work on the project at cer- tain key stages in the product development cycle when their expertise was needed. The head of Graphics managed the GUI designers’ schedule while the head of Soft- ware managed the software engineer assignments. At the end of each project Account Managers submitted performance reviews of their team. The Director of Sales was responsible for the Account Managers’ performance reviews based on customer satis- faction, generation of sales, and project performance. Horizon believed in iterative development, and every two to three weeks Account Managers were expected to demonstrate the latest version of applications to clients. This led to useful feedback and in many cases redefining the scope of the project. Often clients wanted to add more functionality to their application once they realized what the software could do. Depending upon the complexity of the application and changes introduced once the project was under way, it typically took Horizon two to four months to deliver a finished product to a client. Patti was currently working on three projects. One was for Shanghai Wok, a busy Chi- nese mom and pop restaurant located in downtown Charlotte, North Carolina. The owners of Shanghai Wok wanted Horizon to create a smartphone app that would allow customers to order and pay in advance for meals they would simply pick up at a walk-up window. The second project was for Taste of India that operated in Kannapolis, North Carolina. They wanted Horizon to create a phone app that would allow staff at the nearby bio-tech firms to order food that would be delivered on-site during lunch and dinner hours. The last project was for Nearly Normal, a vegetarian restaurant which wanted to send out e-mail alerts to subscribers that would describe in detail their daily fresh specials. James Thrasher was an admirer of Google and encouraged a playful but focused environment at work. Employees were allowed to decorate their work spaces, bring pets to work, and play ping-pong or pool when they needed a break. Horizon paid its employees well but the big payoff was the annual Christmas bonus. This bonus was based on overall company profits, which were distributed proportionately based on pay grade and performance reviews. It was not uncommon for employees to receive a 10–15 percent boost in pay at the end of the year.

STATUS REPORT MEETING As was her habit Patti entered the status report meeting room early. David Briggs was in the midst of describing the game-winning catch John Lorsch had made in last night’s softball game. Horizon sponsored a co-ed city league softball team which most of the Account Managers played on. Patti had been coaxed to play to ensure that the requisite number of “females” were on the field. She balked at the idea at first; softball wasn’t really her sport, but she was glad she did. Not only was it fun, but it gave her a chance to get to know the other managers. James Thrasher entered the room and everyone settled down to business. He started off as he always did by asking if anybody had important news to bring to everyone’s attention. Jackson Browne slowly raised his hand and said, “I am afraid I do. I just received notification from Apple IOS that they have rejected our TAT app.” TAT was a phone app that Jackson was the project lead on that allowed subscribers to reserve and see in real time what swimming lanes were available at a prestigious athletic club. This announcement was followed by a collective groan. Before an Apple app could go operational it had to be submitted and approved by Apple. Usually this was not a prob- lem, but lately Apple had been rejecting apps for a variety of reasons. Jackson went on

Chapter 3 Organization: Structure and Culture 99

to circulate the list of changes that had to be made before Apple would approve the app. The group studied the list, and in some cases ridiculed the new requirements. Ultimately, James Thrasher asked Jackson how long it would take to make the nec- essary changes and resubmit the app for approval. Jackson felt it would probably take two to three weeks at most. Thrasher asked who the engineers that worked on this project were. Patti’s heart fell. One of the app engineers who had developed the TAT app was working on her Shanghai Wok project. She knew what was going to happen next. Thrasher announced, “OK everyone, it only makes sense that these engineers are the best ones to finish what they had started so they are all going to have to be reas- signed back to the TAT project. Those affected are going to have to get together after this meeting and figure how you are going to replace them.” The meeting then pro- ceeded as planned with all the account managers reporting the status of their projects, and sharing relevant issues with the group.

POST-MEETING As everyone filed out, Patti looked around to see who else was in her same boat. There were three other Account Managers as well as Jackson Browne. Resource assignments were a reoccurring issue at Horizon given the nature of their work. Horizon had devel- oped a policy where decisions were made based on project priority. Each project was assigned a Green, Blue or Purple designation based on the company priority. Priority status was based on the extent the project contributed to the mission of the firm. The Shanghai Wok project given its limited size and scope was a Purple project, which was the lowest ranking. The list of available software engineers was displayed on the big screen. Patti was only familiar with a few of the names. Leigh Taylor who had the only Green project immediately selected Jason Wheeler from the list. She had used him before and was confident in his work. Tom Watson and Samantha Stewart both had Blue Projects and both needed to replace a mobile app engi- neer. They both immediately jumped on the name of Prem Mathew, claiming he was the best person for their project. After some friendly jousting, Tom said, “OK, Sam, you can have him; I remember when you helped me out on the Argos project; besides my project is just beginning. I’ll take Shin Chen.” Everyone looked at Patti; she started by saying, “You know, I am only familiar with a few of these names; I guess I’ll go with Mike Thu.” Jackson interjected, “Hey everyone, I am really sorry this happened, and I am sure Mike is a good programmer, but I recommend you work with Axel Gerthoff. I have used him before, and he is a very quick study and a joy to work with.” This was a relief to Patti and she quickly took his advice. They left to submit a report to Thrasher detailing the decisions they each had made and the impact on their projects. 1. How successful was the post-meeting? 2. What factors contributed to the success or failure of this meeting? 3. What kind of project management structure does Horizon use? Is it the right struc-

ture? Explain.

100

Defining the Project4 LEARNING OBJECTIVES After reading this chapter you should be able to:

4-1 Identify key elements of a project scope state- ment and understand why a complete scope statement is critical to project success.

4-2 Understand why it is important to establish project priorities in terms of cost, time, and performance.

4-3 Demonstrate the importance of a work break- down structure (WBS) to the management of proj- ects and how it serves as a data base for planning and control.

4-4 Demonstrate how the organization breakdown structure (OBS) establishes accountability to organizational units.

4-5 Describe a process breakdown structure (PBS) and when to use it.

4-6 Create responsibility matrices for small projects.

4-7 Create a communication plan for a project.

OUTLINE 4.1 Step 1: Defining the Project Scope

4.2 Step 2: Establishing Project Priorities

4.3 Step 3: Creating the Work Breakdown Structure

4.4 Step 4: Integrating the WBS with the Organization

4.5 Step 5: Coding the WBS for the Information System

4.6 Process Breakdown Structure

4.7 Responsibility Matrices

4.8 Project Communication Plan

Summary

C H A P T E R F O U R

101

Select a dream Use your dream to set a goal Create a plan Consider resources Enhance skills and abilities Spend time wisely Start! Get organized and go . . . it is one of those acro-whatevers, said Pooh.*

Project managers in charge of a single small project can plan and schedule the project tasks without much formal planning and information. However, when the project man- ager must manage several small projects or a large complex project, a threshold is quickly reached in which the project manager can no longer cope with the detail.

Project networks

6

Managing risk 7

Monitoring progress

13

Teams 11

Outsourcing 12

Project manager

10

Strategy 2

Introduction 1

Organization 3

Schedule resources & costs

8

Intern ation

al

proje cts

15

Agile PM 16

Project closure

14

Estimate 5

Reducing duration

9

Define project

4

* Roger E. Allen and Stephen D. Allen, Winnie-the-Pooh on Success (New York: Penguin, 1997), p. 10.

102 Chapter 4 Defining the Project

This chapter describes a disciplined, structured method for selectively collect- ing information to use through all phases of the project life cycle, to meet the needs of all stakeholders (e.g., customer, project manager), and to measure performance against the strategic plan of the organization. The method suggested is a selective outline of the project called the work breakdown structure. The early stages of developing the outline serve to ensure that all tasks are identified and that partici- pants of the project have an understanding of what is to be done. Once the outline and its detail are defined, an integrated information system can be developed to schedule work and allocate budgets. This baseline information is later used for control. In addition, the chapter presents a variant of the work breakdown structure called the process breakdown structure as well as responsibility matrices that are used for smaller, less complex projects. With the work of the project defined through the work breakdown structure, the chapter concludes with the process of creating a communica- tion plan used to help coordinate project activities and follow progress. The five generic steps described herein provide a structured approach for collect- ing the project information necessary for developing a work breakdown structure. These steps and the development of project networks found in the next chapters all take place concurrently, and several iterations are typically required to develop dates and budgets that can be used to manage the project. The old saying “We can control only what we have planned” is true; therefore, defining the project is the first step.

4.1 Step 1: Defining the Project Scope Defining the project scope sets the stage for developing a project plan. Project scope is a definition of the end result or mission of your project—a product or service for your client/customer. The primary purpose is to define as clearly as possible the deliverable(s) for the end user and to focus project plans. Research clearly shows that a poorly defined scope or mission is the most frequently mentioned barrier to project success. In a study involving more than 1,400 project managers in the United States and Canada, Gobeli and Larson (1990) found that approximately 50 percent of the planning problems relate to unclear definition of scope and goals. This and other studies suggest a strong correlation between project success and clear scope definition (Ashley et al., 1987; Pinto and Slevin, 1988; Standish Group, 2009). The scope document directs focus on the project purpose throughout the life of the project for the customer and project participants. The scope should be developed under the direction of the project manager, cus- tomer, and other significant stakeholders. The project manager is responsible for see- ing that there is agreement with the owner on project objectives, deliverables at each stage of the project, technical requirements, and so forth. For example, a deliverable in the early stage might be specifications; for the second stage, three prototypes for pro- duction; for the third, a sufficient quantity to introduce to market; and finally, market- ing promotion and training. Your project scope definition is a document that will be published and used by the project owner and project participants for planning and measuring project success. Scope describes what you expect to deliver to your customer when the project is com- plete. Your project scope should define the results to be achieved in specific, tangible, and measurable terms.

Identify key elements of a project scope state- ment and understand why a complete scope statement is critical to project success.

4-1LO

Chapter 4 Defining the Project 103

Employing a Project Scope Checklist Clearly, project scope is the keystone interlocking all elements of a project plan. To ensure that scope definition is complete, you may wish to use the following checklist:

Project Scope Checklist

1. Project objective 2. Deliverables 3. Milestones 4. Technical requirements 5. Limits and exclusions 6. Reviews with customer

1. Project objective. The first step of project scope definition is to define the overall objective to meet your customer’s need(s). For example, as a result of extensive market research a computer software company decides to develop a program that automatically translates verbal sentences in English to Russian. The project should be completed within three years at a cost not to exceed $1.5 million. Another exam- ple is to design and construct a portable, hazardous-waste thermal treatment system in 13 months at a cost not to exceed $13 million. The project objective answers the questions of what, when, how much, and at times, where.

2. Deliverables. The next step is to define major deliverables—the expected, measur- able outputs over the life of the project. For example, deliverables in the early design phase of a project might be a list of specifications. In the second phase deliverables could be software coding and a technical manual. The next phase could be the pro- totype. The final phase could be final tests and approved software. Note: Deliver- ables and requirements are often used interchangeably.

3. Milestones. A milestone is a significant event in a project that occurs at a point in time. The milestone schedule shows only major segments of work; it represents first, rough-cut estimates of time, cost, and resources for the project. The milestone schedule is built using the deliverables as a platform to identify major segments of work and an end date—for example, testing complete and finished by July 1 of the same year. Milestones should be natural, important control points in the project. Milestones should be easy for all project participants to recognize.

4. Technical requirements. More frequently than not, a product or service will have technical requirements to ensure proper performance. Technical requirements typi- cally clarify either the deliverables or define the performance specifications. For example, a technical requirement for a personal computer might be the ability to accept 120-volt alternating current or 240-volt direct current without any adapters or user switches. Another well-known example is the ability of 911 emergency sys- tems to identify the caller’s phone number and location of the phone. Examples from information systems projects include speed and capacity of database systems and connectivity with alternative systems. For understanding the importance of key requirements, see Snapshot from Practice 4.1: Big Bertha.

5. Limits and exclusions. The limits of scope should be defined. Failure to do so can lead to false expectations and to expending resources and time on the wrong problem. Examples of limits are: work on site is allowed only between the hours of 8:00 pm - 5:00 am; system maintenance and repair will be done only up to one month after final inspection; client will be billed for additional training beyond that

104 Chapter 4 Defining the Project

In 1991 Callaway Golf Equipment introduced their Big Bertha driver and revolutionized the golf equipment business. Big Bertha—named after the World War I Ger- man long-distance cannon—was much larger than con- ventional woods and lacked a hosel (the socket in the head of the club into which the shaft is inserted) so that the weight could be better distributed throughout the head. This innovative design gave the clubhead a larger sweet spot, which allowed a player to strike the golf ball off-center and not suffer much loss in distance or accuracy. Callaway has maintained its preeminent position in the golf industry by utilizing space-age tech- nology to extend the accuracy and distance of golf equipment. In 2000 Callaway introduced the Big Bertha ERC II forged titanium driver. The driver was technologically superior to any driver on the market. However, there was one big problem. The new version of Bertha did not conform to the coefficient of restitution (COR) requirement established by the United States Golf Association (USGA). As a result it was barred from use by golfers in North America who intended to play by the USGA’s Rules of Golf. The USGA believed that the rapid technological advances in golf equipment made by Callaway Golf and other golf manufacturers were threatening the integrity of the game. Players were hitting balls so much farther and straighter that golf courses around the world were

S N A P S H O T F R O M P R A C T I C E 4 . 1 Big Bertha II versus the USGA’s COR Requirement*

being redesigned to make them longer and more difficult. So in 1998 the USGA established performance thresholds for all new golf equipment. In order to pre- vent manufacturers from developing more powerful clubs, the USGA limited the COR of new golf equip- ment to 0.83. The COR was calculated by firing a golf ball at a driver out of a cannon-like machine at 109 miles per hour. The speed that the ball returned to the cannon could not exceed 83 percent of its initial speed (90.47 mph). The USGA called the ratio of incoming to outgoing velocity the coefficient of resti- tution (COR). The intent of the USGA COR threshold was to limit the distance that golf balls could be hit since studies indicated that 0.01 increase in COR resulted in two extra yards of carry. The Big Bertha ERC II’s COR was 0.86. After numerous efforts to get USGA to change its technical requirements, Callaway’s engineers went back to the drawing board and in 2002 introduced Great Big Bertha II, which conformed to USGA’s 0.83 COR restriction.

* John E. Gamble, “Callaway Golf Company: Sustaining Advantage in a Changing Industry,” in A. A. Thompson, J. E. Gamble, and A. J. Strickland, Strategy: Winning in the Marketplace (Boston: McGraw-Hill/Irwin, 2004), pp. C204–C228.

© Les Jorgensen/Getty

Chapter 4 Defining the Project 105

prescribed in the contract. Exclusions further define the boundary of the project by stating what is not included. Examples include: data will be collected by the client, not the contractor; a house will be built, but no landscaping or security devices added; software will be installed, but no training given.

6. Reviews with customer. Completion of the scope checklist ends with a review with your customer—internal or external. The main concern here is the understanding of and agreement to expectations. Is the customer getting what he or she desires in deliverables? Does the project definition identify key accomplishments, budgets, timing, and performance requirements? Are questions of limits and exclusions cov- ered? Clear communication in all these issues is imperative to avoid claims or misunderstanding.

Scope definition should be as brief as possible but complete; one or two pages are typical for small projects. See Snapshot from Practice 4.2: Scope Statement. The project scope checklist in Step 1 is generic. Different industries and companies will develop unique checklists and templates to fit their needs and specific kinds of projects. A few companies engaged in contracted work refer to scope statements as “statements of work” (SOW). Other organizations use the term project charter. How- ever, the term project charter has emerged to have a special meaning in the world of

PROJECT OBJECTIVE To construct a high-quality, custom home within five months at cost not to exceed $700,000 on lot 42A in Green- dale, Oregon.

DELIVERABLES

- ished home.

microwave, and dishwasher.

thermostat.

MILESTONES 1. Permits approved—March 5

2. Foundation poured—March 14

3. Drywall in. Framing, sheathing, plumbing, electri- cal, and mechanical inspections passed—May 25

4. Final inspection—June 7

TECHNICAL REQUIREMENTS 1. Home must meet local building codes.

2. All windows and doors must pass NFRC class 40 energy ratings.

3. Exterior wall insulation must meet an “R” factor of 21.

4. Ceiling insulation must meet an “R” factor of 38.

5. Floor insulation must meet an “R” factor of 25.

6. Garage will accommodate two large-size cars and one 20-foot Winnebago.

7. Structure must pass seismic stability codes.

LIMITS AND EXCLUSIONS 1. The home will be built to the specifications and

design of the original blueprints provided by the customer.

2. Owner is responsible for landscaping.

3. Refrigerator is not included among kitchen appliances.

4. Air conditioning is not included but prewiring is included.

5. Contractor reserves the right to contract out services.

6. Contractor is responsible for subcontracted work.

7. Site work limited to Monday through Friday, 8:00 a.m. to 6:00 p.m.

CUSTOMER REVIEW John and Joan Smith

S N A P S H O T F R O M P R A C T I C E 4 . 2 Scope Statement

106 Chapter 4 Defining the Project

project management. A project charter refers to a document that authorizes the project manager to initiate and lead the project. This document is issued by upper management and provides the project manager with written authority to use organizational resources for project activities. Often the charter will include a brief scope description as well as such items as risk limits, business case, spending limits, and even team composition. Many projects suffer from scope creep, which is the tendency for the project scope to expand over time—usually by changing requirements, specifications, and priorities. Scope creep can be reduced by carefully writing your scope statement. A scope state- ment that is too broad is an invitation for scope creep. Scope creep can have a positive or negative effect on the project, but in most cases scope creep means added costs and possible project delays. Changes in requirements, specifications, and priorities fre- quently result in cost overruns and delays. Examples are abundant—Denver airport baggage handling system; Boston’s new freeway system (“The Big Dig”); Sochi Winter Olympics; and the list goes on. On software development projects, scope creep is mani- fested in bloated products in which added functionality undermines ease of use. If the project scope needs to change, it is critical to have a sound change control process in place that records the change and keeps a log of all project changes. The log identifies the change, impact, and those responsible for accepting or rejecting a pro- posed change. Change control is one of the topics of Chapter 7. Project managers in the field con- stantly suggest that dealing with changing requirements is one of their most challeng- ing problems.

4.2 Step 2: Establishing Project Priorities Quality and the ultimate success of a project are traditionally defined as meeting and/ or exceeding the expectations of the customer and/or upper management in terms of cost (budget), time (schedule), and performance (scope) of the project (see Figure 4.1). The interrelationship among these criteria varies. For example, sometimes it is neces- sary to compromise the performance and scope of the project to get the project done quickly or less expensively. Often the longer a project takes, the more expensive it becomes. However, a positive correlation between cost and schedule may not always be true. Other times project costs can be reduced by using cheaper, less efficient labor or equipment that extends the duration of the project. Likewise, as will be seen in Chapter 9, project managers are often forced to expedite or “crash” certain key activi- ties by adding additional labor, thereby raising the original cost of the project. One of the primary jobs of a project manager is to manage the trade-offs among time, cost, and performance. To do so, project managers must define and understand the nature of the priorities of the project. They need to have a candid discussion with the project customer and upper management to establish the relative importance of

Understand why it is important to establish project priorities in terms of cost, time, and performance.

4-2LO

Quality

Cost Time

Scope FIGURE 4.1 Project Management Trade-offs

Chapter 4 Defining the Project 107

each criterion. For example, what happens when the customer keeps adding require- ments? Or if, midway through the project, a trade-off must be made between cost and expediting, which criterion has priority? One technique found in practice that is useful for this purpose is completing a prior- ity matrix for the project to identify which criterion is constrained, which should be enhanced, and which can be accepted:

Constrain. The original parameter is fixed. The project must meet the completion date, specifications and scope of the project, or budget. Enhance. Given the scope of the project, which criterion should be optimized? In the case of time and cost, this usually means taking advantage of opportunities to either reduce costs or shorten the schedule. Conversely, with regard to perfor- mance, enhancing means adding value to the project. Accept. For which criterion is it tolerable not to meet the original parameters? When trade-offs have to be made, is it permissible for the schedule to slip, to reduce the scope and performance of the project, or to go over budget?

Figure 4.2 displays the priority matrix for the development of a new wireless router. Because time to market is important to sales, the project manager is instructed to take advantage of every opportunity to reduce completion time. In doing so, going over budget is acceptable though not desirable. At the same time, the original performance specifications for the modem as well as reliability standards cannot be compromised. Priorities vary from project to project. For example, for many software projects time to market is critical, and companies like Microsoft may defer original scope require- ments to later versions in order to get to the market first. Alternatively, for special event projects (conferences, parades, tournaments) time is constrained once the date has been announced, and if the budget is tight, the project manager will compromise the scope of the project in order to complete the project on time. Some would argue that all three criteria are always constrained and that good proj- ect managers should seek to optimize each criterion. If everything goes well on a project and no major problems or setbacks are encountered, their argument may be valid. However, this situation is rare, and project managers are often forced to make tough decisions that benefit one criterion while compromising the other two. The pur- pose of this exercise is to define and agree on what the priorities and constraints of the project are so that when “push comes to shove,” the right decisions can be made.

Constrain

Enhance

Accept

Time Performance Cost FIGURE 4.2 Project Priority Matrix

108 Chapter 4 Defining the Project

There are likely to be natural limits to the extent managers can constrain, optimize, or accept any one criterion. It may be acceptable for the project to slip one month behind schedule but no further or to exceed the planned budget by as much as $20,000. Likewise, it may be desirable to finish a project a month early, but after that cost con- servation should be the primary goal. Some project managers document these limits as part of creating the priority matrix. In summary, developing a priority matrix for a project before the project begins is a useful exercise. It provides a forum for clearly establishing priorities with customers and top management so as to create shared expectations and avoid misunderstandings. The priority information is essential to the planning process, where adjustments can be made in the scope, schedule, and budget allocation. Finally, the matrix is useful mid- way in the project for approaching a problem that must be solved. One caveat must be mentioned; during the course of a project, priorities may change. The customer may suddenly need the project completed one month sooner, or new directives from top management may emphasize cost saving initiatives. The project manager needs to be vigilant in order to anticipate and confirm changes in priorities and make appropriate adjustments.

4.3 Step 3: Creating the Work Breakdown Structure

Major Groupings Found in a WBS Once the scope and deliverables have been identified, the work of the project can be successively subdivided into smaller and smaller work elements. The outcome of this hierarchical process is called the work breakdown structure (WBS). Use of a WBS helps to assure project managers that all products and work elements are identified, to integrate the project with the current organization, and to establish a basis for control. Basically, the WBS is an outline of the project with different levels of detail. Figure 4.3 shows the major groupings commonly used in the field to develop a hier- archical WBS. The WBS begins with the project as the final deliverable. Major project work deliverables/systems are identified first; then the subdeliverables necessary to accomplish the larger deliverables are defined. The process is repeated until the subde- liverable detail is small enough to be manageable and where one person can be respon- sible. This subdeliverable is further divided into work packages. Because the lowest subdeliverable usually includes several work packages, the work packages are grouped by type of work—for example, design and testing. These groupings within a subdeliv- erable are called cost accounts. This grouping facilitates a system for monitoring proj- ect progress by work, cost, and responsibility.

How WBS Helps the Project Manager The WBS defines all the elements of the project in a hierarchical framework and establishes their relationships to the project end item(s). Think of the project as a large work package that is successively broken down into smaller work packages; the total project is the summation of all the smaller work packages. This hierarchical structure facilitates evaluation of cost, time, and technical performance at all levels in the organization over the life of the project. The WBS also provides management with information appropriate to each level. For example, top management deals primarily with major deliverables, while first-line supervisors deal with smaller subdeliverables and work packages.

Demonstrate the impor- tance of a work break- down structure (WBS) to the management of proj- ects and how it serves as a data base for planning and control.

4-3LO

Chapter 4 Defining the Project 109

Each item in the WBS needs a time and cost estimate. With this information it is possible to plan, schedule, and budget your project. The WBS also serves as a frame- work for tracking cost and work performance. As the WBS is developed, organizational units and individuals are assigned respon- sibility for executing work packages. This integrates the work and the organization. In practice, this process is sometimes called the organization breakdown structure (OBS), which will be further discussed later in the chapter. Use of the WBS provides the opportunity to “roll up” (sum) the budget and actual costs of the smaller work packages into larger work elements so that performance can be measured by organizational units and work accomplishment. The WBS can also be used to define communication channels and assist in under- standing and coordinating many parts of the project. The structure shows the work and organizational units responsible and suggests where written communication should be directed. Problems can be quickly addressed and coordinated because the structure integrates work and responsibility.

A Simple WBS Development Figure 4.4 shows a simplified WBS to develop a new prototype tablet computer. At the top of the chart (level 1) is the project end item—the E-Slim Tablet x-13 Prototype. The subdeliverables levels (2–5) below level 1 represent further decomposition of work. The levels of the structure can also represent information for different levels of

FIGURE 4.3 Hierarchical Breakdown of the WBS

Cost account*

Work package

Subdeliverable

Deliverable

Lowest subdeliverable

Level Hierarchical breakdown Description

Complete project

Major deliverables

Supporting deliverables

Lowest management responsibility level

Grouping of work packages for monitoring progress and responsibility

Identifiable work activities

1

2

3

4

5

Project

* This breakdown groups work packages by type of work within a deliverable and allows assignment of responsibility to an organizational unit. This extra step facilitates a system for monitoring project progress (discussed in Chapter 13).

FI GU

RE 4

.4

W or

k Br

ea kd

ow n

St ru

ct ur

e

W P-

F1 W

P- S1

W P-

A 1

W P-

A 2

W P-

A 3

W P-

K1

W P-

C 1

W P-

C 2

W P-

C 3

W P-

C 4

W P-

TS 1

W P-

TS 2

W P-

TS 3

W P-

L1 W

P- L2

W P-

L3

W P-

R1 W

P- R2

W P-

R3

Lo w

es t M

an ag

ea bl

e Su

bd el

iv er

ab le

s

Le ve

l

1 2 3 4 5

E- Sl

im T

ab le

t x -1

3 Pr

ot ot

yp e

M or

e ite

m s

Fr am

e C

am er

as Sp

ea ke

rs A

nt en

na Ke

yb oa

rd

U SB

S lo

ts In

te rn

et To

uc h

Sc re

en

C PU

H ar

dw ar

e

Po w

er Su

pp ly

B at

te ry

To uc

h Se

ns or

s B

ac k

Li gh

t Re

so lu

tio n

C ha

rg er

Fl as

h RO

M I/O

C on

tr ol

le r

W or

k Pa

ck ag

es

110

Chapter 4 Defining the Project 111

management. For example, level 1 information represents the total project objective and is useful to top management; levels 2, 3, and 4 are suitable for middle manage- ment; and level 5 is for first-line managers. In Figure 4.4 level 2 indicates there are two major deliverables—Hardware and CPU, or central processing unit. (There are likely to be other major deliverables such as software, but for illustrative purposes we are limiting our focus to just two major deliverables.) At level 3, the CPU is connected to three deliverables—Power Supply, Flash ROM, and I/O Controller. The I/O Controller has three subdeliverables at level 4—USB Slots, Internet, and Touch Screen. The many subdeliverables for USB Slots and Internet have not been decomposed. The Touch Screen (shaded) has been decom- posed down to level 5 and to the work package level. Note that level 2, Hardware, skips levels 3 and 4 because the final subdeliverables can be pushed down to the lowest manageable level 5; skipping levels 3 and 4 suggests little coordination is needed and skilled team members are already familiar with the work needed to complete the level 5 subdeliverables. For example, Hardware requires four subdeliverables at level 5—Frame, Cameras, Speakers, and Antenna. Each subde- liverable includes work packages that will be completed by an assigned organizational unit. Observe that the Cameras subdeliverable includes four work packages—WP-C1, 2, 3, and 4. The Back Light, a subdeliverable of Touch Screen, includes three work packages—WP-L 1, 2, and 3. The lowest level of the WBS is called a work package. Work packages are short- duration tasks that have a definite start and stop point, consume resources, and represent cost. Each work package is a control point. A work package manager is responsible for seeing that the package is completed on time, within budget, and according to technical specifications. Practice suggests a work package should not exceed 10 workdays or one reporting period. If a work package has a duration exceeding 10 days, check or monitor- ing points should be established within the duration, say, every three to five days, so progress and problems can be identified before too much time has passed. Each work package of the WBS should be as independent of other packages of the project as pos- sible. No work package is described in more than one subdeliverable of the WBS. There is an important difference from start to finish between the last work break- down subdeliverable and a work package. Typically, a work breakdown subdeliverable includes the outcomes of more than one work package from perhaps two or three depart- ments. Therefore, the subdeliverable does not have a duration of its own and does not consume resources or cost money directly. (In a sense, of course, a duration for a par- ticular work breakdown element can be derived from identifying which work package must start first [earliest] and which package will be the latest to finish; the difference from start to finish becomes the duration for the subdeliverable.) The higher elements are used to identify deliverables at different phases in the project and to develop status reports during the execution stage of the project life cycle. Thus, the work package is the basic unit used for planning, scheduling, and controlling the project. To review, each work package in the WBS

1. Defines work (what). 2. Identifies time to complete a work package (how long). 3. Identifies a time-phased budget to complete a work package (cost). 4. Identifies resources needed to complete a work package (how much). 5. Identifies a single person responsible for units of work (who). 6. Identifies monitoring points for measuring progress (how well).

112 Chapter 4 Defining the Project

Creating a WBS from scratch can be a daunting task. Project managers should take advantage of relevant examples from previous projects to begin the process. WBSs are products of group efforts. If the project is small, the entire project team may be involved breaking down the project into its components. For large, complex projects, the people responsible for the major deliverables are likely to meet to establish the first two levels of deliverables. In turn, further detail would be delegated to the people respon- sible for the specific work. Collectively this information would be gathered and inte- grated into a formal WBS by a project support person. The final version would be reviewed by the inner echelon of the project team. Relevant stakeholders (most notably customers) would be consulted to confirm agreement and revise when appropriate. Project teams developing their first WBS frequently forget that the structure should be end-item, output oriented. First attempts often result in a WBS that follows the organization structure—design, marketing, production, finance. If a WBS follows the organization structure, the focus will be on the organization function and processes rather than the project output or deliverables. In addition, a WBS with a process focus will become an accounting tool that records costs by function rather than a tool for “output” management. Every effort should be made to develop a WBS that is output oriented in order to concentrate on concrete deliverables. See Snapshot from Prac- tice 4.3: Creating a WBS.

Figure 4.4 represents the classic WBS in which the project is broken down to the lowest manageable deliverable and subsequent work packages. Many situations do not require this level of

detail. This begs the question of how far you should break down the work. There is no set answer to this question. However, here are some tips given by project managers: Break down the work until you can do an estimate that is accurate enough for your purposes. If you are doing a ball-park estimate to see if the project is worthy of serious consideration, you probably do not need to break it down beyond major deliverables. On the other hand, if you are pricing a project to submit a competitive bid, then you are likely to go down to the work package level. The WBS should conform to how you are going to schedule work. For example, if assignments are made in terms of days, then tasks should be limited as best as possible to one day or more to complete. Conversely, if hours are the smallest unit for scheduling, then work can be broken down to one-hour increments. Final activities should have clearly defined start/ end events. Avoid open-ended tasks like “research” or “market analysis.” Take it down to the next level in which deliverables/outcomes are more clearly defined.

S N A P S H O T F R O M P R A C T I C E 4 . 3 Creating a WBS

Instead of ending with market analysis include items such as identify market share, list user requirements, or write a problem statement. If accountability and control are important, then break the work down so that one individual is clearly responsible for the work. For example, instead of stop- ping at product design, take it to the next level and identify specific components of the design (i.e., electri- cal schematics, power source, etc.) that different indi- viduals will be responsible for creating. The bottom line is that the WBS should provide the level of detail needed to manage the specific project successfully.

© astephan/Shutterstock

Chapter 4 Defining the Project 113

4.4 Step 4: Integrating the WBS with the Organization The WBS is used to link the organizational units responsible for performing the work. In practice, the outcome of this process is the organization breakdown structure (OBS). The OBS depicts how the firm has organized to discharge work responsibility. The purposes of the OBS are to provide a framework to summarize organization unit work performance, identify organization units responsible for work packages, and tie the organizational unit to cost control accounts. Recall, cost accounts group similar work packages (usually under the purview of a department). The OBS defines the organization subdeliverables in a hierarchical pattern in successively smaller and smaller units. Frequently, the traditional organization structure can be used. Even if the project is completely performed by a team, it is necessary to break down the team structure for assigning responsibility for budgets, time, and technical performance. As in the WBS, the OBS assigns the lowest organizational unit the responsibility for work packages within a cost account. Herein lies one major strength of using WBS and OBS; they can be integrated as shown in Figure 4.5. The intersection of work packages and the organizational unit creates a project control point (cost account) that integrates work and responsibility. For example, at level 5 Touch Sensors has three work pack- ages that have been assigned to the Design, Quality Control Test, and Production departments. The intersection of the WBS and OBS represents the set of work pack- ages necessary to complete the subdeliverable located immediately above and the organizational unit on the left responsible for accomplishing the packages at the inter- section. Note that the design department is responsible for five different work packages across the Hardware and Touch Screen deliverables. Later we will use the intersection as a cost account for management control of proj- ects. For example, the Cameras element requires completion of work packages whose primary responsibility will include the design, QC test, production, and outsourcing departments. Control can be checked from two directions—outcomes and responsibil- ity. In the execution phase of the project, progress can be tracked vertically on deliver- ables (client’s interest) and tracked horizontally by organization responsibility (own- er’s interest).

4.5 Step 5: Coding the WBS for the Information System Gaining the maximum usefulness of a breakdown structure depends on a coding sys- tem. The codes are used to define levels and elements in the WBS, organization ele- ments, work packages, and budget and cost information. The codes allow reports to be consolidated at any level in the structure. The most commonly used scheme in practice is numeric indention. A portion of the E-Slim Tablet x-13 Prototype project is pre- sented in Exhibit 4.1. Note the project identification is 1.0. Each successive indention represents a lower element or work package. Ultimately the numeric scheme reaches down to the work package level, and all tasks and elements in the structure have an identification code. The “cost account” is the focal point because all budgets, work assignments, time, cost, and technical performance come together at this point. This coding system can be extended to cover large projects. Additional schemes can be added for special reports. For example, adding a “23” after the code could indicate a site location, an elevation, or a special account such as labor. Some letters can be used as special identifiers such as “M” for materials or “E” for engineers. You are not

Demonstrate how the organization breakdown structure (OBS) estab- lishes accountability to organizational units.

4-4LO

FI GU

RE 4

.5

In te

gr at

io n

of W

BS a

nd O

BS

E- Sl

im T

ab le

t x-

13

M or

e ite

m s

Fr am

e C

am er

as Sp

ea ke

rs A

nt en

na Ke

yb oa

rd

U SB

S lo

ts In

te rn

et To

uc h

Sc re

en Lo

w es

t M an

ag ea

bl e

Su bd

el iv

er ab

le s

C os

t A cc

ou nt

N um

be r

C PU

H ar

dw ar

e

Le ve

l

1 2 3 4 5

Po w

er Su

pp ly

B at

te ry

To uc

h Se

ns or

s B

ac k

Li gh

t Re

so lu

tio n

C ha

rg er

Fl as

h RO

M I/O

C on

tr ol

le r

D es

ig n

Q C

T es

t

Pr od

uc tio

n

O ut

so ur

ci ng

O rg

an iz

at io

n

C os

t A

cc ou

nt

1.2 .3

.3 .2

.3

1.2 .3

.3 .1

1.2 .3

.3 .2

1.2 .3

.3 .3

1.2 .3

.3 .4

1.1 .4

.1

1.0 1.2 1.1

1.2 .1

1.2 .2

1.2 .3

1.2 .1.

1

1.1 .1

1.1 .2

1.1 .3

1.1 .41

.2 .1.

2 1.2

.3 .1

1.2 .3

.2 1.2

.3 .3

C os

t A

cc ou

nt

C os

t A

cc ou

nt

C os

t A

cc ou

nt

C os

t A

cc ou

nt C

os t

A cc

ou nt

C os

t A

cc ou

nt C

os t

A cc

ou nt

C os

t A

cc ou

nt C

os t

A cc

ou nt

C os

t A

cc ou

nt C

os t

A cc

ou nt

C os

t A

cc ou

nt C

os t

A cc

ou nt

C os

t A

cc ou

nt

C os

t A

cc ou

nt

C os

t A

cc ou

nt

114

Chapter 4 Defining the Project 115

limited to only 10 subdivisions (0–9); you can extend each subdivision to large numbers—for example, .1−.99 or .1−.9999. If the project is small, you can use whole numbers. The following example is from a large, complex project:

3R−237A−P2−33.6 where 3R identifies the facility, 237A represents elevation and the area, P2 represents pipe two inches wide, and 33.6 represents the work package number. In practice most organizations are creative in combining letters and numbers to minimize the length of WBS codes. On larger projects, the WBS is further supported with a WBS dictionary that pro- vides detailed information about each element in the WBS. The dictionary typically includes the work package level (code), name, and functional description. In some cases the description is supported with specifications. The availability of detailed descriptions has an added benefit of dampening scope creep.

EXHIBIT 4.1 Coding the WBS

116 Chapter 4 Defining the Project

4.6 Process Breakdown Structure The WBS is best suited for design and build projects that have tangible outcomes such as an offshore mining facility or a new car prototype. The project can be decomposed or broken down into major deliverables, subdeliverables, further subdeliverables, and ultimately to work packages. It is more difficult to apply WBS to less tangible, pro- cess-oriented projects in which the final outcome is a product of a series of steps or phases. Here, the big difference is that the project evolves over time with each phase affecting the next phase. Information systems projects typically fall in this category— for example, creating an extranet website or an internal software database system. Process projects are driven by performance requirements, not by plans/blueprints. Some practitioners choose to utilize what we refer to as a process breakdown struc- ture (PBS) instead of the classic WBS. Figure 4.6 provides an example of a PBS for a software development project. Instead of being organized around deliverables, the project is organized around phases. Each of the five major phases can be broken down into more specific activities until a suf- ficient level of detail is achieved to communicate what needs to be done to complete that phase. People can be assigned to specific activities, and a complementary OBS can be created just as is done for the WBS. Deliverables are not ignored but are defined as outputs required to move to the next phase. The software industry often refers to PBS as the “waterfall method” since progress flows downward through each phase.1

Describe a process breakdown structure (PBS) and when to use it.

4-5LO

FIGURE 4.6 PBS for Software Development Project

Software development project

Construct

Develop technical design

Define processing flow

Design logical database structure

Design system interfaces

Define application architecture

Develop detailed design

Establish quality requirements

Define user interface

DesignAnalysis Test Rollout

Design phase deliverables: Design document

1 Level Major phases:

2 Level Activities:

3 Level Activities:

Outputs:

User documentation outline

Application architecture Application flow Database design End user interface design Workflow diagram

1 The limitations of the waterfall method for software development have led to the emergence of Agile project manage- ment methods that are the subject of Chapter 17.

Chapter 4 Defining the Project 117

Checklists that contain the phase exit requirements are developed to manage project progress. These checklists provide the means to support phase walk-throughs and reviews. Checklists vary depending upon the project and activities involved but typi- cally include the following details: ∙ Deliverables needed to exit a phase and begin a new one. ∙ Quality checkpoints to ensure that deliverables are complete and accurate. ∙ Sign-offs by all responsible stakeholders to indicate that the phase has been success-

fully completed and that the project should move on to the next phase. As long as exit requirements are firmly established and deliverables for each phase are well defined, the PBS provides a suitable alternative to the standard WBS for projects that involve extensive development work.

4.7 Responsibility Matrices In many cases, the size and scope of the project do not warrant an elaborate WBS or OBS. One tool that is widely used by project managers and task force leaders of small projects is the responsibility matrix (RM). The RM (sometimes called a linear respon- sibility chart) summarizes the tasks to be accomplished and who is responsible for what on a project. In its simplest form an RM consists of a chart listing all the project activities and the participants responsible for each activity. For example, Figure 4.7 illustrates an RM for a market research study. In this matrix the R is used to identify the committee member who is responsible for coordinating the efforts of other team members assigned to the task and making sure that the task is completed. The S is used to identify members of the five-person team who will support and/or assist the individual responsible. Simple RMs like this one are useful not only for organizing and assigning responsibilities for small projects but also for subprojects of large, more complex projects. More complex RMs not only identify individual responsibilities but also clarify critical interfaces between units and individuals that require coordination. For

Create responsibility matrices for small projects.

4-6LO

FIGURE 4.7 Responsibility Matrix for a Market Research Project

Identify target customers Develop draft questionnaire Pilot-test questionnaire Finalize questionnaire Print questionnaire Prepare mailing labels Mail questionnaires Receive and monitor returned questionnaires Input response data Analyze results Prepare draft of report Prepare final report

Task Richard

R R

R

S R

Dan

Project Team

R = Responsible S = Supports/assists

S S R S

R R

Dave

S

S

R S S S

Linda

S

S S

R

S S

Elizabeth

R R R S

FI GU

RE 4

.8

Re sp

on sib

ili ty

M at

ri x

fo r t

he C

on ve

yo r B

el t P

ro je

ct

A rc

hi te

ct ur

al d

es ig

ns H

ar dw

ar e

sp ec

ifi ca

tio ns

Ke rn

el s

pe ci

fic at

io ns

U til

iti es

s pe

ci fic

at io

ns H

ar dw

ar e

de si

gn D

is k

dr iv

er s

M em

or y

m an

ag em

en t

O pe

ra tin

g sy

st em

d oc

um en

ta tio

n Pr

ot ot

yp es

In te

gr at

ed a

cc ep

ta nc

e te

st

D el

iv er

ab le

s D

es ig

n

1 2 1 2 1 3 1 2 5 5

D ev

el op

m en

t

O rg

an iz

at io

n

1 2 3 4 5

Re sp

on si

bl e

Su pp

or t

C on

su lt

N ot

ifi ca

tio n

A pp

ro va

l

2 1 3 1 1 3 2 2

D oc

um en

ta tio

n

2 1 4 2

A ss

em bl

y

3 1

Te st

in g

2 3 3 3 1

Pu rc

ha si

ng

2 3 3

Q ua

lit y

A ss

ur .

3 3 3 5

M an

uf ac

tu rin

g

3 3 3 3 4 5

118

Chapter 4 Defining the Project 119

example, Figure 4.8 is an RM for a larger, more complex project to develop a new piece of automated equipment. Notice that within each cell a numeric coding scheme is used to define the nature of involvement on that specific task. Such an RM extends the WBS/OBS and provides a clear and concise method for depicting responsibility, authority, and communication channels. Responsibility matrices provide a means for all participants in a project to view their responsibilities and agree on their assignments. They also help clarify the extent or type of authority exercised by each participant in performing an activity in which two or more parties have overlapping involvement. By using an RM and by defining authority, responsibility, and communications within its framework, the relationship between dif- ferent organizational units and the work content of the project is made clear.

4.8 Project Communication Plan Once the project deliverables and work are clearly identified, following up with an internal communication plan is vital. Stories abound of poor communication as a major contributor to project failure. Having a robust communications plan can go a long way toward mitigating project problems and can ensure that customers, team members, and other stakeholders have the information to do their jobs. The communication plan is usually created by the project manager and/or the proj- ect team in the early stage of project planning. Communication is a key component in coordinating and tracking project schedules, issues, and action items. The plan maps out the flow of information to different stake- holders and becomes an integral part of the overall project plan. The purpose of a project communication plan is to express what, who, how, and when information will be trans- mitted to project stakeholders so schedules, issues, and action items can be tracked. Project communication plans address the following core questions: ∙ What information needs to be collected and when? ∙ Who will receive the information? ∙ What methods will be used to gather and store information? ∙ What are the limits, if any, on who has access to certain kinds of information? ∙ When will the information be communicated? ∙ How will it be communicated? Developing a communication plan that answers these questions usually entails the fol- lowing basic steps: 1. Stakeholder analysis. Identify the target groups. Typical groups could be the cus-

tomer, sponsor, project team, project office, or anyone who needs project information to make decisions and/or contribute to project progress. A common tool found in practice to initially identify and analyze major project stakeholders’ communication needs is presented in Figure 4.9.2 How and what is communicated is influenced by the stakeholder interest and power. Some of these stakeholders may have the power either to block or enhance your project. By identifying stakeholders and prioritizing them on the “Power/Interest” map, you can plan the type and frequency of communications needed. (More on stakeholders will be discussed in Chapter 10.)

Create a communication plan for a project.

4-7LO

2 For a more elaborate scheme for assessing stakeholders, see: Lynda Bourne, Stakeholder Relationship Management

120 Chapter 4 Defining the Project

For example, on a typical project you want to manage closely the professionals doing the work, while you want to satisfy senior management and project sponsor with periodic updates. Unions and operation managers interested in capacity would be someone you would want to keep informed, while you would only need to pro- vide general information to the legal, public relations, and other departments.

2. Information needs. What information is pertinent to stakeholders who contribute to the project’s progress? The simplest answer to this question can be obtained by asking the different people what information they need and when they need it. For example, top management needs to know how the project is progressing, whether it is encountering critical problems, and the extent to which project goals are being realized. This information is required so that they can make strategic decisions and manage the portfolio of projects. Project team members need to see schedules, task lists, specifications, and the like, so they know what needs to be done next. External groups need to know any changes in the schedule and performance requirements of the components they are providing. Frequent information needs found in communi- cation plans are:

Project status reports Deliverable issues Changes in scope Team status meetings Gating decisions Accepted request changes Action items Milestone reports

3. Sources of information. When the information needs are identified, the next step is to determine the sources of information. That is, where does the information reside? How will it be collected? For example, information relating to the milestone report, team meetings, and project status meetings would be found in the minutes and reports of various groups.

4. Dissemination modes. In today’s world, traditional status report meetings are being supplemented by e-mail, teleconferencing, SharePoint, and a variety of database shar- ing programs to circulate information. In particular, many companies are using the Web to create a “virtual project office” to store project information. Project manage- ment software feeds information directly to the website so that different people have immediate access to relevant project information. In some cases, appropriate informa- tion is routed automatically to key stakeholders. Backup paper hardcopy to specific stakeholders is still critical for many project changes and action items.

FIGURE 4.9 Stakeholder Communications

Interest

D

A

F H

C

D

E

G

B

High

HighLow

Power

Provide General Information

Manage Closely

Keep Informed

Low

Keep Satisfied

Chapter 4 Defining the Project 121

5. Responsibility and timing. Determine who will send out the information. For example, a common practice is to have secretaries of meetings forward the minutes or specific information to the appropriate stakeholders. In some cases the responsi- bility lies with the project manager or project office. Timing and frequency of dis- tribution appropriate to the information need to be established.

The advantage of establishing a communication plan is that instead of responding to information requests, you are controlling the flow of information. This reduces confu- sion and unnecessary interruptions, and it can provide project managers greater auton- omy. Why? By reporting on a regular basis how things are going and what is happening, you allow senior management to feel more comfortable about letting the team complete the project without interference. See Figure 4.10 for a sample Shale Oil Research Project Communication Plan. The importance of establishing up-front a plan for communicating important proj- ect information cannot be overstated. Many of the problems that plague a project can be traced back to insufficient time devoted to establishing a well-grounded internal communication plan.

What Information

Milestone report

Project status reports & agendas

Team status reports

Issues report

Escalation reports

Outsourcing performance

Accepted change requests

Oversight gate decisions

Senior management and project manager

Senior management and project manager Bimonthly

Weekly

E-mail and hardcopy Project office

Project manager

Team recorder

Team recorder

Project manager

Project manager

Design department

Oversight group or

project office

E-mail and hardcopy

E-mail and hardcopy

E-mail meeting report

E-mail

E-mail

Meeting and hardcopy

Meeting

Weekly

Weekly

When needed

Bimonthly

Anytime

As required

Project office, senior mgmt., customer, staff,

and project mgr.

Staff and customer

Staff and customer

Staff and customer

Project manager and project office

Staff and customer

Target Audience When?

Method of Communication Provider

FIGURE 4.10 Shale Oil Research Project Communication Plan

Summary The project scope definition, priorities, and breakdown structure are the keys to nearly every aspect of managing the project. The scope definition provides focus and emphasis on the end item(s) of the project. Establishing project priorities allows managers to make appropriate trade-off decisions. The WBS structure helps ensure all tasks of the project are identified and provides two views of the project—one on deliverables and one on

122 Chapter 4 Defining the Project

Key Terms Cost account, 113 Milestone, 103 Organization breakdown structure (OBS), 113 Priority matrix, 107

Process breakdown structure (PBS), 116 Project charter, 105 Responsibility matrix, 117 Scope creep, 106

Scope statement, 105 WBS dictionary, 115 Work breakdown structure (WBS), 108 Work package, 111

organization responsibility. The WBS avoids having the project driven by organization function or by a finance system. The structure forces attention to realistic requirements of personnel, hardware, and budgets. Use of the structure provides a powerful framework for project control that identifies deviations from plan, identifies responsibility, and spots areas for improved performance. No well-developed project plan or control system is possible without a disciplined, structured approach. The WBS, OBS, and cost account codes provide this discipline. The WBS will serve as the database for developing the project network which establishes the timing of work, people, equipment, and costs. PBS is often used for process-based projects with ill-defined deliverables. In small projects responsibility matrices may be used to clarify individual responsibility. Clearly defining your project is the first and most important step in planning. The absence of a clearly defined project plan consistently shows up as the major reason for project failures. Whether you use a WBS, PBS, or responsibility matrix will depend pri- marily on the size and nature of your project. Whatever method you use, definition of your project should be adequate to allow for good control as the project is being implemented. Follow-up with a clear communication plan for coordinating and tracking project prog- ress will help keep important stakeholders informed and avoid some potential problems.

1. What are the six elements of a typical scope statement? 2. What questions does a project objective answer? What would be an example of a

good project objective? 3. What does it mean if the priorities of a project include: Time-constrain, Scope-

accept, and Cost-enhance? 4. What kinds of information are included in a work package? 5. When would it be appropriate to create a responsibility matrix rather than a full-

blown WBS? 6. How does a communication plan benefit management of projects?

Review Questions

Exercises 1. You are in charge of organizing a dinner-dance concert for a local charity. You have reserved a hall that will seat 30 couples and have hired a jazz combo. a. Develop a scope statement for this project that contains examples of all the ele-

ments. Assume that the event will occur in four weeks and provide your best guess estimate of the dates for milestones.

b. What would the priorities likely be for this project? 2. In small groups, identify real life examples of a project that would fit each of the

following priority scenarios: a. Time-constrain, Scope-enhance, Cost-accept b. Time-accept, Scope-constrain, Cost-accept c. Time-constrain, Scope-accept, Cost-enhance

Chapter 4 Defining the Project 123

3. Develop a WBS for a project in which you are going to build a bicycle. Try to iden- tify all of the major components and provide three levels of detail.

4. You are the father or mother of a family of four (kids ages 13 and 15) planning a weekend camping trip. Develop a responsibility matrix for the work that needs to be done prior to starting your trip.

5. Develop a WBS for a local stage play. Be sure to identify the deliverables and orga- nizational units (people) responsible. How would you code your system? Give an example of the work packages in one of your cost accounts. Develop a correspond- ing OBS which identifies who is responsible for what.

6. Use an example of a project you are familiar with or are interested in. Identify the deliverables and organizational units (people) responsible. How would you code your system? Give an example of the work packages in one of your cost accounts.

7. Develop a communication plan for an airport security project. The project entails installing the hardware and software system that (1) scans a passenger’s eyes, (2) fingerprints the passenger, and (3) transmits the information to a central location for evaluation.

8. Go to an Internet search engine (e.g., Google) and type in “project communication plan.” Check three or four that have “.gov” as their source. How are they similar or dissimilar? What would be your conclusion concerning the importance of an inter- nal communication plan?

9. Your roommate is about to submit a scope statement for a spring concert sponsored by the entertainment council at Western Evergreen State University (WESU). WESU is a residential university with over 22,000 students. This will be the first time in six years since WESU sponsored a spring concert. The entertainment council has bud- geted $40,000 for the project. The event is to occur on June 5th. Since your room- mate knows you are taking a class on project management she has asked you to review her scope statement and make suggestions for improvement. She considers the concert a resume-building experience and wants to be as professional as possible. Below is a draft of her scope statement. What suggestions would you make and why?

WESU Spring Music Concert

Project Objective To organize and deliver a 6-hour music concert

Deliverables

Milestones

1. Secure all permissions and approvals 2. Sign big-name artist 3. Contact secondary artists 4. Secure vendor contracts

5. Advertising campaign 6. Plan set-up 7. Concert 8. Clean-up

Technical Requirements

1. Professional sound stage and system 2. At least five performing acts 3. Restroom facilities 4. Parking 5. Compliance with WESU and city requirements/ordinances

Limits and Exclusions

Customer Review: WESU

Ashley, D. B., et al., “Determinants of Construction Project Success,” Project Man- agement Journal, vol. 18, no. 2 (June 1987), p. 72. Chilmeran, A. H., “Keeping Costs on Track,” PM Network, vol. 19, no. 2 (2004), pp. 45–51. Gary, L. “Will Project Scope Cost You—Or Create Value?” Harvard Management Update, January 2005. Gobeli, D. H., and E. W. Larson, “Project Management Problems,” Engineering Management Journal, vol. 2 (1990), pp. 31–36. Ingebretsen, M., “Taming the Beast,” PM Network, July 2003, pp. 30–35. Katz, D. M., “Case Study: Beware ‘Scope Creep’ on ERP Projects,” CFO.com, March 27, 2001. Kerzner, H., Project Management: A Systems Approach to Planning, 8th ed. (New York: Van Nostrand Reinhold, 2003). Lewis, J. P., Project Planning, Scheduling and Controlling, 3rd ed. (Burr Ridge, IL: McGraw-Hill, 2000). Luby, R. E., D. Peel, and W. Swahl, “Component-Based Work Breakdown Structure,” Project Management Journal, vol. 26, no. 2 (December 1995), pp. 38–44. Murch, R., Project Management: Best Practices for IT Professionals (Upper Darby, NJ: Prentice Hall, 2001). Pinto, J. K., and D. P. Slevin, “Critical Success Factors Across the Project Life Cycle,” Project Management Journal, vol. 19, no. 3 (June 1988), p. 72. Pitagorsky, G., “Realistic Project Planning Promotes Success,” Engineer’s Digest, vol. 29, no. 1 (2001). PMI Standards Committee, Guide to the Project Management Body of Knowledge (Newton Square, PA: Project Management Institute, 2000).

References

124 Chapter 4 Defining the Project

Posner, B. Z., “What It Takes to Be a Good Project Manager,” Project Management Journal, vol. 18, no. 1 (March 1987), p. 52. Raz, T., and S. Globerson, “Effective Sizing and Content Definition of Work Packages,” Project Management Journal, vol. 29, no. 4 (1998), pp. 17–23. The Standish Group, CHAOS Summary 2009, pp. 1–4. Tate, K., and K. Hendrix, “Chartering IT Projects,” Proceedings, 30th Annual, Project Management Institute (Philadelphia, PA. 1999), CD.

Case 4.1

Manchester United Soccer Club Nicolette Larson was loading the dishwasher with her husband, Kevin, and telling him about the first meeting of the Manchester United Tournament Organizing Committee. Nicolette, a self-confessed “soccer mom,” had been elected tournament director and was responsible for organizing the club’s first summer tournament. Manchester United Soccer Club (MUSC), located in Manchester, New Hampshire, was formed in 1992 as a way of bringing recreational players to a higher level of com- petition and preparing them for the State Olympic Development Program and/or high school teams. The club currently has 24 boys and girls (ranging in age from under 9 to 16) on teams affiliated with the New Hampshire Soccer Association and the Granite State Girls Soccer League. The club’s board of directors decided in the fall to sponsor a summer invitational soccer tournament to generate revenue. Given the boom in youth soccer, hosting summer tournaments has become a popular method for raising funds. MUSC teams regularly compete in three to four tournaments each summer at different locales in New England. These tournaments have been reported to generate between $50,000 and $70,000 for the host club. MUSC needs additional revenue to refurbish and expand the number of soccer fields at the Rock Rimmon soccer complex. Funds would also be used to augment the club’s scholarship program, which provides financial aid to players who cannot afford the $450 annual club dues. Nicolette gave her husband a blow-by-blow account of what transpired during the first tournament committee meeting that night. She started the meeting by having everyone introduce themselves and by proclaiming how excited she was that the club was going to sponsor its own tournament. She then suggested that the committee brainstorm what needed to be done to pull off the event; she would record their ideas on a flipchart. What emerged was a free-for-all of ideas and suggestions. One member immedi- ately stressed the importance of having qualified referees and spent several minutes describing in detail how his son’s team was robbed in a poorly officiated championship game. This was followed by other stories of injustice on the soccer field. Another member suggested that they needed to quickly contact the local colleges to see if they could use their fields. The committee spent more than 30 minutes talking about how they should screen teams and how much they should charge as an entry fee. An argu- ment broke out over whether they should reward the winning teams in each age bracket with medals or trophies. Many members felt that medals were too cheap, while others thought the trophies would be too expensive. Someone suggested that they seek local

Chapter 4 Defining the Project 125

126 Chapter 4 Defining the Project

corporate sponsors to help fund the tournament. The proposed sale of tournament T-shirts and sweatshirts was followed by a general critique of the different shirts par- ents had acquired at different tournaments. One member advocated that they recruit an artist he knew to develop a unique silk-screen design for the tournament. The meeting adjourned 30 minutes late with only half of the members remaining until the end. Nicolette drove home with seven sheets of ideas and a headache. As Kevin poured a glass of water for the two aspirin Nicolette was about to take, he tried to comfort her by saying that organizing this tournament would be a big project not unlike the projects he worked on at his engineering and design firm. He offered to sit down with her the next night and help her plan the project. He suggested that the first thing they needed to do was to develop a WBS for the project. 1. Make a list of the major deliverables for the project and use them to develop a draft

of the work breakdown structure for the tournament that contains at least three lev- els of detail. What are the major deliverables associated with hosting an event such as a soccer tournament?

2. How would developing a WBS alleviate some of the problems that occurred during the first meeting and help Nicolette organize and plan the project?

3. Where can Nicolette find additional information to help her develop a WBS for the tournament?

4. How could Nicolette and her task force use the WBS to generate cost estimates for the tournament? Why would this be useful information?

Case 4.2

The Home Improvement Project Lukas Nelson and his wife, Anne, and their three daughters had been living in their house for over five years when they decided it was time to make some modest improvements. One area they both agreed needed an upgrade was the bathtub. Their current house had one standard shower bathtub combination. Lukas was 6 feet four, and could barely squeeze into it. In fact, he had taken only one bath since they moved in. He and Anne both missed soaking in the older, deep bathtubs they enjoyed when they lived back East. Fortunately, the previous owners that built the house had plumbed the corner of a large exercise room in the basement for a hot tub. They contacted a trusted remodeling contractor who assured them it would be relatively easy to install a new bathtub and it shouldn’t cost more than $1,500. They decided to go ahead with the project. First the Nelsons went to the local plumbing retailer to pick out a tub. They soon realized that for a few hundred dollars more they could buy a big tub with water jets (a Jacuzzi). With old age on the horizon a Jacuzzi seemed like a luxury that was worth the extra money. Originally the plan was to install the tub using the simple plastic frame the bath came with and install a splash guard around the tub. Once Anne saw the tub, frame, and splashguard in the room she balked. She did not like how it looked with the cedar paneling in the exercise room. After significant debate, Ann won out, and the Nelsons agreed to pay extra to have a cedar frame built for the tub and use attractive tile instead of the plastic splashguard. Lukas rationalized the changes would pay for themselves when they tried to sell the house.

Chapter 4 Defining the Project 127

The next hiccup occurred when it came time to address the flooring issue. The exer- cise room was carpeted, which wasn’t ideal when getting out of a bathtub. The original idea was to install relatively cheap laminated flooring in the drying and undressing area adjacent to the tub. However, the Nelsons couldn’t agree on the pattern to use. One of Anne’s friends said it would be a shame to put such cheap flooring in such a nice room. She felt they should consider using tile. The contractor agreed and said he knew a tile installer who needed work and would give them a good deal. Lukas reluctantly agreed that the laminated options just didn’t fit the style or quality of the exercise room. Unlike the laminated floor debate both Anne and Lukas immedi- ately liked a tile pattern that matched the tile used around the tub. Anxious not to delay the project, they agreed to pay for the tile flooring. Once the tub was installed and the framing was almost completed, Anne realized that something had to be done about the lighting. One of her favorite things to do was to read while soaking in the tub. The existing lights didn’t provide sufficient illumina- tion for doing so. Lukas knew this was “non-negotiable” and they hired an electrician to install additional lighting over the bathtub. While the lighting was being installed and the tile was being laid, another issue came up. The original plan was to tile only the exercise room and use remnant rugs to cover the area away from the tub where the Nelsons did their exercises. The Nelsons were very happy with how the tile looked and fit with the overall room. However, it clashed with the laminated flooring in the adjacent bathroom. Lukas agreed with Ann, that it really made the adjacent bathroom look cheap and ugly. He also felt the bath- room was so small it wouldn’t cost much more. After a week the work was completed. Both Lukas and Anne were quite pleased with how everything turned out. It cost much more than they had planned, but they planned to live in the house until the girls graduated from college so they felt it was a good long-term investment. Anne had the first turn using the bathtub followed by their three girls. Everyone enjoyed the Jacuzzi. It was 10:00 p.m. when Lukas began running water for his first bath. At first the water was steaming hot, but by the time he was about to get in, it was lukewarm at best. Lukas groaned, “After paying all of that money I still can’t enjoy a bath.” The Nelsons rationed bathing for a couple weeks, until they decided to find out what if anything could be done about the hot water problem. They asked a reputable heating contractor to assess the situation. The contractor reported that the hot water tank was insufficient to service a family of five. This had not been discovered before because baths were rarely taken in the past. The contractor said it would cost $2,200 to replace the existing water heater with a larger one that would meet their needs. The heating contractor also said if they wanted to do it right they should replace the existing furnace with a more energy efficient one. A new furnace would not only heat the house but also indirectly heat the water tank. Such a furnace would cost $7,500, but with the improved efficiency and savings in the gas bill, the furnace would pay for itself in 10 years. Besides, the Nelsons would likely receive tax credits for the more fuel-efficient furnace. Three weeks later, after the new furnace was installed, Lukas settled into the new bathtub. He looked around the room at all the changes that had been made and mut- tered to himself, “And to think that all I wanted was to soak in a nice, hot bath.”

1. What factors and forces contributed to scope creep in this case? 2. Is this an example of good or bad scope creep? Explain. 3. How could scope creep have been better managed by the Nelsons?

128

Estimating Project Times and Costs5

LEARNING OBJECTIVES After reading this chapter you should be able to:

5-1 Understand estimating project times and costs are the foundation for project planning and control.

5-2 Describe guidelines for estimating time, costs, and resources.

5-3 Describe the methods, uses, and advantages and disadvantages of top-down and bottom-up esti- mating methods.

5-4 Distinguish different kinds of costs associated with a project.

5-5 Suggest a scheme for developing an estimating database for future projects.

5-6 Understand the challenge of estimating mega projects and describe steps that lead to better informed decisions.

5-7 Define a “white elephant” in project management and provide examples.

OUTLINE 5.1 Factors Influencing the Quality of Estimates

5.2 Estimating Guidelines for Times, Costs, and Resources

5.3 Top-Down versus Bottom-Up Estimating

5.4 Methods for Estimating Project Times and Costs

5.5 Level of Detail

5.6 Types of Costs

5.7 Refining Estimates

5.8 Creating a Database for Estimating

5.9 Mega Projects: A Special Case

Summary

Appendix 5.1: Learning Curves for Estimating

C H A P T E R F I V E

129

Project estimation is indeed a yardstick for project cost control. And if the yardstick is faulty, you start on the “wrong foot.” . . . We exhort you not to underestimate the estimate.*

Given the urgency to start work on the project, managers sometimes minimize or avoid the effort to follow through on estimating project time and cost. This attitude is a huge mistake and costly. There are important reasons to make the effort and incur the cost of estimating for your project. Exhibit 5.1 summarizes some key reasons. Estimating is the process of forecasting or approximating the time and cost of com- pleting project deliverables. Estimating processes are frequently classified as top-down and bottom-up. Top-down estimates are usually done by senior management. Manage- ment will often derive estimates from analogy, group consensus, or mathematical relationships. Bottom-up estimates are typically performed by the people who are

Project networks

6

Managing risk 7

Monitoring progress

13

Teams 11

Outsourcing 12

Project manager

10

Strategy 2

Introduction 1

Organization 3

Schedule resources & costs

8

Intern ation

al

proje cts

15

Agile PM 16

Project closure

14

Estimate 5

Reducing duration

9

Define project

4

* O. P. Kharbanda and J. K. Pinto, What Made Gertie Gallop: Learning from Project Failures (New York: Von Nostrand Rein- hold, 1996), p. 73.

Understand estimating project times and costs are the foundation for project planning and control.

5-1LO

130 Chapter 5 Estimating Project Times and Costs

doing the work. Their estimates are based on estimates of elements found in the work breakdown structure. All project stakeholders prefer accurate cost and time estimates, but they also under- stand the inherent uncertainty in all projects. Inaccurate estimates lead to false expec- tations and consumer dissatisfaction. Accuracy is improved with greater effort, but is it worth the time and cost?—estimating costs money! Project estimating becomes a trade-off, balancing the benefits of better accuracy against the costs for securing increased accuracy. Cost, time, and budget estimates are the lifeline for control; they serve as the stan- dard for comparison of actual and plan throughout the life of the project. Project status reports depend on reliable estimates as the major input for measuring variances and taking corrective action. Ideally, the project manager, and in most cases the customer, would prefer to have a database of detailed schedule and cost estimates for every work package in the project. Regrettably, such detailed data gathering is not always possible or practical and other methods are used to develop project estimates.

5.1 Factors Influencing the Quality of Estimates A typical statement in the field is the desire to “have a 95 percent probability of meet- ing time and cost estimates.” Past experience is a good starting point for developing time and cost estimates. But past experience estimates must almost always be refined by other considerations to reach the 95 percent probability level. Factors related to the uniqueness of the project will have a strong influence on the accuracy of estimates. Project, people, and external factors all need to be considered to improve quality of estimates for project times and costs.

Planning Horizon  The quality of the estimate depends on the planning horizon; estimates of current events are close to 100 percent accurate but are reduced for more distant events. For example, cost estimates for a party you are organizing this weekend should be much more accurate than the estimates for a party that will take place in six months. The accuracy of time and cost estimates should improve as you move from the conceptual phase to the point where individual work packages are defined. Long-duration projects increase the uncertainty in estimates.

Project Complexity  Time to implement new technology has a habit of expanding in an increasing, nonlin- ear fashion. Sometimes poorly written scope specifications for new technology result in errors in estimating times and costs.

Source: O. P. Kharbanda and J. K. Pinto, What Made Gertie Gallop: Learning from Project Failures (New York: Von Nostrand Reinhold, 1996), p. 73.

EXHIBIT 5.1 Why Estimating Time and Cost Is Important

Chapter 5 Estimating Project Times and Costs 131

People  The people factor can influence the quality of time and cost estimates. For example, accuracy of estimates depends on the skills of the people making the estimates. How familiar are they with the task they are estimating?

Project Structure and Organization  Which project structure is chosen to manage the project will influence time and cost estimates. One of the major advantages of a dedicated project team discussed earlier is the speed gained from concentrated focus and localized project decisions. This speed comes at an additional cost of tying up personnel full time. Conversely, projects operat- ing in a matrix environment may reduce costs by more efficiently sharing personnel across projects but may take longer to complete since attention is divided and coordi- nation demands are higher.

Padding Estimates  In some cases people are inclined to pad estimates. For example, if you are asked how long it takes you to drive to the airport, you might give an average time of 30  minutes, assuming a 50/50 chance of getting there in 30 minutes. If you are asked the fastest you could possibly get there, you might reduce the driving time to 20 minutes. Finally, if you are asked how long the drive would take if you abso- lutely had to be there to meet with the president, it is likely you would increase the estimate to say 50 minutes to ensure not being late. In work situations where you are asked for time and cost estimates, most of us are inclined to add a little padding to increase the probability and reduce the risk of being late. If everyone at all levels of the project adds a little padding to reduce risk, the project duration and cost are seri- ously overstated. This phenomenon causes some managers or owners to call for a 10–15 percent cut in time and/or cost for the project. Of course the next time the game is played, the person estimating cost and/or time will pad the estimate to 20 percent or more. Clearly such games defeat chances for realistic estimates, which is what is needed to be competitive.

Organization Culture  Organization culture can significantly influence project estimates. In some organiza- tions padding estimates is tolerated and even privately encouraged. Other organiza- tions place a premium on accuracy and strongly discourage estimating gamesmanship. Organizations vary in the importance they attach to estimates. The prevailing belief in some organizations is that detailed estimating takes too much time and is not worth the effort or that it’s impossible to predict the future. Other organizations subscribe to the belief that accurate estimates are the bedrock of effective project management. Orga- nization culture shapes every dimension of project management; estimating is not immune to this influence.

Other Factors  Finally, nonproject factors can impact time and cost estimates. For example, equip- ment down-time can alter time estimates. National holidays, vacations, and legal limits can influence project estimates. Project priority can influence resource assignment and impact time and cost.

132 Chapter 5 Estimating Project Times and Costs

Project estimating is a complex process. The quality of time and cost estimates can be improved when these variables are considered in making the estimates. Estimates of time and cost together allow the manager to develop a time-phased budget, which is imperative for project control. Before discussing macro and micro estimating methods for times and costs, a review of estimating guidelines will remind us of some of the important “rules of the game” that can improve estimating.

5.2 Estimating Guidelines for Times, Costs, and Resources Managers recognize time, cost, and resource estimates must be accurate if project planning, scheduling, and controlling are to be effective. However, there is substan- tial evidence suggesting poor estimates are a major contributor to projects that have failed. Therefore, every effort should be made to see that initial estimates are as accurate as possible since the choice of no estimates leaves a great deal to luck and is not palatable to serious project managers. Even though a project has never been done before, a manager can follow seven guidelines to develop useful work package estimates.

1. Responsibility. At the work package level, estimates should be made by the person(s) most familiar with the task. Draw on their expertise! Except for supertech- nical tasks, those responsible for getting the job done on schedule and within budget are usually first-line supervisors or technicians who are experienced and familiar with the type of work involved. These people will not have some preconceived, imposed duration for a deliverable in mind. They will give an estimate based on experience and best judgment. A secondary benefit of using those responsible is the hope they will “buy in” to seeing that the estimate materializes when they imple- ment the work package. If those involved are not consulted, it will be difficult to hold them responsible for failure to achieve the estimated time. Finally, drawing on the expertise of team members who will be responsible helps to build communica- tion channels early.

2. Use several people to estimate. It is well known that a cost or time estimate usually has a better chance of being reasonable and realistic when several people with rel- evant experience and/or knowledge of the task are used (sometimes called “crowd- sourcing”). True, people bring different biases based on their experience. But dis- cussion of the individual differences in their estimate leads to consensus and tends to eliminate extreme estimate errors.

3. Normal conditions. When task time, cost, and resource estimates are determined, they are based on certain assumptions. Estimates should be based on normal condi- tions, efficient methods, and a normal level of resources. Normal conditions are sometimes difficult to discern, but it is necessary to have a consensus in the organi- zation as to what normal conditions mean in this project. If the normal workday is eight hours, the time estimate should be based on an eight-hour day. Similarly, if the normal workday is two shifts, the time estimate should be based on a two-shift workday. Any time estimate should reflect efficient methods for the resources nor- mally available. The time estimate should represent the normal level of resources— people or equipment. For example, if three programmers are available for coding or two road graders are available for road construction, time and cost estimates should be based on these normal levels of resources unless it is anticipated the project will

Describe guidelines for estimating time, costs, and resources.

5-2LO

Chapter 5 Estimating Project Times and Costs 133

change what is currently viewed as “normal.” In addition, possible conflicts in demand for resources on parallel or concurrent activities should not be considered at this stage. The need for adding resources will be examined when resource sched- uling is discussed in a later chapter.

4. Time units. Specific time units to use should be selected early in the development phase of the project network. All task time estimates need consistent time units. Estimates of time must consider whether normal time is represented by calendar days, workdays, workweeks, person days, single shift, hours, minutes, etc. In prac- tice the use of workdays is the dominant choice for expressing task duration. How- ever, in projects such as a heart transplant operation, minutes probably would be more appropriate as a time unit. One such project that used minutes as the time unit was the movement of patients from an old hospital to an elegant new one across town. Since there were several life-endangering moves, minutes were used to ensure patient safety so proper emergency life-support systems would be available if needed. The point is, network analysis requires a standard unit of time. When com- puter programs allow more than one option, some notation should be made of any variance from the standard unit of time. If the standard unit of time is a five-day workweek and the estimated activity duration is in calendar days, it must be con- verted to the normal workweek.

5. Independence. Estimators should treat each task as independent of other tasks that might be integrated by the WBS. Use of first-line managers usually results in considering tasks independently; this is good. Top managers are prone to aggregate many tasks into one time estimate and then deductively make the indi- vidual task time estimates add to the total. If tasks are in a chain and performed by the same group or department, it is best not to ask for all the time estimates in the sequence at once to avoid the tendency for a planner or a supervisor to look at the whole path and try to adjust individual task times in the sequence to meet an arbitrary imposed schedule or some rough “guesstimate” of the total time for the whole path or segment of the project. This tendency does not reflect the uncertainties of individual activities and generally results in optimistic task time estimates. In summary, each task time estimate should be considered inde- pendently of other activities.

6. Contingencies. Work package estimates should not include allowances for contin- gencies. The estimate should assume normal or average conditions even though every work package will not materialize as planned. For this reason top manage- ment needs to create an extra fund for contingencies that can be used to cover unforeseen events.

7. Adding risk assessment to the estimate helps to avoid surprises to stakeholders. It is obvious some tasks carry more time and cost risks than others. For example, a new technology usually carries more time and cost risks than a proven process. Simply identifying the degree of risk lets stakeholders consider alternative methods and alter process decisions. A simple breakdown by optimistic, most likely, and pes- simistic for task time could provide valuable information regarding time and cost. See Chapter 7 for further discussion of project risk.

Where applicable, these guidelines will greatly help to avoid many of the pitfalls found so often in practice. See Snapshot from Practice 5.1: Reducing Estimating Errors for a similar set of guidelines.

134 Chapter 5 Estimating Project Times and Costs

5.3 Top-Down versus Bottom-Up Estimating Since estimating efforts cost money, the time and detail devoted to estimating are important decisions. Yet, when estimating is considered, you as a project manager may hear statements such as these:

Rough order of magnitude is good enough. Spending time on detailed estimating wastes money. Time is everything; our survival depends on getting there first! Time and cost accuracy is not an issue. The project is internal. We don’t need to worry about cost. The project is so small, we don’t need to bother with estimates. Just do it.

However, there are sound reasons for using top-down or bottom-up estimates. Table 5.1 depicts conditions that suggest when one approach is preferred over another. Top-down estimates usually are derived from someone who uses experience and/ or information to determine the project duration and total cost. However, these esti- mates are sometimes made by top managers who have very little knowledge of the component activities used to complete the project. For example, a mayor of a major

Describe the methods, uses, and advantages and disadvantages of top-down and bottom-up estimating methods.

5-3LO

Complexity is the major source of esti- mating error, says Kerry Willis, Project Management Sr. Director at the health- care services organization Cigna, in Hartford, Connecticut. “Project manag-

ers cannot possibly be experts in all areas and therefore need to rely on the stakeholders for their expertise when estimating,” Willis notes. To minimize errors he recommends treating estimating as a living process and not a one-time event. He follows the same approach on all of his projects:

1. Identify all of the stakeholders based on the scope of the project and organizational history.

2. Involve the stakeholders when creating the estimates. “You can’t hold people accountable for estimates they didn’t help create,” Willis says.

S N A P S H O T F R O M P R A C T I C E 5 . 1 Reducing Estimating Errors*

3. Aggregate the estimates by comparing several models (resource based, parametric, etc.).

4. Manage the project against the estimates. This includes making adjustments based on changes in project scope.

5. Track projects closely using tools such as earned value to gauge progress toward estimates.

6. Track actual costs and time at a granular level to recalibrate the model for future projects.

“The initial estimate could be perfect, but if it is not managed, then the end result will be bad and people will point to the estimating process,” Wills argues.

* S. Swanson, “Estimating Errors,” PMNetwork, October 2011, pp. 62–66.

TABLE 5.1 Conditions for Preferring Top-Down or Bottom-Up Time and Cost Estimates

Condition Top-Down Estimates Bottom-Up Estimates

Strategic decision making X Cost and time important X High uncertainty X Internal, small project X Fixed-price contract X Customer wants details X Unstable scope X

Chapter 5 Estimating Project Times and Costs 135

city making a speech noted that a new law building would be constructed at a cost of $23 million and would be ready for occupancy in two and one-half years. Although the mayor probably asked for an estimate from someone, the estimate could have come from a luncheon meeting with a local contractor who wrote an estimate (guesstimate) on a napkin. This is an extreme example, but in a relative sense this scenario is fre- quently played out in practice. See Snapshot from Practice 5.2: Council Fumes, for another example of this. The question actually is, do these estimates represent low- cost, efficient methods? Seldom. The fact that the estimate came from the top can influence people responsible to “do what it takes to make the estimate.” If possible and practical, you want to push the estimating process down to the work package level for bottom-up estimates that establish low-cost, efficient methods. This process can take place after the project has been defined in detail. Good sense suggests project estimates should come from the people most knowledgeable about the estimate needed. The use of several people with relevant experience with the task can improve the time and cost estimate. The bottom-up approach at the work package level can serve as a check on cost elements in the WBS by rolling up the work packages and associated cost accounts to major deliverables. Similarly, resource requirements can be checked. Later, the time, resource, and cost estimates from the work packages can be consolidated into time-phased networks, resource schedules, and budgets that are used for control. The bottom-up approach also provides the customer with an opportunity to compare the low-cost, efficient method approach with any imposed restrictions. For example, if the project completion duration is imposed at two years and your bottom-up analysis tells you the project will take two and one-half years, the client can now consider the trade-off of the low-cost method versus compressing the project to two years—or in

Portland, Oregon’s, Willamette riverfront development has exploded with seven condominium towers and a new health sciences center under construction. The health science complex is to be

linked with Oregon Health Sciences University (OHSU), which is high on a nearby hill, with an aerial cable tram. The aerial tram linking the waterfront district to OHSU is to support the university expansion, to increase biotech- nology research, and to become Portland’s icon equiva- lent to Seattle’s Space Needle. All of the hype turned south when news from a hearing suggested that the real budget for the tram construction, originally estimated at $15 million, is going to be about $55–$60 million, more than triple the original estimate. The estimate could even go higher.  Commissioners want to find out why city staff knowingly relied on flawed estimates. Mike Lindberg, president of the nonprofit Aerial Transportation Inc., acknowledged “the $15 million number was not a good number. It was simply a guesstimate.” Commissioner

S N A P S H O T F R O M P R A C T I C E 5 . 2 Council Fumes as Tram Tale Unfolds*

© Spaces Images/Blend Images LLC

* The Oregonian, January 13, 2006, by Frank Ryan, pages A1 and A14, and April 2, 2006, page A1.

Erik Sten said, “Those numbers were presented as much more firm than they appear to have been. . . . It appears the actual design wasn’t costed out. That’s pretty shoddy.”

136 Chapter 5 Estimating Project Times and Costs

rare cases canceling the project. Similar trade-offs can be compared for different levels of resources or increases in technical performance. The assumption is any movement away from the low-cost, efficient method will increase costs—e.g., overtime. The pre- ferred approach in defining the project is to make rough top-down estimates, develop the WBS/OBS, make bottom-up estimates, develop schedules and budgets, and recon- cile differences between top-down and bottom-up estimates. Hopefully, these steps will be done before final negotiation with either an internal or external customer. In conclusion, the ideal approach is for the project manager to allow enough time for both the top-down and bottom-up estimates to be worked out so a complete plan based on reliable estimates can be offered to the customer. In this way false expectations are minimized for all stakeholders and negotiation is reduced.

5.4 Methods for Estimating Project Times and Costs

Top-Down Approaches for Estimating Project Times and Costs At the strategic level top-down estimating methods are used to evaluate the project proposal. Sometimes much of the information needed to derive accurate time and cost estimates is not available in the initial phase of the project—for example, design is not finalized. In these situations top-down estimates are used until the tasks in the WBS are clearly defined.

Consensus Methods  This method simply uses the pooled experience of senior and/or middle managers to estimate the total project duration and cost. This typically involves a meeting where experts discuss, argue, and ultimately reach a decision as to their best guess estimate. Firms seeking greater rigor will use the Delphi Method to make these macro estimates. See Snapshot from Practice 5.3: The Delphi Method.

Originally developed by the RAND Corporation in 1969 for technological forecasting, the Delphi Method is a group decision process about the like- lihood that certain events will occur.

The Delphi Method makes use of a panel of experts familiar with the kind of project in question. The notion is that well-informed individuals, calling on their insights and experience, are better equipped to esti- mate project costs/times than theoretical approaches or statistical methods. Their responses to estimate questionnaires are anonymous, and they are provided with a summary of opinions. Experts are then encouraged to reconsider, and if appropriate, to change their previous estimate in light of the replies of other experts. After two or three rounds it is believed that the group will converge toward the

S N A P S H O T F R O M P R A C T I C E 5 . 3 The Delphi Method

“best” response through this consensus process. The midpoint of responses is statistically categorized by the median score. In each succeeding round of question- naires, the range of responses by the panelists will pre- sumably decrease and the median will move toward what is deemed to be the “correct” estimate. One distinct advantage of the Delphi Method is that the experts never need to be brought together physi- cally. The process also does not require complete agreement by all panelists, since the majority opinion is represented by the median. Since the responses are anonymous, the pitfalls of ego, domineering personali- ties, and the “bandwagon or halo effect” in responses are all avoided. On the other hand, future develop- ments are not always predicted correctly by iterative consensus nor by experts, but at times by creative, “off the wall” thinking.

Chapter 5 Estimating Project Times and Costs 137

It is important to recognize that these first top-down estimates are only a rough cut and typically occur in the “conceptual” stage of the project. The top-down estimates are helpful in initial development of a complete plan. However, such estimates are sometimes significantly off the mark because little detailed information is gathered. At this level individual work items are not identified. Or, in a few cases, the top-down estimates are not realistic because top management “wants the project.” Nevertheless, the initial top-down estimates are helpful in determining whether the project warrants more formal planning, which would include more detailed estimates. Be careful that macro estimates made by senior managers are not dictated to lower level managers who might feel compelled to accept the estimates even if they believe resources are inadequate. Although your authors prefer to avoid the top-down approach if possible, we have witnessed surprising accuracy in estimating project duration and cost in isolated cases. Some examples are building a manufacturing plant, building a distribution warehouse, developing air control for skyscraper buildings, and road construction. However, we have also witnessed some horrendous miscalculations, usually in areas where the tech- nology is new and unproven. Top-down methods can be useful if experience and judg- ment have been accurate in the past.

Ratio Methods  Top-down methods (sometimes called parametric) usually use ratios, or surrogates, to estimate project times or costs. Top-down approaches are often used in the concept or “need” phase of a project to get an initial duration and cost estimate for the project. For example, contractors frequently use number of square feet to estimate the cost and time to build a house; that is, a house of 2,700 square feet might cost $160 per square foot (2,700 feet × $160 per foot equals $432,000). Likewise, knowing the square feet and dollars per square foot, experience suggests it should take approximately 100 days to complete. Two other common examples of top-down cost estimates are the cost for a new plant estimated by capacity size, or a software product estimated by features and complexity.

Apportion Methods  This method is an extension to the ratio method. Apportionment is used when proj- ects closely follow past projects in features and costs. Given good historical data, estimates can be made quickly with little effort and reasonable accuracy. This method is very common in projects that are relatively standard but have some small variation or customization. Anyone who has borrowed money from a bank to build a house has been exposed to this process. Given an estimated total cost for the house, banks and the FHA (Federal Housing Authority) authorize pay to the contractor by completion of specific segments of the house. For example, foundation might represent 3 percent of the total loan, fram- ing 25 percent, plumbing and heating 15 percent, etc. Payments are made as these items are completed. An analogous process is used by some companies that apportion costs to deliverables in the WBS—given average cost percentages from past projects. Figure 5.1 presents an example similar to one found in practice. Assuming the total project cost is estimated, using a top-down estimate, to be $500,000, the costs are apportioned as a percentage of the total cost. For example, the costs apportioned to the “Document” deliverable are 5 percent of the total, or $25,000. The subdeliverables “Doc-1 and Doc-2” are allocated 2 and 3 percent of the total—$10,000 and $15,000, respectively.

138 Chapter 5 Estimating Project Times and Costs

Function Point Methods for Software and System Projects  In the software industry, software development projects are frequently estimated using weighted macro variables called “function points” or major parameters such as num- ber of inputs, number of outputs, number of inquiries, number of data files, and num- ber of interfaces. These weighted variables are adjusted for a complexity factor and added. The total adjusted count provides the basis for estimating the labor effort and cost for a project (usually using a regression formula derived from data of past proj- ects). This latter method assumes adequate historical data by type of software project for the industry—for example, MIS systems. In the U.S. software industry, one person- month represents on average five function points. A person working one month can generate on average (across all types of software projects) about five function points. Of course each organization needs to develop its own average for its specific type of work. Such historical data provide a basis for estimating the project duration. Varia- tions of this top-down approach are used by companies such as IBM, Bank of America, Sears Roebuck, HP, AT&T, Ford Motors, GE, DuPont, and many others. See Table 5.2 and Table 5.3 for a simplified example of function point count methodology. From historical data the organization developed the weighting scheme for complex- ity found in Table 5.2. Function points are derived from multiplying the number of kinds of elements by weighted complexity.

Total project cost $500,000

Design 20%

100,000

D-1 10%

50,000

D-2 10%

50,000

Program 30%

150,000

Test 40%

200,000

Document 5%

25,000

Produce CD 5%

25,000

Doc-1 2%

10,000

Doc-2 3%

15,000

CD-1 5%

25,000

P-1 20%

100,000

P-2 5%

25,000

P-3 5%

25,000

T-1 10%

50,000

T-2 10%

50,000

T-3 20%

100,000

FIGURE 5.1 Apportion Method of Allocating Project Costs Using the Work Breakdown Structure

TABLE 5.2 Simplified Basic Function Point Count Process for a Prospective Project or Deliverable

Complexity Weighting

Element Low Average High Total

Number of inputs _____ × 2 + _____ × 3 + _____ × 4 = _____ Number of outputs _____ × 3 + _____ × 6 + _____ × 9 = _____ Number of inquiries _____ × 2 + _____ × 4 + _____ × 6 = _____ Number of files _____ × 5 + _____ × 8 + _____ × 12 = _____ Number of interfaces _____ × 5 + _____ × 10 + _____ × 15 = _____

Chapter 5 Estimating Project Times and Costs 139

Table 5.3 shows the data collected for a specific task or deliverable: Patient Admit- ting and Billing—the number of inputs, outputs, inquiries, files, and interfaces along with the expected complexity rating. Finally, the application of the element count is applied and the function point count total is 660. Given this count and the fact that one person-month has historically been equal to 5 function points, the job will require 132 person-months (660/5 = 132). Assuming you have 10 programmers who can work on this task, the duration would be approximately 13 months. The cost is easily derived by multiplying the labor rate per month times 132 person-months. For example, if the monthly programmer rate is $4,000, then the estimated cost would be $528,000 (132 × 4,000). Although function point metrics are useful, their accuracy depends on adequate historical data, currency of data, and relevancy of the project/deliverable to past averages.

Learning Curves  Some projects require that the same task, group of tasks, or product be repeated several times. Managers know intuitively that the time to perform a task improves with repeti- tion. This phenomenon is especially true of tasks that are labor intensive. In these cir- cumstances the pattern of improvement phenomenon can be used to predict the reduc- tion in time to perform the task. From empirical evidence across all industries, the pattern of this improvement has been quantified in the learning curve (also known as improvement curve, experience curve, and industrial progress curve), which is described by the following relationship: Each time the output quantity doubles, the unit labor hours are reduced at a constant rate.

In practice the improvement ratio may vary from 60 percent, representing very large improvement, to 100 percent, representing no improvement at all. Generally, as the difficulty of the work decreases the expected improvement also decreases and the improvement ratio that is used becomes greater. One significant factor to consider is the proportion of labor in the task in relation to machine-paced work. Obviously, a lower percentage of improvement can occur only in operations with high labor content. Appendix 5.1 at the end of the chapter provides a detailed example of how the improve- ment phenomenon can be used to estimate time and cost for repetitive tasks.

TABLE 5.3 Example: Function Point Count Method

Software Project 13: Patient Admitting and Billing

15 Inputs Rated complexity as low (2) 5 Outputs Rated complexity as average (6) 10 Inquiries Rated complexity as average (4) 30 Files Rated complexity as high ##(12) 20 Interfaces Rated complexity as average #(10)

Application of Complexity Factor

Element Count Low Average High Total

Inputs ####15 × 2 = 30 Outputs 5 ×  6 = 30 Inquiries ###10 ×  4 = 40 Files 30 × 12 = 360 Interfaces 20 × 10 = 200 Total 660

140 Chapter 5 Estimating Project Times and Costs

The main disadvantage of top-down approaches to estimating is simply that the time and cost for a specific task are not considered. Grouping many tasks into a common basket encourages errors of omission and the use of imposed times and costs. Micro estimating methods are usually more accurate than macro methods.

Bottom-Up Approaches for Estimating Project Times and Costs Template Methods  If the project is similar to past projects, the costs from past projects can be used as a starting point for the new project. Differences in the new project can be noted and past times and costs adjusted to reflect these differences. For example, a ship repair dry- dock firm has a set of standard repair projects (i.e., templates for overhaul, electrical, mechanical) that are used as starting points for estimating the cost and duration of any new project. Differences from the appropriate standardized project are noted (for times, costs, and resources) and changes are made. This approach enables the firm to develop a potential schedule, estimate costs, and develop a budget in a very short time span. Development of such templates in a database can quickly reduce estimate errors.

Parametric Procedures Applied to Specific Tasks  Just as parametric techniques such as cost per square foot can be the source of top- down estimates, the same technique can be applied to specific tasks. For example, as part of an MS Office conversion project, 36 different computer workstations needed to be converted. Based on past conversion projects, the project manager determined that on average one person could convert three workstations per day. Therefore the task of converting the 36 workstations would take three technicians four days [(36/3)/3]. Simi- larly, to estimate the wallpapering allowance on a house remodel, the contractor fig- ured a cost of $5 per square yard of wallpaper and $2 per yard to install it, for a total cost of $7. By measuring the length and height of all the walls she was able to calculate the total area in square yards and multiply it by $7.

Range Estimating  When do you use range estimating? Range estimating works best when work packages have significant uncertainty associated with the time or cost to complete. If the work pack- age is routine and carries little uncertainty, using a person most familiar with the work package is usually the best approach. She is likely to know best how to estimate work packages durations and costs. However, when work packages have significant uncertainty associated with the time or cost to complete, it is a prudent policy to require three time estimates—low, average, and high (borrowed from PERT methodology that uses proba- bility distributions). The low to high give a range within which the average estimate will fall. Determining the low and high estimates for the activity is influenced by factors such as complexity, technology, newness, familiarity. How do you get the estimates? Since range estimating works best for work packages that have significant uncertainty, having a group determine the low, average, and high cost or duration gives best results. Group estimating tends to refine extremes by bringing more evaluative judgments to the estimate and potential risks. The judgment of others in a group helps to moderate extreme perceived risks associated with a time or cost estimate. Involving others in making activity estimates gains buy-in and credibility to the estimate. Figure 5.2 presents an abridged estimating template using three time estimates for work packages developed by a cross functional group(s) of project stakeholders. The group estimates show the low, average, and high for each work package. The Risk

Chapter 5 Estimating Project Times and Costs 141

Level column is the group’s independent assessment of the degree of confidence that the actual time will be very close to the estimate. In a sense this number represents the group’s evaluation of many factors (e.g., complexity, technology) that might impact the average time estimate. In our example, the group feels work packages 104, 108, 110, 111, and 114 have a high chance that the average time may vary from expected. Likewise, the group’s confidence feels the risk of work packages 102, 105, and 112 not materializing as expected is low. How do you use the estimate? Group range estimating gives the project manager and owner an opportunity to assess the confidence associated with project times (and/or costs). For example, a contractor responsible for building a high rise apartment building can tell the owner that the project will cost between 3.5 and 4.1 million dollars and take between six and nine months to complete. The approach helps to reduce surprises as the project progresses. The range estimating method also provides a basis for assessing risk, managing resources, and determining the project contingency fund. (See Chapter 7 for a discussion of contingency funds.) Range estimating is popular in software and new product projects where up-front requirements are fuzzy and not well known. Group range estimating is often used with phase estimating, which is discussed next.

A Hybrid: Phase Estimating This approach begins with a top-down estimate for the project and then refines esti- mates for phases of the project as it is implemented. Some projects by their nature cannot be rigorously defined because of the uncertainty of design or the final product. Although rare, such projects do exist. These projects are often found in aerospace proj- ects, IT projects, new technology projects, and construction projects where design is incomplete. In these projects, phase or life-cycle estimating is frequently used. Phase estimating is used when an unusual amount of uncertainty surrounds a proj- ect and it is impractical to estimate times and costs for the entire project. Phase estimat- ing uses a two-estimate system over the life of the project. A detailed estimate is developed for the immediate phase and a macro estimate is made for the remaining phases of the project. Figure 5.3 depicts the phases of a project and the progression of estimates over its life.

FIGURE 5.2 Range Estimating Template

142 Chapter 5 Estimating Project Times and Costs

For example, when the project need is determined, a macro estimate of the project cost and duration is made so analysis and decisions can be made. Simultaneously a detailed estimate is made for deriving project specifications and a macro estimate for the remainder of the project. As the project progresses and specifications are solidi- fied, a detailed estimate for design is made and a macro estimate for the remainder of the project is computed. Clearly, as the project progresses through its life cycle and more information is available, the reliability of the estimates should be improving. See Snapshot from Practice 5.4: Estimate Accuracy. Phase estimating is preferred by those working on projects where the final product is not known and the uncertainty is very large—for example, the integration of wireless phones and computers. The commitment to cost and schedule is only necessary over the next phase of the project and commitment to unrealistic future schedules and costs based on poor information is avoided. This progressive macro/micro method provides a stron- ger basis for using schedule and cost estimates to manage progress during the next phase.

FIGURE 5.3 Phase Estimating over Project Life Cycle

Phase

1

Need 1

Specifications 2

Detailed estimate

Design 3

Produce 4

Deliver 5

Detailed estimate

Detailed estimate

Detailed estimate

2

3

4

5

Macro estimate

Macro estimate

Macro estimate

Macro estimate

The smaller the element of a work package, the more accurate the over- all estimate is likely to be. The extent of this improvement varies by type of project. The table below is developed

to reflect this observation. For example, information technology projects that determine their time and cost estimates in the conceptual stage can expect their “actuals” to err up to 200 percent over cost and

S N A P S H O T F R O M P R A C T I C E 5 . 4 Estimate Accuracy

duration and, perhaps, as much as 30 percent under estimates. Conversely, estimates for buildings, roads, etc., made after the work packages are clearly defined, have a smaller error in actual costs and times of 15 per- cent over estimate and 5 percent less than estimate. Although these estimates vary by project, they can serve as ballpark numbers for project stakeholders selecting how project time and cost estimates will be derived.

Time and Cost Estimate Accuracy by Type of Project

Bricks and Mortar Information Technology

Conceptual stage +60% to −30% +200% to −30% Deliverables defined +30% to − 15% + 100% to − 15% Work packages defined + 15% to − 5% + 50% to − 5%

Chapter 5 Estimating Project Times and Costs 143

Unfortunately your customer—internal or external—will want an accurate estimate of schedule and cost the moment the decision is made to implement the project. Addi- tionally, the customer who is paying for the project often perceives phase estimating as a blank check because costs and schedules are not firm over most of the project life cycle. Even though the reasons for phase estimating are sound and legitimate, most customers have to be sold on its legitimacy. A major advantage for the customer is the opportunity to change features, re-evaluate, or even cancel the project in each new phase. In conclusion, phase estimating is very useful in projects that possess huge uncertainties concerning the final nature (shape, size, features) of the project. See Figure 5.4 for a summary of the differences between top-down and bottom-up estimates. Obtaining accurate estimates is a challenge. Committed organizations accept the challenge of coming up with meaningful estimates and invest heavily in developing their capacity to do so. Accurate estimates reduce uncertainty and support a discipline for effectively managing projects.

5.5 Level of Detail Level of detail is different for different levels of management. At any level the detail should be no more than is necessary and sufficient. Top management interests usually center on the total project and major milestone events that mark major accomplishments—e.g., “Build Oil Platform in the North Sea” or “Complete Proto- type.” Middle management might center on one segment of the project or one mile- stone. First-line managers’ interests may be limited to one task or work package. One of the beauties of WBS is the ability to aggregate network information so each level of management can have the kind of information necessary to make decisions. Getting the level of detail in the WBS to match management needs for effective implementation is crucial, but the delicate balance is difficult to find. See Snapshot from Practice 5.5: Level of Detail. The level of detail in the WBS varies with the

Top-Down Estimates

Bottom-Up Estimates

Intended Use Feasibility/conceptual phase

Rough time/cost estimate Fund requirements

Resource capacity planning

Intended Use Budgeting Scheduling

Resource requirements Fund timing

Preparation Cost 1/10 to 3/10 of a percent

of total project cost

Preparation Cost 3/10 of a percent

to 1.0 percent of total project cost

Accuracy Minus 20%, to plus 60%

Accuracy Minus 10%, to plus 30%

Method Consensus

Ratio Apportion

Function point Learning curves

Method Template

Parametric WBS packages

Range estimates

FIGURE 5.4 Top-Down and Bottom-Up Estimates

144 Chapter 5 Estimating Project Times and Costs

complexity of the project; the need for control; the project size, cost, duration; and other factors. If the structure reflects excessive detail, there is a tendency to break the work effort into department assignments. This tendency can become a barrier to suc- cess, since the emphasis will be on departmental outcomes rather than on deliverable outcomes. Excessive detail also means more unproductive paperwork. Note that if the level of the WBS is increased by one, the number of cost accounts may increase geo- metrically. On the other hand, if the level of detail is not adequate, an organization unit may find the structure falls short of meeting its needs. Fortunately, the WBS has built- in flexibility. Participating organization units may expand their portion of the structure to meet their special needs. For example, the engineering department may wish to further break their work on a deliverable into smaller packages by electrical, civil, and mechanical. Similarly, the marketing department may wish to break their new product promotion into TV, radio, periodicals, and newspapers.

5.6 Types of Costs Assuming work packages are defined, detailed cost estimates can be made. Here are typical kinds of costs found in a project: 1. Direct costs

a. Labor c. Equipment b. Materials d. Other

2. Direct project overhead costs 3. General and administrative (G&A) overhead costs

Distinguish different kinds of costs associated with a project.

5-4LO

Practicing project managers advocate keeping the level of detail to a mini- mum. But there are limits to this sug- gestion. One of the most frequent errors of new project managers is to

forget that the task time estimate will be used to control schedule and cost performance. A frequent rule of thumb used by practicing project managers says that a task duration should not exceed 5 workdays or at the most 10 workdays, if workdays are the time units used for the project. Such a rule probably will result in a more detailed network, but the additional detail pays off in controlling schedule and cost as the project progresses. Suppose the task is “build prototype computer- controlled conveyor belt,” the time estimate is 40 work- days, and the budget $300,000. It may be better to divide the task into seven or eight smaller tasks for control purposes. If one of the smaller tasks gets behind because of problems or a poor time estimate, it will be possible to take corrective action quickly and avoid delaying successive tasks and the project. If the

S N A P S H O T F R O M P R A C T I C E 5 . 5 Level of Detail—Rule of Thumb

single task of 40 workdays is used, it is possible that no corrective action would be taken until day 40, since many people have a tendency to “wait and see” or avoid admitting they are behind or passing on bad news; the result may mean far more than 5 days behind schedule. The 5- to 10-day rule of thumb applies to cost and performance goals. If using the rule of thumb sug- gested above results in too many network tasks, an alternative is available, but it has conditions. The activ- ity time can be extended beyond the 5- to 10-day rule only IF control monitoring checkpoints for segments of the task can be established so clear measures of prog- ress can be identified by a specific percent complete. This information is invaluable to the control process of measuring schedule and cost performance—for example, payments for contract work are paid on “per- cent complete” basis. Defining a task with clear defin- able start and end points and intermediate points enhances the chances of early detection of problems, corrective action, and on-time project completion.

Chapter 5 Estimating Project Times and Costs 145

The total project cost estimate is broken down in this fashion to sharpen the control process and improve decision making.

Direct Costs  These costs are clearly chargeable to a specific work package. Direct costs can be influenced by the project manager, project team, and individuals implementing the work package. These costs represent real cash outflows and must be paid as the project progresses; therefore, direct costs are usually separated from overhead costs. Lower- level project rollups frequently include only direct costs.

Direct Project Overhead Costs  Direct overhead rates more closely pinpoint which resources of the organization are being used in the project. Direct project overhead costs can be tied to project deliver- ables or work packages. Examples include the salary of the project manager and tem- porary rental space for the project team. Although overhead is not an immediate out- of-pocket expense, it is real and must be covered in the long run if the firm is to remain viable. These rates are usually a ratio of the dollar value of the resources used—e.g., direct labor, materials, equipment. For example, a direct labor burden rate of 20 per- cent would add a direct overhead charge of 20 percent to the direct labor cost estimate. A direct charge rate of 50 percent for materials would carry an additional 50 percent charge to the material cost estimate. Selective direct overhead charges provide a more accurate project (job or work package) cost, rather than using a blanket overhead rate for the whole project.

General and Administrative (G&A) Overhead Costs  These represent organization costs that are not directly linked to a specific project. These costs are carried for the duration of the project. Examples include organization costs across all products and projects such as advertising, accounting, and senior man- agement above the project level. Allocation of G&A costs varies from organization to organization. However, G&A costs are usually allocated as a percent of total direct cost, or a percent of the total of a specific direct cost such as labor, materials, or equipment. Given the totals of direct and overhead costs for individual work packages, it is pos- sible to cumulate the costs for any deliverable or for the entire project. A percentage can be added for profit if you are a contractor. A breakdown of costs for a proposed contract bid is presented in Figure 5.5. Perceptions of costs and budgets vary depending on their users. The project manager must be very aware of these differences when setting up the project budget and when communicating these differences to others. Figure 5.6 depicts these different

FIGURE 5.5 Contract Bid Summary Costs

Direct costs $80,000 Direct overhead  ###$20,000 Total direct costs $100,000 G&A overhead (20%)  ###$20,000 Total costs $120,000 Profit (20%)  ###$24,000 Total bid $144,000

146 Chapter 5 Estimating Project Times and Costs

perceptions. The project manager can commit costs months before the resource is used. This information is useful to the financial officer of the organization in forecasting future cash outflows. The project manager is interested in when the budgeted cost is expected to occur, and when the budgeted cost actually is charged (earned); the respective timings of these two cost figures are used to measure project schedule and cost variances.

5.7 Refining Estimates As described earlier in Chapter 4, detailed work package estimates are aggregated and “rolled up” by deliverable to estimate the total direct cost of the project. Similarly, esti- mated durations are entered into the project network to establish the project schedule and determine the overall duration of the project. Experience tells us that for many projects the total estimates do not materialize and the actual costs and schedule of some projects significantly exceed original work package–based estimates. In order to compensate for the problem of actual cost and schedule exceeding estimates, some project managers adjust total costs by some multiplier (i.e., total estimated costs × 1.20). The practice of adjusting original estimates by 20 percent or even 100 percent begs the question of why, after investing so much time and energy on detailed estimates, the numbers could be so far off. There are a number of reasons for this, most of which can be traced to the estimating process and the inherent uncertainty of predicting the future. Some of these reasons are discussed below. ∙ Interaction costs are hidden in estimates. According to the guidelines, each task

estimate is supposed to be done independently. However, tasks are rarely completed in a vacuum. Work on one task is dependent upon prior tasks, and the hand-offs between tasks require time and attention. For example, people working on prototype development need to interact with design engineers after the design is completed, whether to simply ask clarifying questions or to make adjustments in the original design. Similarly, the time necessary to coordinate activities is typically not reflected in independent estimates. Coordination is reflected in meetings and briefings as

Committed

Actual cost

Scheduled budget

$6,000

5,000

4,000

3,000

2,000

1,000

Project duration

C os

ts

FIGURE 5.6 Three Views of Cost

Chapter 5 Estimating Project Times and Costs 147

well as time necessary to resolve disconnects between tasks. Time, and therefore cost, devoted to managing interactions rises exponentially as the number of people and different disciplines involved increases on a project.

∙ Normal conditions do not apply. Estimates are supposed to be based on normal conditions. While this is a good starting point, it rarely holds true in real life. This is especially true when it comes to the availability of resources. Resource shortages, whether in the form of people, equipment, or materials, can extend original estimates. For example, under normal conditions four bulldozers are typically used to clear a certain site size in five days, but the availability of only three bulldozers would extend the task duration to eight days. Similarly, the decision to outsource certain tasks can increase costs as well as extend task durations since time is added to acclimating out- siders to the particulars of the project and the culture of the organization.

∙ Things go wrong on projects. Design flaws are revealed after the fact, extreme weather conditions occur, accidents happen, and so forth. Although you shouldn’t plan for these risks to happen when estimating a particular task, the likelihood and impact of such events need to be considered.

∙ Changes in project scope and plans. As one gets further and further into the proj- ect, a manager obtains a better understanding of what needs to be done to accom- plish the project. This may lead to major changes in project plans and costs. Like- wise, if the project is a commercial project, changes often have to be made midstream to respond to new demands by the customer and/or competition. Unstable project scopes are a major source of cost overruns. While every effort should be made up front to nail down the project scope, it is becoming increasingly difficult to do so in our rapidly changing world.

∙ Overly optimistic. There is solid research indicating that there is a tendency in people to overestimate how quickly they can get things done and underestimate how long it will take them to complete tasks (Lovallo, D., and D. Kahneman, 2003; Buehler, R., D. Griffin, and M. Ross, 1994).

∙ Strategic misrepresentation. There is growing evidence that some project promot- ers underestimate the costs of projects and overestimate project benefits in order to win approval. This appears to be particularly true for large-scale public works proj- ects which have a notorious habit of coming in way over budget (remember the earlier Snapshot from Practice 5.2: Council Fumes).

The reality is that for many projects not all of the information needed to make accu- rate estimates is available, and it is impossible to predict the future. The challenge is further compounded by human nature and the political dynamics associated with gain- ing project approval. The dilemma is that without solid estimates, the credibility of the project plan is eroded. Deadlines become meaningless, budgets become rubbery, and accountability becomes problematic. Challenges similar to those described above will influence the final time and cost estimates. Even with the best estimating efforts, it may be necessary to revise estimates based on relevant information prior to establishing a baseline schedule and budget. Effective organizations adjust estimates of specific tasks once risks, resources, and particulars of the situation have been more clearly defined. They recognize that the rolled- up estimates generated from a detailed estimate based on the WBS are just the starting point. As they delve further into the project-planning process, they make appropriate revi- sions both in the time and cost of specific activities. They factor the final assignment of resources into the project budget and schedule. For example, when they realize that only

148 Chapter 5 Estimating Project Times and Costs

three instead of four bulldozers are available to clear a site, they adjust both the time and cost of that activity. They adjust estimates to account for specific actions to mitigate poten- tial risks on the project. For example, to reduce the chances of design code errors, they would add the cost of independent testers to the schedule and budget. Finally, organizations adjust estimates to take into account abnormal conditions. For example, if soil samples reveal excessive ground water, then they adjust foundation costs and times. There will always be some mistakes, omissions, and adjustments that will require addi- tional changes in estimates. Fortunately every project should have a change management system in place to accommodate these situations and any impact on the project baseline. Change management and contingency funds will be discussed later in Chapter 7.

5.8 Creating a Database for Estimating The best way to improve estimates is to collect and archive data on past project esti- mates and actuals. Saving historical data—estimates and actuals—provides a knowl- edge base for improving project time and cost estimating. Creating an estimating data- base is a “best practice” among leading project management organizations. Some organizations have large estimating departments of professional estimators— e.g., Boeing, IBM—that have developed large time and cost databases. Others collect these data through the project office. This database approach allows the project estima- tor to select a specific work package item from the database for inclusion. The estima- tor then makes any necessary adjustments concerning the materials, labor, and equip- ment. Of course any items not found in the database can be added to the project—and ultimately to the database if desired. Again, the quality of the database estimates depends on the experience of the estimators, but over time the data quality should improve. Such structured databases serve as feedback for estimators and as bench- marks for cost and time for each project. In addition, comparison of estimate and actual for different projects can suggest the degree of risk inherent in estimates. See Figure 5.7 for the structure of a database similar to those found in practice.

Suggest a scheme for developing an estimating database for future projects.

5-5LO

FIGURE 5.7 Estimating Database Templates

Estimating database

Operation processes

Risk analysis

Documentation

Hardware MIS

EXAMPLE

1. Estimated & actuals on A. Labor B. Materials C. Equipment 2. Benchmarking ratios 3. Code of accounts

Product production

Programming

Chapter 5 Estimating Project Times and Costs 149

5.9 Mega Projects: A Special Case Mega projects are large-scale, complex ventures that typically cost $1 billion or more, take many years to complete, and involve multiple private and public stakeholders. They are often transformational, and impact millions of people (Flyvbjerg, 2014). Examples include high-speed rail lines, airports, healthcare reform, the Olympics, development of new aircraft, and so forth. What do these projects have in common beyond scope and complexity? They all tend to go way over budget and fall behind schedule. For example, the new Denver airport that opened in 1995 had cost overrun of 200 percent and was completed two years later than planned. The “Chunnel,” the 31-mile-plus tunnel that connects France with England, was 80 percent over budget. These are but two examples of many public works and other large-scale projects in which costs came in way over than planned. In a study of government infrastructure projects, Flyvbjerg found costs for bridges and tunnels, road, and rail to be underesti- mated 34 percent, 20 percent, and 45 percent, respectively, from baseline estimates (Flyvbjerg, Bruzelius, and Rothengatter, 2003)! Mega projects often involve a double whammy. Not only did they cost much more than expected, but they underdelivered on benefits they were to provide. The Denver Airport realized only 55 percent of forecasted traffic during its first year of operation. The Chunnel traffic revenues have been one-half of what was predicted with internal rate of return of −14.5 percent! Again Flyvbjerg’s study revealed a consistent pattern of underusage on most infrastructure projects (Flyvbjerg et al., 2003), including only a 5 percent forecasted usage for the Kolkata metro! So why does there appear to be a consistent pattern of overestimating benefits and underestimating costs? Many argue the sheer complexity and long time horizon make it impossible to accurately estimate costs and benefits. While this is certainly true, Flyvbjerg and his colleagues’ research suggests that other factors come in to play. They concluded that in most cases project promoters use deception to promote projects not for public good but for personal gain, political or economic. Deception may be delib- erate, or may be the product of overzealousness, optimism, and ignorance (Flyvbjerg et al., 2003). In some cases, promoters rationalize that nothing great would ever get built if people knew in advance what the real costs and challenges involved were (Hirschman, 1967). On some mega projects, there is a triple whammy. Not only are they over budget and under value, but the cost of maintaining them exceeds the benefits received. These kinds of projects are called white elephants. A “white elephant” suggests a valuable, but burdensome, possession which the owner cannot easily dispose of and whose cost (particularly upkeep) is out of propor- tion with its usefulness. The term derives from the story that the Kings of Siam (now Thailand) would often make a present of a white elephant to courtiers who had fallen out of favor with the king. At first glance, it was a great honor to receive such a revered beast from the king. However, the true intent was to ruin the recipient by forcing him to absorb the costs of taking care of the animal. Examples of white elephants abound. While traveling across southern China one of the authors was struck by the palatial stature of the Trade Expo buildings each city had. It was as if each city tried to outdo its neighbor in terms of grandeur. When asked how often they were used, city officials would say once or twice a year. The 2015 FIFA scandal brought attention to the hidden costs of hosting the World Cup. South Africa built six new world class stadiums for the 2010 competition. None of the post-World Cup revenue generated from these stadiums exceeds their maintenance cost (Molloy and Chetty, 2015).

Understand the chal- lenge of estimating mega projects and describe steps that lead to better informed decisions.

5-6LO

Define a “white ele- phant” in project man- agement and provide examples.

5-7LO

150 Chapter 5 Estimating Project Times and Costs

White elephants are not limited to buildings and stadiums. Air France had to moth- ball the Concorde, the world’s fastest commercial airline, because maintenance costs and noise restrictions did not justify a three-flights-a-week schedule. It is not uncom- mon in our personal lives to acquire white elephants, such as underutilized vacation homes or yachts. Flyvbjerg and others argue that cost overrun is not the price of doing big things and that we are capable of making better informed decisions on mega projects. The first step is to assume there is optimism bias and even deception on the part of promoters. Propos- als should require a thorough review by impartial observers who do not have vested inter- est in the project. Some if not all financial risk should be absorbed by promoters and those who benefit financially from the project. Sustainable business practices should be used and maintenance costs be integrated into the forecasted cost/benefit analyses of projects. See Snapshot from Practice 5.6: London 2012 Olympics to see how British organizers tried to avoid the curse of the white elephant in the 2012 Olympic games.

Once hosting the Olympics was consid- ered the crown prize and a tremendous source of national and local pride. Seven cities competed to host the 1992 Winter Olympics. For the 2022 Winter

Olympics only Beijing and Almaty (Kazakhstan) submit- ted bids. Oslo (Norway), the favorite, withdrew applica- tion due to a lack of public support. Likewise, Boston withdrew application for the 2024 Summer Olympics in the face of public outcry. Why the outcry? Because of the legacy of exorbitant cost overruns and draining mainte- nance costs. The Olympics has a long history of expen- sive white elephants. For example, the Beijing National Stadium, nicknamed the Bird’s Nest, built at cost of $480 million for the 2008 Olympic games, requires over $10 million each year to maintain, and has no regular tenant. Some have attributed the Greek economic melt- down to exorbitant debt accrued from hosting the 2004 summer games (Flyvbjerg, 2014). Perhaps the most infa- mous example is the “Big Owe,” Montreal’s Olympic Stadium, which took Canadian taxpayers over thirty years to pay off and was not even finished in time for the 1976 Olympics! The London 2012 organizers were committed to turning this around. In particular, they were well aware of hidden post-Olympic maintenance costs of buildings that were no longer in demand. One advantage they had over less developed countries is that the infrastructure and many of the arenas were already in place and the Olympics provided a necessary upgrade. They built tem- porary arenas for less popular sports. For example, after the games the water polo arena was deconstructed and

© Sophie Vigneault /123RF

S N A P S H O T F R O M P R A C T I C E 5 . 6 London 2012 Olympics: Avoiding White Elephant Curse*

materials recycled. The 12,000-seat basketball arena was designed to be portable so it could be used in future Olympics. Scalability was another key consideration. For example, during the Olympics over 17,000 people watched swimming events in the newly constructed aquatic center. The aquatic center was downsized to a 2,500-person capacity after the Olympics and is now open to the public. In recognition of its achievements, London 2012 Olympics won Gold in the Environmental and Sustain- ability category of the 6th International Sports Events awards. “We set out with a huge promise to the world, to deliver the most sustainable Olympic Games of mod- ern times,” says David Stubbs, London 2012’s Head of Sustainability. “Seven years, nine million visitors, and 2,484 medals later, that’s exactly what we achieved.”

* “London 2012’s Sustainability Legacy Lives On,” Olympic .org, accessed October 10, 2015.

Chapter 5 Estimating Project Times and Costs 151

In particular, Flyvbjerg advocates an external view based on the outcome of similar projects completed in the past. It is called reference class forecasting (RCF) and involves three major steps: 1. Select a reference class of projects similar to your potential project, for example,

cargo ships or bridges. 2. Collect and arrange outcome data as a distribution. Create a distribution of cost

overruns as a percentage of the original project estimate (low to high). 3. Use the distribution data to arrive at a realistic forecast. Compare the original cost

estimate for the project with the reference class projects. (For example, ask an advo- cate of rail tunnel what strong evidence do you have that your project will not follow the tunnel projects in the reference class?)

The benefits of RCF are compelling: ∙ Outside empirical data mitigates human bias. ∙ Political, strategic, and promoter forces have difficulty ignoring outside RCF

information. ∙ Serves as reality check for funding large projects. ∙ Helps executives avoid unsound optimism. ∙ Leads to improved accountability. ∙ Provides basis for project contingency funds. The use of RCF is increasing as governments and organizations require this method be used to temper project promoters’ estimates and reduce cost/benefit inaccuracies.

Summary Quality time and cost estimates are the bedrock of project control. Past experience is the best starting point for these estimates. The quality of estimates is influenced by other factors such as people, technology, and downtimes. The key for getting estimates that represent realistic average times and costs is to have an organization culture that allows errors in estimates without incriminations. If times represent average time, we should expect that 50 percent will be less than the estimate and 50 percent will exceed the estimate. The use of teams that are highly motivated can help in keeping task times and costs near the average. For this reason, it is crucial to get the team to buy into time and cost estimates. Using top-down estimates is good for initial and strategic decision making or in situations where the costs associated with developing better estimates have little ben- efit. However, in most cases the bottom-up approach to estimating is preferred and more reliable because it assesses each work package, rather than the whole project, section, or deliverable of a project. Estimating time and costs for each work package facilitates development of the project schedule and a time-phased budget, which are needed to control the project as it is implemented. Using the estimating guidelines will help eliminate many common mistakes made by those unacquainted with estimating times and costs for project control. Establishing a time and cost estimating database fits well with the learning organization philosophy. The level of time and cost detail should follow the old saying of “no more than is necessary and sufficient.” Managers must remember to differentiate between commit- ted outlays, actual costs, and scheduled costs. It is well known that up-front efforts in

152 Chapter 5 Estimating Project Times and Costs

clearly defining project objectives, scope, and specifications vastly improve time and cost estimate accuracy. How estimates are gathered and how they are used can affect their usefulness for planning and control. The team climate, organization culture, and organization struc- ture can strongly influence the importance attached to time and cost estimates and how they are used in managing projects. Finally, large-scale mega projects like subway systems or football stadiums often suffer from underestimated costs and overestimated benefits. They also can evolve into “white elephants” in which the cost of maintenance exceeds benefits. Steps must be taken to remove bias and compare mega project estimates with similar projects that have been done in the past.

Key Terms Apportionment, 137 Bottom-up estimates, 135 Delphi Method, 136 Direct costs, 145 Function points, 138 Learning curve, 139

Overhead costs, 145 Phase estimating, 141 Range estimating, 140 Ratio methods, 137 Reference class forecasting (RCF), 151

Template method, 140 Time and cost databases, 148 Top-down estimates, 134 White elephant, 149

1. Why are accurate estimates critical to effective project management? 2. How does the culture of an organization influence the quality of estimates? 3. What are the differences between bottom-up and top-down estimating approaches?

Under what conditions would you prefer one over the other? 4. What are the major types of costs? Which costs are controllable by the project

manager? 5. Why is it difficult to estimate mega project (e.g., airports, stadiums, etc.) costs and

benefits? 6. Define what a “white elephant” is in project management. Provide a real-life

example.

Review Questions

1. Calculate the direct cost of labor for a project team member using the following data:

Hourly rate: $40/hr Hours needed: 80 Overhead rate: 40%

2. Mrs. Tolstoy and her husband, Serge, are planning their dream house. The lot for the house sits high on a hill with a beautiful view of the Appalachian Mountains. The plans show the size of the house to be 2,900 square feet. The average price for a lot and house similar to this one has been $120 per square foot. Fortunately, Serge is a retired plumber and feels he can save money by installing the plumbing him- self. Mrs. Tolstoy feels she can take care of the interior decorating.

Exercises

The following average cost information is available from a local bank that makes loans to local contractors and dispenses progress payments to contractors when spe- cific tasks are verified as complete.

24% Excavation and framing complete   8% Roof and fireplace complete   3% Wiring roughed in   6% Plumbing roughed in   5% Siding on 17% Windows, insulation, walks, plaster, and garage complete   9% Furnace installed   4% Plumbing fixtures installed 10% Exterior paint, light fixtures installed, finish hardware installed   6% Carpet and trim installed   4% Interior decorating   4% Floors laid and finished

a. What is the estimated cost for the Tolstoys’ house if they use contractors to com- plete all of the house?

b. Estimate what the cost of the house would be if the Tolstoys use their talents to do some of the work themselves.

3. Exercise Figure 5.1 is a project WBS with cost apportioned by percentages. If the total project cost is estimated to be $600,000, what are the estimated costs for the following deliverables? a. Design b. Programming c. In-house testing

What weaknesses are inherent in this estimating approach?

Router systems project Cost: $600,000

Definition

10%

Design

40%

Implementation

50%

Objectives

4%

Requirements

6%

Inputs

3%

Outputs

3%

Files

4%

Interfaces

10%

Programming

20%

In-house testing

40%

Customer testing & review

10%

EXERCISE FIGURE 5.1  WBS Figure

Chapter 5 Estimating Project Times and Costs 153

4. Firewall Project XT. Using the “complexity weighting” scheme shown in Table 5.3 and the function point complexity weight table shown below, estimate the total function point count. Assume historical data suggest five function points equal one person a month and six people can work on the project.

Complexity Weight Table

Number of inputs ####10 Rated complexity low Number of outputs 20 Rated complexity average Number of inquiries ####10 Rated complexity average Number of files 30 Rated complexity high Number of interfaces 50 Rated complexity high

a. What is the estimated project duration? b. If 20 people are available for the project, what is the estimated project duration? c. If the project must be completed in six months, how many people will be needed

for the project?

References Buehler, R., D. Griffin, and M. Ross, “Exploring the ‘Planning Fallacy’: Why People Underestimate Their Task Completion Times,” Journal of Personality and Social Psychology, vol. 67, no. 3 (1994), pp. 366–81. Dalkey, N. C., D. L. Rourke, R. Lewis, and D. Snyder, Studies in the Quality of Life: Delphi and Decision Making (Lexington, MA: Lexington Books, 1972). Flyvbjerg, Bent, “From Nobel Prize to Project Management: Getting Risks Right,” Project Management Journal, August 2006, pp. 5–15. Flyvbjerg, Bent, “Curbing Optimism Bias and Strategic Misrepresentation in Plan- ning: Reference Class Forecasting in Practice,” European Planning Studies, vol. 16, no. 1 (January 2008), pp. 3–21. Flyvbjerg, Bent, N. Bruzelius, and W. Rothengatter, Mega Projects and Risk: An Anatomy of Ambition (Cambridge Press, 2003). Flyvbjerg, B., “What You Should Know about Megaprojects and Why: An Over- view,” Project Management Journal, vol. 45, no. 2 (April/May 2014), pp. 6–19. Gray, N. S., “Secrets to Creating the Elusive ‘Accurate Estimate,’” PM Network, vol. 15, no. 8 (August 2001), p. 56. Hirschman. A. O., “The Principle of the Hiding Hand,” The Public Interest, Winter 1967, pp. 10–23. Jeffery, R., G. C. Low, and M. Barnes, “A Comparison of Function Point Counting Techniques,” IEEE Transactions on Software Engineering, vol. 19, no. 5 (1993), pp. 529–32. Jones, C., Applied Software Measurement (New York: McGraw-Hill, 1991). Jones, C., Estimating Software Costs (New York: McGraw-Hill, 1998). Kharbanda, O. P., and J. K. Pinto, What Made Gertie Gallop: Learning from Project Failures (New York: Von Nostrand Reinhold, 1996).

154 Chapter 5 Estimating Project Times and Costs

Lovallo, D., and D. Kahneman, “Delusions of Success: How Optimism Undermines Executives’ Decisions,” Harvard Business Review, July 2003, pp. 56–63. Magne, E., K. Emhjellenm, and P. Osmundsen, “Cost Estimation Overruns in the North Sea,” Project Management Journal, vol. 34, no. 1 (2003), pp. 23–29. McLeod, G., and D. Smith, Managing Information Technology Projects (Cambridge, MA: Course Technology, 1996). Molloy, E., and T. Chetty, “The Rocky Road to Legacy: Lessons from the 2010 FIFA World Cup South Africa Stadium Program,” Project Management Journal, vol. 46, no. 3 (June/July 2015), pp. 88–107. Milosevic, D. Z., Project Management ToolBox (Upper Saddle River, NJ: John Wiley, 2003), p. 229. Pressman, R. S., Software Engineering: A Practitioner’s Approach, 4th ed. (New York: McGraw-Hill, 1997). Symons, C. R., “Function Point Analysis: Difficulties and Improvements,” IEEE Transactions on Software Engineering, vol. 14, no. 1 (1988), pp. 2–11.

Case 5.1

Sharp Printing, AG Three years ago the Sharp Printing (SP) strategic management group set a goal of hav- ing a color laser printer available for the consumer and small business market for less than $200. A few months later the senior management met off-site to discuss the new product. The results of this meeting were a set of general technical specifications along with major deliverables, a product launch date, and a cost estimate based on prior experience. Shortly afterward, a meeting was arranged for middle management explaining the project goals, major responsibilities, the project start date, and importance of meeting the product launch date within the cost estimate. Members of all departments involved attended the meeting. Excitement was high. Although everyone saw the risks as high, the promised rewards for the company and the personnel were emblazoned in their minds. A few participants questioned the legitimacy of the project duration and cost estimates. A couple of R&D people were worried about the technology required to produce the high-quality product for less than $200. But given the excitement of the moment, everyone agreed the project was worth doing and doable. The color laser printer project was to have the highest project priority in the company. Lauren was selected to be the project manager. She had 15 years of experience in printer design and manufacture, which included successful management of several projects related to printers for commercial markets. Since she was one of those uncom- fortable with the project cost and time estimates, she felt getting good bottom-up time and cost estimates for the deliverables was her first concern. She quickly had a meeting with the significant stakeholders to create a WBS identifying the work packages and organizational unit responsible for implementing the work packages. Lauren stressed

Chapter 5 Estimating Project Times and Costs 155

156 Chapter 5 Estimating Project Times and Costs

she wanted time and cost estimates from those who would do the work or were the most knowledgeable, if possible. Getting estimates from more than one source was encouraged. Estimates were due in two weeks. The compiled estimates were placed in the WBS/OBS. The corresponding cost esti- mate seemed to be in error. The cost estimate was $1,250,000 over the top-down senior management estimate; this represented about a 20 percent overrun! Furthermore the bottom-up time estimate based on the project network was four months longer than the top management time estimate. Another meeting was scheduled with the significant stakeholders to check the estimates and to brainstorm for alternative solutions. At this meeting everyone agreed the bottom-up cost and time estimates appeared to be accu- rate. Some of the suggestions for the brainstorming session are listed below. ∙ Change scope. ∙ Outsource technology design. ∙ Use the priority matrix (found in Chapter 4) to get top management to clarify their

priorities. ∙ Partner with another organization or build a research consortium to share costs and

to share the newly developed technology and production methods. ∙ Cancel the project. ∙ Commission a break-even study for the laser printer. Very little in the way of concrete savings was identified, although there was consen- sus that time could be compressed to the market launch date, but at additional costs. Lauren met with the marketing (Connor), production (Kim), and design (Gage) man- agers who yielded some ideas for cutting costs, but nothing significant enough to have a large impact. Gage remarked, “I wouldn’t want to be the one to deliver the message to top management that their cost estimate is $1,250,000 off! Good luck, Lauren.” 1. At this point, what would you do if you were the project manager? 2. Was top management acting correctly in developing an estimate? 3. What estimating techniques should be used for a mission critical project such as this?

Case 5.2

Post Graduation Adventure Josh and Mike met each other as roommates during freshman year at MacAlister Col- lege in St. Paul, Minnesota. Despite a rocky start they became best friends. They are planning on going on a two-week adventure together to celebrate their graduation in June. Josh has never been to Europe and wants to visit France or Spain. Mike spent a semester abroad in Aarhus, Denmark, and traveled extensively in northern Europe. Even though he never went to France or Spain, Mike wants to go to someplace more exotic like South Africa or Vietnam. For the past week they have been arguing back and forth over where they should go. Josh argues that it will cost too much to fly to South Africa or Vietnam, while Mike counters that it will be much cheaper to travel in Vietnam or South Africa once they are there. Each of them agreed that they can spend no more than $3,500 each on the trip and could be gone for only two weeks. One evening when they were arguing with each other over beers with friends, Sara said, “Why don’t you use what you learned in your project management class

Chapter 5 Estimating Project Times and Costs 157

to decide what to do?” Josh and Mike looked at each other and agreed that made perfect sense. 1. Assume you are either Mike or Josh; how would you go about making a decision

using project management methodology? 2. Looking first at only cost, what decision would you make? 3. After cost, what other factors should be considered before making a decision?

Appendix 5.1

LEARNING OBJECTIVES After reading this appendix you should be able to:

A5-1 Use learning curves to improve task estimates.

Learning Curves for Estimating A forecast estimate of the time required to perform a work package or task is a basic necessity for scheduling the project. In some cases, the manager simply uses judgment and past experience to estimate work package time, or may use historical records of similar tasks. Most managers and workers intuitively know that improvement in the amount of time required to perform a task or group of tasks occurs with repetition. A worker can perform a task better/quicker the second time and each succeeding time she/he per- forms it (without any technological change). It is this pattern of improvement that is important to the project manager and project scheduler. This improvement from repetition generally results in a reduction of labor hours for the accomplishment of tasks and results in lower project costs. From empirical evi- dence across all industries, the pattern of this improvement has been quantified in the learning curve (also known as improvement curve, experience curve, and industrial progress curve), which is described by the following relationship:

Each time the output quantity doubles, the unit labor hours are reduced at a constant rate.

For example, assume that a manufacturer has a new contract for 16 prototype units and a total of 800 labor hours were required for the first unit. Past experience has indi- cated that on similar types of units the improvement rate was 80 percent. This relation- ship of improvement in labor hours is shown below:

Unit Labor Hours    1 800   2 800 × .80 = 640   4 640 × .80 = 512   8 512 × .80 = 410 16 410 × .80 = 328

By using Table A5.1 unit values, similar labor hours per unit can be determined. Looking across the 16 unit level and down the 80 percent column, we find a ratio

Use learning curves to improve task estimates.

A5-1LO

158 Chapter 5 Estimating Project Times and Costs

TABLE A5.1 Learning Curves Unit Values

Units 60% 65% 70% 75% 80% 85% 90% 95%

1 1.0000 1.0000 1.0000 1.0000 1.0000 1.0000 1.0000 1.0000 2 .6000 .6500 .7000 .7500 .8000 .8500 .9000 .9500 3 .4450 .5052 .5682 .6338 .7021 .7729 .8462 .9219 4 .3600 .4225 .4900 .5625 .6400 .7225 .8100 .9025 5 .3054 .3678 .4368 .5127 .5956 .6857 .7830 .8877 6 .2670 .3284 .3977 .4754 .5617 .6570 .7616 .8758 7 .2383 .2984 .3674 .4459 .5345 .6337 .7439 .8659 8 .2160 .2746 .3430 .4219 .5120 .6141 .7290 .8574 9 .1980 .2552 .3228 .4017 .4930 .5974 .7161 .8499 10 .1832 .2391 .3058 .3846 .4765 .5828 .7047 .8433 12 .1602 .2135 .2784 .3565 .4493 .5584 .6854 .8320 14 .1430 .1940 .2572 .3344 .4276 .5386 .6696 .8226 16 .1296 .1785 .2401 .3164 .4096 .5220 .6561 .8145 18 .1188 .1659 .2260 .3013 .3944 .5078 .6445 .8074 20 .1099 .1554 .2141 .2884 .3812 .4954 .6342 .8012 22 .1025 .1465 .2038 .2772 .3697 .4844 .6251 .7955 24 .0961 .1387 .1949 .2674 .3595 .4747 .6169 .7904 25 .0933 .1353 .1908 .2629 .3548 .4701 .6131 .7880 30 .0815 .1208 .1737 .2437 .3346 .4505 .5963 .7775 35 .0728 .1097 .1605 .2286 .3184 .4345 .5825 .7687 40 .0660 .1010 .1498 .2163 .3050 .4211 .5708 .7611 45 .0605 .0939 .1410 .2060 .2936 .4096 .5607 .7545 50 .0560 .0879 .1336 .1972 .2838 .3996 .5518 .7486 60 .0489 .0785 .1216 .1828 .2676 .3829 .5367 .7386 70 .0437 .0713 .1123 .1715 .2547 .3693 .5243 .7302 80 .0396 .0657 .1049 .1622 .2440 .3579 .5137 .7231 90 .0363 .0610 .0987 .1545 .2349 .3482 .5046 .7168 100 .0336 .0572 .0935 .1479 .2271 .3397 .4966 .7112 120 .0294 .0510 .0851 .1371 .2141 .3255 .4830 .7017 140 .0262 .0464 .0786 .1287 .2038 .3139 .4718 .6937 160 .0237 .0427 .0734 .1217 .1952 .3042 .4623 .6869 180 .0218 .0397 .0691 .1159 .1879 .2959 .4541 .6809 200 .0201 .0371 .0655 .1109 .1816 .2887 .4469 .6757 250 .0171 .0323 .0584 .1011 .1691 .2740 .4320 .6646 300 .0149 .0289 .0531 .0937 .1594 .2625 .4202 .5557 350 .0133 .0262 .0491 .0879 .1517 .2532 .4105 .6482 400 .0121 .0241 .0458 .0832 .1453 .2454 .4022 .6419 450 .0111 .0224 .0431 .0792 .1399 .2387 .3951 .6363 500 .0103 .0210 .0408 .0758 .1352 .2329 .3888 .6314 600 .0090 .0188 .0372 .0703 .1275 .2232 .3782 .6229 700 .0080 .0171 .0344 .0659 .1214 .2152 .3694 .6158 800 .0073 .0157 .0321 .0624 .1163 .2086 .3620 .6098 900 .0067 .0146 .0302 .0594 .1119 .2029 .3556 .6045 1,000 .0062 .0137 .0286 .0569 .1082 .1980 .3499 .5998 1,200 .0054 .0122 .0260 .0527 .1020 .1897 .3404 .5918 1,400 .0048 .0111 .0240 .0495 .0971 .1830 .3325 .5850 1,600 .0044 .0102 .0225 .0468 .0930 .1773 .3258 .5793 1,800 .0040 .0095 .0211 .0446 .0895 .1725 .3200 .5743 2,000 .0037 .0089 .0200 .0427 .0866 .1683 .3149 .5698 2,500 .0031 .0077 .0178 .0389 .0606 .1597 .3044 .5605 3,000 .0027 .0069 .0162 .0360 .0760 .1530 .2961 .5530

Chapter 5 Estimating Project Times and Costs 159

of .4096. By multiplying this ratio times the labor hours for the first unit, we obtain the per unit value:

.4096 × 800 = 328 hours or 327.68 That is, the 16th unit should require close to 328 labor hours, assuming an 80 percent improvement ratio. Obviously, a project manager may need more than a single unit value for estimating the time for some work packages. The cumulative values in Table A5.2 provide factors for computing the cumulative total labor hours of all units. In the previous example, for the first 16 units, the total labor hours required would be

800 × 8.920 = 7,136 hours By dividing the total cumulative hours (7,136) by the units, the average unit labor hours can be obtained:

7,136 labor hours/16 units = 446 average labor hours per unit Note how the labor hours for the 16th unit (328) differs from the average for all 16 units (446). The project manager, knowing the average labor costs and processing costs, could estimate the total prototype costs. (The mathematical derivation of factors found in Tables A5.1 and A5.2 can be found in Jelen, F. C., and J. H. Black, Cost and Optimization Engineering, 2nd ed. (New York: McGraw-Hill, 1983.)

FOLLOW-ON CONTRACT EXAMPLE Assume the project manager gets a follow-on order of 74 units; how should she esti- mate labor hours and cost? Going to the cumulative Table A5.2 we find at the 80 per- cent ratio and 90 total units intersection—a 30.35 ratio.

800 × 30.35 = 24,280 labor hours for 90 units Less previous 16 units =   7,136 Total follow-on order = 17,144 labor hours 17,144/74 equals 232 average labor hours per unit

Labor hours for the 90th unit can be obtained from Table A5.1: .2349 × 800 = 187.9 labor hours. (For ratios between given values, simply estimate.) Exercise A5.1

Norwegian Satellite Development Company Cost Estimates for World Satellite Telephone Exchange Project

NSDC has a contract to produce eight satellites to support a worldwide telephone sys- tem (for Alaska Telecom, Inc.) that allows individuals to use a single, portable tele- phone in any location on earth to call in and out. NSDC will develop and produce the eight units. NSDC has estimated that the R&D costs will be NOK (Norwegian Krone) 12,000,000. Material costs are expected to be NOK 6,000,000. They have estimated the design and production of the first satellite will require 100,000 labor hours and an

160 Chapter 5 Estimating Project Times and Costs

TABLE A5.2 Learning Curves Cumulative Values

Units 60% 65% 70% 75% 80% 85% 90% 95%

1 1.000 1.000 1.000 1.000 1.000 1.000 1.000 1.000 2 1.600 1.650 1.700 1.750 1.800 1.850 1.900 1.950 3 2.045 2.155 2.268 2.384 2.502 2.623 2.746 2.872 4 2.405 2.578 2.758 2.946 3.142 3.345 3.556 3.774 5 2.710 2.946 3.195 3.459 3.738 4.031 4.339 4.662 6 2.977 3.274 3.593 3.934 4.299 4.688 5.101 5.538 7 3.216 3.572 3.960 4.380 4.834 5.322 5.845 6.404 8 3.432 3.847 4.303 4.802 5.346 5.936 6.574 7.261 9 3.630 4.102 4.626 5.204 5.839 6.533 7.290 8.111 10 3.813 4.341 4.931 5.589 6.315 7.116 7.994 8.955 12 4.144 4.780 5.501 6.315 7.227 8.244 9.374 10.62 14 4.438 5.177 6.026 6.994 8.092 9.331 10.72 12.27 16 4.704 5.541 6.514 7.635 8.920 10.38 12.04 13.91 18 4.946 5.879 6.972 8.245 9.716 11.41 13.33 15.52 20 5.171 6.195 7.407 8.828 10.48 12.40 14.64 17.13 22 5.379 6.492 7.819 9.388 11.23 13.38 15.86 18.72 24 5.574 6.773 8.213 9.928 11.95 14.33 17.10 20.31 25 5.668 6.909 8.404 10.19 12.31 14.80 17.71 21.10 30 6.097 7.540 9.305 11.45 14.02 17.09 20.73 25.00 35 6.478 8.109 10.13 12.72 15.64 19.29 23.67 28.86 40 6.821 8.631 10.90 13.72 17.19 21.43 26.54 32.68 45 7.134 9.114 11.62 14.77 18.68 23.50 29.37 36.47 50 7.422 9.565 12.31 15.78 20.12 25.51 32.14 40.22 60 7.941 10.39 13.57 17.67 22.87 29.41 37.57 47.65 70 8.401 11.13 14.74 19.43 25.47 33.17 42.87 54.99 80 8.814 11.82 15.82 21.09 27.96 36.80 48.05 62.25 90 9.191 12.45 16.83 22.67 30.35 40.32 53.14 69.45 100 9.539 13.03 17.79 24.18 32.65 43.75 58.14 76.59 120 10.16 14.16 19.57 27.02 37.05 50.39 67.93 90.71 140 10.72 15.08 21.20 29.67 41.22 56.78 77.46 104.7 160 11.21 15.97 22.72 32.17 45.20 62.95 86.80 118.5 180 11.67 16.79 24.14 34.54 49.03 68.95 95.96 132.1 200 12.09 17.55 25.48 36.80 52.72 74.79 105.0 145.7 250 13.01 19.28 28.56 42.08 61.47 88.83 126.9 179.2 300 13.81 20.81 31.34 46.94 69.66 102.2 148.2 212.2 350 14.51 22.18 33.89 51.48 77.43 115.1 169.0 244.8 400 15.14 23.44 36.26 55.75 84.85 127.6 189.3 277.0 450 15.72 24.60 38.48 59.80 91.97 139.7 209.2 309.0 500 16.26 25.68 40.58 63.68 98.85 151.5 228.8 340.6 600 17.21 27.67 44.47 70.97 112.0 174.2 267.1 403.3 700 18.06 29.45 48.04 77.77 124.4 196.1 304.5 465.3 800 18.82 31.09 51.36 84.18 136.3 217.3 341.0 526.5 900 19.51 32.60 54.46 90.26 147.7 237.9 376.9 587.2 1,000 20.15 34.01 57.40 96.07 158.7 257.9 412.2 647.4 1,200 21.30 36.59 62.85 107.0 179.7 296.6 481.2 766.6 1,400 22.32 38.92 67.85 117.2 199.6 333.9 548.4 884.2 1,600 23.23 41.04 72.49 126.8 218.6 369.9 614.2 1001. 1,800 24.06 43.00 76.85 135.9 236.8 404.9 678.8 1116. 2,000 24.83 44.84 80.96 144.7 254.4 438.9 742.3 1230. 2,500 26.53 48.97 90.39 165.0 296.1 520.8 897.0 1513. 3,000 27.99 52.62 98.90 183.7 335.2 598.9 1047. 1791.

Chapter 5 Estimating Project Times and Costs 161

80 percent improvement curve is expected. Skilled labor cost is NOK 300 per hour. Desired profit for all projects is 25 percent of total costs. A. How many labor hours should the eighth satellite require? B. How many labor hours for the whole project of eight satellites? C. What price would you ask for the project? Why? D. Midway through the project your design and production people realize that a

75 percent improvement curve is more appropriate. What impact does this have on the project?

E. Near the end of the project, Deutsch Telefon AG has requested a cost estimate for four satellites identical to those you have already produced. What price will you quote them? Justify your price.

162

Developing a Project Plan6 LEARNING OBJECTIVES After reading this chapter you should be able to:

6-1 Understand the linkage between WBS and the project network.

6-2 Diagram a project network using AON methods.

6-3 Calculate early, late, and slack activity times.

6-4 Identify and understand the importance of managing the critical path.

6-5 Distinguish free slack from total slack.

6-6 Demonstrate understanding and application of lags in compressing projects or constraining the start or finish of an activity.

OUTLINE 6.1 Developing the Project Network

6.2 From Work Package to Network

6.3 Constructing a Project Network

6.4 Activity-on-Node (AON) Fundamentals

6.5 Network Computation Process

6.6 Using the Forward and Backward Pass Information

6.7 Level of Detail for Activities

6.8 Practical Considerations

6.9 Extended Network Techniques to Come Closer to Reality

Summary

C H A P T E R S I X

163

I keep six honest serving-men (they taught me all I knew); their names are What and Why and When and How and Where and Who. —Rudyard Kipling

6.1 Developing the Project Network The project network is the tool used for planning, scheduling, and monitoring project progress. The network is developed from the information collected for the WBS and is a graphic flow chart of the project job plan. The network depicts the project activities that must be completed, the logical sequences, the interdependencies of the activities to be completed, and in most cases the times for the activities to start and finish along with the longest path(s) through the network—the critical path. The network is the framework for the project information system that will be used by the project managers to make decisions concerning project time, cost, and performance. Developing the project networks takes time for someone or some group to develop; therefore, they cost money! Are networks really worth the struggle? The answer is

Project networks

6

Managing risk 7

Monitoring progress

13

Teams 11

Outsourcing 12

Project manager

10

Strategy 2

Introduction 1

Organization 3

Schedule resources & costs

8

Intern ation

al

proje cts

15

Agile PM 16

Project closure

14

Estimate 5

Reducing duration

9

Define project

4

164 Chapter 6 Developing a Project Plan

definitely yes, except in cases where the project is considered trivial or very short in duration.1 The network is easily understood by others because the network presents a graphic display of the flow and sequence of work through the project. Once the net- work is developed, it is very easy to modify or change when unexpected events occur as the project progresses. For example, if materials for an activity are delayed, the impact can be quickly assessed and the whole project revised in only a few minutes with the computer. These revisions can be communicated to all project participants quickly (for example, via e-mail or project website). The project network provides other invaluable information and insights. It provides the basis for scheduling labor and equipment. It enhances communication that melds all managers and groups together in meeting the time, cost, and performance objectives of the project. It provides an estimate of project duration rather than picking a project completion date from a hat or someone’s preferred date. The network gives the times when activities can start and finish and when they can be delayed. It provides the basis for budgeting the cash flow of the project. It identifies which activities are “critical” and, therefore, should not be delayed if the project is to be completed as planned. It highlights which activities to consider if the project needs to be compressed to meet a deadline. There are other reasons project networks are worth their weight in gold. Basically, project networks minimize surprises by getting the plan out early and allowing correc- tive feedback. A commonly heard statement from practitioners is that the project net- work represents three-quarters of the planning process. Perhaps this is an exaggeration, but it signals the perceived importance of the network to project managers in the field.

6.2 From Work Package to Network Project networks are developed from the WBS. The project network is a visual flow diagram of the sequence, interrelationships, and dependencies of all the activities that must be accomplished to complete the project. An activity is an element in the project that consumes time—for example, work or waiting. Work packages from the WBS are used to build the activities found in the project network. An activity can include one or more work packages. The activities are placed in a sequence that provides for orderly completion of the project. Networks are built using nodes (boxes) and arrows (lines). Integrating the work packages and the network represents a point where the man- agement process often fails in practice. The primary explanations for this failure are that (1) different groups (people) are used to define work packages and activities and (2) the WBS is poorly constructed and not deliverable/output oriented. Integration of the WBS and project network is crucial to effective project management. The project manager must be careful to guarantee continuity by having some of the same people who defined the WBS and work packages develop the network activities. Networks provide the project schedule by identifying dependencies, sequencing, and timing of activities, which the WBS is not designed to do. The primary inputs for devel- oping a project network plan are work packages. Remember, a work package is defined independently of other work packages, has definite start and finish points, requires spe- cific resources, includes technical specifications, and has cost estimates for the package. However, dependency, sequencing, and timing of each of these factors are not included in the work package. A network activity can include one or more work packages.

Understand the linkage between WBS and the project network.

6-1LO

1 This process could be clarified and improved by using a simple responsibility matrix (see Chapter 4).

Chapter 6 Developing a Project Plan 165

FIGURE 6.1 WBS/Work Packages to Network

Circuit board

Lowest element

Design cost

account

O r g a n i z a t i o n

U n i t s

Production cost

account

Test cost

account

Software cost

account

A

D -1-1 D -1-2

Design WP D-1-1 Specifications WP D-1-2 Documentation

Production WP P-10-1 Proto 1 WP P-10-2 Final Proto 2

Test systems WP T-13-1 Test

Software WP S-22-1 Software preliminary WP S-22-2 Software final version

B

P -10-1

C

S -22-1

D

P -10-2

Activity network for circuit board work packages

F

S -22-2

K

T -13-1

A

Specifications and documentation

2

B

Proto 1 5

C

Software preliminary

3

D

Final proto 2

4

F

Final software

2

K

Test 3

Figure 6.1 shows a segment of the WBS example and how the information is used to develop a project network. The lowest level deliverable in Figure 6.1 is “circuit board.” The cost accounts (design, production, test, software) denote project work, organiza- tion unit responsible, and time-phased budgets for the work packages. Each cost account represents one or more work packages. For example, the design cost account has two work packages (D-1-1 and D-1-2)—specifications and documentation. The software and production accounts also have two work packages. Developing a network requires sequencing tasks from all work packages that have measurable work. Figure 6.1 traces how work packages are used to develop a project network. You can trace the use of work packages by the coding scheme. For example, activity A uses work packages D-1-1 and D-1-2 (specifications and documentation), while activity C

166 Chapter 6 Developing a Project Plan

uses work package S-22-1. This methodology of selecting work packages to describe activities is used to develop the project network, which sequences and times project activities. Care must be taken to include all work packages. The manager derives activ- ity time estimates from the task times in the work package. For example, activity B (proto 1) requires five weeks to complete; activity K (test) requires three weeks to complete. After computing the activity early times and late times, the manager can schedule resources and time-phase budgets (with dates).

6.3 Constructing a Project Network

Terminology Every field has its jargon that allows colleagues to communicate comfortably with each other about the techniques they use. Project managers are no exception. Here are some terms used in building project networks.

Activity. For project managers, an activity is an element of the project that requires time. It may or may not require resources. Typically an activity consumes time—either while people work or while people wait. Examples of the latter are time waiting for contracts to be signed, materials to arrive, drug approval by the government, budget clearance, etc. Activities usually represent one or more tasks from a work package. Descriptions of activities should use a verb/noun format: for example, develop product specifications. Merge Activity. This is an activity that has more than one activity immediately preceding it (more than one dependency arrow flowing to it). Parallel Activities. These are activities that can take place at the same time, if the manager wishes. However, the manager may choose to have parallel activities not occur simultaneously. Path. A sequence of connected, dependent activities. Critical Path. When this term is used, it means the path(s) with the longest dura- tion through the network; if an activity on the path is delayed, the project is delayed the same amount of time. Burst Activity. This activity has more than one activity immediately following it (more than one dependency arrow flowing from it).

Basic Rules to Follow in Developing Project Networks The following eight rules apply in general when developing a project network: 1. Networks flow typically from left to right. 2. An activity cannot begin until all preceding connected activities have been completed. 3. Arrows on networks indicate precedence and flow. Arrows can cross over each other. 4. Each activity should have a unique identification number. 5. An activity identification number must be larger than that of any activities that precede it. 6. Looping is not allowed (in other words, recycling through a set of activities cannot

take place). 7. Conditional statements are not allowed (that is, this type of statement should not

appear: If successful, do something; if not, do nothing). 8. Experience suggests that when there are multiple starts, a common start node can be

used to indicate a clear project beginning on the network. Similarly, a single project end node can be used to indicate a clear ending.

Diagram a project network using AON methods.

6-2LO

Chapter 6 Developing a Project Plan 167

Read the Snapshot from Practice 6.1: The Yellow Sticky Approach to see how these rules are used to create project networks.

6.4 Activity-on-Node (AON) Fundamentals Historically, two methods have been used to develop project networks: Activity- on-node (AON) and Activity-on-arrow (AOA). Over time the availability of advanced computer graphics improved the clarity and visual appeal of the AON method. Today, the activity-on-node method has come to dominate nearly all project network plans. For this reason, we have limited our discussion to AON methods. Figure 6.2 shows a few typical uses of building blocks for the AON network

In practice small project networks (25 to 100 activities) are frequently devel- oped using yellow Post-it® stickers. The meeting requirements and process for the project team are described herein.

The following are the requirements for such a project:

1. Project team members and a facilitator.

2. One yellow sticker (3 × 4 inches or larger) for each activity with the description of the activity printed on the sticker.

3. Erasable whiteboard with marker pen (a long, 4-foot-wide piece of butcher paper can be used in place of the whiteboard).

All of the yellow stickers are placed in easy view of all team members. The team begins by identifying those activity stickers that have no predecessors. Each of these activity stickers is then attached to the white- board. A start node is drawn, and a dependency arrow is connected to each activity. Given the initial network start activities, each activ- ity is examined for immediate successor activities. These activities are attached to the whiteboard and dependency arrows drawn. This process is continued until all of the yellow stickers are attached to the white- board with dependency arrows. (Note: The process can be reversed, beginning with those activities that have no successor activities and connecting them to a proj- ect end node. The predecessor activities are selected for each activity and attached to the whiteboard with dependency arrows marked.) When the process is complete, the dependencies are recorded in the project software, which develops a

computer-designed network along with the critical path(s) and early, late, and slack times. This methodol- ogy sensitizes team members early to the interdepen- dencies among activities of the project. But more importantly, the methodology empowers team mem- bers by giving them input to the important decisions that they must implement later.

S N A P S H O T F R O M P R A C T I C E 6 . 1 The Yellow Sticky Approach (for Constructing a Project Network)

© Image Source/Alamy

168 Chapter 6 Developing a Project Plan

FIGURE 6.2 Activity-on-Node Network Fundamentals

A B C A is preceded by nothing B is preceded by A C is preceded by B

X

Z

Y Y and Z are preceded by X

Y and Z can begin at the same time, if you wish

(A)

(B) X is a burst activity

M is a merge activity(C)

(D)

K M

L

J J, K, & L can all begin at the same time, if you wish (they need not occur simultaneously)

but

All (J, K, L) must be completed before M can begin

X Z

Y AA

Z is preceded by X and Y

AA is preceded by X and Y

construction. An activity is represented by a node (box). The node can take many forms, but in recent years the node represented as a rectangle (box) has dominated. The dependencies among activities are depicted by arrows between the rectangles (boxes) on the AON network. The arrows indicate how the activities are related and the sequence in which things must be accomplished. The length and slope of the arrow are arbitrary and set for convenience of drawing the network. The letters in the boxes serve here to identify the activities while you learn the fundamentals of network construction and analysis. In practice, activities have identification num- bers and descriptions. There are three basic relationships that must be established for activities included in a project network. The relationships can be found by answering the following three questions for each activity: 1. Which activities must be completed immediately before this activity? These activi-

ties are called predecessor activities. 2. Which activities must immediately follow this activity? These activities are called

successor activities. 3. Which activities can occur while this activity is taking place? This is known as a

concurrent or parallel relationship.

Chapter 6 Developing a Project Plan 169

Sometimes a manager can use only questions 1 and 3 to establish relationships. This information allows the network analyst to construct a graphic flow chart of the sequence and logical interdependencies of project activities. Figure 6.2A is analogous to a list of things to do where you complete the task at the top of the list first and then move to the second task, etc. This figure tells the project manager that activity A must be completed before activity B can begin, and activity B must be completed before activity C can begin. Figure 6.2B tells us that activities Y and Z cannot begin until activity X is com- pleted. This figure also indicates that activities Y and Z can occur concurrently or simultaneously if the project manager wishes; however, it is not a necessary condition. For example, pouring a concrete driveway (activity Y) can take place while landscape planting (activity Z) is being accomplished, but land clearing (activity X) must be completed before activities Y and Z can start. Activities Y and Z are considered paral- lel activities. Parallel paths allow concurrent effort, which may shorten time to do a series of activities. Activity X is sometimes referred to as a burst activity because more than one arrow bursts from the node. The number of arrows indicates how many activi- ties immediately follow activity X. Figure 6.2C shows us activities J, K, and L can occur simultaneously if desired, and activity M cannot begin until activities J, K, and L are all completed. Activities J, K, and L are parallel activities. Activity M is called a merge activity because more than one activity must be completed before M can begin. Activity M could also be called a milestone—a significant accomplishment. In Figure 6.2D, activities X and Y are parallel activities that can take place at the same time; activities Z and AA are also parallel activities. But activities Z and AA cannot begin until activities X and Y are both completed. Given these fundamentals of AON, we can practice developing a simple network. Remember, the arrows can cross over each other (e.g., Figure 6.2D), be bent, or be any length or slope. Neatness is not a criterion for a valid, useful network—only accurate inclusion of all project activities, their dependencies, and time estimates. Information for a simplified project network is given in Table 6.1. This project rep- resents a new automated warehouse system for picking frozen food package orders and moving them to a staging area for delivery to stores. Figure 6.3 shows the first steps in constructing the AON project network from the information in Table 6.1. We see that activity A (define requirements) has nothing preceding it; therefore, it is the first node to be drawn. Next, we note that activities B and C (assign team and design hardware) are both preceded by activity A. We draw two arrows and connect them to activities B and C. This segment shows

TABLE 6.1 Network Information

AUTOMATED WAREHOUSE Order Picking System

Activity Description Preceding Activity

A Define Requirements None B Assign Team A C Design Hardware A D Code Software B E Build and Test Hardware C F Develop Patent Request C G Test Software D H Integrate Systems E, F, G

170 Chapter 6 Developing a Project Plan

the project manager that activity A must be completed before activities B and C can begin. After A is completed, B and C can take place concurrently, if desired. Figure 6.4 shows the completed network with all of the activities sequences and dependencies. The information in Figure 6.4 is tremendously valuable to those managing the proj- ect. However, estimating the duration for each activity will further increase the value of the network. A realistic project plan and schedule require reliable time estimates for project activities. The addition of time to the network allows us to estimate how long the project will take. When activities can or must start, when resources must be avail- able, which activities can be delayed, and when the project is estimated to be complete are all determined from the times assigned. Deriving an activity time estimate neces- sitates early assessment of resource needs in terms of material, equipment, and people. In essence the project network with activity time estimates links planning, scheduling, and controlling of projects.

Automated Warehouse Order Picking System

Define Requirements

Design Hardware

Assign Team

B

A C

FIGURE 6.3 Automated Warehouse—Partial Network

Automated Warehouse Order Picking System

A

F

Develop Patent Request

C E H

Define Requirements

Design Hardware

Build & Test Hardware

Integrate Systems

Assign Team

Code Software

D G

Test Software

B

FIGURE 6.4 Automated Warehouse—Completed Network

Chapter 6 Developing a Project Plan 171

Calculate early, late, and slack activity times.

6-3LO

6.5 Network Computation Process Drawing the project network places the activities in the right sequence for computing start and finish times of activities. Activity time estimates are taken from the task times in the work package and added to the network (review Figure 6.1). Performing a few simple computations allows the project manager to complete a process known as the forward and backward pass. Completion of the forward and backward pass will answer the following questions: Forward Pass—Earliest Times

1. How soon can the activity start? (early start—ES) 2. How soon can the activity finish? (early finish—EF) 3. How soon can the project be finished? (expected time—TE)

Backward Pass—Latest Times

1. How late can the activity start? (late start—LS) 2. How late can the activity finish? (late finish—LF) 3. Which activities represent the critical path (CP)? This is the longest path in the

network which, when delayed, will delay the project. 4. How long can the activity be delayed? (slack or float—SL) The terms in parentheses represent the acronyms used in most texts and computer pro- grams and by project managers. The forward and backward pass process is presented next.

Forward Pass—Earliest Times The forward pass starts with the first project activity(ies) and traces each path (chain of sequential activities) through the network to the last project activity(ies). As you trace along the path, you add the activity times. The longest path denotes the project completion time for the plan and is called the critical path (CP). Table 6.2 lists the activity times in workdays for the Automated Warehouse project example we used for drawing a network. Figure 6.5 shows the network with the activity time estimate found in the node (see “DUR” for duration in the legend). For example, activity A (define requirements) has an activity duration of 10 workdays, and activity E (build and test hardware) has a duration of 50 days. The forward pass begins with the project start time, which is usually time zero. (Note: Calendar times can be computed for the project later in the planning phase.)

AUTOMATED WAREHOUSE Order Picking System

Activity Description Preceding Activity Activity Time

A Define Requirements None    10 workdays B Assign Team A            5 C Design Hardware A          25 D Code Software B          20 E Build & Test Hardware C          50 F Develop Patent Request C          15 G Test Software D          35 H Integrate Systems E, F, G 15

TABLE 6.2 Network Information

172 Chapter 6 Developing a Project Plan

In our Automated Warehouse example, the early start time for the first activity (activity A) is zero. This time is found in the upper left corner of the activity A node in Figure 6.6. The early finish for activity A is 10 days (EF = ES + DUR or 0 + 10 = 10). Next, we see that activity A is the predecessor for activities B (assign team) and C (design hardware). Therefore, the earliest activities B and C can begin is the instant in time when activity A is completed; this time is 10 days. You can now see in Figure 6.6 that activities B and C have an early start (ES) of 10 days. Using the formula EF = ES + DUR, the early finish (EF) times for activities B and C are 15 and 35 days. Fol- lowing the same process of moving along each network path, the early start and finish times for selected activities are shown here:

Activity D: ES = 15 EF = 15 + 20 = 35 Activity F: ES = 35 EF = 35 + 15 = 50 Activity E: ES = 35 EF = 35 + 50 = 85 Activity G: ES = 35 EF = 35 + 35 = 70

Activity H (integrate system) is a merge activity because it is preceded by more than one activity. The early start (ES) of a merge activity depends on the early finish (EF) of all activities that merge to it. In this project activity H is preceded by activities E, F, and G. Which activity controls the ES of activity H? The answer is activity E. In Figure 6.6 the EF times are 85, 50, and 70. Since 85 days is the largest EF time, activ- ity E controls the ES for activity H, which is 85. If activity E is delayed, activity H will be delayed. The early finish for activity H or the project is 100 days (EF = ES + DUR or 85 + 15 = 100).

FIGURE 6.5 Activity-on-Node Network

Automated Warehouse Order Picking System

A

10

ID

Legend

DUR

ES

LS

EF

LF

SL

F

15

E

50

H

15

B

5

D

20

G

35

Define Requirements

Build & Test Hardware

Integrate Systems

Assign Team

Code Software

Test Software

Develop Patent Request

Design Hardware

C

25

Description

Chapter 6 Developing a Project Plan 173

The forward pass requires that you remember just three things when computing early activity times: 1. You add activity times along each path in the network (ES + DUR = EF). 2. You carry the early finish (EF) to the next activity where it becomes its early start

(ES), or 3. If the next succeeding activity is a merge activity, you select the largest early finish

number (EF) of all its immediate predecessor activities. The three questions derived from the forward pass have been answered; that is, early start (ES), early finish (EF), and the project expected duration (TE) times have been computed. The backward pass is the next process to learn.

Backward Pass—Latest Times The backward pass starts with the last project activity(ies) on the network. You trace backward on each path subtracting activity times to find the late start (LS) and late finish (LF) times for each activity. Before the backward pass can be computed, the late finish for the last project activity(ies) must be selected. In early planning stages, this time is usually set equal to the early finish (EF) of the last project activity (or in the case of multiple finish activities, the activity with the largest EF). In some cases an imposed project duration deadline exists, and this date will be used. Let us assume for planning purposes we can accept the EF project duration (TE) equal to 100 workdays. The LF for activity H becomes 100 days (EF = LF) (see Figure 6.7).

Automated Warehouse Order Picking System

A

10

100

F35 50

15

E

50

35 85 H85

85

50

70 100

15

B10 15

5

D15 35

20

G35 70

35

Build & Test Hardware

Integrate System

Assign Team

Code Software

Test Software

Develop Patent Request

Design Hardware

C

25

10 35

ID

Legend

DUR

Description

ES

LS

EF

LF

SL

Define Requirements

FIGURE 6.6 Activity-on-Node Network Forward Pass

174 Chapter 6 Developing a Project Plan

The backward pass is similar to the forward pass; you need to remember three things: 1. You subtract activity times along each path starting with the project end activity

(LF − DUR = LS). 2. You carry the LS to the preceding activity to establish its LF, or 3. If the next preceding activity is a burst activity; in this case you select the smallest

LS of all its immediate successor activities to establish its LF. Let’s apply these rules to our Automated Warehouse example. Beginning with activ- ity H (integrate systems) and a LF of 100 workdays, the LS for activity H is 85 days (LF − DUR = LS or 100 − 15 = 85). The LS for activity H becomes the LF for activi- ties E, F, and G. Moving backward on the network the late starts for E, F, and G are shown here (LS = LF − DUR):

Activity E: LS = 85 − 50 = 35 Activity G: 85 − 35 = 50 Activity F: LS = 85 − 15 = 70

At this point we see that activity C is a burst activity that ties to (precedes) activities E and F. The late finish for activity C is controlled by the LS of activities E and F. The smallest LS of activities E and F (LS’s = 35 and 70) is activity E. This establishes the LF for activity C. The LS for activity C becomes 10. Moving backward to the first project activity, we note it is also a burst activity that links to activities B and C. The

FIGURE 6.7 Activity-on-Node Network Backward Pass

B

525 30

Assign Team

C

2510 35

A

100 10

10

25

35

70 Define

Requirements

D

2030 50

Code Software

E

5035 85

Build & Test Hardware

F

1570 85

Develop Patent Request

H

1585 100

Integrate Systems

G

3550 85

Automated Warehouse Order Picking System

ID

Legend

DUR

Description

ES

LS

EF

LF

SL

Design Hardware

Test Software

Chapter 6 Developing a Project Plan 175

LF of activity A is controlled by activity C that has the smallest LS of 10 days. Given a LF of 10 days, the LS for activity is time period zero (LS = 10 − 10 = 0). The back- ward pass is complete, and the latest activity times are known. Figure 6.8 shows the completed network with all the early, late, and slack times included. Slack can be important to managing your project.

Determining Slack (or Float) Total Slack When the forward and backward passes have been computed, it is possible to deter- mine which activities can be delayed by computing “slack” or “float.” Total slack tells us the amount of time an activity can be delayed and not delay the project. Stated dif- ferently, total slack is the amount of time an activity can exceed its early finish date without affecting the project end date or an imposed completion date. Total slack or float for an activity is simply the difference between the LS and ES (LS − ES = SL) or between LF and EF (LF − EF = SL). For example, in Figure 6.8 the total slack for activity D is 15 workdays, for activity F is 35 days, and for activity E is zero. If total slack of one activity in a path is used, the ES for all activities that follow in the chain will be delayed and their slack reduced. Use of total slack must be coordinated with all participants in the activities that follow in the chain. After slack for each activity is computed, the critical path(s) is (are) easily identi- fied. When the LF = EF for the end project activity, the critical path can be identified

Identify and understand the importance of managing the critical path.

6-4LO

Automated Warehouse Order Picking System

525

TS = 15 FS = 0

TS = 0 FS = 0TS = 0 FS = 0

TS = 15 FS = 0

TS = 0 FS = 0 TS = 0 FS = 0

TS = 35 FS = 35

TS = 15 FS = 15

30

15

10 15

2030 50

15

15 35

3550 85

15

35 70

117 18

15

2 3

5035 85

0

35 85

1570 85

35

35 50

1585 100

0

8570

85

50

100

2510 35

0

10 35

10 10

0

0 10

B

Assign Team

CA

0

10

25

35

70 Define

Requirements

D

Code Software

E

Build & Test Hardware

F

Develop Patent Request

H

Integrate Systems

G

ID

Legend

DUR

Description

ES

LS

EF

LF

SL

Design Hardware

Test Software

FIGURE 6.8 Forward and Backward Passes Completed with Slack Times

176 Chapter 6 Developing a Project Plan

as those activities that also have LF = EF or a slack of zero (LF − EF = 0 or LS − ES = 0). The critical path is the network path(s) that has (have) the least slack in com- mon. This awkward arrangement of words is necessary because a problem arises when the project finish activity has a LF that differs from the EF found in the forward pass— for example, an imposed duration date. If this is the case, the slack on the critical path will not be zero; it will be the difference between the project EF and the imposed LF of the last project activity. For example, if the EF for the project is 100 days, but the imposed LF or target date is set at 95 days, all activities on the critical path would have a slack of minus 5 days. Of course, this would result in a late start 5 days for the first project activity—a good trick if the project is to start now. Negative slack occurs in practice when the critical path is delayed. In Figure 6.8 the critical path is marked with dashed arrows—activities A, C, E, and H. Delay of any of these activities will delay the total project by the same num- ber of days. Since actual projects may have many critical activities with numerous preceding dependencies, coordination among those responsible for critical activi- ties is crucial. Critical activities typically represent about 10 percent of the activi- ties of the project. Therefore, project managers pay close attention to the critical path activities to be sure they are not delayed. See Snapshot from Practice 6.2: The Critical Path. We use the term sensitivity to reflect the likelihood the original critical path(s) will change once the project is initiated. Sensitivity is a function of the number of critical or near-critical paths. A network schedule that has only one critical path and noncritical activities that enjoy significant slack would be labeled insensitive.

The critical path method (CPM) has long been considered the “Holy Grail” of project management. Here are comments made by veteran project managers when asked about the sig-

nificance of the critical path in managing projects:

best people on critical activities or on those activities that stand the greatest chance of becoming critical.

identifying those risks that can impact the critical path, either directly or indirectly, by making a non- critical activity so late that it becomes critical. When I’ve got money to spend to reduce risks, it usually gets spent on critical tasks.

big project, but I make it a point to keep in touch with the people who are working on critical activi- ties. When I have the time, they are the ones I visit to find out firsthand how things are going. It’s amazing how much more I can find out from

S N A P S H O T F R O M P R A C T I C E 6 . 2 The Critical Path

talking to the rank and file who are doing the work and by reading the facial expressions of people— much more than I can gain from a number-driven status report.

“borrow” people or equipment, I’m much more generous when it involves resources from working on noncritical activities. For example, if another project manager needs an electrical engineer who is assigned to a task with five days of slack, I’m will- ing to share that engineer with another project manager for two to three days.

- tant is because these are the activities that impact completion time. If I suddenly get a call from above saying they need my project done two weeks ear- lier than planned, the critical path is where I sched- ule the overtime and add extra resources to get the project done more quickly. In the same way, if the project schedule begins to slip, it’s the critical activ- ities I focus on to get back on schedule.

Chapter 6 Developing a Project Plan 177

Conversely, a sensitive network would be one with more than one critical path and/ or noncritical activities with very little slack. Under these circumstances the original critical path is much more likely to change once work gets under way on the project. How sensitive is the Automated Warehouse schedule? Not very, since there is only one critical path and the two other noncritical paths have 15 and 35 days of slack, which suggests considerable flexibility. Project managers assess the sensitivity of their network schedules to determine how much attention they should devote to man- aging the critical path.

Free Slack (Float) Free slack (FS) is unique. It is the amount of time an activity can be delayed without delaying any immediately following (successor) activity. Or, free slack is the amount of time an activity can exceed its early finish date without affecting the early start date of any successor(s). Free slack can never be negative. Only activities that occur at the end of a chain of activities, where you have a merge activity, can have free slack. See Figure 6.8, the Automated Warehouse project. In Figure 6.8 activity G has free slack of 15 days, while activities B and D do not. In this case, activity G is the last activity in the upper path, and it merges to activity H. Hence, to delay activity G up to 15 days does not delay any following activities and requires no coordination with managers of other activities. Conversely, if either activ- ity B or D is delayed, the managers of following activities need to be notified that the slack has been used so they can adjust their start schedules. For example, if activity B is delayed 5 days, the manager of activity B should notify those in charge of the fol- lowing activities (D and G) that their slack has been reduced to 10 time units and their early start will be delayed 5 days. In this example, activity D cannot then start until day 20, which reduces activity D slack to 10 days (LS − ES = SL or 30 − 20 = 10). Free slack for activity G is also reduced to 10 days. Free slack occurs at the last activity in a chain of activities. In some situations the “chain” has only one link. Activity F in Figure 6.8 is an example. It has free slack of 35 days. Note that it needs no coordination with other activities—unless a delay exceeds the free slack of 35 days. (Note: The moment you exceed all free slack avail- able, you delay the project and must coordinate with others who are impacted.) The distinction between free and total slack at first glance seems trivial, but in real- ity it is very important. When you are responsible for a late activity that has zero free slack you impact the schedules of subsequent activities. You should notify the manag- ers of the remaining activities in the chain that you will be late. Again, note that total slack is shared across the whole path. Alternatively, if you are responsible for an activ- ity that has free slack when you start, you do not need to notify anyone as long as your work does not absorb all of the slack!

6.6 Using the Forward and Backward Pass Information Returning to the Automated Warehouse project network in Figure 6.8, what does a slack of 35 days for activity F (develop patent request) mean for the project manager? In this specific case it means activity F can be delayed 35 days. In a larger sense the project manager soon learns that free slack is important because it allows flexibility in scheduling scarce project resources—personnel and equipment—that are used on more than one parallel activity or another project.

6-5LO Distinguish free slack from total slack.

178 Chapter 6 Developing a Project Plan

Knowing the four activity times of ES, LS, EF, and LF is invaluable for the plan- ning, scheduling, and controlling phases of the project. The ES and LF tell the project manager the time interval in which the activity should be completed. For example, activity G (test software) must be completed within the time interval 35 and 85 days; the activity can start as early as day 35 or finish as late as day 85. Conversely, activity C (design hardware) must start on day 10, or the project will be delayed. When the critical path is known, it is possible to tightly manage the resources of the activities on the critical path so no mistakes are made that will result in delays. In addi- tion, if for some reason the project must be expedited to meet an earlier date, it is pos- sible to select those activities, or combination of activities, that will cost the least to shorten the project. Similarly, if the critical path is delayed and the time must be made up by shortening some activity or activities on the critical path to make up any negative slack, it is possible to identify the activities on the critical path that cost the least to shorten. If there are other paths with very little slack, it may be necessary to shorten activities on those paths also.

6.7 Level of Detail for Activities Time-phasing work and budgets of the project mandate careful definition of the activi- ties that make up the project network. Typically an activity represents one or more tasks from a work package. How many tasks you include in each activity sets the level of detail. In some cases it is possible to end up with too much information to manage, and this can result in increased overhead costs. Managers of small projects have been able to minimize the level of detail by eliminating some of the preliminary steps to drawing networks. Larger firms also recognize the cost of information overload and are working to cut down the level of detail in networks and in most other dimensions of the project.

6.8 Practical Considerations

Network Logic Errors Project network techniques have certain logic rules that must be followed. One rule is that conditional statements such as “if test successful build proto, if failure redesign” are not permitted. The network is not a decision tree; it is a project plan that we assume will materialize. If conditional statements were allowed, the forward and backward pass would make little sense. Although in reality a plan seldom materializes as we expect in every detail, it is a reasonable initial assumption. You shall see that once a network plan is developed, it is an easy step to make revisions to accommodate changes. Another rule that defeats the project network and computation process is looping. Looping is an attempt by the planner to return to an earlier activity. Recall that the activity identification numbers should always be higher for the activities following an activity in question; this rule helps to avoid the illogical precedence relationships among the activities. An activity should only occur once; if it is to occur again, the activity should have a new name and identification number and should be placed in the right sequence on the network. Figure 6.9 shows an illogical loop. If this loop were allowed to exist, this path would perpetually repeat itself. Many computer programs catch this type of logic error.

Chapter 6 Developing a Project Plan 179

Activity Numbering Each activity needs a unique identification code—a letter or a number. In practice very elegant schemes exist. Most schemes number activities in ascending order, that is, each succeeding activity has a larger number so that the flow of the project activities is toward project completion. It is customary to leave gaps between numbers (1, 5, 10, 15 . . .). Gaps are desirable so you can add missing or new activities later. Because it is nearly impossible to draw a project network perfectly, numbering networks is fre- quently not done until after the network is complete. In practice you will find computer programs that accept numeric, alphabetic, or a com- bination of activity designations. Combination designations are often used to identify cost, work skill, departments, and locations. As a general rule, activity numbering systems should be ascending and as simple as possible. The intent is to make it as easy as you can for project participants to follow work through the network and locate specific activities.

Use of Computers to Develop Networks All of the tools and techniques discussed in this chapter can be used with computer software currently available. Two examples are shown in Figures 6.10 and 6.11. Figure 6.10 presents a generic AON computer output for the Automated Warehouse Picking Sys- tem project. Observe that these computer outputs use numbers to identify activities. The critical path is identified by the nodes (activities) 2, 4, 6, and 9. The activity description is shown on the top line of the activity node. The activity start time and identification are on the second line. The finish time and duration are on the third line of the node. The project starts on January 1 and is planned to finish May 20. Note this sample computer network has included non-workdays of holidays and weekends. Figure 6.11 presents an early start Gantt chart.2 Bar charts are popular because they present an easy-to-understand, clear picture on a time-scaled horizon. They are used dur- ing planning, resource scheduling, and status reporting. The format is a two-dimensional representation of the project schedule, with activities down the rows and time across the horizontal axis. In this computer output the shaded bars represent the activity durations. The extended lines from the bars represent slack. For example, “test software” (ID # 8) has a duration of 35 days (shaded area of the bar) and 15 days slack (represented by the extended line). The bar also indicates test software has an early start of February 19 and would finish April 8, but can finish as late as April 29 because it has 15 days of slack. When calendar dates are used on the time axis, Gantt charts provide a clear overview of the project schedule and can often be found posted on the walls of project offices. Unfor- tunately, when projects have many dependency relationships, the dependency lines soon become overwhelming and defeat the simplicity of the Gantt chart. Project management software can be a tremendous help in the hands of those who understand and are familiar with the tools and techniques discussed in this text. How- ever, there is nothing more dangerous than someone using the software with little or no

FIGURE 6.9 Illogical Loop A

C

B

2 Gantt charts were introduced over 100 years ago by Henry Gantt.

180

FI GU

RE 6

.10

Au to

m at

ed W

ar eh

ou se

O rd

er P

ic ki

ng S

ys te

m N

et wo

rk

D efi

ne R

eq .s

St ar

t: T

ue 1/

1 Fi

ni sh

: M on

1/ 14

Re

s:

ID :

2 D

ur : 1

0 da

ys

A ss

ig n

Te am

St ar

t: Tu

e 1/

15 Fi

ni sh

: M on

1/ 21

Re s:

ID :

3 D

ur : 5

d ay

s

D es

ig n

H ar

dw ar

e St

ar t:

Tu e

1/ 15

Fi ni

sh : M

on 2

/1 8

Re s:

ID :

4 D

ur : 2

5 da

ys

D ev

. P at

en t R

eq ue

st St

ar t:

Tu e

2/ 19

Fi ni

sh : M

on 3

/1 1

Re s:

ID :

7 D

ur : 1

5 da

ys

Te st

S of

tw ar

e St

ar t:

Tu e

2/ 19

Fi ni

sh : M

on 4

/8 Re

s:

ID :

8 D

ur : 3

5 da

ys

In te

gr at

e Sy

st em

s St

ar t:

Tu e

4/ 30

Fi ni

sh : M

on 5

/2 0

Re s:

ID :

9 D

ur : 1

5 da

ys

C od

e So

ft w

ar e

St ar

t: Tu

e 1/

22 Fi

ni sh

: M on

2 /1

8 Re

s:

ID :

5 D

ur : 2

0 da

ys

B ui

ld &

T es

t H W

St ar

t: Tu

e 2/

19 Fi

ni sh

: M on

4 /2

9 Re

s:

ID :

6 D

ur : 5

0 da

ys

A ut

om at

ed W

ar eh

ou se

O rd

er P

ic ki

ng S

ys te

m N

et w

or k

D ia

gr am

181

ID 2 3 4 5 6 7 8 9

10 5 25 20 50 15 35 15

D ur

at io

n St

ar t

Tu e

1/1 Tu

e 1/1

5 Tu

e 1/1

5 Tu

e 1/2

2 Tu

e 2/

19 Tu

e 2/

19 Tu

e 2/

19 Tu

e 4/

30

Fi ni

sh Au

to m

at ed

W ar

eh ou

se O

rd er

P ic

ki ng

S ys

te m

S ch

ed ul

e Ta

bl e

M on

1/ 14

M on

1/ 21

M on

2 /18

M on

2 /18

M on

4 /2

9 M

on 3

/11 M

on 4

/8 M

on 5

/2 0

La te

S ta

rt Tu

e 1/1

Tu e

2/ 5

Tu e

1/1 5

Tu e

2/ 12

Tu e

2/ 19

Tu e

4/ 9

Tu e

3/ 12

Tu e

4/ 30

Tu e

1/1 5

M on

2 /11

M on

2 /18

M on

3 /11

M on

4 /2

9 M

on 4

/2 9

M on

4 /2

9 M

on 5

/2 0

La te

F in

ish Fr

ee S

la ck

0 da

ys 0

da ys

0 da

ys 0

da ys

0 da

ys 35

d ay

s 15

d ay

s 0

da ys

To ta

l S la

ck Ja

n Fe

b M

ar Ap

r 0

da ys

15 d

ay s

0 da

ys 15

d ay

s 0

da ys

35 d

ay s

15 d

ay s

0 da

ys

Ta sk

N am

e D

efi ne

R eq

.s As

sig n

Te am

D es

ig n

H ar

dw ar

e Co

de S

of tw

ar e

Bu ild

a nd

T es

t H W

D ev

. P at

en t R

eq ue

st Te

st S

of tw

ar e

In te

gr at

e Sy

st em

s

M ay

FI GU

RE 6

.11

Au to

m at

ed O

rd er

W ar

eh ou

se P

ic ki

ng S

ys te

m B

ar C

ha rt

182 Chapter 6 Developing a Project Plan

knowledge of how the software derives its output. Mistakes in input are very common and require someone skilled in the concepts, tools, and information system to recog- nize that errors exist so false actions are avoided.

Calendar Dates Ultimately you will want to assign calendar dates to your project activities. If a com- puter program is not used, dates are assigned manually. Lay out a calendar of workdays (exclude non-workdays), and number them. Then relate the calendar workdays to the workdays on your project network. Most computer programs will assign calendar dates automatically after you identify start dates, time units, non-workdays, and other information.

Multiple Starts and Multiple Projects Some computer programs require a common start and finish event in the form of a node—usually a circle or rectangle—for a project network. Even if this is not a require- ment, it is a good idea because it avoids “dangler” paths. Dangler paths give the impression that the project does not have a clear beginning or ending. If a project has more than one activity that can begin when the project is to start, each path is a dangler path. The same is true if a project network ends with more than one activity; these unconnected paths are also called danglers. Danglers can be avoided by tying dangler activities to a common project start or finish node. When several projects are tied together in an organization, using a common start and end node helps to identify the total planning period of all projects. Use of pseudo or dummy wait activities from the common start node allows different start dates for each project.

6.9 Extended Network Techniques to Come Closer to Reality The method for showing relationships among activities in the last section is called the finish-to-start relationship because it assumes all immediate preceding connected activities must be completed before the next activity can begin. In an effort to come closer to the realities of projects, some useful extensions have been added. The use of laddering was the first obvious extension practitioners found very useful.

Laddering The assumption that all immediate preceding activities must be 100 percent complete is too restrictive for some situations found in practice. This restriction occurs most frequently when one activity overlaps the start of another and has a long duration. Under the standard finish-to-start relationship, when an activity has a long duration and will delay the start of an activity immediately following it, the activity can be bro- ken into segments and the network drawn using a laddering approach so the following activity can begin sooner and not delay the work. This segmenting of the larger activity gives the appearance of steps on a ladder on the network, thus the name. The classic example used in many texts and articles is laying pipe, because it is easy to visualize. The trench must be dug, pipe laid, and the trench refilled. If the pipeline is one mile long, it is not necessary to dig one mile of trench before the laying of pipe can begin or to lay one mile of pipe before refill can begin. Figure 6.12 shows how these overlap- ping activities might appear in an AON network using the standard finish-to-start approach.

6-6LO Demonstrate under- standing and application of lags in compressing projects or constraining the start or finish of an activity.

Chapter 6 Developing a Project Plan 183

Use of Lags to Reduce Schedule Detail and Project Duration The use of lags has been developed to offer greater flexibility in network construction. A lag is the minimum amount of time a dependent activity must be delayed to begin or end. The use of lags in project networks occurs for two primary reasons: 1. When activities of long duration delay the start or finish of successor activities, the

network designer normally breaks the activity into smaller activities to avoid the long delay of the successor activity. Use of lags can avoid such delays and reduce network detail.

2. Lags can be used to constrain the start and finish of an activity. The most commonly used relationship extensions are start-to-start, finish-to-finish, and combinations of these two. These relationship patterns are discussed in this section.

Finish-to-Start Relationship The finish-to-start relationship represents the typical, generic network style used in the early part of the chapter. However, there are situations in which the next activity in a sequence must be delayed even when the preceding activity is complete. For example, removing concrete forms cannot begin until the poured cement has cured for two time units. Figure 6.13 shows this lag relationship for AON networks. Finish-to-start lags are frequently used when ordering materials. For example, it may take 1 day to place orders but take 19 days to receive the goods. The use of finish-to-start allows the activity dura- tion to be only 1 day and the lag 19 days. This approach ensures the activity cost is tied to placing the order only rather than charging the activity for 20 days of work. This same finish-to-start lag relationship is useful to depict transportation, legal, and mail lags. The use of finish-to-start lags should be carefully checked to ensure their validity. Con- servative project managers or those responsible for completion of activities have been known to use lags as a means of building in a “slush” factor to reduce the risk of being late. A simple rule to follow is that the use of finish-to-start lags must be justified and approved by someone responsible for a large section of the project. The legitimacy of lags is not usually difficult to discern. The legitimate use of the additional relationship shown can greatly enhance the network by more closely representing the realities of the project.

Start-to-Start Relationship An alternative to segmenting the activities as we did earlier is to use a start-to-start relationship. Typical start-to-start relationships are shown in Figure 6.14. Figure 6.14A

FIGURE 6.12 Example of Laddering Using Finish-to-Start Relationship

Trench 1/3

Trench 1/3

Lay pipe 1/3

Trench 1/3

AON network

Lay pipe 1/3

Refill 1/3

Lay pipe 1/3

Refill 1/3

Refill 1/3

FIGURE 6.13 Finish-to-Start Relationship

X Lag 19

Y

184 Chapter 6 Developing a Project Plan

shows the start-to-start relationship with zero lag, while Figure 6.14B shows the same relationship with a lag of five time units. It is important to note that the relationship may be used with or without a lag. If time is assigned, it is usually shown on the depen- dency arrow of an AON network. In Figure 6.14B, activity Q cannot begin until five time units after activity P begins. This type of relationship typically depicts a situation in which you can perform a por- tion of one activity and begin a following activity before completing the first. This relationship can be used on the pipe-laying project. Figure 6.15 shows the project using an AON network. The start-to-start relationship reduces network detail and project delays by using lag relationships. It is possible to find compression opportunities by changing finish-to-start relations to start-to-start relationships. A review of finish-to-start critical activities may point out opportunities that can be revised to be parallel by using start-to-start relationships. For example, in place of a finish-to-start activity “design house, then build foundation,” a start-to-start relationship could be used in which the foundation can be started, say, five days (lag) after design has started—assuming the design of the foundation is the first part of the total design activity. This start-to-start relationship with a small lag allows a sequential activity to be worked on in parallel and to compress the duration of the criti- cal path. This same concept is frequently found in projects in which concurrent engi- neering is used to speed completion of a project. Concurrent engineering, which is highlighted in the Snapshot from Practice 6.3: Concurrent Engineering, basically breaks activities into smaller segments so that work can be done in parallel and the project

FIGURE 6.14 Start-to-Start Relationship

Activity M

Activity N

Activity P

A

Activity Q

B

Lag 5

FIGURE 6.15 Use of Lags to Reduce Project Duration

Trench 1 mile

Lay pipe 1 mile

Lag 3

Refill 1 mile

Lag 3

Chapter 6 Developing a Project Plan 185

In the old days, when a new product development project was initiated by a firm, it would start its sequential journey in the research and develop- ment department. Concepts and

ideas would be worked out and the results passed to the engineering department, which sometimes reworked the whole product. This result would be passed to manufacturing, where it might be reworked once more in order to ensure the product could be manufactured using existing machinery and opera- tions. Quality improvements were initiated after the fact once defects and improvement opportunities were discovered during production. This sequential approach to product development required a great deal of time, and it was not uncommon for the final product to be totally unrecognizable when compared to original specifications. Given the emphasis on speed to the market, com- panies have abandoned the sequential approach to product development and have adopted a more

holistic approach titled concurrent engineering. In a nutshell, concurrent engineering entails the active involvement of all the relevant specialty areas throughout the design and development process. The traditional chainlike sequence of finish-to-start relationships is replaced by a series of start-to-start lag relationships as soon as meaningful work can be initiated for the next phase. Figure 6.16 summarizes the dramatic gains in time to market achieved by this approach. Within the world of project management this approach is also called Fast Tracking. General Motors used this approach to design the very first American hybrid car, the Chevy Volt. From the very beginning specialists from marketing, engineering, design, manufacturing, quality assurance, and other relevant departments were involved in every stage of the proj- ect. Not only did the project meet all of its objectives, it was completed ahead of schedule.

*“Chevrolet Volt Hits Road, Ahead of Schedule,” The New York Times, June 25, 2009; accessed online June 2, 2011.

S N A P S H O T F R O M P R A C T I C E 6 . 3 Concurrent Engineering*

Engineering design &

development

Engineering design &

development

Product planning

Product planning

Systems engineering

Systems engineering

Time

Procurement

Procurement

Manufacturing & production

Manufacturing & production

Quality assurance

Quality assurance Release

Traditional Sequential Approach

Concurrent Engineering Approach

Release

FIGURE 6.16 New Product Development Process

186 Chapter 6 Developing a Project Plan

expedited (Turtle, 1994). Start-to-start relationships can depict the concurrent engineer- ing conditions and reduce network detail. Of course, the same result can be accom- plished by breaking an activity into small packages that can be implemented in parallel, but this latter approach increases the network and tracking detail significantly. Finish-to-Finish Relationship This relationship is found in Figure 6.17. The finish of one activity depends on the fin- ish of another activity. For example, testing cannot be completed any earlier than four days after the prototype is complete. Note that this is not a finish-to-start relationship because the testing of subcomponents can begin before the prototype is completed, but four days of “system” testing is required after the prototype is finished. Start-to-Finish Relationship This relationship represents situations in which the finish of an activity depends on the start of another activity. For example, system documentation cannot end until three days after testing has started (see Figure 6.18). Here all the relevant information to complete the system documentation is produced after the first three days of testing. Combinations of Lag Relationships More than one lag relationship can be attached to an activity. These relationships are usually start-to-start and finish-to-finish combinations tied to two activities. For exam- ple, debug cannot begin until two time units after coding has started. Coding must be finished four days before debug can be finished (see Figure 6.19).

An Example Using Lag Relationships—The Forward and Backward Pass The forward and backward pass procedures are the same as explained earlier in the chapter for finish-to-start relationships (without lags). The modifying technique lies in the need to check each new relationship to see if it alters the start or finish time of another activity.

FIGURE 6.17 Finish-to-Finish Relationship

Prototype

Testing

Lag 4

FIGURE 6.18 Start-to-Finish Relationship

Testing

System documentation

Lag 3

FIGURE 6.19 Combination Relationships

Debug Lag 2

Lag 4 Code

Chapter 6 Developing a Project Plan 187

An example of the outcome of the forward and backward pass is shown in Fig- ure 6.20. Order hardware depends upon the design of the system (start-to-start). Three days into the design of the system (activity A), it is possible to order the required hard- ware (activity B). It takes four days after the order is placed (activity B) for the hard- ware to arrive so it can begin to be installed (activity C). After two days of installing the software system (activity D), the testing of the system can begin (activity E). System testing (activity E) can be completed two days after the software is installed (activity D). Preparing system documentation (activity F) can begin once the design is com- pleted (activity A), but it cannot be completed until two days after testing the system (activity E). This final relationship is an example of a finish-to-finish lag. Note how an activity can have a critical finish and/or start. Activities E and F have critical finishes (zero slack), but their activity starts have 4 and 12 days of slack. It is only the finishes of activities E and F that are critical. Conversely, activity A has zero slack to start but has five days of slack to finish. The critical path follows activity start and finish constraints that occur due to the use of the additional relationships available and the imposed lags. You can identify the critical path in Figure 6.20 by following the dashed line on the network. If a lag relationship exists, each activity must be checked to see if the start or finish is constrained. For example, in the forward pass the EF of activity E (test system) (18) is controlled by the finish of activity D (install software) and the lag of two time units (16 + lag 2 = 18). Finally, in the backward pass, the LS of activity A (design system) is controlled by activity B (order hardware) and the lag relationship to activity A (3 − 3 = 0).

A

5

5

10

0

50

0

Design system

ID

Legend

Duration

Description

ES

LS

EF

LF

SL SL

F

3

20

20

5

012

17

System documentation

B

1

4

4

3

00

3

Order hardware

C

2

10

10

8

00 Lag 4Lag 3

Lag 2

Lag 2

Lag 2

8

Install hardware

D

6

16

16

10

00

10

Install software

E

2

18

18

12

04

16

Test system

FIGURE 6.20 Network Using Lags

188 Chapter 6 Developing a Project Plan

Hammock Activities Another of the extended techniques uses a hammock activity. This type of activity derives its name because it spans over a segment of a project. The hammock activity duration is determined after the network plan is drawn. Hammock activities are fre- quently used to identify the use of fixed resources or costs over a segment of the project. Typical examples of hammock activities are inspection services, consultants, or con- struction management services. A hammock activity derives its duration from the time span between other activities. For example, a special color copy machine is needed for a segment of a tradeshow publication project. A hammock activity can be used to indi- cate the need for this resource and to apply costs over this segment of the project. This hammock is linked from the start of the first activity in the segment that uses the color copy machine to the end of the last activity that uses it. The hammock duration is simply the difference between the EF for the last activity and the ES of the first activity. The duration is computed after the forward pass and hence has no influence on other activity times. Figure 6.21 provides an example of a hammock activity used in a network. The duration for the hammock activity is derived from the early start of activity B and the early finish of activity F; that is, the difference between 13 and 5, or 8 time units. The hammock duration will change if any ES or EF in the chain-sequence changes. Hammock activities are very useful in assigning and controlling indirect project costs.3 Another major use of hammock activities is to aggregate sections of a project. This is similar to developing a subnetwork, but the precedence is still preserved. This approach is sometimes used to present a “macro network” for upper management lev- els. Using a hammock activity to group activities can facilitate getting the right level of detail for specific sections of a project.

FIGURE 6.21 Hammock Activity Example

H

4

21

21

25

25

0

A

5

ID

Legend

Dur.

ES

LS

EF

LF

SL Description

B

1

C

5

D

4

F

3

0

0

5

5

6

6

6

14

10

18

5

5

6

6

11

11

10

18

13

21

0 0

0

8 8

E

10

11

11

21

21

0

Hammock

G

8

5 13

3 In order to designate G as a Hammock activity in MS Project 2012 you would copy and paste for activity G the start date of activity B and the finish date for activity F (http://support.microsoft.com/kb/141733).

Chapter 6 Developing a Project Plan 189

Key Terms Activity, 164, 166, 168 Activity-on-arrow (AOA), 167 Activity-on-node (AON), 167 Burst activity, 166 Concurrent engineering, 184

Critical path, 166 Early time, 166 Free slack (FS), 177 Gantt chart, 179 Hammock activity, 188 Lag relationship, 183

Late time, 166 Merge activity, 166 Parallel activity, 166 Path, 166 Sensitivity, 176 Total slack, 175

1. How does the WBS differ from the project network? 2. How are WBS and project networks linked? 3. Why bother creating a WBS? Why not go straight to a project network and forget

the WBS? 4. Why is slack important to the project manager? 5. What is the difference between free slack and total slack? 6. Why are lags used in developing project networks? 7. What is a hammock activity, and when is it used?

Review Questions

Many project managers feel the project network is their most valuable exercise and planning document. Project networks sequence and time-phase the project work, resources, and budgets. Work package tasks are used to develop activities for networks. Every project manager should feel comfortable working in an AON envi- ronment. The AON method uses nodes (boxes) for activities and arrows for dependencies. The forward and backward passes establish early and late times for activities. Although most project managers use computers to generate networks and activity times, they find a keen understanding of network development and the abil- ity to compute activity times is invaluable in the field. Computers break down; input errors give false information; some decisions must be made without computer “what if ” analysis. Project managers who are well acquainted with network development and AON methods and who are able to compute activity times will encounter fewer problems than project managers less well acquainted. Project networks help to ensure there are no surprises. Several extensions and modifications have been appended to the original AON method. Lags allow the project planner to more closely replicate the actual conditions found in practice. The use of lags can result in the start or finish of an activity becom- ing critical. Some computer software simply calls the whole activity critical rather than identifying the start or finish as being critical. Caution should be taken to ensure that lags are not used as a buffer for possible errors in estimating time. Finally, hammock activities are useful in tracking costs of resources used for a particular segment of a project. Hammock activities can also be used to reduce the size of a project network by grouping activities for simplification and clarity. All of the discussed refinements to the original AON methodology contribute toward better planning and control of projects.

Summary

190 Chapter 6 Developing a Project Plan

Creating a Project Network 1. Here is a partial work breakdown structure for a wedding. Use the method described

in the Snapshot from Practice 6.1: The Yellow Sticky Approach to create a network for this project.

Note: Do not include summary tasks in the network (i.e., 1.3, Ceremony, is a summary task; 1.2, Marriage license, is not a summary task). Do not consider who would be doing the task in building the network. For example, do not arrange “hiring a band” to occur after “florist” because the same person is responsible for doing both tasks. Focus only on technical dependencies between tasks. Hint: Start with the last activity (wedding reception), and work your way back to the start of the project. Build the logical sequence of tasks by asking the following ques- tion: In order to have or do this, what must be accomplished immediately before this? Once completed, check forward in time by asking this question: Is this task(s) the only thing that is needed immediately before the start of the next task? Work Breakdown Structure 1. Wedding project 1.1 Decide on date 1.2 Marriage license 1.3 Ceremony 1.3.1 Rent church

1.3.2 Florist

1.3.3 Create/print programs

1.3.4 Hire photographer

1.3.5 Wedding ceremony

1.4 Guests 1.4.1 Develop guest list

1.4.2 Order invitations

1.4.3 Address and mail invitations

1.4.4 Track RSVPs

1.5 Reception 1.5.1 Reserve reception hall

1.5.2 Food and beverage

1.5.2.1 Choose caterer

1.5.2.2 Decide on menu

1.5.2.3 Make final order

1.5.3 Hire DJ

1.5.4 Decorate reception hall

1.5.5 Wedding reception

Exercises

Chapter 6 Developing a Project Plan 191

Drawing AON Networks 2. Draw a project network from the following information. What activity(ies) is a burst

activity? What activity(ies) is a merge activity?

ID Description Predecessor

A Survey site None B Excavate site A C Install power lines B D Install drainage B E Pour foundation C, D

3.* Draw a project network from the following information. What activity(ies) is a burst activity? What activity(ies) is a merge activity?

ID Description Predecessor

A Identify topic None B Research topic A C Draft paper B D Edit paper C E Create graphics C F References C G Proof paper D, E, F H Submit paper G

4. Draw a project network from the following information. What activity(ies) is a burst activity? What activity(ies) is a merge activity?

ID Description Predecessor

A Contract signed None B Survey designed A C Target market identified B D Data collection B, C E Develop presentation B F Analyze results D G Demographics C H Presentation E, F, G

5. Draw a project network from the following information. What activity(ies) is a burst activity? What activity(ies) is a merge activity?

ID Description Predecessor

A Order review None B Order standard parts A C Produce standard parts A D Design custom parts A E Software development A F Manufacture custom parts C, D G Assemble B, F H Test E, G

* The solution to this exercise can be found in Appendix One.

192 Chapter 6 Developing a Project Plan

AON Network Times 6. From the following information, develop an AON project network. Complete the

forward and backward pass, compute activity slack, and identify the critical path. How many days will the project take?

ID Description Predecessor Time

A Survey site None 2 B Excavate site A       4 C Install power lines B       3 D Install drainage B     5 E Pour foundation C, D   3

7. The project information for the custom order project of the Air Control Company is presented here. Draw a project network for this project. Compute the early and late activity times and the slack times. Identify the critical path.

ID Description Predecessor Time

A Order review None 2 B Order standard parts A       3 C Produce standard parts A       10 D Design custom parts A       13 E Software development A       18 F Manufacture custom hardware C, D  15 G Assemble B, F  10 H Test E, G   5

8. You have signed a contract to build a garage for the Simpsons. You will receive a $500 bonus for completing the project within 17 working days. The contract also contains a penalty clause in which you will lose $100 for each day the project takes longer than 17 working days.

Draw a project network given the information below. Complete the forward and backward pass, compute the activity slack, and identify the critical path. Do you expect to receive a bonus or a penalty on this project?

ID Description Predecessor Time (days)

A Prepare site None 2 B Pour foundation B 3 C Erect frame C 4 D Roof C 4 E Windows C 1 Doors C 1 G Electrical D, E, F, G 3 H Rough-in frame F, G 2 I Door opener H, I 1 J Paint J 2 K Cleanup 1

9. You are creating a customer database for the Hillsboro Hops minor league baseball team. Draw a project network given the information in the table that follows. Complete the forward and backward pass, compute activity slack, and identify the critical path.

How long will this project take? How sensitive is the network schedule? Calcu- late the free slack and total slack for all noncritical activities.

Chapter 6 Developing a Project Plan 193

ID Description Predecessor Time (days)

A Systems design None 2 B Subsystem A design A 1 C Subsystem B design A 1 D Subsystem C design A 1 E Program A B 2 F Program B C 2 G Program C D 2 H Subsystem A test E 1 I Subsystem B test F 1 J Subsystem C test G 1 K Integration H, I, J 3 L Integration test K 1

10. K. Nelson, project manager of Print Software, Inc., wants you to prepare a project network; compute the early, late, and slack activity times; determine the planned project duration; and identify the critical path. His assistant has collected the fol- lowing information for the Color Printer Drivers Software Project:

ID Description Predecessor Time

A External specifications None 8 B Review design features A        2 C Document new features A        3 D Write software A      60 E Program and test B      40 F Edit and publish notes C        2 G Review manual D        2 H Alpha site E, F  20 I Print manual G      10 J Beta site H, I   10 K Manufacture J       12 L Release and ship K        3

11. * A large Southeast city is requesting federal funding for a park-and-ride project. One of the requirements in the request application is a network plan for the design phase of the project. Sophie Kim, the chief engineer, wants you to develop a proj- ect network plan to meet this requirement. She has gathered the activity time esti- mates and their dependencies shown here. Show your project network with the activity early, late, and slack times. Mark the critical path.

ID Description Predecessor Time

A Survey None 5 B Soils report A 20 C Traffic design A 30 D Lot layout A 5 E Approve design B, C, D 80 F Illumination E 15 G Drainage E 30 H Landscape E 25 I Signage E 15 J Bid proposal F, G, H, I 10

* The solution to this exercise can be found in Appendix One.

194 Chapter 6 Developing a Project Plan

12. You are creating a customer database for the Lehigh Valley IronPigs minor league baseball team. Draw a project network given the information below. Complete the forward and backward pass, compute activity slack, and identify the critical path.

How long will this project take? How sensitive is the network schedule? Calcu- late the free slack and total slack for all noncritical activities.

Time ID Description Predecessor (days)

A Systems design None 2 B Subsystem A design A 1 C Subsystem B design A 2 D Subsystem C design A 1 E Program A B 2 F Program B C 10 G Program C D 3 H Subsystem A test E 1 I Subsystem B test F 1 J Subsystem C test G 1 K Integration H, I, J 3 L Integration test K 1

13. * You are completing a group term paper. Given the project network that follows, complete the forward and backward pass, compute activity slack, and identify the critical path. Use this information to create a Gantt chart for the project. Be sure to show slack for noncritical activities.

* The solution to this exercise can be found in Appendix One.

ID

Legend

DUR

ES

LS

EF

LF

SL

A

1

Identify topic

Research topic

Draft paper

Edit paper

Create graphics

References

Final Draft

Proof

Identify topic

Group Term Paper

B

5

0 2 4 6 8 10 12 14

Research topic

C

3

Draft paper

D

2

Edit paper

G

1

Proof

F

1

References

Description

E

1

Create graphics

Submit Paper

H

1

Chapter 6 Developing a Project Plan 195

ID

Legend

DUR

ES

LS

EF

LF

SL

A

1

Form Project Team

B

5

Interview Users

C

3

Survey Users

D

2

Identify New Features

G

3

Produce Prototype

J

3

Perform Sales Calls

H

3

Design Graphics

I

5

Conduct Marketing

Description

E

4

Acquire Materials

F

2

Develop Mrkt Campaign

Product Upgrade Project

Project Team

Interview Users

Survey Users

ID New Features

Acquire Materials

Dev Mrkt Campaign

Produce Prototypes

Design Graphics

Conduct Marketing

Perform Sales Calls

1 2 3 4 5 6 7 8 9 10 11 1312 14 15 16 17 18

Product Upgrade Project Gantt Chart

14. You are managing a product upgrade project for Bangkokagogo. Given the project network that follows, complete the forward and backward pass, compute activity slack, and identify the critical path. Use this information to create a Gantt chart for the project. Be sure to show slack for noncritical activities.

15. You are creating a database for the Oklahoma City Thunder NBA Basketball team. Given the project network that follows, complete the forward and backward pass, compute activity slack, and identify the critical path. Use this information to create a Gantt chart for the project.

196 Chapter 6 Developing a Project Plan

Computer Exercises 16. The planning department of an electronics firm has set up the activities for devel-

oping and production of a new MP3 Player. Given the information below, develop a project network using Microsoft Project. Assume a five-day workweek and the project starts on January 4, 2017.

Activity Description Activity Activity Time ID Predecessor (weeks)

1 Staff None 2 2 Develop market program 1          3 3 Select channels of distribution 1          8 4 Patent 1       12 5 Pilot production 1         4 6 Test market 5         4 7 Ad promotion 2         4 8 Set up for production 4, 6   16

The project team has requested that you create a network for the project, and deter- mine if the project can be completed in 45 weeks.

ID

Legend

DUR

ES

LS

EF

LF

SL

A

2

Problem Definition

B

3

System Analysis

E

6

Develop Input Screens

H

2

Test System

F

4

Develop Output Reports

G

5

Create Database

Description

C

4

Design I/Q

D

10

Design Database

I

3

Implement System

Problem Definition

System Analysis

Design I/Q

Design Database

Develop Input Screens

Develop Input Reports

Create Database

Test System

Implement System

10 2 3 4 5 6 7 8 9 10 11 1312 14 15 16 17 18 19 20 21 22 23 24 25

Chapter 6 Developing a Project Plan 197

17. Using Microsoft Project, set up the network and determine the critical path for Phase 1 of the Whistler Ski Resort project. The project workweek will be 5 days (M–F).

Whistler Ski Resort Project Given the fact that the number of skiing visitors to Whistler, B.C., Canada, has been increasing at an exciting rate, thanks to the 2010 Winter Olympics, the Whistler Ski Association has been considering construction of another ski lodge and ski complex. The results of an economic feasibility study just completed by members of the staff show that a winter resort complex near the base of Whistler Mountain could be a very profitable venture. The area is accessible by car, bus, train, and air. The board of directors has voted to build the 10-million-dollar complex recommended in the study. Unfortunately, due to the short summer season, the complex will have to be built in stages. The first stage (year 1) will contain a day lodge, chair lift, rope tow, generator house (for electricity), and a park- ing lot designed to accommodate 400 cars and 30 buses. The second and third stages will include a hotel, ice rink, pool, shops, two additional chair lifts, and other attractions. The board has decided that stage one should begin no later than April 1 and be completed by October 1, in time for the next skiing season. You have been assigned the task of project manager, and it is your job to coordinate the ordering of materials and construction activities to ensure the project’s completion by the required date. After looking into the possible sources of materials, you are confronted with the following time estimates. Materials for the chair lift and rope tow will take 30 days and 12 days, respectively, to arrive once the order is submitted. Lumber for the day lodge, generator hut, and foundations will take 9 days to arrive. The electrical and plumbing materials for the day lodge will take 12 days to arrive. The generator will take 12 days to arrive. Before actual construction can begin on the various facilities, a road to the site must be built; this will take 6 days. As soon as the road is in, clearing can begin concurrently on the sites of the day lodge, generator house, chair lift, and rope tow. It is estimated that the clearing task at each site will take 6 days, 3 days, 36 days, and 6 days, respectively. The clearing of the main ski slopes can begin after the area for the chair lift has been cleared; this will take 84 days. The foundation for the day lodge will take 12 days to complete. Construction of the main framework will take an additional 18 days. After the framework is completed, electrical wiring and plumbing can be installed concurrently. These should take 24 and 30 days, respectively. Finally, the finishing construction on the day lodge can begin; this will take 36 days. Installation of the chair lift towers (67 days) can begin once the site is cleared, lum- ber delivered, and the foundation completed (6 days). Also, when the chair lift site has been cleared, construction of a permanent road to the upper towers can be started; this will take 24 days. While the towers are being installed, the electric motor to drive the chair lift can be installed; the motor can be installed in 24 days. Once the towers are completed and the motor installed, it will take 3 days to install the cable and an addi- tional 12 days to install the chairs. Installation of the towers for the rope tow can begin once the site is cleared and the foundation is built and poured; it takes 4 days to build the foundation, pour the con- crete and let it cure, and 20 days to install the towers for the rope tow. While the towers are being erected, installation of the electric motor to drive the rope tow can begin; this activity will take 24 days. After the towers and motor are installed, the rope tow can be strung in 1 day. The parking lot can be cleared once the rope tow is finished; this task will take 18 days.

198 Chapter 6 Developing a Project Plan

The foundation for the generator house can begin at the same time as the foun- dation for the lodge; this will take 6 days. The main framework for the generator house can begin once the foundation is completed; framing will take 12 days. After the house is framed, the diesel generator can be installed in 18 days. Finish- ing construction on the generator house can now begin and will take 12 more days. Assignment: 1. Identify the critical path on your network. 2. Can the project be completed by October 1?

Optical Disk Preinstallation Project 18. The optical disk project team has started gathering the information necessary to

develop the project network—predecessor activities and activity times in weeks. The results of their meeting are found in the following table.

Activity Description Duration Predecessor

   1 Define scope   6 None                     2 Define customer problems  3 1                            3 Define data records and relationships  5 1                            4 Mass storage requirements  5 2, 3                        5 Consultant needs analysis 10 2, 3                        6 Prepare installation network  3 4, 5                        7 Estimate costs and budget  2 4, 5                        8 Design section “point” system  1 4, 5                        9 Write request proposal  5 4, 5                      10 Compile vendor list  3 4, 5                      11 Prepare mgmt. control system  5 6, 7                      12 Prepare comparison report  5  9, 10                     13 Compare system “philosophies”  3 8, 12                    14 Compare total installation  2 8, 12                    15 Compare cost of support  3 8, 12                    16 Compare customer satisfaction level 10 8, 12                    17 Assign philosophies points  1 13                        18 Assign installation cost  1 14                        19 Assign support cost  1 15                        20 Assign customer satisfaction points  1 16                        21 Select best system  1 11, 17, 18, 19, 20 22 Order system  1 21                      

The project team has requested that you create a network for the project, and deter- mine if the project can be completed in 45 weeks.

Lag Exercises 19. From the following information, compute the early, late, and slack times for each

activity. Identify the critical path.

Chapter 6 Developing a Project Plan 199

20. Given the following information, compute the early, late, and slack times for the project network. Which activities on the critical path have only the start or finish of the activity on the critical path?

Lag 4

Lag 2

Lag 2

Legend

ES

LS

SL

EF

LF

SL

Lag 3

A

5

ID

Duration

Design

Description

C

6

Code Software

E

3

Debug

D

3

Assemble

B

1

Order Parts

F

1

Install

Legend

ES

LS

SL

EF

LF

SL

ID

Duration

A

Post Signs

Description

Lag 3

Lag 10 1

B

Prepare Site

Open Lot

3

D

Dig Trenches

5

E

Lay Pipe

5

F

Black Fill

3

G

Pave

2

C

Lights

1

H

Paint Parkin Lines

1

I

Signage

1

J

1

Lag 1

Lag 3

200 Chapter 6 Developing a Project Plan

Legend

Lag 10

Lag 3

Lag 4

Lag 5

Lag 3

A

15

Interview

B

5

Def. New Features

C

2

Order Comps

D

8

Prototype

E

5

Test

F

10

Field Test

ES

LS

SL

EF

LF

SL

ID

Duration

Description

Legend

Lag 2

Lag 5

Lag 1

Lag 5 A

3

Design B

3

Tear Down

C

1

Order Appliances

D

7

Build Cabinets

E

2

Install Cabinets

G

1

Inspect

F

2

Install Appliances

ES

LS

SL

EF

LF

SL

ID

Duration

Description

21. * Given the information in the following lag exercises, compute the early, late, and slack times for the project network. Which activities on the critical path have only the start or finish of the activity on the critical path?

* The solution to this exercise can be found in Appendix One.

22. Given the network below, compute the early, late, and slack time for each activity. Clearly identify the critical path.

Chapter 6 Developing a Project Plan 201

CyClon Project 23. The CyClon project team has started gathering information necessary to develop a

project network—predecessor activities and activity time in days. The results of their meeting are found in the following table:

Activity Description Duration Predecessor

 1 CyClon Project  2 Design      10  3 Procure prototype parts      10            2  4 Fabricate parts       8            2  5 Assemble prototype       4            3, 4  6 Laboratory test       7            5  7 Field test      10            6  8 Adjust design       6            7  9 Order stock components      10            8 10 Order custom components      15            8 11 Assemble test production unit      10            9, 10 12 Test unit        5            11 13 Document results        3            12

Part A. Create a network based on the above information. How long will the project take? What is the critical path? Part B. Upon further review the team recognizes that they missed three finish-to-start lags. Procure prototype parts will involve only 2 days of work but it will take 8 days for the parts to be delivered. Likewise, Order stock components will take 2 days of work and 8 days for delivery and Order custom components 2 days of work and 13 days for delivery. Reconfigure the CyClon schedule by entering the three finish-to-start lags. What impact did these lags have on the original schedule? On the amount of work required to complete the project? Part C. Management is still not happy with the schedule and wants the project com- pleted as soon as possible. Unfortunately, they are not willing to approve additional resources. One team member pointed out that the network contained only finish-to- start relationships and that it might be possible to reduce project duration by creating start-to-start lags. After much deliberation the team concluded that the following rela- tionships could be converted into start-to-start lags:

∙ Procure prototype parts could start 6 days after the start of Design. ∙ Fabricate parts could start 9 days after the start of Design. ∙ Laboratory test could begin 1 day after the start of Assemble prototype. ∙ Field test could start 5 days after the start of Laboratory test. ∙ Adjust design could begin 7 days after the start of Field test. ∙ Order stock and Order custom components could begin 5 days after Adjust design. ∙ Test unit could begin 9 days after the start of Assemble test production unit. ∙ Document results could start 3 days after the start of Test unit.

Reconfigure the CyClon schedule by entering all nine start-to-start lags. What impact did these lags have on the original schedule (Part A)? How long will the project take? Is there a change in the critical path? Is there a change in the sensitivity of the network? Why would management like this solution?

Case 6.1

Advantage Energy Technology Data Center Migration*—Part A Brian Smith, network administrator at Advanced Energy Technology (AET), has been given the responsibility of implementing the migration of a large data center to a new office location. Careful planning is needed because AET operates in the highly com- petitive petroleum industry. AET is one of five national software companies that provide an accounting and business management package for oil jobbers and gasoline distributors. A few years ago, AET jumped into the “application service provider” world. Their large data center provides clients with remote access to AET’s complete suite of application software systems. Traditionally, one of AET’s primary competi- tive advantages has been the company’s trademark IT reliability. Due to the complex- ity of this project, Brian will have to use a parallel method of implementation. Although this will increase project costs, a parallel approach is essential if reliability is not to be compromised. Currently, AET’s data center is located on the second floor of a renovated old bank building in downtown Corvallis, Oregon. The company is moving to a new, one-level building located in the recently developed industrial complex at the Corvallis Interna- tional Airport. On February 1, Brian is formally assigned the task by the Vice Presi- dent of Operations, Dan Whitmore, with the following guidelines: ∙ From start to finish, it is anticipated the entire project will take three to four months

to complete. ∙ It is essential that AET’s 235 clients suffer no downtime. Whitmore advises Brian to come back to the Executive Committee on February 15, with a presentation on the scope of the project that includes costs, “first-cut” timeline, and proposed project team members. Brian had some preliminary discussions with some of AET’s managers and direc- tors from each of the functional departments and then arranged for a full-day scope

202 Chapter 6 Developing a Project Plan

References Gantt, H. L., Work, Wages and Profit, published by The Engineering Magazine, New York, 1910; republished as Work, Wages and Profits (Easton, PA: Hive Publishing Company, 1974). Kelly, J. E., “Critical Path Planning and Scheduling: Mathematical Basis,” Operations Research, vol. 9, no. 3 (May–June 1961), pp. 296–321. Levy, F. K., G. L. Thompson, and J. D. West, “The ABCs of the Critical Path Method,” Harvard Business Review, vol. 41, no. 5 (1963), pp. 98–108. Rosenblatt, A., and G. Watson, “Concurrent Engineering,” IEEE Spectrum, July 1991, pp. 22–37. Turtle, Q. C., Implementing Concurrent Project Management (Englewood Cliffs, NJ: Prentice Hall, 1994).

* Prepared by James Moran, a project management instructor at the College of Business, Oregon State University

Chapter 6 Developing a Project Plan 203

meeting on February 4 with a few of the managers and technical representatives from operations, systems, facilities, and applications. The scope team determined the following: ∙ Three to four months is a feasible project timeline and first-cut cost estimate is

$80,000–$90,000 (this includes the infrastructure upgrade of the new site). ∙ Critical to the “no-downtime” requirement is the need to completely rely on AET’s

remote disaster recovery “hot” site for full functionality. ∙ Brian will serve as project manager of a team consisting of one team member each

from facilities, operations/systems, operations/telecommunications, systems & applications, and customer service.

Brian’s Executive Committee report was positively received and, after a few modifica- tions and recommendations, he was formally charged with responsibility for the proj- ect. Brian recruited his team and scheduled their first team meeting (March 1) as the initial task of his project planning process. Once the initial meeting is conducted Brian can hire the contractors to renovate the new data center. During this time Brian will figure out how to design the net- work. Brian estimates that screening and hiring a contractor will take about one week and that the network design will take about two weeks. The new center requires a new ventilation system. The manufacturer’s requirements include an ambient tem- perature of 67 degrees to keep all of the data servers running at optimal speeds. The ventilation system has a lead time of three weeks. Brian will also need to order new racks to hold the servers, switches, and other network devices. The racks have a two- week delivery time. The data center supervisor requested that Brian replace all of the old power sup- plies and data cables. Brian will need to order these as well. Because Brian has a great relationship with the vendor, they guarantee that it will take only one week lead time for the power supplies and the data cables. Once the new ventilation system and racks arrive, Brian can begin installing them. It will take one week to install the ventilation system and three weeks to install the racks. The renovation of the new data center can begin as soon as the contractors have been hired. The contractors tell Brian that con- struction will take 20 days. Once the construction begins and after Brian installs the ventilation system and racks, the city inspector must approve the construction of the raised floor. The city inspector will take two days to approve the infrastructure. After the city inspection and after the new power supplies and cables have arrived, Brian can install the power supplies and run the cables. Brian estimates that it will take five days to install the power supplies and one week to run all of the data cables. Before Brian can assign an actual date for taking the network off line and switching to the hot remote site, he must get approval from each of the functional units (“Switchover Approval”). Meetings with each of the functional units will require one week. During this time he can initiate a power check to ensure that each of the racks has sufficient voltage. This will require only one day. Upon completion of the power check, he can take one week to install his test servers. The test servers will test all of the primary network functions and act as a safeguard before the network is taken off line. The batteries must be charged, ventilation installed, and test servers up and running before management can be assured that the new infra- structure is safe, which will take two days. Then they will sign off the Primary Systems check, taking one day of intense meetings. They will also set an official date for the network move.

204 Chapter 6 Developing a Project Plan

Brian is happy that everything has gone well thus far and is convinced that the move will go just as smoothly. Now that an official date is set, the network will be shut down for a day. Brian must move all of the network components to the new data center. Brian will do the move over the weekend—two days—when user traffic is at low point.

ASSIGNMENT

1. Generate a priority matrix for AET’s system move. 2. Develop a WBS for Brian’s project. Include duration (days) and predecessors. 3. Using a project planning tool, generate a network diagram for this project. Note: Base your plan on the following guidelines: eight-hour days, five-day weeks

except for when Brian moves the network components over a weekend, no holiday breaks, March 1, 2010, is the project start date. Ordering Ventilation System, New Racks, and Power Supplies/Cables takes only one actual day of work. The remain- ing days are the time necessary for the vendors to fill and ship the order to Brian. So use Finish to Start lags here. Assume that five days after the start of the Renova- tion of the Data Center that the raised floor will be ready for inspection (a Start-to- Start lag).

Case 6.2

Shoreline Stadium Case The G&E Company is preparing a bid to build the new 47,000-seat Shoreline baseball stadium. The construction must start on July 3, 2017, and be completed in time for the start of the 2020 season. A penalty clause of $250,000 per day of delay beyond April 3 is written into the contract. Percival Young, the president of the company, expressed optimism at obtaining the contract and revealed that the company could net as much as $3 million on the project. He also said if they were successful, the prospects of future projects are bright since there is a projected renaissance in building classic ball parks with modern luxury boxes.

ASSIGNMENT Given the information provided in Table 6.3, construct a network schedule for the sta- dium project and answer the following questions: 1. Will the project be able to be completed by the April 3 deadline? How long will it take? 2. What is the critical path for the project? 3. Based on the schedule would you recommend that G&E pursue this contact? Why?

Include a one-page Gantt chart for the stadium schedule.

Chapter 6 Developing a Project Plan 205

TABLE 6.3 Shoreline Stadium Case

ID Activity Duration Predecessor(s)

  1 Baseball Stadium   2 Clear stadium site 70 days           —   3 Demolish building 30 days           2   4 Set up construction site 70 days           3   5 Drive support piling 120 days           4   6 Pour lower concrete bowl 120 days           5   7 Pour main concourse 120 days           6   8 Install playing field 90 days           6   9 Construct upper steel bowl 120 days           6 10 Install seats 140 days           9 11 Build luxury boxes 90 days           9 12 Install jumbotron 30 days           9 13 Stadium infrastructure 120 days           9 14 Construct steel canopy 75 days          10 15 Light installation 30 days          10 16 Build roof supports 90 days           4 17 Construct roof 180 days          16 18 Install roof tracks 90 days          14 19 Install roof 90 days      17, 18 20 Inspection 20 days 8, 11, 13, 15, 19

Case Appendix

Technical Details For The Shoreline Baseball Stadium For purposes of this case assume the following: 1. The following holidays are observed: January 1, Martin Luther King Day (third

Monday in January), Memorial Day (last Monday in May), July 4th, Labor Day (first Monday in September), Thanksgiving Day (4th Thursday in November), December 25 and 26.

2. If a holiday falls on a Saturday then Friday will be given as an extra day off, and if it falls on a Sunday then Monday will be given as a day off.

3. The construction crew work Monday through Friday.

206

Managing Risk7 OUTLINE 7.!1 Risk Management Process

7.2 Step 1: Risk Identification

7.3 Step 2: Risk Assessment

7.4 Step 3: Risk Response Development

7.5 Contingency Planning

7.6 Opportunity Management

7.7 Contingency Funding and Time Buffers

7.8 Step 4: Risk Response Control

7.9 Change Control Management

Summary

Appendix 7.1: PERT and PERT Simulation

LEARNING OBJECTIVES After reading this chapter you should be able to:

7-1 Describe the risk management process.

7-2 Understand how to identify project risks.

7-3 Assess the significance of different project risks.

7-4 Describe the four different responses to man- aging risks.

7-5 Understand the role contingency plans play in risk management process.

7-6 Understand opportunity management and describe the four different approaches to responding to opportunities in a project.

7-7 Understand how contingency funds and time buffers are used to manage risks on a project.

7-8 Recognize the need for risk management being an ongoing activity.

7-9 Describe the change control process.

C H A P T E R S E V E N

207

You’ve got to go out on a limb sometimes because that’s where the fruit is. —Will Rogers

Every project manager understands risks are inherent in projects, deliveries are delayed, accidents happen, people get sick, etc. No amount of planning can overcome risk, or the inability to control chance events. In the context of projects, risk is an uncertain event or condition that, if it occurs, has a positive or negative effect on proj- ect objectives. A risk has a cause and, if it occurs, a consequence. For example, a cause may be a flu virus or change in scope requirements. The event is that team members get stricken with the flu or the product has to be redesigned. If either of these uncertain events occurs, it will impact the cost, schedule, and quality of the project. Some potential risk events can be identified before the project starts—such as equipment malfunction or change in technical requirements. Risks can be anticipated consequences, like schedule slippages or cost overruns. Risks can be beyond imagina- tion like the 2008 financial meltdown. While risks can have positive consequences such as unexpected price reduction in materials, the primary focus of this chapter is on what can go wrong and the risk man- agement process.

Project networks

6

Managing risk 7

Monitoring progress

13

Teams 11

Outsourcing 12

Project manager

10

Strategy 2

Introduction 1

Organization 3

Schedule resources & costs

8

Intern ation

al

proje cts

15

Agile PM 16

Project closure

14

Estimate 5

Reducing duration

9

Define project

4

208 Chapter 7 Managing Risk

Risk management attempts to recognize and manage potential and unforeseen trou- ble spots that may occur when the project is implemented. Risk management identifies as many risk events as possible (what can go wrong), minimizes their impact (what can be done about the event before the project begins), manages responses to those events that do materialize (contingency plans), and provides contingency funds to cover risk events that actually materialize. For a humorous, but ultimately embarrassing example of poor risk management see Snapshot from Practice 7.1: Giant Popsicle Gone Wrong.

7.1 Risk Management Process Figure 7.1 presents a graphic model of the risk management challenge. The chances of a risk event occurring (e.g., an error in time estimates, cost estimates, or design tech- nology) are greatest during the early stages of a project. This is when uncertainty is highest and many questions remain unanswered. As the project progresses toward completion, risk declines as the answers to critical issues (Will the technology work? Is the timeline feasible?) are resolved. The cost impact of a risk event, however, increases over the life of the project. For example, the risk event of a design flaw occurring after a prototype has been made has a greater cost or time impact than if the flaw were discovered during the planning phase of the project. The cost of mismanaged risk control early on in the project is exemplified by the ill-fated 1999 NASA Mars Climate Orbiter. Investigations revealed that Lockheed Martin botched the design of critical navigation software. While flight computers on the ground did calculations based on pounds of thrust per second, the spacecraft’s

7-1LO Describe the risk management process.

An attempt to erect the World’s Larg- est Popsicle in New York City ended with a scene straight out of a disaster film, but much stickier.

The 25-foot-tall, 17½-ton treat of frozen juice melted faster than expected, flooding Union Square in downtown Manhattan with kiwi- strawberry–flavored fluid. Bicyclists wiped out in the stream of goo. Pedestri- ans slipped. Traffic was, well, frozen. Firefighters closed off several streets and used hoses to wash away the thick, sweet slime. The Snapple Company, a leading maker of soft beverages, had been trying to promote a new line of frozen treats by setting a record for the World’s Larg- est Popsicle, but called off the stunt before the fro- zen giant was pulled fully upright by a construction crane. Authorities said they were worried the 2½-story popsicle would collapse.

S N A P S H O T F R O M P R A C T I C E 7 . 1 Giant Popsicle Gone Wrong*

© Brian Smith/Zuma Press, Inc.

Organizers were not sure why it melted so quickly. “We planned for it. We just didn’t expect for it to hap- pen so fast,” said Snapple spokeswoman Lauren Rad- cliffe. She said the company would offer to pay the city for the clean-up costs.

* Associated Press, June 23, 2005.

Chapter 7 Managing Risk 209

computer software used metric units called newtons. A check to see if the values were compatible was never done. “Our check and balances processes did not catch an error like this that should have been caught,” said Ed Weiler, NASA’s associate administrator for space science. “That is the bottom line” (Orlando Sentinel, 1999). If the error had been discovered early the cor- rection would have been relatively simple and inexpensive. Instead the error was never discovered, and after the nine-month journey to the Red Planet, the $125-million probe approached Mars at too low an altitude and burned up in the planet’s atmosphere. Following the 1999 debacle, NASA instituted a more robust risk management sys- tem which has produced a string of successful missions to Mars, including the dra- matic landing of the Curiosity rover in August 2012.1 Risk management is a proactive approach rather than reactive. It is a preventive process designed to ensure that surprises are reduced and that negative consequences associated with undesirable events are minimized. It also prepares the project manager to take action when a time, cost, and/or technical advantage is possible. Successful management of project risk gives the project manager better control over the future and can significantly improve chances of reaching project objectives on time, within budget, and meeting required technical (functional) performance. The sources of project risks are unlimited. There are external sources, such as infla- tion, market acceptance, exchange rates, and government regulations. In practice, these risk events are often referred to as “threats” to differentiate them from those that are not within the project manager’s or team’s responsibility area. (Later we will see bud- gets for such risk events are placed in a “management reserve” contingency budget.) Since such external risks are usually considered before the decision to go ahead with the project, they will be excluded from the discussion of project risks. However, exter- nal risks are extremely important and must be addressed. The major components of the risk management process are depicted in Figure 7.2. Each step will be examined in more detail in the remainder of the chapter.

FIGURE 7.1 Risk Event Graph Risk

High

Low

High

Low

Cost

Chances of risks occurring

Project Life Cycle

Executing DeliveringDefining Planning

Cost to fix risk event

1 E. Landau, “Mars Landing Went ‘Flawlessly,’ Scientists Say,” CNN.com, accessed August 14, 2012.

210 Chapter 7 Managing Risk

7.2 Step 1: Risk Identification The risk management process begins by trying to generate a list of all the possible risks that could affect the project. Typically the project manager pulls together, during the planning phase, a risk management team consisting of core team members and other relevant stakeholders. Research has demonstrated that groups make more accu- rate judgments about risks than individuals do (Snizek and Henry, 1989). The team uses brainstorming and other problem identifying techniques to identify potential problems. Participants are encouraged to keep an open mind and generate as many probable risks as possible. More than one project has been bushwhacked by an event that members thought was preposterous in the beginning. Later during the assessment phase, participants will have a chance to analyze and filter out unreasonable risks. One common mistake that is made early in the risk identification process is to focus on objectives and not on the events that could produce consequences. For example, team members may identify failing to meet schedule as a major risk. What they need to focus on are the events that could cause this to happen (i.e., poor estimates, adverse weather, shipping delays, etc.). Only by focusing on actual events can potential solutions be found. Organizations use risk breakdown structures (RBSs) in conjunction with work breakdown structures (WBSs) to help management teams identify and eventually ana- lyze risks. Figure 7.3 provides a generic example of a RBS. The focus at the beginning should be on risks that can affect the whole project as opposed to a specific section of the project or network. For example, the discussion of funding may lead the team to identify the possibility of the project budget being cut after the project has started as a

FIGURE 7.2 The Risk Management Process

New risks

New risks

New risks

Assess risks in terms of: Severity of impact Likelihood of occurring Controllability

Develop a strategy to reduce possible damage

Develop contingency plans

Implement risk strategy Monitor and adjust plan for

new risks Change management

Analyze the project to identify sources of risk

Step 1 Risk Identification

Step 2 Risk Assessment

Known risks

Risk assessment

Risk management plan

Step 3 Risk Response Development

Step 4 Risk Response Control

7-2LO Understand how to identify project risks.

Chapter 7 Managing Risk 211

FIGURE 7.3 The Risk Breakdown Structure (RBS)

Project

Organizational

Project dependencies

Resources

Funding

Prioritization

External

Subcontractors and suppliers

Regulatory

Market

Customer

Weather

Technical

Requirements

Technology

Complexity and interfaces

Performances and reliability

Quality

Project Management

Estimating

Planning

Controlling

Communication

significant risk event. Likewise, when discussing the market the team may identify responding to new product releases by competitors as a risk event. After the macro risks have been identified, specific areas can be checked. An effec- tive tool for identifying specific risks is the work breakdown structure. Use of the RBS reduces the chance a risk event will be missed. On large projects multiple risk teams are organized around specific deliverables and submit their risk management reports to the project manager. A risk profile is another useful tool. A risk profile is a list of questions that address tra- ditional areas of uncertainty on a project. These questions have been developed and refined from previous, similar projects. Figure 7.4 provides a partial example of a risk profile. Good risk profiles, like RBSs, are tailored to the type of project in question. For exam- ple, building an information system is different from building a new car. They are organi- zation specific. Risk profiles recognize the unique strengths and weaknesses of the firm. Finally, risk profiles address both technical and management risks. For example, the pro- file shown in Figure 7.4 asks questions about design such as, Does the design depend upon unrealistic assumptions? The questions may lead the team to identify that the tech- nology will not work under extreme conditions as a risk. Similarly, questions about work environment (Do people cooperate across functional boundaries?) may lead to the identi- fication of potential communication breakdowns between marketing and R&D as a risk. Risk profiles are generated and maintained usually by personnel from the project office. They are updated and refined during the postproject audit (see Chapter 14). These profiles, when kept up to date, can be a powerful resource in the risk management process. The collective experience of the firm’s past projects resides in their questions. Historical records can complement or be used when formal risk profiles are not available. Project teams can investigate what happened on similar projects in the past to

212 Chapter 7 Managing Risk

identify potential risks. For example, a project manager can check the on-time perfor- mance of selected vendors to gauge the threat of shipping delays. IT project managers can access “best practices” papers detailing other companies’ experiences converting software systems. Inquiries should not be limited to recorded data. Savvy project man- agers tap the wisdom of others by seeking the advice of veteran project managers. The risk identification process should not be limited to just the core team. Input from customers, sponsors, subcontractors, vendors, and other stakeholders should be solicited. Relevant stakeholders can be formally interviewed or included on the risk management team. Not only do these players have a valuable perspective, but by involving them in the risk management process they also become more committed to project success.2 One of the keys to success in risk identification is attitude. While a “can do” atti- tude is essential during implementation, project managers have to encourage critical thinking when it comes to risk identification. The goal is to find potential problems before they happen. The RBS and risk profiles are useful tools for making sure no stones are left unturned. At the same time, when done well the number of risks identified can be overwhelming and a bit discouraging. Initial optimism can be replaced with griping and cries of “what have we gotten ourselves into?” It is important that project manag- ers set the right tone and complete the risk management process so members regain confidence in themselves and the project.

7.3 Step 2: Risk Assessment Step 1 produces a list of potential risks. Not all of these risks deserve attention. Some are trivial and can be ignored, while others pose serious threats to the welfare of the project. Managers have to develop methods for sifting through the list of risks, elimi- nating inconsequential or redundant ones and stratifying worthy ones in terms of importance and need for attention.

7-3LO Assess the significance of different project risks.

FIGURE 7.4 Partial Risk Profile for Product Development Project

Technical Requirements

Are the requirements stable?

Design

Does the design depend on unrealistic or optimistic assumptions?

Testing

Will testing equipment be available when needed?

Development

Is the development process supported by a com- patible set of procedures, methods, and tools?

Schedule

Is the schedule dependent upon the completion of other projects?

Budget

How reliable are the cost estimates?

Quality

Are quality considerations built into the design?

Management

Do people know who has authority for what?

Work Environment

Do people work cooperatively across functional boundaries?

Staffing

Is staff inexperienced or understaffed?

Customer

Does the customer understand what it will take to complete the project?

Contractors

Are there any ambiguities in contractor task definitions?

2 The Delphi Method (see Snapshot from Practice 5.3) is a popular technique for involving stakeholders.

Chapter 7 Managing Risk 213

Scenario analysis is the easiest and most commonly used technique for analyzing risks. Team members assess the significance of each risk event in terms of: ∙ Probability of the event. ∙ Impact of the event. Simply stated, risks need to be evaluated in terms of the likelihood the event is going to occur and the impact or consequences of its occurrence. The risk of a project manager being struck by lightning at a work site would have major negative impact on the project, but the likelihood is so low it is not worthy of consideration. Conversely, people do change jobs, so an event like the loss of key project personnel would have not only an adverse impact but also a high likelihood of occurring in some organiza- tions. If so, then it would be wise for that organization to be proactive and mitigate this risk by developing incentive schemes for retaining specialists and/or engaging in cross-training to reduce the impact of turnover. The quality and credibility of the risk analysis process require that different lev- els of risk probabilities and impacts be defined. These definitions vary and should be tailored to the specific nature and needs of the project. For example, a relatively simple scale ranging from “very unlikely” to “almost certainly” may suffice for one project, whereas another project may use more precise numerical probabilities (e.g., 0.1, 0.3, 0.5, . . .). Impact scales can be a bit more problematic since adverse risks affect project objec- tives differently. For example, a component failure may cause only a slight delay in project schedule but a major increase in project cost. If controlling cost is a high prior- ity, then the impact would be severe. If, on the other hand, time is more critical than cost, then the impact would be minor. Because impact ultimately needs to be assessed in terms of project priorities, differ- ent kinds of impact scales are used. Some scales may simply use rank-order descrip- tors, such as “low,” “moderate,” “high,” and “very high,” whereas others use numeric weights (e.g., 1–10). Some may focus on the project in general while others focus on specific project objectives. The risk management team needs to establish up front what distinguishes a 1 from a 3 or “moderate” impact from “severe” impact. Figure 7.5 pro- vides an example of how impact scales could be defined given the project objectives of cost, time, scope, and quality. Documentation of scenario analyses can be seen in various risk assessment forms used by companies. Figure 7.6 is a partial example of a risk assessment form used on an IS project involving the upgrade from Windows 10 to Windows 11. Notice that in addition to evaluating the severity and probability of risk events the team also assesses when the event might occur and its detection difficulty. Detection difficulty is a measure of how easy it would be to detect that the event was going to occur in time to take mitigating action, that is, how much warning would we have? So in the Windows 11 conversion example, the detection scale would range from 5 = no warning to 1 = lots of time to react. Often organizations find it useful to categorize the severity of different risks into some form of risk assessment matrix. The matrix is typically structured around the impact and likelihood of the risk event. For example, the risk matrix presented in Fig- ure 7.7 consists of a 5 × 5 array of elements with each element representing a different set of impact and likelihood values. The matrix is divided into red, yellow, and green zones representing major, moder- ate, and minor risks, respectively. The red zone is centered on the top right corner of the matrix (high impact/high likelihood), while the green zone is centered on the

214 Chapter 7 Managing Risk

bottom left corner (low impact/low likelihood). The moderate risk, yellow zone extends down the middle of the matrix. Since impact is generally considered more important than likelihood (a 10 percent chance of losing $1,000,000 is usually consid- ered a more severe risk than a 90 percent chance of losing $1,000), the red zone (major risk) extends farther down the high impact column. Using the Windows 11 project again as an example, interface problems and system freezing would be placed in the red zone (major risk), while user backlash and hard- ware malfunctioning would be placed in the yellow zone (moderate risk). The risk severity matrix provides a basis for prioritizing which risks to address. Red zone risks receive first priority followed by yellow zone risks. Green zone risks are typically considered inconsequential and ignored unless their status changes.

FIGURE 7.6 Risk Assessment Form Interface problems

System freezing

User backlash

Hardware malfunctioning

4

LikelihoodRisk Event Impact Detection Difficulty When

2

4

1

4

5

3

5

4

5

3

5

Conversion

Start-up

Postinstallation

Installation

Project Objective

Cost

Time

Scope

Quality

Relative or Numerical Scale

Insignificant cost increase

Insignificant time increase

Scope decrease barely noticeable

Quality degradation barely noticeable

1 Very Low

2 Low

< 10% cost increase

< 5% time increase

Minor areas of scope affected

Only very demanding applications are

affected

10–20% cost increase

5–10% time increase

Major areas of scope affected

Quality reduction requires sponsor

approval

20–40% cost increase

10–20% time increase

Scope reduction unacceptable to

sponsor

Quality reduction unacceptable

to sponsor

> 40% cost increase

> 20% time increase

Project end item is effectively

useless

Project end item is effectively

useless

3 Moderate

4 High

5 Very High

FIGURE 7.5 Defined Conditions for Impact Scales of a Risk on Major Project Objectives (examples for negative impacts only)

Chapter 7 Managing Risk 215

Failure Mode and Effects Analysis (FMEA) extends the risk severity matrix by including ease of detection in the equation:

Impact × Probability × Detection = Risk Value Each of the three dimensions is rated according to a five-point scale. For example, detection is defined as the ability of the project team to discern that the risk event is imminent. A score of 1 would be given if even a chimpanzee could spot the risk com- ing. The highest detection score of 5 would be given to events that could only be dis- covered after it is too late (i.e., system freezing). Similar anchored scales would be applied for severity of impact and the probability of the event occurring. The weight- ing of the risks is then based on their overall score. For example, a risk with an impact in the “1” zone with a very low probability and an easy detection score might score a 1 (1 × 1 × 1 = 1). Conversely, a high-impact risk with a high probability and impos- sible to detect would score 125 (5 × 5 × 5 = 125). This broad range of numerical scores allows for easy stratification of risk according to overall significance. No assessment scheme is absolutely foolproof. For example, the weakness of the FMEA approach is that a risk event rated Impact = 1, Probability = 5, and Detection = 5 would receive the same weighted score as an event rated Impact = 5, Probability = 5, and Detection = 1! This underscores the importance of not treating risk assessment as simply an exercise in mathematics. There is no substitute for thoughtful discussion of key risk events.

Probability Analysis There are many statistical techniques available to the project manager that can assist in assessing project risk. Decision trees have been used to assess alternative courses of action using expected values. Statistical variations of net present value (NPV) have been used to assess cash flow risks in projects. Correlations between past projects’ cash flow and S-curves (cumulative project cost curve—baseline—over the life of the project) have been used to assess cash flow risks.

FIGURE 7.7 Risk Severity Matrix

User backlash

Interface problems

System freezing

Hardware malfunc- tioning

5

5

4

4

3

3 Impact

2

2

1

1

Li ke

lih oo

d

Red zone (major risk)

Yellow zone (moderate risk)

Green zone (minor risk)

216 Chapter 7 Managing Risk

PERT (program evaluation and review technique) and PERT simulation can be used to review activity and project risk. PERT and related techniques take a more macro perspective by looking at overall cost and schedule risks. Here the focus is not on indi- vidual events but on the likelihood the project will be completed on time and within budget. These methods are useful in assessing the overall risk of the project and the need for such things as contingency funds, resources, and time. The use of PERT simulation is increasing because it uses the same data required for PERT, and software to perform the simulation is readily available. Basically PERT simulation assumes a statistical distribution (range between optimis- tic and pessimistic) for each activity duration; it then simulates the network (perhaps over 1,000 simulations) using a random number generator. The outcome is the relative probability, called a criticality index, of an activity becoming critical under the many different, possible activity durations for each activity. PERT simulation also provides a list of potential critical paths and their respective probabilities of occurring. Having this information available can greatly facilitate identifying and assessing schedule risk. (See Appendix 7.1 at the end of this chapter for a more detailed description and discussion.)

7.4 Step 3: Risk Response Development When a risk event is identified and assessed, a decision must be made concerning which response is appropriate for the specific event. Responses to risk can be classi- fied as mitigating, avoiding, transferring, or retaining.

Mitigating Risk Reducing risk is usually the first alternative considered. There are basically two strat- egies for mitigating risk: (1) reduce the likelihood that the event will occur and/or (2) reduce the impact that the adverse event would have on the project. Most risk teams focus first on reducing the likelihood of risk events since, if successful, this may eliminate the need to consider the potentially costly second strategy. Testing and prototyping are frequently used to prevent problems from surfacing later in a project. An example of testing can be found in an information systems proj- ect. The project team was responsible for installing a new operating system in their parent company. Before implementing the project, the team tested the new system on a smaller isolated network. By doing so they discovered a variety of problems and were able to come up with solutions prior to implementation. The team still encountered problems with the installation but the number and severity were greatly reduced. Often identifying the root causes of an event is useful. For example, the fear that a vendor will be unable to supply customized components on time may be attributable to (1) poor vendor relationships, (2) design miscommunication, and (3) lack of motiva- tion. As a result of this analysis the project manager may decide to take his counterpart to lunch to clear the air, invite the vendor to attend design meetings, and restructure the contract to include incentives for on-time delivery. Other examples of reducing the probability of risks occurring are scheduling out- door work during the summer months, investing in up-front safety training, and choos- ing high-quality materials and equipment. When the concerns are that duration and costs have been underestimated, managers will augment estimates to compensate for the uncertainties. It is common to use a ratio between old and new project to adjust time or cost. The ratio typically serves as a con- stant. For example, if past projects have taken 10 minutes per line of computer code, a

7-4 Describe the four different responses to managing risks.

LO

Chapter 7 Managing Risk 217

constant of 1.10 (which represents a 10 percent increase) would be used for the proposed project time estimates because the new project is more difficult than prior projects. An alternative mitigation strategy is to reduce the impact of the risk if it occurs. For example, a bridge-building project illustrates risk reduction. A new bridge project for a coastal port was to use an innovative, continuous cement-pouring process developed by an Australian firm to save large sums of money and time. The major risk was that the continuous pouring process for each major section of the bridge could not be inter- rupted. Any interruption would require that the whole cement section (hundreds of cubic yards) be torn down and started over. An assessment of possible risks centered on delivery of the cement from the cement factory. Trucks could be delayed, or the fac- tory could break down. Such risks would result in tremendous rework costs and delays. Risk was reduced by having two additional portable cement plants built nearby on dif- ferent highways within 20 miles of the bridge project in case the main factory supply was interrupted. These two portable plants carried raw materials for a whole bridge section, and extra trucks were on immediate standby each time continuous pouring was required. Similar risk reduction scenarios are apparent in system and software develop- ment projects where parallel innovation processes are used in case one fails. Snapshot from Practice 7.2: From Dome to Dust details the steps Controlled Demo- lition took to minimize damage when they imploded the Seattle Kingdome.

Avoiding Risk Risk avoidance is changing the project plan to eliminate the risk or condition. Although it is impossible to eliminate all risk events, some specific risks may be avoided before you launch the project. For example, adopting proven technology instead of experimental technology can eliminate technical failure. Choosing an Australian supplier as opposed to an Indonesian supplier would virtually eliminate the chance that political unrest would disrupt the supply of critical materials. Likewise, one could eliminate the risk of choos- ing the wrong software by developing web applications using both ASAP.NET and PHP. Choosing to move a concert indoors would eliminate the threat of inclement weather.

Transferring Risk Passing risk to another party is common; this transfer does not change risk. Passing risk to another party almost always results in paying a premium for this exemption. Fixed- price contracts are the classic example of transferring risk from an owner to a contractor. The contractor understands his or her firm will pay for any risk event that materializes; therefore, a monetary risk factor is added to the contract bid price. Before deciding to transfer risk, the owner should decide which party can best control activities that would lead to the risk occurring. Also, is the contractor capable of absorbing the risk? Clearly identifying and documenting responsibility for absorbing risk is imperative. Another more obvious way to transfer risk is insurance. However, in most cases this is impractical because defining the project risk event and conditions to an insurance broker who is unfamiliar with the project is difficult and usually expensive. Of course, low-probability and high-consequence risk events such as acts of God are more easily defined and insured. Performance bonds, warranties, and guarantees are other finan- cial instruments used to transfer risk. On large, international construction projects like petrochemical plants and oil refineries, host countries are insisting on contracts that enforce Build-Own-Operate- Transfer (BOOT) provisions. Here the prime project organization is expected not only to build the facility, but also to take over ownership until its operation capacity has been proven and all the debugging has occurred before final transfer of ownership to

218 Chapter 7 Managing Risk

the client. In such cases, the host country has transferred financial risk of ownership until the project has been completed and capabilities proven.

Accept Risk In some cases a conscious decision is made to accept the risk of an event occurring. Some risks are so large it is not feasible to consider transferring or reducing the event (e.g., an earthquake or flood). The project owner assumes the risk because the chance of such an event occurring is slim. In other cases risks identified in the budget reserve can simply be absorbed if they materialize. The risk is retained by developing a contin- gency plan to implement if the risk materializes. In a few cases a risk event can be ignored and a cost overrun accepted should the risk event occur.

On March 26, 2000, the largest con- crete domed structure in the world was reduced to a pile of rubble in a dramatic implosion lasting less than 20 seconds. According to Mark Loizeaux, whose Maryland-based Controlled Demolition

Inc. was hired to bring the 24-year-old Seattle Kingdome down, “We don’t blow things up. We use explosives as an engine, but gravity is the catalyst that will bring it down.” Destroying the Kingdome was the most complicated of the 7,000 demolitions Loizeaux’s company has under- taken. Nearly three months of preparations were needed to implode the dome at a total cost of $9 million. The King- dome was considered to be one of the strongest struc- tures in the world containing over 25,000 tons of concrete with each of its 40 vaulted ribs incorporating seven lengths of two-and-one-quarter-inch reinforcing steel bar. Strands of orange detonating cord—basically dyna- mite in a string that explodes at the lightning pace of 24,000 feet per second—connected six pielike divi- sions of the Kingdome to a nearby control center. Throughout each section, Controlled Demolition workers drilled nearly 1,000 holes and packed them with high-velocity gelatin explosives the size of hot dogs. Large charges were placed about one-third of the way up each dome rib; smaller charges were put farther up the ribs. When the detonation button was pushed, blasting caps set off a chain reaction of explo- sions in each section reducing the stadium to rubble. While the actual implosion was a technical tour- de-force, risk management was a critical part of the project’s success. To minimize damage to surrounding buildings, the explosive charges were wrapped in a layer of chain-link fencing covered with thick sheets of geotextile polypropylene fabric to contain flying con- crete. Nearby buildings were protected in various man- ners depending on the structure and proximity to the

Dome. Measures included sealing air-handling units, taping seams on doors and windows, covering floors and windows with plywood and draping reinforced polyethylene sheeting around the outside. To help absorb the impact, air-conditioning units removed from the interior were stacked with other material to create a barrier around the perimeter of the work area. Hundreds of police officers and security personnel were used to cordon off an area extending roughly 1,000 feet from the Dome from overzealous spectators. Traffic was closed for a larger area. Accommodations were provided for people and pets who lived within the restricted zone. Eight water trucks, eight sweeper units, and more than 100 workers were deployed immediately after the blast to control dust and begin the cleanup. As a side note, one-third of the concrete will be crushed and used in the foundation of a new $430-million outdoor football stadium which is being built in its place. The rest of the concrete will be carted away and used in roadbeds and foundations throughout the Seattle area.

© Tim Matsui/Getty Images

S N A P S H O T F R O M P R A C T I C E 7 . 2 From Dome to Dust*

* New York Times—Sunday Magazine (March 19, 2000); Seattle Times (March 27, 2000) website.

Chapter 7 Managing Risk 219

The more effort given to risk response before the project begins, the better the chances are for minimizing project surprises. Knowing that the response to a risk event will be retained, transferred, or mitigated greatly reduces stress and uncertainty. Again, control is possible with this structured approach.

7.5 Contingency Planning A contingency plan is an alternative plan that will be used if a possible foreseen risk event becomes a reality. The contingency plan represents actions that will reduce or mitigate the negative impact of the risk event. A key distinction between a risk response and a contingency plan is that a response is part of the actual implementation plan and action is taken before the risk can materialize, while a contingency plan is not part of the initial implementation plan and only goes into effect after the risk is recognized. Like all plans, the contingency plan answers the questions of what, where, when, and how much action will take place. The absence of a contingency plan, when a risk event occurs, can cause a manager to delay or postpone the decision to implement a remedy. This postponement can lead to panic, and acceptance of the first remedy sug- gested. Such after-the-event decision making under pressure can be potentially danger- ous and costly. Contingency planning evaluates alternative remedies for possible foreseen events before the risk event occurs and selects the best plan among alterna- tives. This early contingency planning facilitates a smooth transition to the remedy or work-around plan. The availability of a contingency plan can significantly increase the chances for project success. Conditions for activating the implementation of the contingency plan should be decided and clearly documented. The plan should include a cost estimate and identify the source of funding. All parties affected should agree to the contingency plan and have authority to make commitments. Because implementation of a contingency plan embodies disruption in the sequence of work, all contingency plans should be com- municated to team members so that surprise and resistance are minimized. Here is an example: A high-tech niche computer company intends to introduce a new “platform” product at a very specific target date. The project’s 47 teams all agree delays will not be acceptable. Their contingency plans for two large component suppli- ers demonstrate how seriously risk management is viewed. One supplier’s plant sits on the San Andreas Fault, which is prone to earthquakes. The contingency plan has an alternative supplier, who is constantly updated, producing a replica of the component in another plant. Another key supplier in Toronto, Canada, presents a delivery risk on their due date because of potential bad weather. This contingency plan calls for a char- tered plane (already contracted to be on standby) if overland transportation presents a delay problem. To outsiders these plans must seem a bit extreme, but in high-tech industries where time to market is king, risks of identified events are taken seriously. Risk response matrices such as the one shown in Figure 7.8 are useful for summa- rizing how the project team plans to manage risks that have been identified. Again, the Windows 11 project is used to illustrate this kind of matrix. The first step is to identify whether to reduce, share, transfer, or accept the risk. The team decided to reduce the chances of the system freezing by experimenting with a prototype of the system. Pro- totype experimentation not only allows them to identify and fix conversion “bugs” before the actual installation, but it also yields information that could be useful in enhancing acceptance by end-users. The project team is then able to identify and docu- ment changes between the old and new system that will be incorporated in the training the users receive. The risk of equipment malfunctioning is transferred by choosing a reliable supplier with a strong warranty program.

Understand the role contingency plans play in risk management process.

7-5LO

220 Chapter 7 Managing Risk

FIGURE 7.8 Risk Response Matrix

Interface problems

System freezing

User backlash

Equipment malfunctions

Mitigate: Test prototype

ResponseRisk Event Contingency Plan Trigger Who Is Responsible

Mitigate: Test prototype

Mitigate: Prototype demonstration

Mitigate: Select reliable vendor Transfer: Warranty

Work around until help comes

Reinstall OS

Increase staff support

Order replacement

Not solved within 24 hours

Still frozen after one hour

Call from top management

Equipment fails

Nils

Emmylou

Eddie

Jim

The next step is to identify contingency plans in case the risk still occurs. For exam- ple, if interface problems prove insurmountable, then the team would attempt a work- around until vendor experts arrived to help solve the problem. If the system freezes after installation, the team will first try to reinstall the software. If user dissatisfaction is high, then the IS department will provide more staff support. If the team is unable to get reliable equipment from the original supplier, then it will order a different brand from a second dealer. The team also needs to discuss and agree what would “trigger” implementation of the contingency plan. In the case of the system freezing, the trigger is not being able to unfreeze the system within one hour or, in the case of user back- lash, an angry call from top management. Finally, the individual responsible for moni- toring the potential risk and initiating the contingency plan needs to be assigned. Smart project managers establish protocols for contingency responses before they are needed. For an example of the importance of establishing protocols see Snapshot from Practice 7.3: Risk Management at the Top of the World. Some of the most common methods for handling risk are discussed here.

Technical Risks Technical risks are problematic; they can often be the kind that cause the project to be shut down. What if the system or process does not work? Contingency or backup plans are made for those possibilities that are foreseen. For example, Carrier Transicold was involved in developing a new Phoenix refrigeration unit for truck-trailer applications. This new unit was to use rounded panels made of bonded metals, which at the time was new technology for Transicold. Furthermore, one of its competitors had tried unsuccessfully to incorporate similar bonded metals in their products. The project team was eager to make the new technology work, but it wasn’t until the very end of the project that they were able to get the new adhesives to bond adequately to complete the project. Throughout the project, the team maintained a welded-panel fabrication approach just in case they were unsuccessful. If this contingency approach had been needed, it would have increased production costs, but the project still would have been completed on time. In addition to backup strategies, project managers need to develop methods to quickly assess whether technical uncertainties can be resolved. The use of sophisti- cated CAD programs has greatly helped resolve design problems. At the same time, Smith and Reinertsen (1995), in their book Developing Products in Half the Time, argue that there is no substitute for making something and seeing how it works, feels, or looks. They suggest that one should first identify the high-risk technical areas, then

Chapter 7 Managing Risk 221

S N A P S H O T F R O M P R A C T I C E 7 . 3 Risk Management at the Top of the World*

The gripping account in the 2015 film Everest of an ill-fated attempt to climb Mount Everest in which six climbers died provides testimony to the risks of extreme mountain climbing. Accounts of Mount Everest expedi-

tions provide insights into project risk management. First, most climbers spend more than three weeks accli- mating their bodies to high-altitude conditions. Native Sherpas are used extensively to carry supplies and set up each of the four base camps that will be used during the final stages of the climb. To reduce the impact of hypoxia, lightheadness, and disorientation caused by shortage of oxygen, most climbers use oxygen masks and bottles during the final ascent. If lucky enough not to be one of the first expeditions of the season, the path to the summit should be staked out and roped by previ- ous climbers. Climbing guides receive last-minute weather reports by radio to confirm whether the weather conditions warrant the risk. Finally, for added insurance, most climbers join their Sherpas in an elabo- rate puja ritual intended to summon the divine support of the gods before beginning their ascent. All of these efforts pale next to the sheer physical and mental rigors of making the final climb from base camp IV to the summit. This is what climbers refer to as the “death zone” because beyond 26,000 feet the mind and body begin to quickly deteriorate despite supplemental oxy- gen. Under fair conditions it takes around 18 hours to make the round-trip to the top and back to the base camp. Climbers leave as early as 1:00 a.m. in order to make it back before night falls and total exhaustion sets in. The greatest danger in climbing Mount Everest is not in reaching the summit but in making it back to the base camp. One out of every five climbers who make it to the summit dies during their descent. The key is establishing a contingency plan in case the climbers encounter hard

© Bobby Model/National Geographic Stock/Getty Images

going or the weather changes. Guides establish a pre- determined turnaround time (i.e., 2:00 p.m.) to ensure a safe return no matter how close the climbers are to the summit. Many lives have been lost by failing to adhere to the turnaround time and pushing forward to the summit. As one climber put it, “With enough determi- nation, any bloody idiot can get to the top of the hill. The trick is to get back alive.” One climber who faced the 2:00 p.m. deadline was Goran Krupp. After cycling 8,000 miles from Stockholm to Katmandu he turned back 1,000 feet from the summit.

* Jon Krakauer, Into Thin Air (New York: Doubleday, 1997), p. 190; Broughton Coburn, Everest: Mountain without Mercy (New York: National Geographic Society, 1997).

build models or design experiments to resolve the risk as quickly as possible. Technol- ogy offers many methods for early testing and validation, ranging from 3-D printing and holographic imagery for model building to focus groups and early design usability testing for market testing (Thamhain, 2013). By isolating and testing the key technical questions early on in a project, project feasibility can be quickly determined and neces- sary adjustments made such as reworking the process or in some cases closing down the project.3

3 This is a key principle of Agile project management, which is discussed in Chapter 17.

222 Chapter 7 Managing Risk

Schedule Risks Often organizations will defer the threat of a project coming in late until it surfaces. Here contingency funds are set aside to expedite or “crash” the project to get it back on track. Crashing, or reducing project duration, is accomplished by shortening (com- pressing) one or more activities on the critical path. This comes with additional costs and risk. Techniques for managing this situation are discussed in Chapter 9. Some contingency plans can avoid costly procedures. For example, schedules can be altered by working activities in parallel or using start-to-start lag relationships. Also, using the best people for high-risk tasks can relieve or lessen the chance of some risk events occurring.

Cost Risks Projects of long duration need some contingency for price changes—which are usually upward. The important point to remember when reviewing price is to avoid the trap of using one lump sum to cover price risks. For example, if inflation has been running about 3 percent, some managers add 3 percent for all resources used in the project. This lump-sum approach does not address exactly where price protection is needed and fails to provide for tracking and control. On cost sensitive projects, price risks should be evaluated item by item. Some purchases and contracts will not change over the life of the project. Those that may change should be identified and estimates made of the magnitude of change. This approach ensures control of the contingency funds as the project is implemented.

Funding Risks What if the funding for the project is cut by 25 percent or completion projections indi- cate that costs will greatly exceed available funds? What are the chances of the project being canceled before completion? Seasoned project managers recognize that a com- plete risk assessment must include an evaluation of funding supply. This is especially true for publicly funded projects. Case in point was the ill-fated ARH-70 Arapaho helicopter which was being developed for the U.S. Army by BellAircraft. Over 300-million dollars had been invested to develop a new age combat and reconnais- sance helicopter, when in October 2008, the Defense Department recommended that the project be canceled. The cancellation reflected a need to cut costs and a switch toward using unmanned aircraft for surveillance as well as attack missions. Just as government projects are subject to changes in strategy and political agenda, business firms frequently undergo changes in priorities and top management. The pet projects of the new CEO replace the pet projects of the former CEO. Resources become tight and one way to fund new projects is to cancel other projects. Severe budget cuts or lack of adequate funding can have a devastating effect on a project. Typically, when such a fate occurs, there is a need to scale back the scope of the project to what is possible. “All-or-nothing projects” are ripe targets to budget cut- ters. This was the case of the Arapaho helicopter once the decision was made to move away from manned reconnaissance aircraft. Here the “chunkability” of the project can be an advantage. For example, freeway projects can fall short of the original intentions but still add value for each mile completed. On a much smaller scale, similar funding risks may exist for more mundane projects. For example, a building contractor may find that due to a sudden downturn in the stock market the owners can no longer afford to build their dream house. Or an IS consulting firm may be left empty handed when a client files for bankruptcy. In the former case the

Chapter 7 Managing Risk 223

contractor may have as a contingency selling the house on the open market, while unfortunately the consulting firm will have to join the long line of creditors.

7.6 Opportunity Management For the sake of brevity, this chapter has focused on negative risks—what can go wrong on a project. There is a flip side—what could go right on a project? This is commonly referred to as a positive risk or opportunity. An opportunity is an event that can have a positive impact on project objectives. For example, unusually favorable weather can accelerate construction work, or a drop in fuel prices may create savings that could be used to add value to a project. Essentially the same process that is used to manage nega- tive risks is applied to positive risks. Opportunities are identified, assessed in terms of likelihood and impact, responses are determined, and even contingency plans and funds can be established to take advantage of the opportunity if it occurs. The major exception between managing negative risks and opportunity is in the responses. The project man- agement profession has identified four different types of response to an opportunity:4

Exploit. This tactic seeks to eliminate the uncertainty associated with an opportu- nity to ensure that it definitely happens. Examples include assigning your best per- sonnel to a critical burst activity to reduce the time to completion or revising a design to enable a component to be purchased rather than developed internally.

Share. This strategy involves allocating some or all of the ownership of an oppor- tunity to another party who is best able to capture the opportunity for the benefit of the project. Examples include establishing continuous improvement incentives for external contractors or joint ventures.

Enhance. Enhance is the opposite of mitigation in that action is taken to increase the probability and/or the positive impact of an opportunity. Examples include choosing site location based on favorable weather patterns or choosing raw materi- als that are likely to decline in price.

Accept. Accepting an opportunity is being willing to take advantage of it if it occurs, but not taking action to pursue it.

While it is only natural to focus on negative risks, it is sound practice to engage in active opportunity management as well.

7.7 Contingency Funding and Time Buffers Contingency funds are established to cover project risks—identified and unknown. When, where, and how much money will be spent is not known until the risk event occurs. Proj- ect “owners” are often reluctant to set up project contingency funds that seem to imply the project plan might be a poor one. Some perceive the contingency fund as an add-on slush fund. Others say they will face the risk when it materializes. Usually such reluctance to establish contingency reserves can be overcome with documented risk identification, assessment, contingency plans, and plans for when and how funds will be disbursed. The size and amount of contingency reserves depend on uncertainty inherent in the project. Uncertainty is reflected in the “newness” of the project, inaccurate time and cost estimates, technical unknowns, unstable scope, and problems not anticipated. In practice, contingencies run from 1 to 10 percent in projects similar to past projects.

7-6LO Understand opportunity management and describe the four different approaches to responding to opportunities in a project.

7-7LO Understand how contingency funds and time buffers are used to manage risks on a project.

4 PMBOK, 5th ed. (Newton Square, PA: PMI, 2013), pp. 345-46.

224 Chapter 7 Managing Risk

However, in unique and high-technology projects it is not uncommon to find contin- gencies running in the 20 to 60 percent range. Use and rate of consumption of reserves must be closely monitored and controlled. Simply picking a percentage of the baseline, say, 5 percent, and calling it the contingency reserve is not a sound approach. Also, adding up all the identified contingency allotments and throwing them into one pot is not conducive to sound control of the reserve fund. In practice, the contingency reserve fund is typically divided into budget and man- agement reserve funds for control purposes. Budget reserves are set up to cover iden- tified risks; these reserves are those allocated to specific segments or deliverables of the project. Management reserves are set up to cover unidentified risks and are allo- cated to risks associated with the total project. The risks are separated because their use requires approval from different levels of project authority. Because all risks are probabilistic, the reserves are not included in the baseline for each work package or activity; they are only activated when a risk occurs. If an identified risk does not occur and its chance of occurring is past, the fund allocated to the risk should be deducted from the budget reserve. (This removes the temptation to use budget reserves for other issues or problems.) Of course if the risk does occur, funds are removed from the reserve and added to the cost baseline. It is important that contingency allowances be independent of the original time and cost estimates. These allowances need to be clearly distinguished to avoid time and budget game playing.

Budget Reserves These reserves are identified for specific work packages or segments of a project found in the baseline budget or work breakdown structure. For example, a reserve amount might be added to “computer coding” to cover the risk of “testing” showing a coding problem. The reserve amount is determined by costing out the accepted contingency or recovery plan. The budget reserve should be communicated to the project team. This openness suggests trust and encourages good cost performance. However, distributing budget reserves should be the responsibility of both the project manager and the team members responsible for implementing the specific segment of the project. If the risk does not materialize, the funds are removed from the budget reserve. Thus, budget reserves decrease as the project progresses.

Management Reserves These reserve funds are needed to cover major unforeseen risks and, hence, are applied to the total project. For example, a major scope change may appear necessary midway in the project. Because this change was not anticipated, it is covered from the management reserve. Management reserves are established after budget reserves are identified and funds established. These reserves are independent of budget reserves and are controlled by the project manager and the “owner” of the project. The “owner” can be internal (top management) or external to the project organization. Most management reserves are set using historical data and judgments concerning the uniqueness and complexity of the project. Placing technical contingencies in the management reserve is a special case. Identi- fying possible technical (functional) risks is often associated with a new, untried, inno- vative process or product. Because there is a chance the innovation may not work out, a fallback plan is necessary. This type of risk is beyond the control of the project man- ager. Hence, technical reserves are held in the management reserve and controlled by

Chapter 7 Managing Risk 225

the owner or top management. The owner and project manager decide when the con- tingency plan will be implemented and the reserve funds used. It is assumed there is a high probability these funds will never be used. Table 7.1 shows the development of a contingency fund estimate for a hypothetical project. Note how budget and management reserves are kept separate; control is easily tracked using this format.

Time Buffers Just as contingency funds are established to absorb unplanned costs, managers use time buffers to cushion against potential delays in the project. And like contingency funds, the amount of time is dependent upon the inherent uncertainty of the project. The more uncertain the project the more time should be reserved for the schedule. The strategy is to assign extra time at critical moments in the project. For example, buffers are added to A. Activities with severe risks. B. Merge activities that are prone to delays due to one or more preceding activities

being late. C. Noncritical activities to reduce the likelihood that they will create another critical

path. D. Activities that require scarce resources to ensure that the resources are available

when needed. In the face of overall schedule uncertainty, buffers are sometimes added to the end of the project. For example, a 300-working-day project may have a 30-day project buffer. While the extra 30 days would not appear on the schedule, it is available if needed. Like management reserves, this buffer typically requires the authorization of top man- agement. A more systematic approach to buffer management is discussed in the Chap- ter 8 appendix on critical chain project management.

7.8 Step 4: Risk Response Control Typically the results of the first three steps of the risk management process are sum- marized in a formal document often called the risk register. A risk register details all identified risks, including descriptions, category, and probability of occurring, impact, responses, contingency plans, owners, and current status. The register is the backbone for the last step in the risk management process: risk control. Risk control involves executing the risk response strategy, monitoring triggering events, initiating contin- gency plans, and watching for new risks. Establishing a change management system to deal with events that require formal changes in the scope, budget, and/or schedule of the project is an essential element of risk control.

Budget Budget Project Activity Baseline Reserve Budget

Design $500,000 $15,000 $515,000 Code 900,000 80,000 980,000 Test 20,000 2,000 22,000 Subtotal $1,420,000 $97,000 $1,517,000 Management reserve — — 50,000 Total $1,420,000 $97,000 $1,567,000

TABLE 7.1 Contingency Fund Estimate

226 Chapter 7 Managing Risk

Project managers need to monitor risks just like they track project progress. Risk assessment and updating needs to be part of every status meeting and progress report system. The project team needs to be on constant alert for new, unforeseen risks. Thamhain studied 35 major product development efforts and found that over half of contingencies that occurred were not anticipated (Thamhain, 2013)! Readiness to respond to the unexpected is a critical element of risk management. Management needs to be sensitive that others may not be forthright in acknowledg- ing new risks and problems. Admitting that there might be a bug in the design code or that different components are not compatible reflects poorly on individual perfor- mance. If the prevailing organizational culture is one where mistakes are punished severely, then it is only human nature to protect oneself. Similarly, if bad news is greeted harshly and there is a propensity to “kill the messenger,” then participants will be reluctant to speak freely. The tendency to suppress bad news is compounded when individual responsibility is vague and the project team is under extreme pressure from top management to get the project done quickly. Project managers need to establish an environment in which participants feel com- fortable raising concerns and admitting mistakes. The norm should be that mistakes are acceptable, hiding mistakes is intolerable. Problems should be embraced not denied. Participants should be encouraged to identify problems and new risks. Here a positive attitude by the project manager toward risks is a key. On large, complex projects it may be prudent to repeat the risk identification/ assessment exercise with fresh information. Risk profiles should be reviewed to test to see if the original responses held true. Relevant stakeholders should be brought into the discussion and the risk register needs to be updated. While this may not be practi- cal on an ongoing basis, project managers should touch base with them on a regular basis or hold special stakeholder meetings to review the status of risks on the project. A second key for controlling the cost of risks is documenting responsibility. This can be problematic in projects involving multiple organizations and contractors. Responsi- bility for risk is frequently passed on to others with the statement, “That is not my worry.” This mentality is dangerous. Each identified risk should be assigned (or shared) by mutual agreement of the owner, project manager, and the contractor or person hav- ing line responsibility for the work package or segment of the project. It is best to have the line person responsible approve the use of budget reserve funds and monitor their rate of usage. If management reserve funds are required, the line person should play an active role in estimating additional costs and funds needed to complete the project. Hav- ing line personnel participate in the process focuses attention on the management reserve, control of its rate of usage, and early warning of potential risk events. If risk management is not formalized, responsibility and responses to risk will be ignored—it is not my area. The bottom line is that project managers and team members need to be vigilant in monitoring potential risks and identify new land mines that could derail a project. Risk assessment has to be part of the working agenda of status meetings, and when new risks emerge they need to be analyzed and incorporated into the risk management process.

7.9 Change Control Management A major element of the risk control process is change management. Every detail of a project plan will not materialize as expected. Coping with and controlling project changes present a formidable challenge for most project managers. Changes come from many sources such as the project customer, owner, project

7-8LO Recognize the need for risk management being an ongoing activity.

7-9LO Describe the change control process.

Chapter 7 Managing Risk 227

manager, team members, and occurrence of risk events. Most changes easily fall into three categories: 1. Scope changes in the form of design or additions represent big changes; for exam-

ple, customer requests for a new feature or a redesign that will improve the product.

2. Implementation of contingency plans, when risk events occur, represent changes in baseline costs and schedules.

3. Improvement changes suggested by project team members represent another category.

Because change is inevitable, a well-defined change review and control process should be set up early in the project planning cycle. Change management systems involve reporting, controlling, and recording changes to the project baseline. (Note: Some organizations consider change control systems part of configuration management.) In practice most change management systems are designed to accomplish the following: 1. Identify proposed changes. 2. List expected effects of proposed change(s) on schedule and budget. 3. Review, evaluate, and approve or disapprove changes formally. 4. Negotiate and resolve conflicts of change, conditions, and cost. 5. Communicate changes to parties affected. 6. Assign responsibility for implementing change. 7. Adjust master schedule and budget. 8. Track all changes that are to be implemented. As part of the project communication plan, stakeholders define up front the com- munication and decision-making process that will be used to evaluate and accept changes. The process can be captured in a flow diagram like the one presented in Figure 7.9. On small projects this process may simply entail approval of a small group of stakeholders. On larger projects more elaborate decision-making processes are established, with different processes being used for different kinds of change. For example, changes in performance requirements may require multiple sign-offs, including the project sponsor and client, while switching suppliers may be autho- rized by the project manager. Regardless of the nature of the project, the goal is to establish the process for introducing necessary changes in the project in a timely and effective manner. Of particular importance is assessing the impact of the change on the project. Often solutions to immediate problems have adverse consequences on other aspects of a project. For example, in overcoming a problem with the exhaust system for a hybrid automobile, the design engineers contributed to the prototype exceeding weight parameters. It is important that the implications of changes are assessed by people with appropriate expertise and perspective. On construction projects this is often the responsibility of the architecture firm, while “software architects” perform a similar function on software development efforts. Organizations use change request forms and logs to track proposed changes. An example of a simplified change request form is depicted in Figure 7.10. Typically change request forms include a description of the change, the impact of not approving the change, the impact of the change on project scope/schedule/cost, and defined sig- nature paths for review as well as a tracking log number.

Distribute for

Action

No

Change Originates

Review Change Request

Yes

Change Request Submitted

Approved ?

Update Plan of Record

FIGURE 7.9 Change Control Process

228 Chapter 7 Managing Risk

An abridged version of a change request log for a construction project is presented in Figure 7.11. These logs are used to monitor change requests. They typically sum- marize the status of all outstanding change requests and include such useful informa- tion as source and date of the change, document codes for related information, cost estimates, and the current status of the request. Every approved change must be identified and integrated into the plan of record through changes in the project WBS and baseline schedule. The plan of record is the current official plan for the project in terms of scope, budget, and schedule. The plan of record serves as a change management benchmark for future change requests as well as the baseline for evaluating project progress. If the change control system is not integrated with the WBS and baseline, project plans and control will soon self-destruct. Thus, one of the keys to a successful change

FIGURE 7.10 Sample Change Request

Priority

Emergency

Urgent

Low

Disposition

Approve

Approve as amended

Disapprove

Deferred

Funding Source

Mgmt. reserve

Budget reserve

Customer

Other

Request number 12

Description of requested change

1. Request river dancers to replace small Irish dance group. 2. Request one combination dance with river dancers and China ballet group.

Reason for change

River dancers will enhance stature of event. The group is well known and loved by Chinese people.

Scope

Schedule

X X

X X

X

Cost

Risk

Other

Areas of impact of proposed change–describe each on separate sheet

Project name Irish/Chinese culture exchange

Jennifer McDonaldOriginator

Date June 6, 2xxx

Sign-off Approvals

Project manager

Project sponsor

Other

Project customer

William O'Mally

Kenneth Thompson

Hong Lee

Date June 12, 2xxx

Date June 13, 2xxx

Date June 18, 2xxx

Date

Project sponsor Irish embassy

Chinese culture office Change requested by

Chapter 7 Managing Risk 229

FIGURE 7.11 Change Request Log

Owner Requested Change Status Report—Open Items OSU—Weatherford

Reference Dates

Rc# Description Document Date Rec’d Date Submit Amount Status Comments

51 Sewer work –188,129 OPEN FUNDING offset FROM OTHER SOURCE 52 Stainless Plates ASI 56 1/5/2013 3/30/2013 9,308 APPROVED at restroom Shower Valves 53 Waterproofing ASI 77 1/13/2013 169,386 OPEN Options 54 Change Electrical RFI 113 12/5/2013 3/29/2013 2,544 SUBMIT floor box spec change 55 VE Option Door 1/14/2013 −20,000 ROM for Style and samples rail doors 56 Pressure Wash Owner 3/15/2013 3/30/2013 14,861 SUBMIT C tower request 57 Fire Lite glass Owner 8,000 QUOTE ROM BASED in stairs request ON FIRELITE NT 58 Cyber Café ASI 65 1/30/2013 3/29/2013 4,628 APPROVED added tele /OFOI equipment 59 Additional Dampers ASI 68 2/4/2013 3/29/2013 1,085 SUBMIT in C wing 60 Revise ASI 72 2/13/2013 3/31/2013 –3,755 SUBMIT Corridor ceilings

OPEN—Requires estimate SUBMIT—RC letter submitted ASI—Architect’s supplemental instructions ROM—Rough order magnitude APPROVED—RC letter approved RFI—Request for information QUOTE—Subcontractor quotes REVISE—RC letter to be reviewed

control process is document, document, document! The benefits derived from change control systems are the following: 1. Inconsequential changes are discouraged by the formal process. 2. Costs of changes are maintained in a log. 3. Integrity of the WBS and performance measures is maintained. 4. Allocation and use of budget and management reserve funds are tracked. 5. Responsibility for implementation is clarified. 6. Effect of changes is visible to all parties involved. 7. Implementation of change is monitored. 8. Scope changes will be quickly reflected in baseline and performance measures. Clearly, change control is important and requires that someone or some group be responsible for approving changes, keeping the process updated, and communicating changes to the project team and relevant stakeholders. Project control depends heavily on keeping the change control process current. This historical record can be used for satisfying customer inquiries, identifying problems in post-project audits, and estimat- ing future project costs.

230 Chapter 7 Managing Risk

To put the processes discussed in this chapter in proper perspective one should rec- ognize that the essence of project management is risk management. Every technique in this book is really a risk management technique. Each in its own way tries to pre- vent something bad from happening. Project selection systems try to reduce the like- lihood that projects will not contribute to the mission of the firm. Project scope statements, among other things, are designed to avoid costly misunderstandings and reduce scope creep. Work breakdown structures reduce the likelihood that some vital part of the project will be omitted or that the budget estimates are unrealistic. Teambuilding reduces the likelihood of dysfunctional conflict and breakdowns in coordination. All of the techniques try to increase stakeholder satisfaction and increase the chances of project success. From this perspective managers engage in risk management activities to compen- sate for the uncertainty inherent in project management and that things never go ac- cording to plan. Risk management is proactive not reactive. It reduces the number of surprises and prepares people for the unexpected. Although many managers believe that in the final analysis, risk assessment and contingency depend on subjective judgment, some standard method for identifying, assessing, and responding to risks should be included in all projects. The very process of identifying project risks forces some discipline at all levels of project management and improves project performance. Contingency plans increase the chance that the project can be completed on time and within budget. Contingency plans can be simple “work-arounds” or elaborate detailed plans. Responsibility for risks should be clearly identified and documented. It is desirable and prudent to keep a reserve as a hedge against project risks. Budget reserves are linked to the WBS and should be communicated to the project team. Con- trol of management reserves should remain with the owner, project manager, and line person responsible. Use of contingency reserves should be closely monitored, con- trolled, and reviewed throughout the project life cycle. Experience clearly indicates that using a formal, structured process to handle pos- sible foreseen and unforeseen project risk events minimizes surprises, costs, delays, stress, and misunderstandings. Risk management is an iterative process that occurs throughout the lifespan of the project. When risk events occur or changes are neces- sary, using an effective change control process to quickly approve and record changes will facilitate measuring performance against schedule and cost. Ultimately success- ful risk management requires a culture in which threats are embraced not denied and problems are identified not hidden.

Summary

Key Terms Accept risk, 218 Avoiding risk, 217 Budget reserve, 224 Change management system, 227 Contingency plan, 219 Management reserve, 224 Mitigating risk, 216

Opportunity, 223 Risk, 207 Risk breakdown structure (RBS), 210 Risk profile, 211 Risk register, 225 Risk severity matrix, 214 Scenario analysis, 213

Time buffer, 225 Transferring risk, 217

Chapter 7 Managing Risk 231

Review Questions

1. Project risks can/cannot be eliminated if the project is carefully planned. Explain. 2. The chances of risk events occurring and their respective costs increasing change

over the project life cycle. What is the significance of this phenomenon to a project manager?

3. What is the difference between avoiding a risk and accepting a risk? 4. What is the difference between mitigating a risk and contingency planning? 5. Explain the difference between budget reserves and management reserves. 6. How are the work breakdown structure and change control connected? 7. What are the likely outcomes if a change control process is not used? Why? 8. What are the major differences between managing negative risks versus positive

risks (opportunities)?

Exercises 1. Gather a small team of students. Think of a project most students would understand; the kinds of tasks involved should also be familiar. Identify and assess major and minor risks inherent to the project. Decide on a response type. Develop a contin- gency plan for two to four identified risks. Estimate costs. Assign contingency reserves. How much reserve would your team estimate for the whole project? Jus- tify your choices and estimates.

2. You have been assigned to a project risk team of five members. Because this is the first time your organization has formally set up a risk team for a project, it is hoped that your team will develop a process that can be used on all future projects. Your first team meeting is next Monday morning. Each team member has been asked to prepare for the meeting by developing, in as much detail as possible, an outline that describes how you believe the team should proceed in handling project risks. Each of the team members will hand out their proposed outline at the beginning of the meeting. Your outline should include but not be limited to the following information:

a. Team objectives. b. Process for handling risk events. c. Team activities. d. Team outputs. 3. The Manchester United Soccer Tournament project team (review the Manchester

United case at the end of Chapter 4) has identified the following potential risks to their project:

a. Referees failing to show up at designated games. b. Fighting between teams. c. Pivotal error committed by a referee that determines the outcome of a game. d. Abusive behavior along the sidelines by parents. e. Inadequate parking. f. Not enough teams sign up for different age brackets. g. Serious injury. How would you recommend that they respond (i.e., avoid, accept, . . .) to these risks

and why? 4. Search the Web using the key words: “best practices, project management.” What

did you find? How might this information be useful to a project manager?

232 Chapter 7 Managing Risk

References Atkinson, W., “Beyond the Basics,” PM Network, May 2003, pp. 38–43. Baker, B., and R. Menon, “Politics and Project Performance: The Fourth Dimension of Project Management,” PM Network, vol. 9, no. 11 (November 1995), pp. 16–21. Carr, M. J., S. L. Konda, I. Monarch, F. C. Ulrich, and C. F. Walker, “Taxonomy- Based Risk Identification,” Technical Report CMU/SEI-93-TR 6, Software Engineer- ing Institute, Carnegie Mellon University, Pittsburgh, 1993. Ford, E. C., J. Duncan, A. G. Bedeian, P. M. Ginter, M. D. Rousculp, and A. M. Adams, “Mitigating Risks, Visible Hands, Inevitable Disasters, and Soft Variables: Management Research That Matters to Managers,” Academy of Management Executive, vol. 19, no. 4 (November 2005), pp. 24–38. Gray, C. F., and R. Reinman, “PERT Simulation: A Dynamic Approach to the PERT Technique,” Journal of Systems Management, March 1969, pp. 18–23. Hamburger, D. H., “The Project Manager: Risk Taker and Contingency Planner,” Project Management Journal, vol. 21, no. 4 (1990), pp. 11–16. Hulett, D. T., “Project Schedule Risk Assessment,” Project Management Journal, 26 (1) 1995, pp. 21–31. Ingebretson, M., “In No Uncertain Terms,” PM Network, 2002, pp. 28–32. Meyer, A. D., C. H. Loch, and M. T. Pich, “Managing Project Uncertainty: From Variation to Chaos,” MIT Sloan Management Review, Winter 2002, pp. 60–67. Orlando Sentinel, “Math Mistake Proved Fatal to Mars Orbiter,” November 23, 1999. Pavlik, A., “Project Troubleshooting: Tiger Teams for Reactive Risk Management,” Project Management Journal, vol. 35, no. 4 (December 2004), pp. 5–14. Pinto, J. K., Project Management: Achieving Competitive Advantage (Upper Saddle River, NJ: Pearson, 2007). Project Management Body of Knowledge (Newton Square, PA: Project Management Institute, 2013). Schuler, J. R., “Decision Analysis in Projects: Monte Carlo Simulation,” PM Network, vol. 7, no. 1 (January 1994), pp. 30–36. Skelton, T. and H. Thamhain, “Managing Risk in New Product Development Projects: Beyond Analytical Methods,” Project Perspectives, vol. 27, no. 1 (2006), pp. 12–20. Skelton, T. and H. Thamhain, “Success Factors for Effective R&D Risk Management,” International Journal of Technology Intelligence and Planning, vol. 3, no. 4 (2007), pp. 376–386. Smith, P. G., and G. M. Merritt, Proactive Risk Management: Controlling Uncertainty in Product Development (New York: Productivity Press, 2002). Smith, P. G., and D. G. Reinertsen, Developing Products in Half the Time (New York: Van Nostrand Reinhold, 1995). Snizek, J. A., and R. A. Henry, “Accuracy and Confidence in Group Judgment,” Orga- nizational Behavior and Human Decision Processes, vol. 4, no. 3 (1989), pp. 1–28. Thamhain, H., “Managing Risks in Complex Projects,” Project Management Journal, vol. 44, no. 20 (2013), pp. 20–35.

Chapter 7 Managing Risk 233

Case 7.1

Alaska Fly-Fishing Expedition*

You are sitting around the fire at a lodge in Dillingham, Alaska, discussing a fishing expedition you are planning with your colleagues at Great Alaska Adventures (GAA). Earlier in the day you received a fax from the president of BlueNote, Inc. The presi- dent wants to reward her top management team by taking them on an all-expense-paid fly-fishing adventure in Alaska. She would like GAA to organize and lead the expedition. You have just finished a preliminary scope statement for the project (see below). You are now brainstorming potential risks associated with the project. 1. Brainstorm potential risks associated with this project. Try to come up with at least

five different risks. 2. Use a risk assessment form similar to Figure 7.6 to analyze identified risks. 3. Develop a risk response matrix similar to Figure 7.8 to outline how you would deal

with each of the risks.

PROJECT SCOPE STATEMENT PROJECT OBJECTIVE To organize and lead a five-day fly-fishing expedition down the Tikchik River system in Alaska from June 21 to 25 at a cost not to exceed $35,000.

DELIVERABLES ∙ Provide air transportation from Dillingham, Alaska, to Camp I and from Camp II

back to Dillingham. ∙ Provide river transportation consisting of two eight-man drift boats with outboard

motors. ∙ Provide three meals a day for the five days spent on the river. ∙ Provide four hours fly-fishing instruction. ∙ Provide overnight accommodations at the Dillingham lodge plus three four-man

tents with cots, bedding, and lanterns. ∙ Provide four experienced river guides who are also fly fishermen. ∙ Provide fishing licenses for all guests.

MILESTONES 1. Contract signed January 22. 2. Guests arrive in Dillingham June 20. 3. Depart by plane to Base Camp I June 21. 4. Depart by plane from Base Camp II to Dillingham June 25.

* This case was prepared with the assistance of Stuart Morigeau.

234 Chapter 7 Managing Risk

TECHNICAL REQUIREMENTS 1. Fly in air transportation to and from base camps. 2. Boat transportation within the Tikchik River system. 3. Digital cellular communication devices. 4. Camps and fishing conform to state of Alaska requirements.

LIMITS AND EXCLUSIONS 1. Guests are responsible for travel arrangements to and from Dillingham, Alaska. 2. Guests are responsible for their own fly-fishing equipment and clothing. 3. Local air transportation to and from base camps will be outsourced. 4. Tour guides are not responsible for the number of King Salmon caught by guests.

CUSTOMER REVIEW The president of BlueNote, Inc.

Case 7.2

Silver Fiddle Construction You are the president of Silver Fiddle Construction (SFC), which specializes in build- ing high-quality, customized homes in the Grand Junction, Colorado, area. You have just been hired by the Czopeks to build their dream home. You operate as a general contractor and employ only a part-time bookkeeper. You subcontract work to local trade professionals. Housing construction in Grand Junction is booming. You are ten- tatively scheduled to complete 11 houses this year. You have promised the Czopeks that the final costs will range from $450,000 to $500,000 and that it will take five months to complete the house once groundbreaking has begun. The Czopeks are will- ing to have the project delayed in order to save costs. You have just finished a preliminary scope statement for the project (see below). You are now brainstorming potential risks associated with the project. 1. Identify potential risks associated with this project. Try to come up with at least

five different risks. 2. Use a risk assessment form similar to Figure 7.6 to analyze identified risks. 3. Develop a risk response matrix similar to Figure 7.8 to outline how you would deal

with each of the risks.

PROJECT SCOPE STATEMENT PROJECT OBJECTIVE To construct a high-quality, custom home within five months at a cost not to exceed $500,000. DELIVERABLES ∙ A 2,500-square-foot, 2½-bath, 3-bedroom, finished home. ∙ A finished garage, insulated and sheetrocked.

Chapter 7 Managing Risk 235

∙ Kitchen appliances to include range, oven, microwave, and dishwasher. ∙ High-efficiency gas furnace with programmable thermostat.

MILESTONES 1. Permits approved July 5. 2. Foundation poured July 12. 3. “Dry in”—framing, sheathing, plumbing, electrical, and mechanical inspections—

passed September 25. 4. Final inspection November 7.

TECHNICAL REQUIREMENTS 1. Home must meet local building codes. 2. All windows and doors must pass NFRC class 40 energy ratings. 3. Exterior wall insulation must meet an “R” factor of 21. 4. Ceiling insulation must meet an “R” factor of 38. 5. Floor insulation must meet an “R” factor of 25. 6. Garage will accommodate two cars and one 28-foot-long Winnebago. 7. Structure must pass seismic stability codes.

LIMITS AND EXCLUSIONS 1. The home will be built to the specifications and design of the original blueprints

provided by the customer. 2. Owner is responsible for landscaping. 3. Refrigerator is not included among kitchen appliances. 4. Air conditioning is not included, but house is prewired for it. 5. SFC reserves the right to contract out services.

CUSTOMER REVIEW “Bolo” and Izabella Czopek.

Case 7.3

Trans LAN Project Trans Systems is a small information systems consulting firm located in Meridian, Louisiana. Trans has just been hired to design and install a local area network (LAN) for the city of Meridian’s social welfare agency. You are the manager for the project, which includes one Trans professional and two interns from a local university. You have just finished a preliminary scope statement for the project (see below). You are now brainstorming potential risks associated with the project. 1. Identify potential risks associated with this project. Try to come up with at least

five different risks. 2. Use a risk assessment form similar to Figure 7.6 to analyze identified risks. 3. Develop a risk response matrix similar to Figure 7.8 to outline how you would deal

with each of the risks.

236 Chapter 7 Managing Risk

PROJECT SCOPE STATEMENT PROJECT OBJECTIVE To design and install a new local area network (LAN) within one month with a budget not to exceed $90,000 for the Meridian Social Service Agency with minimum disrup- tion to ongoing operations.

DELIVERABLES ∙ Twenty workstations and twenty laptop computers. ∙ Server with dual-core processors. ∙ Two color laser printers. ∙ Windows R2 server and workstation operating system (Windows 10). ∙ Migration of existing databases and programs to new system. ∙ Four hours of introduction training for client’s personnel. ∙ Sixteen hours of training for client network administrator. ∙ Fully operational LAN system.

MILESTONES 1. Hardware January 22. 2. Setting users’ priority and authorization January 26. 3. In-house whole network test completed February 1. 4. Client site test completed February 2. 5. Training completed February 16.

TECHNICAL REQUIREMENTS 1. Workstations with 17-inch flat panel monitors, dual-core processors, 4 GB RAM,

8X DVD+RW, wireless card, Ethernet card, 500 GB hard drive. 2. Laptops with 12-inch display monitor, dual-core processors, 2GB RAM,

8X DVD+RW, wireless card, Ethernet card, 500 GB hard drive and weigh less than 4½ lbs.

3. Wireless network interface cards and Ethernet connections. 4. System must support Windows 11 platforms. 5. System must provide secure external access for field workers.

LIMITS AND EXCLUSIONS 1. On-site work to be done after 8:00 p.m. and before 7:00 a.m. Monday through

Saturday. 2. System maintenance and repair only up to one month after final inspection. 3. Warranties transferred to client. 4. Only responsible for installing software designated by the client two weeks before

the start of the project. 5. Client will be billed for additional training beyond that prescribed in the contract.

CUSTOMER REVIEW Director of the city of Meridian’s Social Service Agency.

Chapter 7 Managing Risk 237

Case 7.4

XSU Spring Concert You are a member of the X State University (XSU) student body entertainment com- mittee. Your committee has agreed to sponsor a spring concert. The motive behind this concert is to offer a safe alternative to Hasta Weekend. Hasta Weekend is a spring event in which students from XSU rent houseboats and engage in heavy partying. Tra- ditionally this occurs during the last weekend in May. Unfortunately, the partying has a long history of getting out of hand, sometimes leading to fatal accidents. After one such tragedy last spring, your committee wants to offer an alternative experience for those who are eager to celebrate the change in weather and the pending end of the school year. You have just finished a preliminary scope statement for the project (see below). You are now brainstorming potential risks associated with the project. 1. Identify potential risks associated with this project. Try to come up with at least

five different risks. 2. Use a risk assessment form similar to Figure 7.6 to analyze identified risks. 3. Develop a risk response matrix similar to Figure 7.8 to outline how you would deal

with each of the risks.

PROJECT SCOPE STATEMENT PROJECT OBJECTIVE To organize and deliver an eight-hour concert at Wahoo Stadium at a cost not to exceed $50,000 on the last Saturday in May.

DELIVERABLES ∙ Local advertising. ∙ Concert security. ∙ Separate Beer Garden. ∙ Eight hours of music and entertainment. ∙ Food venues. ∙ Souvenir concert T-shirts. ∙ Secure all licenses and approvals. ∙ Secure sponsors.

MILESTONES 1. Secure all permissions and approvals by January 15. 2. Sign big-name artist by February 15. 3. Complete artist roster by April 1. 4. Secure vendor contracts by April 15. 5. Setup completed on May 27. 6. Concert on May 28. 7. Cleanup completed by May 31.

238 Chapter 7 Managing Risk

Case 7.5

Sustaining Project Risk Management during Implementation

BACKGROUND Bill (Senior VP of product development): Carlos [project manager], we have to talk. I am concerned about the way we manage project risk here at Futuronics. I just came from an international “Future Mote Devices” meeting at UC Berkeley. [Note: A mote is a very small [e.g., 2–3mm square], wireless sensing pod that may be placed on land or in water to measure and communicate data.] The project management sessions receiving most attention addressed risk in product development projects. They described our management of project risk to the letter—failure to sustain risk manage- ment after the project gets rolling. It seems someone has to get burned before risk management is taken seriously. Much to my surprise, almost every project manager there admitted their firms have a problem sustaining team members’ interest in managing risk after the project is on its way. The old saying, “If you don’t manage risk, you pay the price later,” generated horror stories from a few who paid the price. We spent some time brainstorming ways to handle the problem at the project level, but there were very few concrete sugges- tions. The meeting gave me a wakeup call. Carlos, we need to tackle this problem or some new or known risk event could put us both out of a job. The similarities between their horror stories and some of our past mistakes are scary. Since here at Futuronics we only develop new products that are at least seven years beyond anything on the market, the level of both “known risk events and unknown risk” is far higher than in most other organizations. Managing project risk is important to every project, but here at Futuronics every new product project is loaded with risks. Carlos, I’m willing to work with you to improve our management of project risk at Futuronics.

TECHNICAL REQUIREMENTS 1. Professional sound stage and system. 2. At least one big-name artist. 3. At least seven performing acts. 4. Restroom facilities for 10,000 people. 5. Parking available for 1,000 cars. 6. Compliance with XSU and city requirements/ordinances.

LIMITS AND EXCLUSIONS 1. Performers responsible for travel arrangements to and from XSU. 2. Vendors contribute a set percentage of sales. 3. Concert must be over by 11:30 p.m.

CUSTOMER REVIEW The president of XSU student body.

Chapter 7 Managing Risk 239

Carlos: Bill, I am aware of the problem. The PMI Roundtables I attend also talk to the difficulty of keeping teams and other stakeholders willing to revisit risk once the proj- ect is on its way. [PMI Roundtables are monthly meetings of practicing PMs across industries designed to address project management problems.] I also heard war stories at a recent project management roundtable meeting. I have some notes from the meet- ing right here. It all started with the leader’s question: “How many project managers actually man- age risk over the complete project life cycle?”

PM 1: We all work through the risk management process well before the project begins. We have the process template of risk identification, assessment, response, control, risk register, and contingency down pat. We just don’t follow through after the project begins. I think interest dies. Have you ever tried to get project stakehold- ers to come to a risk meeting when the project is moving relatively well?

PM 2: A recent e-mail from one of our stakeholders said, “We’ll deal with it [risk] when it happens.”

PM 3: I agree. Interest seems to move from future oriented to reactionary. Also, risk management seems to degenerate into issue (concerns and problems) manage- ment versus real risk management.

PM 4: I ask team members, “What is the risk of not managing risk over the life of the project?” Sometimes this question nudges a few to respond positively, espe- cially if risks have changed or new ones are perceived. I use a failed project where a solid risk management process would have avoided the project failure. I explain all of the risk management processes that would have helped to improve the risk elements—risk identification, triggers, responsibility, transfer, accept, etc.

PM 5: Risk is not a line item in the budget or schedule. Maybe it is in the contin- gency budget to cover “unknowns of unknowns.” I have to watch that management doesn’t try to squeeze out the contingency budget for something else.

Carlos continued to share with his boss that there were many more comments, but very few gave much guidance. Carlos then shared his idea: Carlos: Colette is our best trainer, especially in transition management, and she would be a great choice for following through on this problem. Her training classes on upfront risk management are excellent. Should we ask her to present a session? Bill: You are right, Carlos, Colette is ideal. She is smart and a great team motivator. Ask her, but give her some kind of direction for focus. A few days later, Carlos sent out a memo: Colette, this is to follow up on our lunch conversation yesterday discussing sustaining risk management after the project is on its way. Given the nature of our futuristic com- pany, we should stress the point that our product development projects carry many more inherent risks than do traditional projects. I suggest the training classes should drill down on concrete actions and policies that will encourage interest of team mem- bers and other project stakeholders in sustaining risk management practices during project execution. Colette, we appreciate your taking on this project. When you have developed your training session, please give me a copy so I can schedule and support your efforts. Regards, Carlos

240 Chapter 7 Managing Risk

CHALLENGE Divide the class into teams of three or more participants. Colette needs your help to develop her training program. You may wish to consider the questions listed below to initiate ideas. ∙ Why do project stakeholders lose interest in project risk after the project is under

way? ∙ What are the dangers of not keeping on top of risk management during

implementation? ∙ What kind of business is Futuronics in? Brainstorm specific actions that will encourage project stakeholders to continue to scan and track the project environment for risk events. Suggest three concrete actions or scenarios that will encourage project stakeholders to change their behavior and truly support risk management while projects are being implemented. The following outline headings may be helpful in developing possible actions that would improve/enhance stakeholder support. ∙ Improving the risk management process ∙ Organization actions ∙ Motivating participation

Appendix 7.1

PERT and PERT Simulation LEARNING OBJECTIVES After reading this appendix you should be able to:

A7-1 Calculate basic Pert Simulation projections.

PERT—PROGRAM EVALUATION AND REVIEW TECHNIQUE In 1958 the Special Office of the Navy and the Booze, Allen, and Hamilton consulting firm developed PERT (program evaluation and review technique) to schedule the more than 3,300 contractors of the Polaris submarine project and to cover uncertainty of activity time estimates. PERT is almost identical to the critical path method (CPM) technique except it assumes each activity duration has a range that follows a statistical distribution. PERT uses three time estimates for each activity. Basically, this means each activity duration can range from an optimistic time to a pessimistic time, and a weighted average can be computed for each activity. Because project activities usually represent work, and because work tends to stay behind once it gets behind, the PERT developers chose an approximation of the beta distribution to represent activity durations. This distribution is known to be flexible and can accommodate empirical data that do not follow a nor- mal distribution. The activity durations can be skewed more toward the high or low end of the data range. Figure A7.1A depicts a beta distribution for activity durations that is skewed toward the right and is representative of work that tends to stay late once it is behind. The distribution for the project duration is represented by a normal

Calculate basic Pert Simulation projections.

A7-1LO

Chapter 7 Managing Risk 241

(symmetrical) distribution shown in Figure A7.1B. The project distribution represents the sum of the weighted averages of the activities on the critical path(s). Knowing the weighted average and variances for each activity allows the project planner to compute the probability of meeting different project durations. Follow the steps described in the hypothetical example given next. (The jargon is difficult for those not familiar with statistics, but the process is relatively simple after working through a couple of examples.) The weighted average activity time is computed by the following formula:

te = a + 4m + b

6 (7.1)

where te = weighted average activity time a = optimistic activity time (1 chance in 100 of completing the activity

earlier under normal conditions) b = pessimistic activity time (1 chance in 100 of completing the activity

later under normal conditions) m = most likely activity time When the three time estimates have been specified, this equation is used to compute the weighted average duration for each activity. The average (deterministic) value is placed on the project network as in the CPM method and the early, late, slack, and project completion times are computed as they are in the CPM method. The variability in the activity time estimates is approximated by the following equa- tions: Equation 7.2 represents the standard deviation for the activity. Equation 7.3 rep- resents the standard deviation for the project. Note the standard deviation of the activity is squared in this equation; this is also called variance. This sum includes only activities on the critical path(s) or path being reviewed.

σte = (b − a6 ) (7.2) σTE = √Σσte

2 (7.3)

Finally, the average project duration (TE) is the sum of all the average activity times along the critical path (sum of te), and it follows a normal distribution.

FIGURE A7.1 Activity and Project Frequency Distributions

a m

ACTIVITY

b

(A)

TE

PROJECT

(B)

242 Chapter 7 Managing Risk

Knowing the average project duration and the variances of activities allows the probability of completing the project (or segment of the project) by a specific time to be computed using standard statistical tables. The equation below (Equation 7.4) is used to compute the “Z” value found in statistical tables (Z = number of standard deviations from the mean), which, in turn, tells the probability of completing the proj- ect in the time specified.

Z = TS − TE √Σσte

2 (7.4)

where

TE = critical path duration TS = scheduled project duration Z = probability (of meeting scheduled duration) found in statistical Table A7.2

A HYPOTHETICAL EXAMPLE USING THE PERT TECHNIQUE The activity times and variances are given in Table A7.1. The project network is presented in Figure A7.2. This figure shows the project network as AOA and AON. The AON net- work is presented as a reminder that PERT can use AON networks as well as AOA. The expected project duration (TE) is 64 time units; the critical path is 1-2-3-5-6. With this information, the probability of completing the project by a specific date can easily be computed using standard statistical methods. For example, what is the prob- ability the project will be completed before a scheduled time (TS) of 67? The normal curve for the project would appear as shown in Figure A7.3. Using the formula for the Z value, the probability can be computed as follows:

Z = TS − TE √Σσte

2

= 67 − 64 √25 + 9 + 1 + 1

= +3 √36

= +0.50 P = 0.69

Reading from Table A7.2, a Z value of +0.5 gives a probability of 0.69, which is inter- preted to mean there is a 69 percent chance of completing the project on or before 67 time units.

Activity a m b te [(b – a)/6] 2

1–2 17 29 47 30 25 2–3 6 12 24 13 9 2–4 16 19 28 20 4 3–5 13 16 19 16 1 4–5 2 5 14 6 4 5–6 2 5 8 5 1

TABLE A7.1 Activity Times and Variances

Chapter 7 Managing Risk 243

FIGURE A7.2 Hypothetical Network

1 30

13 16

20 6

56 59

56 59

5 6

TE = 64

TE = 64

4

2 5

3

A0 30

30

B30

AON Network

AOA Network

43

13

D43 59

16

C30 50

20

E50 56

6

F59 64

645

FIGURE A7.3 Possible Project Durations

TE = 64

TS = 67

Conversely, the probability of completing the project by time period 60 is computed as follows:

Z = 60 − 64 √25 + 9 + 1 + 1

= −4 √36

= −0.67 P ≈ 0.26

244 Chapter 7 Managing Risk

From Table A7.2, a Z value of −0.67 gives an approximate probability of 0.26, which is interpreted to mean there is about a 26 percent chance of completing the project on or before 60 time units. Note that this same type of calculation can be made for any path or segment of a path in the network. When such probabilities are available to management, trade-off decisions can be made to accept or reduce the risk associated with a particular project duration. For example, if the project manager wishes to improve the chances of completing the proj- ect by 64 time units, at least two choices are available. First, management can spend money up front to change conditions that will reduce the duration of one or more activities on the critical path. A more prudent, second alternative would be to allocate money to a contingency fund and wait to see how the project is progressing as it is implemented.

EXERCISES

1. Given the project information below, what is the probability of completing the National Holiday Toy project in 93 time units?

2. The Global Tea and Organic Juice companies have merged. The following information has been collected for the “Consolidation Project.”

Act. ID Description Predecessor Optm. (a) Most likely (m) Pess. (b) Act time te Variance [(b − a)/6] 2 Critical

1 Design package None 6 12 24 2 Design product 1 16 19 28 3 Build package 1 4 7 10 4 Secure patent 2  24 27 36 5 Build product 2 17 29 47 6 Paint 3, 4, 5 4 7 10 7 Test market 6 13 16 19

Z Value Probability Z Value Probability

−3.0 .001 +0.0 .500 −2.8 .003 +0.2 .579 −2.6 .005 +0.4 .655 −2.4 .008 +0.6 .726 −2.2 .014 +0.8 .788 −2.0 .023 +1.0 .841 −1.8 .036 +1.2 .885 −1.6 .055 +1.4 .919 −1.4 .081 +1.6 .945 −1.2 .115 +1.8 .964 −1.0 .159 +2.0 .977 −0.8 .212 +2.2 .986 −0.6 .274 +2.4 .992 −0.4 .345 +2.6 .995 −0.2 .421 +2.8 .997

TABLE A7.2 Z Values and Probabilities

Chapter 7 Managing Risk 245

Variance ID Description Predecessor te [(b − a)/6]

2

1 Pilot production None 6 3 2 Select channels of distrib. None 7 4 3 Develop mktg. program None 4 2 4 Test market 1 4 2 5 Patent 1 10 5 6 Full production 4 16 10 7 Ad promotion 3 3 2 8 Release 2, 5, 6, 7 2 1

1. Compute the expected time for each activity. 2. Compute the variance for each activity. 3. Compute the expected project duration. 4. What is the probability of completing the project by day 112? Within 116 days? 5. What is the probability of completing “Negotiate with Unions” by day 90? 3. The expected times and variances for the project activities are given below. What is

the probability of completing the project in 25 periods?

Activity Description Predecessor a opt m ml b pess

1 Codify accounts None 16 19 28 2 File articles of unification None 30 30 30 3 Unify price and credit policy None 60 72 90 4 Unify personnel policies None 18 27 30 5 Unify data processing 1 17 29 47 6 Train accounting staff 1 4 7 10 7 Pilot run data processing 5 12 15 18 8 Calculate P & L and balance sheet 6, 7 6 12 24 9 Transfer real property 2 18 27 30 10 Train salesforce 3 20 35 50 11 Negotiate with unions 4 40 55 100 12 Determine capital needs 8 11 20 29 13 Explain personnel policies 11 14 23 26 14 Secure line of credit 9, 12 13 16 19 15 End 10, 13, 14 0 0 0

Case A7.1

International Capital, Inc.—Part A International Capital, Inc. (IC), is a small investment banking firm that special- izes in securing funds for small- to medium-sized firms. IC is able to use a stan- dardized project format for each engagement. Only activity times and unusual circumstances change the standard network. Beth Brown has been assigned to this

246 Chapter 7 Managing Risk

MANAGERIAL REPORT Brown and other broker partners have a policy of passing their plan through a project review committee of colleagues. This committee traditionally checks that all details are covered, times are realistic, and resources are available. Brown wishes you to develop a report that presents a planned schedule and expected project completion time in workdays. Include a project network in your report. The average duration for a sourcing capital project is 70 workdays. IC partners have agreed it is good business to set up projects with a 95 percent chance of attaining the plan. How does this project stack up with the average project? What would the average have to be to ensure a 95 percent chance of completing the project in 70 workdays?

Time in Workdays

Activity Optimistic Most Likely Pessimistic

A 4 7 10 B 2 4 8 C 2 5 8 D 16 19 28 E 6 9 24 F 1 7 13 G 4 10 28 H 2 5 14 I 5 8 17 J 2 5 8 K 17 29 45

Case A7.2

Advantage Energy Technology Data Center Migration— Part B In Chapter 6, Brian Smith, network administrator at Advanced Energy Technology (AET), was given the responsibility of implementing the migration of a large data center to a new office location.

Activity Description Immediate Predecessor

A Start story draft using template — B Research client firm — C Create “due diligence” rough draft A, B D Coordinate needs proposal with client C E Estimate future demand and cash flows C F Draft future plans for client company E G Create and approve legal documents C H Integrate all drafts into first-draft proposal D, F, G I Line up potential sources of capital G, F J Check, approve, and print final legal proposal H K Sign contracts and transfer funds I, J

client as project manager partner and has compiled the network information and activity times for the latest client as follows:

Chapter 7 Managing Risk 247

Time in Workdays

Optimistic Most Likely Pessimistic Immediate Task Name Dur. Dur. Dur. Predecessor Critical Path

1 AET DATA CENTER MIGRATION 54 68 92 2 Team meeting 0.5 1 1.5 ✓ 3 Hire contractors 6 7 8 2 4 Network design 12 14 16 2 5 Ventilation system — — — — 6 Order ventilation system 18 21 30 2 7 Install ventilation system 5 7 9 6 8 New racks — — — — 9 Order new racks 13 14 21 2 ✓ 10 Install racks 17 21 25 9 ✓ 11 Power supplies and cables — — — — 12 Order power supplies & cables 6 7 8 2 13 Install power supplies 5 5 11 12, 16 14 Install cables 6 8 10 12, 16 ✓ 15 Renovation of data center 19 20 27 3, 4 16 City inspection 1 2 3 3, 7, 10 ✓ 17 Switchover Meetings — — — — 18 Facilities 7 8 9 14 19 Operations/systems 5 7 9 14 20 Operations/telecommunications 6 7 8 14 21 Systems & applications 7 7 13 14 22 Customer service 5 6 13 14 ✓ 23 Power check 0.5 1 1.5 13, 14, 15 ✓ 24 Install test servers 5 7 9 18, 19, 20, 21, 22, 23 ✓ 25 Management safety check 1 2 3 7, 23, 24 ✓ 26 Primary systems check 1.5 2 2.5 25 ✓ 27 Set date for move 1 1 1 26 ✓ 28 Complete move 1 2 3 27 ✓

Careful planning was needed because AET operates in the highly competitive petroleum industry. AET is one of five national software companies that provide an accounting and business management package for oil jobbers and gasoline distribu- tors. A few years ago, AET jumped into the “application service provider” world. Their large data center provides clients with remote access to AET’s complete suite of application software systems. Traditionally, one of AET’s primary competitive advan- tages has been the company’s trademark IT reliability. Due to the complexity of this project, the Executive Committee insisted that preliminary analysis of the anticipated completion date be conducted. Brian compiled the following information, in preparation for some PERT analysis: 1. Based on these estimates and the resultant expected project duration of 69 days, the

executive committee wants to know what the probability is of completing the proj- ect before a scheduled time (TS) of 68 days.

2. The significance of this project has the executive committee very concerned. The com- mittee has decided that more analysis of the duration of each activity is needed. Prior to conducting that effort, they asked Brian to calculate what the expected project dura- tion would have to be to ensure a 93 percent chance of completion within 68 days.

248 Chapter 7 Managing Risk

ADVANTAGE ENERGY TECHNOLOGY (AET)—ACCOUNTS PAYABLE SYSTEM The AET sales department has been concerned about a new start-up company that is about to release an accounts payable system. Their investigation indicates that this new package will provide features which will seriously compete with AET’s current Accounts Payable system and in some cases exceed what AET offers. Tom Wright, senior applications developer at AET, has been given the responsibil- ity of analyzing, designing, developing, and delivering a new accounts payable system (A/P) for AET customers. Complicating the issue is the concern of the sales department about AET’s recent inability to meet promised delivery dates. They have convinced CEO (Larry Martain) that a significant marketing effort will have to be expended to convince the clients they should wait for the AET product rather than jump to a package provided by a new entry to the petroleum software business. Companion to this effort is the importance of the performance of the software development group. Consequently, Tom has decided to take the following action: tighten up the estimat- ing effort by his developers; incorporate some new estimating procedures; and use some PERT techniques to generate probabilities associated with his delivery dates. Tom’s planning team made a first-cut at the set of activities and associated durations:

Time in Workdays

Optimistic Most Likely Pessimistic Immediate Task Name Dur. Dur. Dur. Predecessor Critical Path

1 ACCOUNTS PAYABLE SYSTEM 2 Planning meeting 1 1 2 ✓ 3 Team assignments 3 4 5 2 ✓ 4 Program specification 5 Customer requirements 8 10 12 3 ✓ 6 Feasibility study 3 5 7 5 7 Systems analysis 6 8 10 5 ✓ 8 Prelim budget & schedule 1 2 3 7 ✓ 9 Functional specification 3 5 7 7 ✓ 10 Prelim design 10 12 14 9 ✓ 11 Configuration & perf needs 3 4 5 10 ✓ 12 Hardware requirements 4 6 8 11 ✓ 13 System specification 5 7 9 10 14 Detailed design 12 14 16 12, 13 ✓ 15 Program specification 8 10 12 14 ✓ 16 Programming—first phase 27 32 37 15 ✓ 17 Documentation 14 16 18 10 18 Prototype 19 Development 5 7 9 16 ✓ 20 User testing & feedback 12 14 16 19 ✓ 21 Programming—second phase 10 12 14 16 22 Beta testing 18 20 22 21 23 Final documentation pkg 9 10 11 17, 20 ✓ 24 Training pkg 4 5 6 21SS, 23 ✓ 25 Product release 3 5 7 22, 23, 24 ✓

SS = Start to Start lag

Chapter 7 Managing Risk 249

3. Based on these estimates and the critical path, the project duration is estimated at 149 days. But an AET salesperson in the Southeast Region has discovered that the competing A/P package (with significant improvements) is scheduled for delivery in approximately 145 days. The sales force is very anxious to beat that delivery time. The executive committee asks Tom for an estimated probability of reducing his expected project duration by two days.

4. The executive committee is advised by Tom that after all the estimating was com- pleted, he determined that one of his two critical systems analysts might have to move out of the area for critical family reasons. Tom is still very confident that with some staff rearrangements, assistance from a subcontractor, and some “hands on” activities on his part he can still meet the original delivery date, based on 149 days.

This news is very disconcerting to the committee and the sales staff. At this point, the committee decides that based on the most recent delivery performance of AET, a modified, comfortable delivery date should be communicated to AET cli- ents—one that Tom and his staff are very likely to meet. Consequently, Tom is asked to calculate what the expected project duration would have to be to ensure a 98 percent chance of completion within 160 days—that is a “published, drop dead date” that can be communicated to the clients.

250

Scheduling Resources and Costs

OUTLINE 8.1 Overview of the Resource Scheduling Problem

8.2 Types of Resource Constraints

8.3 Classification of a Scheduling Problem

8.4 Resource Allocation Methods

8.5 Computer Demonstration of Resource- Constrained Scheduling

8.6 Splitting Activities

8.7 Benefits of Scheduling Resources

8.8 Assigning Project Work

8.9 Multiproject Resource Schedules

8.10 Using the Resource Schedule to Develop a Project Cost Baseline

Summary

Appendix 8.1: The Critical-Chain Approach

LEARNING OBJECTIVES After reading this chapter you should be able to:

8-1 Understand the differences between time- constrained and resource-constrained schedules.

8-2 Identify different types of resource constraints.

8-3 Describe how the smoothing approach is used on time-constrained projects.

8-4 Describe how leveling approach is used for resource-constrained projects.

8-5 Understand how project management soft- ware creates resource-constrained schedules.

8-6 Understand when and why splitting tasks should be avoided.

8-7 Identify general guidelines for assigning people to specific tasks.

8-8 Identify common problems with multiproject resource scheduling.

8-9 Explain why a time-phased budget baseline is needed.

8-10 Create a time-phased project budget baseline.

C H A P T E R E I G H T

8

251

Project network times are not a schedule until resources have been assigned. Cost estimates are not a budget until they have been time-phased.

We have consistently stressed that up-front planning results in big payoffs. For those who have diligently worked through the earlier planning processes chapters, you are nearly ready to launch your project. This chapter completes the final two planning tasks that become the master plan for your project—resource and cost scheduling. (See Figure 8.1.) This process uses the resource schedule to assign time-phased costs that provide the project budget baseline. Given this time-phased baseline, comparisons can be made with actual and planned schedule and costs. This chapter first discusses the process for developing the project resource schedule. This resource schedule will be used to assign the time-phased budgeted values to create a project budget baseline. There are always more project proposals than there are available resources. The priority system needs to select projects that best contribute to the organization’s objec- tives, within the constraints of the resources available. If all projects and their respec- tive resources are computer scheduled, the feasibility and impact of adding a new project to those in process can be quickly assessed. With this information the project

Project networks

6

Managing risk 7

Monitoring progress

13

Teams 11

Outsourcing 12

Project manager

10

Strategy 2

Introduction 1

Organization 3

Schedule resources & costs

8

Intern ation

al

proje cts

15

Agile PM 16

Project closure

14

Estimate 5

Reducing duration

9

Define project

4

252 Chapter 8 Scheduling Resources and Costs

priority team will add a new project only if resources are available. This chapter exam- ines methods of scheduling resources so the team can make realistic judgments of resource availability and project durations. The project manager uses the same sched- ule for implementing the project. If changes occur during project implementation, the computer schedule is easily updated and the effects easily assessed.

8.1 Overview of the Resource Scheduling Problem After staff and other resources were assigned to her project, a project manager listed the following questions that still needed to be addressed: ∙ Will the assigned labor and/or equipment be adequate and available to deal with my

project? ∙ Will outside contractors have to be used? ∙ Do unforeseen resource dependencies exist? Is there a new critical path? ∙ How much flexibility do we have in using resources? ∙ Is the original deadline realistic? Clearly, this project manager has a good understanding of the problems she is facing. Any project scheduling system should facilitate finding quick, easy answers to these questions. The planned network and activity project duration times found in previous chapters fail to deal with resource usage and availability. The time estimates for the work pack- ages and network times were made independently with the implicit assumption that resources would be available. This may or may not be the case. If resources are adequate but the demand varies widely over the life of the project, it may be desirable to even out resource demand by delaying noncritical activities (using slack) to lower peak demand and, thus, increase resource utilization. This pro- cess is called resource smoothing. On the other hand, if resources are not adequate to meet peak demands, the late start of some activities must be delayed, and the duration of the project may be increased. This process is called resource-constrained scheduling. One research study of more than 50 projects by Woodworth and Willie (1975) found that planned project network durations were increased 38 percent when resources were scheduled. The consequences of failing to schedule limited resources are costly and project delays usually manifest themselves midway in the project when quick corrective action is difficult. An additional consequence of failing to schedule resources is ignoring the peaks and valleys of resource usage over the duration of the project. Because project resources are usually overcommitted and because resources seldom line up by avail- ability and need, procedures are needed to deal with these problems. This chapter

Understand the differ- ences between time- constrained and resource-constrained schedules.

8-1LO

FIGURE 8.1 Project Planning Process

Scope/WBS Network

Risk

Resource and Cost Scheduling Master Plan

Chapter 8 Scheduling Resources and Costs 253

FIGURE 8.2 Constraint Examples Technical constraints

(A)

Resource constraints

Plan(C) Hire band Decoratehall Purchase

refreshments

Plan(B) Decoratehall

Purchase refreshments

Hire band

Reception

Reception

Pour

Code

Frame

Test

Roof

Design

End

End

Start

Start

addresses methods available to project managers for dealing with resource utilization and availability through resource leveling and resource-constrained scheduling. Up to now the start and sequence of activities has been based solely on technical or logical considerations. For example, a project network for framing a house might show three activities in a sequence: (1) pour foundation, (2) build frame, and (3) cover roof. A network for a new software project could place the activities in the network, as a sequence of (1) design, (2) code, and (3) test. In other words, you cannot logically perform activity 2 until 1 is completed, and so on. The project network depicts techni- cal constraints (see Figure 8.2A). The network assumes the personnel and equipment are available to perform the required work. This is often not the case! The absence or shortage of resources can drastically alter technical constraints. A proj- ect network planner may assume adequate resources and show activities occurring in parallel. However, parallel activities hold potential for resource conflicts. For example, assume you are planning a wedding reception that includes four activities—(1) plan, (2) hire band, (3) decorate hall, and (4) purchase refreshments. Each activity takes one day. Activities 2, 3, and 4 could be done in parallel by different people. There is no technical reason or dependency of one on another (see Figure 8.2B). However, if one person must perform all activities, the resource constraint requires the activities be performed in sequence or series. Clearly the consequence is a delay of these activities and a very differ- ent set of network relationships (see Figure 8.2C). Note that the resource dependency takes priority over the technological dependency but does not violate the technological depen- dency; that is, hire, decorate, and purchase may now have to take place in sequence rather than concurrently, but they must all be completed before the reception can take place. The interrelationships and interactions among time and resource constraints are complex for even small project networks. Some effort to examine these interactions before the project begins frequently uncovers surprising problems. Project managers

254 Chapter 8 Scheduling Resources and Costs

In rare situations, physical factors cause activities that would normally occur in parallel to be constrained by contractual or environmental conditions. For example, in theory

the renovation of a sailboat compartment might involve four to five tasks that can be done indepen- dently. However, since space allows only one person to work at one time, all tasks have to be performed sequentially. Likewise, on a mining project it may be physically possible for only two miners to work in a shaft at a time. Another example would be the erec- tion of a communication tower and nearby ground- work. For safety considerations, the contract prohib- its groundwork within 2,000 feet of the tower construction.

© Getty Images/iStockphoto

S N A P S H O T F R O M P R A C T I C E 8 . 1 Working in Tight Places

The procedures for handling physical factors are similar to those used for resource constraints.

who do not consider resource availability in moderately complex projects usually learn of the problem when it is too late to correct. A deficit of resources can significantly alter project dependency relationships, completion dates, and project costs. Project managers must be careful to schedule resources to ensure availability in the right quan- tities and at the right time. Fortunately, there are computer software programs that can identify resource problems during the early project planning phase when corrective changes can be considered. These programs only require activity resource needs and availability information to schedule resources. See the Snapshot from Practice 8.1: Working in Tight Places for a third constraint that impinges on project schedules.

8.2 Types of Resource Constraints Resources are people, equipment, and material that can be drawn on to accomplish something. In projects the availability or unavailability of resources will often influ- ence the way projects are managed.

1. People. This is the most obvious and important project resource. Human resources are usually classified by the skills they bring to the project—for example, programmer, mechanical engineer, welder, inspector, marketing director, supervisor. In rare cases some skills are interchangeable, but usually with a loss of productivity. The many dif- fering skills of human resources add to the complexity of scheduling projects.

2. Materials. Project materials cover a large spectrum: for example, chemicals for a scientific project, concrete for a road project, survey data for a marketing project.

Material availability and shortages have been blamed for the delay of many projects. When it is known that a lack of availability of materials is important and probable, materials should be included in the project network plan and schedule. For example, delivery and placement of an oil rig tower in a Siberian oil field has a very small time window during one summer month. Any delivery delay means a one-year, costly delay.

8-2LO Identify different types of resource constraints.

Chapter 8 Scheduling Resources and Costs 255

Another example in which material was the major resource scheduled was the resurfac- ing and replacement of some structures on the Golden Gate Bridge in San Francisco. Work on the project was limited to the hours between midnight and 5:00 a.m. with a penalty of $1,000 per minute for any work taking place after 5:00 a.m. Scheduling the arrival of replacement structures was an extremely important part of managing the five- hour work-time window of the project. Scheduling materials has also become impor- tant in developing products where time-to-market can result in loss of market share.

3. Equipment. Equipment is usually presented by type, size, and quantity. In some cases equipment can be interchanged to improve schedules, but this is not typical. Equip- ment is often overlooked as a constraint. The most common oversight is to assume the resource pool is more than adequate for the project. For example, if a project needs one earthmoving tractor six months from now and the organization owns four, it is common to assume the resource will not delay the pending project. However, when the earthmov- ing tractor is due on-site in six months, all four machines in the pool might be occupied on other projects. In multiproject environments it is prudent to use a common resource pool for all projects. This approach forces a check of resource availability across all proj- ects and reserves the equipment for specific project needs in the future. Recognition of equipment constraints before the project begins can avoid high crashing or delay costs.

8.3 Classification of a Scheduling Problem Most of the scheduling methods available today require the project manager to classify the project as either time constrained or resource constrained. Project managers need to con- sult their priority matrix (see Figure 4.2) to determine which case fits their project. One simple test to determine if the project is time or resource constrained is to ask, “If the criti- cal path is delayed, will resources be added to get back on schedule?” If the answer is yes, assume the project is time constrained; if no, assume the project is resource constrained. A time-constrained project is one that must be completed by an imposed date. If required, resources can be added to ensure the project is completed by a specific date. Although time is the critical factor, resource usage should be no more than is necessary and sufficient. A resource-constrained project is one that assumes the level of resources avail- able cannot be exceeded. If the resources are inadequate, it will be acceptable to delay the project, but as little as possible. In scheduling terms, time constrained means time (project duration) is fixed and resources are flexible, while resource constrained means resources are fixed and time is flexible. Methods for scheduling these projects are presented in the next section.

8.4 Resource Allocation Methods

Assumptions Ease of demonstrating the allocation methods available requires some limiting assump- tions to keep attention on the heart of the problem. The rest of the chapter depends entirely on the assumptions noted here. First, splitting activities will not be allowed. This means once an activity is placed in the schedule, assume it will be worked on continuously until it is finished; hence, an activity cannot be started, stopped for a period of time, and then finished. Second, the level of resources used for an activity cannot be changed. These limiting assumptions do not exist in practice, but simplify learning. It is easy for new project managers to deal with the reality of splitting activi- ties and changing the level of resources when they meet them on the job.

256 Chapter 8 Scheduling Resources and Costs

Time-Constrained Projects: Smoothing Resource Demand Scheduling time-constrained projects focuses on resource utilization. When demand for a specific resource type is erratic, it is difficult to manage, and utilization may be very poor. Practitioners have attacked the utilization problem using resource leveling techniques that balance demand for a resource. Basically, all leveling techniques delay noncritical activities by using positive slack to reduce peak demand and fill in the val- leys for the resources. An example will demonstrate the basic procedure for a time- constrained project. See Figure 8.3. For the purpose of demonstration, the Botanical Garden project uses only one resource (backhoes); all backhoes are interchangeable. The top bar chart shows the activities on a time scale. The dependencies are shown with the vertical connecting

8-3LO Describe how the smoothing approach is used on time- constrained projects.

FIGURE 8.3 Botanical Garden

0

Design

Layout & scarify

Walkways

Lighting

Number of backhoes required

Smoothed number of backhoes required

Irrigation

Fence & walls

Planting

2 4 6 8 10 12 14 16 18 20 22 24 26 28 30

0

4

1 Bh

1 Bh

1 Bh

1 Bh

2 Bh2 Bh 1 Bh

1 Bh

3 Bh

2 Bh 3 Bh2 Bh

3

2

1

4

3

2

1

2 4 6 8 10 12 14 16 18 20 22 24 26 28 30

0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30

1 Bh

2 Bh

1 Bh

3 Bh

1 Bh

2 Bh

Chapter 8 Scheduling Resources and Costs 257

arrows. The horizontal arrows following activities represent activity slack (for example, irrigation requires six days to complete and has six days slack). The number of backhoes needed for each task is shown in the shaded activity duration block (rectangle). After the land has been scarified and the plan laid out, work can begin on the walkways, irriga- tion, and fencing and retaining walls simultaneously. The middle chart shows the resource profile for the backhoes. For periods 4 through 10, four backhoes are needed. Because this project is declared time constrained, the goal will be to reduce the peak requirement for the resource and thereby increase the utilization of the resource. A quick examination of the ES (early start) resource load chart suggests only two activi- ties have slack that can be used to reduce the peak—fence and walls provide the best choice for smoothing the resource needs. Another choice could be irrigation, but it would result in an up and down resource profile. The choice will probably center on the activity that is perceived as having the least risk of being late. The smoothed resource loading chart shows the results of delaying the fence and walls activity. Note the differ- ences in the resource profiles. The important point is the resources needed over the life of the project have been reduced from four to three (25 percent). In addition the profile has been smoothed, which should be easier to manage. The Botanical Garden project schedule reached the three goals of smoothing: ∙ The peak of demand for the resource was reduced. ∙ The number of resources over the life of the project have been reduced. ∙ The fluctuations in resource demand were minimized. The latter improves the utilization of resources. Backhoes are not easily moved from location to location. There are costs associated with changing the level of resources needed. The same analogy applies to the movement of people back and forth among projects. It is well known that people are more efficient if they can focus their effort on one project rather than multitasking their time among, say, three projects. The downside of leveling is a loss of flexibility that occurs from reducing slack. The risk of activities delaying the project also increases because slack reduction can create more critical activities and/or near-critical activities. Pushing leveling too far for a perfectly level resource profile is risky. Every activity then becomes critical. The Botanical Garden example gives a sense of the time-constrained problem and the smoothing approach. However, in practice the magnitude of the problem is very complex for even small projects. Manual solutions are not practical. Fortunately, the software packages available today have very good routines for leveling project resources. Typically, they use activities that have the most slack to level project resources. The rationale is those activities with the most slack pose the least risk. Although this is generally true, other risk factors such as reduction of flexibility to use reassigned resources on other activities or the nature of the activity (easy, com- plex) are not addressed using such a simple rationale. It is easy to experiment with many alternatives to find the one that best fits your project and minimizes risk of delaying the project.

Resource-Constrained Projects When the number of people and/or equipment is not adequate to meet peak demand requirements and it is impossible to obtain more, the project manager faces a resource- constrained problem. Something has to give. The trick is to prioritize and allocate resources to minimize project delay without exceeding the resource limit or altering the technical network relationships.

8-4LO Describe how leveling approach is used for resource-constrained projects.

258 Chapter 8 Scheduling Resources and Costs

The resource scheduling problem is a large combinatorial one. This means even a modest-size project network with only a few resource types might have several thou- sand feasible solutions. A few researchers have demonstrated optimum mathematical solutions to the resource allocation problem but only for small networks and very few resource types (Arrow and Hurowicz, 1977; Talbot and Patterson, 1979; Woodworth and Shanahan, 1988). The massive data requirements for larger problems make pure mathematical solutions (e.g., linear programming) impractical. An alternative approach to the problem has been the use of heuristics (rules of thumb) to solve large combinatorial problems. These practical decision or priority rules have been in place for many years. Heuristics do not always yield an optimal schedule, but they are very capable of yielding a “good” schedule for very complex networks with many types of resources. The efficiency of different rules and combinations of rules has been well documented (Pascoe, 1965; Fendly, 1968; Davis and Patterson, 1975). However, because each proj- ect is unique, it is wise to test several sets of heuristics on a network to determine the priority allocation rules that minimize project delay. The computer software available today makes it very easy for the project manager to create a good resource schedule for the project. A simple example of the heuristic approach is illustrated here. Heuristics allocate resources to activities to minimize project delay; that is, heuris- tics prioritize which activities are allocated resources and which activities are delayed when resources are not adequate. The parallel method is the most widely used approach to apply heuristics, which have been found to consistently minimize project delay over a large variety of projects. The parallel method is an iterative process that starts from the beginning of project time and, when resources needed exceed the resources available, retains activities first by the priority rules:

1. Minimum slack. 2. Smallest duration. 3. Lowest activity identification number.

Those not able to be scheduled without delaying others are pushed out farther in time. However, do not attempt to move activities that have already started. When consider- ing activities not to delay, consider the resources each activity uses. In any period when two or more activities require the same resource, the priority rules are applied. For example, if in period 5 three activities are eligible to start (i.e., have the same ES) and require the same resource, the first activity placed in the schedule would be the activity with the least slack (rule 1). However, if all activities have the same slack, the next rule would be invoked (rule 2), and the activity with the smallest duration would be placed in the schedule first. In very rare cases, when all eligible activities have the same slack and the same duration, the tie is broken by the lowest activity identification number (rule 3), since each activity has a unique ID number. When a resource limit has been reached, the early start (ES) for succeeding activi- ties not yet in the schedule will be delayed (and all successor activities not having free slack) and their slack reduced. In subsequent periods the procedure is repeated until the project is scheduled. The procedure is demonstrated next; see Figure 8.4. The shaded areas in the resource loading chart represent the “scheduling interval” of the time- constrained schedule (ES through LF). You can schedule the resource any place within the interval and not delay the project. Scheduling the activity beyond the LF will delay the project.

Chapter 8 Scheduling Resources and Costs 259

Period Action

See Figure 8.4

0–1 Only activity 1 is eligible. It requires 2 programmers. Load activity 1 into schedule. 1–2 No activities are eligible to be scheduled. 2–3 Activities 2, 3, and 4 are eligible to be scheduled. Activity 3 has the least slack (0)—

apply rule 1. Load Activity 3 into schedule. Activity 2 is next with slack of 2; however, activity 2 requires 2 programmers and only 1 is available. Delay activity 2. Update: ES = 3, slack = 1. The next eligible activity is activity 4, since it only requires 1 programmer. Load activity 4 into schedule.

See Figure 8.5

3–4 Activity 2 is eligible but exceeds limit of 3 programmers in pool. Delay activity 2. Update: ES = 4, slack = 0. 4–5 Activity 2 is eligible but exceeds limit of 3 programmers in pool. Delay activity 2. Update: ES = 5, LF = 11, slack = −1. Delay activity 7. Update: ES = 11, LF = 13, slack = −1. 5–6 Activity 2 is eligible but exceeds limit of 3 programmers in pool. Delay activity 2. Update: ES = 6, LF = 12, slack = −2. Delay activity 7. Update: ES = 12, LF = 14, slack = −2. 6–7 Activities 2, 5, and 6 are eligible with slack of −2, 2, and 0, respectively. Load activity 2 into schedule (rule 1). Because activity 6 has 0 slack, it is the next eligible activity. Load activity 6 into schedule (rule 1). The programmer limit of 3 is reached. Delay activity 5. Update: ES = 7, slack = 1. 7–8 Limit is reached. No programmers available. Delay activity 5. Update: ES = 8, slack = 0. 8–9 Limit is reached. No programmers available. Delay activity 5. Update: ES = 9, LF = 11, slack = −1. 9–10 Limit is reached. No programmers available. Delay activity 5. Update: ES = 10, LF = 12, slack = −2. 10–11 Activity 5 is eligible.

Load activity 5 into schedule. (Note: Activity 6 does not have slack because there are no programmers available— 3 maximum.) 11–12 No eligible activities. 12–13 Activity 7 is eligible.

Load activity 7 into schedule.

The Parallel Method:

The programmers are limited to three. Follow the actions described in Figures 8.4 and 8.5. Note how the limit of three programmers starts to delay the project. Observe how it is necessary to update each period to reflect changes in activity early start and slack times so the heuristics can reflect changing priorities. When using the parallel scheduling method, the network in Figure 8.5 reflects the new schedule date of 14 time units, rather than the time-constrained project duration of 12 time units. The network has also been revised to reflect new start, finish, and slack times for each activity. Note that activity 6 is still critical and has a slack of 0 time units because no resources are available (they are being used on activities 2 and 5). Compare the slack

260 Chapter 8 Scheduling Resources and Costs

1

20

0

2

DUR ES LF SL

ES resource load chart

0 1 2 3 4 5 6 7 8 9 10 11 12ID RES

2 0 2 01 22

2P

6 2 10 22 2 2 2 2 2 2

4 2 6 03 2 2 2 2

2 2 10 64 1 1

2 6 10 25 1 1

4 6 10 06 1 1 1 1

2 10 12 07 1 1

Total resource load 2P 5P 5P 4P 4P 4P 4P 1P 1P 1P 1P

0 2

2P 0

3

42

0

6

2 6

2P 0

2

64

2

10

2 8

2P 2

4

28

6

10

2 4

1P 6

5

28

2

10

6 8

1P 2

6

46

0

10

6 10

1P 0

7

210

0

12

10 12

1P 0

ID

DURLS

SL

LF

ES EF

RES

Legend

SL

DUR ES LF SL

Resource-constrained schedule through period 2–3

0 1 2 3 4 5 6 7 8 9 10 11 12

13

13

14

14ID RES

2 0 2 01 22

2P

6 2 10 23 12 X

4 2 6 03 2 2 2 2

2 2 10 64 1 1

2 6 10 25

4 6 10 06

2 10 12 07

Total resource load 2P 3P 3P 2P 2P

3PResource available 3P 3P 3P 3P 3P 3P 3P 3P 3P 3P 3P

2P

2P

2P

1P

1P

1P

1P

2P

2P

2P

1P

1P

1P

1P

FIGURE 8.4 Resource-Constrained Schedule through Period 2–3

Chapter 8 Scheduling Resources and Costs 261

DUR ES LF SL 0 1 2 3 4 5 6 7 8 9 10 11 12ID RES

2 0 2 01 22

2P

6 2 3 45 6 2 1 0 -1 -22 X X X X

4 2 6 03 2 2 2 2

2 2 10 64 1 1

2 6 10 25

4 6 10 06

2 12 14 -27 X X

Total resource load 2P 3P 3P 2P 2P

3PResource available 3P 3P 3P 3P 3P 3P 3P 3P 3P 3P 3P

1

20

0

2

0 2

2P 0

3

42

0

6

2 6

2P 0

2

66

0

12

6 12 New, resource scheduled network

2P 0

4

24

2

6

2 4

1P 2

5

210

0

12

10 12

1P 0

6

46

0

10

6 10

1P 0

7

212

0

14

12 14

1P 0

ID

DURLS

SL

LF

ES EF

RES

Legend

SL

DUR ES LF SL

Final resource-constrained schedule

Resource-constrained schedule through period 5–6

0 1 2 3 4 5 6 7 8 9 10 11 12

13

13

14

14ID RES

2 0 2 01 22

2P

6 2-1 1 -2

02 X

4 2 6 03 2 2 2 2

SL SL

X X X 2 2 2 2

X X X X

1 1 1 1

2 2

X X

1 1

2 2 6 6 24 1 1

2 2 1 0-1 -25

4 6 10 06

2 0 -1-27

2P 3P 3P 2P 2P 3P 3P 3P 3P 3P 3P 1P 1P

1 1

3P 3P 3P 3P 3P 3P 3P 3P 3P 3P 3P 3P 3P 3P

0 -112 13

12 13 14

10 11 12

10 11

12 10 11

10 11 12

10 11 12

2 3 4 5 6

Total resource load

Resource available

6 7 8 9 10

2P

2P

2P

1P

1P

1P

1P

2P

2P

2P

1P

1P

1P

1P

FIGURE 8.5 Resource-Constrained Schedule through Period 5–6

262 Chapter 8 Scheduling Resources and Costs

for each activity found in Figures 8.4 and 8.5; slack has been reduced significantly. Note that activity 4 has only 2 units of slack rather than what appears to be 6 slack units. This occurs because only three programmers are available, and they are needed to satisfy the resource requirements of activities 2 and 5. Note that the number of criti- cal activities (1, 2, 3, 5, 6, 7) has increased from four to six. This small example demonstrates the scenario of scheduling resources in real proj- ects and the resulting increase in the risk of being late. In practice this is not a trivial problem! Managers who fail to schedule resources usually encounter this scheduling risk when it is too late to work around the problem, resulting in a project delay. Since manually using the parallel method is impractical on real-world projects because of size, project managers will depend on software programs to schedule project resources.

8.5 Computer Demonstration of Resource-Constrained Scheduling Fortunately, project management software is capable of assessing and resolving com- plicated resource-constrained schedules using heuristics similar to what was described above. We will use the EMR project to demonstrate how this is done using MS Project. It is important to note that the software is not “managing” the project. The software is simply a tool the project manager uses to view the project from different perspectives and conditions. See Snapshot from Practice 8.2: Assessing Resource Allocation for more tips on assessing resource problems.

Understand how project management software creates resource- constrained schedules.

8-5LO

One of the strengths of today’s project management software is the ability to identify and provide options for resolv- ing resource allocation problems. A project manager who uses MS Project

to plan projects shared with us the following checklist for dealing with resource conflicts after preliminary assignment of resources has been made.

1. Assess whether you have overallocation problems (see Red in the resource sheet view).

2. Identify where and when conflicts occur by examin- ing the resource usage view.

3. Resolve the problem by

a. Replacing overallocated resources with appro- priate resources that are available. Then ask if this solves the problem.

If not:

b. Use the leveling tool and choose the level within slack option.

i. Does this solve the problem? (Are resources still overallocated?)

ii. Check the sensitivity of the network and ask if this is acceptable.

If not:

c. Consider splitting tasks.

i. Make sure to readjust task durations to take into account additional start-up and shut- down time.

4. If 3 does not work then either:

a. Use level tool default option and ask if you can live with the new completion date.

If not:

b. Negotiate for additional resources to complete the project. If not possible

c. Consider reducing project scope to meet deadline.

While this checklist makes specific references to MS Project, the same steps can be used with most project management software.

S N A P S H O T F R O M P R A C T I C E 8 . 2 Assessing Resource Allocation

Chapter 8 Scheduling Resources and Costs 263

EMR is the name given to the development of a handheld electronic medical refer- ence guide to be used by emergency medical technicians and paramedics. Figure 8.6 contains a time-limited network for the design phase of the project. For the purpose of this example, we assume that only design engineers are required for the tasks and that the design engineers are interchangeable. The number of engineers required to perform each task is noted in the network, where 500 percent means five design engineers are needed for the activity. For example, activity 5, feature specs, requires four design engineers (400 percent). The project begins January 1, and ends February 14, a duration of 45 workdays. The calendar for the project has been set up to work seven days a week so the reader can trace and more easily see the results and impacts of resources—similar to man- ual solutions present in chapter exercises. The time-limited (constrained) bar chart for the project is shown in Figure 8.7. This bar chart incorporates the same informa- tion used to develop the project network, but presents the project in the form of a bar chart along a time line. Finally, a resource usage chart is presented for a segment of the project—January 15 to January 23; see Figure 8.8A. Observe that the time-limited project requires 21 design engineers on January 18 and 19 (168 hrs/8 hrs per engineer = 21 engineers). This segment represents the peak requirement for design engineers for the project. However, due to the shortage of design engineers and commitments to other projects, only eight engineers can be assigned to the project. This creates overallocation prob- lems more clearly detailed in Figure 8.8B, which is a resource loading chart for design engineers. Notice that the peak is 21 engineers and the limit of 8 engineers is shown by the gray shaded area. To resolve this problem we use the “leveling” tool within the software and first try to solve the problem by leveling only within slack. This solution would preserve the original finish date. However, as expected, this does not solve all of the allocation problems. The next option is to allow the software to apply scheduling heuristics and level outside of slack. The new schedule is contained in the revised, resource-limited network chart presented in Figure 8.9. The resource-limited project network indicates the project duration has now been extended to 2/26, or 57 workdays (versus 45 days time limited). The critical path is now 2, 3, 9, 13. Figure 8.10 presents the project bar chart and the results of leveling the project schedule to reflect the availability of only eight design engineers. The application of the heuristics can be seen in the scheduling of the internal, external, and feature speci- fication activities. All three activities were originally scheduled to start immediately after activity 1, architectural decisions. This is impossible, since the three activities collectively require 14 engineers. The software chooses to schedule activity 5 first because this activity is on the original critical path and has zero slack (heuristic rule # 1). Next, and concurrently, activity 4 is chosen over activity 3 because activity 4 has a shorter duration (heuristic rule # 2); internal specs, activity 3, is delayed due to the limitation of 8 design engineers. Notice that the original critical path no longer applies because of the resource dependencies created by having only eight design engineers. See Figure 8.9 for the original planned critical path. Compare the bar chart in Figure 8.10 with the time-limited bar chart in Figure 8.7. For example, note the different start dates for activity 8 (screen). In the time-limited plan (Figure 8.7), the start date for activity 8 is 1/18, while the start date in the resource limited schedule (Figure 8.10) is 2/16, almost a month later!

264

A rc

hi te

ct ur

al d

ec is

io ns

St ar

t: 1

/1 Fi

ni sh

: 1 /5

Re s:

D es

ig n

En gi

ne er

s [5

00 %

]

ID :

2 D

ur : 5

d ay

s

EM R

p ro

je ct

St ar

t: 1

/1 Fi

ni sh

: 2 /1

4 C

om p:

0 %

ID :

1 D

ur : 4

5 da

ys

Ex te

rn al

s pe

cs St

ar t:

1 /6

Fi ni

sh : 1

/1 2

Re s:

D es

ig n

En gi

ne er

s [4

00 %

]

ID :

4 D

ur : 7

d ay

s

Fe at

ur e

sp ec

s St

ar t:

1 /6

Fi ni

sh : 1

/1 5

Re s:

D es

ig n

En gi

ne er

s [4

00 %

]

ID :

5 D

ur : 1

0 da

ys

In te

rn al

s pe

cs St

ar t:

1 /6

Fi ni

sh : 1

/1 7

Re s:

D es

ig n

En gi

ne er

s [5

00 %

]

ID :

3 D

ur : 1

2 da

ys

Sc re

en St

ar t:

1 /1

8 Fi

ni sh

: 1 /1

9 Re

s: D

es ig

n En

gi ne

er s

[3 00

% ]

ID :

8 D

ur : 2

d ay

s

D at

ab as

e St

ar t:

1 /1

6 Fi

ni sh

: 2 /9

Re s:

D es

ig n

En gi

ne er

s [4

00 %

]

ID :

9 D

ur : 2

5 da

ys

Re vi

ew d

es ig

n St

ar t:

2 /1

0 Fi

ni sh

: 2 /1

4 Re

s: D

es ig

n En

gi ne

er s

[5 00

% ]

ID :

13 D

ur : 5

d ay

s

M ic

ro ph

on e-

so un

dc ar

d St

ar t:

1 /1

6 Fi

ni sh

: 1 /2

0 Re

s: D

es ig

n En

gi ne

er s

[2 0

0% ]

ID :

10 D

ur : 5

d ay

s

D ig

ita l d

ev ic

es St

ar t:

1 /1

6 Fi

ni sh

: 1 /2

2 Re

s: D

es ig

n En

gi ne

er s

[3 00

% ]

ID :

11 D

ur : 7

d ay

s

C om

pu te

r I /O

St ar

t: 1

/1 6

Fi ni

sh : 1

/2 0

Re s:

D es

ig n

En gi

ne er

s [3

00 %

]

ID :

12 D

ur : 5

d ay

s

C as

e St

ar t:

1 /1

8 Fi

ni sh

: 1 /2

1 Re

s: D

es ig

n En

gi ne

er s

[2 0

0% ]

ID :

7 D

ur : 4

d ay

s

Vo ic

e re

co gn

iti on

S W

St ar

t: 1

/1 8

Fi ni

sh : 1

/2 7

Re s:

D es

ig n

En gi

ne er

s [4

00 %

]

ID :

6 D

ur : 1

0 da

ys

FI GU

RE 8

.6

EM R

P ro

je ct

N et

wo rk

V iew

S ch

ed ul

e b ef

or e R

es ou

rc es

L ev

el ed

265

ID 1 2 3 4 5 6 7 8 9 10 11 12 13

St ar

t Tu

e 1 /1

Tu e 1

/1 Su

n 1 /6

Su n 1

/6 Su

n 1 /6

Fr i 1/

18 Fr

i 1/ 18

Fr i 1/

18 W

ed 1/

16 W

ed 1/

16 W

ed 1/

16 W

ed 1/

16 Su

n 2 /10

Fin ish

Th u 2

/14 Sa

t 1 /5

Th u 1

/17 Sa

t 1 /12

Tu e 1

/15 Su

n 1 /2

7 Mo

n 1 /2

1 Sa

t 1 /19

Sa t 2

/9 Su

n 1 /2

0 Tu

e 1 /2

2 Su

n 1 /2

0 Th

u 2 /14

La te

S tar

t Tu

e 1 /1

Tu e 1

/1 Sa

t 1 /19

Th u 1

/2 4

Su n 1

/6 Th

u 1 /3

1 W

ed 2

/6 Fr

i 2 /8

W ed

1/ 16

Tu e 2

/5 Su

n 2 /3

Tu e 2

/5 Su

n 2 /10

La te

Fi nis

h Th

u 2 /14

Sa t 1

/5 W

ed 1/

30 W

ed 1/

30 Tu

e 1 /15

Sa t 2

/9 Sa

t 2 /9

Sa t 2

/9 Sa

t 2 /9

Sa t 2

/9 Sa

t 2 /9

Sa t 2

/9 Th

u 2 /14

Fr ee

S lac

k 0

da ys

0 da

ys 0

da ys

5 da

ys 0

da ys

13 d

ay s

19 d

ay s

21 d

ay s

0 da

ys 20

d ay

s 18

d ay

s 20

d ay

s 0

da ys

To tal

S lac

k 27

Ja nu

ary

0 da

ys 0

da ys

13 d

ay s

18 d

ay s

0 da

ys 13

d ay

s 19

d ay

s 21

d ay

s 0

da ys

20 d

ay s

18 d

ay s

20 d

ay s

0 da

ys

Ta sk

N am

e EM

R pr

oje ct

Ar ch

ite ctu

ra l d

ec isi

on s

Int er

na l s

pe cs

Ex te

rn al

sp ec

s Fe

atu re

sp ec

s Vo

ice re

co gn

itio n S

W Ca

se Sc

re en

Da tab

as e

Mi cro

ph on

e- so

un dc

ar d

Di git

al de

vic es

Co mp

ut er

I/O Re

vie w

de sig

n

29 31

2 4

6 8

10 12

14 16

18 20

22 24

26 28

30 1

3 5

7 9

11 13

15 Fe

br ua

ry

Su m

m ar

y

Ta sk

Sl ac

k

Cr iti

ca l t

as k

FI GU

RE 8

.7

EM R

P ro

je ct

b ef

or e R

es ou

rc es

A dd

ed

266 Chapter 8 Scheduling Resources and Costs

While resource bar graphs are commonly used to illustrate overallocation problems, we prefer to view resource usage tables like the one presented in Figure 8.8A. This table tells you when you have an overallocation problem and identifies activities that are causing the overallocation. The Impacts of Resource-Constrained Scheduling Like leveling schedules, the limited resource schedule usually reduces slack, reduces flexibility by using slack to ensure delay is minimized, and increases the number of critical and near-critical activities. Scheduling complexity is increased because resource constraints are added to technical constraints; start times may now have two constraints. The traditional critical path concept of sequential activities from the start to the end of the project is no longer meaningful. The resource constraints can break the sequence and leave the network with a set of disjointed critical activities.1

3,024 hrs 200 hrs 480 hrs 224 hrs 320 hrs 320 hrs

64 hrs 48 hrs

800 hrs 80 hrs

168 hrs 120 hrs

200 hrs

T 72h

40h

32h

136h

40h

32h 16h 24h 24h

136h

40h

32h 16h 24h 24h

168h

32h 16h 24h 32h 16h 24h 24h

168h

32h 16h 24h 32h 16h 24h 24h

900%Peak Units

Overallocated:Design Engineers Allocated:

2,500%

2,000%

1,500%

1,000%

500%

1,700% 1,700% 2,100% 2,100% 1,800% 1,300% 1,100% 800%

W T F S 144h

32h 16h

32h 16h 24h 24h

S 104h

32h 16h

32h

24h

M 88h

32h

32h

24h

T 64h

32h

32h

W Design engineers

Work Jan 15 Jan 21Resource Name

Architectural decisions Internal specs External specs Feature specs Voice recognition SW Case Screen Database Microphone-soundcard Digital devices Computer I/O Review design

FIGURE 8.8A EMR Project—Time-Constrained Resource Usage View, January 15–23

FIGURE 8.8B Resource Loading Chart for EMR Project, January 15–23

1 See the appendix at the end of this chapter for more on how resource constraints affect project schedule.

267

A rc

hi te

ct ur

al d

ec is

io ns

St ar

t: 1

/1 Fi

ni sh

: 1 /5

Re s:

D es

ig n

En gi

ne er

s [5

00 %

]

ID :

2 D

ur : 5

d ay

s

EM R

p ro

je ct

St ar

t: 1

/1 Fi

ni sh

: 2 /2

6 C

om p:

0 %

ID :

1 D

ur : 5

7 da

ys

Ex te

rn al

s pe

cs St

ar t:

1 /6

Fi ni

sh : 1

/1 2

Re s:

D es

ig n

En gi

ne er

s [4

00 %

]

ID :

4 D

ur : 7

d ay

s

Fe at

ur e

sp ec

s St

ar t:

1 /6

Fi ni

sh : 1

/1 5

Re s:

D es

ig n

En gi

ne er

s [4

00 %

]

ID :

5 D

ur : 1

0 da

ys

In te

rn al

s pe

cs St

ar t:

1 /1

6 Fi

ni sh

: 1 /2

7 Re

s: D

es ig

n En

gi ne

er s

[5 00

% ]

ID :

3 D

ur : 1

2 da

ys

Sc re

en St

ar t:

2 /1

6 Fi

ni sh

: 2 /1

7 Re

s: D

es ig

n En

gi ne

er s

[3 00

% ]

ID :

8 D

ur : 2

d ay

s

D at

ab as

e St

ar t:

1 /2

8 Fi

ni sh

: 2 /2

1 Re

s: D

es ig

n En

gi ne

er s

[4 00

% ]

ID :

9 D

ur : 2

5 da

ys

Re vi

ew d

es ig

n St

ar t:

2 /2

2 Fi

ni sh

: 2 /2

6 Re

s: D

es ig

n En

gi ne

er s

[5 00

% ]

ID :

13 D

ur : 5

d ay

s

M ic

ro ph

on e-

so un

dc ar

d St

ar t:

1 /1

6 Fi

ni sh

: 1 /2

0 Re

s: D

es ig

n En

gi ne

er s

[2 00

% ]

ID :

10 D

ur : 5

d ay

s

D ig

ita l d

ev ic

es St

ar t:

1 /2

6 Fi

ni sh

: 2 /1

Re s:

D es

ig n

En gi

ne er

s [3

00 %

]

ID :

11 D

ur : 7

d ay

s

C om

pu te

r I /O

St ar

t: 1

/2 1

Fi ni

sh : 1

/2 5

Re s:

D es

ig n

En gi

ne er

s [3

00 %

]

ID :

12 D

ur : 5

d ay

s

C as

e St

ar t:

2 /1

2 Fi

ni sh

: 2 /1

5 Re

s: D

es ig

n En

gi ne

er s

[2 00

% ]

ID :

7 D

ur : 4

d ay

s

Vo ic

e re

co gn

iti on

S W

St ar

t: 2

/2 Fi

ni sh

: 2 /1

1 Re

s: D

es ig

n En

gi ne

er s

[4 00

% ]

ID :

6 D

ur : 1

0 da

ys

FI GU

RE 8

.9

EM R

P ro

je ct

N et

wo rk

V iew

S ch

ed ul

e a fte

r R es

ou rc

es L

ev el

ed

268

ID 1 2 3 4 5 6 7 8 9 10 11 12 13

Sta rt

Tu e 1

/1 Tu

e 1 /1

We d 1

/16 Su

n 1 /6

Su n 1

/6 Sa

t 2 /2

Tu e 2

/12 Sa

t 2 /16

Mo n 1

/28 We

d 1 /16

Sa t 1/

26 Mo

n 1 /21

Fri 2/

22

Fin ish

Th u 2

/26 Sa

t 1/ 5

Su n 1

/27 Sa

t 1/ 12

Tu e 1

/15 Mo

n 2 /11

Fri 2/

15 Su

n 2 /17

Th u 2

/21 Su

n 1 /20

Fri 2/

1 Fri

1/2 5

Tu e 2

/26

La te

Sta rt

Tu e 1

/1 Tu

e 1 /1

Su n 1

/20 Fri

1/2 5

Su n 1

/6 Tu

e 2 /12

Mo n 2

/18 We

d 2 /20

Mo n 1

/28 Su

n 2 /17

Fri 2/

15 Su

n 2 /17

Fri 2/

22

La te

Fin ish

Tu e 2

/26 Sa

t 1/ 5

Th u 1

/31 Th

u 1 /31

Tu e 1

/15 Th

u 2 /21

Th u 2

/21 Th

u 2 /21

Th u 2

/21 Th

u 2 /21

Th u 2

/21 Th

u 2 /21

Tu e 2

/26

Fre e S

lac k

0 d ay

s 0 d

ay s

0 d ay

s 15

da ys

0 d ay

s 10

da ys

6 d ay

s 4 d

ay s

0 d ay

s 32

da ys

20 da

ys 27

da ys

0 d ay

s

To tal

Sl ac

k 27

Ja nu

ary

0 d ay

s 0 d

ay s

4 d ay

s 19

da ys

0 d ay

s 10

da ys

6 d ay

s 4 d

ay s

0 d ay

s 32

da ys

20 da

ys 27

da ys

0 d ay

s

Ta sk

N am

e EM

R p roj

ec t

Ar ch

ite ctu

ral de

cis ion

s Int

ern al

sp ec

s Ex

ter na

l s pe

cs Fe

atu re

sp ec

s Vo

ice re

co gn

itio n S

W Ca

se Sc

ree n

Da tab

as e

Mi cro

ph on

e-s ou

nd ca

rd Di

git al

de vic

es Co

mp ute

r I/ O

Re vie

w de

sig n

29 31

2 4

6 8

10 12

14 16

18 20

22 24

26 28

30 1

3 5

7 9

11 13

15 17

19 21

23 25

27 Fe

bru ary

Su m

m ar

y

Ta sk

Sl ac

k

Cr iti

ca l t

as k

5

4 4

4

4 4

2

3 3

2

5

5

FI GU

RE 8

.10

EM R

P ro

je ct

R es

ou rc

es L

ev el

ed

Chapter 8 Scheduling Resources and Costs 269

Conversely, parallel activities can become sequential. Activities with slack on a time- constrained network can change from critical to noncritical.

8.6 Splitting Activities Splitting tasks is a scheduling technique used to get a better project schedule and/or to increase resource utilization. A planner splits the continuous work included in an activity by interrupting the work and sending the resource to another activity for a period of time and then having the resource resume work on the original activity. Splitting can be a useful tool if the work involved does not include large start-up or shutdown costs—for example, moving equipment from one activity location to another. The most common error is to interrupt “people work,” where there are high conceptual start-up and shutdown costs. For example, having a bridge designer take time off to work on the design problem of another project may cause this individual to lose four days shifting conceptual gears in and out of two activities. The cost may be hidden, but it is real. Figure 8.11 depicts the nature of the splitting problem. The original activity has been split into three separate activities: A, B, and C. The shut- down and start-up times lengthen the time for the original activity. One study reported that task switching can cost from 20 percent to 40 percent loss in efficiency (Rubin- stein, Meyer, and Evans, 2001). Some have argued that the propensity to deal with resource shortages by splitting is a major reason why projects fail to meet schedule (c.f., Goldratt, 1997; Newbold, 1997). We agree. Planners should avoid the use of splitting as much as possible, except in situations where splitting costs are known to be small or when there is no alternative for resolving the resource problem. Computer software offers the splitting option for each activity; use it sparingly. See Snapshot from Practice 8.2: Assessing Resource Allocation.

Understand when and why splitting tasks should be avoided.

8-6LO

Activity duration without splitting

Activity duration split into three segments—A, B, C

Activity A

Activity A

Activity B

Activity B

Activity C

Activity C

Activity duration split with shutdown and start-up

Shutdown Start-up

FIGURE 8.11 Splitting Activities

270 Chapter 8 Scheduling Resources and Costs

8.7 Benefits of Scheduling Resources It is important to remember that, if resources are truly limited and activity time esti- mates are accurate, the resource-constrained schedule will materialize as the project is implemented—not the time-constrained schedule! Therefore, failure to schedule lim- ited resources can lead to serious problems for a project manager. The benefit of creat- ing this schedule before the project begins leaves time for considering reasonable alternatives. If the scheduled delay is unacceptable or the risk of being delayed too high, the assumption of being resource constrained can be reassessed. Cost-time trade- offs can be considered. In some cases priorities may be changed. See Snapshot from Practice 8.3: U.S. Forest Service Resource Shortage. Resource schedules provide the information needed to prepare time-phased work package budgets with dates. Once established, they provide a quick means for a proj- ect manager to gauge the impact of unforeseen events such as turnover, equipment breakdowns, or transfer of project personnel. Resource schedules also allow project managers to assess how much flexibility they have over certain resources. This is use- ful when they receive requests from other managers to borrow or share resources. Honoring such requests creates goodwill and an “IOU” that can be cashed in during a time of need.

A major segment of work in managing U.S. Forest Service (USFS) forests is selling mature timber to logging com- panies that harvest the timber under contract conditions monitored by the

Service. The proceeds are returned to the federal gov- ernment. The budget allocated to each forest depends on the two-year plan submitted to the U.S. Department of Agriculture. Olympic Forest headquarters in Olympia, Washington, was developing a two-year plan as a basis for funding. All of the districts in the forest submitted their timber sale projects (numbering more than 50) to headquarters, where they were compiled and aggregated into a project plan for the whole forest. The first computer run was reviewed by a small group of senior managers to deter- mine if the plan was reasonable and “doable.” Manage- ment was pleased and relieved to note all projects appeared to be doable in the two-year time frame until a question was raised concerning the computer printout. “Why are all the columns in these projects labeled ‘RESOURCE’ blank?” The response from an engineer was, “We don’t use that part of the program.” The discussion that ensued recognized the impor- tance of resources in completing the two-year plan and ended with a request to “try the program with resources

© Seth Lazar/Alamy

S N A P S H O T F R O M P R A C T I C E 8 . 3 U.S. Forest Service Resource Shortage

included.” The new output was startling. The two-year program turned into a three-and-a-half-year plan because of the shortage of specific labor skills such as road engineer and environmental impact specialist. Analysis showed that adding only three skilled people would allow the two-year plan to be completed on time. In addition, further analysis showed hiring only a few more skilled people, beyond the three, would allow an extra year of projects to also be compressed into the two-year plan. This would result in additional revenue of more than $3 million. The Department of Agriculture quickly approved the requested extra dollars for addi- tional staff to generate the extra revenue.

Chapter 8 Scheduling Resources and Costs 271

8.8 Assigning Project Work When making individual assignments, project managers should match, as best they can, the demands and requirements of specific work with the qualifications and experi- ence of available participants. In doing so, there is a natural tendency to assign the best people the most difficult tasks. Project managers need to be careful not to overdo this. Over time these people may grow to resent the fact that they are always given the toughest assignments. At the same time, less experienced participants may resent the fact that they are never given the opportunity to expand their skill/knowledge base. Project managers need to balance task performance with the need to develop the tal- ents of people assigned to the project. Project managers not only need to decide who does what but who works with whom. A number of factors need to be considered in deciding who should work together. First, to minimize unnecessary tension, managers should pick people with compatible work habits and personalities but who complement each other (i.e., one person’s weakness is the other person’s strength). For example, one person may be bril- liant at solving complex problems but sloppy at documenting his or her progress. It would be wise to pair this person with an individual who is good at paying attention to details. Experience is another factor. Veterans should be teamed up with new hires— not only so they can share their experience but also to help socialize the newcomers to the customs and norms of the organization. Finally, future needs should be considered. If managers have some people who have never worked together before but who have to later on in the project, they may be wise to take advantage of opportunities to have these people work together early on so that they can become familiar with each other. Finally, see the Snapshot in Practice 8.4: Managing Geeks for some interesting thoughts from the former CEO of Google on how to put together teams.

Identify general guidelines for assigning people to specific tasks.

8-7LO

Eric Schmidt, after a successful career at Sun Microsystems, took over strug- gling Novell, Inc., and helped turn it around within two years. Four years later he became the CEO of Google.

One of the keys to his success is his ability to manage the technical wizards who develop the sophisticated systems, hardware, and software that are the back- bone of electronically driven companies. He uses the term “geek” (and he can, since he is one, with a Ph.D. in computer science) to describe this group of technol- ogists who rule the cyberworld. Schmidt has some interesting ideas about assign- ing geeks to projects. He believes that putting geeks together in project teams with other geeks creates pro- ductive peer pressure. Geeks care a great deal about how other geeks perceive them. They are good at judg- ing the quality of technical work and are quick to praise

as well as criticize each other’s work. Some geeks can be unbearably arrogant, but Schmidt claims that having them work together on projects is the best way to con- trol them—by letting them control each other. At the same time, Schmidt argues that too many geeks spoil the soup. By this he means that, when there are too many geeks on a development team, there is a tendency for intense technical navel gazing. Members lose sight of deadlines, and delays are inevitable. To combat this tendency, he recommends using geeks only in small groups. He urges breaking up large proj- ects into smaller, more manageable projects so that small teams of geeks can be assigned to them. This keeps the project on time and makes the teams respon- sible to each other.

*Russ Mitchel, “How to Manage Geeks,” Fast Company, May 31, 1999, pp. 175–80.

S N A P S H O T F R O M P R A C T I C E 8 . 4 Managing Geeks*

272 Chapter 8 Scheduling Resources and Costs

8.9 Multiproject Resource Schedules For clarity we have discussed key resource allocation issues within the context of a single project. In reality resource allocation generally occurs in a multiproject environ- ment where the demands of one project have to be reconciled with the needs of other projects. Organizations must develop and manage systems for efficiently allocating and scheduling resources across several projects with different priorities, resource requirements, sets of activities, and risks. The system must be dynamic and capable of accommodating new projects as well as reallocating resources once project work is completed. While the same resource issues and principles that apply to a single project also apply to this multiproject environment, application and solutions are more com- plex, given the interdependency among projects. The following lists three of the more common problems encountered in managing multiproject resource schedules. Note that these are macro manifestations of single- project problems that are now magnified in a multiproject environment:

1. Overall schedule slippage. Because projects often share resources, delays in one project can have a ripple effect and delay other projects. For example, work on one software development project can grind to a halt because the coders scheduled for the next critical task are late in completing their work on another development project.

2. Inefficient resource utilization. Because projects have different schedules and requirements, there are peaks and valleys in overall resource demands. For example, a firm may have a staff of 10 electricians to meet peak demands when, under normal conditions, only 5 electricians are required.

3. Resource bottlenecks. Delays and schedules are extended as a result of shortages of critical resources that are required by multiple projects. For example, at one Lattice Semiconductor facility, project schedules were delayed because of competition over access to test equipment necessary to debug programs. Likewise, several projects at a U.S. forest area were extended because there was only one silviculturist on the staff.

To deal with these problems, more and more companies create project offices or depart- ments to oversee the scheduling of resources across multiple projects. One approach to multiple project resource scheduling is to use a first come–first served rule. A project queue system is created in which projects currently under way take precedence over new projects. New project schedules are based on the projected availability of resources. This queuing tends to lead to more reliable completion estimates and is preferred on contracted projects that have stiff penalties for being late. The disadvantages of this deceptively sim- ple approach are that it does not optimally utilize resources or take into account the priority of the project. See the Snapshot from Practice 8.5: Multiple Project Resource Scheduling. Many companies utilize more elaborate processes for scheduling resources to increase the capacity of the organization to initiate projects. Most of these methods approach the problem by treating individual projects as part of one big project and adapting the sched- uling heuristics previously introduced to this “megaproject.” Project schedulers monitor resource usage and provide updated schedules based on progress and resource availabil- ity across all projects. One major improvement in project management software in recent years is the ability to prioritize resource allocation to specific projects. Projects can be prioritized in ascending order (e.g., 1, 2, 3, 4,…), and these priorities will override sched- uling heuristics so that resources go to the project highest on the priority list. (Note: This improvement fits perfectly with organizations that use project priority models similar to those described in Chapter 2.) Centralized project scheduling also makes it easier to identify resource bottlenecks that stifle progress on projects. Once identified, the impact

Identify common prob- lems with multiproject resource scheduling.

8-8LO

Chapter 8 Scheduling Resources and Costs 273

of the bottlenecks can be documented and used to justify acquiring additional equipment, recruiting critical personnel, or delaying the project. Finally, many companies are using outsourcing as a means for dealing with their resource allocation problems. In some cases, a company will reduce the number of proj- ects they have to manage internally to only core projects and outsource noncritical proj- ects to contractors and consulting firms. In other cases, specific segments of projects are outsourced to overcome resource deficiencies and scheduling problems. Companies may hire temporary workers to expedite certain activities that are falling behind schedule or contract project work during peak periods when there are insufficient internal resources to meet the demands of all projects. The ability to more efficiently manage the ebbs and flows of project work is one of the major driving forces behind outsourcing today.

8.10 Using the Resource Schedule to Develop a Project Cost Baseline Once resource assignments have been finalized we are able to develop a baseline bud- get schedule for the project. Using your project schedule, you can time-phase work packages and assign them to their respective scheduled activities to develop a budget schedule over the life of your project. Understanding the reason for time-phasing your budget is very important. Without a time-phased budget good project schedule and cost control are impossible.

Why a Time-Phased Budget Baseline Is Needed The need for a time-phased budget baseline is demonstrated in the following scenario. The development of a new product is to be completed in 10 weeks at an estimated cost

Explain why a time- phased budget baseline is needed.

8-9LO

The case for a central source to over- see project resource scheduling is well known by practitioners. Here is a syn- opsis of a conversation with one mid- dle manager.

Interviewer: Congratulations on acceptance of your multiproject scheduling proposal. Everyone tells me you were very convincing. Middle Manager: Thanks. Gaining acceptance was easy this time. The board quickly recognized we have no choice if we are to keep ahead of competition by placing our resources on the right projects. Interviewer: Have you presented this to the board before? Middle Manager: Yes, but not this company. I pre- sented the same spiel to the firm I worked for two years ago. For their annual review meeting I was charged to present a proposal suggesting the need and benefits of central capacity resource planning for managing the projects of the firm. I tried to build a case for bringing projects under one umbrella to standardize practices and to forecast

and assign key people to mission critical projects. I explained how benefits such as resource demands would be aligned with mission critical projects, proac- tive resource planning, and a tool for catching resource bottlenecks and resolving conflicts. Almost everyone agreed the idea was a good one. I felt good about the presentation and felt confi- dent something was going to happen. But the idea never really got off the ground; it just faded into the sunset. With hindsight, managers really did not trust col- leagues in other departments, so they only gave half- hearted support to central resource planning. Manag- ers wanted to protect their turf and ensure that they would not have to give up power. The culture there was simply too inflexible for the world we live in today. They are still struggling with constant conflicts among projects. I’m glad I made the switch to this firm. The culture here is much more team-oriented. Management is com- mitted to improving performance.

S N A P S H O T F R O M P R A C T I C E 8 . 5 Multiple Project Resource Scheduling

274 Chapter 8 Scheduling Resources and Costs

of $400,000 per week for a total cost of $4 million. Management wants a status report at the end of five weeks. The following information has been collected: ∙ Planned costs for the first five weeks are $2,000,000. ∙ Actual costs for the first five weeks are $2,400,000. How are we doing? It would be easy to draw the conclusion there is a $400,000 cost over- run. But we really have no way of knowing. The $400,000 may represent money spent to move the project ahead of schedule. Assume another set of data at the end of five weeks: ∙ Planned costs for the first five weeks are $2,000,000. ∙ Actual costs for the first five weeks are $1,700,000. Is the project costing $300,000 less than we expected? Perhaps. But the $300,000 may rep- resent the fact that the project is behind schedule and work has not started. Could it be the project is behind schedule and over cost? We cannot tell from these data. The many systems found in the real world that use only planned funds (a constant burn rate) and actual costs can provide false and misleading information. There is no way to be certain how much of the physical work has been accomplished. These systems do not measure how much work was accomplished for the money spent! Hence, without time-phasing cost to match your project schedule, it is impossible to have reliable information for control purposes.

Creating a Time-Phased Budget By using information from your WBS and resource schedule, you can create a time- phased cost baseline. Remember from the WBS for the PC Project in Chapters 4 and 5 we integrated the WBS and OBS organization breakdown structure so the work pack- ages could be tracked by deliverable and organization responsible. See Figure 8.12 for an example of the PC Prototype Project arranged by deliverable and organization unit responsible. For each intersection point of the WBS/OBS matrix, you see work pack- age budgets and the total cost. The total cost at each intersection is called a cost or control account. For example, at the intersection of the Read/write head deliverable and the Production department we see there are three work packages with a total bud- get of $200,000. The sum of all cost accounts in a column should represent the total costs for the deliverable. Conversely, the sum of the cost accounts in a row should represent the costs or budget for the organizational unit responsible to accomplish the work. You can continue to “roll up” costs on the WBS/OBS to total project costs. This WBS provides the information you can use to time phase work packages and assign them to their respective scheduled activities over the life of the project. Recall, from the development of your work breakdown structure for each work package, the following information needed to be developed: 1. Define work (what). 2. Identify time to complete a work package (how long). 3. Identify a time-phased budget to complete a work package (cost). 4. Identify resources needed to complete a work package (how much). 5. Identify a single person responsible for units of work (who). 6. Identify monitoring points for measuring progress (how well). Number three, time-phasing the work package, is critical for the final step of creating your budget baseline. The process of time-phasing work packages, which is illustrated next, is demonstrated in Figure 8.13. The work package has a duration of three weeks. Assuming labor, materials, and equipment are tracked separately, the work package

Create a time-phased project budget baseline.

8-10LO

Chapter 8 Scheduling Resources and Costs 275

costs for labor are distributed over the three weeks as they are expected to occur— $40,000, $30,000, and $50,000 for each week, respectively. When the three-week work package is placed in the network schedule, the costs are distributed to the time-phased budget for the same three scheduled weeks. Fortunately, most single WPs become an

Disk storage units

$5,160

External USB 500

Manufacturing 1,250

Organization $1,660

Motor 10

Circuit board 1,000

Chassis frame

50

Read/write head 600

Optical 3,000

Hard disks 1,660

Total budget for cost account Work package budget

10 10

120 120

140 260

400

50 130 180

Summarize by organizational units

10 20 20

50 130 40 30

200

300300

100100

150 150 300

Design 600

Production 650

Test 220

Purchasing 10

Software 180

Su m

m ar

te b

y de

liv er

ab le

s

FIGURE 8.12 Direct Labor Budget Rollup ($000)

FIGURE 8.13 Time-Phased Work Package Budget (labor cost only)

Work Package Description

Work Package ID

Deliverable

Responsible organization unit

Work Package Duration weeks

Page of

Project

Date

Estimator

Total labor cost

Test 1

PC Prototype

3/24/xx

CEG

$120,000

1

Test

3

1.1.3.2.3

Circuit board

Time-Phased Work Package Budget Labor cost only

Time-Phased Labor Budget ($000)

Work Periods--WeeksWork Package

Code 1.1.3.2.3

Labor rate

$xxxx/ week

$40 $30 $50 $120

1 2 3 4 5 Total Resource

Quality testers

276 Chapter 8 Scheduling Resources and Costs

activity and the process of distributing costs is relatively simple. That is, the relationship is one-for-one. Such budget timing is directly from the work package to the activity. In a few instances an activity will include more than one work package, where the pack- ages are assigned to one responsible person or department and deliverable. In this case the work packages are consolidated into one activity. As seen in Figure 8.14, this activity includes two WPs. The first, WP-1.1.3.2.4.1 (Code), is distributed over the first three weeks. The second, WP-1.1.3.2.4.2 (Integration), is sequenced over weeks 3 and 4. The activity duration is four weeks. When the activity is placed in the schedule, the costs are distributed starting with the schedule start—$20,000, $15,000, $75,000, and $70,000, respectively. These time-phased budgets for work packages are lifted from your WBS and are placed in your project schedule as they are expected to occur over the life of the proj- ect. The outcome of these budget allocations is the project cost baseline (also called planned value—PV), which is used to determine cost and schedule variances as the project is implemented. Figure 8.15 shows the Patient Entry Project network schedule, which is used to place the time-phased work packages’ budgets in the baseline. Figure 8.16 presents the project time-phased budget for the Patient Entry Project and the cumulative graph of the project budget baseline. In this figure you can see how the time-phased work pack- age costs were placed into the network and how the cumulative project budget graph for a project is developed. Notice that costs do not have to be distributed linearly, but the costs should be placed as you expect them to occur. You have now developed complete time and cost plans for your project. These project baselines will be used to compare planned schedule and costs using an integrative system called earned value. The application and use of project baselines to measure performance are discussed in detail in Chapter 13. With your project budget baseline established, you are also able to generate cash flow statements for your project like the one presented in Figure 8.17. Such statements prepare the firm to cover costs over the lifespan of the proj- ect. Finally, with resource assignments finalized you are able to generate resource usage schedules for your project (see Figure 8.18). These schedules map out the full deployment of personnel and equipment and can be used to generate individual work schedules.

Work Package Description

Work Package ID

Deliverable

Responsible organization unit

Work Package Duration weeks

Page of

Project

Date

Estimator

Total labor cost

Software 1 1

PC Prototype

3/24/xx

LGG

$180,000

Software

4

1.1.3.2.4.1 and 1.1.3.2.4.2

Circuit board

Time-Phased Labor Budget ($000)

Work Periods--WeeksWork Package

Code 1.1.3.2.4.1

Integration 1.1.3.2.4.2

Labor rate

$2,000/ week

$2,500/ week

$20

$20

$15

$15

$15

$60

$75

$70

$70

$130

$180

$50

1 2 3 4 5 Total Resource

Program’rs

System/ program’rs

Total

Time-Phased Work Package Budget Labor cost only

FIGURE 8.14 Two Time-Phased Work Packages (labor cost only)

Chapter 8 Scheduling Resources and Costs 277

ID

Legend

DUR

Activity description

ES

LS

EF

LF

SL

3

3

Establish entry codes

5 8

4

5

Get RFP bids

1 6

Design entry forms2

5

7

6

Program system

6 12

7

Establish acct. codes

8 11

Collect trial data

5 11

1

10 1

Merge data & codes

11

Test system

12

Patient Entry System Project (Weeks)

1 3 3

2

9

0

0

1 1

4

3

4

4

4

1

0

6 6

0

12

9

2

10

1412

0

2

2

5

6 8

1 12

9

2 14

6

3

Design data system

FIGURE 8.15 Patient Entry Project Network

FIGURE 8.16 Patient Entry Time- Phased Work Packages Assigned Design data

system Design entry

forms Establish entry

codes

Get RFP bids

Collect trial data

Establish account codes

Program system

Merge data & codes

Test system

Week total

Cumulative

1

2

3

4

5

6

7

8

9

1

3

5

6

3

6

1

2

2

5 5

6

3

6

5

12

4

7

4 2 2

2

2

2 2

1 1 1 1

1

1

2 2 1

2 4 42

4

1

5 652 4 3 3 4 4 1 5 6 0 4 4 3

4 3

5 15 18 21 25 29 30 35 41 41 45 49 5211

60

50

40

30

20

10

0 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14ID Dur. Task Budget

Cumulative Baseline Budget

(PV)

($000) Week

278 Chapter 8 Scheduling Resources and Costs

CEBOO Project Hardware

Hardware specifications

Hardware design

Prototypes

Order GXs

Assemble preproduction models

Operating system

Kernel specifications

Drivers

OC drivers

Serial VO drivers

Memory management

Operating system documentation

Network interface

Utilities

Utilities specifications

Routine utilities

Complex utilities

Utilities documentation

Shell

System integration

Architectural decisions

Integration first phase

System H/S test

Project documentation

Integration acceptance test

Total

Hardware documentation

January February March

$11,480.00 $24,840.00

$5,320.00

$20,400.00

$9,880.00

$10,240.00 $21,760.00

$3,360.00

$8,400.00

$5,760.00 $21,120.00

$7,680.00 $17,920.00

$20,160.00 $10,560.00

$12,320.00 $11,760.00 $12,880.00

$3,360.00

$23,120.00 $29,920.00 $14,960.00

$14,080.00 $24,320.00

April May June July

$37,200.00 $44,960.00 $48,240.00 $55,120.00 $80,400.00 $56,240.00 $23,440.00

FIGURE 8.17 CEBOO Project Monthly Cash Flow Statement

FIGURE 8.18 CEBOO Project Weekly Resource Usage Schedule

I. Suzuki Hardware specifications Hardware design Hardware documentation Operating system documentation Utilities documentation Architectural decisions J. Lopez Hardware specifications Hardware design Prototypes Kernel specifications Utilities specifications Architectural decisions Integration first phase J.J. Putz Hardware documentation Kernel specifications Operating system documentation Utilities documentation Project documentation R. Sexon Hardware specifications Prototypes Assemble preproduction models OC drivers Complex utilities Integration first phase System H/S test Integration acceptance test

12/30 1/6 1/13 1/20 1/27 2/03 24 hrs 40 hrs 40 hrs 40 hrs

24 hrs

24 hrs 40 hrs 40 hrs 16 hrs

40 hrs 40 hrs

40 hrs 40 hrs

24 hrs 40 hrs 40 hrs 40 hrs 12 hrs

24 hrs 40 hrs 40 hrs 16 hrs

40 hrs 20 hrs

40 hrs 20 hrs

24 hrs

24 hrs

40 hrs

40 hrs

40 hrs

40 hrs

24 hrs 24 hrs

40 hrs 40 hrs

40 hrs 40 hrs

12 hrs 20 hrs 20 hrs

Chapter 8 Scheduling Resources and Costs 279

Summary Usage and availability of resources are major problem areas for project managers. Attention to these areas in developing a project schedule can point out resource bottle- necks before the project begins. Project managers should understand the ramifications of failing to schedule resources. The results of resource scheduling are frequently significantly different from the results of the standard CPM method. With the rapid changes in technology and emphasis on time-to-market, catching resource usage and availability problems before the project starts can save the costs of crashing project activities later. Any resource deviations from plan and schedule that occur when the project is being implemented can be quickly recorded and the effect noted. Without this immediate update capability, the real negative effect of a change may not be known until it happens. Tying resource availability to a multiproject, multiresource system supports a project priority process that selects projects by their contribution to the organization’s objectives and strategic plan. Assignment of individuals to projects may not fit well with those assigned by com- puter software routines. In these cases overriding the computer solution to accommo- date individual differences and skills is almost always the best choice. The project resource schedule is important because it serves as your time base- line, which is used for measuring time differences between plan and actual. The resource schedule serves as the basis for developing your time-phased project cost budget baseline. The baseline (planned value, PV) is the sum of the cost accounts, and each cost account is the sum of the work packages in the cost account. Remem- ber, if your budgeted costs are not time-phased, you really have no reliable way to measure performance. Although there are several types of project costs, the cost baseline is usually limited to direct costs (such as labor, materials, equipment) that are under the control of the project manager; other indirect costs can be added to project costs separately.

Key Terms Heuristics, 258 Leveling, 256 Planned value (PV), 276

Resource-constrained project, 255 Resource smoothing, 252 Splitting, 269

Time-constrained project, 255 Time-phased budget baseline, 273

1. How does resource scheduling tie to project priority? 2. How does resource scheduling reduce flexibility in managing projects? 3. Present six reasons scheduling resources is an important task. 4. How can outsourcing project work alleviate the three most common problems asso-

ciated with multiproject resource scheduling? 5. Explain the risks associated with leveling resources, compressing or crashing proj-

ects, and imposed durations or “catch-up” as the project is being implemented. 6. Why is it critical to develop a time-phased baseline?

Review Questions

280 Chapter 8 Scheduling Resources and Costs

Exercises 1. Given the network plan that follows, compute the early, late, and slack times. What is the project duration? Using any approach you wish (e.g., trial and error), develop a loading chart for resources, Electrical Engineers (EE), and resource, Mechanical Engineers (ME). Assume only one of each resource exists. Given your resource schedule, compute the early, late, and slack times for your project. Which activities are now critical? What is the project duration now? Could something like this hap- pen in real projects?

2

4

10

0

2

3

3

EE

ME

10

Develop a loading schedule for each resource below. (Figure 8.3)

2 3 4 5 6 7 8

Pl an

9 10 11 12

4

1

6

2

5

6

7

4

1-EE

ID/RES

2-EE

3-ME

4-EE

5-ME

6-ME

7-EE

Fill in the times below for a resource activity schedule. LSES EF LF SL

ID

DURLS

SL

LF

ES EF

Legend

SL

Resource

Sc he

du le

Start End

EE EE ME

ME

EEME

EE

0

2. Given the network plan that follows, compute the early, late, and slack times. What is the project duration? Using any approach you wish (e.g., trial and error), develop a loading chart for resources Carpenters (C) and Electricians (E). Assume only one

Chapter 8 Scheduling Resources and Costs 281

Carpenter is available and two Electricians are available. Given  your resource schedule, compute the early, late, and slack times for your project. Which activities are now critical? What is the project duration now?

Carpenter

Electrician

10

Develop a loading schedule for each resource below.

2 3 4 5 6 7 8

Pl an

9 10 11 1412 13

2

4

3

1

4

3

5

5

10

3

6

2

1-C

2-C

3-C

4-E

5-2-E

6-C

Fill in the times below for a resource activity schedule. LSESID/RES EF LF SL

ID

DURLS

SL

LF

ES EF

Legend

SL

Resource

Sc he

du le

C

C E

C

2-EC

3. Compute the early, late, and slack times for the activities in the network that follows, assuming a time-constrained network. Which activities are critical? What is the time-constrained project duration?

Note: Recall, in the schedule resource load chart the time-constrained scheduling interval (ES through LF) has been shaded. Any resource scheduled beyond the shaded area will delay the project.

Assume you have only three resources and you are using a computer that uses software that schedules projects by the parallel method and following heuristics. Schedule only one period at a time!

Minimum slack Smallest duration Lowest identification number

282 Chapter 8 Scheduling Resources and Costs

Keep a log of each activity change and update you make each period—e.g., period 0–1, 1–2, 2–3, etc. (Use a format similar to the one on page 259.) The log should include any changes or updates in ES and slack times each period, activities scheduled, and activities delayed. (Hint: Remember to maintain the technical dependencies of the network.) Use the resource load chart to assist you in schedul- ing (see Figures 8.4 and 8.5).

List the order in which you scheduled the activities of the project. Which activi- ties of your schedule are now critical?

Recompute your slack for each activity given your new schedule. What is the slack for activity 1? 4? 5?

2

4

0

1

3

0

3

5

0

4

6

5

4

6

3

DUR ES LF SL

Scheduled resource load chart with ES and slack updates

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15RES

3 0 4 1

4 0 4 0

5 0 6 1

6 4 10 0

4 5 10 1

3 10 13 0

ID

1

2

3

4

5

6

Resources scheduled

3Resources available 3 3 3 3 3 3 3 3 3 3 3 3 3 3

ID

DURLS

SL

LF

ES EF

Legend

SL

Resource

2

1

2

2

1

1

2

1

1

1

2

2

Chapter 8 Scheduling Resources and Costs 283

4. *You have prepared the following schedule for a project in which the key resource is a tractor(s). There are three tractors available to the project. Activities A and D require one tractor to complete while activities B, C, E, and F require 2 tractors.

Develop a resource-constrained schedule in the loading chart that follows. Use the parallel method and heuristics given. Be sure to update each period as the com- puter would do. Record the early start (ES), late finish (LF), and slack (SL) for the new schedule.

DUR ES LF SL 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15RES

4

5

4

5

3

2

ID

A

B

C

D

E

F

Resources scheduled

3Resources available 3 3 3 3 3 3 3 3 3 3 3 3 3 3

ID

DURLS

SL

LF

ES EF

Legend

SL

Resource

1

2

2

1

2

2

A

4

0 4

11

1 5

1

B

5

0 5

00

0 5

2

C

4

4 8

22

6 10

2

D

5

5 10

00

5 10

1

F

2

10 12

00

10 12

2

E

3

5 8

22

7 10

2

Use the following heuristics: Minimum slack Smallest duration Lowest identification number

*The solution to this exercise can be found in Appendix 1.

284 Chapter 8 Scheduling Resources and Costs

5. Develop a resource schedule in the loading chart that follows. Use the parallel method and heuristics given. Be sure to update each period as the computer would do. Note: activities 2, 3, 5, and 6 use two of the resource skills. Three of the resource skills are available. How has slack changed for each activity? Has the risk of being late changed? How?

4 83

00

83 5

1

3 51

33

84 4

2

53 6

2 2

5 83

2

1 1

1

1

2 3

3

6 108

2

2

8

0

10

0

List the order in which your activities are scheduled /_____ /_____ /_____ / /_____ /_____ /_____ /

2

0

00

33

0

22

32

Use the following heuristics: Minimum slack Smallest duration Lowest identification number

ID

DURLS

SL

LF

ES EF

Legend

SL

DUR ES LF SL

What is the schedule slack for 1____, 3____, and 4_____? Which activities are critical now? _____________________

0 1 2 3 4 5 6 7 8 9 10 11 12 13ID RES

1 0 31

3 0 32

4 1 83

5 3 84

35

26

Resources scheduled

3Resources available 3 3 3 3 3 3 3 3 3 3 3 3

1

2

2

1

2

2

RES

6. You have prepared the following schedule for a project in which the key resource is a backhoe(s). This schedule is contingent on having 3 backhoes. You receive a call from your partner, Brooker, who desperately needs one of your backhoes. You tell

Chapter 8 Scheduling Resources and Costs 285

Brooker you would be willing to let him have the backhoe if you are still able to complete your project in 11 months.

Develop a resource schedule in the loading chart that follows to see if it is pos- sible to complete the project in 11 months with only 2 backhoes. Be sure to record the order in which you schedule the activities using scheduling heuristics. Activities 5 and 6 require 2 backhoes, while activities 1, 2, 3, and 4 require 1 backhoe. No splitting of activities is possible. Can you say yes to Brooker’s request?

2 20

11

2 31

1 10

4 4

4 51 4 42

33

2 75 6 97

2 97

00

3 30

00

3 30

1

1

1

1

2

ID

DURLS

SL

LF

ES EF

Legend

SL

Resource

2

5 73

4 73

00

DUR ES LF SL

Schedule the resource load chart with ES and Slack updates

0 1 2 3 4 5 6 7 8 9 10 11 12 13ID RES

1 5 41

2 3 12

3 3 03

2 7 34

4 7 05

2

0

0

0

2

3

7 9 06

Resources scheduled

2Resources available 2 2 2 2 2 2 2 2 2 2 2 2

1

1

1

1

2

2

7. *You are one of three carpenters assigned to complete a short construction project. Right before the start of the project, one of your fellow carpenters was hospitalized and will not be available to work on the project.

Develop a resource-constrained schedule in the loading chart that follows to see how long the project will take with only 2 carpenters. Be sure to record the order in

*The solution to this exercise can be found in Appendix 1.

286 Chapter 8 Scheduling Resources and Costs

which you schedule the activities using the scheduling heuristics. Activities A, B, C, D, E, G, and H require 2 carpenters to complete. Activity F requires only 1 carpenter. No splitting of activities is possible.

You will receive a bonus if the project is completed within 15 days. Should you start planning how you will spend your bonus?

DUR ES LF SL 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18RES

2

1

3

1

2

3

2

2

ID

A

B

C

D

E

F

G

H

Resources scheduled

2Resources available 2 2 2 2 2 2 2 22 2 2 2 2 2 2 2 2

2

2

2

2

2

1

2

2

A

2

0 2

00

0 2

2

B

1

2 3

22

4 5

2

C

3

2 5

00

2 5

2

D

1

5 6

00

5 6

2

E

2

6 8

00

6 8

2

F

3

6 9

11

7 10

1

Use the following heuristics: Minimum slack Smallest duration Lowest identification number

G

2

8 10

00

8 10

2

H

2

10 12

00

10 12

2

ID

DURLS

SL

LF

ES EF

Legend

SL

Resource

8. Given the time-phased work packages, complete the baseline budget form for the project.

Chapter 8 Scheduling Resources and Costs 287

Activity 1

Task Budget

Activity 2

Activity 3

Activity 4

Activity 5

Total

Cumulative

4

6

10

8

3

31

4

1 3 2

2 4 2 2

2 3 3

2 1

10 2 3 4 5 6 7 8 9 10

Time-phased budget ($ 000) Week

9. Given the time-phased work packages and network, complete the baseline budget form for the project.

3

Report

Design

Task Budget

Time-Phased Budget

Week

11 4

0 1 2 3 4 5 6 7 8 9 10 11 12

5 2

21

8

40

Survey

Report

Cumulative

Total

Market Survey Project

WBS Work Package Cost by Week

Project Network

3

Design

0 33

0

0

3

Survey

3

WP Design 4 5 2

WP Survey 2 2 4 4 4 5

WP Report 3 3 2

1

6

2

3

288 Chapter 8 Scheduling Resources and Costs

10. *Given the time-phased work packages and network, complete the baseline budget form for the project.

0 1 2 3 4 5 6 7 8 9 10 11 12Bu dg

et

ID

A

B

C

D

E

F

Total

Cumulative

40

32

48

18

28

40

206

A

4

0 4

11

1 5

B

5

0 5

00

0 5

C

4

4 8

22

6 10

D

5

5 10

00

5 10

F

2

10 12

00

10 12

E

3

5 8

22

7 10

Cost by Week

A

B

C

D

E

F

10

8

12

6

8

20

10

4

12

2

8

20

10

8

12

2

12

10

4

12

2

8

6

ID

DURLS

SL

LF

ES EF

Legend

SL

*The solution to this exercise can be found in Appendix 1.

Chapter 8 Scheduling Resources and Costs 289

11. Given the time-phased work packages and network, complete the baseline budget form for the project.

Legend

4

4

5

5

Prepare marketing

3

2

2

3

Build prototype

Soccer Toy Project

6

2

Assemble & test

7

1

Launch

1

2

0

Design prototype

Order parts

Prepare production

ID

DUR

ES

LS

EF

LF

SL Description

Build prototype

Design prototype

Bu dg

et

24

30

10

64

30

36

12

206

0 1 2 3 4 5 6 7 8 9 10 11 12 13

Order parts

Prepare prod’n

Prepare market’g Assemble

& test

Launch

Total

Cumulative

Soccer Toy Project

Design prototype

Build prototype

Order parts

Prepare production

Prepare marketing

Assemble & test

Launch

Time-phased Budget ($000)

Week

Cost by Week ($000)

1

12

2 3 4 5

12

10 1010

16 10

55

22 16

6 126 06

18 18

12

290 Chapter 8 Scheduling Resources and Costs

12. The National Oceanic Research Institute is planning a research study on global warming in Antarctica. The 16-month network schedule is presented below. It is followed by budgets for each activity. Create a time-phased budget for the research project in the form provided.

A

3

0

0

0

Preliminary plan

3

3

B

2

3

0

3

Detail plan

5

5

C

2

5

2

7

Hire staff

7

9

G

2

7

6

13

Plane transportation

Global Warming Antarctic Research Project Months.... ($000)

9

15

F

3

7

2

9

Purchase clothing

10

12

K

3

10

2

12

Ship supplies

13

15

L

1

15

0

15

Travel

16

16

E

1

7

6

13

Train

8

14

J

1

14

0

14

Test equipment

15

15

D

1

5

0

5

Select equipment

6

6

H

5

6

0

6

Get custom equipment

11

11

I

3

11

0

11

Additional equipment

14

14

Global Warming Antarctic Research Project Activity Time Phased Work Packages by Month ($000)

Task Duration Budget 0 1 2 3 4 5 6

A Preliminary plan 3 3 1 1 1

B Detail plan 2 2 1 1

C Hire staff 2 4 4

D Select equipment 1 5 5

E Train 1 3 3

F Purchase clothing 3 9 3 0 6

G Plane transportation 2 60 5 55

H Get custom equipment 5 36 5 5 10 10 6

I Additional equipment 3 20 10 5 5

J Test equipment 1 6 6

K Ship all supplies 5 15 3 3 0 0 9

L Travel 1 9 9

Total budget 172

Chapter 8 Scheduling Resources and Costs 291

Arrow, K. J., and L. Hurowicz, Studies in Resource Allocation Process (New York: Cambridge University Press, 1997). Brucker, P., A. Drexl, R. Mohring, L. Newmann, and E. Pesch, “Resource-constrained Project Scheduling: Notation, Classification, Models and Methods,” European Journal of Operational Research, vol. 112 (1999), pp. 3–42. Burgess, A. R., and J. B. Kellebrew, “Variations in Activity Level on Cyclical Arrow Diagrams,” Journal of Industrial Engineering, vol. 13 (March–April 1962), pp. 76–83. Charnes, A., and W. W. Cooper, “A Network Interpretation and Direct Sub Dual Algorithm for Critical Path Scheduling,” Journal of Industrial Engineering, July–August 1962. Davis, E. W., and J. Patterson, “A Comparison of Heuristic and Optimum Solutions in Resource-Constrained Project Scheduling,” Management Science, April 1975, pp. 944–955. Demeulemeester, E. L., and W. S. Herroelen, Project Scheduling: A Research Hand- book (Norwell, MA: Kluwer Academic Publishers, 2002). Fendly, L. G., “Towards the Development of a Complete Multi Project Scheduling System,” Journal of Industrial Engineering, vol. 19 (1968), pp. 505–15. Goldratt, E., Critical Chain (Great Barrington, MA: North River Press, 1997). Kurtulus, I., and E. W. Davis, “Multi-project Scheduling: Categorization of Heuristic Rules Performance,” Management Science, February 1982, pp. 161–72. Newbold, R. C., “Leveraging Project Resources: Tools for the Next Century,” Pro- ceedings of 28th Annual Project Management Institute, 1997 Seminars and Sympo- sium (Newtown, PA: Project Management Institute, 1997), pp. 417–21. Pascoe, T. L., “An Experimental Comparison of Heuristic Methods for Allocating Resources,” Ph.D. dissertation, University of Cambridge, United Kingdom, 1965. Reinersten, D., “Is It Always a Bad Idea to Add Resources to a Late Project?” Electric Design, October 30, 2000, pp. 17–18. Rubinstein, J., D. Meyer, and J. Evans, “Executive Control of Cognitive Processes in Task Switching,” Journal of Experimental Psychology: Human Perception and Per- formance, vol. 27, no. 4 (2001), pp. 763–97. Talbot, B. F., and J. H. Patterson, “Optimal Methods for Scheduling Under Resource Constraints,” Project Management Journal, December 1979. Wiest, J. D., “A Heuristic Model for Scheduling Large Projects with Unlimited Resources,” Management Science, vol. 18 (February 1967), pp. 359–77. Woodworth, B. M., and C. J. Willie, “A Heuristic Algorithm for Resource Leveling in Multiproject, Multiresource Scheduling,” Decision Sciences, vol. 6 (July 1975), pp. 525–40. Woodworth, B. M., and S. Shanahan, “Identifying the Critical Sequence in a Resource Constrained Project,” International Journal of Project Management, vol. 6 (1988), pp. 89–96.

References

292 Chapter 8 Scheduling Resources and Costs

Case 8.1

Blue Mountain Cabin Jack and Jill Smith have just retired and want to build a small, basic cabin in the Blue Mountains of Vermont. They have hired Daryl Hannah as the general contractor for the project. She has assembled a team of three workers to complete the project: Tom, Dick, and Harry. Daryl has negotiated a cost-plus contract with the Smiths whereby she will receive 15 percent beyond the cost of labor and materials. Before they sign the contract the Smiths want an estimate of how much the project is likely to cost and how long it will take. Darryl has estimated that the cost for materials, permits, etc., will total $40,000. She wants to determine labor costs as well as how long the project will take. This is one of sev- eral projects Daryl is managing, and other than occasionally helping out, her role is strictly limited to supervising. She has devised the following master plan and assignments. Note that Dick is the only skilled plumber in the group while Harry is the only skilled electrician. Tom is a general carpenter and can assist them with their work. Dick and Harry each get paid $300 a day while Tom gets paid $200 per day. Darryl has negotiated a 10 percent management reserve to deal with unexpected problems. Unused funds will be returned to the Smiths.

Case 8.2

Power Train, Ltd. We have smashing systems for reporting, tracking, and controlling costs on design proj- ects. Our planning of projects is better than any I have seen at other companies. Our scheduling seemed to serve us well when we were small and we had only a few projects. Now that we have many more projects and schedule using multiproject software, there are too many occasions when the right people are not assigned to the projects deemed important to our success. This situation is costing us big money, headaches, and stress! Claude Jones, VP, Design and Operations

Prepare a short proposal for the Smiths that includes a Gantt chart with resources assigned, and cost estimates if the project starts on 8/1/16. Did resource limitations affect the final schedule? If so, how? What financial risks does this project face? What can the Smiths do to protect themselves against those risks?

ID Task Predecessor Time (days) Assignment

A Prepare Site none 2 Tom, Dick, Harry B Pour Foundation A 2 Tom, Dick, Harry C Erect Frame B 4 Tom, Dick, Harry D Roof C 3 Tom, Dick, Harry E Windows/Doors D 2 Tom, Dick F Electrical D 2 Harry, Tom G Plumbing D 2 Dick, Tom H Rough-in-frame E, F,G 2 Tom, Dick, Harry I Clean up H 1 Tom, Dick, Harry

Chapter 8 Scheduling Resources and Costs 293

HISTORY Power Train, Ltd. (PT), was founded in 1970 by Daniel Gage, a skilled mechanical engineer and machinist. Prior to founding PT he worked for three years as design engi- neer for a company that designed and built transmissions for military tanks and trucks. It was a natural transition for Dan to start a company designing and building power trains for farm tractor companies. Today, Dan is no longer active in the management of PT but is still revered as its founder. He and his family still own 25 percent of the com- pany, which went public in 1998. PT has been growing at a 6 percent clip for the last five years but expects industry growth to level off as supply exceeds demand. Today, PT continues its proud tradition of designing and building the best-quality power trains for manufacturers of farm tractors and equipment. The company employs 178 design engineers and has about 1,800 production and support staff. Contract design projects for tractor manufacturers represent a major portion of PT’s revenue. At any given time, about 45 to 60 design projects are going on concurrently. A small por- tion of their design work is for military vehicles. PT only accepts military contracts that involve very advanced, new technology and are cost plus. A new phenomenon has attracted management of PT to look into a larger market. Last year a large Swedish truck manufacturer approached PT to consider designing power trains for its trucks. As the industry consolidates, the opportunities for PT should increase because these large firms are moving to more outsourcing to cut infra- structure costs and stay very flexible. Only last week a PT design engineer spoke to a German truck manufacturing manager at a conference. The German manager was already exploring outsourcing of drive trains to Porsche and was very pleased to be reminded of PT’s expertise in the area. A meeting is set up for next month.

CLAUDE JONES Claude Jones joined PT in 1999 as a new MBA from the University of Edinburgh. He worked as a mechanical engineer for U.K. Hydraulics for five years prior to returning to school for the MBA. “I just wanted to be part of the management team and where the action is.” Jones moved quickly through the ranks. Today he is the vice president of design and operations. Sitting at his desk, Jones is pondering the conflicts and confusion that seem to be increasing in scheduling people to projects. He gets a real rush at the thought of designing power trains for large trucks; however, given their current project scheduling problems, a large increase in business would only compound their problems. Somehow these conflicts in scheduling have to be resolved before any serious thought can be given to expanding into design of power transmissions for truck manufacturers. Jones is thinking of the problems PT had in the last year. The MF project is the first to come to mind. The project was not terribly complex and did not require their best design engineers. Unfortunately, the scheduling software assigned one of the most creative and expensive engineers to the MF project. A similar situation, but reversed, happened on the Deer project. This project involved a big customer and new hydro- static technology for small tractors. In this project the scheduling software assigned engineers who were not familiar with small tractor transmissions. Somehow, thinks Jones, the right people need to be scheduled to the right projects. Upon reflection, this problem with scheduling has been increasing since PT went to multiproject schedul- ing. Maybe a project office is needed to keep on top of these problems. A meeting with the information technology team and software vendors was positive but not very helpful because these people are not really into detailed scheduling prob- lems. The vendors provided all sorts of evidence suggesting the heuristics used—least

294 Chapter 8 Scheduling Resources and Costs

slack, shortest duration, and identification number—are absolutely efficient in sched- uling people and minimizing project delays. One project software vendor, Lauren, kept saying their software would allow PT to customize the scheduling of projects and people to almost any variation selected. Lauren repeated over and over, “If the standard heuristics do not meet your requirements, create your own heuristics that do.” Lauren even volunteered to assist in setting up the system. But she is not willing to spend time on the problem until PT can describe to her exactly what criteria will be used (and their sequence) to select and schedule people to projects.

WHAT NEXT? Potential expansion into the truck power train business is not feasible until the confu- sion in project scheduling is solved or reduced significantly. Jones is ready to tackle this problem, but he is not sure where to start. What criteria should he consider? What should be the sequence for selecting and assigning people to projects?

Appendix 8.1

The Critical-Chain Approach LEARNING OBJECTIVES After reading this appendix you should be able to:

A8-1 Define what is meant by the term “critical chain.”

A8-2 Identify the reasons why projects are late even when estimates are padded.

A8-3 Describe the basic critical-chain methodology.

A8-4 Describe the differences between critical-chain scheduling and the traditional approach to scheduling.

In practice, project managers carefully manage slack on sensitive resource-limited proj- ects. If possible, they will add slack at the end of the project by committing to a comple- tion date that goes beyond the scheduled date. For example, the plans say the project should be completed on April 1, although the official completion date is May 1. Other managers take a more aggressive approach to managing slack within the schedule. They use an early start schedule and prohibit use of slack on any activity or work package to be used unless authorized by the project manager. Progress by percent complete and by remaining time are carefully monitored. Activities that are beating estimated comple- tion times are reported so that succeeding activities can start ahead of schedule. This ensures that the time gained is used to start a succeeding activity earlier and time is not wasted. The overall intent is to create and save slack as a time buffer to complete the project early or to cover delay problems that may creep up on critical activities or paths. Eliyahu Goldratt, who championed the “theory of constraints” in his popular book The Goal, advocates an alternative approach to managing slack.1 He has coined the term “critical chain” to recognize that the project network may be constrained by both resource and technical dependencies. Each type of constraint can create task dependencies, and in the case of resource constraints, new task dependencies can be Define what is meant by

the term “critical chain.”

A8-1LO

1 E. Goldratt, The Goal (Great Barrington, MA: North River Press, 1997).

Chapter 8 Scheduling Resources and Costs 295

created! Remember how resource constraints shifted the critical path? If not, visit Figure 8.5 again. The critical chain refers to the longest string of dependencies that exist on the project. Chain is used instead of path, since the latter tends to be associ- ated with just technical dependencies not resource dependencies. Goldratt uses the critical chain concept to develop strategies for accelerating the completion of proj- ects. These strategies are based on his observations about time estimates of individ- ual activities.

TIME ESTIMATES Goldratt argues that there is a natural tendency for people to add safety (just-in-case) time to their estimations. It is believed that those who estimate activity times provide an estimate that has about an 80 to 90 percent chance of being completed on or before the estimated time. Hence, the median time (50/50 chance) is overestimated by approximately 30 to 40 percent. For example, a programmer may estimate that there is a 50/50 chance that he can complete an activity in six days. However, to ensure success and to protect against potential problems, he adds three days of safety time and reports that it will take nine days to complete the task. In this case the median (50/50) time is overestimated by approximately 50 percent. He now has a 50/50 chance of completing the project three days ahead of the schedule. If this hid- den contingency is pervasive across a project, then most activities in theory should be completed ahead of schedule. Not only do workers add safety, but project managers like to add safety to ensure that they will be able to bring the project in ahead of schedule. They will add a month to a nine-month project to cover any delays or risks that might spring up. This situation raises an interesting paradox:

Why, if there is a tendency to overestimate activity durations, and add safety to the end of a project, do so many projects come in behind schedule?

Critical-Chain Project Management (CCPM) offers several explanations: ∙ Parkinson’s law: Work fills the time available. Why hustle to complete a task today

when it isn’t due until tomorrow? Not only will the pace of work be dictated by deadline, but workers will take advantage of perceived free time to catch up on other things. This is especially true in matrix environments where workers will use this time to clear work backlog on other projects and duties.

∙ Self-protection: Participants fail to report early finishes out of fear that management will adjust their future standards and demand more next time. For example, if a team member estimates that a task will take seven days and delivers it in five, the next time he is asked for an estimate, the project manager may want to trim the estimate based on past performance. Peer pressure may also be a factor here: to avoid being labeled a “rate buster,” members may not report early finishes.

∙ Dropped baton: Goldratt uses the metaphor of project as relay race to illustrate the impact of poor coordination. Just as a runner’s time is lost if the next runner is not ready to receive the baton, so is the time gained from completing a task early lost if the next group of people are not ready to receive the project work. Poor communication and inflexible resource schedules prevent progress from occurring.

∙ Excessive multitasking: The norm in most organizations is to have project person- nel work on several projects, activities, or assignments at the same time. This leads to costly interruptions and excessive task splitting. As pointed out in our discussion

Identify the reasons why projects are late even when estimates are padded.

A8-2LO

296 Chapter 8 Scheduling Resources and Costs

of splitting tasks, this adds time to each activity. When looked at in isolation the time loss may seem minimal, but when taken as a whole the transition costs can be staggering.

∙ Resource bottlenecks: In multiproject organizations projects are frequently delayed because test equipment or other necessary resources are tied up on other project work.

∙ Student syndrome (procrastination): Goldratt asserts that just as students delay writing a term paper until the last minute, workers delay starting tasks when they perceive that they have more than enough time to complete the task. The problem with delaying the start of a task is that obstacles are often not detected until the task is under way. By postponing the start of the task, the opportunity to cope with these obstacles and complete the task on time is compromised.

Critical-Chain in Action CCPM’s solution to reducing project time overruns is to insist on people using the “true 50/50” activity time estimates (rather than estimates which have an 80 to 90 percent chance of being completed before the estimated time); the 50/50 estimates result in a project duration about one-half the low risk of 80 to 90 percent estimates. This requires a corporate culture which values accurate estimates and refrains from blaming people for not meeting deadlines. According to CCPM, using 50/50 esti- mates will discourage Parkinson’s law, the student syndrome, and self-protection from coming into play because there is less “free time” available. Productivity will be increased as individuals try to meet tighter deadlines. Similarly, the compressed time schedule reduces the likelihood of the dropped baton effect. CCPM recommends inserting time buffers into the schedule to act as “shock absorb- ers” to protect the project completion date against task durations taking longer than the 50/50 estimate. The rationale is that by using 50/50 estimates you are in essence taking out all of the “safety” in individual tasks. CCPM also recommends using portions of this collective safety strategically by inserting time buffers where potential problems are likely to occur. There are three kinds of buffers in CCPM: ∙ Project buffer: First, since all activities along the critical chain have inherent uncer-

tainty that is difficult to predict, project duration is uncertain. Therefore, a project time buffer is added to the expected project duration. CCPM recommends using roughly 50 percent of the aggregate safety. For example, if the modified schedule reduces the project duration by 20 days from 50 to 30, then a 10-day project buffer would be used.

∙ Feeder buffers: Buffers are added to the network where noncritical paths merge with the critical chain. These buffers protect the critical chain from being delayed.

∙ Resource buffers: Time buffers are inserted where scarce resources are needed for an activity. Resource time buffers come in at least two forms. One form is a time buffer attached to a critical resource to ensure that the resource is on call and avail- able when needed. This preserves the relay race. The second form of time buffer is added to activities preceding the work of a scarce resource. This kind of buffer protects against resource bottlenecks by increasing the likelihood that the preceding activity will be completed when the resource is available.

All buffers reduce the risk of the project duration being late and increase the chance of early project completion.2 See Snapshot from Practice A8.1: Critical Chain Applied to Airplane Part Arrivals.

Describe the basic critical-chain methodology.

A8-3LO

2 For more information on buffers, see: L. P. Leach, “Critical Chain Project Management Improves Project Performance,” Project Management Journal, vol. 30, no. 2 (1999), pp. 39–51.

Chapter 8 Scheduling Resources and Costs 297

Critical-Chain versus Traditional Scheduling Approach To illustrate how CCPM affects scheduling let’s compare it with the traditional approach to project scheduling. We will first resolve resource problems in the way described in Chapter 8 and then using the CCPM method. Figure A8.1A shows the planned Air Con- trol project network without any concern for resources. That is, activities are assumed to be independent and resources will be made available and/or are interchangeable. Figure A8.1B depicts the bar chart for the project. The dark blue bars represent the durations of critical activities; the light blue bars represent the durations of noncritical activities; the gray bars represent slack. Note that the duration is 45 days and the criti- cal path is represented by activities 1, 4, 6, 7, and 8. Parallel activities hold potential for resource conflicts. This is the case in this project. Ryan is the resource for activities 3 and 6. If you insert Ryan in the bar chart in Figure A8.1B for activities 3 and 6, you can see activity 3 overlaps activity 6 by five days—an impossible situation. Because Ryan cannot work two activities simultaneously and no other person can take his place, a resource dependency exists. The result is that two activities (3 and 6) that were assumed to be independent now become dependent. Some- thing has to give! Figure A8.2A shows the Air Control project network with the resources included. A pseudo-dashed arrow has been added to the network to indicate the resource dependency. The bar chart in Figure A8.2B reflects the revised schedule resolving the overallocation of Ryan. Given the new schedule, slack for some activities has changed. More importantly, the critical path has changed. It is now 1, 3, 6, 7, 8. The resource schedule shows the new project duration to be 50 days rather than 45 days.

Describe the differences between critical-chain scheduling and the traditional approach to scheduling.

A8-4LO

In the past Spirit Aero Systems, manu- facturer of airplane parts, were forced to delay product development projects as a result of missing parts for assem- blies. Spirit management cycled

through several approaches, such as lean, value chain, cycle time reduction, knowledge based engineering, to reduce the problem. Although each yielded minor improvements, the impacts were not substantial. Rework, overtime, delay costs, and vendor expediting costs continued to have significant impact on costs, meeting commitments, and reputation. Spirit turned to critical-chain management methodology in a pilot project. Joseph Zenisek, the critical-chain manager, said the choice of critical chain was “a game changer for us.” Spirit applied the critical-chain approach to assem- bly of newly designed pylons (brackets) used for failure destruction testing of casings for a jet engine project. Zenisek credited success to three key factors:

all parts and staff are available.

- lantly monitoring assembly parts that use a large num- ber of parts or where rate or number used is high.

vendors and buffers to ensure that delivery of over 300 parts arrived on time.

The critical chain program led to impressive results. The parts and staffing rule cut down on late deliveries and rework on partially completed work packages caused by missing parts. The result was a reduction of 50 percent in overtime. Reducing delays reduced assembly cycle time by 18 percent. Work in process and work packages were also reduced since availability of buffer parts avoided delays. The critical-chain method led to better resource management and reduced stress. Given the success of the critical-chain program, Spirit intends to expand the application of the critical- chain method to new product development projects for their clients.

*Peter Fretty, “E Is in the Air,” PM Network, vol. 26, no. 2 (February 2012), pp. 50–56.

S N A P S H O T F R O M P R A C T I C E A 8 . 1 Critical Chain Applied to Airplane Part Arrivals*

298 Chapter 8 Scheduling Resources and Costs

Now let’s apply the CCPM approach to the Air Control project. Figure A8.3 details many of the changes. First, notice that task estimates now represent approximations of the 50/50 rule. Second, observe that not all of the activities on the critical chain are technically linked. Manufacture custom parts is included because of previously defined resource dependency. Third, a project time buffer is added at the end of schedule. Finally, feeder buffers are inserted at each point where a noncritical activity merges with the critical chain. The impact the CCPM approach has on the project schedule can best be seen in the Gantt chart presented in Figure A8.4. Notice first the late start times for each of the three noncritical activities. For example, under the critical path method, order vendor parts and software development would be scheduled to begin immediately after the order review. Instead they are scheduled later in the project. Three-day feeder buffers have been added to each of these activities to absorb any delays that might occur in these activities. Finally, instead of taking 50 days the project is now estimated to take only 27 days with a 10-day project buffer!

0

1 Order review 2

2 Order vendor parts 15

3 Produce std. parts 18

4 Design cust. parts 13

5 Software developm’t 18

6 Mfgr. cust. parts 15

7 Assemble 10

8 Test 5

5 10 15 20 25 30 35 40 45 50

Critical SlackNoncritical

FIGURE A8.1B Air Control Project: Time Plan without Resources

Manufacture custom parts Early start: 15 Early finish: 30

ID: 6 Dur: 15 days

Produce std. parts Early start: 2 Early finish: 20

ID: 3 Dur: 18 days

Order vendor parts Early start: 2 Early finish: 17

ID: 2 Dur: 15 days

Assemble Early start: 30 Early finish: 40

ID: 7 Dur: 10 days

Design custom parts Early start: 2 Early finish: 15

ID: 4 Dur: 13 days

Software development Early start: 2 Early finish: 20

ID: 5 Dur: 18 days

Order review Early start: 0 Early finish: 2

ID: 1 Dur: 2 days

Test Early start: 40 Early finish: 45

ID: 8 Dur: 5 days

Project duration 45 days

FIGURE A8.1A Air Control Project: Time Plan without Resources

Chapter 8 Scheduling Resources and Costs 299

Manufacture custom parts Early start: 20 Early finish: 35 Res: Ryan

ID: 6 Dur: 15 days

Produce std. parts Early start: 2 Early finish: 20 Res: Ryan

ID: 3 Dur: 18 days

Order vendor parts Early start: 2 Early finish: 17 Res: Carly

ID: 2 Dur: 15 days

Assemble Early start: 35 Early finish: 45 Res: Dawn

ID: 7 Dur: 10 days

Design custom parts Early start: 2 Early finish: 15 Res: Lauren

ID: 4 Dur: 13 days

Software development Early start: 2 Early finish: 20 Res: Connor

ID: 5 Dur: 18 days

Order review Early start: 0 Early finish: 2 Res: Ryan

ID: 1 Dur: 2 days Test

Early start: 45 Early finish: 50 Res: Kevin

ID: 8 Dur: 5 days

Project duration 50 days

FIGURE A8.2A Air Control Project: Schedule with Resources Limited

0

1 Order review 2

2 Order vendor parts 15

3 Produce std. parts 18

4 Design cust. parts 13

5 Software developm’t 18

6 Mfgr. cust. parts 15

7 Assemble 10

8 Test 5

5 10 15 20 25 30 35 40 45 50

Critical Slack

Ryan

Carly

Ryan

Ryan

Dawn

Kevin

Lauren

Connor

Noncritical

FIGURE A8.2B Air Control Project: Schedule with Resources Limited

Test Project buffer

Critical chain

3 Order review

1

FB

FB

Order vendor parts

8

Produce std. parts

8

Design cust. parts

7

FB

FBFeederbufferSoftwaredev.

10

Task

DUR

Mfgr. cust. parts

8

Assemble

6

FIGURE A8.3 Air Control Project: CCPM Network

300 Chapter 8 Scheduling Resources and Costs

Activity

1. Order review

2. Order vendor parts

3. Produce std. parts

4. Design cust. parts

5. Software dev.

6. Mfgr. cust. parts

7. Assemble

8. Test

DUR

1

8

8

7

10

8

6

3

LS

0

7

1

1

11

11

18

24

LF

1

15

9

8

21

19

24

27

Buffer

0

3

0

3

3

0

0

12

0 5 10 15 20 25 30 35 40

Activity Buffer

FIGURE A8.4 Air Control Project Gantt Chart: CCPM Network

This example provides an opportunity for explaining the differences between buffers and slack. Slack is spare time inherent in the schedule of noncritical activi- ties and can be determined by differences between the early start and late start of a specific activity. Buffers, on the other hand, are dedicated time blocks reserved to cover most likely contingencies and are monitored closely so, if they are not needed, subsequent activities can proceed on schedule. Buffers are needed in part because the estimates are based on 50/50 approximations, and therefore roughly half of the activities will take longer than planned. To protect against these extended activity durations, buffers are inserted to minimize the impact on the schedule. Buffers are not part of the project schedule and are used only when sound manage- ment dictates it. While not depicted in the figures, an example of a resource buffer would be to add six days to Ryan’s schedule (remember he is the critical resource that caused the sched- ule to be extended). This would ensure that he could continue to work on the project beyond the 18th day in case either produce standard parts and/or manufacture custom parts takes longer than planned. Progress on these two tasks would be monitored closely, and his schedule would be adjusted accordingly.

CCPM and Splitting Tasks Buffers do not address the insidious effects of pervasive task splitting, especially in a multiproject environment where workers are juggling different project assign- ments. CCPM has three recommendations that will help to reduce the impact of splitting activities: 1. Reduce the number of projects so people are not assigned to as many projects

concurrently. 2. Control start dates of projects to accommodate resource shortages. Don’t start proj-

ects until sufficient resources are available to work full time on the project. 3. Contract (lock in) for resources before the project begins.

Monitoring Project Performance The CCPM method uses buffers to monitor project time performance. Remember that as shown in Figure A8.3 a project buffer is used to insulate the project against

Chapter 8 Scheduling Resources and Costs 301

FIGURE A8.5 Project Control— Buffer Management

OK

100% Full buffer time left

0% No buffer

time left

Region III Region II Region I

Act Watch

& Plan

delays along the critical chain. For monitoring purposes, this buffer is typically divided into three zones—OK, Watch and Plan, and Act, respectively (see Figure A8.5). As the buffer begins to decrease and moves into the second zone, alarms are set off to seek corrective action. To be truly effective, buffer management requires comparing buffer usage with actual progress on the project. For example, if the proj- ect is 75 percent complete and you have only used 50 percent of the project buffer, then the project is in pretty good shape. Conversely, if the project is only 25 percent complete and 50 percent of the buffer has already been used, you are in trouble and corrective action is needed. A method for estimating percentage complete is described in Chapter 13. The CCPM Method Today CCPM has generated considerable debate within the project management community. While sound in theory, support at this time is limited but growing. For example, Harris Semiconductor was able to build a new automated wafer fabrication facility within 13 months using CCPM methods when the industry standard for such a facility is 26–36 months. The Israeli aircraft industry has used CCPM techniques to reduce aver- age maintenance work on aircraft from two months to two weeks. The U.S. Air Force and Navy as well as Boeing, Lucent Technologies, Intel, GM, and 3M are applying critical-chain principles to their multiproject environments.3 CCPM is not without critics. First, CCPM does not address the biggest cause of project delays, which is an ill-defined and unstable project scope. Second, some critics challenge Goldratt’s assumptions about human behavior. They question the tendency of experts to pad estimates and that employees act deliberately against the organization for their own interest and benefit (c.f., Button, 2011; Pinto, 1999). Critics also object to the insinuation that trained professionals would exhibit the student syndrome habits (Zalmanson, 2001). Third, evidence of success is almost exclusively anecdotal and based on single case studies or on computer modeling. The lack of systematic evidence raises questions about generalizability of application. CCPM may prove to work best for only certain kinds of projects (Raz, Barnes, & Dvir, 2003). One of the keys to implementing CCPM is the culture of the organization. If the organization honors noble efforts that fail to meet estimates as it does efforts that do meet estimates, then greater acceptance will occur. Conversely, if management treats honest failure differently from success, then resistance will be high. Organizations adopting the CCPM approach have to invest significant energy to obtaining “buy-in” on the part of all participants to its core principles and allaying the fears that this system may generate.

3 Cited in materials developed by the Eliyahu Goldratt Institute (New Haven, CT) for a workshop attended by one of the authors entitled, “Project Management the TOC Way,” 1998.

302 Chapter 8 Scheduling Resources and Costs

Appendix Summary Regardless of where one stands in the debate, the CCPM approach deserves credit for bringing resource dependency to the forefront, highlighting the modern ills of multi- tasking, and forcing us to rethink conventional methods of project scheduling. Appendix Review Questions 1. Explain how time is wasted in management of projects. 2. Distinguish between project and feeder buffers. 3. Buffers are not the same as slack. Explain.

Appendix Exercises 1. Check out the Goldratt Institute’s homepage at http://www.goldratt.com for current

information on the application of critical-chain techniques to project management. 2. Apply critical-chain scheduling principles to the Print Software, Inc., project

(Exercise 10) presented in Chapter 6. Revise the estimated time durations by 50 percent except round up the odd time durations (i.e., 3 becomes 4). Draw a CCPM network diagram similar to the one contained in Figure A8.3 for the Print Soft- ware project as well as a Gantt chart similar to Figure A8.4. How would these diagrams differ from the ones generated using the traditional scheduling technique?

Appendix References Budd, C. S., and M. J. Cooper, “Improving On-time Service Delivery: The Case of

Project as Product,” Human Systems Management, vol. 24, no. 1 (2005), pp. 67–81. Button, S., “A Critical Look at Critical Chain”, EM 540 research Paper, March 2011. Goldratt, E., Critical Chain (Great Barrington, MA: North River Press, 1997). Herroelen, W., R. Leus, and E. Demeulemeester, “Critical Chain Project Scheduling:

Do Not Oversimplify,” Project Management Journal,  vol. 33, no. 4 (2002), pp. 48–60.

Leach, L. P., “Critical Chain Project Management,” Proceedings of 29th Annual Proj- ect Management Institute, 1998, Seminars and Symposium (Newtown, PA: Project Management Institute, 1998), pp. 1239–44.

Levine, H. A., “Shared Contingency: Exploring the Critical Chain,” PM Network, October 1999, pp. 35–38.

Newbold, R. C., Project Management in the Fast Lane: Applying the Theory of Con- straints (Boca Raton, FL: St. Lucie Press, 1998).

Noreen, E., D. Smith, and J. Mackey, The Theory of Constraints and Its Implication for Management Accounting (Great Barrington, MA: North River Press, 1995).

Pinto, J., “Some Constraints on the Theory of Constraints: Taking a Critical Look at Critical Chain,” PM Network, vol. 13, no. 8 (1999), pp. 49–51.

Raz, T., R. Barnes, and D. Dvir, “A Critical Look at Critical Chain Project Manage- ment,” Project Management Journal, December 2003, pp. 24–32.

Sood, S., “Taming Uncertainty: Critical-Chain Buffer Management Helps Minimize Risk in the Project Equation,” PM Network, March 2003, pp. 57–59.

Steyn, H., “An Investigation into the Fundamentals of Critical Chain Scheduling,” International Journal of Project Management, vol. 19 (2000), pp. 363–69.

Zalmanson, E., “Readers Feedback,” PM Network, vol. 15, no. 1 (2001), p. 4.

Chapter 8 Scheduling Resources and Costs 303

Case A8.1

The CCPM Dilemma Pinyarat worked in the IT department of a diversified IT firm. She was describing the firm’s early encounters with critical-chain scheduling to a friend in another IT firm. Three years ago management decided to add 10 percent time to all activity estimates because almost all projects were coming in late. One thought was people were simply working too hard and needed some relief. This approach did not work! Projects still came in late. Next, management decided to take away the extra time for activities and add 10 percent for project estimates to ensure project durations would be met. Again, nothing improved and projects continued to come in late. Recently, the firm hired a consultant who promoted critical-chain scheduling, which was implemented for all projects in her division. Almost all failed to perform. Pinyarat explained, “The estimates were basically impossible. The activity dura- tions got squeezed down to less than the 50 percent guideline. We were late on nearly every task. In addition, I was not allowed to put in a big enough project buffer, which only added to projects being late. One colleague who was working on six projects gave up and quit; he said he was killing himself and saw no hope of things getting better. My projects are not the only ones having big problems. Some people had no idea why anyone would use CCPM scheduling. To quote one of my best programmers: ‘They ask for an estimate and then they cut it 50 percent or more.’ What kind of game is this? Apparently they don’t trust us.” A week later, to Pinyarat’s surprise, she was called to the IT manager’s office. Pinyarat imagined numerous bad scenarios of how the meeting would go—even to the remote possibility of being fired! The manager wanted the division to straighten out their project management practices and stop this business of nearly all IT projects being late. There were rumors of cleaning house or outsourcing IT work. The manager believed Pinyarat, who passed the PMP exam, had the best chance of turning things around. He said, “Pinyarat, I’m nearing the desperate level; top manage- ment is reaching the end of the rope with our division. We need to turn this around for both our sakes. Give me a plan that I can sponsor within the week.” Pinyarat explained to her friend a few of her ideas—like squeezing estimates too far. But she said she would take any ideas she could get from anyone. Give Pinyarat a report that identifies the key problems and a plan of action she can present to her sponsor. Limit your report to 800 words or less.

Reducing Project Duration9 LEARNING OBJECTIVES After reading this chapter you should be able to:

9-1 Understand the different reasons for crashing a project.

9-2 Identify the different options for crashing an activ- ity when resources are not constrained.

9-3 Identify the different options for crashing an activ- ity when resources are constrained.

9-4 Determine the optimum cost-time point in a proj- ect network.

9-5 Understand the risks associated with compressing or crashing a project.

9-6 Identify different options for reducing the costs of a project.

OUTLINE 9.1 Rationale for Reducing Project Duration

9.2 Options for Accelerating Project Completion

9.3 Project Cost–Duration Graph

9.4 Constructing a Project Cost–Duration Graph

9.5 Practical Considerations

9.6 What If Cost, Not Time, Is the Issue?

Summary

C H A P T E R N I N E

304

In skating over thin ice our safety is in our speed. —Ralph Waldo Emerson

Imagine the following scenarios: — After finalizing your project schedule, you realize the estimated completion date

is two months beyond what your boss publicly promised an important customer. — Five months into the project, you realize that you are already three weeks

behind the drop-dead date for the project. — Four months into a project top management changes its priorities and now tells

you that money is not an issue. Complete the project ASAP!

What do you do? This chapter addresses strategies for reducing project duration either prior to setting the baseline for the project or in the midst of project execution. Choice of options is based on the constraints surrounding the project. Here the project priority matrix introduced in Chapter 4 comes into play. For example, there are many more options available for reduc- ing project time if you are not resource constrained than if you cannot spend more than

Project networks

6

Managing risk 7

Monitoring progress

13

Teams 11

Outsourcing 12

Project manager

10

Strategy 2

Introduction 1

Organization 3

Schedule resources & costs

8

Intern ation

al

proje cts

15

Agile PM 16

Project closure

14

Estimate 5

Reducing duration

9

Define project

4

305

306 Chapter 9 Reducing Project Duration

your original budget. We will begin first by examining the reasons for reducing project duration followed by a discussion of different options for accelerating project completion. The chapter will conclude with the classic time-cost framework for selecting which activi- ties to “crash.” Crash is a term that has emerged in the Project Management lexicon for shortening the duration of an activity or project beyond when it can be normally done.

9.1 Rationale for Reducing Project Duration There are many good reasons for attempting to reduce the duration of a project. One of the more important reasons today is time to market. Intense global competition and rapid technological advances have made speed a competitive advantage. To succeed, companies have to spot new opportunities, launch project teams, and bring new prod- ucts or services to the marketplace in a flash. Perhaps in no industry does speed matter as much as in the electronics industry. For example, a rule of thumb for moderate- to high-technology firms is that a six-month delay in bringing a product to market can result in a loss of market share of about 35 percent. In these cases, high-technology firms typically assume that the time savings and avoidance of lost profits are worth any additional costs to reduce time without any formal analysis. See the Snapshot from Practice 9.1: Smartphone Wars for more on this.

Understand the different reasons for crashing a project.

9-1LO

Speed has been critical in business ever since the California Gold Rush. The smartphone industry is a good example of an intensely competitive business that places a premium on

speed and innovation. Analysts forecast over 14 differ- ent new smartphones on the market in 2016 including Acer Predator 6, Samsung Galaxy 7, and Iphone 7. In order to survive, RIM, Samsung, Apple, and other smartphone manufacturers have become masters at project management. They have been able to cut the market release time of new phones from 12–18 months to 6–9 months. What is at stake is over $1 billion in forecasted sales of new smartphones.

© Rex Features/AP Images

S N A P S H O T F R O M P R A C T I C E 9 . 1 Smartphone Wars*

* Hall, C., and B. O’Boyle, “Best Smartphones to Look Forward to in 2016,” pocket-lint.com, accessed January 11, 2015.

Chapter 9 Reducing Project Duration 307

Business survival depends not only on rapid innovation but also on adaptability. Global recession and energy crises have stunned the business world, and those compa- nies that survive will be those that can quickly adapt to new challenges. This requires speedy project management! For example, the fate of the U.S. auto industry depends in part on how quickly they shift their efforts to develop fuel-efficient, alternative forms of transportation. Another common reason for reducing project time occurs when unforeseen delays— for example, adverse weather, design flaws, and equipment breakdown—cause sub- stantial delays midway in the project. Getting back on schedule usually requires compressing the time on some of the remaining critical activities. The additional costs of getting back on schedule need to be compared with the consequences of being late. This is especially true when time is a top priority. Incentive contracts can make reduction of project time rewarding—usually for both the project contractor and owner. For example, a contractor finished a bridge across a lake 18 months early and received more than $6 million for the early completion. The availability of the bridge to the surrounding community 18 months early to reduce traffic gridlock made the incentive cost to the community seem small to users. In another example, in a continuous improvement arrangement, the joint effort of the owner and contractor resulted in early completion of a river lock and a 50/50 split of the savings to the owner and contractor. See Snapshot from Practice 9.2: Northridge Earthquake for a classic example of a contractor who went to great lengths to quickly complete a project with a big payoff. “Imposed deadlines” is another reason for accelerating project completion. For example, a politician makes a public statement that a new law building will be avail- able in two years. Or the president of a software company remarks in a speech that new advanced software will be available in one year. Such statements too often become imposed project duration dates—without any consideration of the problems or cost of meeting such a date. The project duration time is set while the project is in its “con- cept” phase before or without any detailed scheduling of all the activities in the proj- ect. This phenomenon occurs very frequently in practice! Unfortunately, this practice almost always leads to a higher-cost project than one that is planned using low-cost and detailed planning. In addition, quality is sometimes compromised to meet dead- lines. More important, these increased costs of imposed duration dates are seldom recognized or noted by project participants. Sometimes very high overhead costs are recognized before the project begins. For example, it may cost $80,000 per day to simply house and feed a construction crew in the farthest reaches of Northern Alaska. In these cases it is prudent to examine the direct costs of shortening the critical path versus the overhead cost savings. Usually there are opportunities to shorten a few critical activities at less than the daily over- head rate. Under specific conditions (which are not rare), huge savings are possible with little risk. Finally there are times when it is important to reassign key equipment and/or people to new projects. Under these circumstances, the cost of compressing the project can be compared with the opportunity costs of not releasing key equipment or people.

9.2 Options for Accelerating Project Completion Managers have several effective methods for crashing specific project activities when resources are not constrained. Several of these are summarized below.

308 Chapter 9 Reducing Project Duration

On January 17, 1994, a 6.8-magnitude earthquake struck the Los Angeles basin, near suburban Northridge, causing 60 deaths, thousands of inju- ries, and billions of dollars in property

damage. Nowhere was the destructive power of nature more evident than in the collapsed sections of the free- way system that disrupted the daily commute of an estimated 1 million Los Angelenos. The Northridge earthquake posed one of the greatest challenges to the California Department of Transportation (CalTrans) in its nearly 100-year history. To expedite the recovery process, Governor Pete Wilson signed an emergency declaration allowing CalTrans to streamline contracting procedures and offer attractive incentives for complet- ing work ahead of schedule. For each day that the schedule was beaten, a sizable bonus was to be awarded. Conversely, for each day over the deadline, the contractor would be penalized the same amount. The amount ($50,000 to $200,000) varied depending on the importance of the work. The incentive scheme proved to be a powerful motivator for the freeway reconstruction contractors. C. C. Myers, Inc., of Rancho Cordova, California, won the contract for the reconstruction of the Interstate 10 bridges. Myers pulled out all stops to finish the project in a blistering 66 days—a whopping 74 days ahead of schedule—and earning a $14.8 million bonus! Myers took every opportunity to save time and streamline operations. They greatly expanded the workforce. For example, 134 iron-workers were employed instead of the normal 15. Special lighting equipment was set up so that work could be performed around the clock. Likewise, the sites were prepared and special materi- als were used so that work could continue despite inclement weather that would normally shut down con- struction. The work was scheduled much like an assembly line so that critical activities were followed by

S N A P S H O T F R O M P R A C T I C E 9 . 2 Responding to the Northridge Earthquake*

the next critical activity. A generous incentive scheme was devised to reward teamwork and reach milestones early. Carpenters and iron-workers competed as teams against each other to see who could finish first. Although C. C. Myers received a substantial bonus for finishing early, they spent a lot of money on over- time, bonuses, special equipment, and other premiums to keep the job rolling along. CalTrans supported Myers’s efforts. With reconstruction work going on 24 hours a day, including jackhammering and pile-driving, CalTrans temporarily housed many families in local motels. CalTrans even erected a temporary plastic soundwall to help reduce the construction noise travel- ing to a nearby apartment complex. The double-layer curtain, 450 feet long and 20 feet high, was designed to reduce construction noise by 10 decibels. Despite the difficulties and expense incurred by around-the-clock freeway building, most of Los Angeles cheered CalTrans’s quake recovery efforts. The Governor’s Office of Planning and Research issued a report concluding that for every day the Santa Monica Freeway was closed, it cost the local economy more than $1 million.

© David Butow/Corbis SABA

* Jerry B. Baxter, “Responding to the Northridge Earthquake,” PM Network (November 1994), pp. 13–22.

Options When Resources Are Not Constrained Adding Resources  The most common method for shortening project time is to assign additional staff and equipment to activities. There are limits, however, as to how much speed can be gained by adding staff. Doubling the size of the workforce will not necessarily reduce com- pletion time by half. The relationship would be correct only when tasks can be parti- tioned so minimal communication is needed between workers, as in harvesting a crop by hand or repaving a highway. Most projects are not set up that way; additional

Identify the different options for crashing an activity when resources are not constrained.

9-2LO

Chapter 9 Reducing Project Duration 309

workers increase the communication requirements to coordinate their efforts. For example, doubling a team by adding two workers requires six times as much pairwise intercommunication than is required in the original two-person team. Not only is more time needed to coordinate and manage a larger team; there is the additional delay of training the new people and getting them up to speed on the project. The end result is captured in Brooks’s law: Adding manpower to a late software project makes it later.1 Frederick Brooks formulated this principle based on his experience as a project manager for IBM’s System/360 software project during the early 1960s. While subse- quent research confirmed Brooks’s prediction, it also discovered that adding more people to a late project does not always cause the project to be later.2 The key is whether the new staff is added early so there is sufficient time to make up for lost ground once the new members have been fully assimilated.

Outsourcing Project Work A common method for shortening the project time is to subcontract an activity. The subcontractor may have access to superior technology or expertise that will accelerate the completion of the activity. For example, contracting for a backhoe can accomplish in two hours what it can take a team of laborers two days to do. Likewise, by hiring a consulting firm that specializes in ADSI programming, a firm may be able to cut in half the time it would take for less experienced, internal programmers to do the work. Subcontracting also frees up resources that can be assigned to a critical activity and will ideally result in a shorter project duration. See Snapshot from Practice 9.3: Out- sourcing in Bio-Tech. Outsourcing will be addressed more fully in Chapter 12.

In the face of increasing time-to- market pressures, many bio-tech firms are turning to outsourcing to expedite the drug development process. Panos Kalaritis, vice president of operations

for Irix Pharmaceuticals, says that outsourcing process development can accelerate a drug’s evolution by allowing a pharmaceutical company to continue research while a contractor works on process optimiza- tion. Susan Dexter of Lonza Biologics identified different types of outsourcing contracts including agreements for product development, clinical trial supplies, in-market or commercial supplies, and technology transfer. Often, she said, a given project can encompass more than one of the above stages over a period of several years. Using a contractor, said Paul Henricks, business manager for Patheon Inc., gives the client company

access to specialized knowledge and infrastructure as well as flexible resources and capacity. The sponsoring company can also manage risks by sharing responsi- bilities through outsourcing. “Communication is key to a successful outsourc- ing relationship,” said Dan Gold, vice president of pro- cess development for Covance, which was formerly Corning Bio. “Contractors and sponsors should both assign project managers, and the two must work together to maintain, track, and document project completion. There must be a concerted effort on the part of both parties to work as partners to complete the project.”

S N A P S H O T F R O M P R A C T I C E 9 . 3 Outsourcing in Bio-Tech Picks Up Speed*

* Mathew Lerner, “Outsourcing in Bio-Technology Picks Up Speed,” Chemical Market Reporter, vol. 251, no. 14 (2002), p. 17.

1 Brooks’s The Mythical Man-Month (Reading, MA: Addison-Wesley, 1994) is considered a classic on software project management. 2 R. L. Gordon and J. C. Lamb, “A Close Look at Brooks’ Law,” Datamation, June 1977, pp. 81–86.

310 Chapter 9 Reducing Project Duration

Scheduling Overtime The easiest way to add more labor to a project is not to add more people, but to schedule overtime. If a team works 50 hours a week instead of 40, it might accomplish 20 percent more. By scheduling overtime you avoid the additional costs of coordina- tion and communication encountered when new people are added. If people involved are salaried workers, there may be no real additional cost for the extra work. Another advantage is that there are fewer distractions when people work outside normal hours. Overtime has disadvantages. First, hourly workers are typically paid time and a half for overtime and double time for weekends and holidays. Sustained overtime work by salaried employees may incur intangible costs such as divorce, burnout, and turnover. The latter is a key organizational concern when there is a shortage of workers. Further- more, it is an oversimplification to assume that, over an extended period of time, a person is as productive during his or her eleventh hour at work as during his or her third hour of work. There are natural limits to what is humanly possible, and extended overtime may actually lead to an overall decline in productivity when fatigue sets in (DeMarco, 2002). Overtime and working longer hours is the preferred choice for accelerating project completion, especially when the project team is salaried. The key is to use overtime judiciously. Remember a project is a marathon not a sprint! You do not want to run out of energy before the finish line.

Establish a Core Project Team As discussed in Chapter 3, one of the advantages of creating a dedicated core team to complete a project is speed. Assigning professionals full time to a project avoids the hidden cost of multitasking in which people are forced to juggle the demands of mul- tiple projects. Professionals are allowed to devote their undivided attention to a spe- cific project. This singular focus creates a shared goal that can bind a diverse set of professionals into a highly cohesive team capable of accelerating project completion. Factors that contribute to the emergence of high-performing project teams will be discussed in detail in Chapter 11.

Do It Twice—Fast and Correctly If you are in a hurry, try building a “quick and dirty” short-term solution, then go back and do it the right way. For example, pontoon bridges are used as temporary solutions to damaged bridges in combat. In business, software companies are notorious for releasing version 1.0 of products that are not completely finished and tested. Subse- quent versions 1.1 . . . x correct bugs and add intended functionality to the product. The additional costs of doing it twice are often more than compensated for by the benefits of satisfying the deadline.

Options When Resources Are Constrained A project manager has fewer options for accelerating project completion when addi- tional resources are either not available or the budget is severely constrained. This is especially true once the schedule has been established. Below are some of these options, which are also available when resources are not constrained.

Improve the Efficiency of the Project Team The project team may be able to improve productivity by implementing more efficient ways to do their work. This can be achieved by improving the planning and

Identify the different options for crashing an activity when resources are constrained.

9-3LO

Chapter 9 Reducing Project Duration 311

organization of the project or eliminating barriers to productivity such as excessive bureaucratic interference and red tape. Fast-Tracking Sometimes it is possible to rearrange the logic of the project network so that critical activities are done in parallel (concurrently) rather than sequentially. This alternative is commonly referred to as fast tracking and is a good one if the project situation is right. When this alternative is given serious attention, it is amazing to observe how creative project team members can be in finding ways to restructure sequential activities in paral- lel. As noted in Chapter 6, one of the most common methods for restructuring activities is to change a finish-to-start relationship to a start-to-start relationship. For example, instead of waiting for the final design to be approved, manufacturing engineers can begin building the production line as soon as key specifications have been established. Changing activi- ties from sequential to parallel is not without risk. Late design changes can produce wasted effort and rework. Fast tracking requires close coordination among those respon- sible for the activities affected and confidence in the work that has been completed. Critical-Chain Critical-chain project management (CCPM) is designed to accelerate project comple- tion. As discussed in Appendix 8.1, it would be difficult to apply CCPM midstream in a project. CCPM requires considerable training and a shift in habits and perspectives that takes time to adopt. Although there have been reports of immediate gains, espe- cially in terms of completion times, a long-term management commitment is probably necessary to reap full benefits. See the Snapshot from Practice 9.4: The Fastest House in the World for an extreme example of CCPM application. Reducing Project Scope Probably the most common response for meeting unattainable deadlines is to reduce or scale back the scope of the project. This invariably leads to a reduction in the functional- ity of the project. For example, the new car will average only 25 mpg instead of 30, or the software product will have fewer features than originally planned. While scaling back the scope of the project can lead to big savings in both time and money, it may come at a cost of reducing the value of the project. If the car gets lower gas mileage, will it stand up to competitive models? Will customers still want the software minus the features? The key to reducing a project scope without reducing value is to reassess the true specifications of the project. Often requirements are added under best-case, blue-sky scenarios and represent desirables, but not essentials. Here it is important to talk to the customer and/or project sponsors and explain the situation—you can get it your way but not until February. This may force them to accept an extension or to add money to expedite the project. If not, then a healthy discussion of what the essential require- ments are and what items can be compromised in order to meet the deadline needs to take place. More intense reexamination of requirements may actually improve the value of the project by getting it done more quickly and for a lower cost. Calculating the savings of reduced project scope begins with the work breakdown structure. Reducing functionality means certain tasks, deliverables, or requirements can be reduced or even eliminated. These tasks need to be found and the schedule adjusted. Focus should be on changes in activities on the critical path. Compromise Quality Reducing quality is always an option, but it is rarely acceptable or used. If quality is sacrificed, it may be possible to reduce the time of an activity on the critical path.

312 Chapter 9 Reducing Project Duration

December 17, 2002—After revving up their power tools and lin-

ing up volunteers, Shelby County Habitat for Humanity broke the world record for the fastest house ever built, clock- ing in at 3 hours, 26 minutes, and 34 seconds. Former record holder New Zealand’s Habitat Affiliate Mannakau held the record for three years at 3 hours, 44 minutes, and 59 seconds. The Alabama project beat the New Zealand record by 18 minutes. “This was different than any construction project that I’ve ever been a part of,” said Project Manager Chad Calhoun. “The minute-by-minute schedule, the planning of each precise movement, the organization of all the teams and materials, could not have gone more smoothly on build day. All the long hours of plan- ning definitely paid off.” In preparation for the build, Habitat volunteers put the foundation in place and constructed prefabricated wall panels. Once the whistle blew at 11:00 a.m. on December 17th, the exterior wall panels were raised into place, followed by the interior panel, which took only 16 minutes. Special color coded teams of workers connected the wiring and plumbing, put in insulation, installed appliances, laid carpet and tile, installed light fixtures, painted the house inside, applied vinyl siding outside, and attached assembled front and back porches. At the same time, the roof was constructed on the ground next to the house. Once the roof was completed—approximately 1½ hours later—a Steel City crane lifted the 14,000–pound roof assembly into

S N A P S H O T F R O M P R A C T I C E 9 . 4 The Fastest House in the World*

place. Crews attached the roof while others completed the interior work. There was even time to lay sod, plant shrubbery, and decorate a Christmas tree in the front yard—all within the official build time of 3 hours, 26 minutes, and 34 seconds. The recipient of this wonderful holiday gift was Bonnie Lilly, a single mother and nursing technician who had applied to Habitat for Humanity three times before she was selected to receive the three-bedroom, two-bath home. “It’s amazing,” Lilly said. “Who am I to have this happen for me? A world record, hundreds of people coming together to build my house—I still can’t believe it.” Habitat for Humanity is an international charitable organization that builds simple, affordable houses and sells them on a no-interest, no-profit basis to needy families.

© Blend Images/Ariel Skelley/Getty Images

* “The house that love built, really FAST—and just in time for Christmas kicker: Habitat for Humanity breaks world record set by New Zealand,” Erin Drummond, www.csre.com. “Shelby County, Ala. Builds fastest Habitat House in three and a half hours,” www.habitat.org/newsroom/2002archive.

In practice the methods most commonly used to crash projects are scheduling over- time, outsourcing, and adding resources. Each of these maintains the essence of the original plan. Options that depart from the original project plan include do it twice and fast-tracking. Rethinking of project scope, customer needs, and timing become major considerations for these techniques.

Chapter 9 Reducing Project Duration 313

9.3 Project Cost–Duration Graph Nothing on the horizon suggests that the need to shorten project time will change. In fact, if anything the pressure to get projects done quicker and sooner is likely to increase in importance. The challenge for the project manager is to use a quick, logical method to compare the benefits of reducing project time with the cost. When sound, logical methods are absent, it is difficult to isolate those activities that will have the greatest impact on reducing project time at least cost. This section describes a proce- dure for identifying the costs of reducing project time so that comparisons can be made with the benefits of getting the project completed sooner. The method requires gathering direct and indirect costs for specific project durations. Critical activities are searched to find the lowest direct-cost activities that will shorten the project duration. Total cost for specific project durations are computed and then compared with the benefits of reducing project time—before the project begins or while it is in progress.

Explanation of Project Costs The general nature of project costs is illustrated in Figure 9.1, Project Cost–Duration Graph. The total cost for each duration is the sum of the indirect and direct costs. Indirect costs continue for the life of the project. Hence, any reduction in project dura- tion means a reduction in indirect costs. Direct costs on the graph grow at an increas- ing rate as the project duration is reduced from its original planned duration. With the information from a graph such as this for a project, managers can quickly judge any alternative such as meeting a time-to-market deadline. Further discussion of indirect and direct costs is necessary before demonstrating a procedure for developing the information for a graph similar to the one depicted in Figure 9.1. Project Indirect Costs Indirect costs generally represent overhead costs such as supervision, administration, consultants, and interest. Indirect costs cannot be associated with any particular work

Determine the optimum cost-time point in a project network.

9-4LO

60

50

40

30

20

10

4 6 8 10 12 14 16 Project duration

Total costs

Indirect costs

Direct costs

Optimum cost-time

point

Low-cost plan duration

pointC os

ts

0

FIGURE 9.1 Project Cost– Duration Graph

314 Chapter 9 Reducing Project Duration

package or activity, hence the term. Indirect costs vary directly with time. That is, any reduction in time should result in a reduction of indirect costs. For example, if the daily costs of supervision, administration, and consultants are $2,000, any reduction in project duration would represent a savings of $2,000 per day. If indirect costs are a significant percentage of total project costs, reductions in project time can represent very real savings (assuming the indirect resources can be utilized elsewhere).

Project Direct Costs Direct costs commonly represent labor, materials, equipment, and sometimes subcon- tractors. Direct costs are assigned directly to a work package and activity, hence the term. The ideal assumption is that direct costs for an activity time represent normal costs, which typically mean low-cost, efficient methods for a normal time. When proj- ect durations are imposed, direct costs may no longer represent low-cost, efficient methods. Costs for the imposed duration date will be higher than for a project duration developed from ideal normal times for activities. Because direct costs are assumed to be developed from normal methods and time, any reduction in activity time should add to the costs of the activity. The sum of the costs of all the work packages or activities represents the total direct costs for the project. The major challenge faced in creating the information for a graph similar to Fig- ure 9.1 is computing the direct cost of shortening individual critical activities and then finding the total direct cost for each project duration as project time is compressed; the process requires selecting those critical activities that cost the least to shorten. (Note: The graph implies that there is always an optimum cost-time point. This is only true if shortening a schedule has incremental indirect cost savings exceeding the incremental direct cost incurred. However, in practice there are almost always several activities in which the direct costs of shortening are less than the indirect costs.)

9.4 Constructing a Project Cost–Duration Graph There are three major steps required to construct a project cost–duration graph: 1. Find total direct costs for selected project durations. 2. Find total indirect costs for selected project durations. 3. Sum direct and indirect costs for these selected durations. The graph is then used to compare additional cost alternatives for benefits. Details of these steps are presented here.

Determining the Activities to Shorten The most difficult task in constructing a cost–duration graph is finding the total direct costs for specific project durations over a relevant range. The central concern is to decide which activities to shorten and how far to carry the shortening process. Basi- cally, managers need to look for critical activities that can be shortened with the small- est increase in cost per unit of time. The rationale for selecting critical activities depends on identifying the activity’s normal and crash times and corresponding costs. Normal time for an activity represents low-cost, realistic, efficient methods for com- pleting the activity under normal conditions. Shortening an activity is called crashing. The shortest possible time an activity can realistically be completed in is called its crash time. The direct cost for completing an activity in its crash time is called crash cost. Both normal and crash times and costs are collected from personnel most familiar

Chapter 9 Reducing Project Duration 315

with completing the activity. Figure 9.2 depicts a hypothetical cost–duration graph for an activity. The normal time for the activity is 10 time units, and the corresponding cost is $400. The crash time for the activity is five time units and $800. The intersection of the normal time and cost represents the original low-cost, early-start schedule. The crash point represents the maximum time an activity can be compressed. The heavy line connecting the normal and crash points represents the slope, which assumes the cost of reducing the time of the activity is constant per unit of time. The assumptions underlying the use of this graph are as follows: 1. The cost-time relationship is linear. 2. Normal time assumes low-cost, efficient methods to complete the activity. 3. Crash time represents a limit—the greatest time reduction possible under realistic

conditions. 4. Slope represents cost per unit of time. 5. All accelerations must occur within the normal and crash times. Knowing the slope of activities allows managers to compare which critical activities to shorten. The less steep the cost slope of an activity, the less it costs to shorten one time period; a steeper slope means it will cost more to shorten one time unit. The cost per unit of time or slope for any activity is computed by the following equation:

Cost slope = RiseRun = Crash cost − Normal cost Normal time − Crash time

= CC − NCNT − CT = $800 − $400

10 − 5

= $4005 = $80 per unit of time

In Figure 9.2 the rise is the y axis (cost) and the run is the x axis (duration). The slope of the cost line is $80 for each time unit the activity is reduced; the limit reduction of the

FIGURE 9.2 Activity Graph $800

600

400

200

0 5 10 Activity duration (units)

Normal point

Crash pointCrash cost

Normal cost

A ct

iv ity

c os

t

0

316 Chapter 9 Reducing Project Duration

activity time is five time units. Comparison of the slopes of all critical activities allows us to determine which activity(ies) to shorten to minimize total direct cost. Given the preliminary project schedule (or one in progress) with all activities set to their early-start times, the process of searching critical activities as candidates for reduction can begin. The total direct cost for each specific compressed project duration must be found.

A Simplified Example Figure 9.3A presents normal and crash times and costs for each activity, the computed slope and time reduction limit, the total direct cost, and the project network with a duration of 25 time units. Note the total direct cost for the 25-period duration is $450. This is an anchor point to begin the procedure of shortening the critical path(s) and finding the total direct costs for each specific duration less than 25 time units. The maximum time reduction of an activity is simply the difference between the normal and crash times for an activity. For example, activity D can be reduced from a normal

10

Activity ID

A

B

C

D

E

F

G

$20

40

30

25

30

30

0

1

2

1

4

2

1

0

Maximum crash time

Direct costs

CrashNormal

3

6

10

11

8

5

6

Time

$50

80

60

50

100

40

70

Cost

2

4

9

7

6

4

6

Time

$70

160

90

150

160

70

70

Cost Slope

Time 25

C

6x

G

6

B

3

A

Initial total direct cost

Total direct cost Legend

ACT

DUR

$ 450

Total direct cost $ 470

Activities changed A

$20

$450

11

D

8

E

5

F

(A)

(B)

10

Time 24

C

6x

G

6

B

2x

A

11

D

8

E

5

F

FIGURE 9.3 Cost–Duration Trade-off Example

Chapter 9 Reducing Project Duration 317

time of 11 time units to a crash time of 7 time units, or a maximum of 4 time units. The positive slope for activity D is computed as follows:

Slope = Crash cost − Normal costNormal time − Crash time = $150 − $50

11 − 7

= $1004 = $25 per period reduced

The network shows the critical path to be activities A, D, F, G. Because it is impossible to shorten activity G (“x” is used to indicate this), activity A is circled because it is the least-cost candidate; that is, its slope ($20) is less than the slopes for activities D and F ($25 and $30). Reducing activity A one time unit cuts the project duration to 24 time units but increases the total direct costs to $470 ($450 + $20 = $470). Figure 9.3B reflects these changes. The duration of activity A has been reduced to two time units; the “x” indicates the activity cannot be reduced any further. Activity D is circled because it costs the least ($25) to shorten the project to 23 time units. Compare the cost of activity F. The total direct cost for a project duration of 23 time units is $495 (see Figure 9.4A).

FIGURE 9.4 Cost–Duration Trade-off Example (continued)

Total direct cost $ 495

Activities changed D

$25

(A)

10

Time 23

C

6x

G

6

B

2x

A

10

D

8

E

5

F

Total direct cost $ 525

Activities changed F

$30

(B)

10

Time 22

C

6x

G

6

B

2x

A

10

D

8

E

4x

F

Total direct cost $ 610

Activities changed C

$30 D

$25 E

$30

(C)

9x

Time 21

C

6x

G

6

B

2x

A

9

D

7

E

4x

F

318 Chapter 9 Reducing Project Duration

Observe that the project network in Figure 9.4A now has two critical paths—A, C, F, G and A, D, F, G. Reducing the project to 22 time units will require that activity F be reduced; thus, it is circled. This change is reflected in Figure 9.4B. The total direct cost for 22 time units is $525. This reduction has created a third critical path—A, B, E, G; all activities are critical. The least-cost method for reducing the project duration to 21 time units is the combination of the circled activities C, D, E which cost $30, $25, $30, respectively, and increase total direct costs to $610. The results of these changes are depicted in Figure 9.4C. Although some activities can still be reduced (those with- out the “x” next to the activity time), no activity or combination of activities will result in a reduction in the project duration. With the total direct costs for the array of specific project durations found, the next step is to collect the indirect costs for these same durations. These costs are typically a rate per day and are easily obtained from the accounting department. Figure 9.5 pres- ents the total direct costs, total indirect costs, and total project costs. These same costs are plotted in Figure 9.6. This graph shows that the optimum cost-time duration is 22 time units and $775. Assuming the project will actually materialize as planned, any movement away from this time duration will increase project costs. The movement from 25 to 22 time units occurs because, in this range, the absolute slopes of the indi- rect costs are greater than the direct cost slopes.

9.5 Practical Considerations

Using the Project Cost–Duration Graph This graph, as presented in Figures 9.1 and 9.6, is valuable to compare any proposed alternative or change with the optimum cost and time. More importantly, the creation of such a graph keeps the importance of indirect costs in the forefront of decision

Project duration

25

24

23

22

21

Direct costs

+ =

450

470

495

525

610

Indirect costs

400

350

300

250

200

Total costs

$850

820

795

775

810

FIGURE 9.5 Summary Costs by Duration

$1,000

800

600

400

200

20 21 22 23 24 25

Duration (units)

Total project

cost

$775

Total direct cost

Total indirect

cost

C os

t 0

Optimum cost-time

point

FIGURE 9.6 Project Cost–Duration Graph

Chapter 9 Reducing Project Duration 319

making. Indirect costs are frequently forgotten in the field when the pressure for action is intense. Finally, such a graph can be used before the project begins or while the project is in progress.  Creating the graph in the preproject planning phase without an imposed duration is the first choice because normal time is more meaningful. Creating the graph in the project planning phase with an imposed duration is less desirable because normal time is made to fit the imposed date and is probably not low cost. Creating the graph after the project has started is the least desirable because some alternatives may be ruled out of the decision process. Managers may choose not to use the formal procedure demon- strated. However, regardless of the method used, the principles and concepts inherent in the formal procedure are highly applicable in practice and should be considered in any cost–duration trade-off decision.

Crash Times Collecting crash times for even a moderate-size project can be difficult. The meaning of crash time is difficult to communicate. What is meant when you define crash time as “the shortest time you can realistically complete an activity”? Crash time is open to different interpretations and judgments. Some estimators feel very uncomfortable pro- viding crash times. Regardless of the comfort level, the accuracy of crash times and costs is frequently rough at best, when compared with normal time and cost.

Linearity Assumption Because the accuracy of compressed activity times and costs is questionable, the con- cern of some theorists—that the relationship between cost and time is not linear but curvilinear—is seldom a concern for practicing managers. Reasonable, quick compari- sons can be made using the linear assumption.3 The simple approach is adequate for most projects. There are rare situations in which activities cannot be crashed by single time units. Instead, crashing is “all or nothing.” For example, activity A will take 10 days (for say $1,000) or it will take 7 days (for say $1,500), but no options exist in which activity A will take 8 or 9 days to complete. In a few rare cases of very large, complex, long-duration projects, the use of present value techniques may be useful; such techniques are beyond the scope of this text.

Choice of Activities to Crash Revisited The cost–time crashing method relies on choosing the cheapest method for reducing the duration of the project. There are other factors that should be assessed beyond sim- ply cost. First, the inherent risks involved in crashing particular activities need to be considered. Some activities are riskier to crash than others. For example, accelerating the completion of a software design code may not be wise if it increases the likelihood of errors surfacing downstream. Conversely, crashing a more expensive activity may be wise if fewer inherent risks are involved. Second, the timing of activities needs to be considered. Crashing an early activity may be prudent if there is concern that subsequent activities are likely to be delayed, and absorb the time gained. Then the manager would still have the option of crashing final activities to get back on schedule. Third, crashing frequently results in overallocation of resources. The resources required to accelerate a cheaper activity may suddenly not be available. Resource availability, not cost, may dictate which activities are crashed.

Understand the risks as- sociated with compress- ing or crashing a project.

9-5LO

3Linearity assumes that the cost for crashing each day is constant.

320 Chapter 9 Reducing Project Duration

Finally, the impact crashing would have on the morale and motivation of the project team needs to be assessed. If the least-cost method repeatedly signals a subgroup to accelerate progress, fatigue and resentment may set in. Conversely, if overtime pay is involved, other team members may resent not having access to this benefit. This situation can lead to tension within the entire project team. Good project managers gauge the response that crashing activities will have on the entire project team. See Snapshot from Practice 9.5: I’ll Bet You… for a novel approach to motivating employees to work faster.

Time Reduction Decisions and Sensitivity Should the project owner or project manager go for the optimum cost-time? The answer is, “It depends.” Risk must be considered. Recall from our example that the

The focus of this chapter has been on how project managers crash activities by typically assigning additional man- power and equipment to cut significant time off of scheduled tasks. Project

managers often encounter situations in which they need to motivate individuals to accelerate the completion of a specific, critical task. Imagine the following scenario. Bruce Young just received a priority assignment from corporate headquarters. The preliminary engi- neering sketches that were due tomorrow need to be e-mailed to the West Coast by 4:00 p.m. today so that the model shop can begin construction of a prototype to present to top management. He approaches Danny Whitten, the draftsman responsible for the task, whose initial response is, “That’s impossible!” While he agrees that it would be very difficult he does not believe that it is as impossible as Danny suggests or that Danny truly believes that. What should he do? He tells Danny that he knows this is going to be a rush job, but he is confident that he can do it. When Danny balks, he responds, “I tell you what, I’ll make a bet with you. If you are able to finish the design by 4:00, I’ll make sure you get two of the company’s tick- ets to tomorrow night’s Celtics–Knicks basketball game.” Danny accepts the challenge, works feverishly to complete the assignment, and is able to take his daughter to her first professional basketball game. Conversations with project managers reveal that many use bets like this one to motivate extraordinary performance. These bets range from tickets to sporting and entertainment events to gift certificates at high-class restaurants to a well-deserved afternoon off. For bets to work they need to adhere to the principles of expectancy theory of motivation.* Boiled down to simple terms, expectancy theory rests on three key questions:

S N A P S H O T F R O M P R A C T I C E 9 . 5 I’II Bet You . . .

1. Can I do it (Is it possible to meet the challenge)?

2. Will I get it (Can I demonstrate that I met the chal- lenge and can I trust the project manager will de- liver his/her end of the bargain)?

3. Is it worth it (Is the payoff of sufficient personal value to warrant the risk and extra effort)?

If in the mind of the participant the answer to any of these three questions is no, then the person is unlikely to accept the challenge. However, when the answers are affirmative, then the individual is likely to accept the bet and be motivated to meet the challenge. Bets can be effective motivational tools and add an element of excitement and fun to project work. But, the following practical advice should be heeded:

1. The bet has greater significance if it also benefits fam- ily members or significant others. Being able to take a son or daughter to a professional basketball game al- lows that individual to “score points” at home through work. These bets also recognize and reward the sup- port project members receive from their families and reinforces the importance of their work to loved ones.

2. Bets should be used sparingly; otherwise every- thing can become negotiable. They should be used only under special circumstances that require ex- traordinary effort.

3. Individual bets should involve clearly recognizable individual effort, otherwise others may become jealous and discord may occur within a group. As long as others see it as requiring truly remarkable, “beyond the call of duty” effort, they will consider it fair and warranted.

* Expectancy Theory is considered one of the major theories of human motivation and was first developed by V. H. Vroom, Work and Motivation (New York: John Wiley & Sons, 1964).

Chapter 9 Reducing Project Duration 321

optimum project time point represented a reduced project cost and was less than the original normal project time (review Figure 9.6). The project direct-cost line near the normal point is usually relatively flat. Because indirect costs for the project are usually greater in the same range, the optimum cost-time point is less than the normal time point. Logic of the cost-time procedure suggests managers should reduce the project duration to the lowest total cost point and duration. How far to reduce the project time from the normal time toward the optimum depends on the sensitivity of the project network. A network is sensitive if it has sev- eral critical or near-critical paths. In our example project movement toward the opti- mum time requires spending money to reduce critical activities, resulting in slack reduction and/or more critical paths and activities. Slack reduction in a project with several near-critical paths increases the risk of being late. The practical outcome can be a higher total project cost if some near-critical activities are delayed and become critical; the money spent reducing activities on the original critical path would be wasted. Sensitive networks require careful analysis. The bottom line is that compres- sion of projects with several near-critical paths reduces scheduling flexibility and increases the risk of delaying the project. The outcome of such analysis will probably suggest only a partial movement from the normal time toward the optimum time. There is a positive situation where moving toward the optimum time can result in very real, large savings—this occurs when the network is insensitive. A project network is insensitive if it has a dominant critical path, that is, no near-critical paths. In this project circumstance, movement from the normal time point toward the optimum time will not create new or near-critical activities. The bottom line here is that the reduction of the slack of noncritical activities increases the risk of their becoming critical only slightly when compared with the effect in a sensitive network. Insensitive networks hold the greatest potential for real, sometimes large, savings in total project costs with a minimum risk of noncritical activities becom- ing critical. Insensitive networks are not a rarity in practice; they occur in perhaps 25 percent of all projects. For example, a light rail project team observed from their network a dominant critical path and relatively high indirect costs. It soon became clear that by spending some dollars on a few critical activities, very large savings of indirect costs could be realized. Savings of several million dollars were spent extending the rail line and adding another station. The logic found in this example is just as applicable to small projects as large ones. Insensitive networks with high indirect costs can produce large savings. Ultimately, deciding if and which activities to crash is a judgment call requiring careful consideration of the options available, the costs and risks involved, and the importance of meeting a deadline.

9.6 What If Cost, Not Time, Is the Issue? In today’s fast-paced world, there appears to be a greater emphasis on getting things done quickly. Still, organizations are always looking for ways to get things done cheaply. This is especially true for fixed-bid projects, where profit margin is derived from the difference between the bid and actual cost of the project. Every dollar saved is a dollar in your pocket. Sometimes, in order to secure a contract, bids are tight, which puts added pressure on cost containment. In other cases, there are financial incentives tied to cost containment.

Identify different options for reducing the costs of a project.

9-6LO

322 Chapter 9 Reducing Project Duration

Even in situations where cost is transferred to customers there is pressure to reduce cost. Cost overruns make for unhappy customers and can damage future business opportunities. Budgets can be fixed or cut, and when contingency funds are exhausted, then cost overruns have to be made up with remaining activities. As discussed earlier, shortening project duration may come at the expense of over- time, adding additional personnel, and using more expensive equipment and/or materi- als. Conversely, sometimes cost savings can be generated by extending the duration of a project. This may allow for a smaller workforce, less-skilled (expensive) labor, and even cheaper equipment and materials to be used. Below are some of the more com- monly used options for cutting costs.

Reduce Project Scope Just as scaling back the scope of the project can gain time, delivering less than what was originally planned also produces significant savings. Again, calculating the sav- ings of a reduced project scope begins with the work breakdown structure. However, since time is not the issue, you do not need to focus on critical activities. For example, on over-budget movie projects it is not uncommon to replace location shots with stock footage to cut costs.

Have Owner Take on More Responsibility One way of reducing project costs is identifying tasks that customers can do them- selves. Homeowners frequently use this method to reduce costs on home improvement projects. For example, to reduce the cost of a bathroom remodel, a homeowner may agree to paint the room instead of paying the contractor to do it. On IS projects, a cus- tomer may agree to take on some of the responsibility for testing equipment or provid- ing in-house training. Naturally, this arrangement is best negotiated before the project begins. Customers are less receptive to this idea if you suddenly spring it on them. An advantage of this method is that, while costs are lowered, the original scope is retained. Clearly this option is limited to areas in which the customer has expertise and the capability to pick up the tasks.

Outsourcing Project Activities or Even the Entire Project When estimates exceed budget, it not only makes sense to re-examine the scope but also search for cheaper ways to complete the project. Perhaps instead of relying on internal resources, it would be more cost effective to outsource segments or even the entire project, opening up work to external price competition. Specialized subcontrac- tors often enjoy unique advantages, such as material discounts for large quantities, as well as equipment that not only gets the work done more quickly but also less expen- sively. They may have lower overhead and labor costs. For example, to reduce costs of software projects, many American firms outsource work to firms overseas where the salary of a software engineer is one-third that of an American software engineer. How- ever, outsourcing means you have less control over the project and will need to have clearly definable deliverables.

Brainstorming Cost Savings Options Just as project team members can be a rich source of ideas for accelerating project activities, they can offer tangible ways for reducing project costs. For example, one project manager reported that his team was able to come up with over $75,000 worth

Chapter 9 Reducing Project Duration 323

Summary The need for reducing the project duration occurs for many reasons such as imposed duration dates, time-to-market considerations, incentive contracts, key resource needs, high overhead costs, or simply unforeseen delays. These situations are very common in practice and are known as cost-time trade-off decisions. This chapter presented a logi- cal, formal process for assessing the implications of situations that involve shortening the project duration. Crashing the project duration increases the risk of being late. How far to reduce the project duration from the normal time toward the optimum de- pends on the sensitivity of the project network. A sensitive network is one that has several critical or near-critical paths. Great care should be taken when shortening sen- sitive networks to avoid increasing project risks. Conversely, insensitive networks rep- resent opportunities for potentially large project cost savings by eliminating some overhead costs with little downside risk. Alternative strategies for reducing project time were discussed within the context of whether or not the project is resource limited. Project acceleration typically comes at a cost of either spending money for more resources or compromising the scope of the project. If the latter is the case, then it is essential that all relevant stakeholders be con- sulted so that everyone accepts the changes that have to be made. One other key point is the difference in implementing time-reducing activities in the midst of project exe- cution versus incorporating them into the project plan. You typically have far fewer options once the project is under way than before it begins. This is especially true if you want to take advantage of the new scheduling methodologies such as fast-tracking and critical-chain. Time spent up front considering alternatives and developing contin- gency plans will lead to time savings in the end.

Key Terms Crashing, 314 Crash point, 315 Crash time, 314

Direct costs, 314 Fast-tracking, 311 Indirect costs, 313

Project Cost–Duration Graph, 313

1. What are five common reasons for crashing a project? 2. What are the advantages and disadvantages of reducing project scope to accelerate

a project? What can be done to reduce the disadvantages? 3. Why is scheduling overtime a popular choice for getting projects back on schedule?

What are the potential problems for relying on this option? 4. Identify four indirect costs you might find on a moderately complex project. Why

are these costs classified as indirect? 5. How can a cost–duration graph be used by the project manager? Explain. 6. Reducing the project duration increases the risk of being late. Explain. 7. It is possible to shorten the critical path and save money. Explain how.

Review Questions

of cost saving suggestions without jeopardizing the scope of the project. Project managers should not underestimate the value of simply asking if there is a cheaper, better way.

324 Chapter 9 Reducing Project Duration

1. Use the information contained below to compress one time unit per move using the least cost method. Reduce the schedule until you reach the crash point of the network. For each move identify what activity(ies) was crashed and the adjusted total cost.

Note: The correct normal project duration, critical path, and total direct cost are provided.

Act. Crash Cost (Slope) Maximum Crash Time Normal Time Normal Cost

A 50 1 3 150 B 100 1 3 100 C 60 2 4 200 D 60 2 3 200 E 70 1 4 200 F 0 0 1 150

1x

F

3

B

3

A

3

D Initial project duration: 12

Total direct cost: 4

E

4

C 1,000

2. *Use the information contained below to compress one time unit per move using the least cost method. Reduce the schedule until you reach the crash point of the network. For each move identify what activity(ies) was crashed and the adjusted total cost.

Note: Choose B instead of C and E (equal costs) because it is usually smarter to crash early rather than late AND one activity instead of two activities

Act. Crash Cost (Slope) Maximum Crash Time Normal Time Normal Cost

A 0 2 150 B 100 1 3 100 C 50 2 4 200 D 40 1 4 200 E 50 1 3 200 F 0 1 150

1x

F

3

B

2x

A

6

C Initial project duration 13

Total direct cost 3

E

4

D 1,000

Exercises

Chapter 9 Reducing Project Duration 325

3. Use the information contained below to compress one time unit per move using the least cost method. Reduce the schedule until you reach the crash point of the network. For each move identify what activity(ies) was crashed and the adjusted total cost.

Act. Crash Cost (Slope) Maximum Crash Time Normal Time Normal Cost

A 100 1 2 150 B 80 1 3 100 C 60 1 2 200 D 40 1 5 200 E 40 2 5 200 F 40 2 3 150 G 20 1 5 200 H 1 200

16

1,400

Project duration

Total direct cost

B

D G

C

2

A

2

3

E

5

5 5

H

1x

F

3

4. Given the data and information that follow, compute the total direct cost for each project duration. If the indirect costs for each project duration are $90 (15 time units), $70 (14), $50 (13), $40 (12), and $30 (11), compute the total project cost for each duration. What is the optimum cost-time schedule for the project? What is this cost?

Act. Crash Cost (Slope) Maximum Crash Time Normal Time Normal Cost

A   30 1 5     50 B   60 2 3     60 C     0 0 4     70 D   10 1 2     50 E   60 3 5   100 F 100 1 2     90 G   30 1 5     50 H   40 0 2     60 I 200 1 3     200 $730

D I

E

F

G

C

H

Initial project duration 15

Total direct cost $730

3

25

52

24

B

A

5

3

326 Chapter 9 Reducing Project Duration

5. Use the information contained below to compress one time unit per move using the least cost method. Assume the total indirect cost for the project is $700 and there is a savings of $50 per time unit reduced. Record the total direct, indirect, and project costs for each duration. What is the optimum cost-time schedule for the project? What is the cost?

Note: The correct normal project duration and total direct cost are provided.

Act. Crash Cost (Slope) Maximum Crash Time Normal Time Normal Cost

A 0 2 100 B 100 1 3 200 C 40 1 5 200 D 60 2 3 200 E 20 1 5 200 F 40 1 4 150 G 0 2 150

G

C

D

E A

B

F

Project duration 14

Total direct cost 1,200

2x 2x

4

5

5

33

6. If the indirect costs for each duration are $300 for 27 days, $240 for 26 days, $180 for 25 days, $120 for 24 days, $60 for 23 days, and $50 for 22 days, compute the direct, indirect, and total costs for each duration. What is the optimum cost-time schedule? The customer offers you $10 for every day you shorten the project from your original network. Would you take it? If so for how many days?

Act. Crash Cost (Slope) Maximum Crash Time Normal Time Normal Cost

A   80 2 10     40 B   30 3   8     10 C   40 1   5     80 D   50 2 11     50 E 100 4 15   100 F   30 1   6     20 $300

B F

C

D

Project duration

Total direct cost

A

E

10

8

5 15

11

6

27

$300

Chapter 9 Reducing Project Duration 327

7. Use the information contained below to compress one time unit per move using the least cost method. Assume the total indirect cost for the project is $2,000 and there is a savings of $100 per time unit reduced. Calculate the total direct, indirect, and project costs for each duration. Plot these costs on a graph. What is the optimum cost-time schedule for the project?

Note: The correct normal project duration and total direct cost are provided.

Act. Crash Cost (Slope) Maximum Crash Time Normal Time Normal Cost

A 0 2 200 B 50 1 4 1000 C 200 2 5 800 D 200 2 5 1000 E 100 1 3 800 F 40 1 5 1000 G 40 1 4 1000 H 0 1 200

Total cost 8,000

Project duration 20

Direct cost 6,000 1x

H

5

C

5

F

4

G

5

D

4

B

2x

A

3

E

Indirect cost 2,000

8.* Use the information contained below to compress one time unit per move using the least cost method. Reduce the schedule until you reach the crash point of the network. For each move identify what activity(ies) was crashed, the adjusted total cost, and explain your choice if you have to choose between activities that cost the same.

If the indirect cost for each duration is $1,500 for 17 weeks, $1,450 for 16 weeks, $1,400 for 15 weeks, $1,350 for 14 weeks, $1,300 for 13 weeks, $1,250 for 12 weeks, $1,200 for 11 weeks, and $1,150 for 10 weeks, what is the optimum cost-time schedule for the project? What is the cost?

* The solution to this exercise can be found in Appendix One.

328 Chapter 9 Reducing Project Duration

Act. Crash Cost (Slope) Maximum Crash Time Normal Time Normal Cost

A     0 0 3 150 B 100 1 4 200 C   60 1 3 250 D   40 1 4 200 E     0 0 2 250 F   30 2 3 200 G   20 1 2 250 H   60 2 4 300 I 200 1 2 200

D

4

A

3x

I

2

E

G

Normal time 17

Total direct cost $2,000

C

F

2

H

42x3

B

34

Abdel-Hamid, T., and S. Madnick, Software Project Dynamics: An Integrated Approach (Englewood Cliffs, NJ: Prentice Hall, 1991). Baker, B. M., “Cost/Time Trade-off Analysis for the Critical Path Method,” Journal of the Operational Research Society, vol. 48, no. 12 (1997), pp. 1241–44. Brooks, F. P., Jr., The Mythical Man-Month: Essays on Software Engineering Anniversary Edition (Reading, MA: Addison-Wesley Longman, Inc., 1994), pp. 15–26. DeMarco, T., Slack: Getting Past Burnout, Busywork, and the Myth of Total Efficiency (New York: Broadway, 2002). Gordon, R. I. and J. C. Lamb, “A Closer Look at Brooke’s Law,” Datamation, June 1977, pp. 81–86. Ibbs, C. W., S. A. Lee, and M. I. Li, “Fast-Tracking’s Impact on Project Change,” Project Management Journal, vol. 29, no. 4 (1998), pp. 35–42. Khang, D. B., and M.Yin, “Time, Cost, and Quality Trade-off in Project Management,” International Journal of Project Management, vol. 17, no. 4 (1999), pp. 249–56. Perrow, L. A., Finding Time: How Corporations, Individuals, and Families Can Benefit From New Work Practices (Ithaca, NY: Cornell University Press, 1997). Roemer, T. R., R. Ahmadi, and R. Wang, “Time-Cost Trade-offs in Overlapped Product Development,” Operations Research, vol. 48, no. 6 (2000), pp. 858–65. Smith, P. G., and D. G. Reinersten, Developing Products in Half the Time (New York: Van Nostrand Reinhold, 1995). Verzuh, E., The Fast Forward MBA in Project Management, 4th ed. (New York: John Wiley, 2012). Vroom, V. H., Work and Motivation (New York: John Wiley & Sons, 1964).

References

Chapter 9 Reducing Project Duration 329

Case 9.1

International Capital, Inc.—Part B Given the project network derived in Part A of the case from Chapter 7, Brown also wants to be prepared to answer any questions concerning compressing the project duration. This question will almost always be entertained by the accounting depart- ment, review committee, and the client. To be ready for the compression question, Brown has prepared the following data in case it is necessary to crash the project. (Use your weighted average times (te) computed in Part A of the International Capital case found in Chapter 7.)

Activity Normal Cost Maximum Crash Time Crash Cost/Day

A $ 3,000 3 $ 500 B       5,000 2  1,000 C       6,000 0      — D     20,000 3 3,000 E     10,000 2 1,000 F       7,000 1 1,000 G     20,000 2 3,000 H       8,000 1 2,000 I       5,000 1 2,000 J       7,000 1 1,000 K     12,000 6 1,000 Total normal costs = $103,000

Using the data provided, determine the activity crashing decisions and best-time cost project duration. Given the information you have developed, what suggestions would you give Brown to ensure she is well prepared for the project review committee? Assume the overhead costs for this project are $700 per workday. Will this alter your suggestions?

Case 9.2

Whitbread World Sailboat Race Each year countries enter their sailing vessels in the nine-month Round the World Whitbread Sailboat Race. In recent years, about 14 countries entered sailboats in the race. Each year’s sailboat entries represent the latest technologies and human skills each country can muster. Bjorn Ericksen has been selected as a project manager because of his past experi- ence as a master helmsman and because of his recent fame as the “best designer of racing sailboats in the world.” Bjorn is pleased and proud to have the opportunity to design, build, test, and train the crew for next year’s Whitbread entry for his country. Bjorn has picked Karin Knutsen (as chief design engineer) and Trygve Wallvik (as master helmsman) to be team leaders responsible for getting next year’s entry ready for the traditional parade of all entries on the Thames River in the United Kingdom, which signals the start of the race.

330 Chapter 9 Reducing Project Duration

As Bjorn begins to think of a project plan, he sees two parallel paths running through the project—design and construction and crew training. Last year’s boat will be used for training until the new entry can have the crew on board to learn mainte- nance tasks. Bjorn calls Karin and Trygve together to develop a project plan. All three agree the major goal is to have a winning boat and crew ready to compete in next year’s competition at a cost of $3.2 million. A check of Bjorn’s calendar indicates he has 45 weeks before next year’s vessel must leave port for the United Kingdom to start the race.

THE KICKOFF MEETING Bjorn asks Karin to begin by describing the major activities and the sequence required to design, construct, and test the boat. Karin starts by noting that design of the hull, deck, mast, and accessories should only take six weeks—given the design prints from past race entries and a few prints from other countries’ entries. After the design is complete, the hull can be constructed, the mast ordered, sails ordered, and accessories ordered. The hull will require 12 weeks to complete. The mast can be ordered and will require a lead time of eight weeks; the seven sails can be ordered and will take six weeks to get; accessories can be ordered and will take 15 weeks to receive. As soon as the hull is finished, the ballast tanks can be installed, requiring two weeks. Then the deck can be built, which will require five weeks. Concurrently, the hull can be treated with special sealant and friction-resistance coating, taking three weeks. When the deck is completed and mast and accessories received, the mast and sails can be installed, requiring two weeks; the accessories can be installed, which will take six weeks. When all of these activities have been completed, the ship can be sea-tested, which should take five weeks. Karin believes she can have firm cost estimates for the boat in about two weeks. Trygve believes he can start selecting the 12-man or woman crew and securing their housing immediately. He believes it will take six weeks to get a committed crew on-site and three weeks to secure housing for the crew members. Trygve reminds Bjorn that last year’s vessel must be ready to use for training the moment the crew is on-site until the new vessel is ready for testing. Keeping the old vessel operating will cost $4,000 per week as long as it is used. Once the crew is on-site and housed, they can develop and implement a routine sailing and maintenance training program, which will take 15 weeks (using the old vessel). Also, once the crew is selected and on-site, crew equip- ment can be selected, taking only two weeks. Then crew equipment can be ordered; it will take five weeks to arrive. When the crew equipment and maintenance training program are complete, crew maintenance on the new vessel can begin; this should take 10 weeks. But crew maintenance on the new vessel cannot begin until the deck is com- plete and the mast, sails, and accessories have arrived. Once crew maintenance on the new vessel begins, the new vessel will cost $6,000 per week until sea training is complete. After the new ship maintenance is complete and while the boat is being tested, initial sail- ing training can be implemented; training should take seven weeks. Finally, after the boat is tested and initial training is complete, regular sea training can be implemented— weather permitting; regular sea training requires eight weeks. Trygve believes he can put the cost estimates together in a week, given last year’s expenses. Bjorn is pleased with the expertise displayed by his team leaders. But he believes they need to have someone develop one of those critical path networks to see if they can safely meet the start deadline for the race. Karin and Trygve agree. Karin suggests the cost estimates should also include crash costs for any activities that can be

Chapter 9 Reducing Project Duration 331

Bjorn reviews the materials and wonders if the project will come in within the bud- get of $3.2 million and in 45 weeks. Advise the Whitbread team of their situation.

TWO WEEKS LATER Karin and Trygve submit the following cost estimates for each activity and corre- sponding crash costs to Bjorn (costs are in thousands of dollars):

Constrain

Enhance

Accept

Time Performance CostFIGURE C9.1 Project Priority Matrix: Whitbread Project

Normal Normal Crash Crash Activity Time Cost Time Cost

A Design 6 $ 40 2 $ — B Build hull 12 1,000 2 — C Install ballast tanks 2 100 0 — D Order mast 8 100 1 200 E Order sails 6 40 0 — F Order accessories 15 600 2 100 G Build deck 5 200 0 — H Coat hull 3 40 0 — I Install accessories 6 300 1 100 J Install mast and sails 2 40 1 40 K Test 5 60 1 40 L Sea trials 8 200 1 250 M Select crew 6 10 1 10 N Secure housing 3 30 0 — O Select crew equipment 2 10 0 — P Order crew equipment 5 30 0 — Q Routine sail/maintenance 15 40 3 30 R Crew maintenance training 10 100 1 240 S Initial sail training 7 50 2 150

Total direct cost $2,990

compressed and the resultant costs for crashing. Karin also suggests the team complete the following priority matrix for project decision making:

332 Chapter 9 Reducing Project Duration

Case 9.3

Nightingale Project—A You are the assistant project manager to Rassy Brown, who is in charge of the Nightingale project. Nightingale was the code name given to the development of a handheld electronic medical reference guide. Nightingale would be designed for emergency medical techni- cians and paramedics who need a quick reference guide to use in emergency situations. Rassy and her project team were developing a project plan aimed at producing 30 working models in time for MedCON, the biggest medical equipment trade show each year. Meeting the MedCON October 25 deadline was critical to success. All the major medical equipment manufacturers demonstrated and took orders for new products at MedCON. Rassy had also heard rumors that competitors were considering developing a similar product, and she knew that being first to market would have a significant sales advantage. Besides, top management made funding contingent upon developing a workable plan for meeting the MedCON deadline. The project team spent the morning working on the schedule for Nightingale. They started with the WBS and developed the information for a network, adding activities when needed. Then the team added the time estimates they had collected for each activity. Fol- lowing is the preliminary information for activities with duration time and predecessors:

Activity Description Duration Predecessor   1 Architectural decisions 10 None   2 Internal specifications 20 1   3 External specifications 18 1   4 Feature specifications 15 1   5 Voice recognition 15 2,3   6 Case   4 2,3   7 Screen   2 2,3   8 Speaker output jacks   2 2,3   9 Tape mechanism   2 2,3 10 Database 40 4 11 Microphone/soundcard   5 4 12 Pager   4 4 13 Barcode reader   3 4 14 Alarm clock   4 4 15 Computer I/O   5 4 16 Review design 10 5,6,7,8,9,10,11,12,13,14,15 17 Price components   5 5,6,7,8,9,10,11,12,13,14,15 18 Integration 15 16,17 19 Document design 35 16 20 Procure prototype components 20 18 21 Assemble prototypes 10 20 22 Lab test prototypes 20 21 23 Field test prototypes 20 19,22 24 Adjust design 20 23 25 Order stock parts 15 24 26 Order custom parts   2 24 27 Assemble first production unit 10 25, FS—8 time units 26, FS—13 time units 28 Test unit 10 27 29 Produce 30 units 15 28 30 Train sales representatives 10 29

Chapter 9 Reducing Project Duration 333

Use any project network computer program available to you to develop the schedule for activities (see Case Appendix for further instructions)—noting late and early times, the critical path, and estimated completion for the project. Prepare a short memo that addresses the following questions: 1. Will the project as planned meet the October 25th deadline? 2. What activities lie on the critical path? 3. How sensitive is this network?

Case 9.4

Nightingale Project—B Rassy and the team were concerned with the results of your analysis. They spent the afternoon brainstorming alternative ways for shortening the project duration. They rejected outsourcing activities because most of the work was developmental in nature and could only be done in-house. They considered altering the scope of the project by eliminating some of the proposed product features. After much debate, they felt they could not compromise any of the core features and be successful in the marketplace. They then turned their attention to accelerating the completion of activities through overtime and adding additional technical manpower. Rassy had built into her proposal a discretionary fund of $200,000. She was willing to invest up to half of this fund to accelerate the project, but wanted to hold onto at least $100,000 to deal with unex- pected problems. After a lengthy discussion, her team concluded that the following activities could be reduced at the specified cost: ∙ Development of voice recognition system could be reduced from 15 days to 10 days

at a cost of $15,000. ∙ Creation of database could be reduced from 40 days to 35 days at a cost of $35,000. ∙ Document design could be reduced from 35 days to 30 days at a cost of $25,000. ∙ External specifications could be reduced from 18 days to 12 days at a cost of $20,000. ∙ Procure prototype components could be reduced from 20 days to 15 days at a cost

of $30,000. ∙ Order stock parts could be reduced from 15 days to 10 days at a cost of $20,000. Ken Clark, a development engineer, pointed out that the network contained only finish-to-start relationships and that it might be possible to reduce project duration by creating start-to-start lags. For example, he said that his people would not have to wait for all of the field tests to be completed to begin making final adjustments in the design. They could start making adjustments after the first 15 days of testing. The project team spent the remainder of the day analyzing how they could introduce lags into the network to hopefully shorten the project. They concluded that the following finish-to-start relationships could be converted into lags: ∙ Document design could begin 5 days after the start of the review design. ∙ Adjust design could begin 15 days after the start of field test prototypes. ∙ Order stock parts could begin 5 days after the start of adjust design. ∙ Order custom parts could begin 5 days after the start of adjust design.

334 Chapter 9 Reducing Project Duration

∙ Training sales representatives could begin 5 days after the start of test unit and com- pleted 5 days after the production of 30 units.

As the meeting adjourns, Rassy turns to you and tells you to assess the options presented and try to develop a schedule that will meet the October 25th deadline. You are to pre- pare a report to be presented to the project team that answers the following questions: 1. Is it possible to meet the deadline? 2. If so, how would you recommend changing the original schedule (Part A) and why?

Assess the relative impact of crashing activities versus introducing lags to shorten project duration.

3. What would the new schedule look like? 4. What other factors should be considered before finalizing the schedule?

CASE APPENDIX: TECHNICAL DETAILS Create your project schedule and assess your options based on the following information: 1. The project will begin the first working day in January, 2010. 2. The following holidays are observed: January 1, Memorial Day (last Monday in

May), July 4, Labor Day (first Monday in September), Thanksgiving Day (fourth Thursday in November), December 25 and 26.

3. If a holiday falls on a Saturday, then Friday will be given as an extra day off; if it falls on a Sunday, then Monday will be given as a day off.

4. The project team works Monday through Friday, 8 hour days. 5. If you choose to reduce the duration of any one of the activities mentioned, then it

must be for the specified time and cost (i.e., you cannot choose to reduce database to 37 days at a reduced cost; you can only reduce it to 35 days at a cost of $35,000).

6. You can only spend up to $100,000 to reduce project activities; lags do not contain any additional costs.

Case 9.5

The “Now” Wedding—Part A* On December 31 of last year, Lauren burst into the family living room and announced that she and Connor (her college boyfriend) were going to be married. After recover- ing from the shock, her mother hugged her and asked, “When?” The following conver- sation resulted:

Lauren: January 21. Mom: What? Dad: The Now Wedding will be the social hit of the year. Wait a minute. Why so

soon? Lauren: Because on January 30 Connor, who is in the National Guard, will be ship-

ping out overseas. We want a week for a honeymoon.

* This case was adapted from a case originally written by Professor D. Clay Whybark, University of North Carolina, Chapel Hill, N.C.

Chapter 9 Reducing Project Duration 335

Mom: But Honey, we can't possibly finish all the things that need to be done by then. Remember all the details that were involved in your sister's wedding? Even if we start tomorrow, it takes a day to reserve the church and recep- tion hall, and they need at least 14 days' notice. That has to be done before we can start decorating, which takes 3 days. An extra $200 on Sunday would probably cut that 14 day notice to 7 days, though.

Dad: Oh, boy! Lauren: I want Jane Summers to be my maid of honor. Dad: But she's in the Peace Corps in Guatemala, isn't she? It would take her 10

days to get ready and drive up here. Lauren: But we could fly her up in 2 days and it would only cost $1,000. Dad: Oh, boy! Mom: And catering! It takes 2 days to choose the cake and decorations, and Jack's

Catering wants at least 5 days' notice. Besides, we'd have to have those things before we could start decorating.

Lauren: Can I wear your wedding dress, Mom? Mom: Well, we'd have to replace some lace, but you could wear it, yes. We could

order the lace from New York when we order the material for the brides- maids' dresses. It takes 8 days to order and receive the material. The pat- tern needs to be chosen first, and that would take 3 days.

Dad: We could get the material here in 5 days if we paid an extra $20 to air- freight it. Oh, boy!

Lauren: I want Mrs. Jacks to work on the dresses. Mom: But she charges $48 a day. Dad: Oh, boy! Mom: If we did all the sewing we could finish the dresses in 11 days. If Mrs.

Jacks helped we could cut that down to 6 days at a cost of $48 for each day less than 11 days. She is very good too.

Lauren: I don't want anyone but her. Mom: It would take another 2 days to do the final fitting and 2 more days to clean

and press the dresses. They would have to be ready by rehearsal night. We must have rehearsal the night before the wedding.

Dad: Everything should be ready rehearsal night. Mom: We've forgotten something. The invitations! Dad: We should order the invitations from Bob's Printing Shop, and that usually

takes 7 days. I'll bet he would do it in 6 days if we slipped him an extra $20!

Mom: It would take us 2 days to choose the invitation style before we could order them and we want the envelopes printed with our return address.

Lauren: Oh! That will be elegant. Mom: The invitations should go out at least 10 days before the wedding. If we let

them go any later, some of the relatives would get theirs too late to come and that would make them mad. I'll bet that if we didn't get them out until 8 days before the wedding, Aunt Ethel couldn't make it and she would reduce her wedding gift by $200.

Dad: Oh, boy!! Mom: We'll have to take them to the Post Office to mail them and that takes a day.

Addressing would take 3 days unless we hired some part-time girls and we can't start until the printer is finished. If we hired the girls we could prob- ably save 2 days by spending $40 for each day saved.

336 Chapter 9 Reducing Project Duration

Lauren: We need to get gifts for the bridesmaids. I could spend a day and do that. Mom: Before we can even start to write out those invitations we need a guest list.

Heavens, that will take 4 days to get in order and only I can understand our address file.

Lauren: Oh, Mom, I'm so excited. We can start each of the relatives on a different job.

Mom: Honey, I don't see how we can do it. Why, I've got to choose the invitations and patterns and reserve the church and . . .

Dad: Why don't you just take $3,000 and elope. Your sister's wedding cost me $2,400 and she didn't have to fly people up from Guatemala, hire extra girls and Mrs. Jacks, use airfreight, or anything like that.

1. Using a yellow sticky approach shown in Snapshot from Practice 6.1, develop a project network for the “Now” Wedding.

2. Create a schedule for the wedding using MS Project. Can you reach the deadline of January 21 for the “Now” Wedding? If you cannot, what would it cost to make the January 21 deadline and which activities would you change?

Case 9.6

The “Now” Wedding—Part B Several complications arose during the course of trying to meet the deadline of Janu- ary 20 for the “Now” Wedding rehearsal. Since Lauren was adamant on having the wedding on January 21 (as was Connor for obvious reasons), the implications of each of these complications had to be assessed. 1. On January 1 the chairman of the Vestry Committee of the church was left unim-

pressed by the added donation and said he wouldn’t reduce the notice period from 14 to 7 days.

2. Mother comes down with the three-day flu as she starts work on the guest list January 2.

3. Bob’s Printing Shop press was down for one day on January 5 in order to replace faulty brushes in the electric motor.

4. The lace and dress material are lost in transit. Notice of the loss is received on January 10.

Can the wedding still take place on January 21? If not, what options are available?

Being an Effective Project Manager10

LEARNING OBJECTIVES After reading this chapter you should be able to:

10-1 Understand the difference between leading and managing a project.

10-2 Understand the need to manage project stakeholders.

10-3 Identify and apply different “influence currencies” to build positive relations with others.

10-4 Create a stakeholder map and develop strategies for managing project dependencies.

10-5 Understand the need for a highly interactive man- agement style on projects.

10-6 More effectively manage project expectations.

10-7 Develop strategies for managing upward relations.

10-8 Understand the importance of building trust and acting in an ethical manner while working on a project.

10-9 Identify the qualities of an effective project manager.

OUTLINE 10.1 Managing versus Leading a Project

10.2 Managing Project Stakeholders

10.3 Influence as Exchange

10.4 Social Network Building

10.5 Ethics and Project Management

10.6 Building Trust: The Key to Exercising Influence

10.7 Qualities of an Effective Project Manager

Summary

338

C H A P T E R T E N

I couldn’t wait to be the manager of my own project and run the project the way I thought it should be done. Boy, did I have a lot to learn!

—First-time project manager

This chapter is based on the premise that one of the keys to being an effective project manager is building cooperative relationships among different groups of people to complete projects. Project success does not just depend on the performance of the project team. Success or failure often depends on the contributions of top manage- ment, functional managers, customers, suppliers, contractors, and others. The chapter begins with a brief discussion of the differences between leading and managing a project. The importance of managing project stakeholders is then intro- duced. Managers require a broad influence base to be effective in this area. Different sources of influence are discussed and are used to describe how project managers build social capital. This management style necessitates constant interacting with dif- ferent groups of people whom project managers depend on. Special attention is devoted to managing the critical relationship with top management and the importance of leading by example. The importance of gaining cooperation in ways that build and

Project networks

6

Managing risk 7

Monitoring progress

13

Teams 11

Outsourcing 12

Project manager

10

Strategy 2

Introduction 1

Organization 3

Schedule resources & costs

8

Intern ation

al

proje cts

15

Agile PM 16

Project closure

14

Estimate 5

Reducing duration

9

Define project

4

339

340 Chapter 10 Being an Effective Project Manager

sustain the trust of others is emphasized. The chapter concludes by identifying per- sonal attributes associated with being an effective project manager. Subsequent chap- ters will expand on these ideas in a discussion of managing the project team and working with people outside the organization.

10.1 Managing versus Leading a Project In a perfect world, the project manager would simply implement the project plan and the project would be completed. The project manager would work with others to for- mulate a schedule, organize a project team, keep track of progress, and announce what needs to be done next, and then everyone would charge along. Of course no one lives in a perfect world, and rarely does everything go according to plan. Project partici- pants get testy; they fail to get along with each other; other departments are unable to fulfill their commitments; technical glitches arise; work takes longer than expected. The project manager’s job is to get the project back on track. A manager expedites certain activities; figures out ways to solve technical problems; serves as peacemaker when tensions rise; and makes appropriate trade-offs among time, cost, and scope of the project. However, project managers often do more than put out fires and keep the project on track. They also innovate and adapt to ever-changing circumstances. They sometimes have to deviate from what was planned and introduce significant changes in the project scope and schedule to respond to unforeseen threats or opportunities. For example, cus- tomers’ needs may change, requiring significant design changes midway through the project. Competitors may release new products that dictate crashing project deadlines. Working relationships among project participants may break down, requiring a refor- mulation of the project team. Ultimately, what was planned or expected in the begin- ning may be very different from what was accomplished by the end of the project. Project managers are responsible for integrating assigned resources to complete the project according to plan. At the same time they need to initiate changes in plans and schedules as persistent problems make plans unworkable. In other words, managers want to keep the project going while making necessary adjustments along the way. According to Kotter (1990) these two different activities represent the distinction between management and leadership. Management is about coping with complexity, while leadership is about coping with change. Good management brings about order and stability by formulating plans and objec- tives, designing structures and procedures, monitoring results against plans, and taking corrective action when necessary. Leadership involves recognizing and articulating the need to significantly alter the direction and operation of the project, aligning people to the new direction, and motivating them to work together to overcome hurdles pro- duced by the change and to realize new objectives. Strong leadership, while usually desirable, is not always necessary to successfully complete a project. Well-defined projects that encounter no significant surprises require little leadership, as might be the case in constructing a conventional apartment building in which the project manager simply administrates the project plan. Con- versely, the higher the degree of uncertainty encountered on a project—whether in terms of changes in project scope, technological stalemates, breakdowns in coordina- tion between people, and so forth—the more leadership is required. For example, strong leadership would be needed for a software development project in which the parameters are always changing to meet developments in the industry.

10-1 Understand the difference between leading and managing a project.

LO

Chapter 10 Being an Effective Project Manager 341

It takes a special person to perform both roles well. Some individuals are great visionaries who are good at exciting people about change. Too often though, these same people lack the discipline or patience to deal with the day-to-day drudgeries of managing. Likewise, there are other individuals who are very well organized and methodical but lack the ability to inspire others. Strong leaders can compensate for their managerial weaknesses by having trusted assistants who oversee and manage the details of the project. Conversely, a weak leader can complement his or her strengths by having assistants who are good at sensing the need to change and rallying project participants. Still, one of the things that make good project managers so valuable to an organization is that they have the ability to both manage and lead a project. In doing so they recognize the need to create a social net- work that allows them to find out what needs to be done and obtain the cooperation necessary to achieve it.

10.2 Managing Project Stakeholders First-time project managers are eager to implement their own ideas and manage their people to successfully complete their project. What they soon find out is that project success depends on the cooperation of a wide range of individuals, many of whom do not directly report to them. For example, during the course of a system integration project, a project manager was surprised by how much time she was spending negoti- ating and working with vendors, consultants, technical specialists, and other functional managers:

Instead of working with my people to complete the project, I found myself being constantly pulled and tugged by demands of different groups of people who were not directly involved in the project but had a vested interest in the outcome.

Too often when new project managers do find time to work directly on the project, they adopt a hands-on approach to managing the project. They choose this style not because they are power-hungry egomaniacs but because they are eager to achieve results. They become quickly frustrated by how slowly things operate, the number of people that have to be brought on board, and the difficulty of gaining cooperation. Unfortunately, as this frustration builds, the natural temptation is to exert more pres- sure and get more heavily involved in the project. These project managers quickly earn the reputation of “micro managing” and begin to lose sight of the real role they play on guiding a project. Some new managers never break out of this vicious cycle. Others soon realize that authority does not equal influence and that being an effective project manager involves managing a much more complex and expansive set of interfaces than they had previ- ously anticipated. They encounter a web of relationships that requires a much broader spectrum of influence than they felt was necessary or even possible. For example, a significant project, whether it involves renovating a bridge, creating a new product, or installing a new information system, will likely involve in one way or another working with a number of different groups of stakeholders. First, there is the core group of specialists assigned to complete the project. This group is likely to be supplemented at different times by professionals who work on specific segments of the project. Second, there are the groups of people within the performing organization who are either directly or indirectly involved with the project. The most notable is top management, to whom the project manager is accountable. There are also other

10-2LO Understand the need to manage project stakeholders.

342 Chapter 10 Being an Effective Project Manager

managers who provide resources and/or may be responsible for specific segments of the project, and administrative support services such as human resources, finance, etc. Depending on the nature of the project, there are a number of different groups outside the organization that influence the success of the project; the most important is the customer for which the project is designed (see Figure 10.1). Each of these groups of stakeholders brings different expertise, standards, priorities, and agendas to the project. Stakeholders are people and organizations that are actively involved in the project, or whose interests may be positively or negatively affected by the project (PMBOK, 2013). The sheer breadth and complexity of stakeholder relationships distinguish project management from regular management. To be effective, a project manager must understand how stakeholders can affect the project and develop methods for managing the dependency. The nature of these dependencies is identified here: ∙ The project team manages and completes project work. Most participants want to

do a good job, but they are also concerned with their other obligations and how their involvement on the project will contribute to their personal goals and aspirations.

∙ Project managers naturally compete with each other for resources and the support of top management. At the same time they often have to share resources and exchange information.

∙ Administrative support groups, such as human resources, information systems, purchasing agents, and maintenance, provide valuable support services. At the same time they impose constraints and requirements on the project such as the documen- tation of expenditures and the timely and accurate delivery of information.

FIGURE 10.1 Network of Stakeholders

Project manager

Pro ject

Project

Team

Tea m

Project managers

Functional managers

Administrative support

Top management

Other organizations

Customers

Government agencies

Contractors

Project sponsors

Chapter 10 Being an Effective Project Manager 343

∙ Functional managers, depending on how the project is organized, can play a minor or major role toward project success. In matrix arrangements, they may be respon- sible for assigning project personnel, resolving technical dilemmas, and overseeing the completion of significant segments of the project work. Even in dedicated proj- ect teams, the technical input from functional managers may be useful, and accep- tance of completed project work may be critical to in-house projects. Functional managers want to cooperate up to a point, but only up to a certain point. They are also concerned with preserving their status within the organization and minimizing the disruptions the project may have on their own operations.

∙ Top management approves funding of the project and establishes priorities within the organization. They define success and adjudicate rewards for accomplishments. Significant adjustments in budget, scope, and schedule typically need their approval. They have a natural vested interest in the success of the project, but at the same time have to be responsive to what is best for the entire organization.

∙ Project sponsors champion the project and use their influence to gain approval of the project. Their reputation is tied to the success of the project, and they need to be kept informed of any major developments. They defend the project when it comes under attack and are a key project ally.

∙ Contractors may do all the actual work, in some cases, with the project team merely coordinating their contributions. In other cases, they are responsible for ancillary segments of the project scope. Poor work and schedule slips can affect work of the core project team. While contractors’ reputations rest with doing good work, they must balance their contributions with their own profit margins and their commitments to other clients.

∙ Government agencies place constraints on project work. Permits need to be secured. Construction work has to be built to code. New drugs have to pass a rigor- ous battery of U.S. Food and Drug Administration tests. Other products have to meet safety standards, for example, Occupational Safety and Health Administration standards.

∙ Other organizations, depending on the nature of the project, may directly or indi- rectly affect the project. For example, suppliers provide necessary resources for completion of the project work. Delays, shortages, and poor quality can bring a project to a standstill. Public interest groups may apply pressure on government agencies. Customers often hire consultants and auditors to protect their interests on a project.

∙ Customers define the scope of the project, and ultimate project success rests in their satisfaction. Project managers need to be responsive to changing customer needs and requirements and to meeting their expectations. Customers are primarily concerned with getting a good deal and, as will be elaborated in Chapter 11, this naturally breeds tension with the project team.

These relationships are interdependent in that a project manager’s ability to work effectively with one group will affect her ability to manage other groups. For example, functional managers are likely to be less cooperative if they perceive that top manage- ment’s commitment to the project is waning. Conversely, the ability of the project manager to buffer the team from excessive interference from a client is likely to increase her standing with the project team. The project management structure being used will influence the number and degree of external dependencies that will need to be managed. One advantage of creating a

344 Chapter 10 Being an Effective Project Manager

dedicated project team is that it reduces dependencies, especially within the organiza- tion, because most of the resources are assigned to the project. Conversely, a func- tional matrix structure increases dependencies, with the result that the project manager is much more reliant upon functional colleagues for work and staff. The old-fashioned view of managing projects emphasized planning and directing the project team; the new perspective emphasizes managing project stakeholders and anticipating change as the most important jobs. Project managers need to be able to assuage concerns of customers, sustain support for the project at higher levels of the organization, quickly identify problems that threaten project work, while at the same time defend the integrity of the project and the interests of the project participants.1 Within this web of relationships, the project manager must find out what needs to be done to achieve the goals of the project and build a cooperative network to accom- plish it. Project managers must do so without the requisite authority to expect or demand cooperation. Doing so requires sound communication skills, political savvy, and a broad influence base. See the Snapshot from Practice 10.1: The Project Manager as Conductor for more on what makes project managers special. See Research High- light 10.1: Give and Take for an interesting finding regarding this concept.

1 For a systematic treatise on stakeholder management, see: Lynda Bourne, Stakeholder Relationship Management (Farnham, England: Gower Publishing Ltd., 2009).

Metaphors convey meaning beyond words. For example, a meeting can be described as being difficult or “like wading through molasses.” A popular metaphor for the role of a project

manager is that of conductor. The conductor of an orchestra integrates the divergent sounds of different instruments to perform a given composition and make beautiful music. Similarly, the project manager inte- grates the talents and contributions of different spe- cialists to complete the project. Both have to be good at understanding how the different players contribute to the performance of the whole. Both are almost entirely dependent upon the expertise and know-how of the players. The conductor does not have command of all the musical instruments. Likewise, the project manager usually possesses only a small proportion of the technical knowledge to make decisions. As such, the conductor and project manager both facilitate the performance of others rather than actually perform. Conductors use their arms, baton, and other non- verbal gestures to influence the pace, intensity, and involvement of different musicians. Likewise, project managers orchestrate the completion of the project by

S N A P S H O T F R O M P R A C T I C E 1 0 . 1 The Project Manager as Conductor

managing the involvement and attention of project members. Project managers balance time and process and induce participants to make the right decisions at the right time just as the conductor induces the wind instruments to perform at the right moment in a move- ment. Each controls the rhythm and intensity of work by managing the tempo and involvement of the players. Finally, each has a vision that transcends the music score or project plan. To be successful they must both earn the confidence, respect, and trust of their players.

© JGI/Jamie Grill/Blend Images LLC

345

10.3 Influence as Exchange To successfully manage a project, a manager must adroitly build a cooperative network among divergent allies. Networks are mutually beneficial alliances that are generally gov- erned by the law of reciprocity (Kaplan, 1984; Grant, 2013). The basic principle is that “one good deed deserves another, and likewise, one bad deed deserves another.” The pri- mary way to gain cooperation is to provide resources and services for others in exchange for future resources and services. This is the age-old maxim: “Quid pro quo (something for something).” Or in today’s vernacular: “You scratch my back, I’ll scratch yours.” Cohen and Bradford (1990) described the exchange view of influence as “curren- cies.” If you want to do business in a given country, you have to be prepared to use the appropriate currency, and the exchange rates can change over time as conditions change. In the same way, what is valued by a marketing manager may be different from what is valued by a veteran project engineer, and you are likely to need to use different influence currency to obtain the cooperation of each individual. Although this analogy is a bit of an oversimplification, the key premise holds true that in the long run, “debit” and “credit” accounts must be balanced for cooperative relationships to work. Table 10.1 presents the commonly traded organizational currencies identified by Cohen and Bradford; they are then discussed in more detail in the following sections.

Task-Related Currencies This form of influence comes in different forms and is based on the project manager’s ability to contribute to others’ accomplishing their work. Probably the most significant form of this currency is the ability to respond to subordinates’ requests for additional

10-3LO Identify and apply differ- ent “influence currencies” to build positive relations with others.

Adam Grant from the University of Pennsylvania identified three funda- mental styles of social interaction with regard to the law of reciprocity:

Takers: Like to get more than give and put their own interests ahead of others.

Givers: Prefer to give more than they get and pay more attention to what others need. Matchers: Strive to preserve an equal balance be- tween giving and getting and operate on the prin- ciple of fairness.

While Grant admits that people will shift from one style to another, he cites research that indicates that most people develop a primary interaction style. He goes on to review research on the relationship between interaction style and professional success. Not surprisingly, he found Givers tend to sink to the bottom of the success ladder. They make others better off but sacrifice their own success in the process. Guess who was at the very top of the success lad- der? It was Givers again! Grant goes on to explain this paradox by arguing that while it is true that many

Givers are too caring and too timid, there are other Givers who are willing to give more than they receive, and still keep their own interests in sight, using them as a guide for choosing when, how, and to whom to give. These kind of Givers are able to create much bigger and more powerful social networks than Takers and Matchers. The good will they are able to generate is a major factor behind the success of this kind of Givers. Grant claims that Abraham Lincoln is a perfect example of a Giver that climbed to the top. When he won the presidency in 1860, he recruited bitter com- petitors whom he had earlier defeated to join his management team (Cabinet) in key positions. Grant predicts a Taker would have protected his ego and invited only “yes men” and a Matcher would have offered appointments to allies. Lincoln reported he needed the best men possible to run the country and by always focusing on what was best for the country he was able to forge an effective manage- ment team.

Research Highlight 10.1 Give and Take*

* Adam Grant, Give and Take: A Revolutionary Approach to Success (New York: Viking Press, 2013).

346 Chapter 10 Being an Effective Project Manager

Task-related currencies

Resources Lending or giving money, budget increases, personnel, etc. Assistance Helping with existing projects or undertaking unwanted tasks. Cooperation Giving task support, providing quicker response time, or aiding

implementation. Information Providing organizational as well as technical knowledge.

Position-related currencies

Advancement Giving a task or assignment that can result in promotion. Recognition Acknowledging effort, accomplishments, or abilities. Visibility Providing a chance to be known by higher-ups or significant others in the

organization. Network/contacts Providing opportunities for linking with others.

Inspiration-related currencies

Vision Being involved in a task that has larger significance for the unit, organiza- tion, customer, or society.

Excellence Having a chance to do important things really well. Ethical correctness Doing what is “right” by a higher standard than efficiency.

Relationship-related currencies

Acceptance Providing closeness and friendship. Personal support Giving personal and emotional backing. Understanding Listening to others’ concerns and issues.

Personal-related currencies

Challenge/learning Sharing tasks that increase skills and abilities. Ownership/involvement Letting others have ownership and influence. Gratitude Expressing appreciation.

TABLE 10.1 Commonly Traded Organizational Currencies

Source: Adapted from A. R. Cohen and David L. Bradford, Influence without Authority (New York: John Wiley & Sons, 1990).

manpower, money, or time to complete a segment of a project. This kind of currency is also evident in sharing resources with another project manager who is in need. At a more personal level, it may simply mean providing direct assistance to a colleague in solving a technical problem. Providing a good word for a colleague’s proposal or recommendation is another form of this currency. Because most work of significance is likely to generate some form of opposition, the person who is trying to gain approval for a plan or proposal can be greatly aided by having a “friend in court.” Another form of this currency includes extraordinary effort. For example, fulfilling an emergency request to complete a design document in two days instead of the nor- mal four days is likely to engender gratitude. Finally, sharing valuable information that would be useful to other managers is another form of this currency.

Position-Related Currencies This form of influence stems from the manager’s ability to enhance others’ positions within their organization. A project manager can do this by giving someone a chal- lenging assignment that can aid their advancement by developing their skills and abili- ties. Being given a chance to prove yourself naturally generates a strong sense of gratitude. Sharing the glory and bringing to the attention of higher-ups the efforts and accomplishments of others generate goodwill.

Chapter 10 Being an Effective Project Manager 347

Project managers confide that a useful strategy for gaining the cooperation of pro- fessionals in other departments/organizations is figuring out how to make these people look good to their bosses. For example, a project manager worked with a subcontractor whose organization was heavily committed to total quality management (TQM). The project manager made it a point in top-level briefing meetings to point out how quality improvement processes initiated by the contractor contributed to cost control and problem prevention. Another variation of recognition is enhancing the reputation of others within the firm. “Good press” can pave the way for lots of opportunities, while “bad press” can quickly shut a person off and make it difficult to perform. This currency is also evident in helping to preserve someone’s reputation by coming to the defense of someone unjustly blamed for project setbacks. Finally, one of the strongest forms of this currency is sharing contacts with other people. Helping individuals expand their own networks by introducing them to key people naturally engenders gratitude. For example, suggesting to a functional manager that he should contact Sally X if he wants to find out what is really going on in that department or to get a request expedited is likely to engender a sense of indebtedness.

Inspiration-Related Currencies Perhaps the most powerful form of influence is based on inspiration. Most sources of inspiration derive from people’s burning desire to make a difference and add meaning to their lives. Creating an exciting, bold vision for a project can elicit extraordinary commitment. For example, many of the technological breakthroughs associated with the introduction of the original Macintosh computer were attributed to the feeling that the project members had a chance to change the way people approached computers. A variant form of vision is providing an opportunity to do something really well. Being able to take pride in your work often drives many people. Often the very nature of the project provides a source of inspiration. Discovering a cure for a devastating disease, introducing a new social program that will help those in need, or simply building a bridge that will reduce a major traffic bottleneck can pro- vide opportunities for people to feel good about what they are doing and that they are making a difference. Inspiration operates as a magnet—pulling people as opposed to pushing people toward doing something.

Relationship-Related Currencies These currencies have more to do with strengthening the relationship with someone than directly accomplishing the project tasks. The essence of this form of influence is forming a relationship that transcends normal professional boundaries and extends into the realm of friendship. Such relationships develop by giving personal and emo- tional backing. Picking people up when they are feeling down, boosting their confi- dence, and providing encouragement naturally breed goodwill. Sharing a sense of humor and making difficult times fun is another form of this currency. Similarly, engaging in non-work-related activities such as sports and family outings is another way relationships are naturally enhanced. Perhaps the most basic form of this currency is simply listening to other people. Psychologists suggest that most people have a strong desire to be understood and that relationships break down because the parties stop listening to each other. Sharing per- sonal secrets/ambitions and being a wise confidant also creates a special bond between individuals.

348 Chapter 10 Being an Effective Project Manager

Personal-Related Currencies This last form of currency deals with individual needs and an overriding sense of self-esteem. Some argue that self-esteem is a primary psychological need; the extent to which we can help others feel a sense of importance and personal worth will naturally generate goodwill. A project manager can enhance a colleague’s sense of worth by asking for help and seeking opinions, delegating authority over work and allowing individuals to feel comfortable stretching their abilities. This form of currency can also be seen in sincere expressions of gratitude for the contri- butions of others. Care, though, must be exercised in expressing gratitude since it is easily devalued when overused. That is, the first thank you is likely to be more valued than the fiftieth. The bottom line is that a project manager will be influential only insofar as she can offer something that others value. Furthermore, given the diverse cast of people a proj- ect manager depends on, it is important that she be able to acquire and exercise differ- ent influence currencies. The ability to do so will be constrained in part by the nature of the project and how it is organized. For example, a project manager who is in charge of a dedicated team has considerably more to offer team members than a manager who is given the responsibility of coordinating the activities of different professionals across different departments and organizations. In such cases, that manager will prob- ably have to rely more heavily on personal and relational bases of influence to gain the cooperation of others.

10.4 Social Network Building

Mapping Stakeholder Dependencies The first step to social network building is identifying those stakeholders on whom the project depends for success. The project manager and his or her key assistants need to ask the following questions: ∙ Whose cooperation will we need? ∙ Whose agreement or approval will we need? ∙ Whose opposition would keep us from accomplishing the project? Many project managers find it helpful to draw a map of these dependencies. For exam- ple, Figure 10.2 contains the dependencies identified by a project manager responsible for installing a new financial software system in her company. It is always better to overestimate rather than underestimate dependencies. All too often, otherwise talented and successful project managers have been derailed because they were blindsided by someone whose position or power they had not anticipated. After identifying the stakeholders associated with your project, it is important to assess their significance. Here the power/interest matrix introduced in Chapter 3 becomes useful. Those individuals with the most power over and interest in the project are the most significant stakeholders and deserve the greatest attention. In particular, you need to “step into their shoes” and see the project from their perspective: ∙ What differences exist between myself and the people on whom I depend (goals,

values, pressures, working styles, risks)? ∙ How do these different people view the project (supporters, indifferents,

antagonists)?

10-4LO Create a stakeholder map and develop strate- gies for managing proj- ect dependencies.

Chapter 10 Being an Effective Project Manager 349

∙ What is the current status of the relationship I have with the people I depend on? ∙ What sources of influence do I have relative to those on whom I depend? Once you start this analysis you can begin to appreciate what others value and what currencies you might have to offer as a basis on which to build a working relation- ship. You begin to realize where potential problems lie—relationships in which you have a current debit or no convertible currency. Furthermore, diagnosing another’s point of view as well as the basis for their positions will help you anticipate their reactions and feelings about your decisions and actions. This information is vital for selecting the appropriate influence strategy and tactics and producing win/win solutions. For example, after mapping her dependency network, the project manager who was in charge of installing the software system realized that she was likely to have serious problems with the manager of the receipts department, who would be one of the pri- mary users of the software. She had no previous history of working with this individ- ual but had heard through the grapevine that the manager was upset with the choice of software and that he considered this project to be another unnecessary disruption of his department’s operation.  Prior to project initiation the project manager arranged to have lunch with the manager, where she sat patiently and listened to his concerns. She invested addi- tional time and attention to educate him and his staff about the benefits of the new software. She tried to minimize the disruptions the transition would cause in his department. She altered the implementation schedule to accommodate his prefer- ences as to when the actual software would be installed and the subsequent training would occur. In turn, the receipts manager and his people were much more accept- ing of the change, and the transition to the new software went more smoothly than anticipated.

Software installation

project

Billing and receipts

Purchasing

Top management

Software vendor

Inventory

Information technology manager

Information technology

director Shipping

FIGURE 10.2 Stakeholder Map for Financial Software Installation Project

350 Chapter 10 Being an Effective Project Manager

Management by Wandering Around (MBWA) The preceding example illustrates a key point - project management is a “contact sport.” Once you have established who the key players are, then you initiate contact and begin to build a relationship with those players. Building this relationship requires an interactive management style employees at Hewlett-Packard refer to as “manage- ment by wandering around” (MBWA) to reflect that managers spend the majority of their time outside their offices. MBWA is somewhat of a misnomer in that there is a purpose/pattern behind the “wandering.” Through face-to-face interactions, project managers are able to stay in touch with what is really going on in the project and build cooperation essential to project success. Effective project managers initiate contact with key players to keep abreast of devel- opments, anticipate potential problems, provide encouragement, and reinforce the objectives and vision of the project. They are able to intervene to resolve conflicts and prevent stalemates from occurring. In essence, they “manage” the project. By staying in touch with various aspects of the project they become the focal point for information on the project. Participants turn to them to obtain the most current and comprehensive information about the project which reinforces their central role as project manager. We have also observed less-effective project managers who eschew MBWA and attempt to manage projects from their offices and computer terminals. Such managers proudly announce an open-door policy and encourage others to see them when a prob- lem or an issue comes up. To them no news is good news. This allows their contacts to be determined by the relative aggressiveness of others. Those who take the initiative and seek out the project manager get too high a proportion of the project manager’s attention. Those people less readily available (physically removed) or more passive get ignored. This behavior contributes to the adage, “Only the squeaky wheel gets greased,” which breeds resentment within the project team. Effective project managers also find the time to regularly interact with more distal stakeholders. They keep in touch with suppliers, vendors, top management, and other functional managers. In doing so they maintain familiarity with different parties, sus- tain friendships, discover opportunities to do favors, and understand the motives and needs of others. They remind people of commitments and champion the cause of their project. They also shape people’s expectations (see Snapshot from Practice 10.2: Man- aging Expectations). Through frequent communication they alleviate people’s con- cerns about the project, dispel rumors, warn people of potential problems, and lay the groundwork for dealing with setbacks in a more effective manner. Unless project managers take the initiative to build a supportive network up front, they are likely to see a manager (or other stakeholder) only when there is bad news or when they need a favor (e.g., they don’t have the data they promised or the project has slipped behind schedule). Without prior, frequent, easy give-and-take interactions around nondecisive issues, the encounter prompted by the problem is likely to provoke excess tension. The parties are more likely to act defensively, interrupt each other, and lose sight of the common goal. Experienced project managers recognize the need to build relationships before they need them. They initiate contact with the key stakeholders at times when there are no outstanding issues or problems and therefore no anxieties and suspicions. On these social occasions, they naturally engage in small talk and responsive banter. They respond to others’ requests for aid, provide supportive counsel, and exchange informa- tion. In doing so they establish good feelings which will allow them to deal with more serious problems down the road. When one person views another as pleasant, credible,

10-5LO Understand the need for a highly interactive man- agement style on projects.

10-6LO More effectively manage project expectations.

Chapter 10 Being an Effective Project Manager 351

Dorothy Kirk, a project management consultant and program manager with Financial Solutions Group of Mynd, offers several keen insights about the art of managing stake- holder expectations:

. . . expectations are hardy. All they need to take root is the absence of evidence to the contrary. Once rooted, the unspoken word encourages growth. They can develop and thrive without being grounded in re- ality. For this reason, project managers do daily battle with unrealistic expectations.

She goes on to offer several tips for managing expectations:

or muddy expectations. For example, if you esti- mate that a task will take 317 hours, you are set- ting high expectations by your precision. The stakeholder is likely to be unhappy if it takes 323 hours. The stakeholder will not be unhappy with 323 hours if you quoted an estimate of 300–325 hours.

situation in one’s best interest. For example, if you tell someone it will be done by January, you are in- clined to interpret it to your advantage and assume

you have to the end of January, while the other per- son believes it will be done January 1st.

with reality. Too often we avoid opportunities to ad- just expectations because we hold onto a false hope that things will somehow work out.

- provement if you do not intend to do something with their input. Asking for their input raises expectations.

obscure to others.

openly and in person. Expect some anger and frus- tration. Do not get defensive in return. Be prepared to explain the impact of the problems. For example, never say the project is going to be late without be- ing able to give a new date. Explain what you are doing to see that this does not continue to happen.

All stakeholders have expectations about the schedule, cost, and project benefits. Project managers need to listen for, understand, and manage these expectations.

S N A P S H O T F R O M P R A C T I C E 1 0 . 2 Managing Expectations*

* D. Kirk, “Managing Expectations,” PM Network, August 2000, pp. 59–62.

and helpful based on past contact, he or she is much more likely to be responsive to requests for help and less confrontational when problems arise.2

Managing Upward Relations Research consistently points out that project success is strongly affected by the degree to which a project has the support of top management.3 Such support is reflected in an appropriate budget, responsiveness to unexpected needs, and a clear signal to others in the organization of the importance of the project and the need to cooperate. Visible top management support is not only critical for securing the support of other managers within an organization, but it also is a key factor in the project man- ager’s ability to motivate the project team. Nothing establishes a manager’s right to

10-7LO Develop strategies for managing upward relations. 2 This discussion is based on Leonard R. Sayles, Leadership: Managing in Real Organizations (New York: McGraw-Hill, 1989)

pp. 70–78. 3 See, for example: J. L. Pinto and S. K. Mantel, “The Causes of Project Failure,” IEEE Transactions in Engineering Manage- ment, vol. 37, no. 4 (1990), pp. 269–76.

352 Chapter 10 Being an Effective Project Manager

lead more than her ability to defend. To win the loyalty of team members, project managers have to be effective advocates for their projects. They have to be able to get top management to rescind unreasonable demands, provide additional resources, and recognize the accomplishments of team members. This is more easily said than done. Working relationships with upper management are a common source of consterna- tion. Laments like the following are often made by project managers about upper management:

They don’t know how much it sets us back losing Neil to another project. I would like to see them get this project done with the budget they gave us. I just wish they would make up their minds as to what is really important.

While it may seem counterintuitive for a subordinate to “manage” a superior, smart project managers devote considerable time and attention to influencing and garnering the support of top management. Project managers have to accept profound differences in perspective and become skilled at the art of persuading superiors. Many of the tensions that arise between upper management and project managers are a result of differences in perspective. Project managers become naturally absorbed with what is best for their project. To them the most important thing in the world is their project. Top management should have a different set of priorities. They are con- cerned with what is best for the entire organization. It is only natural for these two interests to conflict at times. For example, a project manager may lobby intensively for additional personnel only to be turned down because top management believes that the other departments cannot afford a reduction in staff. Although frequent communica- tion can minimize differences, the project manager has to accept the fact that top man- agement is inevitably going to see the world differently. Once project managers accept that disagreements with superiors are more a ques- tion of perspective than substance, they can focus more of their energy on the art of persuading upper management. But before they can persuade superiors, they must first prove loyalty.4 Loyalty in this context simply means that most of the time project man- agers have to show that they consistently follow through on requests and adhere to the parameters established by top management without a great deal of grumbling or fuss. Once managers have proven loyalty to upper management, senior management is much more receptive to their challenges and requests. Project managers have to cultivate strong ties with upper managers who are spon- soring the project. As noted earlier, these are high-ranking officials who championed approval and funding of the project; as such, their reputations are aligned with the project. Sponsors are also the ones who defend the project when it is under attack in upper circles of management. They shelter the project from excessive interference (see Figure 10.3). Project managers should always keep such people informed of any prob- lems that may cause embarrassment or disappointment. For example, if costs are beginning to outrun the budget or a technical glitch is threatening to delay the comple- tion of the project, managers make sure that the sponsors are the first to know. Timing is everything. Asking for additional budget the day after disappointing third- quarter earnings are reported is going to be much more difficult than making a similar request four weeks later. Good project managers pick the optimum time to appeal to top management. They enlist their project sponsors to lobby their cause. They also realize there are limits to top management’s accommodations. Here, the Lone Ranger analogy is appropriate—you have only so many silver bullets, so use them wisely.

FIGURE 10.3 The Significance of a Project Sponsor

Project sponsor

Project

4 Sayles, Leadership, pp. 136–45.

Chapter 10 Being an Effective Project Manager 353

Project managers need to adapt their communication pattern to that of the senior group. For example, one project manager recognized that top management had a ten- dency to use sports metaphors to describe business situations, so she framed a recent slip in schedule by admitting that “we lost five yards, but we still have two plays to make a first down.” Smart project managers learn the language of top management and use it to their advantage. Finally, a few project managers admit ignoring chains of command. If they are con- fident that top management will reject an important request and that what they want to do will benefit the project, they do it without asking permission. While acknowledging that this is very risky, they claim that bosses typically won’t argue with success.

Leading by Example A highly visible, interactive management style is not only essential to building and sustaining cooperative relationships, it also allows project managers to utilize their most powerful leadership tool—their own behavior (Peters, 1988; Kouznes & Posner, 2012). Often, when faced with uncertainty, people look to others for cues as to how to respond and demonstrate a propensity to mimic the behavior of people they respect. A project manager’s behavior symbolizes how other people should work on the proj- ect. Through her behavior a project manager can influence how others act and respond to a variety of issues related to the project. (See Snapshot from Practice 10.3: Leading at the Edge for a dramatic example of this.) To be effective, project managers must “walk the talk” (see Figure 10.4). Six aspects of leading by example are discussed next.

Priorities Actions speak louder than words. Subordinates and others discern project managers’ priorities by how they spend their time. If a project manager claims that this project is critical and then is perceived as devoting more time to other projects, then all his ver- bal reassurances are likely to fall on deaf ears. Conversely, a project manager who takes the time to observe a critical test instead of simply waiting for a report affirms

FIGURE 10.4 Leading by Example

Urgency

Standards of

performance

Cooperation

Problem solving

Ethics Priorities Leading

by example

354 Chapter 10 Being an Effective Project Manager

In 1914, the intrepid explorer Ernest Shackleton embarked on the Endur- ance with his team of seamen and sci- entists, intent upon crossing the unexplored Antarctic continent. What

happened in the two years between their departure and their ultimate incredible rescue has rarely been matched in the annals of survival: a ship crushed by expanding ice pack . . . a crew stranded on the floes of the frozen Weddell Sea . . . two perilous treks in open boats across a raging Southern Ocean . . . a team marooned on the wild, forlorn Elephant Island, stretched to the limits of human endurance. This adventure provided the basis for the book Lead- ing at the Edge: Leadership Lessons from the Extraordi- nary Saga of Shackleton’s Antarctic Expedition written by Dennis Perkins. Perkins provides numerous incidents of how Shackleton’s personal example influenced the behavior of his beleaguered crew. For example, from the beginning of the Trans-Atlantic expedition to its end, Shackleton consistently encouraged behavior that emphasized caring and respect:

After the destruction of the Endurance Shackleton heated hot milk for the crew and went from tent to tent with the “life giving” drink. After the sail to the island of South Georgia, when the exhausted crew had landed, Shackleton took the first watch, which he kept for three hours instead of the usual one.

Crew members emulated the caring behaviors that Shackleton modeled. A good example of this occurred during one of the most dramatic moments in the Endur- ance saga. The food supply had dwindled to perilously low levels. Less than a week’s supply remained, and the tiny ration of seal steak usually served at breakfast was eliminated. The waste meat generally used to feed the dogs was inspected for edible scraps. Under these wretched conditions, and after a wet sleepless night, an argument broke out among some of the team members. Caught in the middle, one crew member (Greenstreet) spilled his tiny ration of pow- dered milk and shouted at the biologist (Clark). Alfred Lansing described what happened next:

Greenstreet paused to get his breath, and in that in- stant his anger was spent and he suddenly fell silent. Everyone else in the tent became quiet, too, and looked at Greenstreet, shaggy-haired, bearded, and filthy with blubber soot, holding his empty mug in his hand and looking helplessly down into the snow that had thirstily soaked up his precious milk. The loss was so tragic he seemed almost on the point of weeping. Without speaking, Clark reached out and poured some milk into Greenstreet’s mug. Then Worsely, then Macklin, and Rickerson and Kerr, Orde-Lees, and fi- nally Blackborrow. They finished in silence.

S N A P S H O T F R O M P R A C T I C E 1 0 . 3 Leading at the Edge*

© Topham/The Image Works

* Adapted from Dennis N. T. Perkins, Leading at the Edge: Leadership Lessons from the Extraordinary Saga of Shackleton’s Antarctica Expedition (New York: AMACOM Press, 2000), pp. 94–95; and Alfred Lansing, Endurance: Shackleton’s Incredible Voyage (New York: Carroll & Graf, 1998), p. 127.

the importance of the testers and their work. Likewise, the types of questions project managers pose communicate priorities. By repeatedly asking how specific issues relate to satisfying the customer, a project manager can reinforce the importance of customer satisfaction.

Chapter 10 Being an Effective Project Manager 355

Urgency Through their actions project managers can convey a sense of urgency, which can per- meate project activities. This urgency in part can be conveyed through stringent dead- lines, frequent status report meetings, and aggressive solutions for expediting the project. The project manager uses these tools like a metronome to pick up the beat of the project. At the same time, such devices will be ineffective if there is not also a cor- responding change in the project manager’s behavior. If they want others to work faster and solve problems quicker, then they need to work faster. They need to hasten the pace of their own behavior. They should accelerate the frequency of their interactions, talk and walk more quickly, get to work sooner, and leave work later. By simply increasing the pace of their daily interaction patterns, project managers can reinforce a sense of urgency in others.

Problem Solving How project managers respond to problems sets the tone for how others tackle prob- lems. If bad news is greeted by verbal attacks, then others will be reluctant to be forth- coming.5 If the project manager is more concerned with finding out who is to blame instead of how to prevent problems from happening again, then others will tend to cover their tracks and cast the blame elsewhere. If, on the other hand, project managers focus more on how they can turn a problem into an opportunity or what can be learned from a mistake, then others are more likely to adopt a more proactive approach to problem solving.

Cooperation How project managers act toward outsiders influences how team members interact with outsiders. If a project manager makes disparaging remarks about the “idiots” in the marketing department, then this oftentimes becomes the shared view of the entire team. If project managers set the norm of treating outsiders with respect and being responsive to their needs, then others will more likely follow suit.

Standards of Performance Veteran project managers recognize that if they want participants to exceed project expectations then they have to exceed others’ expectations of a good project manager. They establish a high standard for project performance through the quality of their daily interactions. They respond quickly to the needs of others, carefully prepare and run crisp meetings, stay on top of all the critical issues, facilitate effective problem solving, and stand firm on important matters.

Ethics How others respond to ethical dilemmas that arise in the course of a project will be influenced by how the project manager has responded to similar dilemmas. In many cases, team members base their actions on how they think the project manager would respond. If project managers deliberately distort or withhold vital information from customers or top management, then they are signaling to others that this kind of behav- ior is acceptable. Project management invariably creates a variety of ethical dilemmas; this would be an appropriate time to delve into this topic in more detail.

5 This is the classic “kill the messenger” syndrome. This and other forces that contribute to distorting information can be found in Erik Larson and Jon King “The Systemic Distortion of Information: An On-going Management Challenge,” Organi- zational Dynamics, Winter 1996, pp. 49–62.

356 Chapter 10 Being an Effective Project Manager

10.5 Ethics and Project Management Questions of ethics have already arisen in previous chapters that discussed padding of cost and time estimations, exaggerating pay-offs of project proposals, and so forth. Ethical dilemmas involve situations where it is difficult to determine whether conduct is right or wrong.  In a survey of project managers, 81 percent reported that they encounter ethical issues in their work.6 These dilemmas range from being pressured to alter status reports, backdate signatures, compromising safety standards to accelerate progress, and approving shoddy work. The more recent work of Müller and colleagues suggests that the most common dilemma project managers face involves transparency issues related to project performance (Müller et al., 2013, 2014). For example, is it accept- able to falsely assure customers that everything is on track when in reality you are doing so to prevent them from panicking and making matters even worse? Project management is complicated work, and, as such, ethics invariably involve gray areas of judgment and interpretation. For example, it is difficult to distinguish deliberate falsification of estimates from genuine mistakes or the willful exaggeration of project payoffs from genuine optimism. It becomes problematic to determine whether unfulfilled promises were deliberate deception or an appropriate response to changing circumstances. To provide greater clarity to business ethics, many companies and professional groups publish a code of conduct. Cynics see these documents as simply window dressing, while advocates argue that they are important, albeit limited, first steps. In practice, personal ethics do not lie in formal statutes but at the intersection of one’s work, family, education, profession, religious beliefs, and daily interactions. Most project managers report that they rely on their own private sense of right and wrong— what one project manager called his “internal compass.” One common rule of thumb for testing whether a response is ethical is to ask, “Imagine that whatever you did was going to be reported on the front page of your local newspaper. How would you like that? Would you be comfortable?” Unfortunately, scandals at Enron, Worldcom, and Arthur Andersen have demon- strated the willingness of highly trained professionals to abdicate personal responsibil- ity for illegal actions and to obey the directives of superiors (see Snapshot from Practice 10.4: The Collapse of Arthur Andersen). Top management and the culture of an organization play a decisive role in shaping members’ beliefs of what is right and wrong. Many organizations encourage ethical transgressions by creating a “win at all cost” mentality. The pressures to succeed obscure consideration of whether the ends justify the means. Other organizations place a premium on “fair play” and command a market position by virtue of being trustworthy and reliable.7 Many project managers claim that ethical behavior is its own reward. By following your own internal compass your behavior expresses your personal values. Others sug- gest that ethical behavior is doubly rewarding. You not only are able to fall asleep at night but you also develop a sound and admirable reputation. As will be explored in the next section, such a reputation is essential to establishing the trust necessary to exercise influence effectively.

Understand the impor- tance of building trust and acting in an ethical manner while working on a project.

10-8LO

6 While this survey is a bit old, our conversations with project managers suggest that the results hold true today (J. Cabanis, “A Question of Ethics: The Issues Project Managers Face and How They Resolve Them,” PM Network, December 1995, pp. 8–28). 7 For a more in-depth discussion of ethics, see: L. Trevino and K. Nelson, Managing Business Ethics: Straight Talk about How to Do It Right, 5th ed. (Hoboken, NJ: John Wiley & Sons, 2011).

Chapter 10 Being an Effective Project Manager 357

10.6 Building Trust: The Key to Exercising Influence The significance of trust can be discerned by its absence. Imagine how different a working relationship is when you distrust the other party as opposed to trusting them. Here is what one line manager had to say about how he reacted to a project manager he did not trust:

Whenever Jim approached me about something, I found myself trying to read between the lines to figure what was really going on. When he made a request, my initial reaction was “no” until he proved it.

“Think straight and talk straight” was the principle on which Arthur E. Andersen built his accounting firm in the early 1900s. It was a phrase his mother taught him and became the

firm’s motto. The commitment to integrity and a sys- tematic, planned approach to work were instrumental in Arthur Andersen becoming one of the largest and best-known accounting firms in the world. According to the book, Inside Arthur Anderson by Susan Squires and colleagues:

Working for Arthur Andersen was not for everyone. It could be a tough culture. It was much too hierarchi- cal and top down for the more free spirited. Many people left after less than two years, believing the re- wards did not warrant the demands that were made on them. Others learned to play by the rules and some even thrived. To remain in the firm, staff mem- bers were expected to work hard, respect authority of rank, and maintain a high level of conformity. In return they were rewarded with support, promotion, and the possibility of making partner. Those individuals who made a career with the firm grew old together, pro- fessionally and personally, and most had never worked anywhere else. To these survivors, Andersen was their second family, and they developed strong loyalties to the firm and its culture. (p. 133)

On October 23, 2001, David Duncan told his Enron proj- ect team that they needed to start complying with Andersen’s new policy on handling audit documents. The policy had been instituted to make sure that the firm’s extraneous paperwork could not be used in court cases. Although the document retention policy required that papers supporting the firm’s opinions and audit be retained, it allowed a broad category of secondary documents to be destroyed. The team reacted with

stunned silence to Duncan’s directive. Then everyone got up and began racing to do what they had been told to do. No one asked Duncan to explain further. None asked whether what they were doing was wrong. No one questioned whether what he or she were doing might be illegal. Andersen’s Houston staff just reacted, following orders without question. On November 9, 2001, the day after the Securities Exchange Commission (SEC) issued a subpoena to Andersen, the shredding stopped. More than one ton of documents had been destroyed and 30,000 e-mails and Enron-related computer files erased. According to Andersen’s legal defense team, the shredding was busi- ness as usual. The lawyers claimed that the shredding was standard practice for eliminating unnecessary files. To the SEC, it appeared to be the start of a deep cover- up operation. Subsequently one of the most respected accounting firms in the world closed its doors.

S N A P S H O T F R O M P R A C T I C E 1 0 . 4 The Collapse of Arthur Andersen*

© Stephen J. Carrera/AP Photo

* Susan E. Squires, Cynthia J. Smith, Lorna McDougall, and William R. Yeak, Inside Arthur Andersen: Shifting Values, Unexpected Consequences (Upper Saddle River, NJ: Prentice Hall, 2004).

358 Chapter 10 Being an Effective Project Manager

Conversely, trust is the “lubricant” that maintains smooth and efficient interactions. For example, here is what a functional manager had to say about how he dealt with a project manager he trusted:

If Sally said she needed something, no questions were asked. I knew it was important or she wouldn’t have asked. Likewise, if I needed something, I know she would come through for me if she could. 

Trust is an elusive concept. It is hard to nail down in precise terms why some project managers are trusted and others are not. One popular way to understand trust is to see it as a function of character and competence. Character focuses on personal motives (i.e., does he or she want to do the right thing?), while competence focuses on skills necessary to realize motives (i.e., does he or she know the right things to do?). Stephen Covey resurrected the significance of character in the leadership litera- ture in his best-selling Seven Habits of Highly Effective People. Covey criticized popular management literature as focusing too much on shallow human relations skills and manipulative techniques, which he labeled the personality ethic. He argues that at the core of highly effective people is a character ethic that is deeply rooted in personal values and principles such as dignity, service, fairness, the pursuit of truth, and respect. One of the distinguishing traits of character is consistency. When people are guided by a core set of principles, they are naturally more predictable because their actions are consistent with these principles. Another feature of character is openness. When peo- ple have a clear sense of who they are and what they value, they are more receptive to others. This trait provides them with the capacity to empathize and the talent to build consensus among divergent people. Finally, another quality of character is a sense of purpose. Managers with character are driven not only by personal ambitions but also for the common good. Their primary concern is what is best for their organization and the project, not what is best for themselves. This willingness to subordinate personal interests to a higher purpose garners the respect, loyalty, and trust of others. The significance of character is summarized by the comments made by two team members about two very different project managers.

At first everyone liked Joe and was excited about the project. But after a while, people became suspicious of his motives. He had a tendency to say different things to different people. People began to feel manipulated. He spent too much time with top management. People began to believe that he was only looking out for himself. It was HIS project. When the project began to slip he jumped ship and left us holding the bag. I’ll never work for that guy again. My first impression of Jack was nothing special. He had a quiet, unassuming management style. Over time I learned to respect his judgment and his ability to get people to work together. When you went to him with a problem or a request, he always listened carefully. If he couldn’t do what you wanted him to do, he would take the time to explain why. When disagreements arose he always thought of what was best for the project. He treated everyone by the same rules; no one got special treatment. I’d jump at the opportunity to work on a project with him again.

Character alone will not engender trust. We must also have confidence in the compe- tency of individuals before we really trust them (Kanter, 1979). We all know well- intended managers whom we like but do not trust because they have a history of coming up short on their promises. Although we may befriend these managers, we don’t like to work with or for them. Competence is reflected at a number of different levels. First, there is task-related knowledge and skills reflected in the ability to answer questions, solve technical

Chapter 10 Being an Effective Project Manager 359

problems, and excel in certain kinds of work. Second, there is competence at an inter- personal level demonstrated in being able to listen effectively, communicate clearly, resolve arguments, provide encouragement, and so forth. Finally, there is organiza- tional competence. This includes being able to run effective meetings, set meaningful objectives, reduce inefficiencies, and build a social network. Too often there is a ten- dency for young engineers and other professionals to place too much value on task or technical competence. They underestimate the significance of organizational skills. Veteran professionals, on the other hand, recognize the importance of management and place a greater value on organizational and interpersonal skills. One problem new project managers experience is that it takes time to establish a sense of character and competency. Character and competency are often demonstrated when they are tested, such as when a tough call has to be made or when difficult prob- lems have to be solved. Veteran project managers have the advantage of reputation and an established track record of success. Although endorsements from credible sponsors can help a young project manager create a favorable first impression, ultimately he or she will have to demonstrate character and competence during the course of dealings with others in order to gain their trust. So far this chapter has addressed the importance of building a network of relation- ships to complete the project based on trust and reciprocity. The next section examines the nature of project management work and the personal qualities needed to excel at it.

10.7 Qualities of an Effective Project Manager Project management is, at first glance, a misleading discipline in that there is an inher- ent logic to the process. There is a natural progression from formulating a project scope statement, to creating a WBS, developing a network, adding resources, finaliz- ing a plan, and reaching milestones. However, when it comes to actually implementing and completing projects, this logic can quickly disappear. Project managers often encounter a much messier world, filled with inconsistencies and paradoxes. Effective project managers have to be able to deal with the contradictory nature of their work. Some of those contradictions are listed here: ∙ Innovate and maintain stability. Project managers have to put out fires, restore

order, and get the project back on track. At the same time they need to be innovative and develop new, better ways of doing things. Innovations unravel stable routines and spark new disturbances that have to be dealt with.

∙ See the big picture while getting your hands dirty. Project managers have to see the big picture and how their project fits within the larger strategy of their firm. There are also times when they must get deeply involved in project work and tech- nology. If they don’t worry about the details, who will?

∙ Encourage individuals but stress the team. Project managers have to motivate, cajole, and entice individual performers while at the same time maintaining team- work. They have to be careful that they are considered fair and consistent in their treatment of team members while at the same time treating each member as a spe- cial individual.

∙ Hands-off/Hands-on. Project managers have to intervene, resolve stalemates, solve technical problems, and insist on different approaches. At the same time they have to recognize when it is appropriate to sit on the sidelines and let other people figure out what to do.

Identify the qualities of an effective project manager.

10-9LO

360 Chapter 10 Being an Effective Project Manager

∙ Flexible but firm. Project managers have to be adaptable and responsive to events and outcomes that occur on the project. At the same time they have to hold the line at times and tough it out when everyone else wants to give up.

∙ Team versus organizational loyalties. Project managers need to forge a unified project team whose members stimulate one another to extraordinary performance. But at the same time they have to counter the excesses of cohesion and the team’s resistance to outside ideas. They have to cultivate loyalties to both the team and the parent organization.

Managing these and other contradictions requires finesse and balance. Finesse involves the skillful movement back and forth between opposing behavioral patterns (Sayles, 1989). For example, most of the time project managers actively involve others, move by increment, and seek consensus. There are other times when project managers must act as autocrats and take decisive, unilateral action. Balance involves recognizing the danger of extremes and that too much of a good thing invariably becomes harmful. For example, many managers have a tendency to always delegate the most stressful, diffi- cult assignments to their best team members. This habit often breeds resentment among those chosen (“why am I always the one who gets the tough work?”) and never allows the weaker members to develop their talents further. There is no one management style or formula for being an effective project manager. The world of project management is too complicated for formulas. Successful project managers have a knack for adapting styles to specific circumstances of the situation. So, what should one look for in an effective project manager? Many authors have addressed this question and have generated list after list of skills and attributes associ- ated with being an effective manager (Posner, 1987; Shenhar and Nofziner, 1997; Turner and Müller, 2005). When reviewing these lists, one sometimes gets the impres- sion that to be a successful project manager requires someone with superhuman pow- ers. While we agree that not everyone has the right stuff to be an effective project manager, there are some core traits and skills that can be developed to successfully perform the job. Eight of these traits are noted below. 1. Systems thinking. Project managers must be able to take a holistic rather than a

reductionist approach to projects. Instead of breaking up a project into individual pieces (planning, budget) and managing it by understanding each part, a systems perspective focuses on trying to understand how relevant project factors collectively interact to produce project outcomes. The key to success then becomes managing the interaction between different parts and not the parts themselves.8

2. Personal integrity. Before you can lead and manage others, you have to be able to lead and manage yourself (Bennis, 1989). Begin by establishing a firm sense of who you are, what you stand for, and how you should behave. This inner strength provides the buoyancy to endure the ups and downs of the project life cycle and the credibility essential to sustaining the trust of others.

3. Proactive. Good project managers take action before it is needed to prevent small concerns from escalating into major problems. They spend the majority of their time working within their sphere of influence to solve problems and not dwelling on things they have little control over. Project managers can’t be whiners.9

8 For a practical elaboration on what it means to be a systems thinker, see: Peter M. Senge, The Fifth Discipline (New York: Doubleday, 1990). 9 For a more extensive discussion of the habit of being proactive, see Stephen Covey, The Seven Habits of Highly Effective People (New York: Simon & Schuster, 1989), pp. 65–94.

4. High emotional intelligence (EQ). Project management is not for the meek. Project managers have to have command of their emotions and be able to respond constructively to others when things get a bit out of control. See the Research Highlight 10.2: Emotional Intelligence to read more about this quality.

5. General business perspective. Because the primary role of a project manager is to integrate the contributions of different business and technical disciplines, it is important that a manager have a general grasp of business fundamentals and how the different functional disciplines interact to contribute to a successful business.

6. Effective time management. Time is a manager’s scarcest resource. Project man- agers have to be able to budget their time wisely and quickly adjust their priorities. They need to balance their interactions so no one feels ignored.

7. Skillful politician. Project managers have to be able to deal effectively with a wide range of people and win their support and endorsement of their project. They need to be able to sell the virtues of their project without compromising the truth.

8. Optimist. Project managers have to display a can-do attitude. They have to be able to find rays of sunlight in a dismal day and keep people’s attention positive. A good sense of humor and a playful attitude are often a project manager’s greatest strength.

So how does one develop these traits? Workshops, self-study, and courses can upgrade one’s general business perspective and capacity for systems thinking. Training pro- grams can improve emotional intelligence and political skills. People can also be

361

Emotional intelligence (EQ) de- scribes the ability or skill to per- ceive, assess, and manage the emotions of oneself and others. Al- though the notion of EQ emerged

in the 1920s, it was not until Daniel Goleman published his book Emotional Intelligence that the concept captured the attention of business people and the public alike. Goleman divided EQ into the following five emotional competences:

Self-awareness—knowing your emotions, recog- nizing feelings as they occur, and understanding the link between your emotions and your behav- ior. Self-awareness is reflected in confidence, realistic assessment of personal strengths/weak- nesses, and ability to make fun of oneself. Self-regulation—being able to control disrup- tive impulses and moods and respond appro- priately to situations. Self-regulation is reflected in trustworthiness and openness to change. Self-motivation—being able to gather up your feelings and pursue goals with energy, pas- sion, and persistence. The hallmarks of self- motivation include a strong desire to achieve and internal optimism.

Empathy—being able to recognize the feelings of others and tuning into their verbal and nonverbal cues. Empathy is reflected in the ability to sustain relationships and in cross-cultural sensitivity. Social skills—being able to build social net- works and rapport with different kinds of people. Social skills include being able to lead change, resolve conflicts, and build effective teams.

Not much imagination is needed to see how EQ would contribute to being an effective project manager. In Goleman’s view, these competences build on each other in a hierarchy. At the bottom of his hier- archy is self-awareness. Some level of self-aware- ness is needed to move to self-regulation. Ultimately, social skills require all four of the other competences in order to begin to be proficient at leading others. Experts believe that most people can learn to significantly increase their EQ. Numer- ous training programs and materials have emerged to help individuals realize their EQ potential.

Research Highlight 10.2 Emotional Intelligence*

* T. Bradberry, and J. Graves, The Emotional Intelligence Quick Book: How to Put Your EQ to Work (New York: Simon & Schuster, 2005); J. Cabanis-Brewin, “The Human Task of a Project Leader: Daniel Goleman on the Value of High EQ,” PM Network, November 1999, pp. 38–42.

362 Chapter 10 Being an Effective Project Manager

taught stress and time management techniques. However, we know of no workshop or magic potion that can transform a pessimist into an optimist or provide a sense of pur- pose when there is not one. These qualities get at the very soul or being of a person. Optimism, integrity, and even being proactive are not easily developed if there is not already a predisposition to display them.

Summary To be successful, project managers must build a cooperative network among a diverse set of allies. They begin by identifying who the key stakeholders on a project are, fol- lowed by a diagnosis of the nature of the relationships, and the basis for exercising influence. Effective project managers are skilled at acquiring and exercising a wide range of influence. They use this influence and a highly interactive management style to monitor project performance and initiate appropriate changes in project plans and direction. They do so in a manner that generates trust, which is ultimately based on others’ perceptions of their character and competence. Project managers are encouraged to keep in mind the following suggestions: ∙ Build relationships before you need them. Identify key players and what you can do

to help them before you need their assistance. It is always easier to receive a favor after you have granted one. This requires the project manager to see the project in systems terms and to appreciate how it affects other activities and agendas inside and outside the organization. From this perspective they can identify opportunities to do good deeds and garner the support of others.

∙ Trust is sustained through frequent face-to-face contact. Trust withers through neglect. This is particularly true under conditions of rapid change and uncertainty that naturally engender doubt, suspicion, and even momentary bouts of paranoia. Project managers must maintain frequent contact with key stakeholders to keep abreast of developments, assuage concerns, engage in reality testing, and focus attention on the project. Frequent face-to-face interactions either directly or by tele- conferencing affirm mutual respect and trust in each other.

Ultimately, exercising influence in an effective and ethical manner begins and ends with how you view the other parties. Do you view them as potential partners or obsta- cles to your goals? If obstacles, then you wield your influence to manipulate and gain compliance and cooperation. If partners, you exercise influence to gain their commit- ment and support. People who view social network building as building partnerships see every interaction with two goals: resolving the immediate problem/concern and improving the working relationship so that next time it will be even more effective. Experienced project managers realize that “what goes around comes around” and try at all cost to avoid antagonizing players for quick success.

Key Terms Emotional intelligence (EQ), 361 Inspiration-related currencies, 347 Law of reciprocity, 345 Leading by example, 353 Management by wandering around (MBWA), 350

Personal-related currencies, 348 Position-related currencies, 346 Proactive, 360 Relationship-related currencies, 347

Social network building, 348 Stakeholder, 342 Systems thinking, 360 Task-related currencies, 345

1. Do an Internet search for the Keirsey Temperament Sorter Questionnaire and find a site that appears to have a reputable self-assessment questionnaire. Respond to the questionnaire to identify your temperament type. Read supportive documents asso- ciated with your type. What does this material suggest are the kinds of projects that would best suit you? What does it suggest your strengths and weaknesses are as a project manager? How can you compensate for your weaknesses?

2. Access the Project Management Institute website and review the standards con- tained in the PMI Member Ethical Standards section. How useful is the information for helping someone decide what behavior is appropriate and inappropriate?

3. You are organizing a benefit concert in your hometown that will feature local heavy metal rock groups and guest speakers. Draw a dependency map identifying the major groups of people that are likely to affect the success of this project. Who do you think will be most cooperative? Who do you think will be the least cooperative? Why?

4. You are the project manager responsible for the overall construction of a new inter- national airport. Draw a dependency map identifying the major groups of people that are likely to affect the success of this project. Who do you think will be most cooperative? Who do you think will be the least cooperative? Why?

5. Identify an important relationship (co-worker, boss, friend) in which you are having trouble gaining cooperation. Assess this relationship in terms of the influence currency model. What kinds of influence currency have you been exchanging in this relation- ship? Is the “bank account” for this relationship in the “red” or the “black”? What kinds of influence would be appropriate for building a stronger relationship with that person?

6. Each of the following seven mini-case scenarios involves ethical dilemmas associ- ated with project management. How would you respond to each situation, and why?

Jack Nietzche You returned from a project staffing meeting in which future project assignments were finalized. Despite your best efforts, you were unable to persuade the director of project management to promote one of your best assistants, Jack Nietzche, to a project manager position. You feel a bit guilty because you dangled the prospect of this promotion to motivate Jack. Jack responded by putting in extra hours to ensure that his segments of the project were completed on time. You wonder how Jack will react to this disappointment. More importantly, you wonder how his reaction might affect your project. You have five days remaining to meet a critical deadline for a very important customer. While it won’t

Exercises

Chapter 10 Being an Effective Project Manager 363

1. What is the difference between leading and managing a project? 2. Why is a conductor of an orchestra an appropriate metaphor for being a project

manager? What aspects of project managing are not reflected by this metaphor? Can you think of other metaphors that would be appropriate?

3. What does the exchange model of influence suggest you do to build cooperative relationships to complete a project?

4. What differences would you expect to see between the kinds of influence currencies that a project manager in a functional matrix would use and the influence a project manager of a dedicated project team would use?

5. Why is it important to build a relationship before you need it? 6. Why is it critical to keep the project sponsor informed? 7. Why is trust a function of both character and competence? 8. Which of the eight traits/skills associated with being an effective project manager is

the most important? The least important? Why?

Review Questions

be easy, you believed you would be able to complete the project on time. Now you’re not so sure. Jack is halfway through completing the documentation phase, which is the last critical activity. Jack can be pretty emotional at times, and you are worried that he will blow up once he finds he didn’t get the promotion. As you return to your office, you wonder what you should do. Should you tell Jack that he isn’t going to be promoted? What should you say if he asks about whether the new assignments were made? Seaburst Construction Project You are the project manager for the Seaburst construction project. So far the project is progressing ahead of schedule and below budget. You attribute this in part to the good working relationship you have with the carpenters, plumbers, electricians, and machine operators who work for your organization. More than once you have asked them to give 110 percent, and they have responded. One Sunday afternoon you decide to drive by the site and show it to your son. As you point out various parts of the project to your son, you discover that several pieces of valuable equipment are missing from the storage shed. When you start work again on Monday you are about to discuss this matter with a supervisor when you realize that all the missing equipment is back in the shed. What should you do? Why? The Project Status Report Meeting You are driving to a project status report meeting with your client. You encountered a significant technical problem on the project that has put your project behind schedule. This is not good news because completion time is the number one priority for the project. You are confident that your team can solve the problem if they are free to give their undi- vided attention to it and that with hard work you can get back on schedule. You also believe if you tell the client about the problem, she will demand a meeting with your team to discuss the implications of the problem. You can also expect her to send some of her personnel to oversee the solution to the problem. These interruptions will likely further delay the project. What should you tell your client about the current status of the project? Gold Star LAN project You work for a large consulting firm and were assigned to the Gold Star LAN project. Work on the project is nearly completed and your clients at Gold Star appear to be pleased with your performance. During the course of the project, changes in the original scope had to be made to accommodate specific needs of managers at Gold Star. The costs of these changes were documented as well as overhead and submitted to the centralized accounting department. They processed the information and submitted a change order bill for your signature. You are surprised to see the bill is 10 percent higher than what you submitted. You contact Jim Messina in the accounting office and ask if a mistake has been made. He curtly replies that no mistake was made and that management adjusted the bill. He recommends that you sign the document. You talk to another project manager about this and she tells you off the record that overcharging clients on change orders is common practice in your firm. Would you sign the document? Why? Why not? Cape Town Bio-Tech You are responsible for installing the new Double E production line. Your team has collected estimates and used the WBS to generate a project schedule. You have confi- dence in the schedule and the work your team has done. You report to top management that you believe that the project will take 110 days and be completed by March 5. The news is greeted positively. In fact, the project sponsor confides that orders do not have to be shipped until April 1. You leave the meeting wondering whether you should share this information with the project team or not.

364 Chapter 10 Being an Effective Project Manager

Chapter 10 Being an Effective Project Manager 365

Ryman Pharmaceuticals You are a test engineer on the Bridge project at Ryman Pharmaceuticals in Nashville, Tennessee. You have just completed conductivity tests of a new electrochemical com- pound. The results exceeded expectations. This new compound should revolutionize the industry. You are wondering whether to call your stockbroker and ask her to buy $20,000 worth of Ryman stock before everyone else finds out about the results. What would you do and why? Princeton Landing You are managing the renovation of the Old Princeton Landing Bar and Grill. The pro- ject is on schedule despite receiving a late shipment of paint. The paint was supposed to arrive on 1/30, but instead arrived on 2/1. The assistant store manager apologizes profusely for the delay and asks if you would be willing to sign the acceptance form and backdate it to 1/30. He says he won’t qualify for a bonus that he has worked hard to meet for the past month if the shipment is reported late. He promises to make it up to you on future projects. What would you do and why?

Abrashoff, D. M., It’s Your Ship (New York: Business Plus, 2002). Anand, V., B. E. Ashforth, and M. Joshi, “Business as Usual: The Acceptance and Perpetuation of Corruption in Organizations,” Academy of Management Executive, vol. 19, no. 4 (2005), pp. 9–23. Ancona, D. G., and D. Caldwell, “Improving the Performance of New-Product Teams,” Research Technology Management, vol. 33, no. 2 (March-April 1990), pp. 25–29. Badaracco, J. L., Jr., and A. P. Webb, “Business Ethics: A View from the Trenches,” California Management Review, vol. 37, no. 2 (Winter 1995), pp. 8–28. Baker, B., “Leadership and the Project Manager,” PM Network, December 2002, p. 20. Baker, W. E., Network Smart: How to Build Relationships for Personal and Organi- zational Success (New York: McGraw-Hill, 1994). Bennis, W., On Becoming a Leader (Reading, MA: Addison-Wesley, 1989). Bertsche, R., “Seven Steps to Stronger Relationships between Project Managers and Sponsors,” PM Network, September 2014, pp. 50–55. Bourne, L., Stakeholder Relationship Management (Farnham, England: Gower Pub- lishing Ltd., 2009). Bradberry, T., and J. Graves, The Emotional Intelligence Quick Book: How to Put Your EQ to Work (New York: Simon & Schuster, 2005). Cabanis, J., “A Question of Ethics: The Issues Project Managers Face and How They Resolve Them,” PM Network, December 1996, pp. 19–24. Cabanis-Brewin, J., “The Human Task of a Project Leader: Daniel Goleman on the Value of High EQ,” PM Network, November 1999, pp. 38–42. Cohen, A. R., and D. L. Bradford, Influence Without Authority (New York: John Wiley & Sons, 1990). Covey, S. R., The Seven Habits of Highly Effective People (New York: Simon & Schuster, 1989). Dinsmore, P. C., “Will the Real Stakeholders Please Stand Up?” PM Network, December 1995, pp. 9–10.

References

Einsiedel, A. A., “Profile of Effective Project Managers,” Project Management Jour- nal, vol. 31, no. 3 (1987), pp. 51–56. Ferrazzi, K., Never Eat Alone and Other Secrets to Success One Relationship at a Time (Crown Publishers, 2005). Gabarro, S. J., The Dynamics of Taking Charge (Boston: Harvard Business School Press, 1987). Grant, A., Give and Take: A Revolutionary Approach to Success (New York: Viking Press, 2013). Hill, L. A., Becoming a Manager: Mastery of a New Identity (Boston: Harvard Busi- ness School Press, 1992). Kanter, R. M., “Power Failures in Management Circuits,” Harvard Business Review, July–August, 1979, pp. 65–79. Kaplan, R. E., “Trade Routes: The Manager’s Network of Relationships,” Organiza- tional Dynamics, vol. 12, no. 4 (Spring 1984), pp. 37–52. Kirk, D., “Managing Expectations,” PM Network, August 2000, pp. 59–62. Kotter, J. P., “What Leaders Really Do,” Harvard Business Review, vol. 68, no. 3 (May–June 1990), pp. 103–11. Kouzes, J. M., and B. Z. Posner, Credibility: How Leaders Gain and Lose It, Why People Demand It (San Francisco: Jossey-Bass, 1993). Kouzes, J. M., and B. Z. Posner, The Leadership Challenge, 5th ed. (San Francisco: Jossey-Bass, 2012). Larson, E. W., and J. B. King, “The Systemic Distortion of Information: An Ongo- ing Management Challenge,” Organizational Dynamics, vol. 24, no. 3 (Winter 1996), pp. 49–62. Lewis, M. W., M. A. Welsh, G. E. Dehler, and S. G. Green, “Product Development Tensions: Exploring Contrasting Styles of Project Management,” Academy of Man- agement Journal, vol. 45, no. 3 (2002), pp. 546–64. Müller, R., and R. Turner, “Leadership Competency Profiles of Successful Project Managers,” International Journal of Project Management, vol. 28, no. 5 (July 2010), pp. 437–48. Müller R., Erling S. Andersen, Ø. Kvalnes, J. Shao, S. Sankaran, J. R. Turner, C. Biesenthal, D. Walker, and S. Gudergan, “The Interrelationship of Governance, Trust, and Ethics in Temporary Organizations,” Journal of Project Management, vol. 44, no. 4 (August 2013), pp. 26-44. Müller, R., R. Turner, E. Andersen, J. Shao, and O. Kvalnes, “Ethics, Trust, and Goverance in Temporary Organizations,” Journal of Project Management, vol. 45, no. 4 (August/September 2014), pp. 39–54. Peters, L. H., “A Good Man in a Storm: An Interview with Tom West,” Academy of Management Executive, vol. 16, no. 4 (2002), pp. 53–63. Peters, L. H., “Soulful Ramblings: An Interview with Tracy Kidder,” Academy of Management Executive, vol. 16, no. 4 (2002), pp. 45–52. Peters, T., Thriving on Chaos: Handbook for a Management Revolution (New York: Alfred A. Knopf, 1988).

366 Chapter 10 Being an Effective Project Manager

Pinto, J. K., and S. K. Mantel, “The Causes of Project Failure,” IEEE Transactions in Engineering Management, vol. 37, no. 4 (1990), pp. 269–76. Pinto, J. K., and D. P. Sleven, “Critical Success Factors in Successful Project Implementa- tion,” IEEE Transactions in Engineering Management, vol. 34, no. 1 (1987), pp. 22–27. Posner, B. Z., “What It Takes to Be an Effective Project Manager,” Project Manage- ment Journal, March 1987, pp. 51–55. Project Management Institute, Leadership in Project Management Annual (Newtown Square, PA: PMI Publishing, 2006). Project Management Institute, PMBOK Guide, 5th ed. (Newtown Square, PA: Project Management Institute, 2013). Robb, D. J., “Ethics in Project Management: Issues, Practice, and Motive,” PM Network, December 1996, pp. 13–18. Sayles, L. R., Leadership: Managing in Real Organizations (New York: McGraw-Hill, 1989), pp. 70–78. Sayles, L. R., The Working Leader (New York: Free Press, 1993). Senge, P. M., The Fifth Discipline (New York: Doubleday, 1990). Shenhar, A. J., and B. Nofziner, “A New Model for Training Project Managers,” Pro- ceedings of the 28th Annual Project Management Institute Symposium, 1997, pp. 301–6. Shtub, A., J. F. Bard, and S. Globerson, Project Management: Engineering, Technology, and Implementation (Englewood Cliffs, NJ: Prentice Hall, 1994). Trevino, L. K., and K. A. Nelson, Managing Business Ethics: Straight Talk about How to Do It Right, 5th ed. (Hoboken, NJ: John Wiley & Sons, 2011). Turner, J. R., and R. Müller, “The Project Manager Leadership Style as a Success Factor on Projects: A Literature Review,” Project Management Journal, vol. 36, no. 2 (2005), pp. 49–61.

Chapter 10 Being an Effective Project Manager 367

Case 10.1

The Blue Sky Project* Garth Hudson was a 29-year-old graduate of Eastern State University (ESU) with a B.S. degree in management information systems. After graduation he worked for seven years at Bluegrass Systems in Louisville, Kentucky. While at ESU he worked part time for an oceanography professor, Ahmet Green, creating a customized database for a research project he was conducting. Green was recently appointed director of Eastern Oceanography Institute (EOI), and Hudson was confident that this prior experience was instrumental in his getting the job as information services (IS) director at the Insti- tute. Although he took a significant pay cut, he jumped at the opportunity to return to his alma mater. His job at Bluegrass Systems had been very demanding. The long hours and extensive traveling had created tension in his marriage. He was looking for- ward to a normal job with reasonable hours. Besides, Jenna, his wife, would be busy

* Prepared by Erik Larson and V. T. Raja, senior instructor at the College of Business, Oregon State University.

pursuing her MBA at Eastern State University. While at Bluegrass, Hudson worked on a wide range of IS projects. He was confident that he had the requisite technical exper- tise to excel at his new job. Eastern Oceanography Institute was an independently funded research facility aligned with Eastern State University. Approximately 50 full- and part-time staff worked at the Institute. They worked on research grants funded by the National Science Foundation (NSF) and the United Nations (UN), as well as research financed by pri- vate industry. There were typically 7 to 9 major research projects under way at any one time as well as 20 to 25 smaller projects. One-third of the Institute’s scientists had part-time teaching assignments at ESU and used the Institute to conduct their own basic research.

FIRST YEAR AT EOI Hudson made a point of introducing himself to the various groups of people upon his arrival at the Institute. Still, his contact with the staff had been limited. He spent most of his time becoming familiar with EOI’s information system, training his staff, responding to unexpected problems, and working on various projects. Hudson suffered from food allergies and refrained from informal staff lunches at nearby restaurants. He stopped regularly attending the biweekly staff meetings in order to devote more time to his work. He now only attended the meetings when there was a specific agenda item regarding his operation. The IS staff at EOI consisted of two full-time assistants, Tom Jackson and Grant Hill. They were supported by five part-time student assistants from the computer sci- ence department. Grant Hill was assigned full-time to a large five-year NSF grant aimed at creating a virtual library of oceanographic research. Hill worked out of the project leader’s office and had very little interaction with Hudson or Jackson. Hudson’s relationship with Jackson was awkward from the start. He found out, after the fact, that Jackson thought he would get the job as director. They never talked about it, but he sensed tension the first couple of months on the job. One of the problems was that he and Jackson were totally different personalities. Jackson was gregarious and very talk- ative. He had a habit of after lunch walking around the Institute talking to different scientists and researchers. Often this would lead to useful information. Hudson, on the other hand, preferred to stay in his office working on various assignments and ven- tured out only when called upon. While Hudson felt Jackson was not on top of the latest developments as he was, he respected Jackson’s work. Last month the system was corrupted by a virus introduced over the Internet. Hudson devoted an entire weekend to restoring the system to operation. A recurring headache was one of the servers, code-named “Poncho,” that would occasionally shut down for no apparent reason. Instead of replacing it, he decided to nurse Poncho along until it could be replaced. His work was frequently interrupted by frantic calls from staff researchers who needed immediate help on a variety of computer-related prob- lems. He was shocked at how computer illiterate some of the researchers were and how he had to guide them through some of the basics of e-mail management and database configuration. He did find time to help Assistant Professor Amanda Johnson on a proj- ect. Johnson was the only researcher to respond to Hudson’s e-mail announcing that the IS staff was available to help on projects. Hudson created a virtual project office on the Internet so that Johnson could collaborate with colleagues from institutes in Italy and Thailand on a UN research grant. He looked forward to the day when he could spend more time on fun projects like that.

368 Chapter 10 Being an Effective Project Manager

Chapter 10 Being an Effective Project Manager 369

THE BLUE SKY CONVERSION PROJECT The “Blue Sky” conversion project began in earnest four months ago. Ahmet Green returned from Washington, D.C., with grim news. The economic downturn was going to lead to a dramatic reduction in funding. He anticipated as much as a 25 percent reduction in annual budget over the next three to five years. This would lead to staff reductions and cutting operating costs. One cost-cutting measure was moving IT opera- tions to the “cloud.” Green had first proposed the idea to Hudson after attending a meet- ing with several directors of other institutes who faced similar financial challenges. The basic strategy was to move all of the Institute’s databases, software, and even hardware to a “private cloud.” Staff would use their current PCs to simply access more powerful machines over the Internet. These powerful machines could be partitioned and configured differently as per the needs of research staff, giving each staff their own virtual machine (VM). Staff could also access, use, and share virtual servers over the Internet as needed. Hudson worked with the Institute’s accountant on a cost/benefit analysis. From their standpoint it made perfect sense. First, the Institute would not have to replace or upgrade aging computers and servers. Second, the Institute would enjoy significant IT savings since they would pay for only IT resources actually used. They would not have to make any major IT capital expenditures. Third, cloud comput- ing would provide scientists greater flexibility by accessing desired resources or soft- ware from anywhere at any time. And finally, once the system was up and running, the Institute would no longer need the services of at least one full-time IT worker. Green decided to name the project “Blue Sky” to put a positive spin on the conversion. At first the associate directors balked at the idea. Some had a hard time conceptual- izing what cloud computing meant. Others were worried about security and reliability. In the end they reluctantly signed off on the project when given alternative cost-cutting initiatives. Hudson assured them that cloud computing was the wave of the future and setting up or accessing virtual machines on the “cloud” was as simple as setting up or accessing their g-mail account. The conversion project would be completed in stages. The first stage was selecting a provider. The next stage was migrating non–mission critical information to the cloud. The next stages would entail migrating each of the six big grant projects in waves to the cloud. The final stage would focus on the remaining smaller projects. Training would be an integral part of each stage. The Institute would maintain a back-up for all the data until 6 months after complete conversion. After that the cloud service provider would be responsible for backing up the data. At first Jackson was excited about the project. He was savvy enough to realize that this was the future of computing and he was intrigued with how the whole system would work. His feelings soon changed when he started thinking about the potential ramifications for his job. He asked Hudson more than once what the department would look like after the conversion. Hudson replied vaguely that they would figure it out once the system was up and running. A task force was formed, headed by Hudson, to select a cloud service provider. Hudson was surprised by how many choices there were. Plans and cost structures var- ied considerably. After much deliberation the committee narrowed the choices to three. The first two were among the bigger providers in the industry, VMWARE and Micro- soft. The third choice was a relatively new company, OpenRange, which offered a cheaper solution. Jackson argued that even though the bigger providers would cost more, they were a much safer bet. Hudson responded that he had confidence in Open- Range and cutting costs was the primary goal behind the project. In the end, Hudson

persuaded the committee to choose OpenRange. Not only would cost be significantly cheaper, but OpenRange would help in the training of the personnel. Hudson liked this idea; training was not his strength, and he wasn’t looking forward to holding senior scientists’ hands through the process. It took Hudson and Jackson six weeks to identify non-critical data. Hudson worked on the back end while Jackson met with staff to identify non-critical information. The motto was when in doubt, leave it out. The actual migration only took a couple of days. Training proved to be more problematic. The staff sent by OpenRange appeared to be straight out of college. While enthusiastic, they were inexperienced in the art of getting older staff to accept and use new technology. Many trainers had the habit of simply doing things for the staff instead of showing them how to do it themselves. It all came to a head when a power outage at the OpenRange storage system shut down and dis- rupted operations at the Institute for 36 hours. Ahmet held an emergency meeting. Hudson reported that the power outage occurred in North East India and that OpenRange was expanding their back-up systems. Several members argued that the Institute should switch to one of the bigger providers. When this came up Hudson looked at Jackson and was relieved when he remained silent. In the end, Ahmet announced that it would be too costly to switch providers and Hudson and his staff would have to make the conversion work. Jackson stepped forward and volunteered to manage the training. Everyone agreed that the Institute should hire 3 more part-time assistants to help the staff with the transition. Hudson worked behind the scenes, coordinating with his counterparts at Open- Range and planning the conversion of the next segment of the project. Jackson worked closely with the OpenRange trainers and refocused their attention on teaching. Resis- tance was pretty high at first. Jackson used his personal contacts within the Institute to rally support for the change. He persuaded Hudson to change the conversion schedule to begin with those projects in which the leads were most supportive of the change. Training improved and Jackson created some useful training materials, including short videos on how to access the virtual machines. One problem that occurred early in the process involved a graduate research assis- tant who mistakenly hit the wrong commands and terminated her virtual machine instead of logging off. This resulted in complete loss of that machine’s data in the cloud. Fortunately, the Institute still had back-up and Jackson was able recover the work. Collaborating with some programmers at OpenRange, Jackson wrote a program that triggered a pop-up message on the screen warning users not to terminate their virtual machine when logging off.

CLOSING OUT THE BLUE SKY PROJECT It took almost a year to complete the Blue Sky project. After the rocky beginning things went relatively smoothly. Acceptance was slow, but Jackson and his staff worked with the staff to demonstrate how the new system would make their work easier. Two student assistants were always on call to address any problem or question. Hudson spent most of his time interacting with the OpenRange counterparts and rarely ventured out of his office. He had his student assistants collect information from staff so he could configure the new virtual machines to exactly match staff needs. He put in long hours so that customized databases would work in the new environment. This proved to be a very difficult task and he was quite pleased with his work. Twice Open- Range experienced momentary power shortages at their server facility which disrupted work at the Institute. Hudson was happy to report that OpenRange was breaking ground on an alternative server system in Ukraine.

370 Chapter 10 Being an Effective Project Manager

Chapter 10 Being an Effective Project Manager 371

Case 10.2

Tom Bray Tom Bray was mulling over today’s work schedule as he looked across the bay at the storm that was rolling in. It was the second official day of the Pegasus project and now the real work was about to begin. Pegasus was a two-month renovation project for AtlantiCorp, a major financial institution headquartered in Boston, Massachusetts. Tom’s group was responsible for installing the furniture and equipment in the newly renovated accounts receivable department on the third floor. The Pegasus project was a dedicated project team formed out of AtlantiCorp facilities department with Tom as the project lead. Tom was excited because this was his first major league project and he was look- ing forward to practicing a new management style—MBWA, aka management by wandering around. He had been exposed to MBWA in a business class in college, but it wasn’t until he attended an AtlantiCorp leadership training seminar that he decided to change how he managed people. The trainer was a devout MBWA cham- pion (“You can’t manage people from a computer!”). Furthermore, the testimonies from his peers reinforced the difference that MBWA can make when it comes to working on projects. Tom had joined the facilities group at AtlantiCorp five years earlier after working for EDS for six years. He quickly demonstrated technical competences and good work habits. He was encouraged to take all the internal project management workshops offered by AtlantiCorp. On his last two projects he served as assistant project manager responsible for procurement and contract management. He had read books about the soft side of project management and MBWA made sense—after all, people not tools get projects done. His boss had told him he needed to refine his people skills and work on developing rapport with team members. MBWA seemed like a perfect solution. Tom reviewed the list of team member names; some of the foreign names were real tongue twisters. For example, one of his better workers was from Thailand and her name was Pinyarat Sirisomboonsuk. He practiced saying “Pin-ya-răt See-rē-som-boon-sook.”

When the Institute conducted a retrospective (project review) on the Blue Sky proj- ect, some still questioned the choice of OpenRange as a cloud service provider, but praised Jackson’s work on helping the staff make the transition. Despite the criticism over the choice of OpenRange, Hudson felt good about the project. The system was up and running and the staff was beginning to enjoy the flexibility it provided. Besides, the Institute would achieve real savings from the new system. Soon after the retrospective, Hudson was surprised when Ahmet walked into his office and closed the door. Ahmet began by thanking Hudson for his work on the proj- ect. He then cleared his throat and said, “You know, Garth, one of the consequences of Blue Sky is reducing our IT staff. Grant Hill is needed for the data library project. So it comes down to you or Jackson. Frankly there is general agreement among the Associate Directors that Jackson is essential to the Institute. I know this might come as a surprise to you, and before I make a decision I want to give you a chance to change my mind.” 1. If you were Hudson, how would you respond to the director? 2. What mistakes did Hudson make? 3. What are the lessons to be learned from this case?

He got up, tucked in his shirt, and walked out of his office and down to the floor where his team was busy unloading equipment. Tom said “Hi” to the first few workers he met until he encountered Jack and three other workers. Jack was busy pulling hardware out of a box while his teammates were standing around talking. Tom blurted, “Come on guys, we’ve got work to do.” They quickly separated and began unloading boxes. The rest of the visit seemed to go well. He helped Shari unload a heavy box and managed to get an appreciative grin from Pinyarat when he almost correctly pro- nounced her name. Satisfied, Tom went back up to his office thinking that MBWA wouldn’t be that tough to do. After responding to e-mail and calling some vendors, Tom ventured back out to see how things were going downstairs. When he got there, the floor was weirdly quiet. Peo- ple were busy doing their work and his attempts at generating conversation elicited stiff responses. He left thinking that maybe MBWA is going to be tougher than he thought. 1. What do you think is going on at the end of this case? 2. What should Tom do next and why? 3. What can be learned from this case?

372 Chapter 10 Being an Effective Project Manager

Case 10.3

Cerberus Corporation* Cerberus is a successful producer of specialty chemicals. It operates nine large campus sites in the United States, with a number of different business units on each site. These business units operate independently, with direct reporting to corporate headquarters. Site functions such as safety, environmental, and facilities management report to a host organization—typically the business unit that is the largest user of their services.

SUSAN STEELE Susan Steele has worked in the Facilities group at the Cerberus Richmond site for the last two years. The Facilities manager, Tom Stern, reports to the General Manager of the largest business unit on site, the highly profitable Adhesives and Sealants Division. Susan started with Cerberus when she graduated with her business degree from Awsum University. She was excited about her new assignment—leading a project for the first time. She remembered Tom saying, “We’ve got office furniture dating back to the 80s. There are those ugly green-top desks that look like they came from military surplus! I’m especially concerned about computer workstation ergonomics—it’s a major issue that we absolutely must fix! I want you to lead a project to transition our office furniture to the new corporate standard.” Susan assembled her project team: Jeff, the site safety/ergonomics engineer; Gretchen, the space planner; Cindy, the move coordinator; and Kari, the accounting liaison for Facilities. At their first meeting, everyone agreed that ergonomics was the most urgent concern. All five business units responded to a workstation survey that identified injury-causing ergonomics. The team was developing a plan to replace old desks with new, ergo-adjustable furniture by the end of the year. Susan asked Kari about the budget, and Kari responded, “Facilities should not pay for this. We want the individual business units to pay so that the costs will show where they are incurred.” * Courtesy of John Sloan, Oregon State University.

Gretchen spoke up: “You know, we’ve got lots of department moves going on con- stantly. Everybody is always jockeying for space and location as their business needs change. Besides the ergonomics, could we say that only corporate standard furniture gets moved? That would force changing some of the stuff that’s just plain ugly.” Every- one agreed that this was a great idea. Susan presented the project plan to Tom and got a green light to proceed.

JON WOOD Jon Wood is a planning manager, with 22 years experience at Cerberus. His business unit, Photographic Chemicals Division (PCD), is losing money. Digital photography is continuing to reduce the size of the market, and PCD is having trouble matching the competition’s relentless price-cutting. Jon recently transferred to Richmond from cor- porate headquarters, where he ran the economic forecasting group. He is considered a new broom, and he is determined to sweep clean. One of Jon’s early actions was to negotiate with his general manager for a depart- ment move. Money was tight, and the site facilities function charged an arm and a leg for moves (covering all their fixed overhead, the operations people groused). How- ever, Jon felt it was important to move from Building 4, where they were next to Production, to Building 6, where they could be close to Marketing, Forecasting, and Accounting. His General Manager agreed, and there was lots of excitement in his team about their upcoming move. Jon assigned one of his planners, Richard, to work with the Facilities team on the layout and move plan for the group. Things seemed to be going fine—Jon saw Richard sitting down with the move coordinator, and they seemed to be on track. The day before the move, Jon hung up the phone from a particularly tense telecon- ference with a Canadian subcontractor. Production was not going well, and product availability would be tight for the rest of the quarter. Clustered around his desk were Richard, Cindy, and a person he hadn’t met yet, Susan. After hurried introductions, Susan told Jon that his filing cabinets could not be moved. The cabinets are large lat- eral files, five feet wide and two feet deep, a combination of both filing cabinets and bookshelves. Jon brought them with him from Corporate because he thought they looked nice with their dark grey steel sides and wood veneer tops. Susan told him that he would have to replace them with new corporate standard cabinets, virtually the same size. Jon said, “You mean you want me to throw away perfectly good filing cabi- nets and spend another $2,000 on new ones, just so they match? I won’t do it!” Susan replied, “Then I won’t authorize the movement of the old cabinets.” Jon said, “You’re joking—these cabinets are grey, the new ones are grey—the only difference is the wood top! You’d throw away $2,000 for nothing?” Susan replied stiffly, “I’m sorry, that’s the policy.” Jon said, “I don’t care what the policy is. If I have to move them myself, those cabi- nets are not going to the dump. My division is losing money and I’m not going to throw money away. If you don’t like it, you’re going to have to get your general man- ager to convince my general manager to make me do it. Now would you please leave so I can get some work done.” 1. If you were Susan, what would you do? 2. What, if anything, could Susan have done differently to avoid this problem? 3. What could the management of Cerberus do to more effectively manage situations

like this?

Chapter 10 Being an Effective Project Manager 373

Managing Project Teams11 LEARNING OBJECTIVES After reading this chapter you should be able to:

11-1 Identify key characteristics of a high-performance project team.

11-2 Distinguish the different stages of team development.

11-3 Understand the impact situational factors have on project team development.

11-4 Identify strategies for developing a high- performance project team.

11-5 Distinguish functional conflict from dysfunctional conflict and describe strategies for encouraging functional conflict and discouraging dysfunctional conflict.

11-6 Understand the challenges of managing virtual project teams.

11-7 Recognize the different pitfalls that can occur in a project team.

OUTLINE 11.1 The Five-Stage Team Development Model

11.2 Situational Factors Affecting Team Development

11.3 Building High-Performance Project Teams

11.4 Managing Virtual Project Teams

11.5 Project Team Pitfalls

Summary

C H A P T E R E L E V E N

374

Project networks

6

Managing risk 7

Monitoring progress

13

Teams 11

Outsourcing 12

Project manager

10

Strategy 2

Introduction 1

Organization 3

Schedule resources & costs

8

Intern ation

al

proje cts

15

Agile PM 16

Project closure

14

Estimate 5

Reducing duration

9

Define project

4

375

11-1LO Identify key characteristics of a high-performance project team.

Coming together is a beginning. Keeping together is progress. Working together is success.

—Henry Ford

The magic and power of teams is captured in the term “synergy,” which is derived from the Greek word sunergos: “working together.” There is positive and negative synergy. The essence of positive synergy can be found in the phrase “The whole is greater than the sum of the parts.” Conversely, negative synergy occurs when the whole is less than the sum of the parts. Mathematically, these two states can be sym- bolized by the following equations:

Positive Synergy 1 + 1 + 1 + 1 + 1 = 10 Negative Synergy 1 + 1 + 1 + 1 + 1 = 2 (or even −2)

Synergy perhaps can best be seen on a basketball court, a soccer pitch, or a football field where teammates play as one to defeat a superior foe (see Snapshot from Practice 11.1: The 2008 Olympic Redeem Team).

376 Chapter 11 Managing Project Teams

In the 2004 Olympics in Athens, twelve years after Magic Johnson and Michael Jordan led the U.S. Dream Team to Olympic gold in Barcelona, the U.S. Basketball Team composed of

NBA stars lost not once but three times to international competition. For the first time in Olympic history the U.S. settled for a bronze medal in men’s basketball. Basketball was no longer America’s game. An autopsy of the debacle in Athens turned up a severe case of negative synergy. The causes were many. The team featured only three holdovers from the group that had qualified the previous summer. Seven of the original invitees withdrew. In the end some 14 players turned down Uncle Sam, invoking excuses from family obligations to nagging injuries to the security situation in Greece. As a result, coach Larry Brown took charge of a team with an average age of 23 years, and it showed. Behind the scenes, problems of dress and punctuality festered and on the eve of the games Brown wanted to send several players home. The million-dollar players were overconfident, and assumed that their individual brilliance would prevail. An overreliance on one-on-one basketball and poor team defense doomed them as they lost games to Puerto Rico, Lithuania, and Argentina. Enter Jerry Colangelo, 68, former coach, player, and president of the Phoenix Suns. “The way they conducted themselves left a lot to be desired,” he says of the 2004 team. “Watching and listening to how people reacted to our players, I knew we’d hit bottom.” Colangelo told NBA commissioner David Stern that he would only assume duties as managing director if he was given complete control. As a measure of how abysmal the situation was, he immediately got what he asked for. In 2005 Colangelo met face-to-face with every pro- spective national player, to hear in their own words why they wanted to represent their country. The few good men to set things right wouldn’t be paid or guar- anteed playing time, much less a starting spot. A key recruit was superstar LeBron James, who had been tagged “LeBronze” after his performance on the disap- pointing 2004 team. Colangelo says, “I got buy-in. Half- way through my talk with him, LeBron said, I’m in.” Kobe Bryant soon followed and all but two of the 30 top NBA stars accepted Colangelo’s offer. Mike Kryzewski, the college coach at Duke, was hired with one project objective in mind—win the gold medal. To do so he had to change the attitude of team USA. They had to subordinate their superstar egos and buy in to the

S N A P S H O T F R O M P R A C T I C E 1 1 . 1 The 2008 Olympic Redeem Team*

concept of team ball. A blessing in disguise was being knocked out of the 2006 world championship by a Greek team. The players came away from that disappointment committed to team ball as extra passes became the staple in practices. The change in attitude was evident in more subtle ways. The USA on the uniforms was bright red, while the players’ names were muted blue. The players no longer referred to hoops as “our game” and spoke about how it had become the world’s game. Even the team’s offi- cial slogan (United We Rise) and unofficial nickname (the Redeem Team) implied room for improvement. The team bought into a common objective. Team USA marched to the final gold medal game by beating opponents by an average margin of 30+ points. Experts marveled not so much at the victory margin, but by how well they played as a team. “Our goal is to win a gold medal and be humble about it,” said Jason Kidd, six- time all-pro point guard, “and if we do it by 50, to make sure it’s because we’re playing the right way.” Nothing exemplified the right way more than a moment in the final, in which flawless ball movement from the Redeemers for 16 seconds, without a dribble being taken, culminated with Dwight Howard receiving a per- fect pass for an uncontested dunk. In the end, they didn’t dominate the gold medal game. Spain proved to be inspired opponents. They simply closed the game out and for the first time since NBA players have come to the Olympics, the USA played as a team rather than showboating individuals.

© Dusan Vranic/AP Photo

* Alexander Wolff, “The Redeem Team: New Nickname, New Outlook for U.S. at Olympics,” http://sportsillustrated.cnn .com/2008/writers/alexander_wolff/07/22/redeem.team0728 /index.html; and Greg Varkonyi, “The Redeem Team Played Like a Dream in the Olympic Basketball Final,” http://www .sportingo.com/olympic-games/basketball/a10072_redeem -team-played-like-dream-olympic-basketball-final.

Chapter 11 Managing Project Teams 377

Although less visible than in team sports, positive and negative synergy can also be observed and felt in the daily operations of project teams. Here is a description from one team member we interviewed:

Instead of operating as one big team we fractionalized into a series of subgroups. The marketing people stuck together as well as the systems guys. A lot of time was wasted gossiping and com- plaining about each other. When the project started slipping behind schedule, everyone started covering their tracks and trying to pass the blame on to others. After a while we avoided direct conversation and resorted to e-mail. Management finally pulled the plug and brought in another team to salvage the project. It was one of the worst project management experiences in my life.

This same individual fortunately was also able to recount a more positive experience: There was a contagious excitement within the team. Sure we had our share of problems and setbacks, but we dealt with them straight on and, at times, were able to do the impossible. We all cared about the project and looked out for each other. At the same time we challenged each other to do better. It was one of the most exciting times in my life.

The following is a set of characteristics commonly associated with high-performing teams that exhibit positive synergy:1

1. The team shares a sense of common purpose, and each member is willing to work toward achieving project objectives.

2. The team identifies individual talents and expertise and uses them, depending on the project’s needs at any given time. At these times, the team willingly accepts the influ- ence and leadership of the members whose skills are relevant to the immediate task.

3. Roles are balanced and shared to facilitate both the accomplishment of tasks and feelings of group cohesion and morale.

4. The team exerts energy toward problem solving rather than allowing itself to be drained by interpersonal issues or competitive struggles.

5. Differences of opinion are encouraged and freely expressed. 6. To encourage risk taking and creativity, mistakes are treated as opportunities for

learning rather than reasons for punishment. 7. Members set high personal standards of performance and encourage each other to

realize the objectives of the project. 8. Members identify with the team and consider it an important source of both profes-

sional and personal growth. High-performing teams become champions, create breakthrough products, exceed cus- tomer expectations, and get projects done ahead of schedule and under budget. They are bonded together by mutual interdependency and a common goal or vision. They trust each other and exhibit a high level of collaboration.

11.1 The Five-Stage Team Development Model Just as infants develop in certain ways during their first months of life, many experts argue that groups develop in a predictable manner. One of the most popular models identifies five stages (see Figure 11.1) through which groups develop into effective teams (Tuchman, 1965; Tuchman and Jensen, 1977):

11-2LO Distinguish the different stages of team development.

1 See E. H. Schein, Process Consultation, 2nd ed. (Reading, MA: Addison-Wesley, 1988), pp. 42–43; and R. Likert, New Patterns of Management (New York: McGraw-Hill, 1961), pp. 162–77.

378 Chapter 11 Managing Project Teams

1. Forming. During this initial stage the members get acquainted with each other and understand the scope of the project. They begin to establish ground rules by trying to find out what behaviors are acceptable with respect to both the project (what role they will play, what performance expectations are) and interpersonal relations (who’s really in charge). This stage is completed once members begin to think of themselves as part of a group.

2. Storming. As the name suggests, this stage is marked by a high degree of internal conflict. Members accept that they are part of a project group but resist the con- straints that the project and group put on their individuality. There is conflict over who will control the group and how decisions will be made. As these conflicts are resolved, the project manager’s leadership becomes accepted, and the group moves to the next stage.

3. Norming. The third stage is one in which close relationships develop and the group demonstrates cohesiveness. Feelings of camaraderie and shared responsibility for the project are heightened. The norming phase is complete when the group struc- ture solidifies and the group establishes a common set of expectations about how members should work together.

4. Performing. The team operating structure at this point is fully functional and accepted. Group energy has moved from getting to know each other and how the group will work together to accomplishing the project goals.

5. Adjourning. For conventional work groups, performing is the last stage of their development. However, for project teams, there is a completion phase. During this stage, the team prepares for its own disbandment. High performance is no longer a top priority. Instead attention is devoted to wrapping up the project. Responses of members vary in this stage. Some members are upbeat, basking in the project team’s accomplishments. Others may be depressed over loss of camaraderie and friendships gained during the project’s life.

FIGURE 11.1 The Five-Stage Team Development Model Orientation to project

Emotional response to the demands of the project

Open exchange of relevent information

Emergence of a solution

Dissolution of the group

Testing and dependence

Intragroup conflict

Development of group cohesion

Functional roles emerge

Stage 1: Forming

Stage 2: Storming

Stage 3: Norming

Stage 4: Performing

Stage 5: Adjourning

Project Activity Group Process

Chapter 11 Managing Project Teams 379

This model has several implications for those working on project teams. The first is that the model provides a framework for the group to understand its own development. Project managers have found it useful to share the model with their teams. It helps members accept the tensions of the storming phase, and it directs their focus to moving toward the more productive phases. Another implication is that it stresses the impor- tance of the norming phase, which contributes significantly to the level of productivity experienced during the performing phase. Project managers, as we shall see, have to take an active role in shaping group norms that will contribute to ultimate project suc- cess. For an alternative model of group development see Research Highlight 11.1: The Punctuated Equilibrium Model of Group Development.

11.2 Situational Factors Affecting Team Development Experience and research indicate that high-performance project teams are much more likely to develop under the following conditions:2

∙ There are 10 or fewer members per team. ∙ Members volunteer to serve on the project team. ∙ Members serve on the project from beginning to end. ∙ Members are assigned to the project full time. ∙ Members are part of an organization culture that fosters cooperation and trust. ∙ Members report solely to the project manager. ∙ All relevant functional areas are represented on the team. ∙ The project involves a compelling objective. ∙ Members are located within conversational distance of each other. In reality, it is rare that a project manager is assigned a project that meets all of these conditions. For example, many projects’ requirements dictate the active involvement of more than 10 members and may consist of a complex set of interlocking teams com- prising more than 100 professionals. In many organizations, functional managers or central manpower offices assign project members with little input from the project manager. To optimize resource utilization, team member involvement may be part time, and/or participants may move in and out of the project team on an as-needed basis. In the case of ad hoc task forces, no member of the team works full time on the project. In many corporations an NIH (not invented here) culture exists that discour- ages collaboration across functional boundaries. Team members often report to different managers, and, in some cases, the project manager will have no direct input over performance appraisals and advancement opportunities of team members. Key functional areas may not be represented during the entire duration of the project but may only be involved in a sequential manner. Not all projects have a compelling objective. It can be hard to get members excited about mundane projects such as a simple product extension or a conventional apartment complex. Finally, team members are often scattered across different corporate offices and buildings or, in the case of a virtual project, across the entire globe.

Understand the impact situational factors have on project team development.

11-3LO

2 See, for example: G. C. Homans, Social Behavior: Its Elementary Forms (New York: Harcourt Brace Jovanovich, 1961); M. Sherif, Group Conflict and Cooperation: Their Social Psychology (Chicago: Aldine, 1967); J. J. Seta, P. B. Paulus, and J. Schkade, “Effects of Group Size and Proximity under Cooperative and Competitive Conditions,” Journal of Personality and Social Psychology, vol. 98, no. 2 (1976), pp. 47–53; and A. Zander, Making Groups Effective (San Francisco: Jossey-Bass, 1994).

380

Gersick’s research suggests that groups don’t develop in a universal sequence of stages as suggested by the five-phase model. Her research, which is based on the systems con-

cept of punctuated equilibrium, found that the timing of when groups form and actually change the way they work is highly consistent. What makes this research appealing is that it is based on studies of more than a dozen field and laboratory task forces assigned to com- plete a specific project. This research reveals that each group begins with a unique approach to accomplishing its project that is set in its first meeting and includes the behavior and roles that dominate phase I. Phase I con- tinues until one-half of the allotted time for project completion has expired (regardless of actual amount of time). At this midpoint, a major transition occurs that includes the dropping of the group’s old norms and behavior patterns and the emergence of new behavior and working relationships that contribute to increased progress toward completing the project. The last meet- ing is marked by accelerated activity to complete the project. These findings are summarized in Figure 11.2. The remarkable discovery in these studies was that each group experienced its transition at the same point in its calendar—roughly halfway between the first meeting and the completion deadline—despite the fact that some groups spent as little as an hour on their project while others spent six months. It was as if the groups universally experienced a midlife crisis at this point. The midpoint appeared to work like an alarm clock, heightening members’ awareness that time was limited and they needed to get moving.

Within the context of the five-stage model, it suggests that groups begin by combining the forming and norming stages, then go through a period of low per- forming, followed by storming, then a period of high performing, and finally adjourning. Gersick’s findings suggest that there are natural transition points during the life of teams in which the group is receptive to change and that such a moment naturally occurs at the midpoint of a project. However, a manager does not want to have to wait 6 months on a complicated 12-month project for a team to get its act together! Here it is important to note that Gersick’s groups were working on relatively small-scale projects, i.e., a 4-person bank task force in charge of designing a new bank account in one month and a 12-person medical task force in charge of reorganizing two units of a treatment facility. In most cases no formal project plan was established. If anything, the results point to the importance of good project management and the need to establish deadlines and milestones. By impos- ing a series of deadlines associated with important milestones, it is possible to create multiple transition points for natural group development. For example, a 12-month construction project can be broken down into six to eight significant milestones with the chal- lenge of meeting each deadline producing the pre- requisite tension for elevating team performance.

Research Highlight 11.1 The Punctuated Equilibrium Model of Group Development*

FIGURE 11.2 The Punctuated Equilibrium Model of Group Development

High

Pe rfo

rm an

ce

Midpoint Deadline

Completion

Start

First meeting

Phase 2

Phase 1

Transition

* Connie J. Gersick, “Time and Transition in Work Teams: Toward a New Model of Group Development,” Academy of Management Journal, vol. 31, no. 1 (March 1988), pp. 9–41; and Connie J. Gersick, “Making Time Predictable Transitions in Task Groups,” Academy of Management Journal, vol. 32, no. 2 (June 1989), pp. 274–309.

Chapter 11 Managing Project Teams 381

It is important for project managers and team members to recognize the situational constraints they are operating under and do the best they can. It would be naive to believe that every project team has the same potential to evolve into a high-performance team. Under less-than-ideal conditions, it may be a struggle just to meet project objectives. Ingenuity, discipline, and sensitivity to team dynamics are essential to maximizing the performance of a project team.

11.3 Building High-Performance Project Teams Project managers play a key role in developing high-performance project teams. They recruit members, conduct meetings, establish a team identity, create a common sense of purpose or a shared vision, manage a reward system that encourages teamwork, orchestrate decision making, resolve conflicts that emerge within the team, and reju- venate the team when energy wanes (see Figure 11.3). Project managers take advan- tage of situational factors that naturally contribute to team development while improvising around those factors that inhibit team development. In doing so they exhibit a highly interactive management style that exemplifies teamwork and, as dis- cussed in the previous chapter, manage the interface between the team and the rest of the organization.

Recruiting Project Members The process of selecting and recruiting project members will vary across organiza- tions. Two important factors affecting recruitment are the importance of the project and the management structure being used to complete the project. Often for high- priority projects that are critical to the future of the organization, the project manager will be given virtual carte blanche to select whomever he or she deems necessary. For less significant projects, personnel will simply be assigned to the project. In many matrix structures, the functional manager controls who is assigned to the project; the project manager will have to work with the functional manager to obtain necessary personnel. Even in a project team where members are selected and assigned full time to the project, the project manager has to be sensitive to the needs of others. There is no better way to create enemies within an organization than to be perceived as unnecessarily robbing other departments of essential personnel.

Identify strategies for developing a high- performance project team.

11-4LO

Recruit team members

Superior performance

Conduct project meetings Establish team identity Create a shared vision Build a reward system

Manage decision making Manage conflict

Rejuvenate the project team

FIGURE 11.3 Creating a High- Performance Project Team

382 Chapter 11 Managing Project Teams

Experienced project managers stress the importance of asking for volunteers. How- ever, this desirable step oftentimes is outside the manager’s control. Still, the value of having team members volunteer for the project as opposed to being assigned cannot be overlooked. Agreeing to work on the project is the first step toward building personal commitment to the project. Such commitment will be essential to maintain motivation when the project hits hard times and extra effort is required. When selecting and recruiting team members, project managers naturally look for individuals with the necessary experience and knowledge/technical skills critical for project completion. At the same time, there are less obvious considerations that need to be factored into the recruitment process: ∙ Problem-solving ability. If the project is complex and fuzzy, then a manager wants

people who are good at working under uncertainty and have strong problem- identification and problem-solving skills. These same people are likely to be bored and less productive working on straightforward projects that go by the book.

∙ Availability. Sometimes the people who are most available are not the ones wanted for the team. Conversely, if members recruited are already overcommitted, they may not be able to offer much.

∙ Technological expertise. Managers should be wary of people who know too much about a specific technology. They may be technology buffs who like to study but have a hard time settling down and doing the work.

∙ Credibility. The credibility of the project is enhanced by the reputation of the peo- ple involved in the project. Recruiting a sufficient number of “winners” lends con- fidence to the project.

∙ Political connections. Managers are wise to recruit individuals who already have a good working relationship with key stakeholders. This is particularly true for projects operating in a matrix environment in which a significant portion of the work will be under the domain of a specific functional department and not the core project team.

∙ Ambition, initiative, and energy. These qualities can make up for a lot of shortcom- ings in other areas and should not be underestimated.

∙ Familiarity. Research suggests repeat collaboration stifles creativity and innova- tion. On challenging, breakthrough projects it is wise to interject the team with experts who have little previous working experience with others. (Skilton and Dooley, 2010)

See Snapshot from Practice 11.2: Managing Martians for further advice on recruiting team members. After reviewing needed skills, the manager should try to find out through the corporate grapevine who is good, who is available, and who might want to work on the project. Some organizations may allow direct interviews. Often a manager will have to expend political capital to get highly prized people assigned to the project. In matrix environments, the project manager will have to request appoint- ments with functional managers to discuss project requirements for staffing. The following documents should be available at these discussions: an overall proj- ect scope statement, endorsements of top management, and a description of the tasks and general schedule that pertain to the people from their departments. Man- agers need to be precise as to what attributes they are seeking and why they are important.

Chapter 11 Managing Project Teams 383

Conducting Project Meetings The First Project Team Meeting Research on team development confirms what we have heard from project managers: The first project kick-off meeting is critical to the early functioning of the project team. According to one veteran project manager:

The first team meeting sets the tone for how the team will work together. If it is disorganized, or becomes bogged down with little sense of closure, then this can often become a self- fulfilling prophecy for subsequent group work. On the other hand, if it is crisply run, focus- ing on real issues and concerns in an honest and straightforward manner, members come away excited about being part of the project team.

There are typically three objectives project managers try to achieve during the first meeting of the project team. The first is to provide an overview of the project, includ- ing the scope and objectives, the general schedule, method, and procedures. The sec- ond is to begin to address some of the interpersonal concerns captured in the team development model: Who are the other team members? How will I fit in? Will I be able to work with these people? The third and most important objective is to begin to model how the team is going to work together to complete the project. The project manager must recognize that first impressions are important; her behavior will be carefully monitored and interpreted by team members. This meeting should serve as an exemplary role model for subsequent meetings and reflect the leader’s style.

Donna Shirley’s 35-year career as aero- space engineer reached a pinnacle in July 1997 when Sojourner—the solar- powered, self-guided, microwave-oven- sized rover—was seen exploring the

Martian landscape in Pathfinder’s spectacular images from the surface of the red planet. The event marked a milestone in space exploration: No vehicle had ever before roamed the surface of another planet. Shirley, a manager at the Jet Propulsion Laboratory’s Mars Explora- tion Program, headed the mostly male team that designed and built Sojourner. In her insightful memoir, Managing Martians, written with Danelle Morton, she makes the following observation about managing creative teams:

When you are managing really brilliant, creative people, at some point you find it’s impossible to com- mand or control them because you can’t understand what they are doing. Once they have gone beyond your ability to understand them, you have a choice to make as a manager. You can limit them and the project by your intelligence, which I think is the wrong way to do it. Or you can trust them and use your management skills to keep them focused on the goal.

A lot of bad managers get threatened when their “subordinates” know more than they do. They either hire people who are inferior to them so they can always feel in control or they bottleneck people who know something they don’t so they can maintain con- trol. The whole project suffers from the manager’s insecurities.

S N A P S H O T F R O M P R A C T I C E 1 1 . 2 Managing Martians*

Source: NASA/JPL

* Donna Shirley and Danelle Morton, Managing Martians (New York: Broadway Books, 1998), pp. 88–89.

384 Chapter 11 Managing Project Teams

The meeting itself comes in a variety of shapes and forms. It is not uncommon in major projects for the kick-off meeting to involve one or two days, often at a remote site away from interruptions. This retreat provides sufficient time for preliminary introduction, to begin to establish ground rules, and to define the structure of the proj- ect. One advantage of off-site kick-off meetings is that they provide ample opportunity for informal interaction among members during breaks, meals, and evening activities; such informal interactions are critical to forming relationships. However, many organizations do not have the luxury of holding elaborate retreats. In other cases the scope of a project does not warrant such an investment of time. In these cases, the key operating principle should be KISS (keep it simple, stupid!). Too often when constrained by time, project managers try to accomplish too much during the first meeting; in doing so, issues do not get fully resolved, and members come away with an information headache. The project manager needs to remember that the primary goal is to run a productive meeting, and objectives should be realistic given the time available. If the meeting is only one hour, then the project manager should simply review the scope of the project, discuss how the team was formed, and provide an opportunity for members to intro- duce themselves to the team.

Establishing Ground Rules Whether as part of an elaborate first meeting or during follow-up meetings, the project manager must quickly begin to establish operational ground rules for how the team will work together. These ground rules involve not only organizational and procedural issues but also normative issues on how the team will interact with each other. Although specific procedures will vary across organizations and projects, some of the major issues that need to be addressed include the following:

Planning Decisions

∙ How will the project plan be developed? ∙ Will a specific project management software package be used? If so, which one? ∙ What are the specific roles and responsibilities of all the participants? ∙ Who needs to be informed of decisions? How will they be kept informed? ∙ What is the relative importance of cost, time, and performance? ∙ What are the deliverables of the project planning process? ∙ Who will approve and sign off at the completion of each deliverable? ∙ Who receives each deliverable?

Tracking Decisions

∙ How will progress be assessed? ∙ At what level of detail will the project be tracked? ∙ How will team members get data from each other? ∙ How often will they get this data? ∙ Who will generate and distribute reports? ∙ Who needs to be kept informed about project progress, and how will they

be informed? ∙ What content/format is appropriate for each audience?

Chapter 11 Managing Project Teams 385

∙ Meetings – Where will meetings be located? – What kind of meetings will be held? – Who will “run” these meetings? – How will agendas be produced? – How will information be recorded?

Managing Change Decisions

∙ How will changes be instituted? ∙ Who will have change approval authority? ∙ How will plan changes be documented and evaluated?

Relationship Decisions

∙ What department or organizations will the team need to interact with during the project?

∙ What are the roles and responsibilities of each organization (reviewer, approver, creator, user)?

∙ How will all involved parties be kept informed of deliverables, schedule dates, expectations, etc.?

∙ How will the team members communicate among themselves? ∙ What information will and won’t be exchanged? Checklists like these are only a guide; items should be added or deleted as needed. Many of these procedures will have already been established by precedent and will only have to be briefly reviewed. For example, Microsoft Project or Primavera may be the standard software tool for planning and tracking. Likewise, a specific firm is likely to have an established format for reporting status information. How to deal with other issues will have to be determined by the project team. When appropriate, the project manager should actively solicit input from the project team members and draw upon their experience and preferred work habits. This process also contributes to their buy- ing into the operational decisions. Decisions should be recorded and circulated to all members.

Establishing Team Norms During the course of establishing these operational procedures, the project manager, through word and deed, should begin working with members to establish the norms for team interaction. Below are examples of some of the norms researchers have found associated with high-performance teams.3 ∙ Confidentiality is maintained; no information is shared outside the team unless all

agree to it. ∙ It is acceptable to be in trouble, but it is not acceptable to surprise others. Tell

others immediately when deadlines or milestones will not be reached. ∙ There is zero tolerance for bulling a way through a problem or an issue.

3 See J. R. Katzenbach and D. K. Smith, The Wisdom of Teams (Boston: Harvard Business School Press, 1993); L. G. Bolman and T. E. Deal, “What Makes Teams Work,” Organizational Dynamics, vol. 21, no. 2, pp. 34–45; R. Katz, “How a Team at Digital Equipment Designed the ‘Alpha’ Chips,” The Human Side of Managing Technological Innovation, R. Katz, ed. (New York: Oxford Press, 1997), pp. 137–148.

386 Chapter 11 Managing Project Teams

∙ Agree to disagree, but when a decision has been made, regardless of personal feel- ings, move forward.

∙ Respect outsiders, and do not flaunt one’s position on the project team. ∙ Hard work does not get in the way of having fun. One way of making these norms more tangible is by creating a team charter that goes beyond the scope statement of the project and states in explicit terms the norms and val- ues of the team. This charter should be a collaborative effort on the part of the core team. Project managers can lead by proposing certain tenets, but they need to be open to sugges- tions from the team. Once there is general agreement to the rules of conduct, each mem- ber signs the final document to symbolize commitment to the principles it contains. Unfortunately, in some cases charters become a meaningless ritual because the charter is signed and filed away, never to be discussed again. To have a lasting effect, the charter has to be a legitimate part of the project monitoring system. Just as the team reviews progress toward project objectives, the team assesses the extent to which members are adhering to the principles in the charter. Project managers play a major role in establishing team norms through personal example. If they freely admit mistakes and share what they have learned from them, other team members will begin to do the same. At the same time, project managers need to intervene when they believe such norms are being violated. They should talk to offenders privately and clearly state their expectations. The amazing thing about groups is that once a group is cohesive, with well-established norms, the members will police themselves so that the manager doesn’t have to be the heavy. For example, one project manager confided that his team had a practice of having a small bean bag pres- ent at every meeting. If any one member felt that a colleague was shooting hot air or shading the truth, he or she was obligated to toss the bean bag at the speaker. See Snapshot from Practice 11.3: Putting Ford on Fast Forward for examples of norms that encourage innovation. Managing Subsequent Project Meetings The project kick-off meeting is one of several kinds of meetings required to complete a project. Other meetings include status report meetings, problem-solving meetings, and audit meetings. Issues unique to these meetings will be discussed in subsequent chapters. For now, here are some general guidelines for running effective meetings. They speak directly to the person chairing the meeting: ∙ Start meetings on time regardless of whether everyone is present. ∙ Prepare and distribute an agenda prior to the meeting. ∙ Identify an adjournment time. ∙ Periodically take time to review how effective previous meetings have been. ∙ Solicit recommendations and implement changes. ∙ Assign good recordkeeping. ∙ Review the agenda before beginning, and tentatively allocate time for each item. ∙ Prioritize issues so that adjustments can be made given time constraints. ∙ Encourage active participation of all members by asking questions instead of mak-

ing statements. ∙ Summarize decisions, and review assignments for the next meeting. ∙ Prepare and distribute a summary of the meeting to appropriate people. ∙ Recognize accomplishments and positive behavior.

Chapter 11 Managing Project Teams 387

Meetings are often considered anathema to productivity, but this does not have to be the case. The most common complaint is that meetings last too long. Establishing an agenda and adjournment time helps participants budget discussion time and provides a basis for expediting the proceedings. Recordkeeping can be an unwelcome, tedious task. Utilizing laptop computers to record decisions and information in real time can facilitate the communication process. Careful preparation and consistent application of these guidelines can make meetings a vital part of projects.

Establishing a Team Identity One of the challenges project managers often face in building a team is the lack of full- time involvement of team members. Specialists work on different phases of the project and spend the majority of their time and energy elsewhere. They are often members of multiple teams, each competing for their time and allegiance. Project expert J. D. Frame (1995) points out that for many of these specialists a specific project is an abstraction; as a consequence their level of motivation suffers. Project managers need to try to make the project team as tangible as possible to the participants by developing a unique team identity to which participants can become emotionally attached. Team meetings, co-location of team members, team names, and team rituals are common vehicles for doing so. ∙ Effective use of meetings. Periodic project team meetings provide an important

forum for communicating project information. A less obvious function of project meetings is to help establish a concrete team identity. During project meetings,

Adam Gryglak was given mission impossible: deliver an all-new Ford diesel engine in less than 36 months. The challenge was all the more daunt- ing in that in the past Ford had out-

sourced design and manufacture of diesel engines to Navistar. Not only did he have to meet a ridiculous deadline, but he also had to build an in-house engine from scratch. Gryglak, the chief diesel engineer, knew that success depended on short-circuiting the design process at Ford. So he put together a team of hungry engineers, moved offsite, and shielded the team from anxious top management. He called the project Scor- pion after the heavy metal band the Scorpions. Progress was immediate. Specialists who were used to working only with their own kind became famil- iar with what the other engineers were up to. “We saved months by knowing hourly what the other guys were thinking and what their problems were,” says Pat Morgan, a veteran Ford engineer. “The result was that the engine fit into the truck perfectly the first time, and that almost never happens.”

Gryglak also realized that engineers work harder and smarter when they are having fun. To relieve pres- sure the engineers played jokes on each other, building full-size snowmen decorated with machine parts on each other’s desks. Gryglak encouraged friendly competition. After hitting a critical design milestone the team orga- nized a Pinewood Derby contest. Pinewood Derby is a famous Cub Scout event where young boys whittle toy cars out of wood and race them down a ramp. These were engineers not Cub Scouts, so instead of wooden cars, the engineers milled cars out of aluminum. Some of the cars even had remote controls and engines. The new Ford diesel engine was completed on time to critical acclaim. The engine was the first of its kind to use state-of-the-art antipollution technology that meets new federal standards. It also had the best fuel econ- omy in its category and won’t need significant mainte- nance for 300,000 miles. The engine is featured in the best-selling F-150 line of trucks and is considered one of the keys to Ford’s comeback.

S N A P S H O T F R O M P R A C T I C E 1 1 . 3 Putting Ford on Fast Forward*

* “Putting Ford on Fast Forward,” Businessweek, October 26, 2009, pp. 58–59.

388 Chapter 11 Managing Project Teams

members see that they are not working alone. They are part of a larger project team, and project success depends on the collective efforts of all the team members. Timely gatherings of all the project participants help define team membership and reinforce a collective identity.

∙ Co-location of team members. The most obvious way to make the project team tan- gible is to have members work together in a common space. This is not always pos- sible in matrix environments where involvement is part time and members are working on other projects and activities. A worthwhile substitute for co-location is the creation of a project office, sometimes referred to as the project war room or clubhouse. Such rooms are the common meeting place and contain the most signifi- cant project documentation. Frequently, their walls are covered with Gantt charts, cost graphs, and other output associated with project planning and control. These rooms serve as a tangible sign of project effort.

∙ Creation of project team name. The development of a team name such as the “A-Team” or “Casey’s Crusaders” is a common device for making a team more tangible. Frequently an associated team logo is also created. Again the project man- ager should rely on the collective ingenuity of the team to come up with the appro- priate name and logo. Such symbols then can be affixed to stationery, T-shirts, coffee mugs, etc., to help signify team membership.

∙ Get the team to build or do something together early on. Nothing reinforces a sense of a team more than working on something together. In the case of one international project, the manager simply hosted a potluck dinner where each member brought a dish his or her country was famous for.

∙ Team rituals. Just as corporate rituals help establish the unique identity of a firm, similar symbolic actions at the project level can contribute to a unique team subcul- ture. For example, on one project members were given ties with stripes that corre- sponded to the number of milestones on the project. After reaching each milestone, members would gather and cut the next stripe off their ties to signify progress.4 Ralph Katz (2004) reports it was common practice for Digital Equipment’s alpha chip design team to recognize people who found a bug in the design by giving them a phosphorescent toy roach. The bigger the bug that was discovered, the bigger the toy roach received. Such rituals help set project work apart from mainstream opera- tions and reinforce a special status.

Creating a Shared Vision Unlike project scope statements, which include specific cost, completion dates, and performance requirements, a project vision involves the less tangible aspects of project performance. It refers to an image a project team holds in common about how the project will look upon completion, how they will work together, and/or how cus- tomers will accept the project. At its simplest level, a shared vision is the answer to the question, “What do we want to create?” Not everyone will have the same vision, but the images should be similar. Visions come in a variety of shapes and forms; they can be captured in a slogan or a symbol or can be written as a formal vision statement. What a vision is, is not as important as what it does. A vision inspires members to give their best effort. (See Snapshot from Practice 11.4: A Good Man in a Storm.) Moreover, a shared vision unites professionals with different backgrounds and agendas to a common aspiration. It helps motivate members to subordinate their individual agendas and do what is best for the project. As psychologist Robert Fritz puts it,

4 This anecdote was provided by Dr. Frances Hartman, University of Calgary, Alberta.

Chapter 11 Managing Project Teams 389

“In the presence of greatness, pettiness disappears.”5 Visions also provide focus and help communicate less tangible priorities, helping members make appropriate judg- ment calls. Finally, a shared vision for a project fosters commitment to the long term and discourages expedient responses that collectively dilute the quality of the project. Visions can be surprisingly simple. For example, the vision for a new car could be expressed as a “pocket rocket.” Compare this vision with the more traditional product description—“a sports car in the midprice range.” The “pocket rocket” vision provides a much clearer picture of what the final product should be. Design engineers would immediately understand that the car will be both small and fast and that the car should be quick at the getaway, nimble in the turns, and very fast in the straightaways (Bowen et al., 1994). Alternatively, visions can be more concrete: “The Helpdesk Automated Site (HASS) Version 4.5 will address the top 10 cus- tomer complaints across the university without any negative impact on average perfor- mance, reliability or response time across the system.”6

Once upon a time, back in 1976, Data General Corporation needed to come up quickly with a fast, reasonably priced 32-bit mini-computer to compete with Digital Equipment Corporation’s VAX.

Data General CEO Edson de Castro launched the Foun- tainhead Project and gave it the best people and ample resources to complete the 32-bit initiative. As a back-up to the Fountainhead project, Data General created the Eagle project within the Eclipse group under the leadership of Tom West. Work on both projects began in 1978. In 1980 Data General announced its new com- puter, featuring simplicity, power, and low cost. This computer was not the Fountainhead from the well- funded “best” DG group but the Eagle from Tom West’s underfunded Eclipse team. Tracy Kidder saw all this happen and told the story in The Soul of a New Machine, which won a Pulitzer Prize in 1982. This book, which Kidder thought might be of interest to a handful of computer scientists, has become a project management classic. In the beginning of his book, Kidder introduces the readers to the book’s protagonist Tom West by telling the story of him sailing a yacht across rough seas off the coast of New England. Kidder’s title for the pro- logue was “A Good Man in a Storm.” Twenty years after Kidder’s book was published Tom West was interviewed by Lawrence Peters for the Academy of Management Executive. Below are some excerpts that capture Tom’s views on managing innova- tive projects:

On selecting team members:

You explain to a guy what the challenge was, and then see if his eyes light up.

On motivating team members:

Challenge was everything. People, especially creative technical people who really want to make a differ- ence, will do whatever is possible or whatever is necessary. I’ve done this more than once, and I’ve repeated it over and over. It seems to work.

On the importance of having a vision:

You’ve got to find a rallying cry. You need to have something that can be described very simply and has that sort of ring of truth to an engineer that says “yes that’s the thing to be doing right now.” Otherwise you’re going to be rolling rocks up hill all the time.

On the role of being a project manager:

You have to act as a cheerleader. You have to act as the instructor. You have to constantly bring to mind what the purpose is and what’s moving the ball to- wards the goal post, and what’s running sideways, and you have to take up a lot of battles for them. I mean you really don’t want your design engineer ar- guing with the guy in the drafting shop about why he ought to do it the designer’s way. I can do that, and I can pull rank too, and sometimes I did just that.

S N A P S H O T F R O M P R A C T I C E 1 1 . 4 A Good Man in a Storm*

* Tracy Kidder, The Soul of a New Machine (New York: Avon Books, 1981); Lawrence H. Peters, “‘A Good Man in a Storm’: An Interview with Tom West,” Academy of Management Executive, vol. 16, no. 4 (2002), pp. 42–43.

5 Quoted in P. Senge, The Fifth Discipline (New York, Doubleday,1990) p. 209. 6 S. Berkun, The Art of Project Management (Sebastopol. CA: O’Reilly, 2005), p. 79.

390 Chapter 11 Managing Project Teams

There appear to be four essential qualities of an effective vision (see Figure 11.4). First, its essential qualities must be able to be communicated. A vision is worthless if it only resides in someone’s head. Here, the use of concrete, image-based language is considered critical, e.g., “pocket rocket” (Murphy and Clark 2016). Second, visions have to be challenging but also realistic. For example, a task force directed at overhaul- ing the curriculum at the college of business at a state university is likely to roll its collective eyes if the dean announces that their vision is to compete against the Har- vard Business School. Conversely, developing the best undergraduate business pro- gram in that state may be a realistic vision for that task force. Third, the project manager has to believe in the vision. Passion for the vision is an essential element of an effective vision. Finally, it should be a source of inspiration to others. Once a project manager accepts the importance of building a shared vision, the next question is how to get a vision for a particular project. First, project managers don’t get visions. They act as catalysts and midwives for the formation of a shared vision of a project team (Smith, 1994). In many cases visions are inherent in the scope and objectives of the project. People get naturally excited about being the first ones to bring a new technology to the market or solving a problem that is threatening their organization. Even with mundane projects, there are often ample opportunities for establishing a compelling vision. One way is to talk to various people involved in the project and find out early on what gets them excited about the project. For some it may be doing a better job than on the last project or the satisfaction in the eyes of the customers when the project is over. Many visions evolve reactively in response to competition: for example, Samsung engineers trying to develop a next generation smartphone that critics will proclaim superior to the iPhone. Some experts advocate engaging in formal vision-building meetings. These meetings generally involve several steps, beginning with members identifying different aspects of the project and generating ideal scenarios for each aspect. For example, on a construction project the scenarios may include “no accidents,” “no lawsuits,” “winning a prize,” or “how we are going to spend our bonus for completing the project ahead of schedule.” The group reviews and chooses the scenarios that are most appealing and translates them into vision statements for the project. The next step is to identify strategies for achieving the vision statements. For example, if one of the vision statements is that there will be no lawsuits, members will identify how they will have to work with the owner and subcon- tractors to avoid litigation. Next, members volunteer to be the keeper of the flame for each statement. The vision, strategies, and the name of the responsible team member are published and distributed to relevant stakeholders.

Inspire othersPassion

Strategic senseCommunicate FIGURE 11.4 Requirements for an Effective Project Vision

Chapter 11 Managing Project Teams 391

In more cases than not, shared visions emerge informally. Project managers collect information about what excites participants about the project. They test bits of their working vision in their conversations with team members to gauge the level of excite- ment the early ideas elicit in others. To some extent they engage in basic market research. They seize opportunities to galvanize the team, such as a disparaging remark by an executive that the project will never get done on time or the threat of a compet- ing firm launching a similar project. Consensus in the beginning is not essential. What is essential is a core group of at least one-third of the project team that is genuinely committed to the vision. They will provide the critical mass to draw others aboard. Once the language has been formulated to communicate the vision, then the statement needs to be a staple part of every working agenda, and the project manager should be prepared to deliver a “stump” speech at a moment’s notice. When problems or dis- agreements emerge, all responses should be consistent with the vision. Much has been written about visions and leadership. Critics argue that vision is a glorified substitute for shared goals. Others argue that it is one of the things that separate leaders from managers. The key is discovering what excites people about a project, being able to articulate this source of excitement in an appealing manner, and finally protecting and nurturing this source of excitement throughout the duration of the project.

Managing Project Reward Systems Project managers are responsible for managing the reward system that encourages team performance and extra effort. One advantage they have is that often project work is inherently satisfying, whether it is manifested in an inspiring vision or simple sense of accomplishment. Projects provide participants with a change in scenery, a chance to learn new skills, and an opportunity to break out of their departmental cocoon. Another inherent reward is what was referred to in Tracy Kidder, The Soul of a New Machine, as “pinball”—project success typically gives team members an option to play another exciting game.7 Still, many projects are underappreciated, boring, interfere with other more signifi- cant priorities, and are considered an extra burden. In some of these cases, the biggest reward is finishing the project so that team members can go back to what they really enjoy doing and what will yield the biggest personal payoffs. Unfortunately, when this attitude is the primary incentive, project quality is likely to suffer. In these circum- stances, external rewards play a more important role in motivating team performance. Most project managers we talk to advocate the use of group rewards. Because most project work is a collaborative effort, it only makes sense that the reward system would encourage teamwork. Recognizing individual members regardless of their accomplish- ments can distract from team unity. Project work is highly interdependent, so it can become problematic to distinguish who truly deserves additional credit. Cash bonuses and incentives need to be linked to project priorities. It makes no sense to reward a team for completing their work early if controlling cost was the number one priority. One of the limitations of lump-sum cash bonuses is that all too often they are consumed by the household budget to pay the dentist or mechanic. To have more value, rewards need to have lasting significance (Smith and Reinertsen, 1997). Many companies convert cash into vacation rewards, sometimes with corresponding time off. For example, there is one firm that rewarded a project team for getting the job done ahead of schedule with a four-day, all-expenses-paid trip to Walt Disney World for the members’ entire families. That vacation not only will be remembered for 7 T. Kidder, The Soul of a New Machine (New York: Avon Books, 1981), pp. 221–22.

392 Chapter 11 Managing Project Teams

years, but it also recognizes spouses and children who, in a sense, also contributed to the project’s success. Similarly, other firms have been known to give members home computers and entertainment centers. Wise project managers negotiate a discretion- ary budget so that they can reward teams' surpassing milestones with gift certificates to popular restaurants or tickets to sporting events. Impromptu pizza parties and barbecues are also used to celebrate key accomplishments. Sometimes project managers have to use negative reinforcement to motivate project performance. For example, Ritti and Levy (2009) recount the story of one project man- ager who was in charge of the construction of a new, state-of-the-art manufacturing plant. His project team was working with a number of different contracting firms. The project was slipping behind schedule, mostly because of a lack of cooperation among the different players. The project manager did not have direct authority over many key people, especially the contractors from the other companies. He did, however, have the freedom to convene meetings at his convenience. So the project manager instituted daily “coordination meetings,” which were required of all the principals involved, at 6:00 a.m. The meetings continued for about two weeks until the project got back on schedule. At that time the project manager announced that the next meeting was can- celed, and no further sunrise meetings were ever scheduled.8 While project managers tend to focus on group rewards, there are times when they need to reward individual performance. This is done not only to compensate extraordi- nary effort but also to signal to the others what exemplary behavior is. Examples of this kind of rewards include:

∙ Letters of commendation. While project managers may not have responsibility for their team members’ performance appraisals, they can write letters commending their project performance. These letters can be sent to the workers’ supervisors to be placed in their personnel files.

∙ Public recognition for outstanding work. Superlative workers should be publicly recognized for their efforts. Some project managers begin each status review meet- ing with a brief mention of project workers who have exceeded their project goals.

∙ Job assignments. Good project managers recognize that, while they may not have much budgetary authority, they do have substantial control over who does what, with whom, when, and where. Good work should be rewarded with desirable job assignments. Managers should be aware of member preferences and, when appro- priate, accommodate them.

∙ Flexibility. Being willing to make exceptions to rules, if done judiciously, can be a powerful reward. Allowing members to work at home when a child is sick or excus- ing a minor indiscretion can engender long-lasting loyalty.

Individual rewards should be used judiciously, and under extraordinary circum- stances. Nothing undermines the cohesiveness of a team more than members begin- ning to feel that others are getting special treatment or that they are being treated unfairly. Camaraderie and collaboration can quickly vanish only to be replaced by bickering and obsessive preoccupation with group politics. Such distractions can absorb energy that otherwise would be directed toward completing the project. Indi- vidual rewards typically should be used only when everyone in the team recognizes that a member is deserving of special recognition.

8 R. R. Ritti and S. L. Levy, The Ropes to Skip and Ropes to Know: Studies in Organizational Theory and Behavior (New York: Wiley, 2009) pp. 93–94.

Chapter 11 Managing Project Teams 393

Orchestrating the Decision-Making Process Most decisions on a project do not require a formal meeting to discuss alternatives and determine solutions. Instead decisions are made in real time as part of the daily interac- tions between project managers, stakeholders, and team members. For example, as a result of a routine “how’s it going?” question, a project manager discovers that a mechan- ical engineer is stuck trying to meet the performance criteria for a prototype he is respon- sible for building. The project manager and engineer go down the hallway to talk to the designers, explain the problem, and ask what, if anything, can be done. The designers distinguish which criteria are essential and which ones they think can be compromised. The project manager then checks with the marketing group to make sure the modifica- tions are acceptable. They agree with all but two of the modifications. The project man- ager goes back to the mechanical engineer and asks whether the proposed changes would help solve the problem. The engineer agrees. Before authorizing the changes he calls the project sponsor, reviews the events, and gets the sponsor to sign off on the changes. This is an example of how, by practicing MBWA (management by wandering around), project managers consult team members, solicit ideas, determine optimum solutions, and create a sense of involvement that builds trust and commitment to decisions. Still, projects encounter problems and decisions that require the collective wisdom of team members as well as relevant stakeholders. Group decision making should be used when it will improve the quality of important decisions (Vroom and Jago, 1988). This is often the case with complex problems that require the input of a variety of different spe- cialists. Group decision making should also be used when strong commitment to the decision is needed and there is a low probability of acceptance if only one person makes the decision. Participation is used to reduce resistance and secure support for the deci- sion. Guidelines for managing group decision making are provided below. Facilitating Group Decision Making Project managers play a pivotal role in guiding the group decision-making process. They must remind themselves that their job is not to make a decision but to facilitate the discussion within the group so that the team reaches a consensus on the best pos- sible solution. Consensus within this context does not mean that everyone supports the decision 100 percent, but that they all agree what the best solution is under the circum- stances. Facilitating group decision making essentially involves four major steps. Each step is briefly described next with suggestions for how to manage the process.9

1. Problem identification. The project manager needs to be careful not to state the problem in terms of choices (e.g., should we do X or Y?). Rather the project man- ager should identify the underlying problem to which these alternatives and proba- bly others are potential solutions. This allows group members to generate alternatives, not just choose among them. One useful way of defining problems is to consider the gap between where a project is (i.e., the present state) and where it should be (desired state). For example, the project may be four days behind sched- ule or the prototype weighs two pounds more than the specifications. Whether the gap is small or large, the purpose is to eliminate it. The group must find one or more courses of action that will change the existing state into the desired one.

If one detects defensive posturing during the problem identification discussion, then it may be wise to postpone the problem-solving step if possible. This allows for emotions to subside and members to gain a fresh perspective on the issues involved.

9 This discussion is based on the classic work of N. R. F. Maier, Problem-Solving Discussion and Conferences (New York: McGraw-Hill, 1963); and Problem Solving and Creativity in Individuals and Groups (Belmont, CA: Brooks-Cole, 1970).

394 Chapter 11 Managing Project Teams

2. Generating alternatives. Once there is general agreement as to the nature of the problem(s), then the next step is to generate alternative solutions. If the problem requires creativity, then brainstorming is commonly recommended. Here the team generates a list of possible solutions on a flipchart or blackboard. During that time the project manager establishes a moratorium on criticizing or evaluat- ing ideas. Members are encouraged to “piggyback” on others’ ideas by extending them or combining ideas into a new idea. The object is to create as many alterna- tives as possible no matter how outlandish they may appear to be. Some project managers report that for really tough problems they have found it beneficial to conduct such sessions away from the normal work environment; the change in scenery stimulates creativity.

3. Reaching a decision. The next step is to evaluate and assess the merits of alterna- tive solutions. During this phase it is useful to have a set of criteria for evaluating the merits of different solutions. In many cases the project manager can draw upon the priorities for the project and have the group assess each alternative in terms of its impact on cost, schedule, and performance as well as reducing the problem gap. For example, if time is critical, then the solution that solves the problem as quickly as possible would be chosen.

During the course of the discussion the project manager attempts to build con- sensus among the group. This can be a complicated process. Project managers need to provide periodic summaries to help the group keep track of its progress. They must protect those members who represent the minority view and ensure that such views get a fair hearing. They need to guarantee that everyone has an opportunity to share opinions and no one individual or group dominates the conversation. It may be useful to bring a two-minute timer to regulate the use of air time. When conflicts occur, managers need to apply some of the ideas and techniques discussed in the next section.

Project managers need to engage in consensus testing to determine what points the group agrees on and what are still sources of contention. They are careful not to interpret silence as agreement; they confirm agreement by asking questions. Ulti- mately, through thoughtful interaction, the team reaches a “meeting of the minds” as to what solution is best for the project.

4. Follow-up. Once the decision has been made and implemented, it is important for the team to find the time to evaluate the effectiveness of the decision. If the decision failed to provide the anticipated solution, then the reasons should be explored and the lessons learned added to the collective memory bank of the project team.

Managing Conflict within the Project Disagreements and conflicts naturally emerge within a project team during the life of the project. Participants will disagree over priorities, allocation of resources, the quality of specific work, solutions to discovered problems, and so forth. Some conflicts support the goals of the group and improve project performance. For example, two members may be locked in a debate over a design trade-off decision involving different features of a product. They argue that their preferred feature is what the primary customer truly wants. This disagreement may force them to talk to or get more information from the customer, with the result that they realize nei- ther feature is highly valued, but instead the customer wants something else. On the other hand, conflicts can also hinder group performance. Initial disagreements can escalate into heated arguments with both parties storming out of the room and refusing to work together.

11-5LO Distinguish functional conflict from dysfunctional conflict and describe strategies for encouraging functional conflict and discouraging dysfunctional conflict.

Chapter 11 Managing Project Teams 395

Sources of conflict are likely to change as projects progress along the project life cycle (Thamhain and Wilemon, 1975; Posner, 1986; Adams and Brandt, 1988). Figure 11.5 summarizes the major sources of conflict in each phase.

So far the discussion of team building has been directed primarily to signifi- cant projects that command the atten- tion and involvement of assigned members. But what about projects

that have low priority for team members: the perfunc- tory task forces that members begrudgingly join? the committee work people get assigned to do? the part- time projects that pull members away from the critical work they would rather be doing? projects that cause members to privately question why they are doing this? There is no magic wand available that transforms mildly interested, part-time project teams into high- performance teams. We interviewed several project managers about such project scenarios. They all agreed that these can be very difficult and frustrating assign- ments and that there are limits to what is possible. Still, they offered tips and advice for making the best of the situation. Most of these tips focus on building commit- ment to the project when it does not naturally exist. One project manager advocated orchestrating a large “time” investment upfront on such projects— either in the form of a lengthy meeting or a significant early assignment. He viewed this as a form of down payment that members would forfeit if they didn’t carry the project to completion. Others emphasize interjecting as much fun into activities as possible. Here rituals discussed under building team identity come into play. People become

S N A P S H O T F R O M P R A C T I C E 1 1 . 5 Managing Low-Priority Projects

committed because they enjoy working together on the project. One project manager even confided that the perfect attendance at her project meetings was due primarily to the quality of the doughnuts she provided. Another strategy is to make the benefits of the project as real to the team members as possible. One project manager escalated commitment to a mandated accidents prevention task force by bringing accident victims to a project meeting. Another project manager brought the high-ranking project sponsor to recharge the team by rein- forcing the importance of the project to the company. Most project managers emphasized the importance of building a strong personal relationship with each of the team members. When this connection occurs, members work hard not so much because they really care about the project but because they don’t want to let the project manager down. Although not couched in influence cur- rency terms, these managers talked about getting to know each member, sharing contacts, offering encourage- ment, and extending a helping hand when needed. Finally, all project managers cautioned that nothing should be taken for granted on low-priority projects. They recommend reminding people about meetings and bringing extra copies of materials to meetings for those who have forgotten them or can’t find them. Proj- ect managers should remain in frequent contact with team members and remind them of their assignments. One manager summed it up best when he said, “Some- times it all boils down to just being a good nag.”

Defining Planning Executing Delivery

Priorities

Procedures

Schedules

Priorities

Schedule Schedule

Procedures Technical

Technical Workforce

Workforce Priorities

Schedule

es

ule Sche

ures Techn

cal Workf

rce Prior

dule

ical

orce

ties

Sched

d

n

foff

it

ities

dures

dules

Priori

Sched

Proced

Techn

Workf

ti

du

du

ni

foff

FIGURE 11.5 Sources of Conflict over the Project Life Cycle

396 Chapter 11 Managing Project Teams

During project definition, the most significant sources of conflict are priorities, administrative procedures, and schedule. Disputes occur over the relative impor- tance of the project compared with other activities, which project management structure to use (especially how much control the project manager should have), the personnel to be assigned, and the scheduling of the project into existing workloads. During the planning phase, the chief source of conflict remains priorities, followed by schedules, procedures, and technical requirements. This is the phase where the proj- ect moves from a general concept to a detailed set of plans. The relative importance of the project is still trying to be established as well as project priorities (time, cost, scope). Disagreements often emerge over the final schedule, the assignment of resources, communication and decision making procedures, and technical require- ments for the project. During the execution phase, friction arises over schedule slippage, technical prob- lems, and staff issues. Milestones become more difficult to meet because of accumu- lating schedule slippages. This leads to tension within the team as delays prevent others from starting or completing their work. Managing the trade-offs between time, cost, and performance becomes paramount. Project managers must decide between letting the schedule slip, investing additional funds to get back on track, or scaling back the scope of the project in order to save time. Technical problems involve finding solutions to unexpected problems and integrating the contributions of different people. The strain of the project may be expressed in interpersonal conflicts as well as pres- sures to use resources more effectively. During the delivery phase, the level of conflict tends to subside. On troubled proj- ects schedules continue to be the biggest source of conflict as schedule slippages make it more difficult to meet target completion dates. Pressures to meet objectives coupled with growing anxiety over future assignments increase interpersonal ten- sions. Technical problems are rare since most of them have been worked out during the earlier phases.

Encouraging Functional Conflict The demarcation between functional and dysfunctional conflict is neither clear nor precise. In one team, members may exchange a diatribe of four-letter expletives and eventually resolve their differences. Yet in another project team, such behavior would create irreconcilable divisions and would prohibit the parties from ever working together productively again. The distinguishing criterion is how the conflict affects project performance, not how individuals feel. Members can be upset and dissatisfied with the interchange, but as long as the disagreement furthers the objectives of the project, then the conflict is functional. Project managers should recognize that conflict is an inevitable and even a desirable part of project work; the key is to encourage func- tional conflict and manage dysfunctional conflict. A shared vision can transcend the incongruities of a project and establish a common purpose to channel debate in a constructive manner. Without shared goals there is no common ground for working out differences. In the previous example involving the design trade-off decision, when both parties agreed that the primary goal was to sat- isfy the customer, there was a basis for more objectively resolving the dispute. There- fore, agreeing in advance which priority is most important—cost, schedule, or scope—can help a project team decide what response is most appropriate. Sometimes it’s not the presence of conflict, but the absence of conflict that is the problem. Oftentimes as a result of compressed time pressures, self-doubt, and the

Chapter 11 Managing Project Teams 397

desire to preserve team harmony, members are reluctant to voice objections. This hesi- tation robs the team of useful information that might lead to better solutions and the avoidance of critical mistakes. Project managers need to encourage healthy dissent in order to improve problem solving and innovation. They can demonstrate this process by asking tough questions and challenging the rationale behind recommendations. They can also orchestrate healthy conflict by bringing in people with different points of view to critical meetings. Project managers can legitimize dissent within the team by designating someone to play the role of devil’s advocate or by asking the group to take 15 minutes to come up with all the reasons the team should not pursue a course of action. Functional conflict plays a critical role in obtaining a deeper understanding of the issues and coming up with the best decisions possible. One of the most important things project managers can do is model an appropriate response when someone disagrees or challenges their ideas. They need to avoid acting defensively and instead encourage critical debate. They should exhibit effective listen- ing skills and summarize the key issues before responding. They should check to see if others agree with the opposing point of view. Finally, project managers should value and protect dissenters. Organizations have a tendency to create too many yes-men, and the emperor needs to be told when he doesn’t have any clothes on.

Managing Dysfunctional Conflict Managing dysfunctional conflict is a much more challenging task than encouraging functional conflict. First, dysfunctional conflict is hard to identify. A manager might have two highly talented professionals who hate each other’s guts, but in the heat of competition they produce meritorious results. Is this a pleasant situation? No. Is it functional? Yes, as long as it contributes to project performance. Conversely, some- times functional conflict degenerates into dysfunctional conflict. This change occurs when technical disagreements evolve into irrational personality clashes or when failure to resolve an issue causes unnecessary delays in critical project work. The second major difficulty managers face is that there is often no easy solution to dysfunctional conflict. Project managers have to decide among a number of different strategies to manage it; here are five possibilities: 1. Mediate the conflict. The manager intervenes and tries to negotiate a resolution by

using reasoning and persuasion, suggesting alternatives and the like. One of the keys is trying to find common ground. In some cases the project manager can make the argument that the win/lose interchange has escalated to the point that it has become lose/lose for everyone and now is the time to make concessions.

2. Arbitrate the conflict. The manager imposes a solution to the conflict after listen- ing to each party. The goal is not to decide who wins but to have the project win. In doing so, it is important to seek a solution that allows each party to save face; oth- erwise the decision may provide only momentary relief. One project manager admits that she has had great success using a King Solomon approach to resolving conflict. She confides she announces a solution that neither party will like and gives the opponents two hours to come up with a better solution they can both agree on.

3. Control the conflict. Reducing the intensity of the conflict by smoothing over dif- ferences or interjecting humor is an effective strategy. If feelings are escalating, the manager can adjourn the interaction and hope cooler heads prevail the next day. If the conflict continues to escalate, project assignments may need to be rearranged if possible so that two parties don’t have to work together.

398 Chapter 11 Managing Project Teams

4. Accept it. In some cases the conflict will outlive the life of the project and, though a distraction, it is one the manager has to live with.

5. Eliminate the conflict. Sometimes the conflict has escalated to the point that it is no longer tolerable. If there is a clear villain then only he or she should be removed. If, as is often the case, both parties are at fault, then it would be wise if possible to eliminate both individuals. Their removal would give a clear signal to the others on the team that this kind of behavior is unacceptable.

In summary, project managers establish the foundation for functional conflict by estab- lishing clear roles and responsibilities, developing common goals or a shared vision, and using group incentives that reward collaboration. Project managers have to be adroit at reading body language to identify unspoken disagreement. They also have to keep in touch with what is going on in a project to identify small problems that might escalate into big conflicts. Well-timed humor and redirecting the focus to what is best for the project can alleviate the interpersonal tensions that are likely to flare up on a project team.

Rejuvenating the Project Team Over the course of a long project, a team sometimes drifts off course and loses momen- tum. The project manager needs to swing into action to realign the team with the proj- ect objectives and step on the pedal. There are both formal and informal ways of doing this. Informally, the project manager can institute new rituals like the “toy roaches” to reenergize a team. On one project that was experiencing rough going, the project man- ager stopped work and took the team bowling to relieve frustrations. On another proj- ect, a manager showed her team the movie The Shawshank Redemption to rekindle hope and commitment to success. Another option is to have the project sponsor give a pep talk to the “troops.” In other cases, a friendly challenge can reinvigorate a team. For example, one project sponsor offered to cook a five-course meal if the project got back on track and hit the next milestone. Sometimes more formal action needs to be taken. The project manager may recog- nize the need for a team-building session devoted to improving the work processes of the team. This meeting is particularly appropriate if she senses that the team is approaching a transition point in its development. The goal of such a session is to improve the project team’s effectiveness through better management of project demands and group processes. It is an inward look by the team at its own performance, behavior, and culture for the purpose of eliminating dysfunctional behaviors and strengthening functional ones. The project team critiques its performance, analyzes its way of doing things, and attempts to develop strategies to improve its operation. Oftentimes an external consultant is hired, or an internal staff specialist is assigned to facilitate the session. This process brings a more objective, outside perspective to the table, frees the project manager to be part of the process, and provides a specialist trained in group dynamics. Furthermore, if preliminary information is to be collected, team members may be more candid and open to an outsider. One caveat about using outside consultants is that too often managers resort to this as a method for dealing with a problem that they have been unable or unwilling to deal with. The marching order to the consultant is “fix my team for me.” What the manag- ers fail to recognize is that one of the keys to fixing the team is improving the working relationship between themselves and the remainder of the team. For such sessions to be effective, project managers have to be willing to have their own role scrutinized and be receptive to changing their own behavior and work habits based on the comments and suggestions of the project team.

Chapter 11 Managing Project Teams 399

Consultants use a wide variety of team-building techniques to elevate team perfor- mance. Here is a brief description of one of the more common approaches. The first step is to gather information and make a preliminary diagnosis of team performance. Whether through individual interviews or in a group forum, the consultant asks general questions about the project team performance, that is, what obstacles are getting in the way of the team being able to perform better? This information is summarized in terms of themes. When everyone has understood the themes, the group ranks them in terms of both their importance and the extent the team has ownership over them. This last dimension is criti- cal. Ownership refers to whether the team has direct influence over the issue. For example, a team probably has little influence over delivery of contracted supplies, but team members do control how quickly they inform each other of sudden changes in plans. If the group becomes preoccupied with issues outside its control, the meeting can quickly evolve into a demoralizing gripe session. Therefore, the most important issues they have direct control over become the subjects of the agenda. During the course of the meeting, much interpersonal and group process information will be generated, and that is examined too. Thus, the group works on two sets of items: the agenda items and the items that emerge from the interaction of the participants. This is where the expertise of the external facilitator becomes critical for identifying interaction patterns and their implications for team performance. As important problems are discussed, alternatives for action are developed. The team-building session concludes by deciding on specific action steps for remedying problems and setting target dates for who will do what, when. These assignments can be reviewed at project status meetings or at a special follow-up session. It has become fashionable to link team-building activities with outdoor experiences. The outdoor experience—whether it is whitewater rafting down the Rogue River in Oregon or rock climbing in Colorado—places group members in a variety of physi- cally challenging situations that must be mastered through teamwork, not individual effort. By having to work together to overcome difficult obstacles, team members are supposed to experience increased self-confidence, more respect for another’s capabili- ties, and a greater commitment to teamwork. No empirical data are available to sup- port such exotic endeavors other than the enthusiastic support of the participants. Such activities are likely to provide an intense common experience that may accelerate the social development of the team. Such an investment of time and money communicates the importance of teamwork and is considered by some a perk for being on the project. At the same time, unless the lessons from these experiences can be immediately trans- ferred to actual project work, their significance is likely to vanish.

11.4 Managing Virtual Project Teams Building a high-performance project team among a mixture of part-time and full-time members is a challenging task. Consider how much more challenging it is to build a team when members cannot engage in face-to-face interactions. Such would be the case for a virtual project team in which the team members are geographically situ- ated so that they may seldom, if ever, meet face-to-face as a team. For example, Hewlett-Packard’s integrated circuit business headquarters and a portion of the R&D facilities are located in Palo Alto, California; the two wafer fabrication operations are located in Corvallis, Oregon, and Fort Collins, Colorado; and the packaging assembly process is primarily in Singapore and Korea. It is not uncommon for professionals at each of these locations to be involved in the same project. When team members are

Understand the challenges of managing virtual project teams.

11-6LO

400 Chapter 11 Managing Project Teams

spread across different time zones and continents, the opportunity for direct communi- cation is severely limited. Electronic communication such as the Internet, e-mail, and teleconferencing takes on much more importance in virtual projects because this is the primary means of communication. See Snapshot from Practice 11.6: Managing Virtual Global Teams for an example of how this works.

Carl A. Singer, a senior program man- ager at IBM Global Services, described how global time zones were used to complete a time intensive project. The project required subject matter

experts (SMEs) to document existing best practices in maintenance domain and to port these into a knowl- edge management tool. The most proficient SMEs available were on opposite sides of the globe—Australia and Scotland. Review and control of the project was from the United States. Management realized that just working harder and smarter was not going to meet the time and quality tar- gets. For this project they used the dimension of time to their benefit. Applying sound management principles as well as taking advantage of electronic communication systems, the team was able to create a virtual 24-hour workday for quick responses and accelerated reviews. Each team consisted of veteran professionals famil- iar with the rigors of time-pressured consulting proj- ects. A local point person was identified for each team and mutually agreed-upon targets, terminology, and processes were established. An all-hands kick-off meeting was organized in which participants were able to socialize, understand local and projectwide constraints, and finalize an agreed-upon plan. The meeting was held at a corpo- rate hotel with dining accommodations. The facility was considered an “assisted living community for IBM consultants.” This hastened recovery from jet lag and provided an interruption-free work environment. Upon returning to their home bases, each team created the majority of their deliverables indepen- dently with periodic three-way conference calls to maintain coordination. A project control book was established electronically so that all participants had access to the latest project documents. The final phase of the project required intense interfacing and reviews between the teams. These reviews necessitated changes to deal with concerns, differences among subprojects, and other issues. It was here that the worldwide nature of the project was

S N A P S H O T F R O M P R A C T I C E 1 1 . 6 Managing Virtual Global Teams*

leveraged. Using a “dry cleaning approach” (in by 5 p.m. out by 9 a.m.) team members in Australia and Scotland were able to address issues generated during the U.S.-based external reviews and provide concrete responses by the beginning of the next business day. Conference calls at 6:00 a.m. (U.S. EST) were used to coordinate responses and resolve issues. Conference calls at the end of the U.S. workday were used to final- ize issues and assignments. Figure 11.6 depicts the 24-hour clock used to align communication schedules. Telephone conferencing was used instead of video- conferencing due to the setup lead time and because it would force participants to leave their offices. E-mail was used extensively for general communication. An electronic repository of project work was used to coor- dinate global involvement. In practice, a participant could draft a document and deposit it electronically only to wake up the next day to find the document annotated with suggested revisions. Likewise, one could start the day by checking an in-basket populated with documents to review and issues to address. Over time, “G’day” and “Cheers” crept into the U.S. speech— a clear indicator of team cohesion. Singer identified a number of lessons learned from the project. These included:

- lishing goals and procedures as well as “rules of courtesy.”

then step out of the way and let the professionals do their work.

- dards and deliverable templates.

even if only to say “Hello, we have nothing to talk about today.” Conference calls should be guided by pre-established agendas, note-taking procedures, and reviews.

* Carl A. Singer, “Leveraging a Worldwide Project Team,” PM Network, April 2001, pp. 36–40.

Chapter 11 Managing Project Teams 401

Two of the biggest challenges involved in managing a virtual project team are developing trust and effective patterns of communication (Lipsinger and DeRosa, 2010). Trust is difficult to establish in virtual project management. Unlike working as a traditional team, where members can see whether someone has done what they say they have done, virtual team members depend on the word of distant members. At the

FIGURE 11.6 24-Hour Global Clock

United States

(East Coast)

Australia Scotland

Prime time Secondary time Downtime

Comments

12 midnight 1 AM 2 AM 3 AM 4 AM 5 AM 6 AM 7 AM 8 AM 9 AM 10 AM 11AM

12 noon 1 PM 2 PM 3 PM 4 PM 5 PM 6 PM 7 PM 8 PM 9 PM 10 PM 11 PM

12 midnight

2 PM 3 PM 4 PM 5 PM 6 PM 7 PM 8 PM 9 PM 10 PM 11 PM

12 midnight 1 AM 2 AM 3 AM 4 AM 5 AM 6 AM 7 AM 8 AM 9 AM 10 AM 11 AM

12 noon 1 PM 2PM

5 AM 6 AM 7 AM 8 AM 9 AM 10 AM 11 AM

12 noon 1 PM 2 PM 3 PM 4 PM 5 PM 6 PM 7 PM 8 PM 9 PM 10 PM 11 PM

12 midnight 1 AM 2 AM 3 AM 4 AM 5 AM

Australia handoff for off-shift review

3-way conferencing window (primary) 3-way conferencing window (primary) 3-way conferencing window (primary)

Scotland handoff for off-shift review

3-way conferencing window (secondary) 3-way conferencing window (secondary) U.S. handoff for off-shift review

402 Chapter 11 Managing Project Teams

same time, it can be difficult to trust someone whom you may have met only one or two times or not at all. Geographical separation also prohibits the informal social inter- actions that are often essential to building camaraderie among team members. As one virtual team member put it, “You can’t have a beer together over the Internet.” So how can a project manager facilitate the development of trust within a virtual team? First, if it is impossible to hold a face-to-face meeting in the beginning, manag- ers need to orchestrate the exchange of social information—who everyone is and some personal background information during the initial electronic interchange. Second, they need to set clear roles for each team member. Ideally, specific tasks should be assigned to each member so that they can make an immediate contribution to the proj- ect. Trust in virtual projects grows through team member reliability, consistency, and responsiveness (Coutu, 1998). Finally, the project manager must consistently display enthusiasm and an action orientation in all messages; this spirit will hopefully spread to other team members. The second major challenge for managing a virtual project team is to establish effective patterns of communication. E-mail and faxes are great for communicating facts—but not the feelings behind the facts; nor do they allow for real-time communi- cation. Conference calls and project chat rooms can help, but they also have their limi- tations. Videoconferencing is a significant improvement over nonvisual electronic forms of communication. Still, it is a very expensive medium, and real-time interaction is available on only the most advanced and expensive systems. The maxim is match technology to the communication need. Here are some guidelines developed by 3M for use on their distributed projects:10

∙ When to e-mail. To distribute important information and news in a one-to-one or one-to-many frame of reference.

∙ When to use electronic bulletin boards. To encourage discussion and flush out diversity of opinion on issues.

∙ When to videoconference. Videoconference when you need to see each other’s face and expressions. This is important during the early phases of a project, when you are building relationships and developing a common understanding of what needs to be done. Use, again, when working on critical decisions and/or contentious issues.

∙ When to use conference calls. When people in different locations are working with common documents, presentations, sketches, and models. Use for status report meetings and to sustain social camaraderie.

∙ When to fly. Fly to build or repair trust. Use travel budget to get all key players together early on to instill commitment to the goals of the project and engage in team-building activities.

Even with the best communication system, managers have to overcome the problem of time zone differences, cultural nuances, and finding a convenient time for people to conference. Below are some additional tips for alleviating communication problems and enhancing the performance of virtual teams: 1. Don’t let team members vanish. Virtual teams often experience problems getting

in touch with each other. Use Internet scheduling software to store members’ calendars.

10 “3M Meeting Network,” from www.3M.com/meetings, accessed 6/6/2002.

Chapter 11 Managing Project Teams 403

2. Establish a code of conduct to avoid delays. Team members need to agree not only on what, when, and how information will be shared but also on how and when they will respond to it. Develop a priority system to distinguish messages that require immediate response from those with longer time frames.

3. Establish clear norms and protocols for surfacing assumptions and conflicts. Because most communication is nonvisual, project managers cannot watch body language and facial expressions to develop a sense of what is going on. They need to probe deeper when communicating to force members to explain their viewpoints, actions, and concerns more clearly; they must double-check comprehension.

4. Use electronic video technology to verify work. Instead of relying on others’ judgment, have members “show” work that has been done via Internet video. This can avoid costly misunderstanding and provide useful feedback.

5. Share the pain. Do not require everyone to conform to your time zone and prefer- ences. Rotate meeting times so that all team members have a turn working accord- ing to their clock.

To some extent managing a virtual project team is no different from managing a regular project team. The key is working within the constraints of the situation to develop effective ways for team members to interact and combine their talents to com- plete the project.

11.5 Project Team Pitfalls High-performance project teams can produce dramatic results. However, like any good thing, there is a dark side to project teams that managers need to be aware of. In this section we examine in more detail some of the pathologies that high-performance project teams can succumb to and highlight what project managers can do to reduce the likelihood of these problems occurring.

Groupthink Janis (1982) first identified groupthink as a factor that influenced the misguided 1961 Bay of Pigs invasion of Cuba. His term refers to the tendency of members in highly cohesive groups to lose their critical evaluative capabilities. This malady appears when pressures for conformity are combined with an illusion of invincibility to suspend crit- ical discussion of decisions. As a result decisions are made quickly with little consid- eration of alternatives; often the practice leads to fiascoes that, after the fact, appear totally improbable. Some of the symptoms of groupthink include the following: ∙ Illusion of invulnerability. The team feels invincible. It is marked by a high degree

of esprit de corps, an implicit faith in its own wisdom, and an inordinate optimism that allows group members to feel complacent about the quality of their decisions.

∙ Whitewash of critical thinking. The group members discuss only a few solutions, ignoring alternatives; they fail to examine the adverse consequences that could fol- low their preferred course of action; and they too quickly dismiss any alternatives that, on the surface, appear to be unsatisfactory.

∙ Negative stereotypes of outsiders. “Good guy/bad guy” stereotypes emerge in which the group considers any outsiders who oppose their decisions as the bad guys, who are perceived as incompetent and malicious and whose points are unworthy of seri- ous consideration.

11-7LO Recognize the different pitfalls that can occur in a project team.

404 Chapter 11 Managing Project Teams

∙ Direct pressure. When a team member does speak out or question the direction in which the team is headed, direct pressure is applied to the dissenter. He or she is reminded that speed is important and that the aim is agreement, not argument.

Bureaucratic Bypass Syndrome Project teams are often licensed to get things done without having to go through nor- mal protocols of the parent organization. Bypassing bureaucratic channels is appealing and invigorating. However, if bypassing becomes a way of life, it results in the rejec- tion of bureaucratic policies and procedures, which provide the glue for the overall organization. A team that operates outside the organization may alienate other workers who are constrained by the norms and procedures of the organization; eventually, these outside bureaucrats will find ways to put up roadblocks and thwart the project team (Johansen et al., 1991).

Team Spirit Becomes Team Infatuation High-performance project teams can be a tremendous source of personal satisfac- tion. The excitement, chaos, and joy generated by working on a challenging project can be an invigorating experience. Leavitt and Lipman-Blumen (1995) even go so far as to say that team members behave like people in love. They become infatuated with the challenge of the project and the talent around them. This total preoccupa- tion with the project and the project team, while contributing greatly to the remark- able success of the project, can leave in its wake a string of broken professional and personal relationships that contribute to burnout and disorientation upon completion of the project.

Going Native Going native is a phrase first used by the British Foreign Service during colonial times to describe agents who assumed the customs, values, and prerogatives of their foreign country assignment.11 They did so to the point that they were no longer rep- resenting the best interests of the British government but rather those of the natives. This same phenomenon can occur within project teams working abroad or in those who become closely identified with their customers. In essence, the customer’s interests take precedence over the parent organization’s interests. This change in viewpoint can lead to excessive scope creep and open defiance of corporate policy and interests. Dealing with these maladies is problematic because, in most cases, they are a distortion of a good thing, rather than a simple evil. Awareness is the first step for prevention. The next step is to take preemptive action to reduce the likelihood of these pitfalls occurring. For example, managers can reduce the isolation of the proj- ect team by creating work-related connections outside the project team. These inter- actions naturally occur in a matrix environment where members work on multiple projects and maintain ties to their home department. Likewise, the isolation of dedi- cated project teams can be reduced by the timely involvement of external specialists. In either case, the active involvement of relevant members of the parent organization at project status meetings can help maintain the link between the project and the rest of the organization. If the team appears to be suffering from groupthink, then the project manager can encourage functional conflict by playing a devil’s advocate role

11 Movie examples of this include Avatar (2010), The Sleeping Dictionary (2003), and Lawrence of Arabia (1962).

Chapter 11 Managing Project Teams 405

to encourage dissent or using a structured problem-solving approach like the nomi- nal group technique (see Snapshot from Practice 11.7: Nominal Group Technique). Finally, formal team-building sessions may reveal dysfunctional norms and refocus the attention of the team on project objectives.

GE Appliances, U.S. West, Marriott Corp., and Hewlett-Packard are among the many firms that use nominal group technique (NGT) to guide decisions on projects. The NGT begins by gath-

ering project team members and/or stakeholders around a table and identifying the project problem at hand. Each member then writes his or her solutions. Next, each member presents his or her solution to the group, and the leader writes these solutions on a chart. No criticism is allowed. This process continues until all of the ideas have been expressed. Each solution then is discussed and clarified by the group. After all the ideas have been discussed, the group members privately rank-order their preferred solutions. The balloting is tal- lied to create a rank-ordering of each solution. These

S N A P S H O T F R O M P R A C T I C E 1 1 . 7 Nominal Group Technique*

* Andrew Delbeeq, Andrew H. Van de Ven, and D. H. Gustafson, Group Techniques for Program Planning (Glenview, II: Scott Foresman, 1975).

steps are repeated if necessary to refine the list further in order to get the most preferred solution. NGT provides an orderly process for dealing with potentially inflammatory problems. It also prevents groupthink from occurring. NGT discourages any pres- sure to conform to the wishes of a high-status, powerful group member since all ideas are discussed and all pref- erences are expressed privately. Creativity should be enhanced since members are able to offer a solution based on their expertise and viewpoint. Finally, impor- tant decisions can be made in a relatively timely manner. NGT works best when there is a well-defined problem.

Project managers often work under less-than-ideal conditions to develop a cohesive team committed to working together and completing the project to the best of their abilities. They have to recruit personnel from other departments and manage the tem- porary involvement of team members. They often have to bring strangers together and quickly establish a set of operational procedures that unite their efforts and contribu- tions. They have to be skilled at managing meetings so that they do not become a burden but rather a vehicle for progress. Project managers need to forge a team identity and a shared vision that command the attention and allegiance of participants. Project managers have to encourage functional conflict that contributes to superior solutions while being on guard against dysfunctional conflict that can break a team apart. In doing these things, they have to be careful not to do too good a job and avoid the pit- falls of excessive group cohesion. While agendas, charters, visions, rewards, and so forth are important tools and tech- niques, it has been emphasized both in this chapter and in Chapter 10 that the most important tool a project manager has to build an effective project team is his or her own behavior. Just as the founding members of an organization shape the culture of the organization, the project manager shapes and influences the internal culture of the project team. A positive example can define how team members respond to changes, how they handle new tasks, and how they relate to one another and the rest of the orga- nization. There is no easy way to lead by example. It requires personal conviction, discipline, sensitivity to team dynamics, and a constant awareness of how personal actions are perceived by others.

Summary

406 Chapter 11 Managing Project Teams

Key Terms Brainstorming, 394 Dysfunctional conflict, 396 Functional conflict, 396 Groupthink, 403

Nominal group technique (NGT), 405 Positive synergy, 377 Project kick-off meeting, 383

Project vision, 388 Team building, 399 Virtual project team, 399

Review Questions

1. What are the differences between the five-stage model of team development and the punctuated equilibrium model?

2. What are the elements of an effective project vision? Why are they important? 3. Why should a project manager emphasize group rewards over individual rewards? 4. What is the difference between functional and dysfunctional conflict on a project? 5. When would it be appropriate to hold a formal team-building session on a project? 6. What are the unique challenges to managing a virtual project team? 7. What can a project manager do to avoid some of the pitfalls of a highly cohesive

project team?

Exercises 1. The following activities are based on a recently completed group project that you have been involved in. This project may have been a student project, a work project, or an extracurricular project.

a. Analyze the development of the team in terms of the five-phase model and the punctuated equilibrium model. Which model does the best job of describing how the team evolved?

b. Analyze the group in terms of the nine situational factors that influence team development. What factors positively contributed to group performance? What factors negatively contributed to group performance? How did the group try to overcome the negative factors? What could you have done differently to over- come these negative factors?

c. Analyze how effectively the group managed meetings. What did the group do well? What didn’t the group do well? If the group were formed again, what spe- cific recommendations would you make about how the group should manage meetings?

2. Assume that you have the following decision-making options: (1) make the deci- sion on your own with available information, (2) consult others before making a decision, and (3) call a meeting and reach a consensus, seeking to arrive at a final decision everyone can agree on. Which approach would you use to make each of the following decisions and why?

a. You are the project leader for Casino Night on campus, a charitable event orga- nized by your group to raise money for the homeless. The event was a big suc- cess, garnering a net profit of $3,500. Before the event your team researched nearby organizations that support the homeless and to whom the money could be given. You narrowed the choices to the “Chunk of Coal House” and “St. Mary’s Soup Kitchen.” Eventually your group decided that the funds be given to Chunk of Coal. You are about to write a check to its director when you read in the local newspaper that the Chunk of Coal House has terminated operations. What should you do with the money?

Chapter 11 Managing Project Teams 407

b. You are a golf course designer hired by Trysting Tree Golf Club to renovate their golf course. You have worked closely with the board of directors of the club to develop a new layout that is both challenging and aesthetically pleasing. Every- one is excited about the changes. The project is nearly 75 percent complete when you encounter problems on the 13th hole. The 13th hole at Trysting Tree is a 125-yard par three in which golfers have to hit their tee shots over a lake to a modulated green. During the construction of the new tee box, workers discov- ered that an underground spring runs beneath the box to the lake. You inspected the site and agreed with the construction supervisor that this could create serious problems, especially during the rainy winter months. After surveying the area, you believe the only viable option would be to extend the hole to 170 yards and create elevated tees on the adjacent hillside.

c. You are the leader of a new product development project. Your team has worked hard on developing a third-generation product that incorporates new technology and meets customer demands. The project is roughly 50 percent complete. You have just received a report from the marketing department detailing a similar product that is about to be released by a competitor. The product appears to uti- lize radical new design principles that expand the functionality of the product. This poses a serious threat to the success of your project. Top management is considering canceling your project and starting over again. They want you to make a recommendation.

3. The following activities are based on a current or recently completed group project that you have been involved in. This project may be a student project, a work proj- ect, or an extracurricular project.

a. How strong is the team identity on this project and why? b. What could participants do to strengthen team identity? c. What kind of informal activities could be used to rejuvenate the team? Why

would these activities work?

References Adams, J. R., and S. E. Brandt, “Behavioral Implications of the Project Lifecyle,” Project Management Handbook, 2nd ed., D. I. Cleland and W. R. King, eds., (New York: Van Nostrand Reinhold, 1988), pp. 206–30. Berkun, S., The Art of Project Management (Sebastopol, CA: O’Reilly, 2005). Bolman, D. G., and T. E. Deal, “What Makes Teams Work,” Organizational Dynamics, vol. 21, no. 2 (1992), pp. 34–45. Bowen, K. H., K. B. Clark, C. A. Holloway, and S. C. Wheelwright, The Perpetual Enterprise Machine, (New York: Oxford Press, 1994). Cleland, D. I., “Team Building: The New Strategic Weapon,” PM Network, vol. 11, no. 1 (1997). Coutu, D. L., “Organization Trust in Virtual Teams,” Harvard Business Review, vol. 76, no. 3 (1998), pp. 20–21. DeMarco, T., and T. Lister, Peopleware: Productive Projects and Teams, 2nd ed. (New York: Dorsett House, 1999).

408 Chapter 11 Managing Project Teams

Ericksen, J., and L. Dyer, “Right from the Start: Exploring the Effects of Early Team Events on Subsequent Project Team Performance,” Administrative Science Quarterly, vol. 49, no. 3 (2004), pp. 438–71. Frame, J. D., Managing Projects in Organizations (San Francisco: Jossey-Bass, 1995). Hackman, J. R., Leading Teams: Setting the Stage for Great Performances (Cambridge, MA: Harvard Business School Press, 2002). Homans, G. C., Social Behavior: Its Elementary Forms (New York: Harcourt Brace Jovanovich, 1961). Janis, I. L., Groupthink (Boston: Houghton Mifflin, 1982). Johansen, R., D. Sibbett, S. Benson, A. Martin, R. Mittman, and P. Saffo, Leading Business Teams: How Teams can use Technology and Group Process Tools to Enhance Performance (Reading, MA: Addison-Wesley, 1991). Katz, R., “How a Team at Digital Equipment Designed the ‘Alpha’ Chip,” The Human Side of Managing Technological Innovation, 2nd ed., ed. Ralph Katz (New York: Oxford University Press, 2004), pp. 121–33. Katzenbach, J. R., and D. K. Smith, The Wisdom of Teams (Boston: Harvard Business School Press, 1993). Kidder, T., The Soul of a New Machine (New York: Avon Books, 1981). Kirkman, B. L., B. Rosen, C. B. Gibson, P. E. Tesluk, and S. O. McPherson, “Five Challenges to Virtual Team Success: Lessons From Sabre, INC.,” Academy of Management Executive, vol. 16, no. 2 (2002), pp. 67–79. Kuruppuarachchi, P. “Virtual Team Concepts in Projects: A Case Study,” Project Management Journal, June 2009, pp. 19–33. Leavitt, H. J., and J. Lipman-Blumen, “Hot Groups,” Harvard Business Review, vol. 73 (1995), pp. 109–16. Likert, R., New Patterns in Management, (New York: McGraw-Hill, 1961). Linetz, B. P., and K. P. Rea, Project Management for the 21st Century (San Diego: Academic Press, 2001). Lipsinger, R., and D. DeRosa, Virtual Team Success: A Practical Guide for Working and Leading from a Distance (San Francisco: Jossey-Bass, 2010). Maier, N. R. F., Problem Solving and Creativity in Individuals and Groups (Belmont, CA: Brooks-Cole, 1970). Maier, N. R. F., Problem-Solving Discussion and Conference (New York: McGraw-Hill, 1963). Malhotra, A., A. Majchrzak, and B. Rosen, “Leading Virtual Teams,” Academy of Management Perspectives, vol. 21, no. 1 (2007), pp. 60–70. Maznevski, M. L., and K. M. Chudoba, “Bridging Space over Time: Global Virtual Team Dynamics and Effectiveness,” Organization Science, vol. 11. no. 5 (September–October 2000), pp. 473–92.

Chapter 11 Managing Project Teams 409

Murphy, C. and J. Clark, “Picture This: How the Language of Leaders Drives Performance,” Organizational Dynamics, 45 (2), March, 2016, pp. 139–146. Peters, T., Thriving on Chaos: Handbook for a Management Revolution (New York: Knopf, 1988). Posner, B. Z., “What’s All the Fighting About? Conflicts in Project Management,” IEEE Transactions in Engineering Management, EM-33, 1986, pp. 207–211. Ritti, R. R., and S. L. Levy, The Ropes to Skip and the Ropes to Know: Studies in Organizational Theory and Behavior (New York: Wiley, 2009). Senge, P. M., The Fifth Discipline (New York: Doubleday, 1990). Seta, J. J., P. B. Paulus, and J. Schkade, “Effects of Group Size and Proximity under Cooperative and Competitive Conditions,” Journal of Personality and Social Psychology, vol. 98, no. 2 (1976), pp. 47–53. Sherif, M., Group Conflict and Cooperation: Their Social Psychology (Chicago: Aldine, 1967). Siebdrat, F., M. Hoegl, and H. Ernst, “How to Manage Virtual Teams,” MIT Sloan Management Review, http://sloanreview.mit.edu/the-maazine/2009-summer/50412 /how-to manage-virtual teams/2009. Skilton, P. F., and K. J. Dooley, “The Effects of Repeat Collaboration on Creative Abrasion,” Academy of Management Review, vol. 35, no. 1 (2010), pp. 118–34. Smith, B. J., “Building Shared Visions: How to Begin,” The Fifth Discipline Field- book: Strategies and Tools for Building a Learning Organization, ed. P. M. Senge, C. Roberts, R. B. Ross, B. J. Smith, and A. Kleiner (New York: Doubleday, 1994), pp. 312–327. Smith, P. G., and D. G. Reinertsen, Developing Products in Half the Time (New York: Wiley, 1997, 2nd ed). Thamhain, H. J., and D. L. Wilemon, “Conflict Management in Project Life Cycle,” Sloan Management Review, vol. 16, no. 3 (1975), pp. 31–41. Thoms, P., “Creating a Shared Vision with a Project Team,” PM Network, January 1997, pp. 33–35. 3M, “Leading a Distributed Team,” www.3m.com/meetingnetwork/readingroom /meetingguide_distribteam.html. Accessed June 6, 2006. Tuchman, B. W., “Development Sequence of Small Groups,” Psychological Bulletin, vol. 63 (1965), pp. 384–399. Tuchman, B. W., and M. C. Jensen, “Stages of Small Group Development Revisited,” Group and Organizational Studies, vol. 2 (1977), pp. 419–427. Vroom, V. H., and A. G. Jago, The New Leadership (Englewood Cliffs, NJ: Prentice Hall, 1988). Zander, A., Making Groups Effective (San Francisco: Jossey-Bass, 1994).

410 Chapter 11 Managing Project Teams

Case 11.1

Kerzner Office Equipment Amber Briggs looked nervously at her watch as she sat at the front of a large table in the cafeteria at Kerzner Office Equipment. It was now 10 minutes after 3:00 and only 10 of the 14 members had arrived for the first meeting of the Kerzner anniversary task force. Just then two more members hurriedly sat down and mumbled apologies for being late. Briggs cleared her throat and started the meeting.

KERZNER OFFICE EQUIPMENT Kerzner Office Equipment is located in Charleston, South Carolina. It specializes in the manufacture and sales of high-end office furniture and equipment. Kerzner enjoyed steady growth during its first five years of existence with a high-water employment mark of more than 1,400 workers. Then a national recession struck, forcing Kerzner to lay off 25 percent of its employees. This was a traumatic period for the company. Justin Tubbs was brought in as the new CEO, and things began to slowly turn around. Tubbs was committed to employee participation and redesigned operations around the concept of self-managing teams. The company soon introduced an innovative line of ergonomic furniture designed to reduce back strain and carpal tunnel. This line of equipment proved to be a resounding success, and Kerzner became known as a leader in the industry. The company currently employs 1,100 workers and has just been selected for the second straight time by the Charleston Post and Courier as one of the 10 best local firms to work for in South Carolina.

AMBER BRIGGS Amber Briggs is a 42-year-old human resource specialist who has worked for Kerzner for the past five years. During this time she has performed a variety of activities involving recruitment, training, compensation, and team building. David Brown, vice president of human resources, assigned Briggs the responsibility for organizing Kerzner’s 10th anniversary celebration. She was excited about the project because she would report directly to top management. CEO Tubbs briefed her as to the purpose and objectives of the celebration. Tubbs stressed that this should be a memorable event and that it was important to celebrate Kerzner’s success since the dark days of the layoffs. Moreover, he confided that he had just read a book on corporate cultures and believed that such events were important for conveying the values at Kerzner. He went on to say that he wanted this to be an employee celebration—not a celebration conjured up by top management. As such, she would be assigned a task force of 14 employees from each of the major departments to organize and plan the event. Her team was to present a preliminary plan and budget for the event to top management within three months. When discussing budgets, Tubbs revealed that he felt the total cost should be somewhere in the $150,000 range. He concluded the meeting by offering to help Briggs in any way he could to make the event a success. Soon thereafter Briggs received the list of the names of the task force members, and she contacted them either by phone or e-mail to arrange today’s meeting. She had to scramble to find a meeting place. Her cubicle in human resources was too small to accommodate such a group, and all the meeting rooms at Kerzner were booked or being refurbished. She settled on the cafeteria because it was usually

Chapter 11 Managing Project Teams 411

deserted in the late afternoon. Prior to the meeting she posted the agenda on a flip- chart (see Figure C11.1) adjacent to the table. Given everyone’s busy schedules, the meeting was limited to just one hour.

THE FIRST MEETING Briggs began the meeting by saying, “Greetings. For those who don’t know me, I’m Amber Briggs from human resources and I’ve been assigned to manage the 10th anni- versary celebration at Kerzner. Top management wants this to be a special event—at the same time they want it to be our event. This is why you are here. Each of you rep- resents one of the major departments, and together our job is to plan and organize the celebration.” She then reviewed the agenda and asked each member to introduce him/ herself. The tall, red-haired woman to the right of Briggs broke the momentary silence by saying, “Hi, I’m Cara Miller from Plastics. I guess my boss picked me for this task force because I have a reputation for throwing great parties.” In turn each member followed suit. Below is a sampling of their introductions: “Hi, I’m Mike Wales from maintenance. I’m not sure why I’m here. Things have

been a little slow in our department, so my boss told me to come to this meeting.” “I’m Megan Plinski from domestic sales. I actually volunteered for this assignment.

I think it will be a lot of fun to plan a big party.” “Yo, my name is Nick Psias from accounting. My boss said one of us had to join

this task force, and I guess it was my turn.” “Hi, I’m Rick Fennah. I’m the only one from purchasing who has been here since

the beginning. We’ve been through some rough times, and I think it is important to take time and celebrate what we’ve accomplished.”

“Hi, I’m Ingrid Hedstrom from international sales. I think this is a great idea, but I should warn you that I will be out of the country for most of the next month.”

“I’m Abby Bell from engineering. Sorry for being late, but things are a bit crazy in my department.”

Briggs circled the names of the two people who were absent and circulated a roster so that everyone could check to see if their phone numbers and e-mail addresses were cor- rect. She then summarized her meeting with Tubbs and told the group that he expected them to make a formal presentation to top management within 10 weeks. She acknowl- edged that they were all busy people and that it was her job to manage the project as efficiently as possible. At the same time, she reiterated the importance of the project and that this would be a very public event: “If we screw up, everyone will know about it.” Briggs went over the ground rules and emphasized that from now on meetings would start on time and that she expected to be notified in advance if someone was going to be absent. She summarized the first part of the project as centering on five key questions: when, where, what, who, and how much? She created a stir in the group when she responded to a question about cost by informing them that top management was willing to pay up to $150,000 for the event. Megan quipped, “This is going to be one hell of a party.” Briggs then turned the group’s attention to identifying a common meeting time. After jousting for 15 minutes, she terminated the discussion by requesting that each member submit a schedule of free time over the next month by Friday. She would use this information and a new planning software to identify optimal times. She ended the meeting by thanking the members for coming and asking them to begin soliciting ideas from co-workers about how this event should be celebrated. She announced that

3:00

3:15

3:30

3:45

4:00

Introductions

Project overview

Ground rules

Meeting times

Adjourn

Agenda

FIGURE C11.1 Celebration Task Force

412 Chapter 11 Managing Project Teams

she would meet individually with each of them to discuss their role on the project. The meeting was adjourned at 4:00 p.m. 1. Critique Briggs’s management of the first meeting. What, if anything, should she

have done differently? 2. What barriers is she likely to encounter in completing this project? 3. What can she do to overcome these barriers? 4. What should she do between now and the next meeting?

Case 11.2

Ajax Project Tran was taking his dog Callie on her evening walk as the sun began to set over the coastal range. He looked forward to this time of the day. It was an opportunity to enjoy some peace and quiet. It was also a time to review events on the Ajax project and plot his next moves. Ajax is the code name given by CEBEX for a high-tech security system project funded by the U.S. Department of Defense (DOD). Tran is the project manager and his core team consisted of 30 full-time hardware and software engineers. Tran and his family fled Cambodia when he was four years old. He joined the U.S. Air Force when he was 18 and used the education stipend to attend Washington State University. He joined CEBEX upon graduating with a dual degree in mechanical and electrical engineering. After working on a variety of projects for 10 years Tran decided he wanted to enter management. He went to night school at the University of Washington to earn an MBA. Tran became a project manager for the money. He also thought he was good at it. He enjoyed working with people and making the right things happen. This was his fifth project and up to now he was batting .500, with half of his projects coming ahead of schedule. Tran was proud that he could now afford to send his oldest child to Stanford University. Ajax was one of many defense projects the CEBEX Corporation had under contract with DOD. CEBEX is a huge defense company with annual sales in excess of $30 bil- lion and more than 120,000 employees worldwide. CEBEX’s five major business areas are Aeronautics, Electronic Systems, Information & Technology Services, Integrated Systems & Solutions, and Space Systems. Ajax was one of several new projects spon- sored by the Integrated Systems & Solutions division aimed at the homeland security business. CEBEX was confident that it could leverage its technical expertise and polit- ical connections to become a major player in this growing market. Ajax was one of several projects directed at designing, developing, and installing a security system at an important government installation. Tran had two major concerns when he started the Ajax project. The first was the technical risks inherent in the project. In theory the design principles made sense and the project used proven technology. Still the technology had never been applied in the field in this matter. From past experience, Tran knew there was a big difference between the laboratory and the real world. He also knew that integrating the audio, optical, tactile, and laser subsystems would test the patience and ingenuity of his team. The second concern involved his team. The team was pretty much split down the middle between hardware and electrical engineers. Not only did these engineers have different skill sets and tend to look at problems differently, but generational differences between the two groups were evident as well. The hardware engineers were almost all

Chapter 11 Managing Project Teams 413

former military, family men with conservative attire and beliefs. The electrical engi- neers were a much motlier crew. They tended to be young, single, and at times very cocky. While the hardware engineers talked about the Seattle Mariners, raising teenag- ers, and going to Palm Desert to play golf, the software engineers talked about Vapor, the latest concert at the Gorge amphitheater, and going mountain biking in Peru. To make matters worse, tension between these two groups within CEBEX festered around salary issues. Electrical engineers were at a premium, and the hardware engi- neers resented the new hires’ salary packages, which were comparable to what they were earning after 20 years of working for CEBEX. Still the real money was to be made from the incentives associated with project performance. These were all contin- gent on meeting project milestones and the final completion date. Before actual work started on the project, Tran arranged a two-day team-building retreat at a lodge on the Olympic peninsula for his entire team as well as key staff from the government installation. He used this time to go over the major objectives of the project and unveil the basic project plan. An internal consultant facilitated several team-building activities that made light of cross-generational issues. Tran felt a real sense of camaraderie within the team. The good feelings generated from the retreat carried over to the beginning of the project. The entire team bought into the mission of the project and technical challenges it represented. Hardware and electrical engineers worked side by side to solve prob- lems and build subsystems. The project plan was built around a series of five tests, with each test being a more rigorous verification of total system performance. Passing each test represented a key milestone for the project. The team was excited about conducting the first Alpha test one week early—only to be disappointed by a series of minor technical glitches that took two weeks of problem solving to resolve. The team worked extra hard to make up for the lost time. Tran was proud of the team and how hard members had worked together. The Alpha II test was conducted on schedule, but once again the system failed to perform. This time three weeks of debugging was needed before the team received the green light to move to the next phase of the project. By this time, team goodwill had been tested, and emotions were a bit frayed. A cloud of disappointment descended over the team as hopes of bonuses disappeared with the project falling further behind schedule. This was augmented by cynics who felt that the original schedule was unfair and the deadlines were impossible to begin with. Tran responded by starting each day with a status meeting where the team reviewed what they accomplished the previous day and set new objectives for that day. He believed these meetings were helpful in establishing positive momentum and reinforc- ing a team identity among the engineers. He also went out of his way to spend more time with the “troops,” helping them solve problems, offering encouragement, and a sincere pat on the back when one was deserved. He was cautiously optimistic when the time came to conduct the Alpha III test. It was the end of the day when the switch was turned on, but nothing happened. Within minutes the entire team heard the news. Screams could be heard down the hallway. Perhaps the most telling moment was when Tran looked down at the company’s park- ing lot and saw most of his project team walking by themselves to their cars. As his dog Callie chased some wild bunnies, Tran pondered what he should do next.

1. How effective has Tran been as a project manager? Explain. 2. What problem(s) does Tran face? 3. How would you go about solving them? Why?

414 Chapter 11 Managing Project Teams

Case 11.3

Franklin Equipment, Ltd.* Franklin Equipment, Ltd. (FEL), with headquarters and main fabrication facilities in Saint John, New Brunswick, was founded 75 years ago to fabricate custom-designed large machines for construction businesses in the Maritime Provinces. Over the years its product lines became strategically focused on creating rock-crushing equipment for dam and highway construction and for a few other markets that require the processing of aggregate. FEL now designs, fabricates, and assembles stationary and portable rock-crushing plants and services its own products and those of its competitors. In the 1970s, FEL began to expand its market from the Maritime Provinces to the rest of Canada. FEL currently has several offices and fabrication facilities throughout the country. More recently, FEL has made a concerted effort to market its products internationally. Last month, FEL signed a contract to design and fabricate a rock-crushing plant for a Middle East construction project, called Project Abu Dhabi. Charles Gatenby secured this contract and has been assigned as project manager. This project is viewed as a coup because FEL has wanted to open up markets in this area for a long time and has had difficulty getting prospective customers to realize that FEL is a Canadian firm and not from the United States. Somehow these customers view all North American ven- dors as the same and are reluctant to employ any of them because of international political considerations. A project of this scope typically starts with the selection of a team of managers responsible for various aspects of the design, fabrication, delivery, and installation of the product. Manager selection is important because the product design and fabrica- tion vary with the unique needs of each customer. For example, the terrain, rock char- acteristics, weather conditions, and logistical concerns create special problems for all phases of plant design and operations. In addition, environmental concerns and labor conditions vary from customer to customer and from region to region. In addition to the project manager, all projects include a design engineer; an oper- ations manager, who oversees fabrication and on-site assembly; and a cost accoun- tant, who oversees all project financial and cost reporting matters. Each of these people must work closely together if a well-running plant is to be delivered on time and within cost constraints. Because international contracts often require FEL to employ host nationals for plant assembly and to train them for operations, a human resource manager is also assigned to the project team. In such cases, the human resource manager needs to understand the particulars of the plant specifications and then use this knowledge to design selection procedures and assess particular training needs. The human resource manager also needs to learn the relevant labor laws of the customer’s country. FEL assigns managers to project teams based on their expertise and their availabil- ity to work on a particular project given their other commitments. This typically means that managers without heavy current project commitments will be assigned to new projects. For instance, a manager finishing one project will likely be assigned a man- agement position on a new project team. The project manager typically has little to say about who is assigned to his or her team.

* Courtesy of John A. Drexler Jr., Oregon State University.

Chapter 11 Managing Project Teams 415

Because he secured Project Abu Dhabi and has established positive working rela- tionships with the Abu Dhabi customer, Gatenby was assigned to be project manager. Gatenby has successfully managed similar projects. The other managers assigned to Project Abu Dhabi are Bill Rankins, a brilliant design engineer, Rob Perry, operations manager with responsibility for fabrication and installation, Elaine Bruder, finance and cost accounting manager, and Sam Stonebreaker, human resource manager. Each of these managers has worked together on numerous past projects. A few years ago, FEL began contracting for team facilitator services from several consulting firms to help new project teams operate effectively. Last month, FEL recruited Carl Jobe from one of these consulting firms to be a full-time internal con- sultant. A number of managers, including Gatenby, were so impressed with Jobe’s skills that they convinced FEL top management of the need to hire a permanent inter- nal facilitator; Jobe was the obvious choice. Because Gatenby was instrumental in hiring Jobe at FEL, he was excited at the prospect of using Jobe to facilitate team building among Project Abu Dhabi team members. Gatenby was very proud of having secured this project and had expected to be appointed project manager. He knew that this project’s success would be instrumen- tal in advancing his own career. Gatenby told Jobe, “This project is really important to FEL and to me personally. I really need for you to help us develop into a team that works well together to achieve the project’s goals within budget. I’ve observed your success in developing teams on other projects, and I expect you’ll do the same for Project Abu Dhabi. I’ll take care of you if you help me make this work.” Jobe outlined for Gatenby how he would proceed. Jobe would begin by interview- ing team members individually to learn their perceptions of each other and of the promises and pitfalls of being involved in this project. Meetings of the entire team would follow these interviews using the information he collected to help establish a team identity and a shared vision. Jobe interviewed Bruder first. She expressed skepticism about whether the project could succeed. During the interview, Bruder appeared to be distant, and Jobe could not figure out why he had not established good rapport with her. Bruder intimated that she expected a lot of cost overruns and a lot of missed production deadlines. But not know- ing Jobe well, Bruder was reluctant to identify any specific barriers to the project’s success. While she would not directly say so, it was clear to Jobe that Bruder did not want to be a part of Project Abu Dhabi. Jobe left this interview confused and wonder- ing what was going on. Jobe’s next interview was with Perry, the operations manager. Perry has worked at FEL for 15 years, and he immediately came to the point: “This project is not going to work. I cannot understand why upper management keeps assigning me to work on projects with Rankins. We simply cannot work together, and we don’t get along. I’ve disliked him from day one. He keeps dropping the fact that he has earned all these advanced degrees from Purdue. And he keeps telling us how things are done there. I know he’s better educated than I am, and he’s really smart. But I’m smart too and am good at what I do. There’s no need for Rankins to make me feel like an idiot because I don’t have a degree. Jobe, I’ll be honest with you. Rankins has only been here for five years, but I hold him personally responsible for my problem with alcohol, and for its resulting effect on my marriage. I got divorced last year, and it’s Rankins’s fault.” Jobe next talked with Rankins, who said, “I don’t care what you do. Perry and I simply can’t work closely together for the nine months it will take to get it done. One of us will kill the other. Ever since I arrived at FEL, Perry has hated my guts and

416 Chapter 11 Managing Project Teams

does everything he can to sabotage my designs. We usually worry about customers creating change orders; here it’s the fabrication and operations manager who is responsible for them. Perry second-guesses everything I do and makes design changes on his own, and these are always bad decisions. He is out of control. I swear he stays awake at nights thinking up ways to ruin my designs. I don’t have this prob- lem with any other manager.” Jobe left these interviews thoroughly discouraged and could not imagine what would come up in his interview with Stonebreaker. But Stonebreaker was quite posi- tive: “I enjoy these international projects where I get to travel abroad and learn about different cultures. I can’t wait to get started on this.” Jobe asked Stonebreaker about the ability of various team members to work together. Stonebreaker replied, “No problem! We’ve all worked together before and have had no problems. Sure, there have been ruffled feathers and hurt feelings between Rankins and Perry. Rankins can be arrogant and Perry stubborn, but it’s never been anything that we can’t work around. Besides, both of them are good at what they do— both professionals. They’ll keep their heads on straight.” Jobe was even more bewildered. Gatenby says this project’s success rides on Jobe’s facilitation skills. The finance manager appears to want off this project team. The design engineer and operations manager admit they detest each other and cannot work together. And the human resources manager, having worked on projects with Perry and Rankins before, expects a rosy working relationship and anticipates no problems. Jobe had a second meeting with Gatenby. Before discussing the design of the team- building sessions, he asked questions to learn what Gatenby thought about the ability of team members to work together. Gatenby admitted that there has been very bad blood between Perry and Rankins, but added, “That’s why we hired you. It’s your job to make sure that the history between those two doesn’t interfere with Project Abu Dhabi’s success. It’s your job to get them to work well together. Get it done.” Their dialogue toward the end of this meeting progressed as follows: Jobe: “Why do you expect Rankins and Perry to work well together, given their

history? What incentives do they have to do so?” Gatenby: “As you should know, FEL requires formal goal setting between project

managers and functional managers at the beginning of each project. I’ve already done this with Bruder, Stonebreaker, Perry, and Rankins. Perry and Rankins have explicit goals stating they must work well together and cooperate with each other.”

Jobe: “What happens if they do not meet these goals?” Gatenby: “I’ve already discussed this with top management. If it appears to me after

two months that things are not working out between Perry and Rankins, FEL will fire Rankins.”

Jobe: “Does Perry know this?” Gatenby: “Yes.”

1. Evaluate the criteria FEL uses to assign managers to project teams. What efficien- cies do these criteria create? What are the resulting problems?

2. Why is it even more important that project team members work well together on international projects such as Project Abu Dhabi?

3. Discuss the dilemma that Jobe now faces. 4. What should Jobe recommend to Gatenby?

Outsourcing: Managing Interorganizational Relations12

LEARNING OBJECTIVES After reading this chapter you should be able to:

12-1 Understand the advantages and disadvantages of outsourcing project work.

12-2 Describe the basic elements of a Request for Proposal (RFP).

12-3 Identify best practices for outsourcing project work.

12-4 Practice principled negotiation.

12-5 Describe the met-expectations model of customer satisfaction and its implications for working with customers on projects.

OUTLINE 12.1 Outsourcing Project Work

12.2 Request for Proposal (RFP)

12.3 Best Practices in Outsourcing Project Work

12.4 The Art of Negotiating

12.5 A Note on Managing Customer Relations

Summary

Appendix 12.1: Contract Management

C H A P T E R T W E L V E

418

. . . being a good partner has become a key corporate asset. I call it a company’s collaborative advantage. In the global economy, a well-developed ability to create and sustain fruitful collaborations gives companies a significant competitive leg up. —Rosabeth Moss Kanter, Harvard Business School professor

It is rare in today’s flat world to find important projects that are being completed totally in-house. Outsourcing or contracting significant segments of project work to other companies is commonplace. For example, nine states attempting to unify the accounting of all their state agencies did not have the internal resources to implement such a large project. Hence, project teams were formed consisting of personnel from software, hardware, and accounting firms to implement the projects. Small high-tech firms outsource research to determine what features customers value in new products they are developing. Even industry giants such as Microsoft and Intel commonly hire independent firms to test new products they are developing.

Project networks

6

Managing risk 7

Monitoring progress

13

Teams 11

Outsourcing 12

Project manager

10

Strategy 2

Introduction 1

Organization 3

Schedule resources & costs

8

Intern ation

al

proje cts

15

Agile PM 16

Project closure

14

Estimate 5

Reducing duration

9

Define project

4

419

420 Chapter 12 Outsourcing: Managing Interorganizational Relations

Contracting project work has long been the norm in the construction industry, where firms hire general contractors who, in turn, hire and manage cadres of subcontractors to create new buildings and structures. For example, the Chunnel project, which created a transportation tunnel between France and England, involved more than 250 organiza- tions. Contracting is not limited to large projects. For example, an insurance company worked with an outside contractor to develop an answering service that directs custom- ers to specific departments and employees. The trend for the future suggests that more and more projects will involve working with people from different organizations. This chapter extends the previous two chapters’ discussion of building and manag- ing relations by focusing specifically on issues surrounding working with people from other organizations to complete a project. First, the advantages and disadvantages of outsourcing project work are introduced. This is followed by a discussion of Request for Proposals (RFPs) and the solicitation process. Best practices used by firms to out- source and collaborate with each other on are discussed next. The focus then shifts to the art of negotiating, which is at the heart of effective collaboration. Negotiating skills and techniques for resolving disagreements and reaching optimal solutions are then presented. The chapter closes with a brief, but important, note on managing customer relations. In addition, an appendix on contract management is included to augment our discussion of how organizations work together on projects.

12.1 Outsourcing Project Work The term outsourcing has traditionally been applied to the transferring of business functions or processes (e.g., customer support, IT, accounting) to other, often foreign companies. For example, when you call your Internet provider to solve a technical problem you are likely to talk to a technician in Bangalore, India, or Bucharest, Romania. Outsourcing is now being applied to contracting significant chunks of project work. For example, Apple and Motorola work closely with manufacturers in China to develop next-generation smartphones. Toyota and DaimlerChrysler collaborate with suppliers to develop new automobile platforms. The shift toward outsourcing is readily apparent in the film industry. During the golden era of Hollywood, huge, vertically integrated corporations made movies. Stu- dios such as MGM, Warner Brothers, and 20th Century–Fox owned large movie lots and employed thousands of full-time specialists—set designers, camera people, film editors, and directors. Star actors like Humphrey Bogart and Marilyn Monroe were signed to exclusive studio contracts for a set number of films (e.g., six films over three years). Today, most movies are made by a collection of individuals and small compa- nies who come together to make films project-by-project. This structure allows each project to be staffed with the talent most suited to its demands rather than choosing from only those people the studio employs. This same approach is being applied to the creation of new products and services. For example, see Figure 12.1. Figure 12.1 depicts a situation in which a zero-gravity reclining chair is being devel- oped. The genesis for the chair comes from a mechanical engineer who developed the idea in her garage. The inventor negotiates a contract with a catalog firm to develop and manufacture the chair. The catalog company in turn creates a project team of manufac- turers, suppliers, and marketing firms to create the new chair. Each participant adds req- uisite expertise to the project. The catalog firm brings its brand name and distribution channels to the project. Tool and die firms provide customized parts which are delivered to a manufacturing firm that will produce the chair. Marketing firms refine the design, develop packaging, and test market potential names. A project manager is assigned by the catalog firm to work with the inventor and the other parties to complete the project.

12-1LO Understand the advan- tages and disadvantages of outsourcing project work.

Chapter 12 Outsourcing: Managing Interorganizational Relations 421

Many outsourced projects operate in a virtual environment in which people are linked by computers, faxes, computer-aided design systems, and video teleconferenc- ing. They rarely, if ever, see one another face-to-face. On other projects, participants from different organizations work closely together, for example, at a construction site or in shared office space. In either case, people come and go as services are needed, much as in a matrix structure, but they are not formal members of one organization, just technical experts who form a temporary alliance with an organization, fulfill their contractual obligations, and then move on to the next project. The advantages of outsourcing project work are many: 1. Cost reduction. Companies can secure competitive prices for contracted services,

especially if the work can be outsourced offshore. Furthermore, overhead costs are dramatically cut since the company no longer has to internally maintain the con- tracted services.

2. Faster project completion. Not only can work be done more cheaply, but it can also be done faster. Competitive pricing means more resources for the dollar. For exam- ple, you can hire three Indian software engineers for the price of one American software engineer. Furthermore, outsourcing can provide access to equipment that can accelerate completion of project tasks. For example, by contracting a backhoe operater you are able to accomplish in four hours what it would take a landscaping crew four days to complete.

3. High level of expertise. A high level of expertise and technology can be brought to bear on the project. A company no longer has to keep up with technological advances. Instead, it can focus on developing its core competencies and hire firms with the know-how to work on relevant segments of the project.

4. Flexibility. Organizations are no longer constrained by their own resources but can pursue a wide range of projects by combining their resources with talents of other companies. Small companies can instantly go global by working with foreign partners.

Marketing firm

Tool & die firms

Advertising firm

Parts suppliers

Manufacturer

Project manager

Catalog company

Inventor

Legal firm

Reclining chair

FIGURE 12.1 Reclining Chair Project

422 Chapter 12 Outsourcing: Managing Interorganizational Relations

BACKGROUND In 2002 the basic design and plans for  Boeing’s 787 Dreamliner were accepted and given the charter to “Go.” The Dreamliner boasts the latest

design and revolutionary technology in the history of commercial air travel. But the project met bumpy weather. The first 787 aircraft, scheduled to be tested in July 2007, was delayed until December 2009. Orders for the advanced 787 grew quickly to over 800 planes. This rosy picture presented Boeing with a giant-sized headache. For various reasons (such as design, out- sourcing, and labor issues) delivery dates slipped behind three years or more and costs ballooned to sev- eral billion dollars. Many analysts blame outsourcing work to foreign suppliers for a majority of the cost and schedule overruns.

KEY FACTORS INFLUENCING OUTSOURCING DECISION The Dreamliner outsourcing decision that gave 70 per- cent of plane content to outside suppliers included 30 percent to foreign suppliers. These percentages are greater than any previous commercial plane built by Boeing. Boeing’s outsourcing rationale was based on typical economic considerations of cost, sales, and risk. In Boeing’s case this meant:

Cost. Establishing partnerships with suppliers to lower risks and development costs, along with gaining some valuable expertise and process innovation. Sales. Farming out numerous designs and compo- nents to foreign countries (e.g., Sweden, Italy, South Korea, and China) with the expectation that these countries will buy planes from Boeing in the future.

S N A P S H O T F R O M P R A C T I C E 1 2 . 1 The Boeing 787 Dreamliner*

Risk. Recognizing the need to balance risk of out- sourcing at the organizational and operational levels is crucial. The different levels are co-dependent. Tak- ing gigantic steps away from successful outsourcing small amounts of past aircraft to foreign suppliers in- creases risk. The complexities in coordinating new technology and advance capabilities are daunting.

© Kyodo/AP Photo

* http://seattletimes.nwsource.com/html/sundaybuzz /2014125414_sundaybuzz06.html; http://atwonline.com /aircraft-engines-components/news/boeing-commercial -airplanes-ceo-concedes-787-outsourcingbackfired. Accessed: 1/12/2013.

The disadvantages of outsourcing project work are less well documented: 1. Coordination breakdowns. Coordination of professionals from different organiza-

tions can be challenging, especially if the project work requires close collaboration and mutual adjustment. Breakdowns are exacerbated by physical separation with people working in different buildings, different cities, if not different countries.

2. Loss of control. There is potential loss of control over the project. The core team depends on other organizations that they have no direct authority over. While long- term survival of participating organizations depends on performance, a project may falter when one partner fails to deliver.

3. Conflict. Projects are more prone to interpersonal conflict since the different par- ticipants do not share the same values, priorities, and culture. Trust, which is essen- tial to project success, can be difficult to forge when interactions are limited and people come from different organizations.

Chapter 12 Outsourcing: Managing Interorganizational Relations 423

Clearly, the outsourcing decision ricocheted. Costs are over budget, some sales have been rescinded, custom- ers are seeking compensation for delays, and potential ROI is reduced.

IMPACTS Boeing’s brand has been seriously tarnished by delays and mismanagement. The process to manage the logistics of outsourcing was not able to handle the vol- ume of logistical problems and change management issues. Chronic delays of a few nonperforming partners induced Boeing to buy out or support partners and con- sumed cash. Wall Street estimates cost overruns range between 12 and 18 billion dollars over the original planned investment of $5 billion. Lessons learned from outsourcing of the 787 Dreamliner can point the way to bring back the shine to Boeing’s reputation as the leader in design, technology, and integration.

LESSONS LEARNED The lessons learned in the Dreamliner launch have been well documented. A few obvious relevant lessons are noted in suggestion form here:

- nization and component levels. For example, assess the risks and implications of farming out large por- tions (30 percent) of the design and manufacture of crucial components to foreign suppliers. Outsourc- ing tends to work better in noncore areas.

resources. Due diligence reduces problems.

and problems. Increase liaison and supervision of supply chain logistics with outsource partners.

out key expertise. This runs the risk of becoming fully reliant on suppliers and transferring unique intellectual property. Partners get risk-free technical know-how, high margin markets for component parts over the life of the plane, and perhaps the fu- ture ability to become a future competitor.

components carries the burden of careful coordina- tion and liaison.

Boeing executives have acknowledged the prob- lems associated with outsourcing large portions of the 787 Dreamliner. For example, Boeing’s Commer- cial Airplanes Chief, Jim Albaugh, expressed to stu- dents at Seattle University, “We spent a lot more money in trying to recover [the project] than we ever would have spent if we’d tried to keep the key tech- nologies closer to home. The pendulum swung too far.” He added that, in part, chasing the financial mea- sure of return on assets led Boeing astray. Boeing CEO Jim McNerney noted that the 787 game plan may have been overly ambitious, incorporating too many firsts all at once.

THE FUTURE Although Boeing’s 787 outsourcing experience was very costly, outsourcing will continue and evolve. Les- sons learned will prompt aircraft builders to reevaluate future outsourcing and move on. Expect to see empha- sis on risk- and cost-sharing partnerships. The major short-term challenge for Boeing is to ramp up production to satisfy the hundreds of waiting orders. Boeing can recoup by adjusting their integra- tive outsourcing and logistics model as a top priority.

4. Security issues. Depending on the nature of the project, trade and business secrets may be revealed. This can be problematic if the contractor also works for your com- petitor. Confidentiality is another concern and companies have to be very careful when outsourcing processes like payroll, medical transcriptions, and insurance information.

5. Political hot potato. Foreign outsourcing of work is perceived as a major cause of underemployment and U.S. companies are under increased pressure to keep jobs local. Furthermore, companies like Apple have been criticized for the oppressive labor practices of some of their suppliers in China.

Few people disagree that reducing costs is the primary motive behind outsourcing project work. However, there are limits to outsourcing (see Snapshot from Practice 12.1: Boeing 787 Dreamliner), and there appears to be a shift away from simply nailing the best low-cost deal to securing services from companies that provide the best value in

424 Chapter 12 Outsourcing: Managing Interorganizational Relations

terms of both cost and performance. Performance is not limited to simply the quality of specific work but also ability to collaborate and work together. Companies are doing their homework to determine “Can we work with these people?”

12.2 Request for Proposal (RFP) Once an organization decides to outsource project work, the customer or project man- ager is frequently responsible for developing a Request for Proposal (RFP). The responsible project manager will require input from all stakeholders connected to the activities covered in the RFP. The RFP will be announced to external contractors/ vendors with adequate experience to implement the project. For example, government projects frequently advertise with a “request for proposal” to outside contractors for roads, buildings, airports, military hardware, space vehicles. Similarly, businesses use RFPs to solicit bids for building a clean room, developing a new manufacturing pro- cess, delivering software for insurance billing, conducting a market survey. In all of these examples, requirements and features should be in enough detail that contractors have a clear description of the final deliverable that will meet the customer’s needs. RFPs are important. In practice, the most common error is to offer an RFP that lacks sufficient detail. This lack of detail typically results in conflict issues, misunderstand- ings, often legal claims between the contractor and owner, and, ultimately, a dissatisfied customer. All RFPs are different, but the outline in Figure 12.2 is a good starting point for the development of a detailed RFP. Each step is briefly described next. 1. Summary of needs and request for action. The background and a simple descrip-

tion of the final project deliverable are given first. For example, through simulated war games, the U.S. Navy has found their giant warships of the past are too vulner- able against today’s technology (an example is the Silkworm antiship missiles). In addition, the Navy’s mission has shifted to supporting ground forces and peace- keeping missions, which require getting closer to shore. As a result, the Navy is revamping ships for near-shore duty. The Navy will select three designs for further refinement from the responses to its RFP. In general, it is expected that the new ship will be capable of at least 55 knots, measure between 80 and 250 feet in length, and be fitted with radar absorbing panels to thwart guided missiles.

2. Statement of work (SOW) detailing the scope and major deliverables. For example, if the project involves a market research survey, the major deliverables could be design, data collection, data analysis, and providing recommendations by February 21, 2014, for a cost not to exceed $300,000.

3. Deliverable specifications/requirements, features, and tasks. This step should be very comprehensive so bid proposals from contractors can be validated and later

12-2LO Describe the basic ele- ments of a Request for Proposal (RFP).

FIGURE 12.2 Request for Proposal 1. Summary of needs and request for action2. Statement of work (SOW) detailing the scope and major deliverables

3. Deliverable specifications/requirements, features, and tasks 4. Responsibilities—vendor and customer 5. Project schedule 6. Costs and payment schedule 7. Type of contract 8. Experience and staffing 9. Evaluation criteria

Chapter 12 Outsourcing: Managing Interorganizational Relations 425

used for control. Typical specifications cover physical features such as size, quan- tity, materials, speed, and color. For example, an IT project might specify require- ments for hardware, software, and training in great detail. Tasks required to complete deliverables can be included if they are known.

4. Responsibilities—vendor and customer. Failing to spell out the responsibilities for both parties is notorious for leading to serious problems when the contractor implements the project. For example, who pays for what? (If the contractor is to be on site, will the contractor be required to pay for office space?) What are the limits and exclusions for the contractor? (For example, who will supply test equipment?) What communication plan will be used by the contractor and owner? If escalation of an issue becomes necessary, what process will be used? How will progress be evaluated? Well-defined responsibilities will avoid many unforeseen problems later.

5. Project schedule. This step is concerned with getting a “hard” schedule which can be used for control and evaluating progress. Owners are usually very demanding in meeting the project schedule. In today’s business environment, time-to-market is a major “hot button” that influences market share, costs, and profits. The schedule should spell out what, who, and when.

6. Costs and payment schedule. The RFP needs to set out very clearly how, when, and the process for determining costs and conditions for progress payments.

7. Type of contract. Essentially there are two types of contracts—fixed-price and cost-plus. Fixed-price contracts agree on a price or lump sum in advance, and it remains as long as there are no changes to the scope provisions of the agreement. This type is preferred in projects that are well defined with predictable costs and minimal risks. The contractor must exercise care estimating cost because any under- estimating of costs will cause the contractor’s profit to be reduced. In cost-plus contracts the contractor is reimbursed for all or some of the expenses incurred dur- ing performance of the contract. This fee is negotiated in advance and usually involves a percent of total costs. “Time and materials” plus a profit factor are typi- cal of cost-plus contracts. Both types of contracts can include incentive clauses for superior performance in time and cost, or in some cases, penalties—for example, missing the opening date of a new sports stadium. Appendix 12.1 elaborates further on contract management.

8. Experience and staffing. The ability of the contractor to implement the project may depend on specific skills; this necessary experience should be specified, along with assurance such staff will be available for this project.

9. Evaluation criteria. The criteria for evaluating and awarding the project contract should be specified. For example, selection criteria frequently include methodol- ogy, price, schedule, and experience; in some cases these criteria are weighted. Use of the outline in Figure 12.2 will help to ensure key items in the proposal are not omitted. A well-prepared RFP will provide contractors with sufficient guidelines to prepare a proposal that clearly meets the project and customer’s needs.

Selection of Contractor from Bid Proposals Interested contractors respond to project RFPs with a written bid proposal. It is likely that several contractors will submit bid proposals to the customer. The final step in the RFP process is to select the contractor who best meets the require- ments requested in the RFP. The selection criteria given in the RFP are used to evaluate which contractor is awarded the contract to implement the project. Losing contractors

426 Chapter 12 Outsourcing: Managing Interorganizational Relations

should be given an explanation of the key factors that led to the selection of the winning contractor/vendor; appreciation for their participation and effort should be acknowledged. See Figure 12.3, Contractor Evaluation Template, adapted from one used in practice.

12.3 Best Practices in Outsourcing Project Work This section describes some of the best practices we have observed being used by firms that excel in project management (see Figure 12.4). Although the list is by no means comprehensive, it reflects strategies used by organizations with extensive out- sourcing experience. These practices reveal an underlying theme in how firms approach contracted work on projects. Instead of the traditional master–slave relation- ship between owner and provider or buyer and seller, all parties work together as part- ners sharing the ultimate goal of a successful project. Differences between the traditional approach and the partnering approach to man- aging contracted relationships are summarized in Table 12.1.1 Partnering requires more than a simple hand-shake. It typically entails a significant commitment of time and energy to forge and sustain collaborative relations among all parties. This commit- ment is reflected in the seven best practices which will be discussed next.

Well-Defined Requirements and Procedures Convincing people from different professions, organizations, and cultures to work together is difficult. If expectations and requirements are fuzzy or open to debate, this is even harder. Successful firms are very careful in selecting the work to be outsourced. They often choose to contract only work with clearly defined deliverables with

Identify best practices for outsourcing project work.

12-3LO

FIGURE 12.3 Contractor Evaluation Template

Contractor Evaluation Template Maximum Weight Proposal 1 Proposal 2 Proposal 3 Proposal 4

Contractor qualifications Weight = 10 Technical skills available Weight = 20 Understanding of contract and conditions Weight = 5 Financial strength to implement project Weight = 15 Understanding of proposal specifications Weight = 10 Innovativeness and originality of proposal Weight = 5 Reputation for delivering on time and budget Weight = 15 Price Weight = 20 Total 100

W

W

L

FIGURE 12.4 Best Practices in Outsourcing Project Work

1 C. Cowan, C. F. Gray, and E. W. Larson, “Project Partnering,” Project Management Journal, 12 (4) December 1992, pp. 5–15.

Chapter 12 Outsourcing: Managing Interorganizational Relations 427

TABLE 12.1 Key Differences Between Partnering and Traditional Approaches to Managing Contracted Relationships

Partnering Approach Traditional Approach Mutual trust forms the basis for strong working Suspicion and distrust; each party is wary of the relationships. motives for actions by the other. Shared goals and objectives ensure common Each party’s goals and objectives, while similar, direction. are geared to what is best for them. Joint project team exists with high level of Independent project teams; teams are spatially interaction. separated with managed interactions. Open communications avoid misdirection and Communications are structured and guarded. bolster effective working relationships. Long-term commitment provides the opportunity Single project contracting is normal. to attain continuous improvement. Objective critique is geared to candid Objectivity is limited due to fear of reprisal and lack assessment of performance. of continuous improvement opportunity. Access to each other’s organization resources Access is limited with structured procedures and is available. self-preservation taking priority over total optimization. Total company involvement requires Involvement is normally limited to project-level commitment from CEO to team members. personnel. Integration of administrative systems Duplication and/or translation takes place with equipment takes place. attendant costs and delays. Risk is shared jointly among the partners, which Risk is transferred to the other party. encourages innovation and continuous improvement.

measurable outcomes. For example, contractors hire electric firms to install heating and air-conditioning systems, electronic firms use design firms to fabricate enclosures for their products, and software development teams outsource the testing of versions of their programs. In all of these cases, the technical requirements are spelled out in detail. Even so, communicating requirements can be troublesome, especially with foreign providers (see the Snapshot from Practice 12.2: Four Strategies for Communicating with Outsourc- ers), and extra care has to be taken to ensure that expectations are understood. Not only do requirements have to be spelled out, but the different firms’ project management systems need to be integrated. Common procedures and terminology need to be established so that different parties can work together. This can be problem- atic when you have firms with more advanced project management systems working with less developed organizations. Surprisingly, this often is the case when U.S. firms outsource software work to India. We have heard reports that Indian providers are shocked at how unsystematic their U.S. counterparts are in their approach to managing software projects. The best companies address this issue up front instead of waiting for problems to emerge. First they assess “fit” between providers’ project management methods and their own project management system. This is a prime consideration in choosing ven- dors. Work requirements and deliverables are spelled out in detail in the procurement process. They invest significant time and energy to establishing project communica- tion systems to support effective collaboration. Finally, whenever you work with other organizations on projects, security is an important issue. Security extends beyond competitive secrets and technology to include access to information systems. Firms have to establish robust safeguards to prevent information access and the introduction of viruses due to less secure provider systems. Information technology security is an additional cost and risk that needs to be addressed up front before outsourcing project work.

428 Chapter 12 Outsourcing: Managing Interorganizational Relations

Dr. Adam Kolawa offers four strategies for overcoming poor communication with offshore project partners.

STRATEGY 1: RECOGNIZE CULTURAL DIFFERENCES

Realize that not everyone you communicate with shares your assumptions. What is obvious to you is not neces- sarily obvious to your partner. This is especially true with foreign outsourcers. As an American, you likely assume that laws are generally obeyed. Believe it or not, that’s generally not true in most of the world, where laws are guidelines that are not necessarily followed. This can lead to major communication problems! You think if you write a contract, everybody is going to adhere to it. For many people, a contract is merely a suggestion.

STRATEGY 2: CHOOSE THE RIGHT WORDS When you explain your requirements to an outsourcer, word choice is critical. For many outsourcers, English is still a foreign language—even in India, where both out- sourcing and the English language are common. No matter how prevalent English has become, your out- sourcer might have a basic understanding of each word you utter yet be not completely clear on the exact meaning of the message you’re trying to convey. This is why you should speak in a direct manner using short sentences made of basic, simple words.

STRATEGY 3: CONFIRM YOUR REQUIREMENTS You should take the following steps to confirm that the outsourcer thoroughly understands your requirements:

1. Document your requirements. Follow up your con- versations in writing. Commit your requirements to

S N A P S H O T F R O M P R A C T I C E 1 2 . 2 Four Strategies for Communicating with Outsourcers*

paper for the outsourcer. Many people understand written language better than spoken language, probably because they have more time to process the message.

2. Insist your outsourcer re-document your require- ments. Leave nothing to chance. Require outsourc- ers to write the requirements in their own words. If outsourcers cannot relay to you what you explained to them, then they didn’t understand.

3. Request a prototype. After the requirements are written, ask the outsourcer to create a prototype for you. This is a safety net to ensure that your wants and needs are positively understood. Ask the provider to sketch what you want your final product to look like or build a quick, simple program that reflects how the final product will look.

STRATEGY 4: SET DEADLINES Another important cultural difference relates to sched- ules and deadlines. To most Americans, a deadline is a set completion date. In many other cultures, a deadline is a suggestion that maybe something will be finished by that indicated date. To ensure that outsourced work is completed on time it is imperative to add a penalty clause to your contract or enforce late fees. Although these strategies were directed toward working with foreign outsourcers, you would be sur- prised to find how many project managers use them when working with their American counterparts!

*Adam Kolawa, “Four Strategies for Communicating with Outsourcers,” Enterprise Systems Journal at www.esj.com, accessed September 13, 2005.

Extensive Training and Team-Building Activities Too often managers become preoccupied with the plans and technical challenges of the project and assume that people issues will work themselves out over time. Smart firms recognize that people issues are as important, if not more important, than techni- cal issues. They train their personnel to work effectively with people from other orga- nizations and countries. This training is pervasive. It is not limited to management but involves all the people, at all levels, who interact with and are dependent upon out- sourcers. Whether in a general class on negotiation or a specific one on working with Chinese programmers, team members are provided with a theoretical understanding of the barriers to collaboration as well as the skills and procedures to be successful. The training is augmented by interorganizational team-building sessions designed to forge healthy relationships before the project begins. Team-building workshops involve the key players from the different firms, for example, engineers, architects, lawyers,

Chapter 12 Outsourcing: Managing Interorganizational Relations 429

specialists, and other staff. In many cases, firms find it useful to hire an outside consultant to design and facilitate the sessions. Such a consultant is typically well-versed in interor- ganizational team building and can provide an impartial perspective to the workshop. The length and design of the team-building sessions will depend on the experience, commitment, and skill level of the participants. For example, one project, in which the owner and the contractors were relatively inexperienced at working together, utilized a two-day workshop. The first day was devoted to ice-breaking activities and establish- ing the rationale behind partnering. The conceptual foundation was supported by exer- cises and minilectures on teamwork, synergy, win/win, and constructive feedback. The second day began by examining the problems and barriers that prevented collaboration in the past. Representatives from the different organizations were separated and each asked the following: ∙ What actions do the other groups engage in that create problems for us? ∙ What actions do we engage in that we think create problems for them? ∙ What recommendations would we make to improve the situation? The groups shared their responses and asked questions on points needing clarifica- tion. Agreements and disparities in the lists were noted and specific problems were identified. Once problem areas were noted, each group was assigned the task of iden- tifying its specific interests and goals for the project. Goals were shared across groups, and special attention was devoted to establishing what goals they had in common. Recognition of shared goals is critical for transforming the different groups into a cohesive team. The team-building sessions often culminate with the creation of a partnering char- ter signed by all of the participants. This charter states their common goals for the proj- ect as well as the procedures that will be used to achieve these goals (see Figure 12.5 for an example of the first page of a project charter).

Well-Established Conflict Management Processes in Place Conflict is inevitable on a project and, as pointed out in the previous chapter, disagree- ments handled effectively can elevate performance. Dysfunctional conflict, however, can catch fire and severely undermine project success. Outsourced projects are susceptible to conflicts since people are unaccustomed to working together and have different values and perspectives. Successful firms invest significant time and energy up front in estab- lishing the “rules of engagement” so that disagreements are handled constructively. Escalation is the primary control mechanism for dealing with and resolving prob- lems. The basic principle is that problems should be resolved at the lowest level within a set time limit (say, 24 hours), or they are “escalated” to the next level of manage- ment. If so, the principals have the same time limit to resolve the problem, or it gets passed on to the next higher level. No action is not an option. Nor can one participant force concessions from the other by simply delaying the decision. There is no shame in pushing significant problems up the hierarchy; at the same time, managers should be quick to point out to subordinates those problems or questions that they should have been able to resolve on their own. If possible, key personnel from the respective organizations are brought together to discuss potential problems and responses. This is usually part of a coordinated series of team-building activities discussed earlier. Particular attention is devoted to estab- lishing the change management control system where problems often erupt. People who are dependent on each other try to identify potential problems that may occur and

430 Chapter 12 Outsourcing: Managing Interorganizational Relations

FI GU

RE 12

.5 P

ro je

ct P

ar tn

er in

g C

ha rt

er

Chapter 12 Outsourcing: Managing Interorganizational Relations 431

agree in advance how they should be resolved. See the Snapshot from Practice 12.3: “Partnering” a Flu Shot for Projects for the benefits of doing this. Finally, principled negotiation is the norm for resolving problems and reaching agreements. This approach, which emphasizes collaborative problem solving, is dis- cussed in detail later in this chapter.

Frequent Review and Status Updates Project managers and other key personnel from all involved organizations meet on a regular basis to review and assess project performance. Collaborating as partners is considered a legitimate project priority which is assessed along with time, cost, and performance. Teamwork, communication, and timely problem resolution are evalu- ated. This provides a forum for identifying problems not only with the project but also with working relationships so that they can be resolved quickly and appropriately. More and more companies are using online surveys to collect data from all proj- ect participants about the quality of working relations (see Figure 12.6 for a partial example). With this data one can gauge the “pulse” of the project and identify issues that need to be addressed. Comparison of survey responses period by period permits tracking areas of improvement and potential problems. In some cases, follow-up team-building sessions are used to focus on specific problems and recharge collaboration. Finally, when the time to celebrate a significant milestone arrives, no matter who is responsible, all parties gather if possible to celebrate the success. This reinforces a

Before starting a bond-financed school construction project, Ohio does what a theater company does before opening night—it holds a dress rehearsal. Led by Cleveland-based Project Manage-

ment Consultants, state and local school officials, con- struction managers, and architects get together before building begins to figure out how to talk to each other and how to handle problems. Each party discusses problems that have occurred in the past and collec- tively they problem solve ways for preventing them from occurring on the current project. Consultants help participants develop a set of guidelines for working together. Just as a theatrical dress rehearsal can allow a company to find and fix glitches before they ruin a show, preconstruction partnering can find early solu- tions to problems before they become lawsuits. For example, during the discussions it becomes apparent that different parties are interpreting a key requirement differently. Instead of waiting for this difference to escalate into a major problem, the parties reach a shared understanding before work begins.

S N A P S H O T F R O M P R A C T I C E 1 2 . 3 “Partnering” a Flu Shot for Projects*

* Mary Wisneiski, “Partnering Used to Curb Costs in Ohio School Construction,” Bond Buyer, 11/22/2000, 334 (31023) 3/4p, 2bw.

“This works because traditionally everyone does their own work on a project, behind their own walls,” said Jeffrey Applebaum, a construction lawyer and managing director of Project Management Consultants, a wholly owned subsidiary of the law firm of Thomp- son, Hine, & Flory. “We’re taking down the walls. This is more efficient.” “We couldn’t be more pleased with this process,” said Randy Fischer, executive director of the Ohio School Facilities Commission, which distributes state money to school construction projects. “We are cur- rently administering $3 billion of construction, and we don’t have any major disputes.” Crystal Canan, chief of contract administration for the commission, offered a medical metaphor, compar- ing partnering to a “flu shot” that will prevent the debil- itating effects of litigation, work stoppages, and communication breakdowns. “Every building construc- tion project is a candidate for the flu,” Canan said. “We see partnering as a vaccination.”

432 Chapter 12 Outsourcing: Managing Interorganizational Relations

common purpose and project identity. It also establishes positive momentum going into the next phase of the project.

Co-Location When Needed One of the best ways to overcome interorganizational friction is to have people from each organization working side by side on the project. Smart companies rent or make available the necessary accommodations so that all key project personnel can work collectively together. This allows the high degree of face-to-face interaction needed to coordinate activities, solve difficult problems, and form a common bond. This is espe- cially relevant for complex projects in which close collaboration from different parties is required to be successful. For example, the U.S government provides housing and common office space for all key contractors responsible for developing disaster response plans. Our experience tells us that co-location is critical and well worth the added expense and inconvenience. When creating this is not practically possible, the travel budget for the project should contain ample funds to support timely travel to different organizations. Co-location is less relevant for independent work that does not require ongoing coordination between professionals from different organizations. This would be the case if you are outsourcing discrete, independent deliverables like beta testing or a marketing campaign. Here normal channels of communication can handle the coordi- nation issues.

Evaluation of partnering process: attitudes, teamwork, process. (Collected separately from owner and contractor participants, compared, and aggregated.)

1. Communications between the owner/contractor personnel are

1 2 3 4 5

Difficult, guarded

Not evident or inconsistent

Ignored

Cool, detached, unresponsive, removed

Personal issues

Easy, open, up front

Obvious and consistent

Attacked promptly

Genuine, unreserved, complete

Treated as project problems

2. Top management support of partnering process is

3. Problems, issues, or concerns are

4. Cooperation between owner and contractor personnel is

5. Responses to problems, issues, or concerns frequently become

1 2 3 4 5

1 2 3 4 5

1 2 3 4 5

1 2 3 4 5

FIGURE 12.6 Sample Online Survey

Chapter 12 Outsourcing: Managing Interorganizational Relations 433

Fair and Incentive-Laden Contracts When negotiating contracts the goal is to reach a fair deal for all involved. Managers recognize that cohesion and cooperation is undermined if one party feels he or she is being unfairly treated by others. They also realize that negotiating the best deal in terms of price can come back to haunt them with shoddy work and change order gouging. Performance-based contracts, in which significant incentives are established based on priorities of the project, are becoming increasingly popular. For example, if time is critical, then contractors accrue payoffs for beating deadlines; if scope is critical, then bonuses are issued for exceeding performance expectations. At the same time contrac- tors are held accountable with penalty clauses for failure to perform up to standard, meet deadlines, and/or control costs. More specific information about different types of contracts is presented in this chapter’s appendix on contract management. Companies recognize that contracts can discourage continuous improvement and innovation. Instead of trying some new, promising technique that may reduce costs, contractors will avoid the risks and apply tried and true methods to meet contracted requirements. Companies that treat contractors as partners consider continuous improvement as a joint effort to eliminate waste and pursue opportunities for cost sav- ings. Risks as well as benefits are typically shared 50/50 between the principals, with the owner adhering to a fast-track review of proposed changes. How the U.S. Department of Defense reaps the benefits of continuous improvement through value engineering is highlighted in the Snapshot from Practice 12.4: Value Engineering Awards.

Long-Term Outsourcing Relationships Many companies recognize that major benefits can be enjoyed when outsourcing arrangements extend across multiple projects and are long term. For example, Corning and Toyota are among the many firms that have forged a network of long-term strate- gic partnerships with their suppliers. The average large corporation is involved in around 30 alliances today versus fewer than 3 in the early 1990s. Among the many advantages for establishing a long-term partnership are the following: ∙ Reduced administrative costs—The costs associated with bidding and selecting a

contractor are eliminated. Contract administration costs are reduced as partners become knowledgeable of their counterpart’s legal concerns.

∙ More efficient utilization of resources—Contractors have a known forecast of work while owners are able to concentrate their workforce on core businesses and avoid the demanding swings of project support.

∙ Improved communication—As partners gain experience with each other, they develop a common language and perspective, which reduces misunderstanding and enhances collaboration.

∙ Improved innovation—The partners are able to discuss innovation and associated risks in a more open manner and share risks and rewards fairly.

∙ Improved performance—Over time partners become more familiar with each oth- er’s standards and expectations and are able to apply lessons learned from previous projects to current projects.

Working as partners is a conscious effort on the part of management to form col- laborative relationships with personnel from different organizations to complete a project. For outsourcing to work, the individuals involved need to be effective

434 Chapter 12 Outsourcing: Managing Interorganizational Relations

negotiators capable of merging interests and discovering solutions to problems that contribute to the project. The next section addresses some of the key skills and tech- niques associated with effective negotiation.

12.4 The Art of Negotiating Effective negotiating is critical to successful collaboration. All it takes is one key prob- lem to explode to convert a sense of “we” into “us versus them.” At the same time, nego- tiating is pervasive through all aspects of project management work. Project managers must negotiate support and funding from top management. They must negotiate staff and technical input from functional managers. They must coordinate with other project man- agers and negotiate project priorities and commitments. They must negotiate within their project team to determine assignments, deadlines, standards, and priorities. Project man- agers must negotiate prices and standards with vendors and suppliers. A firm under- standing of the negotiating process, skills, and tactics is essential to project success. Many people approach negotiating as if it is a competitive contest. Each negotiator is out to win as much as he or she can for his or her side. Success is measured by how

Practice principled negotiation.

12-4LO

As part of an effort to cut costs the United States Department of Defense (DoD) issues annual Value Engineering Awards. Value engineering is a sys- tematic process to analyze functions

to identify actions to reduce cost, increase quality, and improve mission capabilities across the entire spec- trum of DoD systems, processes, and organizations. The Value Engineering Awards Program is an acknowl- edgment of outstanding achievements and encourages additional projects to improve in-house and contractor productivity. In 2015, 48 different individuals and project teams received recognition from the DoD, reporting over $5.5 billion in savings or cost reduction. One team that received an award was AMRDEC Maintenance Engineering Division at Corpus Christ, Texas, which reported a savings of $66 million with 91 value engineering projects completed. Kevin Rees leads a team of 62 employees respon- sible for the airworthiness of all helicopters that go through the depot in South Texas for maintenance.

“Each aircraft component has an overhaul manual that requires parts to be replaced at certain times. Those parts have to be thrown away,” Rees said. “We worked to repair and reclass those parts so they wouldn’t have to be thrown away. We used new tech- nologies for welding repairs, composite repairs,

S N A P S H O T F R O M P R A C T I C E 1 2 . 4 U.S. Department of Defense’s Value Engineering Awards*

* K. Hawkins “AMCOM, Partners Take Home Big Wins for Value Engineering,” www.army.mil, June 26, 2015.

plating repairs, metal spray repairs and technology repairs. There are 20,000 to 25,000 engine parts, and we are working to reclaim those parts when they have to be replaced.”

“Value engineering is so important to what we are doing, especially in these days with budgets coming down. It’s nice to be able to save cost while also im- proving quality,” Rees said. “But it goes beyond that for us as a team. We all have an intrinsic motivation. We want to do well for the taxpayer and the Soldier. We take a lot of pride in our work. Getting recognized isn’t our motivator, but it does encourage us.”

© Cultura Creative/Alamy RF

Chapter 12 Outsourcing: Managing Interorganizational Relations 435

much is gained compared with the other party. While this may be applicable when negotiating the sale of a house, it is not true for project management. Project manage- ment is not a contest! First, the people working on the project, whether they represent different companies or departments within the same organization, are not enemies or competitors but rather allies or partners. They have formed a temporary alliance to complete a project. For this alliance to work requires a certain degree of trust, coopera- tion, and honesty. Second, if conflicts escalate to the point where negotiations break down and the project comes to a halt, then everyone loses. Third, unlike bartering with a street vendor, the people involved on project work have to continue to work together. Therefore, it behooves them to resolve disagreements in a way that contributes to healthy working relationships. Finally, as pointed out in the previous chapter, conflict on a project can be good. When dealt with effectively it can lead to innovation, better decisions, and more creative problem solving. Project managers accept this noncompetitive view of negotiation and realize that negotiation is essentially a two-part process: The first part deals with reaching an agreement; the second part is the implementation of that agreement. It is the imple- mentation phase, not the agreement itself, that determines the success of negotiations. All too often, managers reach an agreement with someone only to find out later that they failed to do what they agreed to do or that their actual response fell far short of expectations. Experienced project managers recognize that implementation is based on satisfaction not only with the outcome but also with the process by which the agree- ment was reached. If someone feels bullied or tricked into doing something, this feel- ing will invariably be reflected by half-hearted performance. Veteran project managers do the best they can to merge individual interests with what is best for the project and come up with effective solutions to problems. Fisher and Ury from the Harvard Negotiation Project champion an approach to negotiating that embodies these goals.2 It emphasizes developing win/win solutions while protect- ing yourself against those who would take advantage of your forthrightness. Their approach is called principled negotiation and is based on four key points listed in Table 12.2 and discussed in the following sections.

1. Separate the People from the Problem Too often personal relations become entangled with the substantive issues under con- sideration. Instead of attacking the problem(s), people attack each other. Once people feel attacked or threatened their energy naturally goes to defending themselves, and not to solving the problem. The key, then, is to focus on the problem—not the other person—during the negotiation. Avoid personalizing the negotiation and framing the negotiation as a contest. Instead, try to keep the focus on the problem to be resolved. In Fisher and Ury’s words: Be hard on the problem, soft on the people. By keeping the focus on the issues and not the personalities, negotiators are better able to let the other person blow off steam. On important problems it is not uncommon for people to become upset, frustrated, and angry. However, one angry attack produces

2 R. Fisher and W. Ury, Getting to Yes: Negotiating Agreement without Giving In, 2nd ed. (New York: Penguin Books, 1991).

1. Separate the people from the problem. 2. Focus on interests, not positions. 3. Invent options for mutual gain. 4. When possible, use objective criteria.

TABLE 12.2 Principled Negotiation

436 Chapter 12 Outsourcing: Managing Interorganizational Relations

an angry counterattack, and the discussion quickly escalates into a heated argument, an emotional chain reaction. In some cases people use anger as a means of intimidating and forcing concessions because the other person wishes to preserve the relationship. When people become emo- tional, negotiators should keep a cool head and remember the old German proverb, “Let anger fly out the window.”3 In other words, in the face of an emotional outburst, imagine opening a window and letting the heat of the anger out the window. Avoid taking things personally, and redirect personal attacks back to the question at hand. Don’t react to the emotional outburst, but try to find the issues that triggered it. Skilled negotiators keep their cool under stressful times and, at the same time, build a bond with others by empa- thizing and acknowledging common sources of frustration and anger. While it is important to separate the people from the problem during actual negotia- tions, it is beneficial to have a friendly rapport with the other person prior to negotiating. Friendly rapport is consistent with the social network tenet introduced in Chapter 10 of building a relationship before you need it. If, in the past, the relationship has been marked by healthy give-and-take, in which both parties have demonstrated a willing- ness to accommodate the interests of the other, then neither individual is likely to adopt an immediate win/lose perspective. Furthermore, a positive relationship adds a common interest beyond the specific points of contention. Not only do both parties want to reach an agreement that suits their individual interests, but they also want to do so in a manner that preserves their relationship. Each is therefore more likely to seek solutions that are mutually beneficial.

2. Focus on Interests, Not Positions Negotiations often stall when people focus on positions: I’m willing to pay $10,000. No, it will cost $15,000. I need it done by Monday. That’s impossible, we can’t have it ready until

Wednesday. While such interchanges are common during preliminary discussions, managers must prevent this initial posturing from becoming polarized. When such positions are stated, attacked, and then defended, each party figuratively begins to draw a line he or she will not cross. This line creates a win/lose scenario in which someone has to lose by crossing the line in order to reach an agreement. As such, the negotiations can become a war of wills, with concessions being seen as a loss of face. The key is to focus on the interests behind your positions (what you are trying to achieve) and separate these goals from your ego as best you can. Not only should you be driven by your interests, but you should try to identify the interests of the other party. Ask why it will cost so much or why it can’t be done by Monday. At the same time, make your own interests come alive. Don’t just say that it is critical that it be done by Monday; explain what will happen if it isn’t done by Monday. Sometimes when the true interests of both parties are revealed, there is no basis for conflict. Take, for example, the Monday versus Wednesday argument. This argument could apply to a scenario involving a project manager and the production manager of a small, local firm that was contracted to produce prototypes of a new generation of computer mouse. The project manager needs the prototypes on Monday to demon- strate to a users’ focus group. The production manager said it would be impossible. The project manager said this would be embarrassing because marketing had spent a 3 Ibid.

Chapter 12 Outsourcing: Managing Interorganizational Relations 437

lot of time and effort setting up this demonstration. The production manager again denied the request and added that he already had to schedule overtime to meet the Wednesday delivery date. However, when the project manager revealed that the pur- pose of the focus group was to gauge consumers’ reactions to the color and shape of the new devices, not the finished product, the conflict disappeared. The production manager told the project manager that she could pick up the samples today if she wanted because production had an excess supply of shells. When focusing on interests, it is important to practice the communication habit: Seek first to understand, then to be understood. This involves what Stephen Covey calls empathetic listening, which allows a person to fully understand another person’s frame of reference—not only what that person is saying but also how he or she feels. Covey asserts that people have an inherent need to be understood. He goes on to observe that satisfied needs do not motivate human behavior, only unsatisfied needs do. People try to go to sleep when they are tired, not when they are rested. The key point is that until people believe they are being understood, they will repeat their points and reformulate their arguments.4 If, on the other hand, you satisfy this need by seek- ing first to understand, then the other party is free to understand your interests and focus directly on the issues at hand. Seeking to understand requires discipline and compassion. Instead of responding to the other person by asserting your agenda, respond by summarizing both the facts and feelings behind what the other person has said and checking the accuracy of comprehension.

3. Invent Options for Mutual Gain Once the individuals involved have identified their interests, then they can explore options for mutual gain. This is not easy. Stressful negotiations inhibit creativity and free exchange. What is required is collaborative brainstorming in which people work together to solve the problem in a way that will lead to a win/win scenario. The key to brainstorming is separating the inventing from the deciding. Begin by taking 15 minutes to generate as many options as possible. No matter how outlandish any option is, it should not be subject to criticism or immediate rejection. People should feed off the ideas of others to generate new ideas. When all the possible options are exhausted, then sort through the ideas that were generated to focus on those with the greatest possibilities. Clarifying interests and exploring mutual options create the opportunity for dove- tailing interests. Dovetailing means one person identifies options that are of low cost to them but of high interest to the other party. This is only possible if each party knows what the other’s needs are. For example, in negotiating price with a parts supplier, a project manager learned from the discussion that the supplier was in a cash flow squeeze after purchasing a very expensive fabrication machine. Needed cash was the primary reason the supplier had taken such a rigid position on price. During the brain- storming session, one of the options presented was to prepay for the order instead of the usual payment on delivery arrangement. Both parties seized on this option and reached an amicable agreement in which the project manager would pay the supplier for the entire job in advance in exchange for a faster turnaround time and a significant price reduction. Such opportunities for win/win agreements are often overlooked because the negotiators become fixated on solving their problems and not on opportu- nities to solve the other person’s problems.

4 S. R. Covey, The Seven Habits of Highly Effective People (New York: Simon and Schuster, 1990).

438 Chapter 12 Outsourcing: Managing Interorganizational Relations

4. When Possible, Use Objective Criteria Most established industries and professions have developed standards and rules to help deal with common areas of dispute. Both buyers and sellers rely on the blue book to establish price parameters for a used car. The construction industry has building codes and fair practice policies to resolve proof of quality and safe work procedures. The legal profession uses precedents to adjudicate claims of wrongdoing. Whenever possible, you should insist on using external, objective criteria to settle disagreements. For example, a disagreement arose between a regional airlines firm and the independent accounting team entrusted with preparing the annual financial state- ment. The airline firm had made a significant investment by leasing several used air- planes from a larger airline. The dispute involved whether this lease should be classified as an operating or capital lease. This was important to the airline because if the purchase was classified as an operating lease, then the associated debt would not have to be recorded in the financial statement. However, if the purchase was classified as a capital lease, then the debt would be factored into the financial statement and the debt/equity ratio would be much less attractive to stockholders and would-be investors. The two parties resolved this dispute by deferring to formulas established by the Financial Accounting Standards Board. As it turns out the accounting team was cor- rect, but, by deferring to objective standards, they were able to deflect the disappoint- ment of the airline managers away from the accounting team and preserve a professional relationship with that firm.

Dealing with Unreasonable People Most people working on projects realize that in the long run it is beneficial to work toward mutually satisfying solutions. Still, occasionally you encounter someone who has a dominant win/lose attitude about life and will be difficult to deal with. Fisher and Ury recommend that you use negotiation jujitsu when dealing with such a person. That is, when the other person begins to push, don’t push back. As in the martial arts, avoid pitting your strengths against another’s directly; instead use your skill to step aside and turn that person’s strength to your ends. When someone adamantly sets forth a posi- tion, neither reject it nor accept it. Treat it as a possible option and then look for the interests behind it. Instead of defending your ideas, invite criticism and advice. Ask why it’s a bad idea and discover the other’s underlying interest. Those who use negotiation jujitsu rely on two primary weapons. They ask questions instead of making statements. Questions allow for interests to surface and do not pro- vide the opponent with something to attack. The second weapon is silence. If the other person makes an unreasonable proposal or attacks you personally, just sit there and don’t say a word. Wait for the other party to break the stalemate by answering your question or coming up with a new suggestion. The best defense against unreasonable, win/lose negotiators is having what Fisher and Ury call a strong BATNA (best alternative to a negotiated agreement). They point out that people try to reach an agreement to produce something better than the result of not negotiating with that person. What those results would be is the true benchmark for determining whether you should accept an agreement. A strong BATNA gives you the power to walk away and say, “No deal unless we work toward a win/win scenario.” Your BATNA reflects how dependent you are on the other party. If you are negoti- ating price and delivery dates and can choose from a number of reputable suppliers, then you have a strong BATNA. If on the other hand there is only one vendor who can supply you with specific, critical material on time, then you have a weak BATNA.

Chapter 12 Outsourcing: Managing Interorganizational Relations 439

Under these circumstances you may be forced to concede to the vendor’s demands. At the same time, you should begin to explore ways of increasing your BATNA for future negotiations. This can be done by reducing your dependency on that supplier. Begin to find substitutable material or negotiate better lead times with other vendors. Negotiating is an art. There are many intangibles involved. This section has reviewed some time-tested principles of effective negotiating based on the ground- breaking work of Fisher and Ury. Given the significance of negotiating, you are encouraged to read their book as well as others on negotiating. In addition, attending training workshops can provide an opportunity to practice these skills. You should also take advantage of day-to-day interactions to sharpen negotiating acumen.

12.5 A Note on Managing Customer Relations In Chapter 4 it was emphasized that ultimate success is not determined by whether the project was completed on time, within budget, or according to specifications, but whether the customer is satisfied with what has been accomplished. Customer satisfac- tion is the bottom line. Bad news travels faster and farther than good news. For every happy customer who shares his satisfaction regarding a particular product or service with another person, a dissatisfied customer is likely to share her dissatisfaction with eight other people. Project managers need to cultivate positive working relations with clients to preserve their reputations. Customer satisfaction is a complex phenomenon. One simple but useful way of viewing customer satisfaction is in terms of met expectations. According to this model, customer satisfaction is a function of the extent to which perceived perfor- mance (or outcome) exceeds expectations. Mathematically, this relationship can be represented as the ratio between perceived performance and expected performance (see Figure 12.7). When performance falls short of expectations (ratio < 1), the cus- tomer is dissatisfied. If the performance matches expectations (ratio = 1), the customer is satisfied. If the performance exceeds expectations (ratio > 1), the customer is very satisfied or even delighted. High customer satisfaction is the goal of most projects. However, profitability is another major concern. Exceeding expectations typically entails additional costs. For example, completing a construction project two weeks ahead of schedule may involve significant overtime expenses. Similarly, exceeding reliability requirements for a new electronic component may involve considerably more design and debug- ging effort. Under most circumstances, the most profitable arrangement occurs when the customer’s expectations are only slightly exceeded. Returning to the mathemati- cal model, with all other things being equal, one should strive for a satisfaction ratio of 1.05, not 1.5! The met-expectations model of customer satisfaction highlights the point that whether a client is dissatisfied or delighted with a project is not based on hard facts and objective data but on perceptions and expectations. For example, a customer may be dissatisfied with a project that was completed ahead of schedule and under budget

Describe the met- expectations model of customer satisfaction and its implications for working with customers on projects.

12-5LO

FIGURE 12.7 The Met-Expectations Model of Customer Satisfaction

0.90 Dissatisfied =

Perceived performance Expected performance =

1.10 Very satisfied

440 Chapter 12 Outsourcing: Managing Interorganizational Relations

if he thought the work was poor quality and that his fears and concerns were not ade- quately addressed. Conversely, a customer may be very satisfied with a project that was over budget and behind schedule if she felt the project team protected her interests and did the best job possible under adverse circumstances. Project managers must be skilled at managing customer expectations and percep- tions. Too often they deal with these expectations after the fact when they try to alleviate a client’s dissatisfaction by carefully explaining why the project cost more or took longer than planned. A more proactive approach is to begin to shape the proper expectations up front and accept that this is an ongoing process throughout the life of a project. Project managers need to direct their attention both to the cus- tomer’s base expectations, the standard by which perceived performance will be evaluated, and to the customer’s perceptions of actual performance. The ultimate goal is to educate clients so that they can make a valid judgment as to project performance. Managing customer expectations begins during the preliminary project approval phase of negotiations. It is important to avoid the temptation to oversell the virtues of a project to win approval because this may create unrealistic expectations that may be too difficult, if not impossible, to achieve. At the same time, project proponents have been known to lower customer expectations by underselling projects. If the estimated completion time is 10 to 12 weeks, they will promise to have the project completed within 12 to 14 weeks, therefore increasing the chances of exceeding customer expec- tations by getting the project completed early. Once the project is authorized, the project manager and team need to work closely with the client organization to develop a well-defined project scope statement that clearly states the objectives, parameters, and limits of the project work. The project scope statement is essential to establishing customer expectations regarding the proj- ect. It is critical that all parties are in agreement as to what is to be accomplished and that people are reading as best they can from the same page. It is also important to share significant risks that might disrupt project execution. Customers do not like sur- prises, and if they are aware in advance of potential problems they are much more likely to be accepting of the consequences. Once the project is initiated it is important to keep customers abreast of project progress. The days when you would simply take orders from customers and tell them to return when the project is done are over. More and more organizations and their project managers are treating their customers as de facto members of the project team and are actively involving them in key aspects of project work. In the case of consult- ing assignments project managers sometimes morph into a member of the client orga- nization (see Research Highlight 12.1: IT Project Managers). Project managers need to keep customers informed of project developments so that customers can make adjustments in their own plans. When circumstances dictate changing the scope or priorities of the project, project managers need to be quick to spell out as best they can the implications of these changes to the customers so that they can make an informed choice. Active customer involvement allows customers to naturally adjust their expectations in accordance with the decisions and events that transpire on a project, while at the same time, the customer’s presence keeps the proj- ect team focused on the customer’s objectives for the project. Active customer involvement also provides a firmer basis for assessing project per- formance. The customer not only sees the results of the project but also acquires glimpses of the effort and actions that produced those results. Naturally project man- agers want to make sure these glimpses reflect favorably on their project teams, so they

441

Webber and Torti studied the multi- ple roles project managers play on IT projects. Based on a comprehen- sive set of interviews with project managers and clients in three dif-

ferent information-technology service organizations, they identified five key roles critical to successfully implement IT projects in client orga- nizations: entrepreneur, politician, friend, marketer, and coach. They are described in part in Table 12.3. Webber and Torti observed that instead of main- taining a clearly defined relationship with the client, project managers become part of the client

organization. They report that project managers attempt to “dress like the client, act like the client, and participate in the client organization’s activities (i.e., social gatherings, blood drives, etc.).” They become such an integral part of their existence that many cli- ent employees, over the course of time, forget that the project manager is not an employee of the client organization. This helps establish a degree of trust essential to effective collaboration.

Research Highlight 12.1 IT Project Managers Doubling as Client Account Executives*

* S. S. Webber, and M. T. Torti, “Project Managers Doubling as Client Account Executives,” Academy of Management Executive, vol. 18, no. 1 (2004), pp. 60–71.

TABLE 12.3 Project Roles, Challenges, and Strategies

Project Manager Roles Challenges Strategies

Entrepreneur Navigate unfamiliar surroundings Use persuasion to influence others Politician Understand two diverse cultures Align with the powerful individuals (parent and client organization) Friend Determine the important relationships Identify common interests and to build and sustain outside the experiences to bridge a team itself friendship with the client Marketer Understand the strategic objectives Align new ideas/proposals with of the client organization the strategic objectives of the client organization Coach Motivate client team members Provide challenging tasks to build without formal authority the skills of the team members

exercise extra care that customer interactions are handled in a competent and profes- sional manner. In some respects, customer perceptions of performance are shaped more by how well the project team deals with adversity than by actual performance. Project managers can impress customers with how diligently they deal with unex- pected problems and setbacks. Likewise, industry analysts have noted that customer dissatisfaction can be transformed into customer satisfaction by quickly correcting mistakes and being extremely responsive to customer concerns. Managing customer relations on a project is a broad topic; we have only highlighted some of the central issues involved. This brief segment concludes with two words of advice passed on by veteran project managers: Speak with one voice. Nothing erodes confidence in a project more than for a cus-

tomer to receive conflicting messages from different project members. The project manager should remind team members of this fact and work with them to ensure that appropriate information is shared with customers.

Speak the language of the customer. Too often project members respond to cus- tomer inquiries with technical jargon that exceeds the customer’s vocabulary. Proj- ect managers and members need to describe problems, trade-offs, and solutions in ways that the customer can understand.

442 Chapter 12 Outsourcing: Managing Interorganizational Relations

Outsourcing has become an integral part of project management. More and more com- panies are collaborating with each other on projects to compete in today’s business world. The advantages of outsourcing include cost reduction, quicker completion times, greater flexibility, and higher level of expertise. Disadvantages include coordi- nation problems, loss of control, conflicts, security issues and political fallout. A number of proactive best practices have emerged among firms that have mas- tered the outsourcing process. These practices include establishing well-defined requirements and procedures and utilizing fair and incentive-laden contracts. Team- building sessions are held before the project begins to forge relationships between personnel from different organizations. Escalation guidelines for resolving conflicts are established, as are provisions for process improvement and risk sharing. On highly critical work, arrangements are made so that key personnel work together, face to face. Joint assessments of how well people are collaborating is the norm dur- ing status report briefings. Finally, many companies are realizing the benefits of forming long-term alliances with each other on projects. The ultimate goal is to work together as partners. Effective negotiating skills are essential to working on projects as partners. People need to resolve differences at the lowest level possible in order to keep the project on track. Veteran project managers realize that negotiating is not a competi- tive game and work toward collaborative solutions to problems. They accomplish this by separating people from the problem, focusing on interests and not positions, inventing options for mutual gain, and relying on objective criteria whenever pos- sible to resolve disagreements. They also recognize the importance of developing a strong BATNA, which provides them with the leverage necessary to seek col- laborative solutions. Customer satisfaction is the litmus test for project success. Project managers need to take a proactive approach to managing customer expectations and perceptions. They need to actively involve customers in key decisions and keep them abreast of important developments. Active customer involvement keeps the project team focused on the objectives of the project and reduces misunderstandings and dissatisfaction.

Summary

Key Terms Best alternative to a negotiated agreement (BATNA), 438

Escalation, 429 Met-expectations, 439 Outsourcing, 420

Partnering charter, 429 Principled negotiation, 435

1. Why do firms outsource project work? 2. What are the best practices used by firms to outsource project work? 3. What does the term “escalate” refer to, and why is it essential to project success? 4. Why is the principled negotiation approach recommended for negotiating agree-

ments on projects? 5. What does the acronym BATNA refer to, and why is it important to being a suc-

cessful negotiator? 6. How can a project manager influence customer expectations and perceptions?

Review Questions

Chapter 12 Outsourcing: Managing Interorganizational Relations 443

1. Break into groups of four to five students. Assign half of the groups the role of Owner and the other half the role of Contractor.

Owners: After saving for many years you are about to hire a contractor to build your “dream home.” What are your objectives for this project? What concerns or issues do you have about working with a general contractor to build your home?

Contractors: You specialize in building customized homes. You are about to meet with prospective owners to begin to negotiate a contract for building their “dream home.” What are your objectives for this project? What concerns or issues do you have about working with the owners to build their home?

Each Owner group meets with another Contractor group and shares their objec- tives, concerns, and issues.

Identify what objectives, issues, and concerns you have in common and which ones are unique. Discuss how you could work together to realize your objectives. What would be the keys to working as partners on this project?

2. Enter “outsourcing” in an Internet search engine and browse different websites. Who appears to be interested in outsourcing? What are the advantages of outsourc- ing? What are the disadvantages? Does outsourcing mean the same thing to differ- ent people? What are future trends in outsourcing?

3. Break into four groups and review the instructions for “Get the most you can” exer- cise provided by your teacher. Complete the exercise. What was your initial strat- egy? Did it change? If so, why? What does this exercise tell you about our ability to collaborate with each other?

Exercises

References Covey, S. R., The Seven Habits of Highly Effective People (New York: Simon and Schuster, 1990). Cowan, C., C. F. Gray, and E. W. Larson, “Project Partnering,” Project Management Journal, vol. 12, no. 4 (December 1992), pp. 5–15. DiDonato, L. S., “Contract Disputes: Alternatives for Dispute Resolution (Part 1),” PM Network, May 1993, pp. 19–23. Drexler, J. A., and E. W. Larson, “Partnering: Why Project Owner-Contractor Relationships Change,” Journal of Construction Engineering and Management,  vol. 126, no. 4 (July/August 2000), pp. 293–397. Dyer, S., Partner Your Project (Warwickshire, UK: Pendulum Pub., 1997). Economy, P., Business Negotiating Basics (Burr Ridge, IL: Irwin Professional Publishing, 1994). Fisher, R., and W. Ury, Getting to Yes: Negotiating Agreement without Giving In, 2nd ed. (New York: Penguin Books, 1991). Hedberg, B., G. Dahlgren, J. Hansson, and N. Olve, Virtual Organizations and Beyond (New York: Wiley, 1997). Hoang, H., and F. T. Rothaermel, “The Effect of General and Partner-Specific Alliance Experience on Joint R&D Project Performance,” Academy of Management Journal, vol. 48, no. 2 (2005), pp. 332–345. Kanter, R. M., “Collaborative Advantage: The Art of Alliances,” Harvard Business Review, July–August 1994, pp. 92–113.

444 Chapter 12 Outsourcing: Managing Interorganizational Relations

Kezsbom, D. S., D. L. Schilling, and K. A. Edward, Dynamic Project Management (New York: Wiley, 1989). Larson, E. W., “Partnering on Construction Projects: A Study of the Relationship between Partnering Activities and Project Success,” IEEE Transactions in Engineering Management, vol. 44, no. 2 (May 1997), pp. 188–195. Larson, E. W., “Project Partnering: Results of a Study of 280 Construction Projects,” Journal of Management Engineering, vol. 11, no. 2 (March/April 1995), pp. 30–35. Larson, E. W., and J. A. Drexler, “Barriers to Project Partnering: Report from the Firing Line,” Project Management Journal, vol. 28, no. 1 (March 1997), pp. 46–52. Magenau, J. M., and J. K. Pinto, “Power, Influence, and Negotiation in Project Man- agement,” in The Wiley Guide to Managing Projects, P. W. G. Morris and J. K. Pinto, eds. (New York: Wiley, 2004), pp. 1033–60. Maurer, I., “How to Build Trust in Inter-organizational Projects: The Impact of Proj- ect Staffing and Project Rewards on the Formation of Trust, Knowledge Acquisition, and Product Innovation,” International Journal of Project Management, vol. 28, no. 7 (2010), pp. 629–37. Nambisan, S., “Designing Virtual Customer Environments for New Product Develop- ment: Toward a Theory,” Academy of Management Review, vol. 27, no. 3 (2002), pp. 392–413. Nissen, M. E., “Procurement: Process Overview and Emerging Project Management Techniques,” in The Wiley Guide to Managing Projects, P. W. G. Morris and J. K. Pinto, eds. (New York: Wiley, 2004), pp. 643–54. Quinn, R. E., S. R. Faerman, M. P. Thompson, and M. R. McGrath, Becoming a Master Manager: A Competency Framework (New York: Wiley, 1990). Schultzel, H. J., and V. P. Unruh, Successful Partnering: Fundamentals for Project Owners and Contractors (New York: Wiley, 1996). Shell, G. R., Bargaining for Advantage: Negotiation Strategies for Reasonable People (New York: Penguin, 2000).

Case 12.1

Shell Case Fabricators

BACKGROUND Shell Case Fabricators (SCF) designs and builds shell casings that enclose electronic products such as calculators, cell phones, modems. Typically the cases are plastic or plastic compounds. SCF has six different production lines that cover different types of product. For example, the largest high-volume production line for modems can pro- duce three different colors and two models (vertical and flat). Air Connection Links (ACL) is the biggest customer that buys product from this line. This high-output line

Chapter 12 Outsourcing: Managing Interorganizational Relations 445

now runs at full capacity on an eight-hour shift. The other five lines run smaller quan- tities and tend to meet the needs of other specialty products manufactured by different smaller firms. Ninety-five percent of SCF’s product casings line is designed by the original hard- ware manufacturer. Getting a casing to the production stage requires a great deal of collaboration and interaction between the original hardware and case design manufac- turer (e.g., ACL) and SCF’s shell design engineers and production department. The latest new product of ACL is a modem designed to be used for monitoring water activ- ity in bays, e.g., ship traffic, pollution, floating debris. Because of the product’s high functionality and low cost, potential demand for the new product is out of sight. It seems every country with small bays used for shipping wants enough underwater modems to cover their respective bays.

THE UNDERWATER MODEM PROJECT At SCF each new product is assigned a project manager to coordinate and manage the shell design, budgets, and manufacturing startup. Songsee is SCF’s star project man- ager and is the project manager of the shell for the new short-range, underwater acous- tical modem. The shell casing for the underwater modem required special design, materials, custom equipment, and a seal to withstand pressure to 50 meters. Air Connection Links, the product owner, needs sixty thousand modems in 91 days (next January 15) for the Estuary Control Institute meeting in Hong Kong.

CLIENT CHANGE REQUEST Songsee has felt the project was moving along smoothly, with the exception of being two weeks behind schedule. She feels she can “lean on” the design depart- ment to put the project on top priority and make up the two weeks. Yesterday, ACL’s project manager, Sabin, came in with a “simple change.” Change the outer shell shape from rectangular to dome shape; it will improve performance 2 per- cent. Songsee couldn’t believe Sabin. He knows better. He knows the engineering implications, and it is NOT simple! Yet Sabin tells Songsee, “It shouldn’t cost much.” Songsee imagined a sharp retort, but she counted to five and aborted. At this late stage of the game, changes and schedule compression cost big money! Songsee said she would get together with her team and start on a new time and cost estimate today. She told Sabin he would have to give her a written change request of the new requirements by tomorrow. Sabin appeared disappointed. “Why don’t we just add €100,000 to the price and get on with it? We have been doing business with SCF for six years. With expected demand out of sight, SCF will break even quickly and have a great profit on the production side.” Songsee sighed. “Let’s proceed with the change order process. I will bring your request to the change order governance committee.” Songsee’s meeting with her team about the change went about as expected. Every department moaned about changing at this late date. The guesstimate cost and time estimates were over triple Sabin’s idea of €100,000. For example, design- ing a new seal for a dome style modem will require a new custom water sealing approach, possibly an untested different sealant, and new molds. Has ACL frozen the design of the new style modem? Songsee asked the team to come in with a more detailed estimate by tomorrow afternoon, before her meeting with the change order governance committee.

446 Chapter 12 Outsourcing: Managing Interorganizational Relations

THE NEXT DAY (FRIDAY) Sabin called from ACL at midmorning the next day. “Our senior management is upset that we have to be so formal for such a small change. They just want to get on with the project and meet the time to market launch date. €100,000 seems like a fair price. They believe you need to talk to your management. They want a response by Monday.” The team estimates came close to yesterday’s guesstimate (€391,000). Not good news. Songsee knew the answer of the change committee would be to hold for the full amount. She was right. The change committee believed the costs are there and need to be covered to meet the launch date. The committee was also concerned that priorities and resource scheduling would have to change for SCF’s design and production depart- ments. In three hours she would meet with senior management to decide to accept the client’s request at their price or come up with an alternate plan. Songsee realized she should have several options for senior management to consider, along with a recommendation.

1. Should SCF accept or reject ACL’s request? Which option would you select? What risks are involved?

2. How should SCF negotiate with ACL? How can SCF and ACL develop a positive, long-range relationship? Give some specifics.

Case 12.2

The Accounting Software Installation Project Sitting in her office, Karin Chung is reviewing the past four months of the large corpo- rate accounting software installation project she has been managing. Everything seemed so well planned before the project started. Each company division had a task force that provided input into the proposed installation along with potential problems. All the different divisions had been trained and briefed on exactly how their division would interface and use the forthcoming accounting software. All six contractors, which included one of the Big Four consulting companies, assisted in developing the work breakdown structure—costs, specifications, time. Karin hired a consultant to conduct a one-day “partnering” workshop attended by the major accounting heads, a member of each task force group, and key representa- tives from each of the contractors. During the workshop, several different team- building exercises were used to illustrate the importance of collaboration and effective communication. Everyone laughed when Karin fell into an imaginary acid pit during a human bridge-building exercise. The workshop ended on an upbeat note with everyone signing a partnering charter that expressed their commitment to work- ing together as partners to complete the project.

TWO MONTHS LATER One task force member came to Karin to complain that the contractor dealing with billing would not listen to his concerns about problems that could occur in the Virginia division when billings are consolidated. The contractor had told him, the task force member, he had bigger problems than consolidation of billing in the Virginia division. Karin replied, “You can settle the problem with the contractor. Go to him and explain

Chapter 12 Outsourcing: Managing Interorganizational Relations 447

how serious your problem is and that it will have to be settled before the project is completed.” Later in the week in the lunchroom she overheard one consulting contractor bad- mouthing the work of another—“never on time, interface coding not tested.” In the hallway the same day an accounting department supervisor told her that tests showed the new software will never be compatible with the Georgia division’s accounting practices. While concerned, Karin considered these problems typical of the kind she had encountered on other smaller software projects.

FOUR MONTHS LATER The project seemed to be falling apart. What happened to the positive attitude fostered at the team-building workshop? One contractor wrote a formal letter complaining that another contractor was sitting on a coding decision that was delaying their work. The letter went on: “We cannot be held responsible or liable for delays caused by others.” The project was already two months behind, so problems were becoming very real and serious. Karin finally decided to call a meeting of all parties to the project and partnering agreement. She began by asking for problems people were encountering while working on the project. Although participants were reluctant to be first for fear of being perceived as a complainer, it was not long before accusations and tempers flared out of control. It was always some group complaining about another group. Several participants complained that others were sitting on decisions that resulted in their work being held up. One consultant said, “It is impossible to tell who’s in charge of what.” Another participant complained that although the group met separately on small problems, it never met as a total group to assess new risk situations that developed. Karin felt the meeting had degenerated into an unrecoverable situation. Commitment to the project and partnering appeared to be waning. She quickly decided to stop the meeting and cool things down. She spoke to the project stakeholders: “It is clear that we have some serious problems, and the project is in jeopardy. The project must get back on track, and the backbiting must stop. I want each of us to come to a meeting Friday morn- ing with concrete suggestions of what it will take to get the project back on track and specific actions of how we can make it happen. We need to recognize our mutual inter- dependence and bring our relationships with each other back to a win/win environment. When we do get things back on track, we need to figure out how to stay on track.” 1. Why does this attempt at project partnering appear to be failing? 2. If you were Karin, what would you do to get this project back on track? 3. What action would you take to keep the project on track?

Case 12.3

Buxton Hall Chad Cromwell, head of university housing, gazed up at the tower at Buxton Hall and smiled as he walked toward the landmark building. Buxton Hall was built in 1927 as a residential complex for over 350 students at Pacifica State University. At the time Buxton was the tallest building on campus, and

448 Chapter 12 Outsourcing: Managing Interorganizational Relations

its tower had a panoramic view of the athletic fields and coastal range. Buxton quickly became a focal point at Pacifica State. Students perched on the tower dominated the campus during the annual spring water fight with their huge slingshots and catapults. The first intranet on the Pacific coast was created at Buxton that linked students’ com- puters and allowed them to share printers. Around the 1970s, some student artists began the tradition of painting their room doors. Whether a Rolling Stones logo or Bugs Bunny on a skateboard, these colorful doors were an artistic legacy that caught the attention of students and faculty. Buxton Hall served as a residence hall for the university for many years, but time was not kind to the stately building. Leaks destroyed plaster in the interior. Wiring and plumbing became outdated and so dangerous that the building was deemed unsafe. Buxton Hall’s doors were closed to students and windows boarded up at the end of the 1996 spring quarter. For 10 years Buxton sat silent and over time became a symbol of the general decline of Pacifica State. Now thanks to state bonds and generous contributions, Buxton Hall was about to be reopened after a $20 million renovation.

18 MONTHS AGO Chad and key representatives from university facilities were engaged in the second of a two-day partnering workshop. Also in attendance were managers from Craw- ford Construction, the chief contractor for the Buxton renovation project, as well as several key subcontractors and architects from the firm of Legacy West. During the first day a consultant ran them through a series of team-building and communica- tion exercises that accentuated the importance of open communication, principle negotiation, and win/win thinking. The second day began with the “project from hell” exercise, with each group describing the worst project they had ever worked on. Chad was surprised that the people from Crawford and Legacy West descrip- tions were very similar to his own. For example, each group talked about how frus- trating it was when changes were made without proper consultation or costs were hidden until it was too late to do anything about them. This was followed by a dis- cussion of the best project they had ever worked on. The consultant then asked the groups which of the two they wanted the Buxton project to be. A genuine sense of common purpose emerged, and everyone became actively engaged in spelling out in specific terms how they wanted to work together. The session concluded with all of the participants signing a partnering charter followed by a picnic and a friendly softball game.

12 MONTHS AGO Chad was on his way, with Nick Bolas, to meet Dat Nguyen, the Crawford Project Manager, on the third floor at Buxton tower. Dat had contacted him to discuss a prob- lem with the tile work in one of the communal bathrooms. Dat’s people had completed the work, but Nick, who was a Pacifica facilities manager, refused to sign off on it claiming that it was not up to spec. After a 24-hour impasse, the Crawford foreman exercised the escalation clause in partnering agreement and passed the issue up to management’s level to be resolved. Dat and Chad inspected the work. While both agreed that the job could have been prettier, it did meet specification and Chad told Nick to sign off on it. Chad met Dat again later in the day at the weekly Buxton status report meeting. The meeting kicked off with a brief review of what had been accomplished during the past week.

Chapter 12 Outsourcing: Managing Interorganizational Relations 449

Discussion centered on the removal of elm trees. Alternative strategies for dealing with the city inspector, who had a reputation of being a stickler for details, were con- sidered. The project was two weeks behind schedule, which was an important issue since it was imperative that the building be ready for students to move in at the 2008 fall term. The project was also on a very tight budget, and the management reserve had to be carefully administered. Renovation of existing buildings was always a bit of a gamble, since you never knew what you would find once you began tearing down walls. Fortunately, only small amounts of asbestos were found, but rot was much more severe than anticipated. The meeting included a partnering assessment. The results of a Web survey filled out by all the principals were distributed. The results revealed a dip in the ratings between the Crawford foremen and university officials regarding timely collaboration and effective problem solving. One of Chad’s people said that the primary source of frustration was Crawford foremen failing to respond to e-mail and telephone messages. Dat asked for the names of his people and said he would talk to each of them. The Crawford foremen complained that the university officials were being too nit-picky. “We don’t have the time or money to do A+ work on everything,” argued a foreman. Chad told Dat and his people that he would talk to the facilities guys and ask them to focus on what was really important.

6 MONTHS AGO The project status report meeting started on time. Crawford had been able to make up for lost time, and it now looked like the building would open on time. Chad was glad to see that the partnering assessment had been positive and steady over the past month. The big issue was the surge in costs consuming all but $50,000 of management reserve. With six months to go everyone knew that this would not cover all the change orders needed to have the building ready. After all, there was already $24,000 worth of change orders pending. Chad looked across the table and saw nothing but grim faces. Then one of the Crawford foremen proposed postponing treating all of the exterior walls. “Instead of cleaning and preserving the entire brick building, let’s only do the front entrance and the North and South walls that the public sees. We can just refurbish the interior court walls as well as the West side. This would be adequate for at least eight years, in which time money should be available to complete the job.” At first Chad didn’t like this idea, but eventually he realized that this was the only way they could have the building ready for the students. Friendly arguments broke out over which exterior segments needed the full treatment and which ones didn’t. The whole team ended up touring the outside of the building identifying what kind of work needed to be done. In the end, only 70 percent of exterior brick walls were recondi- tioned according to plan with a savings of over $250,000. While this boost to the reserve would still make things tight, everyone felt that they now had a fighting chance to complete the project on time.

TODAY As Chad mingled with a glass of champagne, no one talked about the walls that still needed to be refurbished—tonight was a night to celebrate. All of the major partici- pants and their spouses were at the party, and the university was hosting a five- course meal at the top of the tower. During the toasts, jokes were exchanged and

450 Chapter 12 Outsourcing: Managing Interorganizational Relations

stories told about the ghosts in the west wing and the discovery of a dead skunk in the south basement. Everyone talked about how proud they felt about bringing back to life the grand old building. More than one person mentioned that this was much more satisfying than tearing down an old relic and constructing a new building. The president of the university concluded the festivities by thanking everyone for their hard work and proclaiming that Buxton would become a bright, shining icon for Pacifica State. 1. How successful was this project? 2. What best practices were evident in the case? How did they contribute to project

objectives?

Case 12.4

Goldrush Electronics Negotiation Exercise

OBJECTIVE The purpose of this case is to provide you with an opportunity to practice negotiations.

PROCEDURE

STEP 1 The class is divided into four groups, each comprising the project management group for one of four projects at Goldrush Electronics.

STEP 2 Read the Goldrush Electronics “Background Information” section given below. Then read the instructions for the project you represent. Soon you will meet with the man- agement of the other projects to exchange personnel. Plan how you want to conduct those meetings.

BACKGROUND INFORMATION Goldrush Electronics (GE) produces a range of electronic products. GE has a strong commitment to project management. GE operates as a projectized organization with each project organized as a fully dedicated team. The compensation system is based on a 40 + 30 + 30 formula. Forty percent is based on your base salary, 30 percent on your project performance, and 30 percent on overall performance of the firm. Four new product development projects have been authorized. They are code named: Alpha, Beta, Theta, and Zeta. The preliminary assignment of personnel is listed below. You are assigned to represent the management of one of these projects. The policy at GE is that once preliminary assignments are made, project man- agers are free to exchange personnel as long as both parties agree to the transac- tion. You will have the opportunity to adjust your team by negotiating with other project managers.

Chapter 12 Outsourcing: Managing Interorganizational Relations 451

Alpha Project

Software Engineer Hardware Engineer Design Engineer Jill Cameron Mitch John Chandra Marsha

Beta Project

Software Engineer Hardware Engineer Design Engineer Jake Casey Mike Jennifer Craig Maria

Theta Project

Software Engineer Hardware Engineer Design Engineer Jack Chuck Monika Johan Cheryl Mark

Zeta Project

Software Engineer Hardware Engineer Design Engineer Jeff Carlos Max Juwoo Chad Maile

Personnel may be traded for one or more other personnel.

STEP 3 Meet and negotiate with the other project managers.

STEP 4 Individual project scores are totaled and posted.

STEP 5

DISCUSSION QUESTIONS 1. What was your initial strategy before starting the actual negotiations? How did you

view the other groups? 2. Did your initial strategy change once negotiations began? If so, how and why? 3. What could top management at GE have done to make it easier to reach agreement

with the other groups?

Appendix 12.1

Contract Management

LEARNING OBJECTIVES After reading this appendix you should be able to:

LO A12-1 Describe the procurement management process. LO A12-2 Describe the differences between Fixed-Price and Cost-Plus Contracts and their advantages and

disadvantages.

452 Chapter 12 Outsourcing: Managing Interorganizational Relations

Since most outsourced work on projects is contractual in nature, this appendix discusses the different kinds of contracts that are used, their strengths and weaknesses, and how contracts shape the motives and expectations of different participants. Contract manage- ment is a key element of any project procurement management system. It is beyond the scope of this book to describe this system. However, the basic processes are listed here to put contract management and related topics like Request for Proposal (RFP) (see Appendix 12.1) in perspective. Six main steps comprise procurement management: ∙ Planning purchases and acquisitions involves determining what to procure, when,

and how. This entails the classic build-versus-buy analysis as well as determination of the type of contract to use.

∙ Planning contracting involves describing the requirements for products or services desired from outsourcing and identifying potential suppliers or sellers. Outputs include procurement documents such as a RFP as well as selection criteria.

∙ Requesting seller responses involves obtaining information, quotes, bids, or pro- posals from sellers and providers. The main outputs of this process include a quali- fied sellers list and specific proposals.

∙ Selecting sellers involves choosing from potential suppliers through a process of evaluating potential providers and negotiating a contract.

∙ Administering the contract involves managing the relationship with the selected seller or provider.

∙ Closing the contract involves completion and settlement of the contract. Most companies have purchasing departments that specialize in procurement. Often purchasing agents will be assigned to project teams and they work with other team members to come up with optimum solutions for the project. Even if project teams are not directly involved in contract negotiations and the decision to outsource project work, it is important that the team understand the procurement process and the nature of different kinds of contracts.

CONTRACTS A contract is a formal agreement between two parties wherein one party (the contrac- tor) obligates itself to perform a service and the other party (the client) obligates itself to do something in return, usually in the form of a payment to the contractor. For example, an insurance firm contracted with a consulting firm to reprogram segments of their information system to conform to Windows 10. A contract is more than just an agreement between parties. A contract is a codification of the private law, which governs the relationship between the parties to it. It defines the responsibilities, spells out the conditions of its operations, defines the rights of the par- ties in relationship to each other, and grants remedies to a party if the other party breaches its obligations. A contract attempts to spell out in specific terms the transactional obliga- tions of the parties involved as well as contingencies associated with the execution of the contract. An ambiguous or inconsistent contract is difficult to understand and enforce. There are essentially two different kinds of contracts. The first is the “fixed-price” con- tract in which a price is agreed upon in advance and remains fixed as long as there are no changes to scope or provisions of the agreement. The second is a “cost-plus” contract in which the contractor is reimbursed for all or some of the expenses incurred during the per- formance of the contract. Unlike the fixed-price contract, the final price is not known until the project is completed. Within these two types of contracts, several variations exist.

Describe the procurement management process.

A12-1LO

Describe the differences between Fixed-Price and Cost-Plus Contracts and their advantages and disadvantages.

A12-2LO

Chapter 12 Outsourcing: Managing Interorganizational Relations 453

FIXED-PRICE CONTRACTS Under a fixed-price (FP) or lump-sum agreement, the contractor agrees to perform all work specified in the contract at a fixed price. Clients are able to get a minimum price by putting out the contract to competitive bid. Advertising an invitation for bid (IFB) that lists customer requirements usually results in low bids. Prospective contractors can obtain IFB notices through various channels. In the case of large business organi- zations and government agencies, potential contractors can request to be included on the bidder’s list in the area of interest. In other cases, IFBs can be found by scanning appropriate industry media such as newspapers, trade journals, and websites. In many cases, the owner can put restrictions on potential bidders, such as requiring that they be ISO 9000 certified. With fixed-price contract bids, the contractor has to be very careful in estimating target cost and completion schedule because once agreed upon, the price cannot be adjusted. If contractors overestimate the target cost in the bidding stage, they may lose the contract to a lower-priced competitor; if the estimate is too low, they may win the job but make little or no profit. Fixed-price contracts are preferred by both owners and contractors when the scope of the project is well defined with predictable costs and low implementation risks. Such might be the case for producing parts or components to specifications, executing training programs, or orchestrating a banquet. With fixed-price contracts, clients do not have to be concerned with project costs and can focus on monitoring work progress and performance specifications. Likewise, contractors prefer fixed-price contracts because the client is less likely to request changes or additions to the contract. Fewer potential changes reduce project uncertainty and allow the contractors to more effi- ciently manage their resources across multiple projects. The disadvantage of a fixed-price contract for owners is that it is more difficult and more costly to prepare. To be effective, design specifications need to be spelled out in sufficient detail to leave little doubt as to what is to be achieved. Because the contrac- tor’s profit is determined by the difference between the bid and the actual costs, there is some incentive for contractors to use cheaper quality materials, perform marginal workmanship, or extend the completion date to reduce costs. The client can counteract these by stipulating rigid end-item specifications and completion date and by supervis- ing work. In many cases, the client will hire a consultant who is an expert in the field to oversee the contractor’s work and protect the client’s interest. The primary disadvantage of a fixed-price contract for contractors is that they run the risk of underestimating. If the project gets into serious trouble, cost overruns may make the project unprofitable, and, in some cases, may lead to bankruptcy. To avoid this, contractors have to invest significant time and money to ensure that their esti- mates are accurate. Contracts with long lead times such as construction and production projects may include escalation provisions that protect the contractor against external cost increases in materials, labor rates, or overhead expenses. For example, the price may be tied to an inflation index, so it can be adjusted to sudden increases in labor and material prices, or it may be redetermined as costs become known. A variety of redetermination contracts are used. Some establish a ceiling price for a contract and permit only downward adjust- ments, others permit upward and downward adjustments; some establish one readjust- ment period at the end of the project, others use more than one period. Redetermination contracts are appropriate where engineering and design efforts are difficult to estimate or when final price cannot be estimated for lack of accurate cost data.

454 Chapter 12 Outsourcing: Managing Interorganizational Relations

While, in principle, redetermination contracts are used to make appropriate adjust- ments in cost uncertainties, they are prone to abuse. A contractor may win an initial low bid contract, initiate the contracted work, and then “discover” that the costs are much higher than expected. The contractor can take advantage of redetermination pro- visions and a client’s ignorance to justify increasing the actual cost of the contract. The contract evolves into a cost-plus contract. To alleviate some of the disadvantages of a fixed-price contract while maintaining some certainty as to final cost, many fixed-price contracts contain incentive clauses designed to motivate contractors to reduce costs and improve efficiency. For example, a contractor negotiates to perform the work for a target price based on a target cost and a target profit. A maximum price and maximum profit are also established. If the total cost ends up being less than the target cost, the contractor makes a higher profit up to the profit maximum. If there is a cost overrun, the contractor absorbs some of the over- run until a profit floor is reached. Profit is determined according to a formula based on a cost-sharing ratio (CSR). A CSR of 75/25, for example, indicates that for every dollar spent above target costs, the client pays 75 cents and the contractor pays 25 cents. This provision motivates contractors to keep costs low since they pay 25 cents on every dollar spent above the expected cost and earn 25 cents more on every dollar saved below the expected cost. Fixed-price incentive contracts tend to be used for long-duration projects with fairly predictable cost estimates. The key is being able to negotiate a reasonable target cost estimate. Unscrupulous contractors have been known to take advantage of the igno- rance of the client to negotiate an unrealistically high target cost and use performance incentives to achieve excessive profits.

COST-PLUS CONTRACTS Under a cost-plus contract the contractor is reimbursed for all direct allowable costs (materials, labor, travel) plus an additional fee to cover overhead and profit. This fee is negotiated in advance and usually involves a percentage of the total costs. On small projects this kind of contract comes under the rubric “time and materials con- tract” in which the client agrees to reimburse the contractor for labor cost and mate- rials. Labor costs are based on an hourly or daily rate, which includes direct and indirect costs as well as profit. The contractor is responsible for documenting labor and materials costs. Unlike fixed-price contracts, cost-plus contracts put the burden of risk on the client. The contract does not indicate what the project is going to cost until the end of the project. Contractors are supposed to make the best effort to fulfill the spe- cific technical requirements of the contract but cannot be held liable, in spite of their best efforts, if the work is not produced within the estimated cost and time frame. These contracts are often criticized because there is little formal incentive for the contractors to control costs or finish on time because they get paid regard- less of the final cost. The major factor motivating contractors to control costs and schedule is the effect overruns have on their reputation and their ability to secure future business. The inherent weakness of cost-plus contracts has been compensated for by a variety of incentive clauses directed at providing incentives to contractors to control costs, maintain performance, and avoid schedule overruns. Contractors are reimbursed for costs, but instead of the fee being fixed, it is based on an incentive formula and subject

Chapter 12 Outsourcing: Managing Interorganizational Relations 455

to additional provisions. This is very similar to fixed-price incentive contracts, but instead of being based on a target cost, the fee is based on actual cost, using a cost- sharing formula. Most contracts are concerned with the negotiated cost of the project. However, given the importance of speed and timing in today’s business world, more and more contracts involve clauses concerning completion dates. To some extent schedule incentives provide some cost-control measures because schedule slippage typically but not always involves cost overruns. Schedule incentives/penalties are stipulated depending on the significance of time to completion for the owner. For example, the contract involving the construction of a new baseball stadium is likely to contain stiff penalties if the stadium is not ready for opening day of the season. Conversely, time-constrained projects in which the number one priority is getting the project completed as soon as possible are likely to include attractive incentives for complet- ing the project early. A good example of this can be seen in Snapshot from Practice 9.2: Responding to the Northridge Earthquake in which the construction firm pulled out all the stops to restore the damaged highway system 74 days ahead of schedule. The firm received a $14.8 million bonus for these efforts! Figure A12.1 summarizes the spectrum of risk to the buyer and supplier for differ- ent kinds of contracts. Buyers have the lowest risk with firm fixed-price contracts because they know exactly what they will need to pay the supplier. Buyers have the most risk with cost-plus percentage of cost contracts because they do not know in advance what the suppliers’ costs will be and suppliers may be motivated to increase costs. From the suppliers’ perspective, the cost-plus contract offers the least risk and the firm fixed-price contract entails the most risk.

CONTRACT CHANGE CONTROL SYSTEM A contract change control system defines the process by which the contract may be modified. It includes the paperwork, tracking systems, dispute resolution proce- dures, and approval levels necessary for authorizing changes. There are a number of reasons a contract may need to be changed. Clients may wish to alter the origi- nal design or scope of the project once the project is initiated. This is quite

High

High

Low

Low

CPPC Cost-plus percentage

of cost

CPIF Cost-plus incentive

fee

FFP Firm fixed-price

FPI Fixed-price incentive

BUYER RISK

SELLER RISK

FIGURE A12.1 Contract Type versus Risk

456 Chapter 12 Outsourcing: Managing Interorganizational Relations

common as the project moves from concept to reality. For example, an owner may wish to add windows after inspecting the partially completed homesite. Market changes may dictate adding new features or increasing the performance require- ments of equipment. Declining financial resources may dictate that the owner cut back on the scope of the project. The contractor may initiate changes in the con- tract in response to unforeseen legitimate problems. A building contractor may need to renegotiate the contract in the face of excessive groundwater or the lack of availability of specified materials. In some cases, external forces may dictate con- tract changes, such as a need to comply with new safety standards mandated by the federal government. There need to be formal, agreed-upon procedures for initiating changes in the original contract. Contract change orders are subject to abuse. Contractors some- times take advantage of owners’ ignorance to inflate the costs of changes to recoup profit lost from a low bid. Conversely, owners have been known to “get back” at contractors by delaying approval of contract changes, thus delaying project work and increasing the costs to the contractor. All parties need to agree upon the rules and procedures for initiating and making changes in the original terms of the con- tract in advance.

CONTRACT MANAGEMENT IN PERSPECTIVE Contract management is not an exact science. For decades, the federal govern- ment has been trying to develop a more effective contract administration system. Despite their best efforts, abuses are repeatedly exposed in the news media. The situation is similar to trying to take a wrinkle out of an Oriental rug. Efforts to eliminate a wrinkle in one part of the rug invariably create a wrinkle in another part. Likewise, each new revision in government procurement procedures appears to generate a new loophole that can be exploited. There is no perfect contract management system. Given the inherent uncertainty involved in most project work, no contract can handle all the issues that emerge. Formal contracts cannot replace or eliminate the need to develop effective working relationships between the parties involved that are based on mutual goals, trust, and cooperation. For this reason, the earlier discussion of best practices in outsourcing and effective negotiating is very important.

APPENDIX REVIEW QUESTIONS 1. What are the fundamental differences between fixed-price and cost-plus

contracts? 2. For what kinds of projects would you recommend that a fixed-price contract be

used? For what kinds of projects would you recommend that a cost-plus contract be used?

APPENDIX REFERENCES Angus, R. B., N. A. Gundersen, and T. P. Cullinane, Planning, Performing, and Con- trolling Projects (Upper Saddle River, NJ: Prentice Hall, 2003). Cavendish, J., and M. Martin, Negotiating and Contracting for Project Management (Upper Darby, PA: Project Management Institute, 1982).

Chapter 12 Outsourcing: Managing Interorganizational Relations 457

Fleming, Q. W., Project Procurement Management: Contracting, Subcontracting, Teaming (Tustin, CA: FMC Press, 2003). Fraser, J., Professional Project Proposals (Aldershot, U.K.: Gower/Ashgate, 1995). Lowe, D., “Contract Management” in The Wiley Guide to Managing Projects, P. W. G. Morris and J. K. Pinto, eds. (New York: Wiley, 2004), pp. 678–707. Schwalbe, K., Information Technology Project Management, 4th ed. (Boston: Thomson Course Technology, 2006). Worthington, M. M., and L. P. Goldsman, Contracting with the Federal Government, 4th ed. (New York: Wiley, 1998).

Progress and Performance Measurement and Evaluation13

LEARNING OBJECTIVES After reading this chapter you should be able to:

13-1 Identify the four steps for controlling a project.

13-2 Utilize a tracking Gantt to monitor time performance.

13-3 Understand and appreciate the significance of earned value.

13-4 Calculate and interpret cost and schedule variance.

13-5 Calculate and interpret performance and percent indexes.

13-6 Forecast final project cost.

13-7 Identify and manage scope creep.

OUTLINE 13.1 Structure of a Project Monitoring Information

System

13.2 The Project Control Process

13.3 Monitoring Time Performance

13.4 Development of an Earned Value Cost/Schedule System

13.5 Developing a Status Report: A Hypothetical Example

13.6 Indexes to Monitor Progress

13.7 Forecasting Final Project Cost

13.8 Other Control Issues

Summary

Appendix 13.1: The Application of Additional Earned Value Rules

Appendix 13.2: Obtaining Project Performance Information from MS Project

C H A P T E R T H I R T E E N

458

How does a project get one year late? . . . One day at a time. —Frederick P. Brooks, The Mythical Man Month, p. 153

Evaluation and control are part of every project manager’s job. Control by “wander- ing around” and “involvement” can overcome most problems in small projects. But large projects need some form of formal control. Control holds people accountable, prevents small problems from mushrooming into large problems, and keeps focus. Except for accounting controls, project control is not performed well in most organi- zations. Control is one of the most neglected areas of project management. Unfortunately, it is not uncommon to find resistance to control processes. In essence, those who minimize the importance of control are passing up a great opportunity to be effective managers and, perhaps, allow the organization to gain a competitive edge. Neglecting control in organizations with multiple projects is even more serious. For effective control, the project manager needs a single information system to collect data and report progress on cost, schedule, and specifications. The general structure of such a system is discussed next.

Project networks

6

Managing risk 7

Monitoring progress

13

Teams 11

Outsourcing 12

Project manager

10

Strategy 2

Introduction 1

Organization 3

Schedule resources & costs

8

Intern ation

al

proje cts

15

Agile PM 16

Project closure

14

Estimate 5

Reducing duration

9

Define project

4

459

460 Chapter 13 Progress and Performance Measurement and Evaluation

13.1 Structure of a Project Monitoring Information System A project monitoring system involves determining what data to collect; how, when, and who will collect the data; analysis of the data; and reporting current progress.

What Data Are Collected? Data collected are determined by which metrics will be used for project control. Typical key data collected are actual activity duration times, resource usage and rates, and actual costs, which are compared against planned times, resources, and budgets. Since a major portion of the monitoring system focuses on cost/schedule concerns, it is crucial to provide the project manager and stakeholders with data to answer questions such as:

∙ What is the current status of the project in terms of schedule and cost? ∙ How much will it cost to complete the project? ∙ When will the project be completed? ∙ Are there potential problems that need to be addressed now? ∙ What, who, and where are the causes for cost or schedule overruns? ∙ If there is a cost overrun midway in the project, can we forecast the overrun at

completion?

The performance metrics you need to collect should support answering these ques- tions. Examples of specific metrics and tools for collecting data will be discussed in detail later in this chapter.

Collecting Data and Analysis With the determination of what data are collected, the next step is to establish who, when, and how the data will be assembled. Will the data be collected by the project team, contractor, independent cost engineers, project manager? Or will the data be derived electronically from some form of surrogate data such as cash flow, machine hours, labor hours, or materials in place? Should the reporting period be one hour, one day, one week, or what? Is there a central repository for the data collected and is some- one responsible for its dissemination? Electronic means of collecting data have vastly improved data assembly, analysis, and dissemination. Numerous software vendors have programs and tools to analyze your customized collected data and present it in a form that facilitates monitoring the project, identifying sources of problems, and updating your plan.

Reports and Reporting    First, who gets the progress reports? We have already suggested that different stake- holders and levels of management need different kinds of project information. Senior management’s major interests are usually, “Are we on time and within budget? If not, what corrective action is taking place?” Likewise, an IT manager working on the proj- ect is concerned primarily about her deliverable and specific work packages. The reports should be designed for the right audience.

Chapter 13 Progress and Performance Measurement and Evaluation 461

Typically, project progress reports are designed and communicated in written or oral form. A common topic format for progress reports follows: ∙ Progress since last report ∙ Current status of project 1. Schedule 2. Cost 3. Scope ∙ Cumulative trends ∙ Problems and issues since last report 1. Actions and resolution of earlier problems 2. New variances and problems identified ∙ Corrective action planned Given the structure of your information system and the nature of its outputs, we can use the system to interface and facilitate the project control process. These interfaces need to be relevant and seamless if control is to be effective.

13.2 The Project Control Process Control is the process of comparing actual performance against plan to identify devia- tions, evaluate possible alternative courses of actions, and take appropriate corrective action. The project control steps for measuring and evaluating project performance are presented below. 1. Setting a baseline plan. 2. Measuring progress and performance. 3. Comparing plan against actual. 4. Taking action. Each of the control steps is described in the following paragraphs.

Step 1: Setting a Baseline Plan The baseline plan provides us with the elements for measuring performance. The base- line is derived from the cost and duration information found in the work breakdown structure (WBS) database and time-sequence data from the network and resource scheduling decisions. From the WBS the project resource schedule is used to time- phase all work, resources, and budgets into a baseline plan. See Chapter 8.

Step 2: Measuring Progress and Performance Time and budgets are quantitative measures of performance that readily fit into the integrated information system. Qualitative measures such as meeting customer techni- cal specifications and product function are most frequently determined by on-site inspection or actual use. This chapter is limited to quantitative measures of time and budget. Measurement of time performance is relatively easy and obvious. That is, is the critical path early, on schedule, or late; is the slack of near-critical paths decreasing to cause new critical activities? Measuring performance against budget (e.g., money, units in place, labor hours) is more difficult and is not simply a case of comparing

Identify the four steps for controlling a project.

13-1LO

462 Chapter 13 Progress and Performance Measurement and Evaluation

actual versus budget. Earned value is necessary to provide a realistic estimate of per- formance against a time-phased budget. Earned value (EV) is defined as the budgeted cost of the work performed.

Step 3: Comparing Plan against Actual Because plans seldom materialize as expected, it becomes imperative to measure devi- ations from plan to determine if action is necessary. Periodic monitoring and measur- ing the status of the project allow for comparisons of actual versus expected plans. It is crucial that the timing of status reports be frequent enough to allow for early detection of variations from plan and early correction of causes. Usually status reports should take place every one to four weeks to be useful and allow for proactive correction.

Step 4: Taking Action If deviations from plans are significant, corrective action will be needed to bring the project back in line with the original or revised plan. In some cases, conditions or scope can change, which, in turn, will require a change in the baseline plan to recog- nize new information. The remainder of this chapter describes and illustrates monitoring systems, tools, and components to support managing and controlling projects. Several of the tools you developed in the planning and scheduling chapters now serve as input to your informa- tion system for monitoring performance. Monitoring time performance is discussed first, followed by cost performance.

13.3 Monitoring Time Performance A major goal of progress reporting is to catch any negative variances from plan as early as possible to determine if corrective action is necessary. Fortunately, monitoring schedule performance is relatively easy. The project network schedule, derived from the WBS/OBS, serves as the baseline to compare against actual performance. Gantt charts (bar charts), control charts, and milestone schedules are the typical tools used for communicating project schedule status. As suggested in Chapter 6, the Gantt chart is the most favored, used, and understandable. This kind of chart is com- monly referred to as a tracking Gantt chart. Adding actual and revised time estimates to the Gantt chart gives a quick overview of project status on the report date.

Tracking Gantt Chart Figure 13.1 presents a baseline Gantt chart and a tracking Gantt chart for a project at the end of period 6. The solid bar below the original schedule bar represents the actual start and finish times for completed activities or any portion of an activity completed (see activities A, B, C, D, and E). For example, the actual start time for activity C is period 2; the actual finish time is period 5; the actual duration is three time units, rather than four scheduled time periods. Activities in process show the actual start time; the extended bar represents the expected remaining duration (see activities D and E). The remaining duration for activities D and E are shown with the hatched bar. Activity F, which has not started, shows a revised estimated actual start (9) and finish time (13). Note how activities can have durations that differ from the original schedule, as in activities C, D, and E. Either the activity is complete and the actual is known, or new information suggests the estimate of time be revised and reflected in the status report.

Utilize a tracking Gantt to monitor time performance.

13-2LO

Chapter 13 Progress and Performance Measurement and Evaluation 463

Activity D’s revised duration results in an expected delay in the start of activity F. The project is now estimated to be completed one period later than planned. Although sometimes the Gantt chart does not show dependencies, when it is used with a net- work, the dependencies are easily identified if tracing is needed.

Control Chart This chart is another tool used to monitor past project schedule performance and cur- rent performance and to estimate future schedule trends. Figure 13.2 depicts a project control chart. The chart is used to plot the difference between the scheduled time on the critical path at the report date with the actual point on the critical path. Although Figure 13.2 shows the project was behind early in the project, the plot suggests correc- tive action brought the project back on track. If the trend is sustained, the project will come in ahead of schedule. Because the activity scheduled times represent average durations, four observations trending in one direction indicate there is a very high probability that there is an identifiable cause. The cause should be located and action taken if necessary. Control chart trends are very useful for giving warning of potential problems so appropriate action can be taken if necessary.

Milestone Schedules Milestone schedules are often used to keep more distal stakeholders informed on the progress of a project. Such stakeholders, whether it is senior management, the owner, or regulatory agencies often neither need or desire a detailed accounting of project progress. Instead, their interests can be satisfied by reporting progress towards major project milestones. Remember from Chapter 4, milestones are significant project

Legend

Baseline duration

Actual completed

Slack

A

Tracking Gantt Chart Showing Status—through Period 6

Baseline Gantt Chart

Today

Remaining duration

F

E

D

C

B

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14

A

F

E

D

C

B

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14

FIGURE 13.1 Baseline and Tracking Gantt Charts

464 Chapter 13 Progress and Performance Measurement and Evaluation

events that mark major accomplishments. Below is the milestone schedule used to keep the president of a university and her cabinet informed on the construction of a new College of Business building. ∙ Programming: June–August 31, 2014 ∙ Schematic Design: September–January 15, 2012 ∙ Design Development: January–August 31, 2012 ∙ Historic Review: June–October 31, 2012 ∙ Construction Documents: Sept. 2012–January 15, 2013 ∙ 1% For Art Selection: November 2012–May 31, 2013 ∙ Bid and Permit: January–March 31, 2013 ∙ Construction: April 2013–August 31, 2014 ∙ Furnishing Selections: September–November 30, 2013 ∙ Occupancy: September 7, 2014 Project managers recognize the need to use a more macro schedule of significant deliv- erables to keep external stakeholders informed and a more detailed milestone driven schedule to manage and motivate the project team to achieve those deliverables. For more on the latter, see the Snapshot from Practice 13.1 Guidelines for Setting Milestones.

13.4 Development of an Earned Value Cost/Schedule System Earned value is not new; the original earned value cost/schedule system was pioneered by the U.S. Department of Defense (DoD) in the 1960s. It is probably safe to say proj- ect managers in every major country are using some form of the system. The system is being used on internal projects in the manufacturing, pharmaceutical, and high-tech industries. For example, organizations such as EDS, NCR, Levi Strauss, Tektronics, and Disney have used earned value systems to track projects. The basic framework of the earned value system is withstanding the test of time. Most project management

Understand and appreci- ate the significance of earned value.

13-3LO

FIGURE 13.2 Project Schedule Control Chart

Time periods

0 1 2 3 4 5 6 Reporting period

7 8 9 10 11 12 13

20

15

10

5

0

–5

–10

–15

–20

Today

Ahead of schedule

Behind schedule

Schedule outlook

Chapter 13 Progress and Performance Measurement and Evaluation 465

software includes the original framework; many systems have added industry-specific variations to more precisely track progress and costs. This chapter presents the “generic” core of an integrated cost/schedule information system.1 The earned value system starts with the time-phased costs that provide the project budget baseline, which is called the planned budgeted value of the work scheduled (PV). Given this time-phased baseline, comparisons are made with actual and planned schedule and costs using earned value. The earned value approach provides the miss- ing links not found in conventional cost-budget systems. At any point in time, a status report can be developed for the project. The earned value cost/schedule system uses several acronyms and equations for analysis. Table 13.1 presents a glossary of these acronyms. You will need this glossary as a reference. In recent years acronyms have been shortened to be more phonetically friendly. This movement is reflected in material from the Project Management Insti- tute, in project management software, and by most practitioners. This text edition fol- lows the recent trend. The acronyms found in brackets represent the older acronyms, which are often found in software programs. To the uninitiated, the terms used in practice appear horrendous and intimidating. However, once a few basic terms are understood, the intimidation index will evaporate.

In medieval times mounds of stones were used to mark distance traveled along a path or road. Travelers would use these rock formations to gauge their progress and adjust their plans. In mod-

ern times, milestones are distinct events along the project timeline that are used to gauge progress and adjust plans. Milestones are building blocks for the project’s schedule and often create positive momentum to propel the project along to completion. To be effective milestones need to be concrete, specific, measurable events. Here are some guidelines for setting milestones gleaned from conversations with veteran project managers:

Avoid the temptation to overuse milestones as a motivational tool by labeling every task a mile- stone. Only important deliverables or achievements should be used as milestones.

Timing of milestones is important. Milestones that are placed too far apart will not generate momentum. Conversely, milestones placed too close together quickly lose their distinctiveness. As a rule of thumb, space milestones at intervals no longer than every two weeks for projects of several months in duration.

Critical merge and burst activities are often useful milestones since they indicate significant work has

been or is about to be accomplished. Here it is im- portant to remember that milestones are events not tasks, and the start of a merge activity (i.e., pat- ent application submitted) or the completion of a burst activity (i.e., building permit approved) should be used.

Rates of completion can be used on projects involv- ing repetition and not sequential advancement. For example, on a training project, milestones could be set as percentages of employees fully trained and certified, e.g., 25%, 50%, 75%, and 100%.

Completing a high anxiety, high risk task is always worthy of milestone consideration.

S N A P S H O T F R O M P R A C T I C E 1 3 . 1 Guidelines for Setting Milestones

© Erik Larson

1 See Fleming and Koppelman (2010) for a more complete earned value description.

466 Chapter 13 Progress and Performance Measurement and Evaluation

Following five careful steps ensures that the cost/schedule system is integrated. These steps are outlined here. Steps 1, 2, and 3 are accomplished in the planning stage. Steps 4 and 5 are sequentially accomplished during the execution stage of the project. 1. Define the work using a WBS. This step involves developing documents that

include the following information (see Chapters 4 and 5): a. Scope. b. Work packages. c. Deliverables. d. Organization units. e. Resources. f. Budgets for each work package.

2. Develop work and resource schedule. a. Schedule resources to activities (see Chapter 8). b. Time-phase work packages into a network.

3. Develop a time-phase budget using work packages included in an activity. The cumulative values of these budgets will become the baseline and will be called the planned budgeted cost of the work scheduled (PV). The sum should equal the bud- geted amounts for all the work packages in the cost accounts (see Chapter 8).

4. At the work package level, collect the actual costs for the work performed. These costs will be called the actual cost of the work completed (AC). Collect percent complete and multiply this times the original budget amount for the value of the work actually completed. These values will be called earned value (EV).

5. Compute the schedule variance (SV = EV − PV) and cost variance (CV = EV − AC). Prepare hierarchical status reports for each level of management—from work package manager to customer or project manager. The reports should also include project rollups by organization unit and deliverables. In addition, actual time perfor- mance should be checked against the project network schedule.

Figure 13.3 presents a schematic overview of the integrated information system, which includes the techniques and systems presented in earlier chapters. Those who have tenaciously labored through the early chapters can smile! Steps 1 and 2 are

TABLE 13.1 Glossary of Terms EV Earned value for a task is simply the percent complete times its original budget. Stated differently, EV is the percent of the original budget that has been earned by actual work

completed. [The older acronym for this value was BCWP—budgeted cost of the work performed.] PV The planned time-phased baseline of the value of the work scheduled. An approved cost

estimate of the resources scheduled in a time-phased cumulative baseline [BCWS—budgeted cost of the work scheduled].

AC Actual cost of the work completed. The sum of the costs incurred in accomplishing work [ACWP—actual cost of the work performed].

CV Cost variance is the difference between the earned value and the actual costs for the work completed to date where CV = EV − AC.

SV Schedule variance is the difference between the earned value and the baseline line to date where SV = EV − PV.

BAC Budgeted cost at completion. The total budgeted cost of the baseline or project cost accounts. EAC Estimated cost at completion. ETC Estimated cost to complete remaining work. VAC Cost variance at completion. VAC indicates expected actual over- or underrun cost at completion.

Chapter 13 Progress and Performance Measurement and Evaluation 467

already carefully developed. Observe that control data can be traced backward to spe- cific deliverables and organization unit responsible. The major reasons for creating a baseline are to monitor and report progress and to estimate cash flow. Therefore, it is crucial to integrate the baseline with the perfor- mance measurement system. Costs are placed (time-phased) in the baseline exactly as managers expect them to be “earned.” This approach facilitates tracking costs to their point of origin. In practice, the integration is accomplished by using the same rules in assigning costs to the baseline as those used to measure progress using earned value. You may find several rules in practice, but percent complete is the workhorse most commonly used. Someone familiar with each task estimates what percent of the task has been completed or how much of the task remains.

Percent Complete Rule This rule is the heart of any earned value system. The best method for assigning costs to the baseline under this rule is to establish frequent checkpoints over the duration of the work package and assign completion percentages in dollar terms. For example, units completed could be used to assign baseline costs and later to measure progress. Units might be lines of code, hours, drawings completed, cubic yards of concrete in place, workdays, prototypes complete, etc. This approach to percent complete adds “objectivity” to the subjective observation approaches often used. When measuring percent complete in the monitoring phase of the project, it is com- mon to limit the amount earned to 80 or 90 percent until the work package is 100 percent complete.

What Costs Are Included in Baselines? The baseline (PV) is the sum of the cost accounts, and each cost account is the sum of the work packages in the cost account. Three direct costs are typically included in baselines—labor, equipment, and materials. The reason: these are direct costs the

Scope Deliverables

WBS

O rg

an iz

at io

n

O B

S

Database

Work packages

Time Resources Labor Materials Support effort Budgets Responsibilities Performance standards

Plan, schedule baseline

Control

Time, cost, and specifications by Deliverables and Organization

FIGURE 13.3 Project Management Information System Overview

468 Chapter 13 Progress and Performance Measurement and Evaluation

project manager can control. Overhead costs and profit are typically added later by accounting processes. Most work packages should be discrete, of short time span, and have measurable outputs. If materials and/or equipment are a significant portion of the cost of work packages, they can be budgeted in separate work packages and cost accounts.

Methods of Variance Analysis Generally the method for measuring accomplishments centers on two key computations: 1. Comparing earned value with the expected schedule value. 2. Comparing earned value with the actual costs. These comparisons can be made at the project level or down to the cost account level. Project status can be determined for the latest period, all periods to date, and estimated to the end of the project. Assessing the current status of a project using the earned value cost/schedule sys- tem requires three data elements—planned cost of the work scheduled (PV), budgeted cost of the work completed (EV), and actual cost of the work completed (AC). From these data the schedule variance (SV) and cost variance (CV) are computed each reporting period. A positive variance indicates a desirable condition, while a negative variance suggests problems or changes that have taken place. Cost variance tells us if the work accomplished costs more or less than was planned at any point over the life of the project. If labor and materials have not been separated, cost variance should be reviewed carefully to isolate the cause to either labor or materials—or to both. Schedule variance presents an overall assessment of all work packages in the proj- ect scheduled to date. It is important to note schedule variance contains no critical path information. Critical and non-critical activities are combined in the calculation. Sched- ule variance measures progress in dollars rather than time units. Therefore, it is unlikely that any translation of dollars to time will yield accurate information telling if any milestone or critical path is early, on time, or late (even if the project occurs exactly as planned). The only accurate method for determining the true time progress of the project is to compare the project network schedule against the actual network schedule to measure if the project is on time (refer to Figure 13.1). However, SV is very useful in assessing the direction all the work in the project is taking—after 20 or more per- cent of the project has been completed. Figure 13.4 presents a sample cost/schedule graph with variances identified for a proj- ect at the current status report date. Note the graph also focuses on what remains to be accomplished and any favorable or unfavorable trends. The “today” label marks the report date (time period 25) of where the project has been and where it is going. Because our system is hierarchical, graphs of the same form can be developed for different levels of management. In Figure 13.4 the top line represents the actual costs (AC) incurred for the project work to date. The middle line is the baseline (PV) and ends at the scheduled project duration (45). The bottom line is the budgeted value of the work actually com- pleted to date (EV) or the earned value. The dotted line extending the actual costs from the report date to the new estimated completion date represents revised estimates of expected actual costs; that is, additional information suggests the costs at completion of the project will differ from what was planned. Note that the project duration has been extended and the variance at completion (VAC) is negative (BAC − EAC). Another interpretation of the graph uses percentages. At the end of period 25, 75 percent of the work was scheduled to be accomplished. At the end of period 25, the

Calculate and interpret cost and schedule variance.

13-4LO

Chapter 13 Progress and Performance Measurement and Evaluation 469

value of the work accomplished is 50 percent. The actual cost of the work completed to date is $340, or 85 percent of the total project budget. The graph suggests the proj- ect will have about an 18 percent cost overrun and be five time units late. The current status of the project shows the cost variance (CV) to be over budget by $140 (EV − AC = 200 − 340 = −140). The schedule variance (SV) is negative $100 (EV − PV = 200 − 300 = −100), which suggests the project is behind schedule. Before moving to an example, consult Figure 13.5 to practice interpreting the outcomes of cost/schedule graphs. Remember, PV is your baseline and anchor point.

10 20 30

Today Scheduled end

Project duration

40 50

125%

100%

85%

75%

50%

25%

$500

AC actual cost

PV baseline

EV earned value

BAC

EAC

CV

SV

$400

$340

$300

$200

$100

FIGURE 13.4 Cost/Schedule Graph

$

Time

AC PV

EV

SV = negative

CV = negative

$

Time

AC

PV

EV SV = positive

CV = positive

$

Time

AC

PV

EV

SV = positive

CV = negative

$

Time

AC

PV

EV

SV = negative

CV = positive

FIGURE 13.5 Earned-Value Review Exercise

470 Chapter 13 Progress and Performance Measurement and Evaluation

13.5 Developing a Status Report: A Hypothetical Example Working through an example demonstrates how the baseline serves as the anchor from which the project can be monitored using earned value techniques.

Assumptions Because the process becomes geometrically complex with the addition of project detail, some simplifying assumptions are made in the example to more easily demon- strate the process: 1. Assume each cost account has only one work package, and each cost account will

be represented as an activity on the network. 2. The project network early start times will serve as the basis for assigning the base-

line values. 3. From the moment work on an activity task begins, some actual costs will be

incurred each period until the activity is completed.

Baseline Development Figure 13.6 (Work Breakdown Structure with Cost Accounts) depicts a simple work breakdown structure (WBS/OBS) for the Digital Camera example. There are six deliv- erables (Design Specifications, Shell & Power, Memory/Software, Zoom System, Assemble, and Test), and five responsible departments (Design, Shell, Storage, Zoom, and Assembly). The total for all the cost accounts (CA) is $320,000, which represents

$3 20

Digital Camera Prototype: Design/Build Project

$320 (000)

Design Specifications

$20

Shell & Power

$15

Memory/ Software

$100

Zoom System

$35

Assemble $120

Test $30

Zoom $35

Shell $15

Storage $100O

B S

Design $20

Assembly $150

CA 1–1

$20

CA 2–2

$15

CA 3–3

$100

CA 4–4

$35

CA 5–5

$120

CA 6–5

$30

FIGURE 13.6 Work Breakdown Structure with Cost Accounts

Chapter 13 Progress and Performance Measurement and Evaluation 471

the total project cost. Figure 13.7, derived from the WBS, presents a planning Gantt chart for the Digital Camera project. The planned project duration is 11 time units. This project information is used to time-phase the project budget baseline. Figure 13.8 (Project Baseline Budget) presents a worksheet with an early start baseline developed with costs assigned. They are assigned “exactly” as managers plan to monitor and measure schedule and cost performance.

Development of the Status Report A status report is analogous to a camera snapshot of a project at a specific point in time. The status report uses earned value to measure schedule and cost performance. Measuring earned value begins at the work package level. Work packages are in one of three conditions on a report date: 1. Not yet started. 2. Finished. 3. In-process or partially complete. Earned values for the first two conditions present no difficulties. Work packages that are not yet started earn zero percent of the PV (budget). Packages that are com- pleted earn 100 percent of their PV. In-process packages apply the percent complete rule to the PV baseline to measure earned value (EV). In our camera example we will only use the percent complete rule to measure progress. Table 13.2 presents the completed, separate status reports of the Digital Camera Prototype project for periods 1 through 7. Each period percent complete and actual

Legend

Baseline duration

Slack

A

F

E

D

C

B

Design Spec's

Test

Assemble

Zoom System

Memory/Software

Shell & Power

0 1 2 3 4 5 6 7 8 9 10 11FIGURE 13.7 Digital Camera Prototype Project Baseline Gantt Chart

ES LF SL Time period

Baseline budget needsSchedule information

Total PV 1 2 3 4 5 6 7 8 9 10

ACT/ WP DUR

0 0A 2

2 2B 2

2 0C 4

2 1D 3

6 0E 3

9

2

6

6

6

9

11 0

20

15

100

35

120

30F 2

10

Total PV by period

Cumulative PV by period 20 60 110 150 170 200 240 290 300 320

10 10 40 50 40 20 30 40 50 10 20

10 10

5 10

20 30 30 20

15 10 10

30 40 50

10 20

0 11

FIGURE 13.8 Digital Camera Prototype Project Baseline Budget ($000)

472 Chapter 13 Progress and Performance Measurement and Evaluation

TABLE 13.2 Digital Camera Prototype Status Reports: Periods 1–7

Cost Variance CV = EV − AC Schedule Variance SV = EV − PV Status Report: Ending Period 1 Task %Complete EV AC PV CV SV

A 50%   10   10   10     0     0 Cumulative Totals   10   10   10     0     0

Status Report: Ending Period 2 Task %Complete EV AC PV CV SV

A Finished   20   30   20 −10     0 Cumulative Totals   20  30   20 −10     0

Status Report: Ending Period 3 Task %Complete EV AC PV CV SV

A Finished   20   30   20 −10     0 B 33%     5   10     5   −5     0 C 20%   20   30   20 −10     0 D 60%   21   20   15   +1   +6 Cumulative Totals   66  90   60 −24   +6

Status Report: Ending Period 4 Task %Complete EV AC PV CV SV

A Finished   20   30   20 −10     0 B Finished   15   20   15   −5     0 C 50%   50   70   50 −20     0 D 80%   28   30   25   −2   +3 Comulative Totals 113 150 110 −37   +3

Status Report: Ending Period 5 Task %Complete EV AC PV CV SV

A Finished   20   30   20 −10     0 B Finished   15   20   15   −5     0 C 60%   60 100   80 −40 −20 D 80%   28   50   35 −22   −7 Cumulative Totals 123 200 150 −77 −27

Status Report: Ending Period 6 Task %Complete EV AC PV CV SV

A Finished   20   30   20 −10     0 B Finished   15   20   15   −5     0 C 80%   80 110 100 −30 −20 D Finished   35   60   35 −25     0 Cumulative Totals 150 220 170 −70 −20

Status Report: Ending Period 7 Task %Complete EV AC PV CV SV

A Finished   20   30   20 −10     0 B Finished   15   20   15   −5     0 C 90%   90 120 100 −30 −10 D Finished   35   60   35 −25     0 E 0%    0     0   30     0 −30 F 0%    0     0     0     0     0 Cumulative Totals 160 230 200 −70 −40

Chapter 13 Progress and Performance Measurement and Evaluation 473

cost were gathered for each task from staff in the field. The schedule and cost variance are computed for each task and the project to date. For example, the status in period 1 shows only Task A (Design Specifications) is in process and it is 50 percent complete and actual cost for the task is 10. The planned value at the end of period 1 for Task A is 10 (see Figure 13.8). The cost and schedule variance are both zero, which indicates the project is on budget and schedule. By the end of period 3, Task A is finished. Task B (Shell & Power) is 33 percent complete and AC is 10; Task C is 20 percent complete and AC is 30; and D is 60 percent complete and AC is 20. Again, from Figure 13.8 at the end of period 3, we can see that the PV for Task A is 20 (10 + 10 = 20), for Task B is 5, for Task C is 20, and for Task D is 15. At the end of period 3 it is becoming clear the actual cost (AC) is exceeding the value of the work completed (EV). The cost variance (see Table 13.2) for the project at the end of period 3 is negative 24. Schedule variance is positive 6, which suggests the project may be ahead of schedule. It is important to note that since earned values are computed from costs (or some- times labor hours or other metrics), the relationship of costs to time is not one-for-one. For example, it is possible to have a negative SV variance when the project is actually ahead on the critical path. This would occur when delays in noncritical activities out- weigh progress on the critical path. Therefore, it is important to remember, SV is in dollars and is not an accurate measure of time; however, it is a fairly good indicator of the status of the whole project in terms of being ahead or behind schedule after the project is over 20 percent complete. Only the project network, or tracking Gantt chart, and actual work completed can give an accurate assessment of schedule performance down to the work package level. By studying the separate status reports for periods 5 through 7, you can see the project will be over budget and behind schedule. By period 7 Tasks A, B, and D are finished, but all are over budget—negative 10, 5, and 25. Task C (Memory/Software) is 90 percent complete. Task E is late and hasn’t started because Task C is not yet com- pleted. The result is that, at the end of period 7, the digital camera project is over bud- get $70,000, with a schedule budget over $40,000. Figure 13.9 shows the graphed results of all the status reports through period 7. This graph represents the data from Table 13.2. The cumulative actual costs (AC) to

40

360

320

280

240

200

160

120

80

10 0

2 3 4 5 6 7 8 9 10 11 12

PV

EV

AC

Today

SV = −40

CV = −70

Time periods

D ol

la rs

FIGURE 13.9 Digital Camera Prototype Summary Graph ($000)

474 Chapter 13 Progress and Performance Measurement and Evaluation

date and the earned value budgeted costs to date (EV) are plotted against the original project baseline (PV). The cumulative AC to date is $230; the cumulative EV to date is $160. Given these cumulative values, the cost variance (CV = EV − AC) is negative $70 (160 − 230 = −70). The schedule variance (SV = EV − PV) is negative $40 (160 − 200 = −40). Again, recall that only the project network or tracking Gantt chart can give an accurate assessment of schedule performance down to the work package level. A tracking Gantt bar chart for the Digital Camera Prototype is shown in Figure 13.10. From this figure you can see Task C (Memory/Software), which had an original duration of 4 time units, now is expected to require 6 time units. This delay of 2 time units for Task C will also delay Tasks E and F two time units and result in the project being late 2 time periods. Figure 13.11 shows an oversimplified project rollup at the end of period 7. The rol- lup is by deliverables and organization units. For example, the Memory/Software deliverable has an SV of $ −10 and a CV of −30. The responsible “Storage” depart- ment should have an explanation for these variances. Similarly, the assembly depart- ment, which is responsible for the Assemble and Test deliverables, has an SV of $ −30 due to the delay of Task C (see Figure 13.10). Most deliverables look unfavorable on schedule and cost variance. In more complex projects, the crosstabs of cost accounts by deliverables and orga- nization units can be very revealing and more profound. This example contains the basics for developing a status report, baseline development, and measuring schedule and cost variance. In our example, performance analysis had only one level above the cost account level. Because all data are derived from the detailed database, it is rela- tively easy to determine progress status at all levels of the work and organization breakdown structures. Fortunately, this same current database can provide additional views of the current status of the project and forecast costs at the completion of the project. Approaches for deriving additional information from the database are pre- sented next. To the uninitiated, a caveat is in order. In practice budgets may not be expressed in total dollars for an activity. Frequently, budgets are time-phased for materials and labor separately for more effective control over costs. Another common approach used in practice is to use labor hours in place of dollars in the earned value system. Later,

A

F

E

D

C

B

Design Spec's

Test

Assemble

Zoom System

Memory/Software

Shell & Power

0 1 2 3 4 5 6 7 8 9 10 14131211

Today

Legend

Baseline duration

Actual completed

Slack Remaining duration

FIGURE 13.10 Digital Camera Project-Tracking Gantt Chart Showing Status—Through Period 7

Chapter 13 Progress and Performance Measurement and Evaluation 475

labor hours are converted to dollars. The use of labor hours in the earned value system is the modus operandi for most construction work. Labor hours are easy to understand and are often the way many time and cost estimates are developed. Most earned value software easily accommodates the use of labor hours for development of cost estimates.

13.6 Indexes to Monitor Progress Practitioners sometimes prefer to use schedule and cost indexes over the absolute val- ues of SV and CV, because indexes can be considered efficiency ratios. Graphed indexes over the project life cycle can be very illuminating and useful. The trends are easily identified for deliverables and the whole project. Indexes are typically used at the cost account level and above. In practice, the data- base is also used to develop indexes that allow the project manager and customer to view progress from several angles. An index of 1.00 (100 percent) indicates progress is as planned. An index greater than 1.00 shows progress is better than expected. An

Calculate and interpret performance and percent indexes.

13-5LO

SV =

– 40

C V

= –

70

O B

S

SV = –40 CV = –70

Digital Camera Prototype: Design/Build Project

CA 1–1

SV = 20 – 20 = 0

CV = 20 – 30 = –10

CA 2–2

SV = 15 – 15 = 0

CV = 15 – 20 = –5

CA 3–3

SV = 90 – 100 = –10

CV = 90 – 120 = –30

CA 4–4

SV = 35 – 35 = 0

CV = 35 – 60 = –25

CA 5–5

SV = 0 – 30 = –30

CV = 0 – 0 = 0

CA 6–5

SV = 0 – 0 = 0

CV = 0 – 0 = 0

Design Specifications

SV = 0 CV = –10

Shell & Power SV = 0 CV = –5

Memory/ Software SV = –10 CV = –30

Zoom System

SV = 0 CV = –25

Assemble

SV = –30 CV = 0

Test

SV = 0 CV = 0

Design SV = 0 CV = –10

Assembly SV = –30 CV = 0

Zoom SV = 0 CV = –25

Storage SV = –10 CV = –30

Shell SV = 0 CV = –5

FIGURE 13.11 Project Rollup End Period 7 ($000)

476 Chapter 13 Progress and Performance Measurement and Evaluation

index less than 1.00 suggests progress is poorer than planned and deserves attention. Table 13.3 presents the interpretation of the indexes.

Performance Indexes There are two indexes of performance efficiency. The first index measures cost effi- ciency of the work accomplished to date: (Data from Table 13.2)

Cost performance index (CPI) = EV/AC = 160/230 = .696 or .70 The CPI of .696 shows that $.70 worth of work planned to date has been completed for each $1.00 actually spent—an unfavorable situation indeed. The CPI is the most accepted and used index. It has been tested over time and found to be the most accu- rate, reliable, and stable. For example, U.S. government studies have shown that the CPI is stable from the 20 percent completion point regardless of contract type, pro- gram, or service. The CPI can provide an “early warning signal” as to cost overruns so that adjustments can be made to the budget or scope of a project.2 The second index is a measure of scheduling efficiency to date:

Scheduling performance index (SPI) = EV/PV = 160/200 = .80 The schedule index indicates $.80 worth of work has been accomplished for each $1.00 worth of scheduled work to date. Figure 13.12 shows the indexes plotted for our exam- ple project through period 7. This figure is another example of graphs used in practice.

0 0 1 2 3 4 5 6 7

.10

.20

.30

.40

.50

.60

.70

.80 SPI = .80

CPI = .70

PCIB = .50

.90

1.00

1.20

1.10

Time periods

In de

x

FIGURE 13.12 Indexes Periods 1–7

2 Cited by Q. W. Fleming and J. M. Koppleman, Earned Value Project Management (Newton Square, PA: Project Manage- ment Institute, 2010), pp. 39–42.

Index Cost (CPI) Schedule (SPI) >1.00 Under cost Ahead of schedule =1.00 On cost On schedule <1.00 Over cost Behind schedule

TABLE 13.3 Interpretation of Indexes

Chapter 13 Progress and Performance Measurement and Evaluation 477

Project Percent Complete Indexes Two project percent complete indexes are used, depending on your judgment of which one is most representative of your project. The first index assumes the original budget of work complete is the most reliable information to measure project percent complete. The second index assumes the actual costs-to-date and expected cost at completion are the most reliable for measuring project percent complete. These indexes compare the to-date progress to the end of the project. The implications underlying use of these indexes are that conditions will not change, no improvement or action will be taken, and the information in the database is accurate. The first index looks at percent com- plete in terms of budget amounts:

Percent complete index budgeted costs  PCIB = EV/BAC = 160/320 = .50 (50%)

This PCIB indicates the work accomplished represents 50 percent of the total budgeted (BAC) dollars to date. Observe that this calculation does not include actual costs incurred. Because actual dollars spent do not guarantee project progress, this index is favored by many project managers when there is a high level of confidence in the original budget estimates. The second index views percent complete in terms of actual dollars spent to accom- plish the work to date and the actual expected dollars for the completed project (EAC). For example, at the end of period 7 the staff re-estimates that the EAC will be 575 instead of 320. The application of this view is written as

Percent complete index actual costs  PCIC = AC/EAC = 230/575 = .40 (40%)

Some managers favor this index because it contains actual and revised estimates that include newer, more complete information. These two views of percent complete present alternative views of the “real” percent complete. These percents may be quite different as shown above. (Note: The PCIC index was not plotted in Figure 13.12. The new figures for EAC would be derived each period by estimators in the field.) A third percent index that is popular in the construction industry reflects the amount of Management Reserve that has been absorbed by cost over-runs. Remember Man- agement Reserve are funds set aside to cover unforeseen events (see Chapter 7). Let’s assume that $40 was reserved for Digital Camera Project: Management Reserve index MRI = CV/MR = The percentage of 140/40 = 3.50 (350%!) Clearly this project is in trouble when it comes to cost and changes in either the scope and/or budget are required. Many managers assess cost overruns in terms of Manage- ment Reserve rather than simply cost variance since it reflects how much one can afford to spend on the project.

Software for Project Cost/Schedule Systems Software developers have created sophisticated schedule/cost systems for projects that track and report budget, actual, earned, committed, and index values. These values can be labor hours, materials, and/or dollars. This information supports cost and schedule progress, performance measurements, and cash flow management. Recall from Chap- ter 5 that budget, actual, and committed dollars usually run in different time frames

478 Chapter 13 Progress and Performance Measurement and Evaluation

(see Figure 5.6). A typical computer-generated status report includes the following information outputs: 1. Schedule variance (EV − PV) by cost account and WBS and OBS. 2. Cost variance (EV − AC) by cost account and WBS and OBS. 3. Indexes—total percent complete and performance index. 4. Cumulative actual total cost to date (AC). 5. Expected costs at completion (EAC). 6. Paid and unpaid commitments. The variety of software packages, with their features and constant updating, is too extensive for inclusion in this text. Software developers and vendors have done a superb job of providing software to meet the information needs of most project managers. Dif- ferences among software in the last decade have centered on improving “friendliness” and output that is clear and easy to understand. Anyone who understands the concepts and tools presented in Chapters 4, 5, 6, 8, and 13 should have little trouble understanding the output of any of the popular project management software packages. Appendix 13.2 details how to obtain earned value information from Microsoft Project software.

Additional Earned Value Rules Although the percent complete rule is the most-used method of assigning budgets to baselines and for cost control, there are additional rules that are very useful for reduc- ing the overhead costs of collecting detailed data on percent complete of individual work packages. (An additional advantage of these rules, of course, is that they remove the often subjective judgments of the contractors or estimators as to how much work has actually been completed.) The first two rules are typically used for short-duration activities and/or small-cost activities. The third rule uses gates before the total bud- geted value of an activity can be claimed. ∙ 0/100 rule. This rule assumes credit is earned for having performed the work once

it is completed. Hence, 100 percent of the budget is earned when the work package is completed. This rule is used for work packages having very short durations.

∙ 50/50 rule. This approach allows 50 percent of the value of the work package bud- get to be earned when it is started and 50 percent to be earned when the package is completed. This rule is popular for work packages of short duration and small total costs.

∙ Percent complete with weighted monitoring gates. This more recent rule uses subjective estimated percent complete in combination with hard, tangible monitor- ing points. This method works well on long-duration activities that can be broken into short, discrete work packages of no more than one or two report periods. These discrete packages limit the subjective estimated values. For example, assume a long-duration activity with a total budget of $500. The activity is cut into three sequentially discrete packages with monitoring gates representing 30, 50, and 100 percent of the total budget. The earned amount at each monitoring gate cannot exceed $150, $250, and $500. These hard monitoring points serve as a check on overly optimistic estimates.

Notice the only information needed for the first two rules is that the work package has started and the package has been completed. For those who wish to explore the application of these two rules, or who are studying for certification, Appendix 13.1 presents two exercises that apply these rules along with the percent complete rule.

Chapter 13 Progress and Performance Measurement and Evaluation 479

The third rule is frequently used to authorize progress payments to contractors. This rule supports careful tracking and control of payments; it discourages payment to con- tractors for work not yet completed.

13.7 Forecasting Final Project Cost There are basically two methods used to revise estimates of future project costs. In many cases both methods are used on specific segments of the project. The result is confusion of terms in texts, in software, and among practitioners in the field. We have chosen to note the differences between the methods. The first method allows experts in the field to change original baseline durations and costs because new information tells them the original estimates are not accurate. We have used EACre to represent revisions made by experts and practitioners associ- ated with the project. The revisions from project experts are almost always used on smaller projects. The equation for calculating revised estimated cost at completion (EACre) is as follows:

EACre = AC + ETCre where EACre = revised estimated cost at completion.

AC = cumulative actual cost of work completed to date. ETCre = revised estimated cost to complete remaining work.

A second method is used in large projects where the original budget is reliable. This method uses the actual costs to date plus an efficiency index (CPI = EV/AC) applied to the remaining project work. When the estimate for completion uses the CPI as the basis for forecasting cost at completion, we use the acronym EACf. The equation is presented here. The equation for this forecasting model (EACf) is as follows:

EACf = ETC + AC

ETC = Work remainingCPI = BAC − EV

EV/AC where EACf = forecasted total cost at completion. ETC = estimated cost to complete remaining work. AC = cumulative actual cost of work completed to date. CPI = cumulative cost index to date. BAC = total budget of the baseline. EV = cumulative budgeted cost of work completed to date.

The following information is available from our earlier example; the estimate cost at completion (EACf) is computed as follows:

Total baseline budget (BAC) for the project $320 Cumulative earned value (EV) to date $160 Cumulative actual cost (AC) to date $230

EACf = 320 − 160

160/230 + 230 = 160 .7 + 230 = 229 + 230

EACf = 459

Forecast final project cost.

13-6LO

480 Chapter 13 Progress and Performance Measurement and Evaluation

The final project projected cost forecast is $459,000 versus $320,000 originally planned. Another popular index is the To Complete Performance Index (TCPI), which is useful as a supplement to the estimate at complete (EACf) computation. This ratio mea- sures the amount of value each remaining dollar in the budget must earn to stay within the budget. The index is computed for the Digital Camera project at the end of period 7.

TCPI = BAC − EVBAC − AC = 320 − 160 320 − 230 =

160 90 = 1.78

The index of 1.78 indicates that each remaining dollar in the budget must earn $1.78 in value. There is more work to be done than there is budget left. Clearly, it would be tough to increase productivity that much to make budget. The work to be done will have to be reduced or you will have to accept running over budget. If the TCPI is less than 1.00, you should be able to complete the project without using all of the remain- ing budget. A ratio of less than 1.00 opens the possibility of other opportunities such as improving quality, increasing profit, or expanding scope. Research data indicate that on large projects that are more than 15 percent complete, the model performs well with an error of less than 10 percent (Fleming and Koppleman, 2010; Christensen, 1998). This model can also be used for WBS and OBS cost accounts that have been used to forecast remaining and total costs. It is important to note that this model assumes conditions will not change, the cost database is reliable, EV and AC are cumulative, and past project progress is representative of future progress. This objective forecast represents a good starting point or benchmark that management can use to com- pare other forecasts that include other conditions and subjective judgments. Exhibit 13.1 presents an abridged monthly status report similar to one used by a project organization. The form is used for all projects in their project portfolio. (Note that the schedule variance of −$22,176 does not translate directly to days. The 25 days were derived from the network schedule.) Another summary report is shown in the Snapshot from Practice 13.2: Trojan Decommissioning Project. Compare the differences in format.

Portland General Electric Company has been charged with decommission- ing the Trojan Nuclear Plant. This is a long and complex project extending over two decades. The first segment

of the project of moving the used reactors to a storage location is complete and was awarded the Project of the Year, 2000, by the Project Management Institute (PMI). The remainder of the project—decontamination of the remaining structures and waste—is ongoing. Exhibit 13.2 shows their earned value status report. This report measures schedule and cost performance for monitoring the project. The report also serves as a basis for funding for rate filings with the Public Utilities Commission.

S N A P S H O T F R O M P R A C T I C E 1 3 . 2 Trojan Decommissioning Project

© Don Ryan/AP Photo

Chapter 13 Progress and Performance Measurement and Evaluation 481

EXHIBIT 13.1 Monthly Status Report

Project number: 163 Project manager: Connor Gage

Project priority now: 4

Status as of: April 1

Earned value figures:

PV EV AC SV CV BAC

588,240 566,064 596,800 −22,176 −30,736 1,051,200

EAC VAC EACf CPI PCIB PCIC

1,090,640 −39,440 1,107,469 .95 .538 .547

Project description: A computer-controlled conveyor belt that will move and position items on the belt with accuracy of less than one millimeter. Status summary: The project is approximately 25 days behind schedule. The project has a cost vari- ance of ($30,736). Explanations: The schedule variance has moved from noncritical activities to those on the critical path. Integration first phase, scheduled to start 3/26, is now expected to start 4/19, which means it is approximately 25 days behind schedule. This delay is traced to the loss of the second design team which made it impossible to start utilities documentation on 2/27 as planned. This loss illustrates the effect of losing valuable resources on the project. The cost variance to date is largely due to a design change that cost $21,000. Major changes since last report: The major change was loss of one design team to the project. Total cost of approved design changes: $21,000. Most of this amount is attributed to the improved design of the serial I/O drivers. Projected cost at completion: EACf is estimated to be $1,107,469. This represents an overrun of $56,269, given a CPI of .95. The CPI of .95 causes the forecast to be greater than the VAC −$39,440. Risk watch: Nothing suggests the risk level of any segments has changed.

13.8 Other Control Issues

Technical Performance Measurement Measuring technical performance is as important as measuring schedule and cost per- formance. Although technical performance is often assumed, the opposite can be true. The ramifications of poor technical performance frequently are more profound— something works or it doesn’t if technical specifications are not adhered to. Assessing technical performance of a system, facility, or product is often accom- plished by examining the documents found in the scope statement and/or work pack- age documentation. These documents should specify criteria and tolerance limits against which performance can be measured. For example, the technical performance of a software project suffered because the feature of “drag and drop” was deleted in the final product. Conversely, the prototype of an experimental car exceeded the miles per gallon technical specification and, thus, its technical performance. Frequently tests are conducted on different performance dimensions. These tests become an integral part of the project schedule. It is very difficult to specify how to measure technical performance because it depends on the nature of the project. Suffice it to say, measuring technical perfor- mance must be done. Technical performance is frequently where quality control pro- cesses are needed and used. Project managers must be creative in finding ways to control this very important area.

Identify and manage scope creep.

13-7LO

482 Chapter 13 Progress and Performance Measurement and Evaluation

Co st

/B ud

ge t P

er fo

rm an

ce

De co

m m

is si

on in

g Cu

m ul

at iv

e Co

st s

No m

in al

Y ea

r D ol

la rs

Po rtl

an d

Ge ne

ra l E

le ct

ric C

o. -T

ro ja

n Nu

cle ar

P la

nt

Re po

rt Ru

n: 2 3-

Ja n- 01

Re

po rt

Nu m

be r:

DE CT 00

5 Pa

ge :

1 of

1

Ye ar

-to -D

at e

YT D

De sc

rip tio

n PV

EV

AC

PV

EV

AC

EV

-A C

PV

EV /A

C EV

/P V 

IS FS

I 19

3, 01

4 18

2, 57

3 16

2, 57

9 3, 65

5, 67

7 3, 58

6, 41

1 3, 26

3, 99

5 32

2, 41

6 3, 65

5, 67

7 1. 10

0. 98

RV AI

R 0

0 0

0 0

39 9

(3 99

) 0

0. 00

0. 00

Eq ui

p re

m ov

al —

AB /F

B 79

,0 83

79

,6 49

73

,8 99

49

7, 19

7 50

4, 97

5 30

8, 46

1 19

6, 51

4 49

7, 19

7 1. 64

1. 02

Eq ui

p re

m ov

al —

ot he

r 0

0 0

0 (3 6, 82

2)

51 9

(3 7, 34

1)

0 0. 00

0. 00

Em be

d pi

pi ng

— AB

/F B

3, 88

4 0

2, 11

8 53

2, 27

5 54

0, 23

2 51

5, 23

5 24

,9 97

53

2, 27

5 1. 05

1. 01

Em be

d pi

pi ng

— ot

he r

0 0

3, 43

9 17

5, 40

1 21

0, 87

5 79

,2 35

13

1, 64

0 17

5, 40

1 2. 66

1. 20

Su rfa

ce d

ec on

— AB

/F B

29 ,9 35

23

,2 74

21

,4 56

1, 26

6, 68

5 1, 29

3, 31

5 1, 17

1, 71

2 12

1, 60

3 1, 26

6, 66

5 1. 10

1. 02

Su rfa

ce d

ec on

— ot

he r

2, 87

5 2

11 ,0 05

30

8, 08

5 19

9, 85

3 25

1, 26

5 (5 1, 41

2)

30 8, 08

5 0. 80

0. 65

Su rfa

ce d

ec on

— co

nt ai

nm en

t 68

0, 50

2 43

5, 65

7 47

4, 42

7 5, 27

1, 88

9 4, 95

0, 52

8 4, 82

3, 33

8 12

7, 19

0 5, 27

1, 88

9 1. 03

0. 94

Ra dw

as te

d isp

os al

88

4, 87

3 45

3, 03

2 (2 8, 67

5)

10 ,6 80

,1 18

8, 27

6, 61

6 10

,8 07

,9 16

(2

,5 31

,3 00

) 10

,8 80

,1 18

0. 77

0. 77

Fi na

l s ur

ve y

58 ,2 38

57

,9 85

27

,0 91

78

0, 99

0 78

0, 99

0 70

0, 94

2 80

,0 48

78

0, 99

0 1. 11

1. 00

No nr

ad io

lo gi

ca l a

re as

92

,8 37

91

,9 56

58

,5 38

2, 47

1, 28

1 2, 37

6, 12

3 83

4, 64

3 1, 54

1, 48

0 2, 47

1, 28

1 2. 85

0. 96

St af

fin g

71 4, 80

6 71

4, 50

9 46

8, 85

8 9, 94

7, 77

5 9, 94

7, 77

5 8, 24

1, 38

3 1, 70

6, 39

2 9, 94

7, 77

5 1. 21

1. 00

IS FS

I— Lo

ng -te

rm o

ps

85 ,0 26

85

,0 28

19

,1 73

2, 00

4, 39

8 2, 00

4, 39

8 33

7, 20

6 1, 66

7, 19

2 2, 00

4, 39

8 5. 94

1. 00

La bo

r l oa

di ng

s 25

8, 28

9 25

8, 28

9 24

0, 22

9 3, 21

6, 19

4 3, 21

6, 19

4 2, 75

5, 60

4 46

0, 59

0 3, 21

6, 19

4 1. 17

1. 00

M at

er ia

l l oa

di ng

s 17

,9 10

17

,9 10

(9 5, 12

8)

21 1, 45

4 21

1, 45

4 13

6, 97

3 74

,4 81

21

1, 45

4 1. 54

1. 00

Co rp

or at

e go

ve rn

an ce

15

3, 68

9 22

8, 49

9 22

8, 52

1 1, 81

4, 52

3 1, 81

4, 52

3 1, 81

4, 52

0 3

1, 81

4, 52

3 1. 00

1. 00

Un di

st rib

ut ab

le c

os ts

43

1, 84

0 40

1, 72

0 24

2, 72

4 5, 54

1, 67

9 5, 57

5, 87

9 4, 00

7, 73

2 1, 56

7, 94

7 5, 54

1, 67

9 1. 39

1. 01

To ta

l d ec

om m

iss io

ni ng

3, 68

8, 48

1 3, 00

8, 08

1 1, 90

5, 08

4 48

,3 75

,3 99

45

,4 53

,1 19

40

,0 51

,0 79

5, 40

2, 04

0 48

,3 75

,3 99

1. 13

0. 94

To

ta l (

le ss

IS FS

I a nd

R VA

IR )

3, 49

3, 46

7 2, 84

5, 50

8 1, 74

3, 48

5 44

,7 19

,7 20

41

,8 86

,7 10

36

,7 88

,6 80

5, 08

0, 02

4 44

,7 19

,7 20

1. 14

0. 94

Va ria

nc e

CP

I SP

I

Th e S

PI (0

.9 4)

su gg

es ts

th e p

ro jec

t s ch

ed ul

e i s f

all in

g be

hi nd

. R es

ol vi

ng is

su es

w ith

a m

ajo r v

en do

r a nd

so lu

tio ns

fo r t

ec hn

ica l p

ro bl

em s s

ho ul

d so

lv e t

he se

d ela

y pr

ob lem

s. Th

e C PI

(1 .1

4) fo

r t he

p ro

jec t i

s p os

iti ve

. S om

e o f t

hi s

go od

co st

pe rfo

rm an

ce is

at tri

bu ted

to p

ar tn

er in

g an

d in

ce nt

iv e a

rra ng

em en

ts wi

th ve

nd or

s a nd

la bo

r u ni

on s.

In ter

vi ew

w ith

M ich

ae l B

. L ac

ke y,

ge ne

ra l m

an ag

er , T

ro jan

, P GE

.

EX HI

BI T

13 .2

Chapter 13 Progress and Performance Measurement and Evaluation 483

Scope Creep Large changes in scope are easily identified. It is the “minor refinements” that eventu- ally build to be major scope changes that can cause problems. These small refinements are known in the field as scope creep. For example, the customer of a software devel- oper requested small changes in the development of a custom accounting software package. After several minor refinements, it became apparent the changes represented a significant enlargement of the original project scope. The result was an unhappy customer and a development firm that lost money and reputation. Although scope changes are usually viewed negatively, there are situations when scope changes result in positive rewards. Scope changes can represent significant opportunities.3 In product development environments, adding a small feature to a prod- uct can result in a huge competitive advantage. A small change in the production pro- cess may get the product to market one month early or reduce product cost. Scope creep is common early in projects—especially in new-product development projects. Customer requirements for additional features, new technology, poor design assumptions, etc., all manifest pressures for scope changes. Frequently these changes are small and go unnoticed until time delays or cost overruns are observed. Scope creep affects the organization, project team, and project suppliers. Scope changes alter the organization’s cash flow requirements in the form of fewer or additional resources, which may also affect other projects. Frequent changes eventually wear down team motivation and cohesiveness. Clear team goals are altered, become less focused, and cease being the focal point for team action. Starting over again is annoying and demor- alizing to the project team because it disrupts project rhythm and lowers productivity. Project suppliers resent frequent changes because they represent higher costs and have the same effect on their team as on the project team. The key to managing scope creep is change management. One project manager of an architectural firm related that scope creep was the biggest risk his firm faced in projects. The best defense against scope creep is a well-defined scope statement. Poor scope statements are one of the major causes of scope creep. A second defense against scope creep is stating what the project is not, which can avoid misinterpretations later. (Chapter 7 discusses the process. See Figure 7.9 to review key variables to document in project changes.) First, the original baseline must be well defined and agreed upon with the project customer. Before the project begins, it is imperative that clear procedures be in place for authorizing and documenting scope changes by the customer or project team. If a scope change is necessary, the impact on the baseline should be clearly documented—for example, cost, time, depen- dencies, specifications, responsibilities, etc. Finally, the scope change must be quickly added to the original baseline to reflect the change in budget and schedule; these changes and their impacts need to be communicated to all project stakeholders.

Baseline Changes Changes during the life cycle of projects are inevitable and will occur. Some changes can be very beneficial to project outcomes; changes having a negative impact are the ones we wish to avoid. Careful project definition can minimize the need for changes. The price for poor project definition can be changes that result in cost overruns, late schedules, low morale, and loss of control. Change comes from external sources or from within. Externally, for example, the customer may request changes that were not

3 See S. Keifer, “Scope Creep … Not Necessarily a Bad Thing,” PM Network, vol. 10, no. 5 (1996), pp. 33–35.

484 Chapter 13 Progress and Performance Measurement and Evaluation

included in the original scope statement and that will require significant changes to the project and thus to the baseline. Or the government may render requirements that were not a part of the original plan and that require a revision of the project scope. Internally, stakeholders may identify unforeseen problems or improvements that change the scope of the project. In rare cases scope changes can come from several sources. For example, the Denver International Airport automatic baggage handling system was an afterthought supported by several project stakeholders that included the Denver city government, consultants, and at least one airline customer. The addi- tional $2 billion in costs were staggering, and the airport opening was delayed 16 months. If this automatic baggage scope change had been in the original plan, costs would have been only a fraction of the overrun costs, and delays would have been reduced significantly. Any changes in scope or the baseline should be recorded by the change management system that was set in place during risk control planning. (See Chapter 7.) Generally, project managers monitor scope changes very carefully. They should allow scope changes only if it is clear that the project will fail without the change, the project will be improved significantly with the change, or the customer wants it and will pay for it. This statement is an exaggeration, but it sets the tone for approaching baseline changes. The effect of the change on the scope and baseline should be accepted and signed off by the project customer. Figure 13.13 depicts the cost impact of a scope change on the baseline at a point in time—“today.” Line A represents a scope change that results in an increase in cost. Line B represents a scope change that decreases cost. Quickly recording scope changes to the baseline keeps the computed earned values valid. Failure to do so results in misleading cost and schedule variances. Care should be taken to not use baseline changes to disguise poor performance on past or current work. A common signal of this type of baseline change is a constantly revised baseline that seems to match results. Practitioners call this a “rubber baseline” because it stretches to match results. Most changes will not result in serious scope changes and should be absorbed as positive or negative variances. Retroactive changes for work already accomplished should not be allowed. Transfer of money among cost

FIGURE 13.13 Scope Changes to a Baseline

C os

t

Time

Today

Original baseline

New baseline B

cost decrease

New baseline A

cost increase

Chapter 13 Progress and Performance Measurement and Evaluation 485

A consultant for the U.S. Forest Ser- vice suggested the use of earned value to monitor the 50-plus timber sale projects taking place concurrently in the district. As projects were com-

pleted, new ones were started. Earned value was tried for approximately nine months. After a nine-month trial, the process was to be reviewed by a task force. The task force concluded the earned value system provided good information for monitoring and forecasting proj- ect progress; however, the costs and problems of col- lecting timely percent complete data were unacceptable because there were no funds available to collect such data. The level of detail dilemma was discussed, but no suggestions satisfied the problem. The discussion rec- ognized that too little data fail to offer good control, while excessive reporting requires paperwork and people, which are costly. The task force concluded progress and performance could be measured using a

S N A P S H O T F R O M P R A C T I C E 1 3 . 3 A Pseudo-Earned Value Percent Complete Approach

pseudo-version of percent complete while not giving up much accuracy for the total project. This modified approach to percent complete required that very large work packages (about 3 to 5 percent of all work pack- ages in a project) be divided into smaller work pack- ages for closer control and identification of problems sooner. It was decided work packages of about a week’s duration would be ideal. The pseudo-version required only a telephone call and “yes/no” answers to one of the following questions to assign percent complete:

Has work on the work package started? No = 0% Working on the package? Yes = 50% Is the work package completed? Yes = 100%

Data for the pseudo-earned value percent complete system was collected for all 50-plus projects by an intern working fewer than eight hours each week.

accounts should not be allowed after the work is complete. Unforeseen changes can be handled through the contingency reserve. The project manager typically makes this decision. In some large projects, a partnering “change review team,” made up of mem- bers of the project and customer teams, makes all decisions on project changes.

The Costs and Problems of Data Acquisition Data acquisition is time consuming and costly. The Snapshot from Practice 13.3: A Pseudo-Earned Value Percent Complete Approach captures some of the frequent issues surrounding resistance to data collection of percent complete for earned value systems. Similar pseudo-percent complete systems have been used by others. Such pseudo-percent complete approaches appear to work well in multiproject environments that include several small and medium-sized projects. Assuming a one-week reporting period, care needs to be taken to develop work packages with a duration of about one week long so problems are identified quickly. For large projects, there is no substitute for using a percent complete system that depends on data collected through observa- tion at clearly defined monitoring points. In some cases data exist but are not sent to the stakeholders who need information relating to project progress. Clearly, if the information does not reach the right people in a timely manner, you can expect serious problems. Your communication plan devel- oped in the project planning stage can greatly mitigate this problem by mapping out the flow of information and keeping stakeholders informed on all aspects of project progress and issues. See Figure 13.14 for an internal communication plan for a WiFi Project. The information developed in this chapter contributes significant data to sup- port your communication plan and ensures correct dissemination of the data.

486 Chapter 13 Progress and Performance Measurement and Evaluation

FIGURE 13.14 Conference Center WiFi Project Communication Plan

What Information When? Mode? Responsible? Recipient?

Milestone report Bimonthly E-mail Project office Senior management Time/cost report Weekly E-mail Project office Staff and customer Risk report Weekly E-mail Project office Staff and customer Issues Weekly E-mail Anyone Staff and customer Team meeting times Weekly Meeting Project manager Staff and customer Outsourcing performance Bimonthly Meeting Project manager Project office, staff, and customer Change requests Anytime Document Project manager, Project office, staff, customer, design and customer Stage gate decisions Monthly Meeting Project office Senior management

Summary The best information system does not result in good control. Control requires the proj- ect manager to use information to steer the project through rough waters. Control and Gantt charts are useful vehicles for monitoring time performance. The cost/schedule system allows the manager to have a positive influence on cost and schedule in a timely manner. The ability to influence cost decreases with time; therefore, timely reports identifying adverse cost trends can greatly assist the project manager in getting back on budget and schedule. The integrated cost/schedule model provides the project manager and other stakeholders with a snapshot of the current and future status of the project. The benefits of the cost/schedule model are as follows: 1. Measures accomplishments against plan and deliverables. 2. Provides a method for tracking directly to a problem work package and organization

unit responsible. 3. Alerts all stakeholders to early identification of problems, and allows for quick,

proactive corrective action. 4. Improves communication because all stakeholders are using the same database. 5. Keeps customer informed of progress, and encourages customer confidence that the

money spent is resulting in the expected progress. 6. Provides for accountability over individual portions of the overall budget for each

organizational unit. With your information system in place, you need to use your communication plan to keep stakeholders informed so timely decisions can be made to ensure the project is managed effectively.

Key Terms Control chart, 463 Cost performance index (CPI), 476 Cost variance (CV), 466 Earned value (EV), 462

Forecasted total cost at completion (EACf), 479 Management Reserve Index (MRI), 477

Percent complete index actual costs (PCIC), 477 Percent complete index budgeted costs (PCIB), 477

Chapter 13 Progress and Performance Measurement and Evaluation 487

Revised estimated cost at completion (EACre), 479 Schedule variance (SV), 466

Scheduling performance index (SPI), 476 Scope creep, 483 To complete performance index (TCPI), 480

Tracking Gantt, 462 Variance at completion (VAC), 468

1. How does a tracking Gantt chart help communicate project progress? 2. How does earned value give a clearer picture of project schedule and cost status

than a simple plan versus actual system? 3. Schedule variance (SV) is in dollars and does not directly represent time. Why is it

still useful? 4. How would a project manager use the CPI? 5. What are the differences between BAC and EAC? 6. Why is it important for project managers to resist changes to the project baseline?

Under what conditions would a project manager make changes to a baseline? When would a project manager not allow changes to a baseline?

1. In month 9 the following project information is available: actual cost is $2,000, earned value is $2,100, and planned cost is $2,400. Compute the SV and CV for the project.

2. On day 51 a project has an earned value of $600, an actual cost of $650, and a planned cost of $560. Compute the SV, CV, and CPI for the project. What is your assessment of the project on day 51?

3. Given the project network and baseline information below, complete the form to develop a status report for the project at the end of period 4 and the end of period 8. From the data you have collected and computed for periods 4 and 8, what informa- tion are you prepared to tell the customer about the status of the project at the end of period 8?

F12

0

15

0

12 153

A0

0

2

0

2 22

D8

0

12

0

8 124

E7

2

10

2

9 123

C2

2

7

2

4 95

B2

0

8

0

2 86

LEGEND

ES ID EF

SL SL

LS DUR LF

Review Questions

Exercises

488 Chapter 13 Progress and Performance Measurement and Evaluation

ES LF SL

Project baseline (PV) (in $)

Budget (PV)

1 2 3 4 5 6 7 8 10 129 11 13 14 Task DUR

0 02

2 06

2 2 200 400

600

500 100

400 400 400 400

3005

8 04

7 23

12

2

8

9

12

12

15 0

400 200200

2400 200 200 200600 600

1500

1600

900 300 200400

600

200 200 400 1000 700 700 500 900 800 600 400 400 200 100

200 400 800 1800 2500 3200 3700 4600 5400 6000 6400 6800 7000 7100

300

200 100 300

7400

3

Period PV total

Cumulative PV total

A

B

C

D

E

F

0 15

End of Period 8

Task Actual % Complete EV AC PV CV SV A Finished ——   300  400 —— —— B Finished —— 2200 2400 —— —— C Finished —— 1500 1500 —— —— D 25% ——   300      0 —— —— E 33% ——   300 —— —— —— F 0% ——      0 —— —— —— Cumulative Totals —— —— —— —— ——

End of Period 4

Task Actual % Complete EV AC PV CV SV A Finished ——   300 400 —— —— B 50% —— 1000 800 —— —— C 33% ——   500 600 —— —— D   0% ——     0 —— —— —— E   0% —— —— —— —— —— Cumulative Totals —— —— —— —— ——

Chapter 13 Progress and Performance Measurement and Evaluation 489

4. Given the following project network, baseline, and status information, develop sta- tus reports for periods 2, 4, 6, 8 and complete the performance indexes table. Cal- culate the EACf and the VACf. Based on your data, what is your assessment of the current status of the project? At completion?

LEGEND

ES ID EF

SL SL

LS DUR LF

F10

0 0

12

10 122

A0

1

4

1

1 54

C4

2

8

2

6 104

E5

2

8

2

7 103

D5

0

10

0

5 105B0

0

5

0

0 55

Budget ($000)

1 2 3 4 5 6 7 8 109 11 ID

40 1010

32

48

18

28

40

18 14 18 14 20 26 22 26 2 6 20 20

20 20

18 32 50 64 84 110 132 158 160 166 186 206

Total

Cumulative

A

B

C

D

E

F

0

206

1010

48 4 8

12 12 12 12

6 2 2

8 8 12

2 6

8

12

490 Chapter 13 Progress and Performance Measurement and Evaluation

Status Report: Ending Period 2 ($000)

Task % Complete EV AC PV CV SV A 75% —— 25 —— —— —— B 50% —— 12 —— —— —— Cumulative Totals —— 37 —— —— ——

Status Report: Ending Period 4 ($000)

Task % Complete EV AC PV CV SV A 100% —— 35 —— —— —— B 100% —— 24 —— —— —— Cumulative Totals —— 59 —— —— ——

Status Report: Ending Period 6 ($000)

Task % Complete EV AC PV CV SV A 100% —— 35 —— —— —— B 100% —— 24 —— —— —— C   75% —— 24 —— —— —— D     0% ——   0 —— —— —— E   50% —— 10 —— —— —— Cumulative Totals —— 93 —— —— ——

Status Report: Ending Period 8 ($000)

Task % Complete EV AC PV CV SV A 100% —— 35 —— —— —— B 100% —— 24 —— —— —— C 100% —— 32 —— —— —— D   33% —— 20 —— —— —— E 100% —— 20 —— —— —— Cumulative Totals —— 131 —— —— ——

Performance Indexes Summary

Period EV AC PV SPI CPI PCI-B 2 —— —— —— —— —— —— 4 —— —— —— —— —— —— 6 —— —— —— —— —— —— 8 —— —— —— —— —— ——

EACf = ____________ VACf = ____________

Chapter 13 Progress and Performance Measurement and Evaluation 491

5. Given the following project network, baseline, and status information, develop sta- tus reports for periods 1–4 and complete the project summary graph (or a similar one). Report the final SV, CV, CPI, and PCIB. Based on your data, what is your assessment of the current status of the project? At completion?

ES ID

LEGEND

EF

SL SL

LS DUR LF

75

0 0

6

5 61

62

0

5

0

2 53

42

1

4

1

3 52

30

0

2

0

0 22

10

1

2

1

1 32

20

0

3

0

0 33

53

0

5

0

3 52

ES LF SL Time period

Baseline budget needs ($ 000)

Schedule information

Total PV 1 2 3 4 5 6

ACT/ WP DUR

0 11 2

0 02 3

0 03 2

2 14 2

3 05 2

2

5

3

3

2

5

5

5

6

0

0

12

15

8

6

10

9

5

6

7

3

1

11

Total PV by period

Cumulative PV by period 30 41 53 60 65

11 19 11 12 7 5

4

3

4

8

7

3 3

4

3

6

3 3

5

4

5

0

492 Chapter 13 Progress and Performance Measurement and Evaluation

Status Report: Ending Period 1 ($000)

Task %Complete EV AC PV CV SV 1 50%    ——   6 4 —— —— 2 40%    ——   8 3 —— —— 3 25%    ——   3 —— —— —— Cumulative Totals —— 17 —— —— ——

Status Report: Ending Period 2 ($000)

Task %Complete EV AC PV CV SV 1 Finished —— 13 —— —— —— 2 80%    —— 14 —— —— —— 3 75%    ——   8 —— —— —— Cumulative Totals —— 35 —— —— ——

Status Report: Ending Period 3 ($000)

Task %Complete EV AC PV CV SV 1 Finished 12 13 —— —— —— 2 80%    —— 15 —— —— —— 3 Finished —— 10 —— —— —— 4 50%    ——   4 —— —— —— 5 0%   ——   0 —— —— —— 6 33.3% ——   4 —— —— —— Cumulative Totals —— —— —— —— ——

Status Report: Ending Period 4 ($000)

Task %Complete EV AC PV CV SV 1 Finished 12 13 —— —— —— 2 Finished 15 18 —— —— —— 3 Finished —— 10 —— —— —— 4 Finished ——   8 —— —— —— 5 30%    ——   3 —— —— —— 6 66.7% ——   8 —— —— —— 7 0%  ——   0 —— —— —— Cumulative Totals —— —— —— —— ——

10 0

10

70

60

40

50

20

30

2 3 4 5 6 7 8

PV

Summary Graph

Time periods

In de

x

Chapter 13 Progress and Performance Measurement and Evaluation 493

6. The following labor hours data have been collected for a nanotechnology project for periods 1 through 6. Compute the SV, CV, SPI, and CPI for each period. Plot the EV and the AC on the summary graph provided (or a similar one). Plot the SPI, CPI, and PCIB on the index graph provided (or a similar one). What is your assess- ment of the project at the end of period 6?

ES ID

Legend

EF

SL SL

LS DUR LF

7

2

6

4

5

4

4

5

2

2

3

6

1

2

ACT/ WP DUR ES

Schedule information

LF SL TotalPV

1 2 0 2 0 20

1 2 3 4 5 6 7

Baseline budget needs–labor hours (00)

Time period 8 9 10 11 12 13

2 2 2 7 3 24

3 6 2 11 3 30

4 5 2 7 0 25

5 4 4 11 3 16

6 4 7 11 0 20

7 2 11 13 0 10

0

1010

816

55 10 3 2 5

1010 2 2 1

4 4 4 4

5 5 6 4

5 5

10 31 23 16 9 7 14 5 610 5 54

20 51 74 90 99 106 120 125 131 135 140 14510

Total PV by period

Cumulative PV by period

14

494 Chapter 13 Progress and Performance Measurement and Evaluation

Status Report: Ending Period 1

Task %Complete EV AC PV CV SV 1 50% ——   500 1000 —— —— Cumulative Totals ——   500 1000 —— ——

Status Report: Ending Period 2

Task %Complete EV AC PV CV SV 1 Finished —— 1500 2000 —— —— Cumulative Totals —— 1500 2000 —— ——

Status Report: Ending Period 3

Task %Complete EV AC PV CV SV 1 Finished 2000 1500 2000 —— —— 2   0% ——      0 —— —— —— 3 10% ——   200 —— —— —— 4 20% ——   500 —— —— —— Cumulative Totals —— 2200 —— —— ——

Status Report: Ending Period 4

Task %Complete EV AC PV CV SV 1 Finished 2000 1500 2000 —— —— 2 50% —— 1000 —— —— —— 3 30% ——   800 —— —— —— 4 40% —— 1500 —— —— —— Cumulative Totals —— 4800 —— —— ——

Status Report: Ending Period 5

Task %Complete EV AC PV CV SV 1 Finished 2000 1500 2000 —— —— 2 Finished —— 2000 —— —— —— 3 50% ——   800 —— —— —— 4 60% —— 1500 —— —— —— 5 25% ——   400 —— —— —— Cumulative Totals —— 6200 —— —— ——

Status Report: Ending Period 6

Task %Complete EV AC PV CV SV 1 Finished 2000 1500 2000 —— —— 2 Finished —— 2000 —— —— —— 3 80% —— 2100 —— —— —— 4 80% —— 1800 —— —— —— 5 50% ——   600 —— —— —— Cumulative Totals —— 8000 —— —— ——

Chapter 13 Progress and Performance Measurement and Evaluation 495

Period SPI CPI PCIB

1 —— —— —— SPI = EV/PV 2 —— —— —— CPI = EV/AC 3 —— —— —— PCIB = EV/BAC 4 —— —— —— 5 —— —— —— 6 —— —— ——

La bo

r h ou

rs

10 0

2 3 4 5 6 7 8 9 10 11 12 13 14 15

4000

2000

6000

8000

10000

12000

14000

16000

Time periods

PV

Summary Graph

0 10 2 3 4

Time periods 5 6 7

.20

.40

.60

.80

In de

x

1.00

1.20

1.40

1.60

1.80

2.00

2.20

Indexes Periods 1–6

496 Chapter 13 Progress and Performance Measurement and Evaluation

ES ID

Legend

EF

SL SL

LS DUR LF

68

2

16

2

10 188

818

0

22

0

18 224

24

2

12

2

6 148

714

0

18

0

14 184

10

0

4

0

0 44

34

0

10

0

4 106

510

0

14

0

10 144

44

2

8

2

6 104

Baseline (PV) ($00)

2 4 6 8 10 12 14 16 2018

2020

4 4

4 4

30 35 35 50 30

10 10

20

20 20 10 10

10 15

10 10

5

10 10

10

10 10

20 10

20 10

4 8 38 73 108 158 188 208 218 238 248

Period PV total

Cumulative PV total

ES

0

4

4

4

10

8

14

18

LF

4

14

10

10

14

18

18

22

SL

0

2

0

2

0

2

0

0

PV ($00)

8

40

30

20

40

60

20

30

DUR

4

8

6

4

4

8

4

4

Task

1

2

3

4

5

6

7

8

0 22

Status Report: Ending Period 2 ($00)

Task %Complete EV    AC PV CV SV 1 50% ——     4 —— —— —— Cumulative Totals ——     4 —— —— ——

7. The following data have been collected for a British health care IT project for two- week reporting periods 2 through 12. Compute the SV, CV, SPI, and CPI for each period. Plot the EV and the AC on the summary graph provided. Plot the SPI, CPI, and PCIB on the index graph provided. (You may use your own graphs.) What is your assessment of the project at the end of period 12?

Chapter 13 Progress and Performance Measurement and Evaluation 497

Status Report: Ending Period 4 ($00)

Task %Complete EV   AC PV CV SV 1 Finished ——   10 —— —— —— Cumulative Totals ——   10 —— —— ——

Status Report: Ending Period 6 ($00)

Task %Complete EV   AC PV CV SV 1 Finished ——   10 —— —— —— 2 25% ——   15 —— —— —— 3 33% ——   12 —— —— —— 4 0% ——     0 —— —— —— Cumulative Totals ——  37 —— —— ——

Status Report: Ending Period 8 ($00)

Task %Complete EV   AC PV CV SV 1 Finished ——   10 —— —— —— 2 30% ——   20 —— —— —— 3 60% ——   25 —— —— —— 4 0% ——     0 —— —— —— Cumulative Totals ——   55 —— —— ——

Status Report: Ending Period 10 ($00)

Task %Complete EV   AC PV CV SV 1 Finished ——   10 —— —— —— 2 60% ——   30 —— —— —— 3 Finished ——   40 —— —— —— 4 50% ——   20 —— —— —— 5 0% ——     0 —— —— —— 6 30% ——   24 —— —— —— Cumulative Totals —— 124 —— —— ——

Status Report: Ending Period 12 ($00)

Task %Complete EV   AC PV CV SV 1 Finished ——  10 —— —— —— 2 Finished ——   50 —— —— —— 3 Finished ——   40 —— —— —— 4 Finished ——   40 —— —— —— 5 50% ——   30 —— —— —— 6 50%   40 —— —— —— Cumulative Totals —— 210 —— —— ——

Period SPI CPI PCIB

2 —— —— —— SPI = EV/PV 4 —— —— —— CPI = EV/AC 6 —— —— —— PCIB = EV/BAC 8 —— —— —— 10 —— —— —— 12 —— —— ——

498 Chapter 13 Progress and Performance Measurement and Evaluation

20 0

4 6 8 10 12 14 16 18 20 22 24

40

20

60

80

120

160

100

140

180

200

220

240

260

PV

Summary Graph

Time periods

D ol

la rs

0 20 4 6 8 10 12 14

.20

.40

.60

.80

1.00

1.20

1.40

1.60

Indexes Periods 2–12

Time periods

In de

x

8. * Part A. You are in charge of the Aurora Project. Given the following project net- work, baseline, and status information, develop status reports for periods 1–8 and complete the performance indexes table. Calculate the EACf and VACf. Based on your data, what is the current status of the project? At completion?

A0

0

2

0

0 22

B2

0

5

0

2 53

C2

0

5

0

2 53

ES ID EF

SL SL

LS DUR LF

H11

0

13

0

11 132

D5

0

7

0

5 72 F7

1

10

1

8 113

E7

0

9

0

7 92

G9

0

11

0

9 112

Legend

* The solution to this exercise can be found in Appendix 1.

Chapter 13 Progress and Performance Measurement and Evaluation 499

Budget ($000)

1 2 3 4 5 6 7 8 109 11 ID

100 5050

250

450

200

300

300

50 50 250 200 250 100 100 300 150 300 50 100

50 100 350 550 800 900 1000 1300 1450 1750 1800 1900

Total

Cumulative 2000

100 100

A

B

C

D

E

F

200

100

G

200H

0

2000

50 100

100 100

200 100

100 50 150

150 50

100

150 150150

1312

Status Report: Ending Period 1 ($000)

Task % Complete EV AC PV CV SV A   25% ——   50 —— —— —— Cumulative Totals ——   50 —— —— ——

Status Report: Ending Period 2 ($000)

Task % Complete EV AC PV CV SV A   50% —— 100 —— —— —— Cumulative Totals —— —— —— —— ——

Status Report: Ending Period 3 ($000)

Task % Complete EV AC PV CV SV A 100% —— 200 —— —— —— B   0% ——     0 —— —— —— C     0% ——     0 —— —— —— Cumulative Totals —— —— —— —— ——

Status Report: Ending Period 4 ($000)

Task % Complete EV AC PV CV SV A 100% —— 200 —— —— —— B   60% —— 100 —— —— —— C   50% —— 200 —— —— —— Cumulative Totals —— 500 —— —— ——

500 Chapter 13 Progress and Performance Measurement and Evaluation

Status Report: Ending Period 5 ($000)

Task % Complete EV AC PV CV SV A 100% —— 200 —— —— —— B 100% —— 200 —— —— —— C 100% —— 400 —— —— —— Cumulative Totals —— 800 —— —— ——

Status Report: Ending Period 6 ($000)

Task % Complete EV AC PV CV SV A 100% —— 200 —— —— —— B 100% —— 200 —— —— —— C 100% —— 400 —— —— —— D   75% —— 100 —— —— —— Cumulative Totals —— 900 —— —— ——

Status Report: Ending Period 7 ($000)

Task % Complete EV AC PV CV SV A 100% —— 200 —— —— —— B 100% —— 200 —— —— —— C 100% —— 400 —— —— —— D 100% —— 150 —— —— —— E   20% —— 100 —— —— —— F     5% ——   50 —— —— —— Cumulative Totals —— 1100   —— —— ——

Status Report: Ending Period 8 ($000)

Task % Complete EV AC PV CV SV A 100% —— 200 —— —— —— B 100% —— 200 —— —— —— C 100% —— 400 —— —— —— D 100% —— 150 —— —— —— E 100% —— 350 —— —— —— F   10% —— 100 —— —— —— Cumulative Totals —— 1400   —— —— ——

Performance Indexes Summary

Period EV AC PV SPI CPI PCI-B 1 —— —— —— —— —— —— 2 —— —— —— —— —— —— 3 —— —— —— —— —— —— 4 —— —— —— —— —— —— 5 —— —— —— —— —— —— 6 —— —— —— —— —— —— 7 —— —— —— —— —— —— 8 —— —— —— —— —— ——

EACf = ____________ VACf = ____________

Chapter 13 Progress and Performance Measurement and Evaluation 501

Part B. You have met with your Aurora project team and they have provided you with the following revised estimates for the remainder of the project:

∙ Activity F will be completed at the end of period 12 at a total cost of 500. ∙ Activity G will be completed at the end of period 10 at a total cost of 150. ∙ Activity H will be completed at the end of period 14 at a total cost of 200. Calculate the EACre and VACre. Based on the revised estimates, what is the expected

status of the project in terms of cost and schedule? Between the VACf and the VACre, which one would you have the greatest confidence in?

EACre = _________________ VACre = _________________

Abramovici, A., “Controlling Scope Creep,” PM Network, vol. 14, no. 1 (January 2000), pp. 44–48. Anbari, F. T., “Earned Value Project Management Method and Extensions,” Project Management Journal, vol. 34, no. 4 (December 2003), pp. 12–22. Bowles, M. “Keeping Score,” PMNetwork, May 2011, pp. 50–59. Brandon, D. M., Jr., “Implementing Earned Value Easily and Effectively,” Project Management Journal, vol. 29, no. 3 (June 1998), pp. 11–17. Christensen, D. S., “The Cost and Benefits of the Earned Value Management Process,” Acquisition Review Quarterly, vol. 5 (1998), pp. 373–86. Christensen, D. S., and S. Heise, “Cost Performance Index Stability,” National Contract Management Association Journal, vol. 25 (1993), pp. 7–15. Fleming, Q., and Joel M. Koppelman, Earned Value Project Management, 4th ed. (Newton Square, PA: Project Management Institute, 2010). Kerzner, H., “Strategic Planning for a Project Office,” Project Management Jour- nal, vol. 34, no. 2 (June 2003), pp. 13–25. Kim, E. H., W. G. Wells, and M. R. Duffey, “A Model for Effective Implementation of Earned Value Methodology,” International Journal of Project Management,  vol. 21, no. 5 (2003), pp. 375–82. Naeni, L., S. Shadrokh, and A. Salehipour, “A Fuzzy Approach to the Earned Value Management,” International Journal of Project Management, vol. 9, no. 6 (2011), pp. 764–72. Webb, A., Using Earned Value: A Project Manager’s Guide (Aldershot, UK: Gower Publishing Co., 2003).

References

502 Chapter 13 Progress and Performance Measurement and Evaluation

Case 13.1

Tree Trimming Project Wil Fence is a large timber and Christmas tree farmer who is attending a project man- agement class in the spring, his off season. When the class topic came to earned value, he was perplexed. Isn’t he using EV? Each summer Wil hires crews to shear fields of Christmas trees for the coming Holiday season. Shearing entails having a worker use a large machete to shear the branches of the tree into a nice, cone-shaped tree. Wil describes his business as follows: A. I count the number of Douglas Fir Christmas trees in the field (24,000). B. Next, I agree on a contract lump sum for shearing with a crew boss for the whole

field ($30,000). C. When partial payment for work completed arrives (5 days later), I count or estimate

the actual number sheared (6,000 trees). I take the actual as a percent of the total to be sheared, multiply the percent complete by total contract amount for the partial payment [(6,000/$30,000 = 25%), (.25 × $30,000 = $7500)].

1. Is Wil over, on, or below cost and schedule? Is Wil using earned value? 2. How can Wil set up a scheduling variance?

Case 13.2

Shoreline Stadium Status Report Case You are an assistant to Percival Young, president of G&L Construction. He has asked you to prepare a brief report on the status of the Shoreline Stadium project. Shoreline stadium is a 47,000-seat professional baseball stadium. Construction started on April 3, 2018, and the stadium is schedule to be completed on March 25, 2020. The project is estimated to cost $310,000,000. There is a $35 million manage- ment reserve to deal with unexpected problems and delays. The stadium must be ready for the 2020 major league season. G&L would accrue a $250,000 per day penalty for not meeting the April 3, 2020 deadline. G&L expects to make more than $3 million on the project. The stadium is one of several major projects G&L has under way in North America, including a professional soccer stadium and another baseball stadium, which broke ground last month. It is 8/8/2019 the day after the key milestone “Start Installing Seats” was to occur. Tables C13.1 and C13.2 contain information submitted by your counterpart at the Shoreline site from which you are to prepare your report. Use the appropriate indexes/ information to prepare a report informing Mr. Young on the overall status of the Shoreline project in terms of costs and schedule. Note: Mr. Young is not interested in specifics, but just how well the overall project is doing and if there is a need to take corrective action.

Chapter 13 Progress and Performance Measurement and Evaluation 503

   PV    EV    AC    CV    SV

Baseball Stadium 209,000,000 200,600,000 210,500,000 −9,900,000 −8,400,000 Clear stadium site --10,000,000 10,000,000 9,000,000 1,000,000 0 Demolish building 2,000,000 2,000,000 2,000,000 0 0 Set up construction site 2,000,000 2,000,000 1,500,000 500,000 0 Drive support piling 40,000,000 40,000,000 41,000,000 −1,000,000 0 Pour lower concrete bowl 50,000,000 50,000,000 55,000,000 −5,000,000 0 Pour main concourse 15,000,000 15,000,000 18,000,000 −3,000,000 0 Install playing field 5,000,000 5,000,000 5,000,000 0 0 Construct upper steel bowl 60,000,000 51,600,000 55,000,000 −3,400,000 −8,400,000 Install seats 10,000,000 Build luxury boxes 25,000,000 Install jumbotron 2,000,000 Stadium infrastructure 22,000,000 Construct steel canopy 20,000,000 Light installation 5,000,000 Build roof supports 10,000,000 10,000,000 10,000,000 0 0 Construct roof 15,000,000 15,000,000 14,000,000 1,000,000 0 Install roof tracks 10,000,000 Install roof 5,000,000 Inspection 2,000,000

BAC EACf VAC

Shoreline Stadium 310,000,000 325,299,103 −15,299,103

TABLE C13.1 Shoreline Project Earned Value Table as of 8/7/2019

Task Name Start Finish Baseline Start Baseline Finish Start Var. Finish Var.

Greendale Stadium Project Mon 7/3/17 Thu 4/8/21 Mon 7/3/17 Thu 3/25/21 0 days 10 days Clear Stadium Site Mon 7/3/17 Tue 10/10/17 Mon 7/3/17 Tue 10/10/17 0 days 0 days Demolish Building Wed 10/11/17 Tue 11/21/17 Wed 10/11/17 Tue 11/21/17 0 days 0 days Set up Construction Site Wed 11/22/17 Fri 2/23/18 Wed 11/22/17 Tue 3/6/18 0 days −7 days Drive Support Pilings Mon 2/26/18 Wed 8/22/18 Wed 3/7/18 Thu 8/23/18 −7 days −1 day Pour Lower Concrete Bowl Thu 8/23/18 Thu 2/21/19 Fri 8/24/18 Fri 2/15/19 −1 day 4 days Pour Main Concourse Fri 2/22/19 Fri 8/2/19 Mon 2/18/19 Tue 8/6/19 4 days −2 days Install Playing Field Fri 2/22/19 Fri 6/28/19 Mon 2/18/19 Mon 6/24/19 4 days 4 days Construct Upper Steel Bowl Fri 2/22/19 Tue 8/20/19 Mon 2/18/19 Tue 8/6/19 4 days 10 days Install Seats Wed 8/21/19 Wed 3/11/20 Wed 8/7/19 Wed 2/26/20 10 days 10 days Build Luxury Boxes Wed 8/21/19 Mon 12/30/19 Wed 8/7/19 Thu 12/12/19 10 days 10 days Install Jumbotron Wed 8/21/19 Wed 10/2/19 Wed 8/7/19 Wed 9/18/19 10 days 10 days Stadium Infrastructure Wed 8/21/19 Wed 2/12/20 Wed 8/7/19 Wed 1/29/20 10 days 10 days Construct Steel Canopy Thu 3/12/20 Thu 6/25/20 Thu 2/27/20 Thu 6/11/20 10 days 10 days Light Installation Thu 3/12/20 Wed 4/22/20 Thu 2/27/20 Wed 4/8/20 10 days 10 days Build Roof Supports Mon 2/26/18 Mon 7/2/18 Wed 3/7/18 Thu 7/12/18 −7 days −7 days Construct Roof Tue 7/3/18 Tue 4/14/20 Fri 7/13/18 Thu 4/23/20 −7 days −7 days Install Roof Tracks Fri 6/26/20 Mon 11/2/20 Fri 6/12/20 Mon 10/19/20 10 days 10 days Install Roof Tue 11/3/20 Thu 3/11/21 Tue 10/20/20 Thu 2/25/21 10 days 10 days Inspection Fri 3/12/21 Thu 4/8/21 Fri 2/26/21 Thu 3/25/21 10 days 10 days

TABLE C13.2 Variance Table for Shoreline Project as of 8/7/2019

504 Chapter 13 Progress and Performance Measurement and Evaluation

Case 13.3

Scanner Project You have been serving as Electroscan’s project manager and are now well along in the project. Develop a narrative status report for the board of directors of the chain store that discusses the status of the project to date (see Table C13.3) and at com- pletion. Be as specific as you can using numbers given and those you might develop. Remember, your audience is not familiar with the jargon used by project managers and computer software personnel; therefore, some explanation may be necessary. Your report will be evaluated on your detailed use of the data, your total perspec- tive of the current status and future status of the project, and your recommended changes (if any).

Electroscan, Inc. 555 Acorn Street, Suite 5 Boston, Massachusetts

Scanner project

H 1.0 Hardware H 1.1 H 1.2 H 1.3 H 1.4 H 1.5 H 1.6 H 1.7

Hardware specifications (DS) Hardware design (DS) Hardware documentation (DOC) Prototypes (PD) Test prototypes (T) Order circuit boards (PD) Preproduction models (PD)

OP 1.0 Operating system

OP 1.2 Drivers

OP 1.3 Code software

OP 1.2.1 Disk drivers (DEV) OP 1.2.2 I/O drivers (DEV)

OP 1.3.1 Code software (C) OP 1.3.2 Document software (DOC) OP 1.3.3 Code interfaces (C) OP 1.3.4 Beta test software (T)

OP 1.1 Kernel specifications (DS)

U 1.0 Utilities U 1.1 U 1.2 U 1.3 U 1.4 U 1.5

Utilities specifications (DS) Routine utilities (DEV) Complex utilities (DEV) Utilities documentation (DOC) Beta test utilities (T)

S 1.0 System integration S 1.1 S 1.2 S 1.3 S 1.4 S 1.5

Architecture decisions (DS) Integration hard/soft (DEV) System hard/software test (T) Project documentation (DOC) Integration acceptance testing (T)

1103

213 15 25

8 40 30 25

100 431

97

336

60 37

200 42 96 30

15

274 15 35

150 20 40

153 8

75 20 12 30

915

260 20 30 10 40 30 30

100 330

70

240

40 30

100 50 60 30

20

200 20 20

100 20 40

125 10 50 20 15 30

–81

16 5 5 1

0 0 5 0

–46

–21

–30

–15 –6

–20 5

–15 0

5

–40 5

–15 –30

0 0

–11 2

–15 0 2 0

–25

–4 0 0

–4 0 0 0 0

–45

10

–55

5 5

–10 –15 –30

0

0

21 0 0

30 –9

0 3 0 5 0

–2 0

476

72 15 25

5 2 0

25 0

196

76

105

45 31

40 25 40

0

15

148 15 35 90

8 0

60 7

45 0 8 0

395

88 20 30

6 2 0

30 0

150

55

75

30 25

20 30 25

0

20

108 20 20 60

8 0

49 9

30 0

10 0

420

92 20 30 10 2 0

30 0

195

45

130

25 20

30 45 55

0

20

87 20 20 30 17 0

46 9

25 0

12 0

Name PV EV AC SV CV BAC EACf

29 In-store Scanner Project (thousands of dollars)

Actual Progress as of January 1

TABLE C13.3

Chapter 13 Progress and Performance Measurement and Evaluation 505

Appendix 13.1

The Application of Additional Earned Value Rules

LEARNING OBJECTIVES After reading this appendix you should be able to:

LO A13.1-1 Apply pseudo earned value rules to measure progress on a project.

The following example and exercises are designed to provide practice in applying the following three earned value rules: ∙ Percent complete rule ∙ 50/50 rule ∙ 0/100 rule See the chapter for an explanation of each of these rules.

Simplifying Assumptions The same simplifying assumptions used for the chapter example and exercises will also be used here. 1. Assume each cost account has only one work package, and each cost account will

be represented as an activity on the network. 2. The project network early start times will serve as the basis for assigning the base-

line values. 3. Except when the 0/100 rule or 50/50 rule is used, baseline values will be assigned

linearly, unless stated differently. (Note: In practice estimated costs should be applied “exactly” as they are expected to occur so measures of schedule and cost performance are useful and reliable.)

4. For purposes of demonstrating the examples, from the moment work on an activity begins, some actual costs will be incurred each period until the activity is completed.

5. When the 0/100 rule is used, the total cost for the activity is placed in the baseline on the early finish date.

6. When the 50/50 rule is used, 50 percent of the total cost is placed in the baseline on the early start date and 50 percent on the early finish date.

Appendix Exercises

1. Given the information provided for development of a product warranty project for periods 1 through 7, compute the SV, CV, SPI, and CPI for each period. Plot the EV and the AC on the PV graph provided. Explain to the owner your assessment of the project at the end of period 7 and the future expected status of the project at com- pletion. Figure A13.1A presents the project network. Figure A13.1B presents the project baseline noting those activities using the 0/100 (rule 3) and 50/50 (rule 2) rules. For example, activity 1 uses rule 3, the 0/100 rule. Although the early start

Apply pseudo earned value rules to measure progress on a project.

A13.1-1LO

506 Chapter 13 Progress and Performance Measurement and Evaluation

time is period 0, the budget is not placed in the time-phased baseline until period 2 when the activity is planned to be finished (EF). This same procedure has been used to assign costs for activities 2 and 7. Activities 2 and 7 use the 50/50 rule. Thus, 50 percent of the budget for each activity is assigned on its respective early start date (time period 2 for activity 2 and period 11 for activity 7) and 50 percent for their respective finish dates. Remember, when assigning earned value as the project is being implemented, if an activity actually starts early or late, the earned values must shift with the actual times. For example, if activity 7 actually starts in period 12 rather than 11, the 50 percent is not earned until period 12.

DUR SL Time period

Baseline budget needsSchedule information

Total PV 1 2 3 4 5 6 7 8 10 129 11 13

EV Rule

ACT/ WP

2 01

3 62

5 0 9 6 6 6

8 2 5 5

33

4 14

4 05

2 3 9 9

6 6

20 10 10

30

20

16 4 44 4

18

3

ES

0

2

2

2

7

6

11

LF

2

11

7

7

11

11

14 0 8

0 6 27 8 21 11 12 13 4 4 4 4 0 4

0 6 33 41 62 73 85 98 102 106 110 114 114 118

4 4

6

7

Total PV by period

Cumulative PV by period

3

2

1

1

1

1

2

0 14

Rule

1 = %complete 2 = 50 ⁄ 50 3 = 0 ⁄ 100

FIGURE A13.1-1B

ES ID

Legend

EF

SL SL

LS DUR LF

711

0

14

0

11 143

66

3

8

3

9 112

57

0

11

0

7 114

42

1

6

1

3 74

22

6

5

6

8 113

32

0

7

0

2 75

10

0

2

0

0 22

FIGURE A13.1-1A

Chapter 13 Progress and Performance Measurement and Evaluation 507

Status Report: Ending Period 1

Task %Complete EV AC PV CV SV 1   0% ——   3 0 —— —— Cumulative Totals ——   3 0 —— ——

Status Report: Ending Period 2

Task %Complete EV AC PV CV SV 1 Finished 6   5 —— —— —— Cumulative Totals 6   5 —— —— ——

Status Report: Ending Period 3

Task %Complete EV AC PV CV SV 1 Finished 6   5 —— —— —— 2   0% ——   5 —— —— —— 3 30% ——   7 —— —— —— 4 25% ——   5 —— —— —— Cumulative Totals —— 22 —— —— ——

Status Report: Ending Period 4

Task %Complete EV AC PV CV SV 1 Finished 6   5 —— —— —— 2   0% ——   7 —— —— —— 3 50% —— 10 —— —— —— 4 50% ——   8 —— —— —— Cumulative Totals —— 30 —— —— ——

Status Report: Ending Period 5

Task %Complete EV AC PV CV SV 1 Finished 6   5 —— —— —— 2 50% ——   8 —— —— —— 3 60% —— 12 —— —— —— 4 70% —— 10 —— —— —— Cumulative Totals —— 35 —— —— ——

Status Report: Ending Period 6

Task %Complete EV AC PV CV SV 1 Finished 6   5 —— —— —— 2 50% —— 10 —— —— —— 3 80% —— 16 —— —— —— 4 Finished —— 15 —— —— —— Cumulative Totals —— 46 —— —— ——

Status Report: Ending Period 7

Task %Complete EV AC PV CV SV 1 Finished 6   5 —— —— —— 2 Finished —— 14 —— —— —— 3 Finished —— 20 —— —— —— 4 Finished —— 15 —— —— —— 5   0% ——   0 —— —— —— 6 50% ——   9 —— —— —— Cumulative Totals —— 63 —— —— ——

508 Chapter 13 Progress and Performance Measurement and Evaluation

2. Given the information provided for development of a catalog product return process for periods 1 through 5, assign the PV values (using the rules) to develop a baseline for the project. Compute the SV, CV, SPI, and CPI for each period. Explain to the owner your assessment of the project at the end of period 5 and the future expected status of the project at the completion.

Period SPI CPI PCIB

1 —— —— —— 2 —— —— —— 3 —— —— —— SPI = EV/PV 4 —— —— —— CPI = EV/AC 5 —— —— —— PCIB = EV/BAC 6 —— —— —— 7 —— —— ——

10 0

10

120 110

100 90 80 70 60 50 40 30 20

2 3 4 5 6 7 8 9 10 11 12 13 14

PV

Time periods

D ol

la rs

FIGURE A13.1-2C

0 10 2 3 4

Time periods 5 6 7

.20

.40

.60

.80

In de

x

1.00

1.20

1.40

1.60

CPI =

SPI =

PCIB =

1.80

2.00

2.20

FIGURE A13.1-2D

Chapter 13 Progress and Performance Measurement and Evaluation 509

ES ID

Legend

EF

SL SL

LS DUR LF

77

0

10

0

7 103

64

0

7

0

4 73

43

2

5

2

5 72

30

0

4

0

0 44

10

2

3

2

2 53

20

1

2

1

1 32

52

1

6

1

3 74

FIGURE A13.1-2A

DUR Time period

Baseline budget needsSchedule information

Total PV 1 2 3 4 5 6 7 8 109

EV Rule

ACT/ WP

31

22

43

24

45

3

30

20

30

10

40

30

3

ES

0

0

0

3

2

4

7

SL

2

1

0

2

1

0

0

LF

5

3

4

7

7

7

10 60

6

7

Total PV by period

Cumulative PV by period

2

3

2

3

2

1

1

0

Rule

1 = %complete 2 = 50 ⁄ 50 3 = 0 ⁄ 100

FIGURE A13.1-2B

Status Report: Ending Period 1

Task %Complete EV AC PV CV SV 1 40% —— 8 —— —— —— 2 0% —— 12 —— —— —— 3 30% —— 10 —— —— —— Cumulative Totals —— 30 —— —— ——

510 Chapter 13 Progress and Performance Measurement and Evaluation

Status Report: Ending Period 2

Task %Complete EV AC PV CV SV 1 80% —— 20 —— —— —— 2 Finished —— 18 —— —— —— 3 50% —— 12 —— —— —— Cumulative Totals —— 50 —— —— ——

Status Report: Ending Period 3

Task %Complete EV AC PV CV SV 1 Finished —— 27 —— —— —— 2 Finished —— 18 —— —— —— 3 70% —— 15 —— —— —— 4 0% —— 5 —— —— —— 5 30% —— 8 —— —— —— Cumulative Totals —— 73 —— —— ——

Status Report: Ending Period 4

Task %Complete EV AC PV CV SV 1 Finished —— 27 —— —— —— 2 Finished —— 18 —— —— —— 3 Finished —— 22 —— —— —— 4 0% —— 7 —— —— —— 5 60% —— 22 —— —— —— Cumulative Totals —— 96 —— —— ——

Status Report: Ending Period 5

Task %Complete EV AC PV CV SV 1 Finished —— 27 —— —— —— 2 Finished —— 18 —— —— —— 3 Finished —— 22 —— —— —— 4 Finished —— 8 —— —— —— 5 70% —— 24 —— —— —— 6 30% —— 10 —— —— —— Cumulative Totals —— 109 —— —— ——

10 0

30

240

210

180

150

120

D ol

la rs

90

60

2 3 4 5 6 7 8 9 10 11 12

PV

Time periods

FIGURE A13.1-2C

Chapter 13 Progress and Performance Measurement and Evaluation 511

Period SPI CPI PCIB

1 —— —— —— 2 —— —— —— SPI = EV/AC 3 —— —— —— CPI = EV/AC 4 —— —— —— PCIB = EV/BAC 5 —— —— ——

Appendix 13.2

Obtaining Project Performance Information from MS Project 2010 or 2015

LEARNING OBJECTIVES After reading this appendix you should be able to:

LO A13.2-1 Obtain project performance information from MS Project 2010 or 2015.

The objective of this appendix is to illustrate how one can obtain the performance information discussed in Chapter 13 from MS Project 2010 or 2015. One of the great strengths of MS Project is its flexibility. The software provides numerous options for entering, calculating, and presenting project information. Flexibility is also the soft- ware’s greatest weakness in that there are so many options that working with the soft- ware can be frustrating and confusing. The intent here is to keep it simple and present basic steps for obtaining performance information. Students with more ambitious agendas are advised to work with the software tutorial or consult one of many instruc- tional books on the market. For purposes of this exercise we will use the Digital Camera project, which was introduced in Chapter 13. In this scenario the project started as planned on March 1 and today’s date is March 7. We have received the following information on the work completed to date:

Design Specs took 2 days to complete at a total cost of $20. Shell & Power took 3 days to complete at a total cost of $25. Memory/Software is in progress with 4 days completed and two days remaining. Cost to date is $100. Zoom System took 2 days to complete at a cost of $25.

All tasks started on time.

Obtain project perfor- mance information from MS Project 2010 or 2015.

A13.2-1LO

512 Chapter 13 Progress and Performance Measurement and Evaluation

STEP 1 ENTERING PROGRESS INFORMATION We enter this progress information in the TRACKING TABLE from the GANTT CHART VIEW ▸ VIEW ▸ TABLES ▸ TRACKING:

TABLE A13.2-1A Tracking Table

ID Task Name Act. Start Act. Finish % Comp. Act. Dur. Rem. Dur. Act. Cost Act. Work

1 Digital Camera Prototype 3/1 NA 61% 6.72 days 4.28 days $170.00 272 hrs 2 Design Spec.s 3/1 3/2 100% 2 days 0 days $20.00 32 hrs 3 Shell & Power 3/3 3/7 100% 3 days 0 days $25.00 40 hrs 4 Memory/Software 3/3 NA 67% 4 days 2 days $100.00 160 hrs 5 Zoom System 3/3 3/4 100% 2 days 0 days $25.00 40 hrs 6 Assemble NA NA 0% 0 days 3 days $0.00 0 hrs 7 Test NA NA 0% 0 days 2 days $0.00 0 hrs

Note that the software automatically calculates the percent complete and actual fin- ish, cost, and work. In some cases you will have to override these calculations if they are inconsistent with what actually happened. Be sure to check to make sure the infor- mation in this table is displayed the way you want it to be. The final step is to enter the current status date (March 7). You do so by clicking PROJECT ▸ PROJECT INFORMATION and inserting the date into the status date window.

STEP 2 ACCESSING PROGRESS INFORMATION MS Project provides a number of different options for obtaining progress information. The most basic information can be obtained from PROJECT ▸ REPORTS ▸ COSTS ▸ EARNED VALUE. You can also obtain this information from GANTT CHART view. Click VIEW ▸ TABLE ▸ MORE TABLES ▸ EARNED VALUE.

TABLE A13.2-1B Earned Value Table

ID Task Name PV EV AC SV CV EAC BAC VAC

2 Design Spec.s $20.00 $20.00 $20.00 $0.00 $0.00 $20.00 $20.00 $0.00 3 Shell & Power $15.00 $15.00 $25.00 $0.00 ($10.00) $25.00 $15.00 ($10.00) 4 Memory/Software $100.00 $70.00 $100.00 ($30.00) ($30.00) $153.85 $100.00 ($53.85) 5 Zoom System $35.00 $35.00 $25.00 $0.00 $10.00 $25.00 $35.00 $10.00 6 Assemble $0.00 $0.00 $0.00 $0.00 $0.00 $120.00 $120.00 $0.00 7 Test $0.00 $0.00 $0.00 $0.00 $0.00 $30.00 $30.00 $0.00 $170.00 $140.00 $170.00 ($30.00) ($30.00) $373.85 $320.00 ($53.85)

When you scale this table to 80 percent you can obtain all the basic CV, SV and VAC information on one convenient page. Note: Some versions of MS Project use the old acronyms:

BCWS = PV BCWP = EV ACWP = AC

and the EAC is calculated using the CPI and is what the text refers to as EACf.

Chapter 13 Progress and Performance Measurement and Evaluation 513

STEP 3 ACCESSING CPI INFORMATION To obtain additional cost information such as CPI and TCPI from the GANTT CHART view, click VIEW ▸ TABLE ▸ MORE TABLES ▸ EARNED VALUE COST INDICATORS, which will display the following information:

TABLE A13.2-1C Earned Value Cost Indicators Table

ID Task Name PV EV CV CV% CPI BAC EAC VAC TCPI

1 Digital Camera Prototype $170.00 $140.00 ($30.00) −21% 0.82 $320.00 $373.85 ($53.85) 1.2 2 Design Spec.s $20.00 $20.00 $0.00 0% 1 $20.00 $20.00 $0.00 3 Shell & Power $15.00 $15.00 ($10.00) −66% 0.6 $15.00 $25.00 ($10.00) 4 Memory/Software $100.00 $70.00 ($30.00) −42% 0.7 $100.00 $153.85 ($53.85) 5 Zoom System $35.00 $35.00 $10.00 28% 1.4 $35.00 $25.00 $10.00 6 Assemble $0.00 $0.00 $0.00 0% 0 $120.00 $120.00 $0.00 7 Test $0.00 $0.00 $0.00 0% 0 $30.00 $30.00 $0.00

Note: For MS Project 2007 users the instructions are very similar except you can access the Tables option directly from Gantt View.

STEP 4 ACCESSING SPI INFORMATION To obtain additional schedule information such as SPI from the GANTT CHART view, click VIEW ▸ TABLE ▸ MORE TABLES ▸ EARNED VALUE SCHEDULE INDICATORS, which will display the following information:

TABLE A13.2-1D Earned Value Schedule Indicators Table

ID Task Name PV EV SV SV% SPI

1 Digital Camera Prototype $170.00 $140.00 ($30.00) −18% 0.82 2 Design Spec.s $20.00 $20.00 $0.00 0% 1 3 Shell & Power $15.00 $15.00 $0.00 0% 1 4 Memory/Software $100.00 $70.00 ($30.00) −30% 0.7 5 Zoom System $35.00 $35.00 $0.00 0% 1 6 Assemble $0.00 $0.00 $0.00 0% 0 7 Test $0.00 $0.00 $0.00 0% 0

STEP 5 CREATING A TRACKING GANTT CHART You can create a tracking Gantt chart like the one presented in Figure 13.1 by simply clicking TASK ▸ GANTT CHART (upper left hand corner) ▸ TRACKING GANTT ▸ TRACKING GANTT.

Tracking Gantt Chart Digital Camera Project

ID Task Name March 6 March 13

1 Digital Camera Prototype Design Spec.s

M T W T F S S M T W T F S S M WT

0% 0%

Shell & Power Memory/Software Zoom System Assemble Test

2 3 4 5 6 7

100%

67%

61%

100%

100%

FIGURE A13.2-1 Tracking Gantt Chart

514

Project Closure

LEARNING OBJECTIVES After reading this chapter you should be able to:

14-1 Identify different types of project closure.

14-2 Understand the challenges of closing out a project.

14-3 Explain the importance of a project audit.

14-4 Know how to use project retrospectives to obtain lessons learned.

14-5 Assess level of project management maturity.

14-6 Provide useful advice for conducting team performance reviews.

14-7 Provide useful advice for conducting performance reviews of project members.

OUTLINE 14.1 Types of Project Closure

14.2 Wrap-up Closure Activities

14.3 Project Audits

14.4 Post-Implementation Evaluation

Summary

Appendix 14.1: Project Closeout Checklist

Appendix 14.2: Euro Conversion

C H A P T E R F O U R T E E N

14

515

Those who cannot remember the past are condemned to relive it. —George Santayana, 1863–1952

Every project comes to an end eventually. But how many project participants get excited about closing out a project? The deliverables are complete. Ownership is ready to be transferred. Everyone’s focus is what’s next—hopefully a new, exciting project. Carefully managing the closure phase is as important as any other phase of the project. Observation tells us that organizations that manage closure and review well prosper. Those who don’t tend to have projects that drag on forever and repeat the same mistakes over and over.

Closing out a project includes a daunting number of tasks. In the past and on small projects the project manager was responsible for seeing all tasks and loose ends were completed and signed off. This is no longer true. In today’s project-driven organiza- tions that have many projects occurring simultaneously, the responsibility for complet- ing closure tasks has been parsed among the project manager, project teams, project office, an oversight “review committee,” and an independent retrospective facilitator. Many tasks overlap, occur simultaneously, and require coordination and cooperation among these stakeholders.

Project networks

6

Managing risk 7

Monitoring progress

13

Teams 11

Outsourcing 12

Project manager

10

Strategy 2

Introduction 1

Organization 3

Schedule resources & costs

8

Intern ation

al

proje cts

15

Agile PM 16

Project closure

14

Estimate 5

Reducing duration

9

Define project

4

516 Chapter 14 Project Closure

The three major deliverables for project closure are described below (see Figure 14.1): 1. Wrapping up the project. The major wrap-up task is to ensure the project is approved

and accepted by the customer. Other wrap-up activities include closing accounts, paying bills, reassigning equipment and personnel, finding new opportunities for project staff, closing facilities, and the final report. Checklists are used extensively to ensure tasks are not overlooked. In many organizations, the lion’s share of closure tasks is largely done by the project office in coordination with the project manager. The final report writing is usually assigned to one project office staff member, who assembles input from all stakeholders. In smaller organizations and projects, these closure activities are left to the project manager and team.

2. Project audit. Audits are post-project reviews of how successful the project was. They include causal analysis and thorough retrospectives which identify lessons learned. These post-project reviews should be held with the team and key stakehold- ers to catch any missing issues or gaps.

3. Evaluation of performance and management of the project. Evaluation includes team, individual team members, and project manager performance. Vendors and the customer may provide external input. Evaluation of the major players provides important information for the future. This chapter begins with the recognition that projects are shut down for many rea-

sons. Not all projects end with a clear “Finished” and are turned over to a customer. Regardless of the conditions for ending a project, the general process of closure is similar, though the endings may differ significantly. Wrap-up closure tasks are noted first. These tasks represent all the tasks that must be “cleaned up” before the project is terminated. Project audits are examined next. Finally, evaluation of individual and team performance is examined.

14.1 Types of Project Closure On some projects the end may not be as clear as would be hoped. Although the scope statement may define a clear ending for a project, the actual ending may or may not correspond. Fortunately, a majority of projects are blessed with a well-defined ending. Regular project reviews will identify projects having endings different from plans. The different types of closure are identified here: Normal The most common circumstance for project closure is simply a completed project. For many development projects, the end involves handing off the final design to production and the creation of a new product or service line. For other internal IT

14-1LO Identify different types of project closure.

FIGURE 14.1 Project Closure and Review Deliverables

Project archives/database

Facilities Customer Vendors Report

Wrap-up closure activities

Project closure deliverables

Team evaluation

Individual evaluations

Performance evaluation

Report Retrospective Lessons Learned

Project audit

Chapter 14 Project Closure 517

projects, such as system upgrades or creation of new inventory control systems, the end occurs when the output is incorporated into ongoing operations. Some modifications in scope, cost, and schedule probably occurred during implementation.

Premature For a few projects, the project may be completed early with some parts of the project eliminated. For example, in a new product development project, a market- ing manager may insist on production models before testing:

Give the new product to me now, the way it is. Early entry into the market will mean big profits! I know we can sell a bazillion of these. If we don’t do it now, the opportunity is lost!

The pressure is on to finish the project and send it to production. Before succumbing to this form of pressure, the implications and risks associated with this decision should be carefully reviewed and assessed by senior management and all stakeholders. Too frequently, the benefits are illusory, dangerous, and carry large risks.

Perpetual Some projects never seem to end. The major characteristic of this kind of project is constant “add-ons,” suggesting a poorly conceived project scope. At some point the review group should recommend methods for bringing final closure to this type of project or the initiation of another project. For example, adding a new feature to an old project could replace a segment of a project that appears to be perpetual.

Failed Project Failed projects are usually easy to identify and easy for a review group to close down. However, every effort should be made to communicate the technical (or other) reasons for termination of the project; in any event project participants should not be left with an embarrassing stigma of working on a project that failed. Many projects will fail because of circumstances beyond the control of the project team. See Snapshot from Practice 14.1: The Wake, for a novel response to a canceled project.

Sally worked as a project manager for a high-tech electronics firm in the late eighties. The company had patented the use of “bubble ink” technology for color printing. She was in charge of a

team tasked with cutting the prohibitive cost of print- ers in half. If successful significant bonuses would be earned and several team members would be given key positions when the product went into production. The team had overcome several difficult technical challenges and was well on its way to accomplishing their objective when the project was canceled. Top management discovered at a trade show that several competitors were about to introduce ink jet printers at a cost one-fifth the price of the printers Sally’s team was developing. What could Sally say to her team? Sally knew they would be devastated. She knew she had to do

something to help them deal with this bitter disap- pointment. So she decided to hold a traditional Irish “wake” for the project. She persuaded management to hire a backhoe to dig a grave in the back yard of their office and purchase an actual coffin. After she and other members gave a brief eulogy about the proj- ect, each member dropped something from the proj- ect into the coffin. For some members it was a piece of a printer prototype, for others it was a memo or a plan. One by one each member put something personal in the coffin. After the coffin was buried, the team retreated to a local brew pub to imbibe and share fond memories of the work they had accomplished. The “wake” became part of the company’s folklore and team members still laugh about the experience.

S N A P S H O T F R O M P R A C T I C E 1 4 . 1 The Wake1

1A wake is a party in honor of deceased that usually involves the consumption of alcohol.

518 Chapter 14 Project Closure

Changed Priority Organizations’ priorities often change and strategy shifts direc- tions. For example, during the 2008–10 financial crisis organizations shifted their focus from money-making projects to cost savings projects. The oversight group continually revises project selection priorities to reflect changes in organizational direction. Proj- ects in process may need to be altered or canceled. Thus, a project may start with a high priority but see its rank erode or crash during its project life cycle as conditions change. When priorities change, projects in process may need to be altered or canceled.

Different types of project termination present unique issues. Some adjustments to generic closure processes may be necessary to accommodate the type of project termi- nation you face.

14.2 Wrap-up Closure Activities The major challenges for the project manager and team members are over. Getting the project manager and project participants to wrap up the odds and ends necessary to fully complete a project is often difficult. It’s like the party is over—now who wants to help clean up? Much of the work is mundane and tedious. Motivation can be the chief challenge. For example, accounting for equipment and completing final reports are perceived as dull administrative tasks by project professionals who are action-oriented individuals. The project manager’s challenge is to keep the project team focused on the remaining project activities and delivery to the customer until the project is complete. Communicating a closure and review plan and schedule early allows the project team to (1) accept the psychological fact the project will end and (2) prepare to move on. The ideal scenario is to have the team member’s next assignment ready when project com- pletion is announced. Project managers need to be careful to maintain their enthusiasm for completing the project and hold people accountable to deadlines, which are prone to slip during the waning stages of the project.

Implementing the closure process includes several wrap-up activities. Many organi- zations develop lengthy lists for closing projects as they gain experience. These are very helpful and ensure nothing is overlooked. Implementing closedown includes the following six major activities: 1. Getting delivery acceptance from the customer. 2. Shutting down resources and releasing to new uses. 3. Reassigning project team members. 4. Closing accounts and seeing all bills are paid. 5. Delivering the project to the customer. 6. Creating a final report. Administering the details of closing out a project can be intimidating. Some organiza- tions have checklists of over 100 wrap-up tasks! These checklists deal with closure details such as facilities, teams, staff, customer, vendors, and the project itself. A par- tial administrative closure checklist is shown in Table 14.1.

Getting delivery acceptance by the customer is a major and critical closure activity. Delivery of some projects to the customer is straightforward. Others are more complex and difficult. Ideally there should be no surprises. This requires a well-defined scope and an effective change management system with active customer involvement. User involvement is critical to acceptance (see Snapshot from Practice 14.2: New Ball Goes Flat in the NBA).

14-2LO Understand the challenges of closing out a project.

Chapter 14 Project Closure 519

TABLE 14.1 Wrap-up Closure Checklist

Completed? Task Yes/No

Team

1 Has a schedule for reducing project staff been developed and accepted? 2 Has staff been released or notified of new assignments? 3 Have performance reviews for team members been conducted? 4 Has staff been offered outplacement services and career

counseling activities?

Vendors/contractors

5 Have performance reviews for all vendors been conducted? 6 Have project accounts been finalized and all billing closed?

Customer/Users

7 Has the customer signed-off on the delivered product? 8 Has an in-depth project review and evaluation interview with the

customer been conducted? 9 Have the users been interviewed to assess their satisfaction with

the deliverables? With the project team? With vendors? With training? With support? With maintenance?

Equipment and facilities

10 Have project resources been transferred to other projects? 11 Have rental or lease equipment agreements been closed out? 12 Has the date for the closure review been set and stakeholders notified?

Attach comments or links on any tasks you feel need explanation.

The conditions for completing and transferring the project should be set before the project begins. A completed software program is a good example of the need to work out the details in advance. If the user has problems using the software, will the cus- tomer withhold final payments? Who is responsible for supporting and training the user? If these conditions are not clearly defined up front, getting delivery acceptance can be troublesome.

Another delivery tactic (briefly mentioned in Chapter 7) for a project that has been outsourced is known as build, own, operate, and transfer (BOOT). In this type of proj- ect the contractor builds, owns, and operates the project deliverable for a set period of time. For example, Haliburton will operate a hydro-electric plant for six months before turning over operations to their Indian counterparts. During this time all the bugs are worked out and conditions for delivery are satisfied. Again, note the delivery condi- tions need to be carefully set up before the project begins; if not, wrap-up activities can develop a life of their own.

Releasing the project team typically occurs gradually during the closure phase. For some people, termination of their responsible activities ends before the project is deliv- ered to the customer or user. Reassignment for these participants needs to take place well before the final finish date. For the remaining team members (full or part time), termination may result in a new project or returning to their functional job. Sometimes, on product development efforts, team members will be assigned to operations positions and play an active role in the production of the new product. For contract people it may mean the end of their assignment to this project; in some cases there may be follow-up work or user support possibilities. A small number of part-time participants may be recommended to the user organization to train or operate new equipment or systems.

520 Chapter 14 Project Closure

On October 31, 2006, the National Basketball Association (NBA) opened its 57th season with new official game balls. The new ball, manufactured by Spalding, featured a new design and a

new material that together were believed to offer bet- ter grip, feel, and consistency than the previous leather ball. The material is microfiber composite with moisture management that provides superior grip and feel throughout the course of a game. Additionally, the new composite material eliminates the need for a break-in period, which is necessary for the current leather ball, and achieves consistency from ball to ball. The NBA and Spalding subjected the ball to a rigor- ous evaluation process that included laboratory and on-court testing process. Every NBA team received the new ball and had the opportunity to use it in practice. The ball was also tested in the NBA summer develop- ment league. At the press conference announcing the shift from leather to microfiber balls, NBA commissioner David Stern pronounced, “The advancement that Spalding has made to the new game ball ensures that the best basketball players in the world will be playing with the best basketball in the world.” Animal rights advocates applauded the shift from leather to microfiber. Such was not the case for the play- ers who would actually use the new ball. Grumblings emerged immediately when training camps opened in October. Washington Wizards guard Gilbert Arenas said the new basketball “gets slippery” when it comes in contact even with small amounts of sweat. Then Miami Heat center Shaquille O’Neil said, “It feels like one of those cheap balls that you buy at a toy store.” Some players, including league MVP Steve Nash, began complaining that the new ball was producing small cuts on their hands. “It’s awful [the friction burns], its like an irritant . . . sometimes I even have to tape my fingers in practice.” Perhaps LeBron James from the Cleveland Cavaliers best summed up the players’ attitudes toward the NBA’s introduction of the new ball when he said, “You

S N A P S H O T F R O M P R A C T I C E 1 4 . 2 New Ball Goes Flat in the NBA*

can change the dress code, you can make our shorts shorter, but when you take our basketball away from us, that’s not a transition we can handle.” On December 1, 2006, four weeks into the season, the NBA players union filed an unfair labor practice suit because the league management switched to the new ball without consulting the players. Ten days later, the NBA announced that they would revert back to the old leather ball beginning January 1, 2007. In a terse state- ment, Commissioner David Stern said, “Our players’ response to this particular composite ball has been over- whelmingly negative and we are acting accordingly.” The failure to check with the players (the end-users) and get buy-in for the new basketball was loudly criti- cized by the press. “How they could actually even get it that far and not have run it by the players is just an amaz- ing, amazing exercise in ineptitude,” Rob Frankel, a Los Angeles–based branding expert told Bloomberg News.

© Ingram Publishing/Alamy

* “NBA Introduces New Game Ball,” www.nba.com/news, posted 6-28-2006; Howard Bloom, “The NBA--Uneventful 2006 II,” Sports Business News, www.sportsbixnews .blogspot.com, 12-30-2006.

Since many work invoices are not submitted until after the project is officially over, closing out contracts is often messy and filled with untied ends. For example, it is improbable all invoices have been finalized, billed, and paid. Further, when contractors are used, there is a need to verify that all the contracted work has been done. Keeping contract records, such as progress reports, invoices, change records, and payment records, is important should a compliance or lawsuit occur. Too often in the haste to

Chapter 14 Project Closure 521

meet deadlines, paperwork and record keeping gets short-changed, only to create major headaches when it comes time for final documentation.

There are many more wrap-up activities; it is important to complete all of them. Experience has proved time and again that not doing all the little cleanup tasks well will create problems later. Two other examples of closure checklists are shown in this chapter: Appendix 14.1 presents an example used by the state of Virginia; and Appen- dix 14.2 presents an abridged closure checklist for the Euro Conversion project.

A final wrap-up activity is some form of celebration. For successful projects, an upbeat, festive celebration brings closure to the enjoyable experiences everyone has had and the need to say good-bye. Celebration is an opportunity to recognize the effort proj- ect stakeholders contributed. Even if the project did not reach its objectives, recognize the effort involved and goals that were achieved. If the project was a success, invite everyone who in some way contributed to project success. Thank the team and each one individually. The spirit of the celebration should be one in which the stakeholders are thanked for a job well done and leave with a good feeling of accomplishment.

14.3 Project Audits Project audits are more than the status reports suggested in Chapter 13, which report on project performance. Project audits do use performance measures and forecast data. But project audits are more inclusive. Project audits not only examine project success but also review why the project was selected. Project audits include a reassessment of the project’s role in the organization’s priorities. Project audits include a check on the organizational culture to ensure it facilitates the type of project being implemented. Project audits assess if the project team is functioning well and is appropriately staffed. Audits of projects in process should include a check on external factors that might change where the project is heading or its importance—for example, technology, gov- ernment laws, competitive products. Project audits include a review of all factors relevant to the project and to managing future projects.

Project audits can be performed while a project is in process and after a project is completed. There are only a few minor differences between these audits. ∙ In-process project audits. Project audits early in projects allow for corrective

changes, if they are needed, on the audited project or others in progress. In-process project audits concentrate on project progress and performance and check if condi- tions have changed. For example, have priorities changed? Is the project mission still relevant? In rare cases, the audit report may recommend closure of a project that is in process.

∙ Postproject audits. These audits tend to include more detail and depth than in- process project audits. Project audits of completed projects emphasize improving the management of future projects. These audits are more long-term oriented than in-process audits. Postproject audits do check on project performance, but the audit represents a broader view of the project’s role in the organization; for example, were the strategic benefits claimed actually delivered?

The depth and detail of the project audit depend on many factors. Some are listed in Table 14.1. Because audits cost time and money, they should include no more time or resources than are necessary and sufficient. Early in-process project audits tend to be perfunctory unless serious problems or concerns are identified. Then, of course, the audit would be carried out in more detail. Because in-process project audits can be

14-3LO Explain the importance of a project audit.

522 Chapter 14 Project Closure

worrisome and destructive to the project team, care needs to be taken to protect project team morale. The audit should be carried out quickly, and the report should be as posi- tive and constructive as possible. Postproject audits are more detailed and inclusive and contain more project team input.

In summary, plan the audit, and limit the time for the audit. For example, in post- project audits, for all but very large projects, a one-week limit is a good benchmark. Beyond this time, the marginal return of additional information diminishes quickly. Small projects may require only one or two days and one or two people to conduct an audit.

The priority team functions well in selecting projects and monitoring perfor- mance—cost and time. However, reviewing and evaluating projects and the process of managing projects is usually delegated to independent audit groups. Each audit group is charged with evaluating and reviewing all factors relevant to the project and to man- aging future projects. The outcome of the project audit is a report.

The Project Audit Process Below are guidelines that should be noted before you conduct a project audit. The guidelines below will improve your chances for a successful audit.

Guidelines for Conducting a Project Audit 1. First and foremost, the philosophy must be that the project audit is not a witch hunt. 2. Comments about individuals or groups participating in the project should be mini-

mized. Keep to project issues, not what happened or by whom. 3. Audit activities should be intensely sensitive to human emotions and reactions. The

inherent threat to those being evaluated should be reduced as much as possible. 4. Accuracy of data should be verifiable or noted as subjective, judgmental, or

hearsay. 5. Senior management should announce support for the project audit and see that the

audit group has access to all information, project participants, and (in most cases) project customers.

6. The attitude toward a project audit and its aftermath depends on the modus operandi of the audit leadership and group. The objective is not to prosecute. The objective is to learn and conserve valuable organization resources where mistakes have been made. Friendliness, empathy, and objectivity encourage cooperation and reduce anxiety.

7. The audit should be completed as quickly as is reasonable. With these guidelines in mind, the process of the project audit is conveniently divided into three steps: initiation and staffing, data collection and analysis, and reporting. Each step is briefly discussed next.

Step 1: Initiation and Staffing Initiation of the audit process depends primarily on organization size and project size along with other factors. In small organizations and projects where face-to-face contact at all levels is prevalent, an audit may be informal and only represent another staff meet- ing. But even in these environments the content of a formal project audit should be examined and covered with notes made of the lessons learned. In medium-sized organi- zations with few projects the audit is likely to be conducted by someone from manage- ment with project management experience. In large companies or organizations with many projects the audit is under the purview of the project office (see Snapshot from Practice 14.3: The Project Office).

Chapter 14 Project Closure 523

As more and more companies embrace project management as a critical vehi- cle for realizing corporate objectives, they are creating centralized project offices (POs) to oversee and improve

the management of projects. PO functions vary widely by organization and need. In some cases, they serve as a simple clearinghouse for project management infor- mation. In other cases, they recruit, train, and assign managers to specific projects. As POs mature and evolve over time, they become full-service providers of project management expertise within a firm. The differ- ent services POs may provide include the following:

- agement information system.

within and outside the organization.

reporting methodologies.

- niques and tools.

programs.

and mentoring services.

containing critical documents, including project plans, funding papers, test plans, audit reports, and so forth.

project management.

within an organization.

A good example of how project offices evolve is the global project office (GPO) at Citibank’s Global Corpo- rate Bank. GPO originated at the grassroots level within the small world of Operations and Technology for Global Cash Management. Committed to bringing order to the chaos of managing projects, GPO insti- tuted training programs and professional project management practices on a very small scale. Soon the success of GPO-supported projects caught the eye of upper management. Within three years the department was expanded to offer a full range of PO services across Citibank’s entire banking operation. GPO’s mission is to establish project management as a core competency throughout the entire Citibank organization.

S N A P S H O T F R O M P R A C T I C E 1 4 . 3 The Project Office*

© Xavier Arnau/Getty Images

*T. R. Block and J. D. Frame, “Today’s Project Office: Gauging Attitudes,” PM Network, August 2001; W. Gradante and D. Gardner, “Managing Projects from the Future, Not from the Past,” Proceedings of the 29th Annual Project Management Institute 1998 Seminars and Symposium (Newtown Square, PA: Project Management Institute, 1998), pp. 289–94.

A major tenet of the project audit is that the outcome must represent an indepen- dent, outside view of the project. Maintaining independence and an objective view is difficult, given that audits are frequently viewed as negative by project stakehold- ers. Careers and reputations can be tarnished even in organizations that tolerate mistakes. In less forgiving organizations, mistakes can lead to termination or exile to less significant regions of an organization. Of course, if the result of an audit is favorable, careers and reputations can be enhanced. Given that project audits are susceptible to internal politics, some organizations rely on outside consulting firms to conduct the audits.

524 Chapter 14 Project Closure

Step 2: Data Collection and Analysis Each organization and project is unique. Therefore, the specific kinds of information that will be collected will depend upon the industry, project size, newness of technol- ogy, and project experience. These factors can influence the nature of the audit. However, information and data are gathered to answer questions similar to those suggested next.

Organization View

1. Was the organizational culture supportive and correct for this type of project? Why? Why not?

2. Was senior management’s support adequate? 3. Did the project accomplish its intended purpose? 4. Were the risks for the project appropriately identified and assessed? Were contin-

gency plans used? Were they realistic? Have risk events occurred that have an impact greater than anticipated?

5. Were the right people and talents assigned to this project? 6. What does evaluation from outside contractors suggest? 7. Were the project start-up and hand-off successful? Why? Is the customer satisfied?

Project Team View

1. Were the project planning and control systems appropriate for this type of project? Should all similar size and type of projects use these systems? Why/why not?

2. Did the project conform to plan? Is the project over or under budget and schedule? Why?

3. Were interfaces and communications with project stakeholders adequate and effective?

4. Did the team have adequate access to organizational resources—people, budget, support groups, equipment? Were there resource conflicts with other ongoing projects?

5. Was the team managed well? Were problems confronted not avoided? The audit group should not be limited to these questions. The audit group should include other questions related to their organization and project type—e.g., research and development, marketing, information systems, construction, facilities. The generic questions above, although overlapping, represent a good starting point and will go a long way toward identifying project problem and success patterns.

Step 3: Reporting The major goal of the audit report is to improve the way future projects are managed. Succinctly, the report attempts to capture needed changes and lessons learned from a current or finished project. The report serves as a training instrument for project man- agers of future projects.

Audit reports need to be tailored to the specific project and organizational environ- ment. Nevertheless, a generic format for all audits facilitates development of an audit database and a common outline for those who prepare audit reports and the managers who read and act on their content. A very general outline common to those found in practice is as follows:

Chapter 14 Project Closure 525

1. Classification The classification of projects by characteristics allows prospective readers and project managers to be selective in the use of the report content. Typical classification categories include the following: ∙ Project type—e.g., development, marketing, systems, construction. ∙ Size—monetary. ∙ Number of staff. ∙ Technology level—low, medium, high, new. ∙ Strategic or support. Other classifications relevant to the organization should be included.

2. Analysis The analysis section includes succinct, factual review statements of the project. For example, ∙ Project mission and objectives. ∙ Procedures and systems used. ∙ Organization resources used. ∙ Outcomes achieved

3. Recommendations Usually audit recommendations represent major corrective actions that should take place. See, for example, Snapshot from Practice 14.4: Lessons Learned from Katrina. Audit recommendations are often technical in nature and focus on solutions to problems that surfaced. For example, to avoid rework, the report of a construction project recommended shifting to a more resilient building material. In other cases, recommendations may include terminating or sustaining vendor or con- tractor relationships.

4. Lessons Learned These do not have to be in the form of recommendations. Lessons learned serve as reminders of mistakes easily avoided and actions easily taken to ensure success. In practice, new project teams reviewing audits of past projects similar to the one they are about to start have found audit reports very useful. Team members will frequently remark later, “The recommendations were good, but the ‘lessons learned’ section really helped us avoid many pitfalls and made our project implementa- tion smoother.” It is precisely this reason that lessons learned in the form of project retrospectives have taken on greater prominence and warrant further discussion. See Snapshot from Practice 14.5: Operation Eagle Claw.

5. Appendix The appendix may include backup data or details of analysis that would allow others to follow up if they wish. It should not be a dumping ground used for filler; only critical pertinent information should be attached.

Project Retrospectives The term retrospective has emerged in recent years to denote specific efforts at iden- tifying lessons learned on projects. Proponents believe that the traditional audit pro- cess focuses too much on project success and evaluation which interferes with the surfacing and transferal of important lessons learned. They advocate a separate effort toward capturing lessons learned. In many ways this effort mirrors the auditing process. Typically, an independent, trained facilitator acts as a guide who leads the project team through an analysis of project activities that went well, what needs improve- ments, and development of follow-up action plan with goals and accountability. This

14-4LO Know how to use project retrospectives to obtain lessons learned.

526 Chapter 14 Project Closure

On August 25, 2005, winds of 145 miles per hour and rains covered 80 percent of New Orleans with some areas under 20 feet of water. Hurri- cane Katrina dispersed havoc on

every corner of New Orleans. In its trail it left over 1,300 people dead in Louisiana and Mississippi. Katrina will long be remembered as the costliest and most deadly hurricane ever recorded in the United States. Response came from many different groups within the country and from other countries. Katrina also drew the largest response of The National Guard to a national emergency in history. Governors from every state sent National Guard troops to support and assist the state of Mississippi. By September 8, 51,000 troops were responding to the emergency. Many other nonprofit groups offered help in a variety of ways—food, shelter, financial, health care, and transportation. Groups that contributed support have reviewed their efforts to see what lessons learned can be used to improve future emergency efforts. The results of the review of The National Guard efforts follow here: Three of the key lessons from The National Guard retrospective are described.

Lack of equipment was one of the biggest prob- lems—especially communication equipment. Ability to communicate among the many different support groups (e.g., civilian and military) was thwarted by incompatible systems or simple lack of availability.

Action Item: $1.3 billion has been authorized for new equipment that is compatible across major emergency groups.

S N A P S H O T F R O M P R A C T I C E 1 4 . 4 Lessons Learned from Katrina*

Lack of protocols and standardization of reports, graphics, and communication caused delays and poor coordination among the many support groups.

Action Item: A single standard protocol for all states is now being applied.

The National Guard is under state control. Guard troops integrated quickly into the host-state com- mand structures and cooperation ensued.

Action Item: Maintain status quo.

Because Guard soldiers are controlled by the states, they were empowered to enforce civil laws, something federal troops are prohibited from doing, except under the provisions of the insurrection laws. Fortunately, coordination and cooperation among state and federal troop command work reasonably well. However, the federal agencies (e.g., Homeland Security) need to incorporate the Guard into planning and preparation for the federal response to catastrophic disasters. Lessons learned from the Katrina disaster are not limited to the military. Almost every agency and sup- port group, such as individuals, communities, churches, and other groups, has developed lessons learned from their project response experience. For example, the Red Cross and state guard have better plans for han- dling thousands of people problems involving shelter, evacuation, and medical assistance. These lessons learned from Katrina are ready to go and should be enormously helpful in future hurricane situations.

*Les A. Melnyk, “Katrina Lessons Learned,” Soldiers Magazine, June 20, 2006 and “Lessons Learned from Katrina: Preparing Your Institution for a Catastrophic Event.” Federal Deposit Insurance Corporation is the source of this information. 1/20/08

facilitator may come from the project office or be an external consultant. Wherever this individual comes from, it is critical that she or he be perceived as being indepen- dent and unbiased.

In retrospecitive methodology, the facilitator uses several questionnaires to conduct post-project audits. These surveys focus not only on project operations, but also on how the organization’s culture impacted project success and failures. Table 14.2 provides a sampling of the former while Table 14.3 provides a sample of the latter.

With survey information in hand, the facilitator visits one-on-one with project team members, project manager, and other stakeholders to dive deeper into cause-effect impacts. For example, the facilitator may discover that one of the primary reasons for lack of timely decision making and poor coordination between groups was that team members were bombarded with too much information and had a difficult time sorting through what was critical and what could be ignored.

Chapter 14 Project Closure 527

Armed with the information gleaned from one-on-one sessions and other sources, the facilitator leads a team retrospective session. The session first reviews the facilita- tor’s report and attempts to add key information. So with regard to the information overload problem, team members not only identify failure to flag critical information, but also a tendency to “cc” everyone just in case. The facilitator works with the team to develop a system that not only prioritizes information, but also does it according to who needs to receive it.

On November 4, 1979, a mob in Iran stormed the U.S. Embassy and took 52 Americans hostage. After six months of failed negotiation, the green light was given to execute Operation Eagle

Claw, a joint military effort to free the hostages. The plan called for eight Navy RH-53D helicopters to fly 600 miles to a remote site in Iran, code named Desert One. Under the cover of darkness, the helicop- ters would be refueled by KC-130 tankers. The helicop- ters would then fly the assault force to a spot near the outskirts of Teheran where they would meet up with special agents already in the country. The agents would lead them to a safe house to await the assault on the embassy the next night. Upon rescuing the hos- tages, the assault team would escort them to a nearby airfield that had already been secured by a second assault team where they would be flown to safety. What actually happened was far different from what was planned. The helicopter pilots were ordered to fly at or below 200 feet to avoid radar. This caused them to run into “haboobs” or dust storms. Two helicopters mal- functioned and turned back. The remainder battled the dust storms and arrived at Desert One one hour late. The rescue attempt was dealt its final blow when it was discovered that a third helicopter had a hydraulic leak and was inoperable. Only five aircraft were serviceable and six were needed, so the mission had to be aborted. Things got worse when one of the helicopters moved into position to refuel and collided with a KC-130 plane. Both aircraft burst into flames. All told, eight soldiers died and dozens were injured. The Iranians scattered the hostages around the country afterward, making any further rescue attempts impossible. Given the gravity of the situation, a special six- member commission was appointed by the Joint Chiefs of Staff to conduct a review of the project. They identified a number of issues that contributed to the failure. One

issue was the selection of the air crews. Given the sig- nificance of the mission, each military service wanted to be involved. Navy and Marine pilots with little experi- ence in long-range overland navigation or refueling were chosen though more than one hundred experi- enced Air Force pilots were available. Another issue was the lack of a comprehensive mission rehearsal pro- gram. From the beginning, training was not conducted in a truly joint manner; it was compartmentalized by service and held in different locations across the United States. The limited rehearsals that were conducted assessed only segments of the total mission. The commission concluded that 10 and perhaps 12 helicopters should have been launched to guarantee the minimum six required for mission completion. Finally, the hopscotch method for ground refueling was criticized. If planners had chosen en-route fueling, the entire Desert One scenario could have been avoided. The final report contained several important lessons learned that have contributed to successful subsequent missions, includ- ing the one against Osama bin Laden in 2011.

S N A P S H O T F R O M P R A C T I C E 1 4 . 5 Operation Eagle Claw*

© Michael OchsArschives/Stringer/Getty

* D. M. Giangreco and T. A. Griswold, Delta: America’s Elite Counter-terrorist Force (New York: Motorbooks International, 1992).

528 Chapter 14 Project Closure

TABLE 14.2 Project Process Review Questionnaire

Item Comments

1. Were the project objectives and strategic intent of the project clearly and explicitly communicated?

2. Were the objectives and strategy in alignment? 3. Were the stakeholders identified and included in

the planning? 4. Were project resources adequate for this project? 5. Were people with the right skill sets assigned to this project? 6. Were time estimates reasonable and achievable? 7. Were the risks for the project appropriately identified and

assessed before the project started? 8. Were the processes and practices appropriate for this type

of project? Should projects of similar size and type use these systems? Why/why not?

9. Did outside contractors perform as expected? Explain. 10. Were communication methods appropriate and adequate

among all stakeholders? Explain. 11. Is the customer satisfied with the project product? 12. Are the customers using the project deliverables as

intended? Are they satisfied? 13. Were the project objectives met? 14. Are the stakeholders satisfied their strategic intents

have been met? 15. Has the customer or sponsor accepted a formal

statement that the terms of the project charter and scope have been met?

16. Were schedule, budget, and scope standards met? 17. Is there any one important area that needs to be reviewed

and improved upon? Can you identify the cause?

TABLE 14.3 Organizational Culture Review Questionnaire

Item Comments

1. Was the organizational culture supportive for this type of project?

2. Was senior management support adequate? 3. Were people with the right skills assigned to this project? 4. Did the project office help or hinder management of

the project? Explain. 5. Did the team have access to organizational resources

(people, funds, equipment)? 6. Was training for this project adequate? Explain. 7. Were lessons learned from earlier projects useful?

Why? Where? 8. Did the project have a clear link to organizational

objectives? Explain. 9. Was project staff properly reassigned? 10. Was the Human Resources Office helpful in finding

new assignments? Comment.

Chapter 14 Project Closure 529

Each lesson is assigned an owner, typically a team member who is very interested and familiar with the lesson. This team member/owner will serve as a contact point for anyone needing information (expertise, contacts, templates, etc.) relating to the lesson. This person often reports lessons learned to larger audiences within their organization that would benefit from the collective wisdom.

Not only is there a contact person, but lessons learned need to be documented and archived in a manner that makes them accessible and usable by others. Here the facilitator works with the Project Office to create repository that uses a sophisti- cated search engine that permits others to quickly sort through and access lessons specific to their needs. Failure to do so will produce a system that is undervalued and underutilized.

Project Audits: The Bigger Picture Individual audits or postproject retrospectives can yield valuable lessons and recom- mendations that team members can apply to future project work. When done on a consistent basis, they can lead to significant improvements in the processes and tech- niques that organizations use to complete projects. A more encompassing look from an organizationwide point of view is to use a project maturity model. The purposes of all maturity models (and there are many available) are to enable organizations to assess their progress in implementing the best practices in their industry and move to improve- ment. It is important to understand that the model does not ensure success; it only serves as a measuring stick and an indicator of progress.

The term maturity model was coined in the late 1980s from a research study by the United States government and the Software Engineering Institute (SEI) at Carnegie- Mellon University. The government wanted a tool to predict successful software devel- opment by contractors. The outcome of this research was the Capability Maturity Model (CMM). The model focuses on guiding and assessing organizations in imple- menting concrete best practices of managing software development projects. Since its development, the model is now used across all industries. Currently, over 2,400 orga- nizations around the world report their maturity progress to the Software Engineering Institute. (See website at http://www.sei.cmu.edu/activities/sema/profile.html.)

One newer model has received a great deal of publicity. In January 2004, after eight years of development, the Project Management Institute rolled out its second version of the “Organizational Project Maturity Model.” The latest version is called OPM3TM. (See www.pmi.org/opm3.) Typically, these models are divided into a continuum of growth levels: Initial, Repeatable, Defined, Managed, and Optimized. Figure 14.2 presents our version, which borrows liberally from other models. What we have tried to do is focus less on a process and more on the state an organization has evolved to in managing projects. Level 1: Ad Hoc Project Management No consistent project management process is in place. How a project is managed depends upon the individuals involved. Character- istics of this level include ∙ No formal project selection system exists—projects are done because people decide

to do them or because a high-ranking manager orders it done. ∙ How any one project is managed varies by individual—unpredictability. ∙ No investment in project management training is made. ∙ Working on projects is a struggle because it goes against the grain of established

policies and procedures.

14-5LO Assess level of project management maturity.

530 Chapter 14 Project Closure

Level 2: Formal Application of Project Management The organization applies established project management procedures and techniques. This level is often marked by tension between project managers and line managers, who need to redefine their roles. Features of this level include ∙ Standard approaches to managing projects including scope statements, WBS, activ-

ity lists are used. ∙ Quality emphasis is on the product or outcome of the project and is inspected

instead of built in. ∙ The organization is moving in the direction of stronger matrix with project manag-

ers and line managers working out their respective roles. ∙ Growing recognition of need for cost control, not just scope and time management, exists. ∙ There is no formal project priority system established. ∙ Limited training in project management is provided. Level 3: Institutionalization of Project Management An organizationwide project management system, tailored to specific needs of the organization with the flexibility to adapt the process to unique characteristics of the project, is established. Character- istics of this level include ∙ An established process for managing projects is evident by planning templates,

status report systems, and checklists for each stage of project life cycle. ∙ Formal criteria are used to select projects. ∙ Project management is integrated with quality management and concurrent

engineering. ∙ Project teams try to build in quality not simply inspect it. ∙ The organization is moving toward a team-based reward system to recognize project

execution. ∙ Risk assessment derived from WBS and technical analyses and customer input is

in place. ∙ The organization offers expanded training in project management.

FIGURE 14.2 Project Management Maturity Model

Time

Ad hoc project mgmt.

Formal application of project mgmt.

Institutionalization of project mgmt.

Management of project

mgmt. system

Optimization of project

mgmt. system

Level 1

Level 2

Level 3

Level 4

Level 5

Chapter 14 Project Closure 531

∙ Time-phased budgets are used to measure and monitor performance based on earned value analysis.

∙ A specific change control system for requirements, cost, and schedule is developed for each project, and a work authorization system is in place.

∙ Project audits tend to be performed only when a project fails. Level 4: Management of Project Management System The organization develops a system for managing multiple projects that are aligned with strategic goals of the orga- nization. Characteristics of this level include   ∙ Portfolio project management is practiced; projects are selected based on resource

capacity and contribution to strategic goals. ∙ A project priority system is established. ∙ Project work is integrated with ongoing operations. ∙ Quality improvement initiatives are designed to improve both the quality of the

project management process and the quality of specific products and services. ∙ Benchmarking is used to identify opportunities for improvement. ∙ The organization has established a Project Management Office or Center for

Excellence. ∙ Project audits are performed on all significant projects; lessons learned are recorded

and used on subsequent projects. ∙ An integrative information system is established for tracking resource usage and

performance of all significant projects.  Level 5: Optimization of Project Management System The focus is on continuous improvement through incremental advancements of existing practices and by innova- tions using new technologies and methods. Features include ∙ A project management information system is fine-tuned; specific and aggregate

information is provided to different stakeholders. ∙ An informal culture that values improvement drives the organization, not policies

and procedures. ∙ There is greater flexibility in adapting the project management process to demands

of a specific project. A major theme of this book is that the culture of the organization has a profound

impact on how project management methodology operates. Audits and performance evaluation require informed judgment. Good decision making depends not only on the accuracy of the information, but also on the right information. For example, imagine how much different your response might be if you made an honest mistake but did not trust management and felt insecure versus if you had confidence and trust in management. Or think how different the quality of information that would surface from a team would be where trust was divided versus a team that works in a Level 5 environment.

Progress from one level to the next will not occur overnight. The Software Engineering Institute estimates the following median times for movement:

Maturity level 1 to 2 is 22 months. Maturity level 2 to 3 is 19 months. Maturity level 3 to 4 is 25 months. Maturity level 4 to 5 is 13 months.

532 Chapter 14 Project Closure

Why does it take so long? One reason is simply organizational inertia. It is difficult for complex social organizations to institute significant changes while at the same time maintaining business efficacy. “How do we find time to change when we are so busy just keeping our heads above water?”

A second significant reason is that one cannot leapfrog past any one level. Just as a child cannot avoid the trials and tribulations of being a teenager by adopting all the lessons learned by his or her parents, people within the organization have to work through the unique challenges and problems of each level to get to the next level. Learning of this magnitude naturally takes time and cannot be avoided by using quick fixes or simple remedies. See Snapshot from Practice 14.6: 2015 PMO of the Year: Navy Federal Credit Union for how a PMO improved the maturity of project manage- ment operations at a large credit union.

14.4 Post-Implementation Evaluation The purpose of project evaluation is to assess how well the project team, team mem- bers, and project manager performed.

Team Evaluation Evaluation of performance is essential to encourage changes in behavior and to support individual career development and continuous improvement through organizational learning. Evaluation implies measurement against specific criteria. Experience corroborates that before commencement of a project, the stage must be set so

Provide useful advice for conducting team performance reviews.

14-6LO

Like many financial institutions, the Navy Federal Credit Union struggled with adapting IT technologies to bet- ter serve their over 5 million members. Navy Federal had no clear method of

prioritizing projects. Project execution processes were ad hoc. Delivery metrics weren’t being tracked. Doomed projects lingered, with no one willing to hit the kill button. In 2010 things began to change. Navy Federal began developing a team of project professionals who could advocate a standardized project delivery system as well as strategic alignment practices. In 2014 the IT department opened its project management office (PMO). The office was not greeted with open arms. The team had to work hard to avoid the perception that it was a document engine or needless bureaucracy. “Throughout our journey, we’ve certainly faced challenges in terms of buy-in and acceptance of proj- ect management,” says Kristin Earley, PMP, assistant vice president of the PMO. “We started with small wins. We had to highlight the demonstrated value that

S N A P S H O T F R O M P R A C T I C E 1 4 . 6 2015 PMO of the Year: Navy Federal Credit Union*

we brought in terms of consistent, repeatable delivery of projects.” The impact has been significant. The percentages of projects that closed according to plan jumped from 55 per- cent in 2014 to 88 percent in 2015. The PMO is now consid- ered an integral part of how Navy Federal does business and was recognized by the Project Management Institute as 2015 PMO of the year. While the initial push was to standardize project management processes, the PMO realized that not all projects are alike and some may benefit from less tra- ditional methods. “The PMO started with a one-size-fits-all approach to project delivery. We realized this really wasn’t the most effective way to work with our business partners to deliver value frequently throughout the project life cycle,” Ms. Earley says. “We’ve tailored our delivery practices to introduce both agile and incremental deliv- ery practices, and that’s helped us improve our delivery within the portfolio.”

*Gantz, J., “Mission Accomplished,” PM Network 29 (12) (December 2015), pp. 30–37.

If team evaluation is not done well in practice, how bad is it? Joseph Fusco surveyed 1,667 project managers representing 134 different projects. Fifty-two percent of the respondents

indicated their team received no collective evaluation of their team performance. Of the 22 percent who indicated their team was evaluated, further probing found their evaluation was informal, lasting little more than 20 minutes. This apparent lack of team evalua- tion practices may be sending the wrong signal.

Individual team members can slough off poor team performance by relying on the old saying, “I did my job.” Strong team evaluation practices need to empha- size team members are “in this together,” while minimizing individual performance. Nearly every com- pany in Fusco’s survey lacked an effective project management reward system.

Research Highlight 14.1 Measures of Team Performance*

* Joseph Fusco, “Better Policies Provide the Key to Implementing Project Management,” Project Management Journal, Vol. 28, No. 3, September 1997, p. 38.

533

expectations, standards, supportive organizational culture, and constraints are in place; if not, the effectiveness of the evaluation process will suffer.

In a macro sense, the evidence today suggests that performance evaluation is not done well. See Research Highlight 14.1: Measures of Team Performance. The major reasons cited by practitioners are twofold: 1. Evaluations of individuals are still left to supervisors of the team member’s home

department. 2. Typical measures of team performance center on time, cost, and specifications.

Most organizations do not go beyond these measures, although they are important and critical. Organizations should consider evaluating the team-building process, effectiveness of group decision and problem-solving processes, group cohesion, trust among team members, and quality of information exchanged. Measurement of cus- tomer and user satisfaction with project deliverables (i.e., the project results) is often missed completely. Yet, project success depends significantly on satisfying these two very important groups. The quality of the deliverables is the responsibility of the team.

Before an evaluation of the project team can be effective and useful, a minimum core of conditions needs to be in place before the project begins (see Chapter 11). Some typical conditions are listed here in the form of questions: 1. Do standards for measuring performance exist? (You can’t manage what you can’t

measure.) Are the goals clear for the team and individuals? Challenging? Attain- able? Lead to positive consequences?

2. Are individual and team responsibilities and performance standards known by all team members?

3. Are team rewards adequate? Do they send a clear signal that senior management believes that the synergy of teams is important?

4. Is a clear career path for successful project managers in place? 5. Is the team empowered to manage short-term difficulties? 6. Is there a relatively high level of trust emanating from the organizational culture? 7. Team evaluation should go beyond time, cost, and specifications. Are there criteria

beyond the constraint criteria? Creation of project deliverables would be a good place to start. The “characteristics of highly effective teams” from Chapter 11 can easily be adapted as measurements of team performance.

The “in-place conditions” will support any evaluation approach for teams and their members.

534 Chapter 14 Project Closure

In practice, the actual team evaluation process takes many forms—especially when evaluation goes beyond time, budget, and specifications. The typical mechanism for evaluation of teams is a survey administered by a consultant, a staff member from the human resources department, or through computer e-mail. The survey is normally restricted to team members, but in some cases, other project stakeholders interacting with the team may be included in the survey. An example of a partial survey is found in Table 14.4. After the results are tabulated, the team meets with the facilitator and/or senior management, and the results are reviewed.

This session is comparable to the team-building sessions described in Chapter 11, except that the focus is on using the survey results to assess the development of the team, its strengths and weaknesses, and the lessons that can be applied to future project work. The results of team evaluation surveys are helpful in changing behavior to better support team communication, the team approach, and continuous improvement of team performance.

Individual, Team Member, and Project Manager Performance Reviews Organizations vary in the extent to which their project managers are actively involved in the appraisal process of team members. In organizations where projects are man- aged within a functional organization, the team member’s area manager, not the project manager, is responsible for assessing performance. The area manager may solicit the project manager’s opinion of the individual’s performance on a specific project; this will be factored into the individual’s overall performance. In a balanced matrix, the project manager and the area manager jointly evaluate an individual’s performance. In project matrix and project organizations in which the lion’s share of the individual’s work is project related, the project manager is responsible for appraising individual performance. One process that appears to be gaining wider acceptance is the multi- rater appraisal or “360-degree feedback,” which involves soliciting feedback concern- ing team members’ performance from all the people their work affects. This would include not only project and area managers, but also peers, subordinates, and even customers. See Snapshot from Practice 14.7: The 360-Degree Feedback.

Performance appraisals generally fulfill two important functions. The first is devel- opmental in nature: the focus is on identifying individual strengths and weaknesses and developing action plans for improving performance. The second is evaluative and involves assessing how well the person has performed in order to determine salary or merit adjustments. These two functions are not compatible. Employees, in their eager- ness to find out how much pay they will receive, tend to tune out constructive feedback on how they can improve their performance. Likewise, managers tend to be more con- cerned with justifying their decision than engaging in a meaningful discussion on how

Provide useful advice for conducting performance reviews of project members.

14-7LO

Disagree Agree

Using the scale below, assess each statement. 1. The team shared a sense of common purpose,

and each member was willing to work toward achieving project objectives. 1 2 3 4 5

2. Respect was shown for other points of view. Differences of opinion were encouraged and freely expressed. 1 2 3 4 5

3. All interaction among team members occurred in a comfortable, supportive atmosphere. 1 2 3 4 5

TABLE 14.4 Sample Team Evaluation and Feedback Survey

Chapter 14 Project Closure 535

the employee can improve his or her performance. It is difficult to be both a coach and a judge. As a result, several experts on performance appraisal systems recommend that organizations separate performance reviews, which focus on individual improve- ment, and pay reviews, which allocate the distribution of rewards (cf., Romanoff, 1989; Latham and Wexley, 1993).

In some matrix organizations, project managers conduct the performance reviews, while area managers are responsible for pay reviews. In other cases, performance reviews are part of the project closure process, and pay reviews are the primary objec- tive of the annual performance appraisal. Other organizations avoid this dilemma by allocating only group rewards for project work and providing annual awards for indi- vidual performance. The remaining discussion is directed at reviews designed to improve performance because pay reviews are often outside the jurisdiction of the project manager.

Individual Reviews Organizations employ a wide range of methods to review individual performance on a project. In general, review methods of individual performance center on the techni- cal and social skills brought to the project and team. Some organizations rely simply on an informal discussion between the project manager and the project member. Other organizations require project managers to submit written evaluations that describe and assess an individual’s performance on a project. Many organizations use rating

More and more companies are discarding the traditional superior-subordinate performance feedback process and replacing it with 360-degree feedback systems. The 360-degree feedback

approach gathers behavioral observations from many sources within the organization and includes employee self-assessment. The individual completes the same structured evaluation process that superiors, project team members, peers and, in many cases, external customers use to evaluate a performance. Survey questionnaires, augmented by a few open-ended questions, are typically used to gather information. Summary results are compared against organiza- tional strategies, values, and business objectives. The feedback is communicated to the individual with the assistance of the company’s human resource depart- ment or an outside consultant. The technique is used by a growing number of firms including General Elec- tric, AT&T, Mobil Oil, Nabisco, Hewlett-Packard, and Warner-Lambert. The objective of the 360-degree process is to identify areas for individual improvement. When anon- ymous feedback solicited from others is compared

with the individual’s self-evaluations, the individual may form a more realistic picture of her or his strengths and weaknesses. This may prompt behav- ioral change if the weaknesses identified were previ- ously unknown to the individual. So, for example, a project manager who thinks he delegates work effec- tively finds out that subordinates disagree. This causes him to rethink how he delegates and to decide to del- egate more and sooner. Many firms obtain feedback from internal and external project customers. For example, a client may evaluate a project manager or member of the project team according to “How effectively does the individual get things done without creating unnecessary adver- sarial relationships?” Incorporating customer feedback in the evaluation process underscores collaboration and the importance of client expectations in determin- ing project success.

S N A P S H O T F R O M P R A C T I C E 1 4 . 7 The 360-Degree Feedback*

* Brian O’Reilly, “360 Feedback Can Change Your Life,” Fortune, October, 17, 1994, pp. 93–100; Robert Hoffman, “Ten Reasons You Should Be Using 360 Degree Feedback,” HR Magazine, April 1995, pp. 82–85; Dick Cochran, “Finally, a Way to Completely Measure Project Manager Performance,” PM Network, September 2000, pp. 75–80.

536 Chapter 14 Project Closure

scales similar to the team evaluation survey in which the project manager rates the individual according to a certain scale (i.e., from 1 to 5) on a number of relevant per- formance dimensions (i.e., teamwork, customer relations). Some organizations augment these rating schemes with behaviorally anchored descriptions of what consti- tutes a 1 rating, a 2 rating, and so forth. Each method has its strengths and weak- nesses, and, unfortunately, in many organizations the appraisal systems were designed to support mainstream operations and not unique project work. The bottom line is that project managers have to use as best they can the performance review system man- dated by their organization.

Regardless of the method, the project manager needs to sit down with each team member and discuss his or her performance. Here are some general tips for conducting performance reviews: ∙ Always begin the process by asking the individual to evaluate his or her contribu-

tions to the project. First, this approach may yield valuable information that you were not aware of. Second, the approach may provide an early warning for situations in which there is disparity in assessments. Finally, this method reduces the judg- mental nature of the discussion.

∙ Avoid, when possible, drawing comparisons with other team members; rather, assess the individual in terms of established standards and expectations. Compari- sons tend to undermine cohesion and divert attention away from what the individual needs to do to improve performance.

∙ When you have to be critical, focus the criticism on specific examples of behavior rather than on the individual personally. Describe in specific terms how the behav- ior affected the project.

∙ Be consistent and fair in your treatment of all team members. Nothing breeds resent- ment more than if, through the grapevine, individuals feel they are being held to a different standard than are other project members.

∙ Treat the review as only one point in an ongoing process. Use it to reach an agree- ment as to how the individual can improve his or her performance. Both managers and subordinates may dread a formal performance review. Neither

side feels comfortable with the evaluative nature of the discussion and the potential for misunderstanding and hurt feelings. Much of this anxiety can be alleviated if the proj- ect manager is doing her job well. Project managers should be constantly giving team members feedback throughout the project so that individual team members can have a pretty good idea how well they have performed and how the manager feels before the formal meeting. Post-project angst can be avoided if pre-project expectations are dis- cussed before the project and regularly reinforced during project performance.

While in many cases the same process that is applied to reviewing the performance of team members is applied to evaluating the project manager, many organizations augment this process, given the importance of the position to their organization. This is where conducting the 360-degree review is becoming more popular. In project- driven organizations, the project office typically will be responsible for collecting information on a specific project manager from customers, vendors, team members, peers, and other managers. This approach has tremendous promise for developing more effective project managers (Cochran, 2000).

In addition to performance reviews, data are collected for project retrospectives, which can present situations that may influence performance. In these situations per- formance evaluations should recognize and note the unusual situation.

Chapter 14 Project Closure 537

The goals of project closure are to complete the project and to improve performance of future projects. Implementing closure and review has three major closure deliver- ables: wrap-up, audit, and performance evaluation. Wrap-up activities put the proj- ect “to bed” and include completing the final project deliverable, closing accounts, finding new opportunities for project staff, closing facilities, and creating the final report. Project audits assess the overall success of the project. Retrospectives are used to identify lessons learned and improve future performance. Individual and team evaluations assess performance and opportunities for improvement. A project should not be considered closed until all three activities have been completed. The culture of the organization and the project team will play a major factor in the effi- cacy of these activities.

Summary

Key Terms Lessons learned, 525 Performance review, 535

Project closure, 516 Project evaluation, 532

Retrospective, 525 360-degree review, 536

1. How does the project closure review differ from the performance measurement con- trol system discussed in Chapter 13?

2. What major information would you expect to find in a project review? 3. Why is it difficult to perform a truly independent, objective review? 4. Comment on the following statement: “We cannot afford to terminate the project

now. We have already spent more than 50 percent of the project budget.” 5. Why should you separate performance reviews from pay reviews? How do you do

this? 6. Advocates of retrospective methodology claim there are distinguishing characteris-

tics that increase its value over past lessons learned methods. What are they? How does each characteristic enhance project closure and review?

1. Consider a course that you recently completed. Perform a review of the course (the course represents a project and the course syllabus represents the project plan).

2. Imagine you are conducting a review of the International Space Station project. Research press coverage and the Internet to collect information on the current status of the project. What are the successes and failures to date? What forecasts would you make about the completion of the project, and why? What recommendations would you make to top management of the program, and why?

3. Interview a project manager who works for an organization that implements multi- ple projects. Ask the manager what kind of closure procedures are used to complete a project and whether lessons learned are used.

4. What are some of the lessons learned from a recent project in your organization? Was a retrospective done? What action plans were generated to improve processes as a result of the project?

Exercises

Review Questions

538 Chapter 14 Project Closure

Anonymous, “Annual Survey of Business Improvement Architects,” Toronto, Canada, in PM Network, “Deliverables,” vol. 21, no. 4 (April 2007), p. 18. Cochran, D., “Finally, a Way to Completely Measure Project Manager Performance,” PM Network, September 2000, pp. 75–80. Cooke-Davies, T., “Project Management Closeout Management: More than Simply Saying Good Bye and Moving On,” in J. Knutson (Ed.), Project Management for Business Processionals (Indianapolis, IN: John Wiley and Sons, 2001), pp. 200–14. Fretty, P., “Why Do Projects Really Fail?” PM Network, March 2006, pp. 45–48. Gobeli, D., and E. W. Larson, “Barriers Affecting Project Success,” in 1986 Proceed- ings Project Management Institute: Measuring Success (Upper Darby, PA: Project Management Institute, 1986), pp. 22–29. Hoffman, R., “Ten Reasons You Should Be Using 360 Degree Feedback,” HR Maga- zine, April 1995, pp. 82–85. Jedd, Marcia, “Standing Guard,” PM Network, vol. 21, no. 1 (January 2007), pp. 73–77. Kendrick, Tom, Identifying and Managing Project Risk, 2nd ed. (New York: ANA- COM, 2009). Kerth, Norman L., Project Retrospectives: A Handbook for Team Reviews (New York: Dorset House, 2001). Kwak, Y. H., and C. W. Ibbs, “Calculating Project Management’s Return on Invest- ment,” Project Management Journal, vol. 31, no. 2 (March 2000), pp. 38–47. Ladika, S., “By Focusing on Lessons Learned, Project Managers Can Avoid Repeating the Same Old Mistakes,” PM Network, Vol. 22, No. 2 (February 2008), pp. 75–77. Latham, G. P., and K. N. Wexley, Increasing Productivity through Performance Appraisal, 2nd ed. (Reading, MA: Addison-Wesley, 1993). Lavell, Debra, and Russ Martinelli, “Program and Project Retrospectives: An Introduction,” PM World Today, vol. 10, no. 1 (January 2008), p. 1. Marlin, Mark, “Implementing an Effective Lessons Learned Process in a Global Project Environment,” PM World Today, vol. 10, no. 11 (November 2008), pp. 1–6. Nelson, Ryan R., “Project Retrospectives: Evaluating Project Success, Failure, and Every- thing in Between,” MIS Quarterly Executive, vol. 4, no. 3 (September 2005), p. 372. Pippett, D. D., and J. F. Peters, “Team Building and Project Management: How Are We Doing?” Project Management Journal, vol. 26, no. 4 (December 1995), pp. 29–37. Romanoff, T. K., “The Ten Commandments of Performance Management,” Personnel, vol. 66, no. 1 (1989), pp. 24–26. Royer, I., “Why Bad Projects Are So Hard to Kill,” Harvard Business Review, February 2003, pp. 49–56. Senge, P., The Fifth Discipline: The Art and Practice of the Learning Organization (New York: Doubleday, 1990). Sheperd, D. A., H. Patzelt, and M. Wolfe, “Moving Forward from Project Failure: Negative Emotions, Affective Commitment, and Learning from the Experience,” Academy of Management Journal, vol. 54, no. 6 (2011), pp. 1229–60.

References

Chapter 14 Project Closure 539

Staw, Berry M., and Jerry Ross, “Knowing When to Pull the Plug,” Harvard Business Review, March-April 1987, pp. 68–74. Wheatly, M., “Over the Bar,” PM Network, vol. 17, no. 1 (January 2003), pp. 40–45. Yates, J. K., and S. Aniftos, “ISO 9000 Series of Quality Standards and the E/C Industry,” Project Management Journal, vol. 28, no. 2 (June 1997), pp. 21–31. Zaitz, Les, “Rail Car Deal Snags Tri Met for Millions,” Oregonian, December 14, 2008, p. 1, and January 7, 2009, p. D4.

Appendix 14.1

Project Closeout Checklist

Project Closeout Transition Checklist Provide basic information about the project including: Project Title—The proper name used to identify this project; Project Working Title—The working name or acronym that will be used for the project; Proponent Secretary—The Secretary to whom the proponent agency is assigned or the Secretary that is sponsoring an enterprise project; Proponent Agency—The agency that will be responsible for the management of the project; Prepared by—The person(s) preparing this document; Date/Control Number—The date the check- list is finalized and the change or configuration item control number assigned.

Project Title: Project Working Title: Proponent Secretary: Proponent Agency: Prepared by: Date/Control Number:

Complete the Status and Comments columns. In the Status column indicate: Yes, if the item has been addressed and completed; No, if the item has not been addressed, or is incomplete; N/A, if the item is not applicable to this project. Provide comments or describe the plan to resolve the item in the last column.

Item Status Comments/Plan to Resolve

1 Have all the product or service deliverables been accepted by the customer?

1.1 Are there contingencies or conditions related to the acceptance? If so, describe in the Comments.

2 Has the project been evaluated against each performance goal established in the project performance plan?

3 Has the actual cost of the project been tallied and compared to the approved cost baseline?

3.1 Have all approved changes to the cost baseline been identified and their impact on the project documented?

(Continued)

Chapter 14 Project Closure 539

540 Chapter 14 Project Closure

Item Status Comments/Plan to Resolve

4 Have the actual milestone completion dates been compared to the approved schedule?

4.1 Have all approved changes to the schedule baseline been identified and their impact on the project documented?

5 Have all approved changes to the project scope been identified and their impact on the perfor- mance, cost, and schedule baselines documented?

6 Has operations management formally accepted responsibility for operating and maintaining the product(s) or service(s) delivered by the project?

6.1 Has the documentation relating to operation and maintenance of the product(s) or service(s) been delivered to, and accepted by, operations management?

6.2 Has training and knowledge transfer of the oper- ations organization been completed?

6.3 Does the projected annual cost to operate and maintain the product(s) or service(s) differ from the estimate provided in the project proposal? If so, note and explain the difference in the Comments column.

7 Have the resources used by the project been transferred to other units within the organization?

8 Has the project documentation been archived or otherwise disposed of as described in the project plan?

9 Have the lessons learned been documented in accordance with the Commonwealth Project Management guideline?

10 Has the date for the post-implementation review been set?

10.1 Has the person or unit responsible for conduct- ing the post-implementation review been identified?

Signatures The signatures of the people below relay an understanding that the key elements within the Closeout Phase section are complete and the project has been formally closed.

Position/Title Name Date Phone Number

 

 

Source: http://www.vita.virginia.gov/projects/cpm/cpmDocs/CPMG-SEC5-Final.pdf

Chapter 14 Project Closure 541

Appendix 14.2

Euro Conversion—Project Closure Checklist

Document finance department acceptance

Customer training in Euro software

Archive all

Schedules/actuals

Budgets/actual costs

Changes

Close out all accounts with vendors

Close out all work orders

Close out partner accounts

Reassign project staff

Evaluation of

Vendors

Staff members

Final report and lessons learned meeting

Lessons learned archive to database

tribute awards

1.

2.

3.

4.

5.

6.

7.

8.

9.

10.

16/12

28/12

31/12

31/12

31/12

31/12

31/12

31/12

16/12

31/12

31/12

4/1

10/1

Due date

Project Euro Conversion

Hans Kramer

Finance Department

12 December XXProject manager

Person responsible Notes

Hans

Joan

Maeyke

Maeyke

Maeyke

Guido

Mayo

Guido

Sophie

Mayo

Sophie

Hans

Maeyke

Sophie

Train all departments before conversion

Use standard questionnaire for vendors Have HR department develop and administer Send notice to all stakeholders

Contact IS department

Notify all stakeholders

Customer

Completion date

542 Chapter 14 Project Closure

Case A14.1

Maximum Megahertz Project Olaf Gundersen, the CEO of Wireless Telecom Company, is in a quandary. Last year he accepted the Maximum Megahertz Project suggested by six up-and-coming young R&D corporate stars. Although Olaf did not truly understand the technical importance of the project, the creators of the project needed only $600,000, so it seemed like a good risk. Now the group is asking for $800,000 more and a six-month extension on a project that is already four months behind. However, the team feels confident they can turn things around. The project manager and project team feel that if they hang in there a little longer they will be able to overcome the roadblocks they are encountering—especially those that reduce power, increase speed, and use a new technology battery. Other managers familiar with the project hint that the power pack problem might be solved, but “the bat- tery problem will never be solved.” Olaf believes he is locked into this project; his gut feeling tells him the project will never materialize, and he should get out. John, his human resource manager, suggested bringing in a consultant to axe the project.

Olaf decided to call his friend Dawn O’Connor, the CEO of an accounting software company. He asked her, “What do you do when project costs and deadlines escalate drastically? How do you handle doubtful projects?” Her response was, “Let another project manager look at the project. Ask: ‘If you took over this project tomorrow, could you achieve the required results, given the extended time and additional money?’ If the answer is no, I call my top management team together and have them review the doubtful project in relation to other projects in our project portfolio.” Olaf feels this is good advice.

Unfortunately, the Maximum Megahertz Project is not an isolated example. Over the last five years there have been three projects that were never completed. “We just seemed to pour more money into them, even though we had a pretty good idea the projects were dying. The cost of those projects was high; those resources could have been better used on other projects.” Olaf wonders, “Do we ever learn from our mistakes? How can we develop a process that catches errant projects early? More importantly, how do we ease a project manager and team off an errant project without embarrassment?” Olaf certainly does not want to lose the six bright stars on the Maximum Megahertz Project.

Olaf is contemplating how his growing telecommunications company should deal with the problem of identifying projects that should be terminated early, how to allow good managers to make mistakes without public embarrassment, and how they all can learn from their mistakes.

Give Olaf a plan of action for the future that attacks the problem. Be specific and provide examples that relate to Wireless Telecom Company.

E P I L O G U E

With Chapter 14 the project life cycle is complete. You have been exposed to the core elements of project management. We have consciously tried to incorporate a blend of sociocultural and process practices required to successfully manage any project. These best practices are transferable across industries. Your understanding of these chapters should enhance your ability to make a positive contribution in any project environment.

The supplemental chapters that follow expand on the core by covering international project management, and Agile methods. ∙ Chapter 15. Explores different international environments in which you may have to

manage a project. In large high technology firms we estimate that 60–90 percent of their projects are virtual and across many cultures. If you find yourself new in this environment, the international chapter is an excellent primer on the types of condi- tions and issues you may encounter in an international project.

∙ Chapter 16. Agile methodology is used in complex projects (e.g., software and new innovation products) where the final design requirements are not known and evolve as the project is implemented. The methodology breaks requirements into small functional pieces that allow rapid response to change. Agile embraces flexibility, change, small teams, and owner involvement.

Project networks

6

Managing risk 7

Monitoring progress

13

Teams 11

Outsourcing 12

Project manager

10

Strategy 2

Introduction 1

Organization 3

Schedule resources & costs

8

Intern ation

al

proje cts

15

Agile PM 16

Project closure

14

Estimate 5

Reducing duration

9

Define project

4

543

544

International Projects

LEARNING OBJECTIVES After reading this chapter you should be able to:

15-1 Describe environmental factors that affect project management in different countries.

15-2 Identify factors that typically are considered in selecting a foreign location for a project.

15-3 Understand cross-cultural issues that impact working on international projects.

15-4 Describe culture shock and strategies for coping with it.

15-5 Understand how organizations select and prepare people to work on international projects.

OUTLINE 15.1 Environmental Factors

15.2 Project Site Selection

15.3 Cross-Cultural Considerations: A Closer Look

15.4 Selection and Training for International Projects

Summary

C H A P T E R F I F T E E N

15

545

The principal benefit of living abroad is that it enables us to get glimpses of ourselves as others see us and to realize that others’ views are more accurate than ours. Progress begins with grasping the truth about our- selves, however unpleasant it may be.

—Russel Ackoff, The Wharton School, University of Pennsylvania

Thanks to technology we live in a “flat world” in which more and more projects have an international element. It could be being sent to Zimbabwe for 9 months as a lead contractor on a bridge construction project or flying back and forth across the Atlantic to work on a joint product venture with German engineers. Or it could be relying on a Korean computer supplier on a business expansion project or Skyping with an Indian counterpart on a software project. This chapter targets the international project man- ager who must resettle in a foreign land to manage a project. The chapter also provides useful information for professionals whose project work requires interacting either directly or virtually with foreign counterparts from around the world.

Project networks

6

Managing risk 7

Monitoring progress

13

Teams 11

Outsourcing 12

Project manager

10

Strategy 2

Introduction 1

Organization 3

Schedule resources & costs

8

Intern ation

al

proje cts

15

Agile PM 16

Project closure

14

Estimate 5

Reducing duration

9

Define project

4

546 Chapter 15 International Projects

There is no generally accepted framework or road map for project managers given international assignments. These project managers typically face a difficult set of problems—for example, absence from home, friends, and sometimes family; personal risks; missed career opportunities; foreign language, culture, and laws; adverse condi- tions. Of course there are positives—for example, increased income, increased responsi- bilities, career opportunities, foreign travel, new lifetime friends. How the international project manager adapts and approaches challenges encountered in the host country often determines the success or failure of a project.

This chapter focuses on four major issues surrounding the management of interna- tional projects. First, major environmental factors that impact project selection and implementation are briefly highlighted. Second, an example of how organizations decide where to expand globally is provided. Third, the challenge of working in a strange and foreign culture is addressed. Finally, how companies select and train profes- sionals for international projects is discussed. Although by no means comprehensive, this chapter provides an understanding of the major issues and challenges confronting the international project manager.

15.1 Environmental Factors The major challenge international project managers face is the reality that what works at home may not work in a foreign environment. Too often project managers impose practices, assumed to be superior, from their home country on host-country nationals without questioning their applicability to the new environment. Although there are similarities between domestic and international projects, it is a fact that good manage- ment practices vary across nations and cultures. It is these differences that can turn an international project into a nightmare. If potential international project managers have a keen awareness of differences in the host country’s environment from their own domestic environment, dangers and obstacles of the global project can be reduced or avoided. There are several basic factors in the host country’s environment that may alter how projects will be implemented: legal/political, security, geographical, eco- nomic, infrastructure, and culture (see Figure 15.1).

Legal/Political Expatriate project managers should operate within the laws and regulations of the host country. Political stability and local laws strongly influence how projects will be

15-1LO Describe environmental factors that affect project management in different countries.

FIGURE 15.1 Environmental Factors Affecting International Projects

Culture

Geography Security

Infrastructure

Legal/politicalEconomic

Chapter 15 International Projects 547

implemented. Typically, these laws favor protection of local workers, suppliers, and environment. For example, how much control will be imposed from government agen- cies? What is the attitude of federal and state bureaucracies toward regulations and approval policies that can cause project delays? How much government interference or support can one expect? For example, some governments interpret regulations arbi- trarily, depending upon personal interests.

The constraints imposed by national and local laws need to be identified and adhered to. Are local ecological laws restrictive? Will manufacturing a new product in a computer chip plant require exporting toxic waste materials? What are the pollution standards? How will labor laws affect the use of indigenous workers to complete the project? Given that laws that affect business vary widely across countries, qualified legal assistance is essential.

Government corruption is a very real part of international business. In China vari- ous forms of obligatory “profit sharing” with city officials in the Hainan province have been reported. Employment of relatives, donations, and other “favors” are an expected cost of doing business in that region. Likewise, Bloomberg BusinessWeek reported that in Russia the threat of being targeted for abuse by government officials—sometimes operating in league with Russian businesses—is the primary reason that country has attracted less than one-fifth of the foreign investment in Brazil (Cahill, 2010).

Political stability is another key factor in deciding to implement a project in a for- eign country. What are the chances that there will be a change in the party in power during the project? Are the tax provisions and government regulations stable or subject to change with the winds of political change? How are laws made, and what is the past record of fairness? How are labor unions treated in the political realm? Does labor unrest exist? Is there a chance for a coup d’état? Contingency plans need to be estab- lished to respond to emergencies.

Security International terrorism is a fact of life in today’s world. Tim Daniel, chief operating officer of International SOS Assistance, Inc., reported that the number of his firm’s clients doubled after September 11th. SOS is a security firm that specializes in evacu- ating expatriates from dangerous situations around the world. The company cites PricewaterhouseCoopers, Nortel Networks Corp., and Citigroup among its clients (Scown, 1993).

While the 9/11 attacks magnified the fact that Americans are vulnerable to terror- ism at home, they also heightened security concerns for working abroad. For example, after September 11th, several American firms canceled or scaled back projects in potential hotspots such as Somalia and the Philippines. Others reported increased pres- sures from expatriates who wanted to return home with their families. On May 7, 2009, the Nobel Peace Prize-winning relief agency Médecins Sans Frontières (Doctors With- out Borders) reduced emergency projects in northwest Pakistan due to clashes between government forces and Taliban fighters.1

Crime is another factor. The growing presence of the Russian Mafia has discour- aged many foreign firms from setting up operations in the former Soviet Union. Kid- napping of American professionals is also a very real threat in many parts of the world.

Security nationally involves the capacity of a country’s military and police forces to prevent and respond to attacks. In many foreign countries, American firms will have to

1 www.doctorswithoutborders.org/press/release, June 2009.

548 Chapter 15 International Projects

augment the countries’ security system. For example, it is common practice to hire tribal bodyguards in such places as Angola and Uzbekistan.

Another real cost associated with international terrorism is the ease of commerce across borders. Heightened security measures have created border congestions that have expanded the time and cost of moving personnel, materials, and equipment across countries. These constraints need to be factored into the budget and schedule of projects.

Risk management is always a vital part of project management. It plays an even big- ger role in managing projects overseas. For example, Strohl Systems Group, a global leader in recovery-planning software and services, includes the following among the questions it uses to evaluate vulnerability to terrorism: Have you included possible ter- rorist targets (facilities and personnel) in your hazard and vulnerability analysis? Have you conducted a counterterrorism exercise complete with law enforcement, fire, medi- cal, and emergency management participation? What should your organization’s pol- icy be on negotiating with a person threatening a terrorist act?2

Managing projects in a dangerous world is a tough assignment. Security precautions are major cost considerations not only in dollars and cents, but also in the psychologi- cal well-being of personnel sent abroad. Effective risk management is critical.

Geography One factor that is often underestimated until project personnel actually arrive at a for- eign destination is the geography of the country. Imagine what it is like to deplane from a modern aircraft and encounter the 105-degree heat and 90 percent humidity of Jakarta, Indonesia, or three feet of fresh snow and −22 degree temperatures in Kokkla, Finland. Whether it is the wind, the rain, the heat, the jungle, or the desert, more than one project manager has asserted that the greatest challenge was overcoming the “elements.” Mother Nature cannot be ignored.

The planning and implementation of a project must take into account the impact the country’s geography will have on the project. For example, a salvage operation off the coast of Greenland can only be scheduled one month out of the year because the water- way is frozen over during the remainder of the year. Construction projects in Southeast Asia have to accommodate the monsoon season when rainfall can be as high as 50 inches per month.

Geography does not just affect outdoor projects. It can have an indirect effect on “indoor” projects. For example, one information systems specialist reported that his performance on a project in northern Sweden declined due to sleep deprivation. He attributed his problems to the 20 hours of daylight this part of the world experiences during summer months. Finally, extreme weather conditions can make extraordinary demands on equipment. Projects can grind to a halt because of equipment breakdown under the brunt of the wind and sand. Working under extreme conditions typically requires special equipment, which increases the costs and complexity of the project.

Before beginning a project in a foreign land, project planners and managers need to study carefully the unique characteristics of the geography of that country. They need to factor into project plans and schedules such items as climate, seasons, altitude, and natural geographical obstacles. See the Snapshot from Practice 15.1: The Filming of Apocalypse Now for an example of a poorly planned endeavor in the Philippines.

2 Contingency Planning and Management.com, “Strohl Systems Offers Terrorism Readiness Questionnaire,” September 24, 2001.

Chapter 15 International Projects 549

Economic Basic economic factors in foreign countries and regions influence choices of site selec- tion and project success. The gross domestic product (GDP) of a country suggests the level of development of a country. A faltering economy may indicate fewer sources of capital funding. Changes in protectionist strategies of a host country, such as import quotas and tariffs, can quickly alter the viability of projects. Other factors such as bal- ance of payments, taxation, labor laws, safety regulations, and market size can influ- ence project choices and operations.

Skills, educational level, and labor supply prevalent in a host country can deter- mine the choice of a project site. Is project selection driven by low wage levels or availability of technically skilled talent? For example, you can hire three computer programmers in Ukraine for the price of one programmer in the United States. Con- versely, many high-tech companies are willing to endure the additional expense of setting up joint projects in Switzerland and Germany to take advantage of their engi- neering prowess.

Financial exposure is a significant risk for many international projects. Let’s look first at the potential impact of currency fluctuations on project success. For example, a U.S. contractor agrees to build a customized product for a German client. The product will be built in the United States. The contractor estimates that the project will cost $925,000, and, in order to earn a nice profit, prices the project at $1,000,000. To

In February 1976, Francis Ford Coppola took his Hollywood film crew to the Philippines to shoot Apocalypse Now, a film adaptation of Joseph Conrad’s Heart of Darkness within the context of

the Vietnam conflict. The Philippines was chosen because the terrain was similar to Vietnam’s, and the government was willing to rent out its helicopter force for the movie. At the time, the U.S. military was unwilling to cooperate on a film about Vietnam. An additional advantage was cheap labor. Coppola was able to hire more than 300 laborers at $1 to $3 per day to construct elaborate production sets, including an impressive Cambodian temple. Apocalypse Now was scheduled for 16 weeks of shooting at a budget of $12 to $14 million. Months earlier, George Lucas, of Star Wars fame, warned Coppola against filming the movie in the Philip- pines. He said, “It’s one thing to go over there for three weeks with five people and scrounge some footage with the Filipino Army, but if you go over there with a big Hollywood production, the longer you stay the more in danger you are of getting sucked into the swamp.” His words turned out to be prophetic. A civil war was going on between government forces and communist rebels. Shooting was repeatedly

interrupted because the Philippine military ordered their helicopter pilots to leave the set and fly to the mountains to fight the rebels. In May 1976, a typhoon struck the Philippine Islands, destroying most of the movie sets. The film team was forced to shut down production and returned to the United States for two months. The lead character was played by Martin Sheen, who suffered a serious heart attack under the stress and heat of the filming and had to return to the United States. Coppola scrambled to film the scenes that did not require Sheen, but eventually production came to a standstill until Sheen’s return nine weeks later. The entire project proved to be a traumatic experi- ence for Coppola, who had enjoyed Academy Award success with his previous Godfather movies. “There were times when I thought I was going to die, literally, from the inability to move the problems I had. I would go to bed at four in the morning in a cold sweat.” Film production ended in May 1977 after more than 200 days of shooting. The final cost was about $30 million.

S N A P S H O T F R O M P R A C T I C E 1 5 . 1 The Filming of Apocalypse Now*

* Hearts of Darkness: A Filmmaker’s Apocalypse (Paramount Pictures, 1991).

550 Chapter 15 International Projects

accommodate the German buyer the price is converted to euros. Suppose at the time of the contract, the exchange rate is $1.15 per euro, and the price specified in the contract is €869,566.

Ten months later the project is completed as expected, with work costing the esti- mated $925,000 and the customer pays the agreed upon price of €869,566. However the exchange rate has changed; it is now $1.05 per Euro. That being the case, the pay- ment equates to €869,566 × 1.05 = $913,044. Instead of reaping a nice profit the contractor suffers a $(913,044 − 925,000) = $−11,956 loss!

A company can protect against adverse currency fluctuations in a number of related ways. First, they can hedge against this risk by having all parties agree to finalize the deal and make payments at a specified future date. Finance people call this a forward exchange or contract. Second, they can stipulate in the contract certain conditions based on exchange rates to insure their profit margin. Finally, many multinational com- panies who do business in the client country avoid currency exchange and simply use local currency to manage operations in that country. Financiers refer to this as a natural hedge (Moffet et al., 2012).

Inflation is another significant risk. One of the greatest strengths of the U.S. econ- omy is its relatively low inflation rate (below 3 percent from 1990–2012). Other coun- tries, especially underdeveloped countries, do not enjoy such stability. Rapid inflation can strike at any time and have profound impact on project costs and profits. For example, a European contractor successfully wins the bid to build a bridge for the Tanzanian government in East Africa. Work started in 2010 and will be completed by the end of 2011. In 2010 the Tanzanian inflation ratio was less than 6 percent with an average inflation rate of 6.7 over the past decade. The contractor used what she consid- ered a conservative inflation rate of 9 percent when estimating the costs of the project at 1,800,000 schillings (Tanzanian currency). In order to win the bid and enjoy a solid profit the agreed upon price is 2,000,000 schillings.

Early in 2011 Tanzania experiences a sporadic rainfall which, coupled with increased oil prices, causes the inflation rate to jump to over 20 percent! Suddenly costs of cer- tain elements of the project increase dramatically and instead of garnering a nice profit the contractor barely breaks even. Companies can protect against inflation by tying costs to a strong currency such as the U.S. dollar, British pound, or euro and/or nego- tiating cost-plus contracts (see Chapter 12 Appendix) with the client.

Bartering is a form of compensation that is still used by some countries and organi- zations. For example, one project in Africa was paid in goat skins. The goat skins were eventually sold to an Italian manufacturer of gloves. Another project along the Caspian Sea was paid for in oil. There is a small group of firms that specialize in bartering for project contractors. These intermediaries charge a commission to sell the bartered goods (e.g., oil, diamonds, wheat) for the contractor. However, dealing with commodi- ties can be a risky enterprise. Infrastructure Infrastructure refers to a country or community’s ability to provide the services required for a project. Infrastructure needs for a project could be communication, transportation, power, technology, and education systems. Power outages are common in many parts of the world. For example, India’s burgeoning economy came to a halt during the 2012 summer when over 670 million people were without power for more than two days. If reliable power is not sufficient, other alternatives need to be consid- ered. For example, construction firms often rely on heavy diesel generators as backups on their projects. Software projects across borders are common today; however, they

Chapter 15 International Projects 551

depend on reliable telecommunication networks. If the project depends on a high ratio of vendor suppliers, good roads, and other transportation modes such as air and sea- ports, a good infrastructure will be imperative.

An example of a project that failed to take into account the needs and infrastructure of the host nation involved a U.S. company that was awarded the contract for building a hospital in an African nation. The local African officials wanted a “low-tech” health care facility that would take local traditions into consideration. Because their relatives generally accompanied patients, space had to be provided for them, too. Electricity was not reliably supplied, and it was doubtful whether well-educated doctors would want to spend careers away from the city. Therefore, the locals wanted a hospital for basic care with minimum technology. The construction company doing the building, on the other hand, had a preconceived notion of what a hospital should be and was not going to be accused of building a second-rate facility. It built a modern hospital that could have stood in any U.S. city. The building was completed; however, even after several years it was not used because the electricity was not sufficient, the air-conditioning could not be used, and doctors refused to live in the rural area (Adler and Gunderson, 2007).

Organizations need to consider the needs of the families of personnel they send overseas. Will the facilities and living conditions for the expatriate families place an undue hardship on families? Will schooling for children be available? The welfare and comfort of expatriate families play an important role in retaining good project manag- ers and promoting their peak performance.

Culture Visiting project managers must respect the customs, values, philosophies, and social standards of their host country. Global managers recognize that if the customs and social cultural dimensions of the host country are not accommodated, projects will rarely succeed. Too many project audits and final reports of international projects reflect challenges and problems linked to cultural differences.

For most project managers, the biggest difference in managing an international project is operating in a national culture where things are done differently. For exam- ple, most developed nations use the same project management techniques (CPM, risk analysis, trade-off analysis). However, how activity work is performed can be very different in the host country. For example, a backhoe is used to dig a trench in France, while 20 laborers are used to dig a similar trench in Ethiopia.

Will English be the operating language, or will the project manager need to be fluent in the foreign language? Will translation services be available and sufficient? Communication problems—because of language differences—often become a major problem in carrying out even simple tasks. Although the use of translators can help tremendously, their use does not solve the communication problem completely because something is lost in translation. For example, consider the disastrous consequences of differences in interpretations and expectations between the Brazilians and Americans highlighted in Snapshot from Practice 15.2: River of Doubt.

Will religious factors influence the project? For example, religious factors touched the spouse of a Scandinavian project manager responsible for building a water desalination plant from sea water in a Middle East country. She was restricted to the living compound for families of foreign guest workers. Going outside the compound to a nearby city meant covering her head, arms, and legs and being accompanied by another woman or, prefera- bly, a man. A physical altercation in the city concerning her clothing was traumatic for her. She left the country and returned home. Her husband requested a transfer back home three months later. The loss of the original project manager set the project back three months.

552 Chapter 15 International Projects

After his crushing election defeat in 1912 as a third-party candidate, for- mer president Theodore (“Teddy”) Roosevelt set his sights on a grand adventure, the first descent of an

unmapped rapids-choked tributary of the Amazon aptly titled the “River of Doubt.” Together with Brazil’s most famous explorer, Candido Mariano da Silva Rondon, Roosevelt accomplished a feat that belongs in the annals of great expeditions. Along the way, Roosevelt and his men faced an unbelievable series of hardships, losing their canoes and supplies to crushing whitewater rapids, and endur- ing starvation, Indian attacks, disease, drowning, and even murder within their ranks. Candice Millard brings alive these extraordinary events in her nonfiction thriller The River of Doubt. While her account details the ill-fated journey it also reveals insights into interna- tional project management as it describes the collabo- ration between the American and Brazilian cohorts. While each party ultimately earned the respect and admiration of the other, friction between the two par- ties simmered from the outset. One source of consternation was the amount of supplies and luggage that the Americans required for the journey. Warned that the luggage requirements of the former president and his party would be extensive, the Brazilian commodore Rondon ordered 110 mules and 17 pack oxen to be used for the expedition’s over- land journey across the Brazilian highland to the great river. Surely, he felt, this would be more than necessary for such a trip. The Brazilians were astounded by the sheer vol- ume of baggage that was unloaded from Roosevelt’s ship, the Vandycks. There were mountains of crates: guns and ammunition, chairs and tables, tents and cots, equipment for collecting and preserving speci- mens, surveying the river, and cooking meals. An exhausted stevedore elicited a roar of laughter from the onlooking crowd when he announced, “Nothing lacking but the piano!” Rather than risk embarrassment by telling Roos- evelt that they were not prepared to take so much lug- gage, Rondon scrambled to find additional animals. Extra oxen and mules were located, but they were far from tame. Loaded with supplies, the oxen would buck and throw off the packs. The expedition was delayed

S N A P S H O T F R O M P R A C T I C E 1 5 . 2 River of Doubt*

as gauchos (South American cowboys) endeavored to “break” the animals as quickly as possible. Within days of finally setting off across the vast highlands, Roosevelt and his men began to experi- ence the harsh realities that were to plague the expe- dition. After crossing a bone-strewn graveyard of oxen and mules that had starved to death or been eaten during previous expeditions, they were stunned by the sight of unopened supply crates, all clearly marked “Roosevelt South American Expedition.” The pack animals, still making their weary away across the plateau ahead of the them, had begun bucking off their heavy loads! As the officers rode slowly past the boxes, they wondered what they were leaving behind and how pre- cious it might become in the months ahead. Little did they know how true those fears would be.

© Fotomas/Topham/TheImageWorks

* Candice Millard, The River of Doubt (New York: Doubleday), 2005.

Chapter 15 International Projects 553

Not only do project managers have to adapt to the culture of the host country, but often overseas projects require working with people from other different countries. For example, on a light rail project in the Philippines, an American firm was hired to over- see the interests of local real estate companies who were funding the project. The American project manager had to work with Czech representatives who were provid- ing the rail equipment, Japanese engineers responsible for building the rail, Australian bankers who were providing additional financing, an Indian firm that were the princi- pal architects, as well as the native Filipinos.

Of all the factors, working within a multicultural environment is most often the greatest challenge for project managers. It will be dealt with in detail later in this chapter.

15.2 Project Site Selection As the project manager studies the factors contributing to site selection, he will see that inherent in all of these factors is the risk level senior management and directors are willing to accept for the potential rewards of a successful international project. One approach for the project manager to digest, clarify, and understand the factors leading to the selection of a specific project is to use a risk matrix similar to those found in Chapter 7. The major difference lies in the selection of the risk factors for different project sites.

Figure 15.2 presents a truncated matrix for project site selection of the construc- tion of a laser printer factory in Singapore, India, or Ireland. In this example, political stability, worker skill and supply, culture compatibility, infrastructure, government support, and product-to-market advantage were the major assessment factors. Each project site is compared against each factor. Figure 15.3 depicts a further breakdown of the infrastructure evaluation factor. In this example, transportation, educated workforce, utilities, telecommunications, and vendor suppliers are considered impor- tant to evaluating the infrastructure for each site. The scores given in Figure 15.3 are used to assign values to the infrastructure factor of the assessment matrix, Figure 15.2. In this project, Ireland was the choice. Clearly, Singapore and Ireland were very close in terms of infrastructure and several other factors. However, the major assessment factor of using Ireland to access the EEC (product-to-market advantage) turned the decision.

15-2LO Identify factors that typically are considered in selecting a foreign location for a project.

FIGURE 15.2 Assessment Matrix Project Site Selection

Singapore

India

Ireland

5

3

5

4

4

4

4

3

5

4

3

5

4

3

5

3

Po litic

al s tab

ility

Wo rke

r sk ill,

sup ply

Cu ltu

re co

mp atib

ility

Inf ras

tru ctu

re

Go ver

nm en

t su pp

ort

Pro du

ct- to-

ma rke

t

ad van

tag e

3

5

Score legend

5 = excellent 3 = acceptable 1 = poor

554 Chapter 15 International Projects

Given the macro economic factors, the firm’s strategic posture toward global proj- ects, and the major considerations for selecting this project, it is imperative the project manager quickly become sensitized to the foreign cultural factors that can spell project success or failure.

15.3 Cross-Cultural Considerations: A Closer Look The concept of culture was introduced in Chapter 3 as referring to the unique personal- ity of a particular firm. More specifically, culture was defined as a system of shared norms, beliefs, values, and customs that bind people together, creating shared meaning and a unique identity. Culture is a concept created for descriptive purposes and depends on the group that is the focus of attention. For example, within a global context culture can refer to certain regions (i.e., Europeans, Arabs), to specific nations (i.e., French, Thai), or to certain ethnic or religious groups (i.e., Kurds, African Americans). This chapter looks at national cultures; we freely recognize that many cultural characteris- tics are borderless and that there is considerable variation within any one country. Still, national cultures provide a useful anchor for understanding different habits, customs, and values around the world.

Right or wrong, Americans have a reputation for not being able to work effectively in foreign cultures. (When we use the term “American,” we are referring to people from the United States; we apologize to our friends in Canada and Central and South America.) In the 1960s, the term “Ugly American” encapsulated the apparent indiffer- ence of Americans to native cultures when working or traveling abroad. Americans are often criticized for being parochial; that is, they view the world solely through their own eyes and perspectives. People with a parochial perspective do not recognize that other people have different ways of living and working effectively. American parochial attitudes probably reflect the huge domestic market of the United States, the geo- graphic isolation of the United States, and the reality that English is becoming the international business language in many parts of the world.

It is important that Americans working on international projects anticipate cultural differences. Take, for example, a project manager from a large North American construction company who was given responsibility to select a site for the design and construction of a large fish-processing plant in a West African country. The manager assessed potential

15-3LO Understand cross-cultural issues that impact work- ing on international projects.

FIGURE 15.3 Evaluation Matrix Breakdown for Infrastructure

Singapore

India

Ireland

5

3

5

4

4

4

5

4

5

5

4

5

4

2

5

Tra nsp

ort atio

n

Ed uca

ted wo

rkf orc

e

Uti litie

s

Tel eco

mm un

ica tio

ns

Ve nd

or sup

plie rs

Score legend

5 = excellent 3 = acceptable 1 = poor

Chapter 15 International Projects 555

sites according to the availability of reliable power, closeness to transportation, nearness to the river for access of fishing boats from the Atlantic Ocean, proximity to main mar- kets, and availability of housing and people for employment. After evaluating alternative sites, the project manager chose the optimum location. Just prior to requesting bids from local contractors for some of the site preparation, the manager discovered, in talking to the contractors, that the site was located on ground considered sacred by the local people, who believed this site was the place where their gods resided. None of the local people upon whom the project manager was depending for staff would ever consider working there! The project manager quickly revised his choice and relocated the site. In this case, he was lucky that the cultural gaffe was discovered prior to construction. Too often these errors are realized only after a project is completed.3

Some argue that Americans have become less parochial. International travel, immi- gration, movies, and the popularity of such international events as the Olympics have made more Americans sensitive to cultural differences. While Americans may be more worldly, there is still a tendency for them to believe that American cultural values and ways of doing things are superior to all others. This ethnocentric perspective is reflected in wanting to conduct business only on their terms and stereotyping other countries as lazy, corrupt, or inefficient. Americans need to make a serious effort to appreciate other ways of approaching work and problems in other countries.

Finally, American project managers have earned a reputation abroad for being very good at understanding technology but not good at understanding people. As one I ndonesian engineer put it, “Americans are great at solving technical problems, but they tend to ignore the people factor.” For example, Americans tend to underestimate the importance that relationship building plays in conducting business in other coun- tries. Americans have a tendency to want to get down to work and let friendships evolve in the course of their work. In most other cultures just the opposite is true. Before a foreigner works with you, he wants to get to know you as a person. Trust is not established by credentials but rather evolves from personal interaction. Business deals often require a lengthy and elaborate courtship (Arms and Lucas, 1978; Chen and Miller, 2010). For example, it may take five to eight meetings before Arab manag- ers are even willing to discuss business details.

Adjustments Two of the biggest adjustments Americans typically have to make in working abroad are adapting to the general pace of life and the punctuality of people. In America “time is money,” and a premium is placed on working quickly. Other cultures do not share Americans’ sense of urgency and are accustomed to a much slower pace of life. They can’t understand why Americans are always in such a hurry. Punctuality varies across cultures. For example, Americans will generally tolerate someone being 5 to 10 min- utes late. In contrast, among Peruvians, the period before an apology or explanation for being late is expected might be 45 minutes to an hour!

While working on multicultural projects, managers sometimes encounter ethical dilemmas that are culturally bound. For example, the 1999 Olympic site selection scandal featured the sordid details of committee members peddling their votes for a wide range of gifts (i.e., university scholarships for their children, extravagant trips). In many societies such “bribes” or “tributes” are expected and the only way to conduct meaningful business. Moreover, many cultures will not grant a female project manager

3 This incident was cited in H. W. Lane and J. J. DiStefano, International Project Management, 2nd ed. (Boston: PWS-Kent, 1992), p. 27.

556 Chapter 15 International Projects

the same respect they will a male project manager. Should U.S. management increase project risk or violate its own sex-discrimination policy?

These cultural differences are just the tip of the iceberg. There are numerous “How to Do Business in . . .” books written by people who have traveled and worked abroad. Although these books may lack rigor, they typically do a good job of identifying local customs and common mistakes made by outsiders. On the other hand, anthropologists have made significant contributions to our understanding of why and how the cultures of societies are different (see Research Highlights 15.1 and 15.2). Students of interna- tional project management are encouraged to study these works to gain a deeper under- standing of the root causes of cultural diversity.

So what can be said to prepare people to work on international projects? The world is too diverse to do justice in one chapter to all the cultural variations managers are likely to encounter when working on international projects. Instead, a sample of some of these differences will be highlighted by discussing working on projects in four dif- ferent countries: Mexico, France, Saudi Arabia, and China. We apologize to our read- ers outside the United States because briefings are presented from the viewpoint of a U.S. project manager working in these countries. Still, in an effort not to be too ethno- centric, we present a fifth scenario for foreign project managers assigned to working in the United States. Although by no means exhaustive, these briefings provide a taste of what it is like to work in and with people from these countries.

Working in Mexico America developed historically in an environment where it was important for strangers to be able to get along, interact, and do business. On the American frontier almost everyone was a stranger, and people had to both cooperate and keep their distance. The New England Yankee sentiment that “Good fences make good neighbors” expresses this American cultural value well. Conversely, Mexico developed historically in an environment where the only people to trust were family and close friends—and by extension, people who were known to those whom you knew well. As a consequence, personal relationships dominate all aspects of Mexican business. While Americans are generally taught not to do business with friends, Mexicans and other Latin Americans are taught to do business with no one but friends.

The significance of personal relationships has created a compadre system in which Mexicans are obligated to give preference to relatives and friends when hiring, con- tracting, procuring, and sharing business opportunities. North Americans often com- plain that such practices contribute to inefficiency in Mexican firms. While this may or may not be the case, efficiency is prized by Americans, while Mexicans place a higher value on friendship.

Mexicans tend to perceive Americans as being “cold.” They also believe that most Americans look down on them. Among the most effective things an American can do to prevent being seen as a typical Gringo is to take the time and effort in the beginning of a working relationship to really get to know Mexican counterparts. Because family is all-important to Mexicans, a good way for developing a personal relationship is exchanging information about each other’s family. Mexicans will often gauge people’s trustworthiness by the loyalty and attention they devote to their family.

The mañana syndrome reflects another cultural difference between Americans and Mexicans. Mexicans have a different concept of time than Americans do. Mexicans feel confined and pressured when given deadlines; they prefer open-ended schedules.

Anthropologists Kluckhohn and Strodtbeck assert that cultural varia- tions reflect how different societies have responded to common issues or problems throughout time (see

Figure 15.4). Five of the issues featured in their com- parative framework are discussed here.

Relationship to nature—This issue reflects how people relate to the natural world around them and to the supernatural. Should people domi- nate their environment, live in harmony with it, or be subjugated to it? North Americans generally strive to harness nature’s forces and change them as they need. Other societies, as in India, strive to live in harmony with nature. Still other societies see themselves at the mercy of physi- cal forces and/or subject to the will of a supreme being. Life in this context is viewed as predeter- mined, preordained, or an exercise in chance. Time orientation—Does the culture focus on the past, present, or future? For example, many Euro- pean countries focus on the past and emphasize maintaining tradition. North Americans, on the other hand, are less concerned with tradition and tend to focus on the present and near future. Paradoxically, Japanese society, while rich with tradition, has a much longer time horizon. Activity orientation—This issue refers to a desir- able focus of behavior. Some cultures emphasize “being” or living in the moment. This orientation stresses experiencing life and seeking immedi- ate gratification. Other cultures emphasize “doing” and emphasize postponing immediate gratification for greater accomplishment. A third alternative is the “control” orientation, where

people restrain their desires by detaching them- selves from objects. The activity dimension affects how people approach work and leisure and the extent to which work-related concerns pervade their lives. It is reflected in the age-old question, “Do we live to work or work to live?” Basic nature of people—Does a culture view peo- ple as good, evil, or some mix of these two? In many Third World countries, people see them- selves as basically honest and trustworthy. Con- versely, some Mediterranean cultures have been characterized as taking a rather evil view of human nature. North Americans are somewhere in between. They see people as basically good but stay on guard so as not to be taken advantage of. Relationships among people—This issue con- cerns the responsibility one has for others. Americans, for instance, tend to be highly indi- vidualistic and believe everyone should take care of him- or herself. In contrast, many Asian societies emphasize concern for the group or community he or she is a member of. A third variation is hierarchical, which is similar to the group except that in these societies groups are hierarchically ranked, and membership is essentially stable over time. This is a character- istic of aristocratic societies and caste systems.

The Kluckhohn and Strodtbeck framework provides a basis for a deeper understanding of cultural differ- ences. At the same time, they warn that not all mem- bers of a culture practice the same behavior all the time, and, as in the United States, there is likely to be considerable variation within a given culture.

Research Highlight 15.1 Cross-Cultural Orientations*

* F. Kluckhohn and F. L. Strodtbeck, Variations in Value Orientations (Evanston, IL: Row, Peterson, 1961).

FIGURE 15.4 Kluckhohn- Strodtbeck’s Cross- Cultural Framework

Note: The line indicates where the United States tends to fall along these issues.

Cultural issue

Relationship to nature

Time orientation

Activity orientation

Nature of people

Relationships among people

Variations

Domination

Past

Being

Good

Individualist

Harmony

Present

Doing

Evil

Group

Subjugation

Future

Controlling

Mixed

Hierarchical

557

The Hofstede framework grew from a study of 88,000 people working in IBM subsidiaries in 50 countries and 3 multicountry regions. Based on responses to a 32-item question-

naire, Dutch social scientist Geert Hofstede developed different dimensions for examining cultures:

1. Individualism versus collectivism. Identifies whether a culture holds individuals or the group responsible for each member’s welfare.

2. Power distance. Describes the degree to which a culture accepts status and power differences among its members.

3. Uncertainty avoidance. Identifies a culture’s willingness to accept uncertainty and ambiguity about the future.

4. Masculinity-femininity. Describes the degree to which the culture emphasizes competitive and achievement-oriented behavior or displays concerns for relationships.

Figure 15.5 shows how he ranked selected coun- tries according to collectivism-individualism and

power distance. Wealth appears to influence both factors. Power distance is correlated with income inequality in a country while individualism is corre- lated with national wealth (Per Capita Gross National Product). As a result high power distance and collec- tivism are often found together, as are low power distance and individualism. This can affect decision making on project teams. For example, while the high collectivism may lead a project team in Thailand to operate consensually, the high power distance may cause decisions to be heavily influenced by the desires of the project manager. Conversely, a similar team operating in a more individualistic and low power distance context such as Great Britain or America might make decisions with more open debate including challenging the preferences of the project manager.

Research Highlight 15.2 Hofstede Framework*

* G. Hofstede, Culture’s Consequences: Comparing Values, Behaviors, Institutions and Organizations Across Nations, 2nd Edition (Thousand Oaks, CA: Sage Publications, 2001). http://www.geerthofstede.nl

FIGURE 15.5 Sample Country Clusters on Hofstede’s Dimensions of Individualism-Collectivism and Power Distance

Collectivism

Individualism Israel, Finland, Germany, Ireland, New Zealand, Canada, Great Britain, United States

Low power distance

Colombia, Peru, Thailand, Singapore, Mexico, Turkey, Indonesia

Spain, South Africa, France, Italy, Belgium

High power distance

They generally consider individuals to be more important than sticking to a schedule. If a friend drops in at work, most Mexicans will stop and talk, regardless of how long it takes, and even if chatting makes their work late. This sometimes contributes to the erroneous perception that Mexicans lack a work ethic. Quite the contrary; given a minimal incentive, Mexicans can be quite industrious and ambitious.

Finally, as in many other cultures, Mexicans do not share Americans’ confidence that they control their own destiny. While Americans are taught, “When the going gets tough, the tough get going,” Mexicans are taught, “Taking action without knowing what is expected or wanted can have dangerous consequences.” Mexicans tend to be more cautious and want to spend more time discussing risks and potential problems that Americans might dismiss as improbable or irrelevant.

558

Chapter 15 International Projects 559

Other useful guidelines for working with Mexicans on projects include the following: 1. Americans tend to be impersonal and practical when making arguments; Mexicans

can be very passionate and emotional when arguing. They enjoy a lively debate. 2. Where Americans tend to use meetings as the place to work things out publicly,

Mexicans tend to see meetings as the place where persons with authority ratify what has been decided during informal private discussions.

3. While Mexicans can be emotional, they tend to shy away from any sort of direct confrontation or criticism. A long silence often indicates displeasure or disagreement.

4. Speech in Mexico is often indirect. People rarely say no directly but are more likely to respond by saying maybe (quizas), or by saying “I will think about it” or changing the subject. Yes (si) is more likely to mean “I understand you” than “yes.”

5. Titles are extremely important in Mexico and are always used when a person is introducing him- or herself or being introduced. Pay as much attention to remem- bering a person’s title as to remembering his or her name.

Today, with NAFTA and increased international business activity in Mexico, old tradi- tions are disappearing. American managers report that cultural differences are less evident in northern Mexico where many multinational firms operate. Here hora ameri- cana (American time) rather than hora mexicana tends to be used when dealing with foreigners. Project managers should devote up-front effort to understanding how much older mores of Mexican culture apply to their project.4

Working in France Some Americans consider the French the most difficult to work with among Europe- ans. This feeling probably stems from a reflection of the French culture, which is quite different from that in the United States.

In France, one’s social class is very important. Social interactions are constrained by class standing, and during their lifetimes most French people do not encounter much change in social status. Unlike an American, who through hard work and success can move from the lowest economic stratum to the highest, a successful French person might, at best, climb one or two rungs up the social ladder. Additionally, the French are very status conscious and like to provide signs of this status, such as knowledge of literature and arts; a well-designed, tastefully decorated house; and a high level of education.

The French tend to admire or be fascinated with people who disagree with them; in contrast, Americans are more attracted to those who agree with them. As a result, the French are accustomed to conflict and, during negotiations, accept the fact that some positions are irreconcilable and must be accepted as such. Americans, on the other hand, tend to believe that conflicts can be resolved if both parties make an extra effort and are willing to compromise. Also, the French often determine a person’s trustwor- thiness based on their first-hand, personal evaluation of the individual’s character. Americans, in contrast, tend to evaluate a person’s trustworthiness on the basis of past achievements and other people’s evaluations.

4 Adapted from E. Kras, Management in Two Cultures: Bridging the Gap between U.S. and Mexican Managers, rev. ed. (Yarmouth, ME: Intercultural Press, 1995); L. W. Tuller, An American’s Guide to Doing Business in Latin America (Avon, MA: Adams Business, 2008).

560 Chapter 15 International Projects

The French are often accused of lacking an intense work ethic. For example, many French workers frown on overtime and on average they have one of the lon- gest vacations in the world (four to five weeks annually). On the other hand, the French enjoy a reputation for productive work, a result of the French tradition of craftsmanship. This tradition places a greater premium on quality than on getting things accomplished quickly.

Most French organizations tend to be highly centralized with rigid structures. As a result, it usually takes longer to carry out decisions. Because this arrangement is quite different from the more decentralized organizations in the United States, many U.S. project managers find the bureaucratic red tape a source of considerable frustration.

In countries like the United States, a great deal of motivation is derived from profes- sional accomplishments. The French do not tend to share this same view of work. While they admire American industriousness, they believe that quality of life is what really matters. As a result they attach much greater importance to leisure time, and many are unwilling to sacrifice the enjoyment of life for a dedication to project work.

Cautions to remember with the French include these: 1. The French value punctuality. It is very important to be on time for meetings and

social occasions. 2. Great importance is placed on neatness and taste. When interacting with French

businesspeople, pay close attention to your own professional appearance and appear cultured and sophisticated.

3. The French can be very difficult to negotiate with. Often, they ignore facts, no mat- ter how convincing they may be. They can be quite secretive about their position. It is difficult to obtain information from them, even in support for their position. Patience is essential for negotiating with them.

4. French managers tend to see their work as an intellectual exercise. They do not share the American view of management as an interpersonally demanding exercise, where plans have to be constantly “sold” upward and downward using personal skills.

5. The French generally consider managers to be experts. They expect managers to give precise answers to work-related questions. To preserve their reputation, some French managers act as if they know the answers to questions even when they don’t.5

Working in Saudi Arabia Project management has a long tradition in Saudi Arabia and other Arab countries. Financed by oil money, European and American firms have contributed greatly to the modernization of Arab countries. Despite this tradition, foreigners often find it very hard to work on projects in Saudi Arabia. A number of cultural differences can be cited for this difficulty.

One is the Arabian view of time. In North America, it is common to use the cliché, “The early bird gets the worm.” In Saudi Arabia, a favorite expression is, “Bukra insha Allah,” which means, “Tomorrow if God wills,” an expression that reflects the Saudis’ approach to time. Unlike Westerners, who believe they control their own time, Arabs believe that Allah controls time. As a result, when Saudis commit themselves to a date in the future and fail to show up, there is no guilt or concern on their part because they have

5 Adapted from R. Hallowell, D. Bowen, and C. I. Knoop, “Four Seasons Goes to Paris,” Academy of Management Executive, 16 (4) November 2002, pp. 7–24; J. Hooker, Working across Cultures (Stanford, CA: Stanford Business Books, 2003); T. Morrison and W. A. Conaway, Kiss, Bow, or Shake Hands (The Bestselling Guide to Doing Business in More than 60 Coun- tries), 2nd ed. (New York: Adams Media, 2006).

Chapter 15 International Projects 561

no control over time in the first place. In planning future events with Arabs, it pays to hold lead time to a week or less, because other factors may intervene or take precedence.

An associated cultural belief is that destiny depends more on the will of a supreme being than on the behavior of individuals. A higher power dictates the outcome of impor- tant events, so individual action is of little consequence. As a result, progress or the lack of progress on a project is considered more a question of fate than effort. This leads Saudis to rely less on detailed plans and schedules to complete projects than Americans do.

Another important cultural contrast between Saudi Arabians and Americans is emo- tion and logic. Saudis often act on the basis of emotion; in contrast, those in an Anglo culture are taught to act on logic. During negotiations, it is important not only to share the facts but also to make emotional appeals that demonstrate your suggestion is the right thing to do.

Saudis also make use of elaborate and ritualized forms of greetings and leave- takings. A businessperson may wait far past the assigned meeting time before being admitted to a Saudi office. Once there, the individual may find a host of others present; one-on-one meetings are rare. Moreover, during the meeting there may be continuous interruptions. Visitors arrive and begin talking to the host, and messengers may come in and go out on a regular basis. The businessperson is expected to take all this activity as perfectly normal and to remain composed and ready to continue discussions as soon as the host is prepared to do so.

Initial meetings are typically used to get to know the other party. Business-related discussions may not occur until the third or fourth meeting. Business meetings typi- cally conclude with an offer of coffee or tea. This is a sign that the meeting is over and that future meetings, if there are to be any, should now be arranged.

Saudis attach a great deal of importance to status and rank. When meeting with them, defer to the senior person. It is also important never to criticize or berate anyone publicly. This causes the individual to lose face; the same is true for the person who makes these comments. Mutual respect is expected at all times.

Other useful guidelines for working in an Arab culture such as Saudi Arabia include the following: 1. It is important never to display feelings of superiority because this makes the other

party feel inferior. No matter how well someone does something, the individual should let the action speak for itself and not brag or draw attention to himself.

2. A lot of what gets done is a result of going through administrative channels in the country. It is often difficult to sidestep a lot of this red tape, and efforts to do so can be regarded as disrespect for legal and governmental institutions.

3. Connections are extremely important in conducting business. More important peo- ple get fast service from less important people. Close relatives take absolute prior- ity; non-relatives are kept waiting.

4. Patience is critical to the success of business negotiations. Time for deliberations should be built into all negotiations to prevent a person from giving away too much in an effort to reach a quick settlement.

5. Important decisions are usually made in person and not by correspondence or tele- phone. While Saudis seek counsel from many people, the ultimate power to make a decision rests with the person at the top, and this individual relies heavily on personal impressions, trust, and rapport.6

6 Adapted from R. T. Moran, P. R. Harris, and S. V. Moran, Managing Cultural Differences, 5th ed. (Houston, TX: Gulf Publishing, 2010); and J. Hooker, Working across Cultures (Stanford, CA: Stanford Business Books, 2003).

562 Chapter 15 International Projects

Working in China In recent years the People’s Republic of China (PRC, or China, for short) has moved away from isolation to encourage more business with the rest of the world. While China holds tremendous promise, many Western firms have found working on projects in China to be a long, grueling process that often results in failure. One of the primary reasons for problems is the failure to appreciate Chinese culture.

Chinese society, like those of Japan and Korea, is influenced by the teachings of Confucius (551–478 B.C.). Unlike America, which relies on legal institutions to regulate behavior, in Confucian societies the primary deterrent against improper or illegal behavior is shame or loss of face. Face is more than simply reputation. There is a Chinese saying: “Face is like the bark of a tree; without its bark, the tree dies.” Loss of face not only brings shame to individuals but also to family members. A member’s actions can cause shame for the entire family, hampering that family from working effectively in Chinese society.

In China, “whom you know is more important than what you know.” The term guanxi refers to personal connections with appropriate authorities or individuals. China observers argue that guanxi is critical for working with the Chinese. Chinese are raised to distrust strangers, especially foreigners. Trust is transmitted via guanxi. That is, a trusted business associate of yours must pass you along to his trusted business associates. Many outsiders criticize guanxi, considering it to be like nepotism where decisions are made regarding contracts or problems based on family ties or connec- tions instead of an objective assessment of ability.

Many believe that the quickest way to build guanxi relationships is through tender- ing favors. Gift-giving, entertainment at lavish banquets, questionable payments, and overseas trips are common. While Westerners see this as nothing short of bribery, the Chinese consider it essential for good business. Another common method for outsiders to acquire guanxi is by hiring local intermediaries, who use their connections to create contacts with Chinese officials and businesspeople.

In dealing with the Chinese, you must realize they are a collective society in which people pride themselves on being a member of a group. For this reason, you should never single out a Chinese for specific praise because this is likely to embarrass the individual in front of his peers. At the same time, you should avoid the use of “I” because it conveys that the speaker is drawing attention to himself or herself.

Chinese do not appreciate loud, boisterous behavior, and when speaking to each other they maintain a greater physical distance than is typical in America. Other cau- tions include the following: 1. Once the Chinese decide who and what is best, they tend to stick to their decisions.

So while they may be slow in formulating a plan, once they get started they make good progress.

2. Reciprocity is important in negotiations. If Chinese give concessions, they expect some in return.

3. The Chinese tend to be less animated than Americans. They avoid open displays of affection and physical contact; they are more reticent and reserved than Americans.

4. The Chinese place less value on the significance of time and often get Americans to concede concessions by stalling.

5. In Confucian societies those in position of power and authority are obligated to assist the disadvantaged. In return they gain face and a good reputation.7

7 Adapted from J. L. Graham and N. M. Lam, “The Chinese Negotiation,” Harvard Business Review, October 1, 2003, pp. 82–91; I. Yeung and R. L. Tung, “Achieving Business Success in Confucian Societies: The Importance of Guanxi (Connections),” Organizational Dynamics, 25 (2) Autumn 1996, pp. 54–65; and Hooker, Working across Cultures.

Chapter 15 International Projects 563

For more insights on Chinese culture see the Snapshot from Practice 15.3: Project Management X-Files.

Working in the United States In the world of international projects, professionals from other countries will come to the United States to manage projects. To them, the United States is a foreign assignment. They will have to adapt their management style to the new environment they find in the States.

Immigration has made the United States a melting pot of diverse cultures. While many are quick to point out the differences between North and South, Silicon Valley and Wall Street, social anthropologists have identified certain cultural characteristics that shape how many Americans conduct business and manage projects.

Mainstream Americans are motivated by achievement and accomplishment. Their identity and, to a certain extent, their self-worth are measured by what they have achieved. Foreigners are often astounded by the material wealth accumulated by Americans and the modern conveniences most Americans enjoy. They are also quick to point out that Americans appear too busy to truly enjoy what they have achieved.

Americans tend to idolize the self-made person who rises from poverty and adversity to become rich and successful. Most Americans have a strong belief that they can influence and create their future, that with hard work and initiative, they can achieve whatever they set out to do. Self-determination and pragmatism dominate their approach to business.

Americans tend to discount the signifi- cance of luck and believe that good fortune is generally a result of hard work. In other cultures, luck takes on greater significance and has supernat-

ural ramifications. For example, in many Asian cultures certain numbers are considered lucky, while others are unlucky. In Hong Kong the numbers 7, 3, and especially 8 (which sounds like the word for prosperity) are consid- ered lucky, while the number 4 is considered unlucky (because it is pronounced like the word “death”). Hong Kong businesspeople go to great lengths to avoid the number 4. For example, there is no fourth floor in office and hotel buildings. Business executives have been known to reject ideal sites in heavily congested Hong Kong because the address would contain the number 4. They pay premium prices for suitable sites containing addresses with the lucky numbers. Likewise, Hong Kong business managers avoid scheduling important events on the fourth day of each month and prefer to arrange critical meetings on the eighth day. Hong Kong is also a place where the ancient art of Feng shui (literally “wind water”) is practiced. This involves making sure a site and buildings are aligned in harmony with the earth’s energy forces so that the location will be propitious. Feng shui practitioners are often called in on construction projects to make sure

that the building is aligned correctly on the site. In some cases, the technical design of the building is changed to conform to the recommendations of such experts. Similarly, Feng shui experts have been known to be called in when projects are experiencing prob- lems. Their recommendations may include reposition- ing the project manager’s desk or hanging up mirrors to deflect the flow of unharmonious influences away from the building or site of the project. In cultures where luck is believed to play a role in business, people who discount luck may not only insult the luck seekers, but risk being thought negligent in not paying enough attention to what is viewed as a legitimate business concern.

S N A P S H O T F R O M P R A C T I C E 1 5 . 3 Project Management X-Files

© bikeriderlondon/Shutterstock

564 Chapter 15 International Projects

Although Americans like to set precise objectives, they view planning as a means and not an end. They value flexibility and are willing to deviate from plans and impro- vise if they believe change will lead to accomplishment. Obstacles on a project are to be overcome, not worked around. Americans think they can accomplish just about anything, given time, money, and technology.

Americans fought a revolution and subsequent wars to preserve their concept of democracy, so they resent too much control or interference, especially by governments. While more an ideal than practice, there is deep-rooted belief in American management philosophy that those people who will be affected by decisions should be involved in making decisions. Many foreign businesspeople are surprised at the amount of autonomy and decision-making authority granted to subordinates. Foreign personnel have to learn to interact with American professionals below their rank in their own organizations.

Businesspeople from different African, Asian, and Latin American countries are amazed and often somewhat distressed at the rapid pace of America. “Getting things done” is an American characteristic. Americans are very time-conscious and efficient. They expect meetings to start on time. They tinker with gadgets and technological systems, always searching for easier, better, more efficient ways of accomplishing things. American professionals are often relentless in pursuing project objectives and expect that behavior of others also.

Americans in play or business generally are quite competitive, reflecting their desire to achieve and succeed. Although the American culture contains contradictory mes- sages about the importance of success (i.e., “It’s not whether you win or lose but how you play the game” versus “nice guys finish last”), winning and being number one are clearly valued in American society. Foreigners are often surprised at how aggressively Americans approach business with adversarial attitudes toward competitors and a desire to not just meet but to exceed project goals and objectives.

Other guidelines and cautions for working with Americans on projects include: 1. More than half of U.S. women work outside the home; females have considerable

opportunity for personal and professional growth, guaranteed by law. It is not uncommon to find women in key project positions. Female professionals expect to be treated as equals. Behavior tolerated in other countries would be subject to harassment laws in the States.

2. In the United States, gifts are rarely brought by visitors in a business situation. 3. Americans tend to be quite friendly and open when first meeting someone. Foreign-

ers often mistake this strong “come-on” for the beginning of a strong reciprocal friendship. This is in contrast to many other cultures where there is more initial reserve in interpersonal relations, especially with strangers. For many foreigners, the American comes on too strong, too soon, and then fails to follow up with the implicitly promised friendship.

4. Although in comparison to the rest of the world Americans tend to be informal in greeting and dress, they are a noncontact culture (e.g., they avoid embracing in pub- lic usually) and Americans maintain certain physical/psychological distance with others (e.g., about two feet) in conversations.

5. American decision making is results oriented. Decisions tend to be based on facts and expected outcomes, not social impact.8

8 Adapted from Moran et al., Managing Cultural Differences; and D. Z. Milosevic, “Echoes of the Silent Language of Project Management,” Project Management Journal, 30 (1) March 1999, pp. 27–39.

Chapter 15 International Projects 565

Summary Comments about Working in Different Cultures These briefings underscore the complexity of working on international projects. It is common practice to rely on intermediaries—often natives who are foreign educated— to bridge the gap between cultures. These intermediaries perform a variety of func- tions. They act as translators. They use their social connections to expedite transactions and protect the project against undue interference. They are used to sidestep the touchy bribery/gift dilemma (see Snapshot from Practice 15.4: Dealing with Customs). They serve as cultural guides, helping outsiders understand and interpret the foreign culture. In today’s world, there are a growing number of consulting firms that perform these functions by helping foreign clients work on projects in their country.

The international briefings also highlight the importance of project managers doing their homework and becoming familiar with the customs and habits of the host country they are going to be working in. As far as possible, the project should be managed in such a way that local-country norms and customs are honored. However, there are limits to the extent to which you should accommodate foreign cultures. Going native is generally not an alternative. After all, it took a Russian his entire life to learn how to be a Russian. It would be foolish to think an outsider could learn to be one in six months, two years, or perhaps ever.

The remainder of this chapter focuses on the selection and training of project per- sonnel for international projects. But before these issues are discussed, this section concludes with a discussion of the phenomenon of culture shock, which can have a profound effect on a foreigner’s performance on a project in a strange culture.

Culture Shock My first few weeks in Chiang Mai [Thailand] were filled with excitement. I was excited about the challenge of building a waste treatment plant in a foreign country. I was fascinated with Thai customs and traditions, the smells and sights of the night market. Soon I noticed a distinct change in my attitude and behavior. I started having problems sleeping and lacked energy. I became irritable at work, frustrated by how long things took to accomplish, and how I couldn’t seem to get anything accomplished. I started staying up late at night drinking Thai whiskey and watching CNN in my hotel room.

Will corruption influence the project? Bribes are illegal in the United States, but in some countries they are the usual way to do business. For example, one American project man- ager in a foreign country requested

that a shipment of critical project equipment be sent “overnight rush.” Two days later, inquiries to the sender confirmed the materials had been delivered to the nearby airport. Further inquiries to the port found the shipment “waiting to pass customs.” Locals quickly informed the American that money paid to the chief customs inspector would expedite clearance. The American project manager’s response

was, “I will not be held hostage. Bribes are illegal!” Two more days of calling government officials did not move the shipment from customs. The manager related his problem to a friendly businessman of the host nation at a social affair. The local businessman said he would see if he could help. The shipment arrived the next morning at 10:00 A.M. The American called his local business friend and thanked him pro- fusely. “I owe you one.” “No,” replied the local. “You owe me a $50 dinner when I visit you in the States.” The use of an intermediary in such situations may be the only avenue available to a manager to reduce the stress and personal conflict with the U.S. value system.

S N A P S H O T F R O M P R A C T I C E 1 5 . 4 Dealing with Customs

566 Chapter 15 International Projects

This engineer is experiencing what many would call “culture shock.” Culture shock is a natural psychological disorientation that most people suffer when they move into a cul- ture different from their own. The culture shock cycle has four stages (see Figure 15.6): 1. Honeymoon—You start your overseas assignment with a sense of excitement. The

new and the unusual are welcomed. At first it is amusing not to understand or be understood. Soon a sense of frustration begins to set in.

2. Irritability and hostility—Your initial enthusiasm is exhausted, and you begin to notice that differences are greater than you first imagined. You become frustrated by your inability to get things done as you are accustomed to. You begin to lose confidence in your abilities to communicate and work effectively in the different culture.

3. Gradual adjustment—You begin to overcome your sense of isolation and figure out how to get things done in the new culture. You acquire a new perspective of what is possible and regain confidence in your ability to work in the culture.

4. Adaptation—You recover from your sense of psychological disorientation and begin to function and communicate in the new culture.

Culture shock is not a disease but a natural response to immersing yourself in a new environment. Culture shock results from a breakdown in your selective perception and effective interpretation system. At a subliminal level, your senses are being bombarded by a wide variety of strange sounds, sights, and smells. At the same time, the normal assumptions you are accustomed to using in your home culture to interpret perceptions and to communicate intentions no longer apply. When this happens, whether in a busi- ness context or in normal attempts to socialize, confusion and frustration set in. The natives’ behavior does not seem to make sense, and, even more importantly, your behav- ior does not produce expected results. Frustration occurs because you are used to being competent in such situations and now find you are unable to operate effectively.

Culture shock is generally considered a positive sign that the professional is becom- ing involved in the new culture instead of remaining isolated in an expatriate ghetto. The significant question is how best to manage culture shock, not how to avoid it. The key appears to be managing the stress associated with culture shock.

Stress-related culture shock takes many forms: disappointment, frustration, with- drawal, anxiety, and physiological responses such as fatigue, sleeplessness, and head- aches. Stress is induced by the senses being overwhelmed by foreign stimuli and the

FIGURE 15.6 Culture Shock Cycle Mood

High

Honeymoon

Irritability and hostility

Gradual adjustment

Adaptation

Months in foreign culture Low

15-4LO Describe culture shock and strategies for coping with it.

Chapter 15 International Projects 567

inability to function effectively in a strange land. Stress is exacerbated when one encounters disturbing situations that, as a foreigner, are neither understood nor con- doned. For example, many North Americans are appalled by the poverty and hunger in many underdeveloped countries.

Coping with Culture Shock There are a wide range of stress management techniques for coping with culture shock. One method does not necessarily work any better than another; success depends on the particular individual and situation involved. Some people engage in regular physical exercise programs, some practice meditation and relaxation exercises, and others find it healthy to keep a journal.

Many effective international managers create “stability zones.” They spend most of their time immersed in the foreign culture but then briefly retreat into an environment— a stability zone—that closely re-creates home. For example, when one of the authors was living in Kraków, Poland, with his family, they would routinely go to the Polish movie houses to see American movies with Polish subtitles. The two hours spent hear- ing English and seeing a familiar environment on the screen had a soothing effect on everyone.

On the project, managers can reduce the stress caused by culture shock by recognizing it and modifying their expectations and behavior accordingly. They can redefine priori- ties and develop more realistic expectations as to what is possible. They can focus their limited energy on only the most important tasks and relish small accomplishments.

After three to six months, depending on the individual and assignment, most people come up from their culture shock “low” and begin living a more normal life in the foreign country. They talk to acquaintances from the host country and experienced outsiders from their own culture to find out how to behave and what to expect. Little by little they learn how to make sense of the new environment. They figure out when “yes” means “yes” and when it means “maybe” and when it means “no.” They begin to master the language so that they can make themselves understood in day-to-day conversations. See the Snapshot from Practice 15.5: Project X—Namibia, Africa, for further insights on coping with culture shock.

The vast majority of people eventually make the adjustment, although for some people it can take much longer than three to six months. A smaller number never recover, and their international experience turns into a nightmare. Some exhibit severe stress symptoms (e.g., alcoholism, drug abuse, nervous breakdown) and must return home before finishing their assignment.

Professionals can use project work as a bridge until they adjust to their new environ- ment. Unfortunately, spouses who do not work do not have this advantage. When spouses are left to cope with the strange environment on their own, they often have a much more difficult time overcoming culture shock. The effect on spouses cannot be underestimated. The number one reason expatriate managers return home is that their spouses failed to adjust to the new environment (Tung, 1987).

Project professionals working overseas accept that they are in a difficult situation and that they will not act as effectively as they did at home, especially in the initial stages. They recognize the need for good stress management techniques, including stability zones. They also recognize that it is not an individual problem and invest extra time and energy to help their spouses and families manage the transition. At the same time, they appreciate that their colleagues are experiencing similar problems and are sensitive to their needs. They work together to manage the stress and pull out of a cul- ture shock low as quickly as possible.

568 Chapter 15 International Projects

It is somewhat ironic, but people who work on projects overseas experience culture shock twice. Many professionals experience the same kind of disorientation and stress when they return home, although it is usually less severe. For some, their current job has less responsibility and is boring compared with the challenge of their overseas assignment. For others, they have problems adjusting to changes made in the home organization while they were gone. This can be compounded by financial shock when the salary and fringe benefits they became accustomed to in the foreign assignment are now lost, and adjusting to a lower standard of living is difficult. It typically takes six months to a year before managers operate again at full effectiveness after a lengthy foreign assignment (Adler and Gunderson, 2007).

15.4 Selection and Training for International Projects When professionals are selected for overseas projects and they do not work out, the overall costs can be staggering. Not only does the project experience a serious setback, but the reputation of the firm is damaged in the region. This is why many firms have developed formal screening procedures to help ensure the careful selection of person- nel for international projects. Organizations examine a number of characteristics to determine whether an individual is suitable for overseas work. They may look for work experience with cultures other than one’s own, previous overseas travel, good physical

While U.S. reality TV shows focus on finding love, outwitting opponents, and garnering audience support, a Norwegian TV show shone a light on project management under extreme

conditions. The plot was deceptively simple: send 10 Scandinavian volunteers 6,000 miles away from home to the dry sub-tropics of southern Africa and charge them with building a school for orphans and poor chil- dren in less than 30 days. Not only would they be forced to adjust to vastly different language, climate, and cuisines, but only one of the 10 had previous con- struction experience. The team’s trials and tribulations were aired over Norwegian TV in 2009. The marketing blitz for the show, titled Project X, played up the drama with the tagline: “Can they achieve the mission?” The team was enthusiastic at the outset, but discon- tent began as soon as they arrived at the small mining town of Tsumeb in Namibia. The team immediately experienced culture shock—all the while the TV crew followed them, sticking cameras in their faces and ask- ing how they felt. The sweltering heat, slumlike conditions, and lim- ited cuisine immediately elicited complaints: “I can’t sleep.” “The food is awful.” “Where are the toilets?”

S N A P S H O T F R O M P R A C T I C E 1 5 . 5 Project X—Namibia, Africa*

One of the biggest mistakes the volunteers made was applying a Eurocentric sense of time and planning. “I brought my Danish mindset that ‘On Friday we will do this and on Saturday we will do that,’” reported Merete Lange, one of the volunteers. “Then I came to under- stand African time, and that was the biggest surprise.” Hoping to secure local buy-in, Ms. Lange arranged for a local carpenter to build desks and tables. A few days before the furniture was needed, she discovered work hadn’t even begun. “I got pretty stressed and tried to be my best at being diplomatic,” Ms. Lange recalls. “I asked, ‘When do you think you will be ready with the furniture?’” The carpenter responded, “Time is unpredictable. I will call you.” Over time, Ms. Lange and her teammates were able to adapt to the elements and figure out ways to work with the locals to successfully build the school within 30 days. “The trick is reflecting upon ‘where people were coming from, how to meet them there, and how to create a win-win situation that would satisfy both parties.’”

* B. G. Yovovich, “Worlds Apart,” PMNetwork, October 2010, pp. 24–29.

15-5LO Understand how organizations select and prepare people to work on international projects.

Chapter 15 International Projects 569

and emotional health, a knowledge of a host nation’s language, and even recent immi- gration background or heritage. Prospective candidates and their family members are often interviewed by trained psychologists, who assess their ability to adapt and func- tion in the new culture.

While there is growing appreciation for screening people for foreign assignments, the number one reason for selection is that the personnel assigned are the best people available for the technical challenges of the project (Mendenhall et al., 1987). Techni- cal know-how takes precedence over cross-cultural sensitivity or experience. As a consequence, training is critical to fill in the cultural gaps and prepare individuals to work in a foreign land.

Training varies widely, depending on the individual, company, nature of the project, and cultures to work with. Project professionals assigned to foreign countries should have a minimal understanding of the following areas: ∙ Religion. ∙ Dress codes. ∙ Education system. ∙ Holidays—national and religious. ∙ Daily eating patterns. ∙ Family life. ∙ Business protocols. ∙ Social etiquette. ∙ Equal opportunity. An example of a short-term training program is the one developed by Underwriter Laboratories, Inc., to train staff who travel to Japan to work with clients on projects. The program is designed around a series of mini-lectures that cover topics ranging from how to handle introductions to the proper way to exchange gifts to the correct way of interpreting Japanese social and business behavior. The two-day program consists of lectures, case studies, role plays, language practice, and a short test on cultural termi- nology; it concludes with a 90-minute question-and-answer period. At the end of the program, participants have a fundamental understanding of how to communicate with the Japanese. More importantly, they know the types of information they lack and how to go about learning more to become effective intercultural communicators.

Other training programs are more extensive. For example, Peace Corps volunteers undergo an intense two- to four-month training program in their country of service. The training includes classes on the history and traditions of the country, intensive language instruction, and cross-cultural training as well as home-stays with local fami- lies. Many companies outsource training to one of the many firms specializing in overseas and intercultural training.

Figure 15.7 attempts to link the length and type of training with the cultural fluency required to successfully complete the project. Three different learning approaches are highlighted (Mendenhall et al., 1987): 1. The “information-giving” approach—the learning of information or skills from a

lecture-type orientation. 2. The “affective” approach—the learning of information/skills that raise the affective

responses on the part of the trainee and result in cultural insights. 3. The “behavioral/experiential” approach—variant of the affective approach tech-

nique that provides the trainee with realistic simulations or scenarios.

570 Chapter 15 International Projects

According to this framework, the length and level of training would depend on the degree of cultural fluency required to be successful. In general, the longer the person is expected to work in the foreign country, the more intensive the training should be. Length of stay should not be the only consideration; high levels of cultural fluency, and therefore more extensive training, may be required to perform short-term, intense proj- ects. In addition, location is important. Working in Australia will likely require less cultural fluency than working on a project in Pakistan.

While English is rapidly becoming the international language for business in many parts of the world, you should not underestimate the value of being able to speak the language of the host country. At a minimum you should be able to exchange basic pleasantries in the native tongue. Most foreigners consider this a sign of respect, and even if you stumble they appreciate the effort.

In many situations translators are used to facilitate communication. While time- consuming, this is the only way to communicate with non-English-speaking personnel. Be careful in the selection of translators, and do not just assume they are competent. For example, one of the authors enlisted the help of a Polish translator to conduct a meeting with some Polish managers. After the meeting the translator, who taught English at a local university, asked if the author “had good time.” I responded that I felt things went well. The translator repeated her question. Puzzled, I reaffirmed that I felt things went well. After the interchange was repeated several times, the translator finally grabbed my wrist, pointed at my watch, and asked again if I “had good time?” Doubts arose concerning the accuracy of the meeting translation!

FIGURE 15.7 Relationship between Length and Rigor of Training and Cultural Fluency Required

LENGTH OF

TRAINING

1–4 weeks

Less than a week

Cross-cultural training approach

Experiential Approach Assessment center Field experiences Simulations Extensive language training

Affective Approach Culture assimilator training Role-playing Cases Culture shock: Stress reduction training Moderate language training

Information-giving Approach Area briefings Cultural briefings Films/books Use of interpreters “Survival-level” language training

HighModerate

Degree of cultural fluency

Low

1–3 years2–12 months1 month or less

High

Level of

Rigor

Low

Length of stay

1–2 months+

Chapter 15 International Projects 571

The number of international projects continues to increase, and nothing on the horizon suggests things will change in the new millennium. More and more project managers will be needed to implement international projects. There are few guidelines for the fledgling international project manager. Preparing for international projects can be enhanced through training. As a general background, potential international project managers can benefit from a basic international business course that sensitizes them to the forces of change in the global economy and to cultural differences. Learning a for- eign language is also strongly recommended. Further training specific to the host country is a very useful preproject endeavor. The length and type of training usually depend on the duration of the project manager’s assignment. Review Figure 15.7. Still, self-learning, on-the-job training, and experi- ence are the best teachers for international project managers. Preparing for a specific international project requires serious preproject homework. Understanding the motivation of the firm in selecting the project and its site provides important insights. What basic political, geographic, economic, and infrastructure fac- tors were key considerations? How will they impact the implementation of the project? Finally, preparation and understanding the cultural differences of the host country go a long way toward making positive first impressions with the nationals and managing the project. International projects have distinct personalities. All people are not the same. Differences within and among countries and cultures are numerous and complex. Project managers need to accept these differences and treat them as real—or live with the consequences. What works at home may not work in the foreign country. Americans are regarded as friendly by our neighbors in the global village, but Americans are also noted to be insensitive to differences in local cultures and customs and awkward in our use of languages other than English. Although most attention in foreign projects is focused on technical efforts and their cost, the project must be carried out within the environment of the country’s social customs, work practices, government controls, and religious beliefs. In most cultures, sincerity and flexibility will pay off.

Summary

Key Terms Cross-cultural orientations, 557

Culture, 551 Culture shock, 566

Infrastructure, 550

Review Questions

Exercises

1. How do environmental factors affect project implementation? 2. What role do local intermediaries play in helping an outsider complete a project? 3. Why is it important to honor the customs and traditions of a country when working

on an international project? 4. What is culture shock? What can you do to reduce the negative effects of culture shock? 5. How should you go about preparing yourself for an international project?

1. Interview someone who has worked or lived in a foreign country for more than six months.

a. What was his experience with culture shock? b. What did he learn about the culture of the country he lived in? c. What advice would he give to someone who would be working on a project in

that country?

572 Chapter 15 International Projects

2. Try as best you can to apply the Kluckhohn-Strodtbeck cross-cultural framework to the four countries discussed in this chapter: Mexico, France, Saudi Arabia, and China. Where do you think these countries lie on each of the cultural issues?

3. Place in order the following countries in terms of what you would think would be the least to most corrupt:

United States, Denmark, Saudi Arabia, Russia, Australia, Hong Kong, Nepal, China, Kenya, Indonesia, Botswana, Greece, Chile.

Use an Internet search engine to find the most recent International Corruptions Perceptions Index (CPI) released by the Berlin-based organization Transparency International.

a. Check your predictions with the Index. b. How well did you do? What countries surprised you? Why? 4. Safety is a major concern when working on projects abroad. Select a country that

you would consider dangerous to work in and look up the travel advisory provided for that country by the U.S. State Department (http://travel.state.gov/). How safe is it to work in that country?

References Ackoff, R. L., Ackoff’s Fables: Irreverent Reflections on Business and Bureaucracy (New York: Wiley, 1991), p. 221. Adler, N., and A. Gunderson, International Dimensions of Organizational Behavior, 5th ed. (Mason, OH: Thomson Publishing, 2007). Arms, P. B. and E. Lucas, “How do Foreign Clients Really See American Project Managers?” Proceedings of the 1978 Annual Seminar/Symposium on Project Man- agement (Newtown, PA: Project Management Institute, 1978), pp. 11K 1–7. Borsuk, R., “In Indonesia, a Twist on Spreading the Wealth: Decentralization of Power Multiplies Opportunities for Bribery, Corruption,” The Wall Street Journal, January 29, 2003, p. A16. Cahill, T., “Deadly Business in Moscow,” Bloomberg Businessweek, March 1, 2010, pp. 22–23. Chen, M., and D. Miller, “West Meets East: Toward an Ambicultural Approach to Management,” The Academy of Management Perspectives, vol. 24, no. 4 (November 2010), pp. 17–24. Contingency Planning and Management.com, “Strohl Systems Offers Terrorism Readiness Questionnaire,” September 24, 2001. Deneire, M., and M. Segalla, “Mr. Christian Pierret, Secretary of State for Industry (1997–2002), on French Perspectives on Organizational Leadership and Manage- ment,” Academy of Management Executive, vol. 16, no. 4 (November 2002), pp. 25–30. Doh, J. P., P. Rodriguez, K. Uhlenbruck, J. Collins, and L. Eden, “Coping with Cor- ruption in Foreign Markets,” Academy of Management Executive, vol. 17, no. 3 (August 2003), pp. 114–27. Graham, J. L., and N. M. Lam, “The Chinese Negotiation,” Harvard Business Review, October 1, 2003, pp. 82–91.

Chapter 15 International Projects 573

Hallowell, R., D. Bowen, and C. I. Knoop, “Four Seasons Goes to Paris,” Academy of Management Executive, vol. 16, no. 4 (November 2002), pp. 7–24. Hodgetts, R. M., and F. Luthans, International Management: Culture, Strategy, and Behavior, 5th ed. (Boston: McGraw-Hill/Irwin, 2003). Hofstede, G., Cultures Consequences: International Difference in Work-Related Val- ues (Beverly Hills, CA: Sage Publishing, 1980). Hooker, J., Working across Cultures (Stanford, CA: Stanford Business Books, 2003). Kluckhohn, F., and F. L. Strodtbeck, Variations in Value Orientations (Evanston, IL: Row, Peterson, 1961). Krane, J., “Intelligence Companies Help Overseas Business Travelers,” The Cincin- nati Enquirer, April 2, 2002, website. Kras, E., Management in Two Cultures: Bridging the Gap between U.S. and Mexican Managers, rev. ed. (Yarmouth, ME: Intercultural Press, 1995). Lane, H. W., and J. J. DiStefano, International Project Management, 2nd ed. (Boston: PWS-Kent, 1992). Lieberthal, K., and G. Lieberthal, “The Great Transition,” Harvard Business Review, October 1, 2003, pp. 71–81. Mendenhall, M. E., E. Dunbar, and G. R. Oddou, “Expatriate Selection, Training, and Career-Pathing: A Review and Critique,” Human Resource Management, vol. 26, no. 3 (Fall 1987), pp. 331–45. Meyer, E., The Culture Map: Breaking through the Invisible Boundaries of Global Business, (New York: Public Affair, 2014). Milosevic, D. Z., “Echoes of the Silent Language of Project Management,” Project Management Journal, vol. 30, no. 1 (March 1999), pp. 27–39. Moffett, M. H., I. Stonehill, and D. K. Eiteman, Fundamentals of Multinational Finance (Boston: Pearson, 2012). Moran, R. T., P. R. Harris, and S. V. Moran, Managing Cultural Differences, 5th ed. (Houston, TX: Gulf Publishing, 2010). Morrison, T., and W. A. Conaway, Kiss, Bow, or Shake Hands (The Bestselling Guide to Doing Business in More than 60 Countries), 2nd ed. (New York: Adams Media, 2006). Ricks, D. A., Blunders in International Business (London: Blackwell, 2000). Saunders, C., C. Van Slyke, and D. R. Vogel, “My Time or Yours? Managing Time Visions in Global Virtual Teams,” Academy of Management Executive, vol. 18, no. 1 (2004), pp. 19–31. Scown, M. J., “Managers Journal: Barstool Advice for the Vietnam Investor,” Asian Wall Street Journal, July 15, 1993. Tung, R. L., “Expatriate Assignments: Enhancing Success and Minimizing Failure,” Academy of Management Executive, vol. 1, no. 2 (1987), pp. 117–26. Yeung, I., and R. L. Tung, “Achieving Business Success in Confucian Societies: The Importance of Guanxi (Connections),” Organizational Dynamics, vol. 25, no. 2 (Autumn 1996), pp. 54–65.

574 Chapter 15 International Projects

Case 15.1

AMEX, Hungary Michael Thomas shouted, “Sasha, Tor-Tor, we’ve got to go! Our driver is waiting for us.” Thomas’s two daughters were fighting over who would get the last orange for lunch that day. Victoria (“Tor-Tor”) prevailed as she grabbed the orange and ran out the door to the Mercedes Benz waiting for them. The fighting continued in the back seat as they drove toward the city of Budapest, Hungary. Thomas finally turned around and grabbed the orange and proclaimed that he would have it for lunch. The back seat became deadly silent as they made their way to the American International School of Budapest. After dropping the girls off at the school, Thomas was driven to his office in the Belvéros area of Budapest. Thomas worked for AMEX Petroleum and had been sent to Budapest four months earlier to set up business operations in central Hungary. His job was to establish 10 to 14 gas stations in the region by purchasing existing stations, building new ones, or negotiating franchise arrangements with existing owners of sta- tions. Thomas jumped at this project. He realized that his career at AMEX was going nowhere in the United States, and if he were going to realize his ambitions, it would be in the “wild, wild east” of the former Soviet empire. Besides, Thomas’s mother was Hungarian, and he could speak the language. At least he thought he could until he arrived in Budapest and realized that he had greatly exaggerated his competence. As he entered the partially refurbished offices of AMEX, he noticed that only three of his staff were present. No one knew where Miklos was, while Margit reported that she would not be at work today because she had to stay at home to take care of her sick mother. Thomas asked Béla why the workmen weren’t present to work on finishing the office. Béla informed him that the work had to be halted until they received approval from the city historian. Budapest, anxious to preserve its historical heritage, required that all building renovations be approved by the city historian. When Thomas asked Béla how long it would take, Béla responded, “Who knows—days, weeks, maybe even months.” Thomas muttered “great” to himself and turned his attention to the morning business. He was scheduled to interview prospective employees who would act as sta- tion managers and staff personnel. The interview with Ferenc Erkel was typical of the many interviews he held that morning. Erkel was a neatly dressed, 42-year-old, unemployed professional who could speak limited English. He had a masters degree in international economics and had worked for 12 years in the state-owned Institute for Foreign Trade. Since being laid off two years ago, he had been working as a taxicab driver. When asked about his work at the Institute, Erkel smiled sheepishly and said that he pushed paper and spent most of the time playing cards with his colleagues. To date Thomas had hired 16 employees. Four quit within three days on the job, and six were let go after a trial period for being absent from work, failing to perform duties, or showing a lack of initiative. Thomas thought that at this rate it would take him over a year just to hire his staff. Thomas took a break from the interview schedule to scan the Budapest Business Journal, an English newspaper that covered business news in Hungary. Two items caught his eye. One article was on the growing threat of the Ukrainian Mafia in Hungary, which detailed extortion attempts in Budapest. The second story was that inflation had risen to 32 percent. This last item disturbed Thomas because at the time

Chapter 15 International Projects 575

only one out of every five Hungarian families owned a car. AMEX’s strategy in Hungary depended on a boom in first-time car owners. Thomas collected his things and popped a few aspirin for the headache he was developing. He walked several blocks to the Kispipa restaurant where he had a supper meeting with Hungarian businessman Zoltán Kodaly. He had met Kodaly briefly at a reception sponsored by the U.S. consulate for American and Hungarian businesspeo- ple. Kodaly reportedly owned three gas stations that Thomas was interested in. Thomas waited, sipping bottled water for 25 minutes. Kodaly appeared with a young lady who could not have been older than 19. As it turned out Kodaly had brought his daughter Annia, who was a university student, to act as translator. While Thomas made an attempt to speak in Hungarian at first, Kodaly insisted that they use Annia to translate. After ordering the house specialty, szekelygulas, Thomas immediately got down to business. He told Kodaly that AMEX was willing to make two offers to him. They would like to either purchase two of his stations at a price of $150,000 each, or they could work out a franchise agreement. Thomas said AMEX was not interested in the third station located near Klinikak because it would be too expensive to modernize the equipment. Annia translated, and as far as Thomas could tell she was doing a pretty good job. At first Kodaly did not respond and simply engaged in side conversations with Annia and exchanged pleasantries with people who came by. Thomas became frustrated and reiterated his offer. Eventually Kodaly asked what he meant by franchis- ing, and Thomas tried to use the local McDonald’s as an example of how it worked. He mentioned that Kodaly would still own the stations, but he would have to pay a fran- chisee fee, share profits with AMEX, and adhere to AMEX procedures and practices. In exchange, AMEX would provide petroleum and funds to renovate the stations to meet AMEX standards. Toward the end of the meal Kodaly asked what would happen to the people who worked at the stations. Thomas asserted that according to his calculation the stations were over-staffed by 70 percent and that to make a profit, at least 15 workers would have to be let go. This statement was greeted with silence. Kodaly then turned the con- versation to soccer and asked Thomas if it was true that in America girls play “foot- ball.” Thomas said that both of his daughters played AYSO soccer in America and hoped to play in Hungary. Kodaly said girls don’t play football in Hungary and that Annia was an accomplished volleyball player. Thomas pressed Kodaly for a response to his offer, but Kodaly rose and thanked Thomas for the meal. He said he would think about his offer and get back in touch with him. Thomas left the Kispipa wondering if he would ever see Kodaly again. He returned to his office where an urgent message was waiting from Tibor. Tibor was responsible for retrofitting the first station Thomas had purchased for AMEX. The new tanks had not arrived from Vienna, and the construction crew had spent the day doing nothing. After several phone calls he found out that the tanks were being held at the border by customs. This irritated him because he had been assured by local officials that every- thing had been taken care of. He asked his secretary to schedule an appointment with the Hungarian trade office as soon as possible. At the end of the day he checked his e-mail from the States. There was a message from headquarters asking about the status of the project. By this time he had hoped to have his office staffed and up and running and at least three stations secured. So far he had only one-third of his staff, his office was in shambles, and only one station was being retrofitted. Thomas decided to wait until tomorrow to respond to the e-mail. Before returning home Thomas stopped off at the English Pub, a favorite hangout for expats in Budapest. There he met Jan Krovert, who worked for a Dutch company

576 Chapter 15 International Projects

that was building a large discount retail store on the outskirts of Budapest. Thomas and Krovert often talked about being “strangers in a strange land” at the pub. Thomas talked about the interviews and how he could just see in their eyes that they didn’t have the drive or initiative to be successful. Krovert responded that Hungary has high unem- ployment but a shortage of motivated workers. Krovert confided that he no longer interviewed anyone over the age of 30, claiming that what fire they had in their bellies was burned out after years of working in state-run companies. 1. What are the issues confronting Thomas in this case? 2. How well is Thomas dealing with these issues? 3. What suggestions would you have for Thomas in managing this project?

Case 15.2

Phuket A On December 26, 2004, an earthquake reaching 9.1 on the Richter scale triggered a series of devastating tsunamis off the coast of Indonesia. They spread throughout the Indian Ocean, killing large numbers of people and inundating coastal communities across South and Southeast Asia, including parts of Indonesia, Sri Lanka, India, and Thailand. The 2004 Asian tsunami was one of the deadliest catastrophes in modern history, with more than 220,000 lives lost. Nils Lofgrin, who had managed several construction projects in Australia and New Guinea, was sent by his construction firm to restore a five-star resort along the Anda- man coast in southern Thailand that had been ravaged by this tsunami. Casualties at the resort included 12 staff and 37 guests. This was Nils’s first assignment in Thailand. Nils flew down and toured the site. His assessment of the damage was that it was not as severe as feared. The basic infrastructure was intact but debris needed to be cleared and the resort refurbished. He reported back to headquarters that with a bit of luck he should have the resort up and running in a matter of months. Little did he real- ize how soon he would regret making such a promise. The problems began immediately when he was unable to recruit workers to help clean up the mess at the resort. Burmese migrant workers comprised a significant por- tion of the workforce in the region. The heavy government presence caused them to flee into the hills out of growing fears of being arrested and deported. Even when he offered double wages he was not able to recruit many Thais. 1. Why do you think Nils is unable to recruit Thai workers for his project?

578

An Introduction to Agile Project Management

OUTLINE 16.1 Traditional versus Agile Methods

16.2 Agile PM

16.3 Agile PM in Action: Scrum

16.4 Applying Agile PM to Large Projects

16.5 Limitations and Concerns

Summary

LEARNING OBJECTIVES After reading this chapter you should be able to:

16-1 Recognize the conditions in which traditional project management versus agile project management should be used.

16-2 Understand the value of incremental, iterative development for creating new products.

16-3 Identify core Agile principles.

16-4 Understand the basic methodology used in Scrum.

16-5 Recognize the limitations of Agile project management.

C H A P T E R S I X T E E N

16

579

We know less about the project today than at any time in the future. —Chet Hendrickson

As project management entered the new millennium, many professionals recognized that one-size fits all project management methods did not meet their needs. This was especially true for those working on software and product development projects in which the end product is not well defined and evolves over time. This project environment requires flexi- bility and the ability to manage changes as more information and learning take place. Enter Agile Project Management (Agile PM). Instead of attempting to plan the entire project up front, Agile PM relies on incremental, iterative development cycles to complete projects.

Ken Schwaber uses the analogy of building a house to explain the difference between incremental, iterative development and traditional project management.1 The traditional approach would be that the buyers could not move into the house until the entire house is completed. The iterative approach would build the house room by room. The plumbing, electrical, and infrastructure would be built for the most important

Project networks

6

Managing risk 7

Monitoring progress

13

Teams 11

Outsourcing 12

Project manager

10

Strategy 2

Introduction 1

Organization 3

Schedule resources & costs

8

International projects15

Agile PM16

Project closure

14

Estimate 5

Reducing duration

9

Define project

4

1 Schwaber, K., Agile Project Management with Scrum (Seattle: Microsoft, 2004) p. xviii.

580 Chapter 16 An Introduction to Agile Project Management

room (i.e., kitchen) first and then extended to each room as it was constructed. Each time a room is completed, the builders and the buyers would assess progress and make adjustments. In some cases, the buyers would realize that they didn’t need that extra room they felt they had to have. In other cases, they would add features they didn’t real- ize they needed to have. Ultimately the house is built to fit the customer’s wishes.

Agile PM is ideal for exploratory projects in which requirements need to be discov- ered and new technology tested. It focuses on active collaboration between the project team and customer representatives, breaking projects into small functional pieces, and adapting to changing requirements. While iterative development principles have been around for some time, it is only recently that agile methodologies have taken root within the project management profession.

In this chapter the core principles of Agile PM are discussed and compared with traditional project management methods. A specific agile methodology called Scrum is used to describe these principles in action. The chapter concludes with a discussion of limitations and concerns. The goal is not to provide a comprehensive account of all the methods associated with Agile PM but to provide a primer on how agile works.

16.1 Traditional versus Agile Methods Traditional approaches to project management concentrate firmly on thorough plan- ning up front. The rationale is that if you plan, execute your plan, and take corrective action on deviations from plan, you have a high probability of success. Once the proj- ect scope has been firmly established, every detail of the project is defined through the WBS. Most problems and risks are identified and assessed before the project begins. Estimates are made, resources assigned, adjustments made, and ultimately a baseline schedule and budget are created. Control of the project is a comparison of plan versus actual and corrective action to get back on plan.

Traditional project management requires a fairly high degree of predictability to be effective. For plans to be useful managers have to have a firm idea on what is to be accomplished and how to do it. For example, when it comes to building a bridge across a river, engineers can draw upon proven technology and design principles to plan and execute the project. Not all projects enjoy such certainty. Figure 16.1 speaks to this issue and is often used to support the use of Agile PM.

Project uncertainty varies according to the extent the project scope is known and stable and the technology to be used is known and proven. Many projects, like the bridge example, as well as other construction projects, events, product extensions, marketing campaigns, and so forth have well-established scopes and use proven tech- nology that provides a degree of predictability for effective planning. However, when the project scope and/or technology are not fully known, things become much less predictable and plan-driven methods suffer.

For example, before agile, software development projects relied on a “waterfall” approach to software development. The waterfall method features a series of logical phases in which progress flows from one phase to the next (see Figure 16.2). The key assumption is that essential requirements can be defined upfront so the software can be designed, built, and tested. Software projects typically involve many different customers with different needs. These needs frequently change and are often difficult to articulate. In many cases, customers only begin to understand what they actually desire when they are provided with someone’s impression of what they want. Under these conditions it would be difficult if not futile to develop a detailed list of scope requirements at project launch. This is one of the major reasons why software projects utilizing the waterfall approach have a history of coming in late and/or being canceled.

Recognize the conditions in which traditional proj- ect management versus agile project manage- ment should be used.

16-1LO

Chapter 16 An Introduction to Agile Project Management 581

Technology can be another source of unpredictability. For example, a development team charged with designing the next generation electric car may know they are to build a car that seats four adults comfortably and travels over 200 miles before being charged, but they may not know if the battery technology exists to power such a vehicle. Again it would be very difficult to develop a reliable schedule when such questions exist.

The key point is that traditional PM techniques were developed to operate in the predictable zone where the scope of the project is fairly well defined and technology to be used is established. Projects also operate in a very different zone in which how or what has yet to be fully discovered. Agile lives in this unpredictable zone. Agile PM

Unknown

UnknownTechnology(How)

Project scope (What)

Known & stable

Predictable

Unpredictable

FIGURE 16.1 Project Uncertainty

Concept phase

Requirements phase

Design phase

Construct phase

Test phase

Deploy phase

FIGURE 16.2 The Waterfall Approach to Software Development

582 Chapter 16 An Introduction to Agile Project Management

represents a fundamental shift away from the traditional plan-driven project manage- ment approach by adopting a more experimental and adaptive approach to managing projects. Projects evolve rather than are executed. Solutions are discovered not imple- mented. Some of the differences between Agile PM and traditional project manage- ment are displayed in Table 16.1.

16.2 Agile PM Fundamentally, Agile PM is related to the rolling wave planning and scheduling project methodology (see Chapter 5). That is, the final project design is not known in great detail and is continuously developed through a series of incremental itera- tions over time. Iterations are short time frames (“time boxes”) that typically last from one to four weeks. The goal of each iteration is to develop a workable product that satisfies one or more desired product features to demonstrate to the customer and other key stakeholders. At the end of each iteration, stakeholders and customers review progress and re-evaluate priorities to ensure alignment with customer needs and company goals. Adjustments are made and a different iterative cycle begins. Each new iteration subsumes the work of the previous iterations and adds new capa- bilities to the evolving product (see Figure 16.3) to produce a next, expanded version of the product. See Snapshot from Practice 16.1: IDEO for an example of iterative development in action.

Understand the value of incremental, iterative development for creating new products.

16-2LO

Traditional Agile Design up front Continuous design Fixed scope Flexible scope Deliverables Features/requirements Freeze design as early as possible Freeze design as late as possible Low uncertainty High uncertainty Avoid change Embrace change Low customer interaction High customer interaction Conventional project teams Self-organized project teams

Project initiation

Iteration 1 Iteration 2 Iteration 3 Iteration 4 Iteration 5

Closeout

New product: Customeracceptance

FIGURE 16.3 Iterative, Incremental Product Development

TABLE 16.1 Traditional Project Management versus Agile Project Management

Chapter 16 An Introduction to Agile Project Management 583

IDEO, headquartered in Palo Alto, California, is one of the premier design firms in the world. They are responsible for a wide range of prod- uct innovations including the first

Apple mouse, Head’s Airflow Tennis Racket, Zyliss Salad Spinner, and Nokia N-Gage Smartphones. IDEO’s many clients include Pepsi-Cola, 3M, Logitech, Nike, and HBO. IDEO has won more of the Business- Week/IDSA Industrial Design Excellence Awards than any other firm. IDEO’s approach to product design relies heavily on an iterative development process in which product pro- totypes are used to explore and further refine product ideas. CEO Tim Brown states that the goal of prototyp- ing “is to learn about the strengths and weaknesses of the idea and identify new directions that the prototype might take.” For example, IDEO worked with Procter and Gam- ble to develop a new Crest toothpaste tube. The chal- lenge was to improve the traditional screw-on cap, which always gets gunked up with toothpaste. IDEO’s first solution was a pop-on, pop-off cap. However, when designers created rough prototypes and watched people use them, they quickly noticed that users kept trying to unscrew the cap even though they were told how it worked. The designers concluded that the action was a well-ingrained habit that would probably be impossible to break. So they came up with a hybrid: a twist-off cap that had a short thread but would still be easy to clean. Focused prototyping resolves critical problems one by one. Brown recommends that prototypes should only take as much time and effort needed to generate useful feedback and evolve an idea.

For example, IDEO was working on a chair for Vecta, a high-end office furniture manufacturer. The project had evolved to the point where the height adjustment lever that tilted with the chair became critical. The team didn’t build the whole chair or even the tilt mechanism. They just built the little lever and its interface with the tilt mechanism. It took only a couple of hours. When finished the pro- totype quickly demonstrated that the principle would work. “It doesn’t matter how clever you are, your first idea about something is never right,” Brown says, “so the great value of prototyping—and prototyping quickly and inexpensively—is that you learn about the idea and make it better.”

* J. M. Pethokoukis, “The Deans of Design: From the Com- puter Mouse to the Newest Swiffer, IDEO Is the Firm behind the Scenes,” U.S. News & World Report, posted 9-24-2008; T. Brown, “Design Thinking,” Harvard Business Review, June 2008, pp. 84–95.

S N A P S H O T F R O M P R A C T I C E 1 6 . 1 IDEO: Masters of Design*

© Cultura Creative/Alamy RF

Iterative development processes provide the following important advantages:

∙ Continuous integration, verification, and validation of the evolving product. ∙ Frequent demonstration of progress to increase the likelihood that the end product

will satisfy customer needs. ∙ Early detection of defects and problems.

There is growing evidence that iterative and evolutionary development is superior to traditional plan-driven project management when it comes to creating new products. (See Research Highlight 16.1: Product Development Practices That Work.)

It should be noted that Agile PM is not one set method, but a family of methods designed to respond to the challenges of unpredictable projects. A few of the more popular ones are listed here:

Scrum RUP (Rational Unified Process) Extreme Programming (XP) Crystal Clear Agile Modeling Dynamic Systems Development Method (DSDM) Lean Development Rapid Product Development (RPD)

While each of these methods has unique elements and applications, most are based on the following Agile principles:

∙ Focus on customer value—Employ business-driven prioritizations of requirements and features.

∙ Iterative and incremental delivery—Create a flow of value to customers by “chunk- ing” project delivery into small, functioning increments.

∙ Experimentation and adaptation—Test assumptions early and build working proto- types to solicit customer feedback and refine product requirements.

∙ Self-organization—Team members decide among themselves what should be done and who should do it.

∙ Continuous improvement—Teams reflect, learn, and adapt to change; work informs the plan.

The Agile methodology known as “Scrum” will be used to illustrate how these core principles are put into action.

Identify core Agile principles.

16-3LO

584

Alan MacCormack and his colleagues at Harvard Business School con- ducted a two-year in-depth study of 29 software projects to answer the question: “Does evolutionary devel-

opment, rather than the waterfall model, result in bet- ter success?” The waterfall model is the name used in the software industry for the traditional approach to project management in which a process breakdown structure (PBS) is used to first define all the require- ments up front and then initiate a design, build, test, deploy sequence. Conversely, evolutionary develop- ment is the term they use to describe an Agile approach in which customers test early versions of the software and requirements emerge and are refined after each demonstration. The results of the study overwhelmingly favored the iterative, Agile approach to software develop- ment. Several key practices now associated with Agile Project Management were found to be statistically correlated with the most successful projects:

1. An iterative life cycle with early release of the evolving product to stakeholders for review and feedback.

2. Daily incorporation of new software and rapid feedback on design changes.

3. A flexible product architecture that is both modu- lar and scaleable.

MacCormack asserts that uncertainty on software projects dictates short “microprojects”—down to level of features. This is not limited to just software projects but to any new product endeavor where uncertainty is high and the need for customer feedback and refine- ment is critical to success.

Research Highlight 16.1 Product Development Practices That Work*

* A. MacCormack, “Product-Development Practices that Work: How Internet Companies Build Software,” MIT Sloan Management Review, 42(2), 2001, pp. 75–84.

Chapter 16 An Introduction to Agile Project Management 585

16.3 Agile PM in Action: Scrum Scrum can be traced back to the work of Hirotaka Takeuchi and Ikujiro Nonaka, who in 1986 described a new holistic approach in new commercial product development efforts. They compare this approach of a cross-functional team collaborating to develop a new product to rugby, where the whole team “tries to go the distance as a unit, pass- ing the ball back and forth.” The scrum metaphor has been expanded and refined into a fairly prescriptive framework that has enjoyed success on high-tech and software development projects (see Snapshot from Practice 16.2: Soul Searching).

Scrum, like other Agile methods, begins with a high-level scope definition and ballpark time and cost estimates for the project. The scope and cost estimates should be complete enough that management is comfortable with the estimates. The theory is that since requirements evolve over time, detailed up-front planning will be wasted. In place of a product WBS, Scrum uses product features as deliverables. A feature is defined as a piece of a product that delivers some useful functionality to a customer. In the case of a software project, a feature may be a bank customer being able to change her PIN. In the case of a high-tech product, it may be 3G wireless access. Features are

Understand the basic methodology used in Scrum.

16-4LO

Over 2,792 lives were lost in the col- lapse of the World Trade Center (WTC) on September 11, 2001. While rescuers labored night and day to recover the bodies, a small team of Michigan soft-

ware engineers set about salvaging their identities. New York City hired Gene Codes, the Ann Arbor, Michigan, bioinformatics company, to reinvent the sci- ence of DNA mass identification by creating software that would inventory and match the victims’ remains and reunite them with their families. They were to do so as soon as possible with no errors. Experts predicted that the violence of the collapse and the intense heat of the fires meant that at best 25 percent of the victims would be identified. Gene Codes hired William Wake, an independent software coach, to work with their team of eight soft- ware engineers on the project. Wake introduced the team to Agile PM. Under Wake’s guidance an environ- ment of intense interaction and communication was created within the programming team by scheduling frequent releases, tempered by constant testing, and feedback from its users. Testing was done before, dur- ing, and after the code was written to ensure the same bugs (errors) didn’t surface twice. At the end of each week’s iteration, the staff held a retrospective. They listed things that worked well and what needed improvement on fluorescent pink, green, and yellow Post-It notes, transforming the entire wall

into a case of art imitating life. Under “Worked Well,” a note said, “Figured out how to use debug form on a wrapped test class.” One square under the “Needs Improvement” category merely read, “I’m tired.” Whether out of patriotism or professionalism, the team routinely arrived each day at 7:00 a.m. and worked till midnight. Engineers like Dave Relyea just wanted to help. “We thought about the victims, the families, and the people at the Office of the Chief Medi- cal Examiner working around the clock. What they were going through made us feel like we could never work hard enough.” The product of their labor was the Mass Fatality Identification System (M-FISys) that contained more than 164,000 lines of code. M-FISys linked all the infor- mation in the identification project: 11,641 swab sam- ples from 7,166 family members; 7,681 personal effects (i.e., toothbrushes, hair brushes) and the results of the three types of DNA tests; and nearly 20,000 human remains. The chance of false match was less than 1 in 3.58 million. In the end, with the help of M-FISys, the New York Medical examiner was able to identify 1,521 of the 2,792 people who perished in the WTC disaster.

S N A P S H O T F R O M P R A C T I C E 1 6 . 2 Soul Searching after 9/11*

* Melissa Krause, “Soul Searching” Bio-ITworld. Accessed on 3/10/2008 at www.bio-itworld.com /archive/091103/soul.html.

586 Chapter 16 An Introduction to Agile Project Management

prioritized by their perceived highest value. The project team tackles the highest, fea- sible priority features first. Priorities are re-evaluated after each iteration. Iterations are called sprints and should last no longer than four weeks. The goal of each sprint is to produce fully functional features. This forces the team to tackle tough decisions early in order to create a workable demo.

Specific features are created according to four distinct phases: analysis, design, build, and test (see Figure 16.4). Each feature can be thought of as a mini-project. The first phase is analysis and review of functional requirements that will be needed to complete the feature. The team commits to meet these requirements. The second phase is the development of a design that meets the requirements of the feature. The third phase is to build the feature so that it is functional. Finally, the feature is tested and documented. At the end of each sprint, features are demonstrated. Within this sprint framework, Scrum relies on specific roles, meetings, and documents/logs to manage the project.

Roles and Responsibilities There are three key roles to the scrum process: Product owner, development team, and scrum master.

Product Owner The product owner acts on behalf of customers/end users to represent their interests. For commercial development projects the product owner may be the product manager. For internal projects, the product owner could be the manager of the business group that will benefit from the software. In other cases, the product owner could be a representative of the client organization. They are responsible for ensuring that the development team focuses their efforts on developing a product that will fulfill the business objective of the project.

The product owner in consultation with others establishes the initial list of product requirements and prioritizes them in the product backlog. Owners often work with the development team to refine features through stories and end user cases (e.g., when the user clicks the F2 key an option drop-down window appears). The product owners negotiate sprint goals and backlog items with the development team. Owners have the

Build

Analysis Selected features

Prioritized feature log

Test Design

Demonstration of functional

featuresIteration

Daily scrum meeting

Sprint 3--4 weeks

FIGURE 16.4 Scrum Development Process

Chapter 16 An Introduction to Agile Project Management 587

option to change features and priorities at the end of each sprint if desired. However, no changes should be made once a sprint has started. Product owners are the final arbiter on requirements questions and are empowered to accept or reject each product increment. They ultimately decide whether the project is completed. Product owners are the keeper of the product vision and the watchdog on project cost.

Development Team The team is responsible for delivering the product. A team is typically made up of five to nine people with cross-functional skill sets. There are no designated roles or titles; people take on different responsibilities depending on the nature of the work. The team is self-organizing in the sense they decide both who does the work and how the work is to be accomplished. Team members should be co-located so that intense face-to-face collaboration occurs. They are responsible for the achiev- ing commitments they make at the sprint planning and sprint review meetings.

Scrum Master (aka Project Manager) The Scrum master facilitates the scrum pro- cess and resolves impediments at the team and organization level. The Scrum master is not the leader of the team (the team leads itself!) but acts as a buffer between the team and outside interference. They have no formal authority. Instead, they are responsible for making sure that the scrum process is adhered to. They help the product owner with planning and try to keep the team energized. The Scrum master serves more as a coach than a manager.

Scrum Meetings Scrum uses a series of coordinated meetings to manage the development process (see Figure 16.5).

Release Planning The purpose of release planning is to establish the goals and gen- eral plan for the project. The product owner works with the team, Scrum master, and others to address the question of how the project can meet or exceed the desired cus- tomer expectations and return on investment. Outcomes of this meeting include estab- lishing highest priority product backlog, the major risks, and the overall features and functionality that the released product will contain. The meeting also produces a prob- able delivery date and initial cost estimates if nothing changes. Management can then monitor progress and make changes to the release plan on a sprint-by-sprint basis.

Sprint Planning At the start of each sprint, the product owner and development team negotiate which product backlog items the team will attempt this sprint. The product owner is responsible for identifying which features are most important, and the team is responsible for determining what is possible within the sprint. If it is impossible to

FIGURE 16.5 Scrum Meetings

Sprint planning meeting

Sprint review meetings

Daily scrum meeting

24 hour

Sprint retrospective meetings

Release Planning

588 Chapter 16 An Introduction to Agile Project Management

complete a certain key item within four weeks, the team works with the product owner to break the feature down into doable pieces. All committed items are recorded in a product backlog. The team uses this backlog to prioritize specific work to be done and assign initial responsibilities. These tasks are recorded in the sprint backlog. Once the meeting has adjourned, the goals for the sprint cannot be changed.

Daily Scrum The heartbeat of an Agile project is the daily meetings which are com- monly referred to as the “Scrum.” Each workday at the same time and place, team members stand in a circle and take turns answering the following key questions: 1. What have you done since the last Scrum? 2. What will you do between now and the next Scrum? 3. What is getting in the way of (blocks) your performing your work as effectively as

possible? The Scrum, which typically lasts 15 minutes, is held next to a whiteboard, after

which time all tasks and blocks are recorded. The Scrum master erases blocks once they have been removed.

The meetings must start on time. A late fine (e.g., $1 to be collected and donated to charity by the Scrum master) is a popular rule. The meeting is limited to just those three core questions. Members stand to create a sense of urgency. Immediately after- ward, specific members may meet to resolve issues that surfaced.

The value of the Scrum is that it creates a daily mechanism to quickly inform the team about the state of the project. It sustains a sense of team identity that encourages open- ness and resolution of problems in real time. Having everyone report what they plan to do for that day generates a social promise to the group, thereby building accountability.

Notice again that the team is self-managed. The Scrum master does not assign daily tasks to team members; the team decides among themselves. The Scrum master role is to see that the scrum is running correctly. They are not “master” of the team but rather “master” of the process.

Sprint Review At the end of each sprint, the team demonstrates the actual work prod- uct increments they have built to the product owner and other relevant stakeholders. Feedback is solicited from the product owner and other relevant stakeholders. The prod- uct owner declares which items are “done” and which items need further work and are returned to the product backlog. The team can take this opportunity to suggest improve- ments and new features for the product owner to accept or reject. The sprint review meeting is an opportunity to examine and adapt the product as it emerges and iteratively refine key requirements. Such refinements will be the subject of the next sprint planning meeting.

Sprint Retrospective The purpose of the retrospective meeting is to reflect on how well the previous sprint went and identify specific actions that can improve future sprints. The Scrum master typically facilitates this meeting and the team decides which changes will be made in how they work together for the next sprint. The retrospective reflects Scrum’s commitment to continuous improvement and the value it places on improving not only products but team interactions.

Product and Sprint Backlogs Each project has a product backlog and a sprint backlog. The product owner controls the product backlog and the team controls the sprint backlog. The product backlog is

Chapter 16 An Introduction to Agile Project Management 589

the customer’s prioritized list of key features desired when the project is completed. The product backlog usually defines each feature and estimates of time, cost, and work remaining. See Figure 16.6 for a partial product backlog for a software project.

The sprint backlog is developed and controlled by the team. It represents the amount of work the team commits to complete during the next sprint. The sprint backlog lists the tasks (activities) that must be completed to deliver a functional feature or segment of a feature. The sprint backlog also serves as a status document by listing the person responsible for each task, remaining hours of work, and record- ing the task as finished, in process, or not yet started. See Figure 16.7 for a partial example of a sprint backlog.

Scrum does not use any of the conventional project management tools like Gantt charts or network diagrams. Instead it relies on the daily scrums and the active involve- ment of the product owner to manage work flow. Risk is mitigated by short develop- mental cycles and rigorous testing. For an alternative approach to tracking work see Snapshot from Practice 16.3: Kanban.

Sprint and Release Burndown Charts Scrum uses “burndown” charts, which focus on the work remaining and are used to track progress. Sprint burndown charts are used to track progress on a daily basis (see Figure 16.8). The axis on the left shows the remaining effort required to com- plete the sprint backlog and the axis on the bottom contains the number of days until

A 1 2 3 4 5 6 7 8 9 10 11

1 2 3 4 5

2 1 3 5 4

100 160 80 40 120

Complete Complete

Started Not started

Started

90 180

12

B C D E F G Phone-In Prescription Software Project

Product Backlog

ID Product

Customer Information Insurance Information Drug Information Doctor Information Inventory status

Priority Status Estimate Hours

Actual Hours

FIGURE 16.6 Partial Product Backlog

A 1 2 3 4 5 6 7 8 9 10 11

Drug categories Generics Branded

Design drug inventory system Code inventory availability Code manufacture order Integrate all inventory systems

EL CE MC LE

0 32 32 16

X X

X

40

4

RT CG AL

0 0 8

X X X

X X X

X

X X X

16 32 24

12 13 14 15 16

B C D E F G H I Phone-In Prescription Software Project

Sprint Backlog

Sprint Description Responsible Defined Tested AcceptedRemaining Hours

Actual Hours

In Progress

FIGURE 16.7 Partial Sprint Backlog

590 Chapter 16 An Introduction to Agile Project Management

Kanban is a lean management meth- odology first developed by Toyota. It has been adapted by agile practitio- ners to help manage project work flow. In its simplest form, Kanban con-

sists of a white board divided into three columns titled: Next, WIP (Work in Progress), and Done. The team iden- tifies the distinct tasks, deliverables, or features associ- ated with their projects. Each is labeled on post-it notes or special “Kanban” cards. The cards are prioritized in terms of what needs to be done first and a queue is created in the Next column. The team works on the top priority items. Once a task or feature has been com- pleted the card is moved to the Done column and the next task is started. Like Scrum, the project team starts each day with a stand-up meeting to update the board, decide what needs to be done, and discuss impedi- ments to progress. Kanban is based on the idea of pull. A completed Kanban card signals when the team is ready for more work, which is pulled from the Next list. Work isn’t pushed from start to finish. It’s only when a task is com- pleted that another task can be started. Limits are set based on the capability of the project team on the num- ber of WIP tasks. For example, no more than three tasks can be in progress at any one time. This reduces the inefficiencies of multi-tasking and prevents

S N A P S H O T F R O M P R A C T I C E 1 6 . 3 Kanban

lingering bottlenecks from emerging. Another strength of Kanban is that it helps the team visualize the work flow on the project and focus their attention on the most critical work. Finally, like Scrum, significant time is devoted to problem solving and developing better ways of accomplishing the work. Depending upon the project more elaborate map- ping schemes can be used. For example, Tarne (2011) described a system for an IT Helpdesk that consisted of six columns: Opened ticket, In Queue, Root Cause Anal- ysis, Develop Fix, Test, and Deploy. More sophisticated Kaban tools can also be found online. For example, AGILEZEN (agilezen.com) provides a user-friendly, vir- tual Kanban board, customizable cards/tags and colors, and a performance metrics tracker.

© anathomy/Shutterstock

the sprint is completed. The remaining effort is calculated by summing the time estimates for incomplete tasks recorded in the sprint backlog. These estimates are updated on a daily basis.

In Figure 16.8 the solid line shows the ideal scenario if the sprint progresses as predicted by the initial task estimates and the dotted line shows the actual performance. Ideally the dotted line should be very close to the solid line. When it is above the solid line the team is behind schedule and when it is below the solid line, the team is ahead of schedule. If the actual remaining line is above the ideal line for an extended period of time, then this signals that adjustments need to be made to the project. This could mean dropping a task, assigning additional resources, or working late. None of these are pleasant, but because of the burndown chart, the team can respond sooner than just before the sprint deadline.

The release burndown chart is used to monitor progress toward completion of the project (see Figure 16.8). This chart displays the amount of work remaining across time. Before the start of each sprint completion estimates are revised in the product backlog and totaled in the release burndown chart. Over time the chart becomes an excellent method for visualizing the relationship between amount of

Chapter 16 An Introduction to Agile Project Management 591

work remaining and the rate at which team is reducing this work. Also the intersec- tion of the trend line for work remaining and the horizontal time line can be used to estimate probable completion date. The product owner and team use this informa- tion to “what if” the project by removing or adding functionality from the release to  achieve a specific completion date or extend the date to include more functionality.

In Figure 16.9 work remaining is recorded for the first six sprints and a trend line is used to revise the expected completion date. Note that in this example the project is

FIGURE 16.8 Sprint Burndown Chart

Sprint Timeline (days)

0 5 10 15 20 0

7

14

21

28

R em

ai ni

ng E

ff or

t ( da

ys )

Behind Schedule

Ahead of Schedule

Ideal  Remaining Effort Actual Remaining Effort

0

10

20

30

40

50

60

70

80

90

100

0 1 2 3 4 5 6 7 98 10

D ay

s  of

 W or

k  Re

m ai

ni ng

Sprint

Original Completion Date

Revised Completion Date

FIGURE 16.9 Release Burndown Chart after Six Sprints

592 Chapter 16 An Introduction to Agile Project Management

expected to be completed later than planned. Does this mean the team is underperform- ing? No, not necessarily! Remember the product backlog is dynamic and at the end of each sprint the backlog is revised. Features are added, modified, or deleted. Work esti- mates are increased or decreased. There is no established baseline in Agile PM.

16.4 Applying Agile PM to Large Projects Scrum and most other Agile methods are ideally suited for distinct projects that can be completed by a small, five-to-nine-person team. Agile methods can be used on larger scale projects in which several teams are working on different features at the same time. In practice this condition is called “scaling.” The chief challenge with scaling is integration—making sure that the different features being created work in harmony with each other.

There are no easy solutions to the integration challenge. Significant up-front planning is required to manage the interdependences of different features that will be developed. This is called “staging” and often is the subject of the first development iteration. Here protocols and roles for coordinating efforts and assuring compatibility are established. This is supported by establishing a clear product vision so that trade-off decisions are consistent at the local team level.

Agile advocates recommend creating a hub structure (see Figure 16.10) with over- lapping roles and responsibilities to manage large projects. There are several feature development teams. A separate integration and build team is formed consisting of part- time members of each feature team. This team tackles the sticky integration issue through testing and establishing requirements for the feature teams. To coordinate the multi-team structure a central project team is created consisting of a higher level proj- ect manager, a product manager (who represents the interests of the customer), and the

Project mgr

Central project management team

Product mgr

Team leads

Feature development

teams A-Z

Team leads

Integration & build team

FIGURE 16.10 Hub Project Management Structure

Chapter 16 An Introduction to Agile Project Management 593

leads (“project managers”) from the feature development teams. The project manage- ment team provides coordination and facilitates project decision making. Their role is to steer rather than command the other teams. Teams may be real, virtual, or a combi- nation. The entire system requires a spirit of collaboration to work.

16.5 Limitations and Concerns Agile methods in the software industry grew at a grass roots level. Many engineers saw traditional plan-driven project management as stifling effective development with too much emphasis on processes and documentation and not enough on creativ- ity and experimentation. Early on there was a rebellious tone to the Agile movement, so much so that several of the key founders published an Agile Manifesto (see Snap- shot from Practice 16.4: Agile Alliance). The manifesto affirmed a different set of values than those currently being applied by management to projects they were working on.

On February 11–13, 2001, at The Lodge at Snowbird ski resort in the Wasatch mountains of Utah, 17 representatives of various new software methodolo- gies (such as Extreme Programming,

Scrum, Adaptive Software Development, and Crystal Clear) met to discuss the need for lighter alternatives to the traditional, documentation-driven project man- agement methodology. They were united by a desire to free themselves of Dilbert manifestations of make- work and arcane policies and spark a revolution in the software industry. By the end of two days they formed the Agile Alliance to champion change and published a manifesto that declared four core values:

We are uncovering better ways of developing software by doing it and helping others do it. Through this work we have come to value:

Individuals and interactions over processes and tools Working software over comprehensive documentation Customer collaboration over contract negotiation Responding to change over following a plan

These four values were expanded upon by a set of 12 guiding principles:

1. Our highest priority is to satisfy the customer through early and continuous delivery of valuable software.

2. Welcome changing requirements, even late in development.

3. Deliver working software frequently, from a couple of weeks to a couple of months, with a preference to the shorter timescale.

4. Businesspeople and developers must work together daily throughout the project.

5. Build projects around motivated individuals. Give them the environment and support they need, and trust them to get the job done.

6. The most efficient and effective method of convey- ing information to and within a development team is face-to-face conversation.

7. Working software is the primary measure of progress.

8. Agile processes promote sustainable development.

9. Continuous attention to technical excellence and good design enhances agility.

10. Simplicity—the art of maximizing the amount of work not done—is essential.

11. The best architectures, requirements, and designs emerge from self-organizing teams.

12. At regular intervals, the team reflects on how to become more effective, then turns and adjusts its behavior accordingly.

To find a wealth of information on Agile PM, log onto the Agile Alliance website at: www.agilealliance.org/.

S N A P S H O T F R O M P R A C T I C E 1 6 . 4 Agile Alliance

594 Chapter 16 An Introduction to Agile Project Management

The revolutionary nature of Agile is reflected in the story one IT manager told the authors about her efforts several years ago at using Agile PM. She worked for a large, multinational high-tech firm that had spent five years institutionalizing a set of tradi- tional project management policies and procedures. Despite their best efforts, her department consistently completed projects behind schedule with several cancella- tions. Out of desperation she started secretly using Agile methods to complete software projects. By using Agile PM her project teams were able to not only meet but beat project schedules—a rarity within her company. When top management confronted her for not conforming to procedure, she pointed to her recent success rate to defend being left alone. Ultimately management couldn’t argue with success, and she was allowed to expand her efforts.

The repeated success and improvement in software development projects have led to key elements of Agile PM being incorporated in the Project Management Body of Knowledge (PMBOK). In 2011 the Project Management Institute began offering a certification in Agile PM along with the traditional Project Management Professional (PMP).

Agile PM does not satisfy top management’s need for budget, scope, and schedule control. Remember the new house analogy. The buyers got exactly what they wanted but did not know how much it would cost. Nor did they know how long it would take or even what it would look like when it was done. While ballpark estimates are pro- vided, Agile methods by their very nature do not provide the detailed estimates of time and costs that management likes. No matter how realistic “it depends” is, management as well as customers are accustomed to working with a greater level of certainty than Agile provides. In response to the financial concerns, many organizations establish “ceilings,” which is the maximum budget that should not be exceeded in the develop- ment of a given product or service.

Even if management totally buys into the value of Agile PM, one cannot simply install it into an organization overnight; it needs to evolve over time. Many of the Agile principles, including self-organizing teams and intense collaboration, are incompatible with corporate cultures. For example, the principle of self-organizing teams, in which members decide who should do what, regardless of rank or title, contradicts command and control structures. Likewise, intense collaboration is not for everyone. One Agile manager confessed that she had to let several of her top engineers go because their lone-wolf personalities were not compatible with collaboration. Most companies report gradual introduction of Agile project management. For example, Siemens Medi- cal Systems started with one Scrum team in 2004, then 10 Scrum teams in 2005, 70 teams in 2006, and over 97 teams in 2007.

A recent survey of over 3,900 respondents working in software/IT, financial and professional services provides a glimpse of the current state of Agile. Nine-four per- cent report their firm uses Agile approaches. Still only 53 percent report that their agile projects have been successful. The biggest reasons for failure were: (1) lack of experi- ence with agile methods, (2) company culture at odds with core agile values, and (3) lack of management support (Schur, 2015).

As noted earlier, Agile methods appear to work best on small projects that require only five to nine dedicated team members to complete the work. Here face-to-face communication replaces time-consuming documentation and informal coordination supplants top-down control.

Although some companies have successfully applied Agile PM to large projects, others have struggled with the scaling challenge. Too often coordination requirements

Chapter 16 An Introduction to Agile Project Management 595

Agile project management has emerged as a response to the challenges of managing projects with loosely defined scopes and high levels of uncertainty. Agile relies on an iterative development process in which the scope of the project evolves over time. Development teams create feature-driven working products at the end of each develop- ment cycle. Active customer involvement is used to guide this process. Here are some of the key advantages of Agile methods: ∙ Work is divided into smaller and smaller chunks that are more easily scheduled and

controlled. ∙ Collaboration between the customer and designers is increased leading to solid

change control. ∙ Methods demand that features be tested and functional when completed.

Agile PM is still evolving. While much of the attention in this chapter has been devoted to software development, Agile PM is being successfully applied to a wide range of unpredictable projects. New methods and approaches will continue to be developed and adapted to meet the specific needs of projects. Stay tuned.

Summary

undermine the adaptability of small teams, which is a chief strength of Agile PM. This has led many companies to use hybrid models that combine Agile and waterfall meth- ods. For example, IPC Media, a subsidiary of Time Inc., uses an iterative waterfall approach in which large projects are broken down into subprojects performed by dif- ferent teams in parallel. Short sprints and additional check points are used within a structured planned process. A recent survey of more than 800 software engineers reported that 40 percent were using a hybrid approach on their projects.2

Companies that enjoy success on large projects tend to have had a strong history of using Agile on smaller projects, and Agile principles are part of their product develop- ment culture.

Agile requires active customer involvement. Involvement comes in different shapes and forms. Designating an internal person to act as a product owner to repre- sent the interests of customers is relatively easy. Soliciting the active participation of external customers can be more problematic. Even though there is consistent evi- dence that customer participation enhances project success, not all customers want to be that actively involved. Many are simply too busy. Others believe that they hired the project team so they would not have to be involved. Securing the cooperation of customers to devote the requisite time to support Agile PM is a common source of frustration in the field.

Agile PM frameworks, like Scrum, are used exclusively to complete software development projects from beginning to end. Other companies are using Agile PM only during the early exploratory phase of a project. Agile PM is used to develop critical breakthrough technology or define essential features. Once the features and technology are known, then traditional project management is applied to complete the project.

2 http://www.jamasoftware.com/media/documents/State_of_Requirements_Management_2011.pdf.

596 Chapter 16 An Introduction to Agile Project Management

1. Break into small groups and identify at least two real-life examples of projects in which:

a. The scope and technology are well known. b. The scope is well known but the technology is less well known. c. The scope is not well known but the technology is known. d. Neither the scope nor the technology is well known. 2. Break into small groups and discuss the following question: What organizational, group, individual, and project factors do you think would pro-

mote the successful adoption of Agile PM methodologies like Scrum? Why? 3. Use a project you are currently working on to hold a Scrum meeting according to

the steps outlined in Figure 16.5. Designate one member to act as the Scrum master and hold a standing meeting that lasts no longer than 15 minutes. Assess the value of such meetings.

4. Below are four mini-cases from practice. Break into small groups and (1) analyze the case and (2) provide five recommendations for the IT department.

Project A You’ve just taken over a project from another project manager and have come back from a very uncomfortable meeting with your business sponsor. In the meeting, the sponsor told you how dissatisfied he is with the project’s performance to date and that he’s getting ready to pull the plug on the project entirely. Deadlines keep slipping, the application isn’t complete, and the sponsor feels like he can’t get in touch with anyone to give him an update on the project’s status and progress.

From conversations with your project team, you learn that requirements still haven’t been finalized, and the team is waiting for input before being able to proceed on several key parts of the application. Despite that, they’ve been able to push forward in other areas, and are quite proud of the work they’ve done. However, they haven’t had a chance to show it to the sponsor.

Exercises

1. Why is the traditional project management approach less effective when project scope and technology are not well known?

2. What is iterative incremental development? Why is it useful for developing new products?

3. What are the advantages of Agile PM? What are the disadvantages of Agile PM? 4. What similarities and differences exist between a traditional project manager and a

Scrum master? 5. What are the differences between a self-organizing team and a conventional project

team? 6. Why is it difficult to apply Agile PM to large-scale projects?

Review Questions

Key Terms Agile Project Management, 579 Feature, 585 Iterative, incremental development (IID), 572

Product backlog, 588 Product owner, 586 Release burndown chart, 590 Scaling, 592

Scrum master, 587 Self-organizing team, 587 Sprint backlog, 589 Sprint burndown chart, 589

Chapter 16 An Introduction to Agile Project Management 597

To complicate matters further, your boss has made it clear that this project must be completed on schedule, because he needs the resources for another project.

What do you do? What impact do your decisions have on the project’s cost, sched- ule, and performance?

Project B Your project team has finished gathering the requirements and developing the solution design. Your team is broken into two main groups: The first group consists of the project manager, business analysts, and management and is located in the United States. The second group consists of the development and QA teams and they are located in India.

The WBS was developed based on estimates from the teams in India. The develop- ment team agreed to provide daily updates to you about progress against the WBS to make sure that the project’s milestones are going to be met.

However, by the time the development team got close to the first milestone, it became obvious that they were behind even though their daily updates indicated that they are on track. In addition, the team adopted a different design approach than the one agreed upon at the beginning of the project.

The lack of meaningful updates from the development team along with a different design track has jeopardized the whole project by rendering the whole plan obsolete. Your team is now at risk of not delivering the project.

What do you do? What is the impact to cost, schedule, and performance?

Project C You have just taken over as the program manager of a large program with multiple tracks and a go-live scheduled in three months. At the first meeting with the project sponsors and key stakeholders, you find out that the business requirements are not complete and in some cases not started, project scope is not realistic to meet the upcoming go-live, and overall the project teams are confused due to lack of communi- cation and understanding of priorities.

What do you do? What impact do your decisions have on the project’s cost, sched- ule, and performance?

Project D You’ve just been assigned to take over a new project from an outgoing project manager. The project is a high-visibility project that is using a development methodology that is new to you and to your company. In your transition meetings with the outgoing project manager, he assures you that development is complete, and all you have to do is shep- herd the project through acceptance testing and release. As a result, several project team members were released as scheduled.

The acceptance testing does not go as smoothly as planned. The application has more defects than anticipated, and some core functionality is not able to be tested. The project team doesn’t feel like they are getting the direction they need to continue mov- ing forward, and the business sponsor has asked you when he can expect to test appli- cation functionality that wasn't a part of the original scope. In addition, your project’s deadline is rapidly approaching, and interproject dependencies make it unlikely that you will be able to push your launch date.

What do you do? What impact do your decisions have on cost, schedule, and performance?

598 Chapter 16 An Introduction to Agile Project Management

Boulter, M., Smart Client Architecture and Design Guide (Seattle: Microsoft Press, 2004). Decarlo, D., eXtreme Project Management (Jossey-Bass, 2004). Faris, R., and I. Abdelshafi, “Project Management and Agile: Perfect Fit,” 2006 PMI Global Congress Proceedings, Seattle, Washington. Gale, S. F., “The Evolution of Agile,” PM Network, January 2012. Griffiths, M., Using Agile Principles Alongside: A Guide to the Project Management Body of Knowledge, PMI Global Proceedings, Anaheim, California, 2004. Highsmith, J., Agile Project Management (Boston: Addison Wesley, 2004). Hildebrand, C., Full Speed Ahead, PM Network, vol. 21, no. 10 (October 2007), pp. 36–41. Jackson, M. B., “Step by Step,” PM Network, vol. 26, no. 6 (June 2012), pp. 57–61. James, M., “Scrum,” 2009 (downloaded PDF @ http://refcardz.dzone.com/ on 5/18/2009). Jonasson, Hans, Determining Project Requirements (Boca Raton, FL: Auerback Publications, 2008). Kruchten, P., The Rational Unified Process: An Introduction, 3rd ed. (Upper Saddle River, NJ: Pearson Education, 2004). Larman, C., Agile & Iterative Development: A Manager’s Guide (Boston: Addison- Wesley, 2004). McConnel, S., Rapid Development: Taming Wild Software Schedules (Redmond, WA: Microsoft Press, 1996). Schur, M., “The State of Agile,” PM Network, September 2015, pp. 16–17. Schwaber, K., Agile Project Management with Scrum (Redmond, WA: Microsoft Press, 2004). Takeuchi, H., and I. Nonaka, “The New Product Development Game,” Harvard Busi- ness Review, January–February 1986. Tarne, R., “Taking Off the Agile Training Wheels, Advance Agile Project Manage- ment using Kanban,” 2011 PMI Global Proceedings, Dallas, TX, 2011. Vanderjack, B., “21 Methods to Engage and Retain Your Product Owner in an Agile Project,” www.pmworldjournal.net, vol. 1, no. 4 (November 2012), pp. 1–6. Worthen, B., “Try Software on Workers First, Fix It Later,” The Wall Street Journal, September 25, 2007, pp. B1 and B4.

References

Chapter 16 An Introduction to Agile Project Management 599

Case 16.1

Introducing Scrum at P2P PART A Kendra Hua had worked for six years as a software engineer in the IT department at Point 2 Point (P2P), a large freight moving company. She liked her job and the people she worked with. While she did some maintenance work, she worked primarily on projects, usually full time. Her work covered a wide range of projects including system upgrades, inventory control, GPS tracking, billing, and customer databases. These projects were typically able to meet project requirements but were consistently late. Within the IT department it was common practice for a betting pool to emerge regard- ing completion dates. The rule of thumb was to take the original schedule and multiply it by 1.5 and start guessing from then on. Management decided to try to turn things around by changing the way P2P completed IT projects. Instead of the traditional waterfall approach in which all the requirements were defined upfront, the IT department was to start using Agile project management, and more specifically Scrum, to complete their projects. Kendra had just been assigned to the Big Foot project, which involved develop- ing a system for monitoring P2P’s carbon footprint. To prepare for this project, Kendra and her entire team of software engineers would attend a two-day Scrum workshop. Everyone was given a book on Scrum to prepare themselves for the workshop. At first Kendra was overwhelmed by terminology—Scrum master, sprints, product man- ager, sprint logs, and so forth. She questioned the rugby metaphor, since the only thing she knew about the sport was that one of her ex-boyfriends in college would come back to the dorm inebriated and bloodied after a match. And why was the project manager called a master? It seemed demeaning to her. Still, she had heard some good things about Scrum from a friend who was using it in another company. He claimed it gave programmers more freedom to do their work and work at a faster pace. So she approached the two-day workshop with an open mind. The workshop was facilitated by a trainer who was well versed in the world of soft- ware development. Participants included her other five team members as well as Prem Gupta, a veteran project manager who would now assume the role of Scrum master, and Isaac Smith, who would act as the product manager representing the interests of the customers. At first everyone gave Prem a hard time, by bowing to him, pleading “mas- ter, master, master . . .” The facilitator quickly corrected them by saying he was not their master but rather master of the Scrum process. The facilitator went on to emphasize that they would work as a self-organizing team. Kendra wasn’t exactly sure what that meant, but she felt it had something to do with the team managing itself, not Prem. The workshop covered all the basic Scrum tools, concepts, and roles. Everyone got to practice the process by completing a simulated project involving the creation of a new board game. Kendra liked the idea of the standing Scrum meeting, since most of her meetings at P2P took way too long. She also liked having the product manager, who was the ultimate decider on features and when work was completed. Everyone laughed at the “only one neck to wring” analogy that the facilitator used to describe this role. Overall she thought the process had promise and she was excited about trying it out on the Big Foot project. The Big Foot project was estimated to be completed after five sprints with each sprint lasting four weeks.

600 Chapter 16 An Introduction to Agile Project Management

THE FIRST SPRINT The first sprint planning meeting went pretty much by the book. Isaac had done his homework and came to the meeting with a comprehensive list of features the software needed to provide. There was healthy discussion, and Isaac amended the list to include some features that the team felt was necessary. The afternoon session featured Isaac, the product owner, prioritizing the features in the product backlog with feedback from the team. The final segment was devoted to the team deciding among themselves which high priority features they would commit to build within the four-week sprint. Prem did a good job of reminding the team that they were expected to build a fully functional feature. This tempered the team’s enthusiasm, and in the end a challenging but doable set of features was assigned to the sprint backlog for the first sprint. The first couple of daily Scrum meetings were a bit awkward as members were care- ful not to step on each other’s toes. One of the first impediments identified was not having a shared understanding of how a self-organizing team worked. Prem kept emphasizing that it was up to the team to decide who does what and when. Then one morning it just suddenly clicked and members came forward claiming work they felt needed to be done. After that the daily scrums took on a life of their own, interrupted only when a member had to do five push-ups for every minute late. The pace of work picked up, and there was a shared enthusiasm as tasks and ultimately functional fea- tures were completed in rapid fashion. Kendra worked side by side with the other software engineers to solve problems and share what they had learned. Occasionally Isaac would be called into the project room to answer questions about specific features and be shown work in progress. By the time of the first sprint review meeting, the team was able to demonstrate all but one of the designated features to Isaac and even three more that were not on the initial hit list. The team got some useful feedback not only from Isaac but also from a couple of the end users he brought with him. Eighty percent of the features were pro- claimed done by Isaac while the others needed only slight modifications. Everyone agreed that the next Sprint review would even be more successful. The sprint retrospective meeting was refreshing as members spoke candidly about both the good and the bad. Everyone agreed that the team needed to do a better job at documentation. Issues regarding fairness and spreading both the fun work and the tough work among the entire team were brought to the surface. Kendra was impressed by how everyone focused on what was best for the project not just themselves.

THE SECOND SPRINT The second sprint meeting went well. The features that needed rework after the first sprint review meeting were at the top of the backlog and Isaac made appropriate adjustments in priorities, and a couple of new features that were discovered during the sprint review meeting were added. The meeting convened with the team confident that they would be able to complete the work they had committed to. Project work progressed quickly over the next week. Kendra felt pressure to accom- plish what she said she would at the daily Scrum. At the same time, she felt a tremen- dous amount of satisfaction reporting work done. The entire team seemed energized. Then one day everything came to a standstill over a sticky integration problem. The team struggled over the next three days trying to solve the problem until, at the next Scrum, Prem stepped forward saying, “I think you should do this . . .” He then pro- ceeded to outline a specific method for solving the problem, even assigning specific

Chapter 16 An Introduction to Agile Project Management 601

tasks to each team member. During the next two days Prem went back and forth between team members coordinating their work and solving problems. While there was some grumbling within the team, his solution worked, and Kendra was grateful to get back on track. From then on Prem took a more active role in daily Scrum meetings, often having the final say as to the work agenda for that day. The meetings took on a different tone as members waited for Prem to speak first. Isaac was absent from the project room during this time as he was visiting sites that would be using the new software. Still, features were being completed and Kendra was happy with the progress. Then one day Isaac showed up at the morning Scrum meeting. He had just gotten back and had fresh information he wanted to introduce into the project. He had rewritten the product log and added several new, high priority features and eliminated a few of the features that the team had been working on. He wanted the team to shift their efforts and complete the new features by the end of the sprint. The team was shocked because one of the principles they had been taught is that you don’t change course midway through a sprint. Prem did his best to explain this to Isaac, but he was insistent. He kept saying that these changes had to be made, otherwise much of the sprint output would be a waste of time. He kept repeating that the team needed to be flexible. “After all, isn’t that what the Agile approach is all about?” The meeting came to an impasse until Prem came forward with a compromise. The team would agree to do the new work, but the sprint needed to be extended by two weeks. Everyone agreed and Kendra went back to work. Up till the end of the second sprint, Prem continued to direct project work. When it came for the sprint review meeting four of the five new features were completed as well as most of the original features. However, the feature demonstrations did not go well. Isaac and several of the end users that were present were critical of the user friendliness of several of the completed features. Kendra and other team members defended their work by saying, “Why didn’t you tell us you wanted it to perform that way?” Prem did his best to keep the meeting under control, but the team had little to say when an important feature simply did not work. In the end, only half of the features were accepted as being done. Kendra walked out of the sprint review discouraged. Tomorrow morning was the sprint retrospective meeting. She had a lot on her mind, but wasn’t sure what she should say or how to say it at the meeting. 1. How well is Scrum working? 2. What are the issues confronting the Big Foot project? 3. Assume you are Kendra. What would you want to say at the retrospective? How

would you say it? 4. What improvements or changes need to be made?

PART B Prem opened the retrospective by saying he had gotten a call from his boss and she was not happy with the progress. Prem said that he and the team were under the gun to get back on track. The list of things that went well during the second sprint was short and when it came time to discuss improvements there was an awkward silence. Kendra spoke up and began by saying she had gone back and reviewed the Scrum book. She went on to say that she thought the whole idea behind Scrum was that the team was to work to solve their own problems and it wasn’t Prem’s role to play task master. A

602 Chapter 16 An Introduction to Agile Project Management

couple of other team members murmured agreement. Prem became defensive and said if he had not intervened it would have taken days for the team to solve the problem. Another member said he thought it was a mistake allowing Isaac to change the sprint commitments. Prem agreed that in principle that was true, but said sometimes you have to bend the rules to do what is right. He admonished the team by saying that they had to practice being more agile. The retrospective ended with few specific rec- ommendations other than that in order to get back on track, Prem felt he would have to get even more involved in the execution of the project. The subsequent sprint 3 planning meeting was more of a formality. Isaac updated the product backlog with revised priorities and Prem signed off for the team as to what they would commit to. There was little interaction between the team and Isaac except seeking clarification on performance requirements for specific features. The team met under Prem’s leadership for their daily Scrums. Sometimes the Scrums went beyond the normal 15 minutes as Prem reviewed progress and described in detail what needed to be done that day. Isaac would occasionally show up, change priorities, review work and answer questions. Kendra worked hard on her assignments and often received praise from Prem for work well done. One evening when the team got together for a few beers and sushi, one of the team members pulled out a spreadsheet and asked who wanted to make the first bet on when they thought the project would be done. After several sprints, Isaac finally signed off on the last feature and declared the project completed. A collective “yahoo” sprang from the team. After the meeting Kendra went around collecting money from each of her teammates—she had predicted that the project would take 12 weeks longer than planned. 1. How would you assess P2P’s effort at introducing Scrum? 2. What challenges does an organization face when adopting an Agile approach like

Scrum? 3. What could P2P have done to enhance success?

603

A P P E N D I X O N E

Solutions to Selected Exercises Chapter 2

2. Payback = Investment Annual savings

PaybackProject Alpha = $150,000 $40,000 = 3.75 years

PaybackProject Beta = $200,000 $50,000 = 4.00 years

A lower payback is better. Project Alpha has the lower payback and so has the better payback.

5. Project NPV = I0 + Σ n t=1

Ft (1 + k)t

For Dust Devils Project using the NPV equation:

NPV = −$500,000 + $50,000(1 + .20)1 + $250,000 (1 + .20)2 +

$350,000 (1 + .20)3

= −$500,000 + $41,667 + $173,611 + $202,546 = − $82,176 For Dust Devils Project using Excel:

A B C D E F  1 Expected ROI 20%  2  3 Dust Devils  4  5 Year Inflows Outflows New flows NPV  6 0 $500,000 −$500,000 −$500,000  7 1   $50,000      $50,000      $41,667 =D7/((1+$C$1)^A7  8 2 $250,000    $250,000    $173,611  9 3 $350,000    $350,000    $202,546 10 −$82,176 11 12 −$82,176 =D6+NPV($C$1,D7:D9)

604 Appendix 1 Solutions to Selected Exercises

The expected ROI is entered in cell C1 and that will be referenced in the worksheets for the next two projects. Cells E6 to E10 repeat the calculations shown in the previ- ous equations, only using Excel. Cells E7 to E9 perform the three discounting cal- culations. The equation used is shown in cell F7. The dollar signs in “$C$1” keep that cell from changing when this formula is copied up or down. In Excel, this is called an absolute reference.

Cell E12 performs the NPV calculations as shown in the textbook. Excel gives the same answer either way. Cell F12 shows the formula for the direct NPV calculations.

For Osprey Project using the NPV equation:

NPV = −$250,000 + $75,000(1 + .20)1 + $75,000

(1 + .20)2 + $75,000

(1 + .20)3 + $50,000

(1 + .20)4

= −$250,000 + $62,500 + $52,083 + $43,403 + $24,113 = −$67,901

For Osprey Project using Excel:

A B C D E F

15 Osprey

16

17 Year Inflows Outflows New flows NPV

18 0 $250,000 −$250,000 −$250,000 19 1 $75,000 $75,000 $62,500 =D19/((1+$C$1)^A19) 20 2 $75,000 $75,000 $52,083

21 3 $75,000 $75,000 $43,403

22 4 $50,000 $50,000 $24,113

23 −$67,901 24

25 −$67,901 =D18+NPV($C$1,D19:D22)

For Voyagers Project using the NPV equation:

NPV = −$75,000 + $15,000(1 + .20)1 + $25,000

(1 + .20)2 + $50,000

(1 + .20)3 + $50,000

(1 + .20)4

+ $150,000(1 + .20)5

= −$75,000 + $12,500 + $17,361 + $28,935 + $24,113 + $60,282 = $68,191

Appendix 1 Solutions to Selected Exercises 605

For Voyagers Project using Excel:

A B C D E F

28 Voyagers

29

30 Year Inflows Outflows New flows NPV

31 0 $75,000 −$75,000 −$75,000 32 1   $15,000    $15,000    $12,500 =D32/((1+$C$1)^A32) 33 2   $25,000    $25,000   $17,361

34 3   $50,000    $50,000    $28,935

35 4   $50,000    $50,000    $24,113

36 5 $150,000 $150,000    $60,282

37 $68,191

38

39 $68,191 =D31+NPV($C$1,D32:D36)

The only project SIMSOX should consider is Voyagers. Each of the other two projects would not satisfy the high rate of return SIMSOX expects from its projects.

Chapter 6 3.

A

Identify topic

Group Term Paper

B

Research topic

C

Draft paper

D

Edit paper

G

Proof

F

References

E

Create graphics

H

Submit paper

Activity C is a burst activity. Activity G is a merge activity.

606 Appendix 1 Solutions to Selected Exercises

11.

C

30

5

0

5

Traffic design

35

35

F

15

115

15

130

Illumination

130

145

G

30

115

0

115

Drainage

145

145

H

25

115

5

120

Landscaping

140

145 D

5

5

25

30

Lot layout

10

35

J

5

145

0

145

Bid proposal

150

150

A

5

0

0

5

Survey

5

5

E

80

35

0

35

Approve design

115

115

B

20

5

10

15

Soils report

25

35

I

15

115

10

130

Signing

130

145

ID

Legend

DUR

ES

SL

LS

Description

EF

LF

Early start, late start, early finish, late finish, and slack are shown on the diagram above. The completion time is 150 days. The critical path is A-C-E-G-J.

13.

A 1

1

0 B 61

D 119

0

2 119

5 61

0 0

0 1

Identify topic

Research topic

C 96

3 96

0 Draftpaper

E 10

11

9

110

1 Creategraphics

G 12

12

11

111

0 Finaldraft

F 10

11

9

110

1 References

Edit paper

ID

Legend

DUR

ES

SL

LS

Description

EF

LF

Group Term Paper

H 13

14

12

112

0 Submitpaper

Appendix 1 Solutions to Selected Exercises 607

Early start, late start, early finish, late finish, and slack are shown on the diagram above. The Gantt chart is shown below.

21.

Legend

Lag 10

Lag 3

Lag 4

Lag 5

Lag 3

A

15

Interview

B

5

Def. New Features

C

2

Order Comps

D

8

Prototype

E

5

TEST

F

10

Field Test

ES

LS

SL

EF

LF

SL

10

Duration

Description

0

0

0

15

0

15

10

3

13

18

0

18

18

0

18

20

0

20

25

0

25

33

0

33

24

1

25

29

1

30

33

0

33

43

0

43

The critical path is A-B (finish only)-C-D-F.

Chapter 8 4. Log of Parallel Method of Scheduling: Exercise 8-4

Period Activity Changes

0–1 B Schedule Activity B (first by minimum slack rule) A Schedule Activity A

1–2 - No changes 2–3 - No changes 3–4 - No changes 4–5 C Delay ES of Activity C to 5. Reduce slack to 1 5–6 D Schedule Activity D (minimum slack rule)

C Schedule Activity C E Delay ES of Activity E to 6. Reduce slack to 1

6–7 E Delay ES of Activity E to 7. Reduce slack to 0 7–8 E Delay ES of Activity E to 8. Reduce slack to −1

F Delay ES of Activity F to 11. Reduce slack to −1 8–9 E Delay ES of Activity E to 9. Reduce slack to −2

F Delay ES of Activity F to 12. Reduce slack to −2 9–10 E Schedule Activity E 10–11 - No changes 11–12 - No changes 12–13 F Schedule Activity F

608 Appendix 1 Solutions to Selected Exercises

7. You should not spend time planning how you are going to spend your bonus. The schedule will take 16 days.

A

2

0 2

00

0 2

2

B

1

2 3

22

4 5

2

C

3

2 5

00

2 5

2

D

RESOURCE SCHEDULE

PLAN

1

5 6

00

5 6

2

E

2

6 8

00

6 8

2

F

3

6 9

11

7 10

1

Use the following heuristics: Minimum slack Smallest duration Lowest identification number

G

2

8 10

00

8 10

2

H

2

10 12

00

10 12

2

ID

DURLS

SL

LF

ES EF

Legend

SL

Resource

DUR ES LF SL 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18RES

2

1

3

1

2

3

2

2 2 2

0

5

2

6 2

7

9 1 1 1

12 2 2

14

2

6

5

7

9

12

14

16

0

0 2

0

0

0

0

0

0

ID

A

B

C

D

E

F

G

H

Resources scheduled

2Resources available 2 2 2 2 2 2 2 22 2 2 2 2 2 2

2 2 2 2 2 2 2 2 12 1 1 2 2 2 2

2

2

2

2

2

1

2

2

2 2

2 2 2

2 2

Appendix 1 Solutions to Selected Exercises 609

10.

0 1 2 3 4 5 6 7 8 9 10 11 12Bu dg

et

ID

A

B

C

D

E

F

Total

Cumulative

40 10 10 10 10

32 8 4 8 84

48 12 12 12 12

18 6 2 2 2 6

28 8 8 12

40

206 18 14 18 14 20 26 22 26 2 6 20 20

20 20

18 32 50 64 84 110 132 158 160 166 186 206

A

4

0 4

11

1 5

B

5

0 5

00

0 5

C

4

4 8

22

6 10

D

5

5 10

00

5 10

F

2

10 12

00

10 12

E

3

5 8

22

7 10

Cost by Week

A

B

C

D

E

F

10

8

12

6

8

20

10

4

12

2

8

20

10

8

12

2

12

10

4

12

2

8

6

ID

DURLS

SL

LF

ES EF

Legend

SL

610 Appendix 1 Solutions to Selected Exercises

Chapter 9 2. Use the information contained below to compress one time unit per move using

the least cost method. Reduce the schedule until you reach the crash point of the network. For each move identify what activity(ies) was crashed and the adjusted total cost.

Note: Choose B instead of C and E (equal costs) because it is usually smarter to crash early rather than late AND one activity instead of two activities.

Act. Crash Cost

(Slope) Maximum

Crash Time Normal

Time Normal

Cost

A 0 2 150 B 100 1 3 100 C 50 2 4 200 D 40 1 4 200 E 50 1 3 200 F 0 1 150

1x

F

3

B

2x

A

6

C Initial project duration 13

Total direct cost 3

E

4

D 1,000

Project duration is reduced from 13 time periods to ten. Total direct cost goes up from 1,000 to 1,240. The steps are shown below:

A B C F Duration: 13 2 3 6 1 12

Direct Cost: $1,000 A B D E F 2 3 4 3 1 13

The project has two paths, A-B-C-F, which takes 12 time periods, and A-B-D-E-F, which takes 13 time periods. This gives the project a duration of 13 time periods. The total direct cost is $1,000.

A B C F Duration: 12 2 3 6 1 12

Direct Cost: $1,040 A B D E F 2 3 3 3 1 12

Appendix 1 Solutions to Selected Exercises 611

The cheapest activity to reduce is D at a cost of $40 for one time period. That makes both paths critical. That means that further reductions will require either reducing the same time from an activity on both paths or finding an activity shared by both paths and reducing that activity. Total direct cost goes up from $1,000 to $1,040.

A B C F Duration: 11 2 2 6 1 11

Direct Cost: $1,140 A B D E F 2 2 3 3 1 11

Activity B is on both paths and can be reduced by one time period at a cost of $100.1 That lowers the completion time to 11 time periods and raises total direct cost to $1,140.

A B C F Duration: 10 2 2 5 1 10

Direct Cost: $1,240 A B D E F 2 2 3 2 1 10

Finally, we can reduce C on the first path at a cost of $50 and E on the second path at a cost of $50. That reduces the completion time to 10 time units and raises total direct cost to $1,240. No further reductions are possible.

Activity Normal Time

Normal Cost

Maximum Crash Time

Crash Cost

A 3 150 0    0 B 4 200 1 100 C 3 250 1   60 D 4 200 1   40 E 2 250 0     0 F 3 200 2   30 G 2 250 1   20 H 4 300 2   60 I 2 200 1 200

8.

1Activities C on the first path and E on the second path also have a combined cost of $100. We select B first since it is usually smarter to crash earlier activities first and it is usually smarter to crash one activity rather than two.

612 Appendix 1 Solutions to Selected Exercises

D IA

3X

A

3X

C

GB

H

B

4

D

3X

F

3

E

2X

G

2

I

C

3

H

4

24

F

3

3

E

2X 4

2

4

2

Total direct cost: 2040

CP=A+B+D+H+I Activities changed:

Normal time:

CP=A+B+D+H+I

17

Time:

D

16

Total direct cost: 2000

D IA

3X

A

3X

C

GB

H

B

4

D

3X

F

3

E

2X

G

2

I

C

3

H

3X

24

F

3

3

E

2X 3

2

2X

2

Total direct cost: 2160

CP=A+B+D+H+I

Activities changed:

Time:

CP=A+B+D+H+I

15

Time:

H

14

Total direct cost: 2100

A+B+F+G+I

Activities changed:

H

Appendix 1 Solutions to Selected Exercises 613

D I

3X

A

3X

C H

B

3X

D

3X

F

3

E

2X

G

2

I

C

3

H

3X

F

3

3

E

2X 2X

2

2X

1X

Total direct costs: 2460

Time:

CP=A+B+D+H+I

13

Time: 12

Total direct costs: 2260

B

CP=A+B+D+H+I

I

G

2

A

B

3X

A+B+F+G+I

Activities changed:

A+B+F+G+I

Activities changed:

Duration Direct Cost Indirect Cost Total Cost

17 2,000 1,500 3,500 16 2,040 1,450 3,490 15 2,100 1,400 3,500 14 2,160 1,350 3,560 13 2,260 1,300 3,660 12 2,460 1,250 3,860

The optimum time-cost schedule would be 16 weeks at a cost of $3,490.

Chapter 13 8. Status Report: Ending Period 1 ($000)

Task % Complete EV AC PV CV SV

A 25% 25 50 50 −25 −25 Cumulative Totals 25 50 50 −25 −25

Status Report: Ending Period 2 ($000)

Task % Complete EV AC PV CV SV

A 50% 50 100 100 −50 −50 Cumulative Totals 50 100 100 −50 −50

614 Appendix 1 Solutions to Selected Exercises

Status Report: Ending Period 3 ($000)

Task % Complete EV AC PV CV SV

A 100% 100 200 100 −100 0 B 0% 0 0 100 0 −100 C 0% 0 0 150 0 −150 Cumulative Totals 100 200 350 −100 −250

Status Report: Ending Period 4 ($000)

Task % Complete EV AC PV CV SV

A 100% 100 200 100 −100 0 B 60% 150 100 150 50 0 C 50% 225 200 300 25 −75 Cumulative Totals 475 500 550 −25 −75

Status Report: Ending Period 5 ($000)

Task % Complete EV AC PV CV SV

A 100% 100 200 100 −100 0 B 100% 250 200 250 50 0 C 100% 450 400 450 50 0 Cumulative Totals 800 800 800 0 0

Status Report: Ending Period 6 ($000)

Task % Complete EV AC PV CV SV

A 100% 100 200 100 −100 0 B 100% 250 200 250 50 0 C 100% 450 400 450 50 0 D 75% 150 100 100 50 50 Cumulative Totals 950 900 900 50 50

Status Report: Ending Period 7 ($000)

Task % Complete EV AC PV CV SV

A 100% 100 200 100 −100 0 B 100% 250 200 250 50 0 C 100% 450 400 450 50 0 D 100% 200 150 200 50 0 E 20% 60 100 0 −40 60 F 5% 15 50 0 −35 15 Cumulative Totals 1075 1100 1000 −25 75

Appendix 1 Solutions to Selected Exercises 615

Status Report: Ending Period 8 ($000)

Task % Complete EV AC PV CV SV

A 100% 100 200 100 −100 0 B 100% 250 200 250 50 0 C 100% 450 400 450 50 0 D 100% 200 150 200 50 0 E 100% 300 350 200 −50 100 F 10% 30 100 100 −70 −70 Cumulative Totals 1330 1400 1300 −70 30

Performance Indexes Summary

Period EV AC PV SPI CPI PCIB

1 25 50 50 .50 .50 2% 2 50 100 100 .50 .50 3% 3 100 200 350 .29 .50 5% 4 475 500 550 .86 .95 24% 5 800 800 800 1.00 1.00 40% 6 950 900 900 1.06 1.06 48% 7 1075 1100 1000 1.08 .98 54% 8 1330 1400 1300 1.02 .95 67%

EACf = (BAC − EV)

(EV/AC) + AC = (2,000 − 1,300)

(1,330/1,400) + 1,400 = 2,105

VACf = BAC − EACf = 2,000 − 2,105 = −105

With two-thirds of the project completed the forecast is that the project will be $105,000 over budget at completion.

616

A P P E N D I X T W O

Computer Project Exercises In developing the exercises, trade-offs had to be made to enrich the learning experi- ence. One of the major problems students initially encounter is data and detail over- load. This reduces their ability to identify project and data problems and to compare alternatives. Although the project found in the exercises is real, it has been reduced and detail has been eliminated many times to concentrate on applying project management principles and understanding linkages. In addition, other simplifying assumptions have been made so that students and instructors can trace problems and discuss outcomes. These assumptions detract from reality, but they keep the focus on the objectives of the exercises and reduce student frustration with software intricacies. Moving from these exercises to real projects is primarily one of increas- ing detail.

The POM+ Project* Big Kola Company has been concerned that specialized fruit drinks have been erod- ing their cola market. The CEO mandates that “If you can’t beat them, join them.” Grape juice was the first product that was successful after an advertising blitz claim- ing the antitoxin benefits. Lately, competition is compressing grape juice margins and profits. Months of additional market surveys and focus groups have resulted in three potential high-margin drinks: cranberry, blueberry, and pomegranate. All these choices represent antitoxins. The decision is to produce the pomegranate drink that has many health claims. For example, the relative ability of these juices to eliminate harmful free radicals (antitoxins) is 71 percent for pomegranate, 33 percent for blue- berry, and 20 percent for cranberry (Technion Institute of Technology). The market potential appears very attractive and should have a higher profit margin than the other potential juice products. Another appeal for pomegranate juice is its familiarity in the Middle East and Asia. The Priority Matrix for the POM+ Project is:

Time Scope Cost

Constrain X Enhance X Accept X

* Cliff Gray, Erik Larson, & Pinyarat Sirisomboonsuk, doctoral candidate at Rawls College of Business, Texas Tech University.

Appendix 2 Computer Project Exercises 617

Connor Gage, the project manager, has formed his project team and the members have come up with the following work breakdown structure.

1.0 POM+Project 1.1 R&D product development 1.1.1 Need survey 1.1.2 Set product specs 1.1.3 Shelf life report 1.1.4 Nutrition report 1.2 Secure fruit suppliers 1.3 Initial Production 1.3.1 Equipment rehab 1.3.2 Production trials 1.3.3 Quality trials 1.3.4 Quality metrics 1.3.5 Quality training 1.4 Distribution 1.4.1 Market testing 1.4.2 Package design 1.4.3 Select distributors 1.5 Legal 1.5.1 Complete FDA certification 1.5.2 Register trademark 1.6 Prepare product launch

Part 1 1. Develop the WBS outline using the software available (save your file). 2. Use this file and the information provided below to create a project

schedule. 3. The following holidays are observed: January 1, Martin Luther King Day (third

Monday in January), Memorial Day (last Monday in May), July 4th, Labor Day (first Monday in September), Thanksgiving Day (4th Thursday in November), December 25 and 26.

4. If a holiday falls on a Saturday then Friday will be given as an extra day off, and if it falls on a Sunday then Monday will be given off.

5. The project team works eight-hour days, Monday through Friday. 6. The project will begin on January 3, 2012. 7. Based on this schedule, submit a memo that answers the following questions: a. When is the project estimated to be completed? How many working days will it

take? b. What is the critical path? c. Which activity has the most total slack? d. How sensitive is this network? e. Identify two sensible milestones and explain your choice.

618 Appendix 2 Computer Project Exercises

Include the following (one page) printouts: ∙ A Gantt chart. ∙ A network diagram highlighting the critical path. ∙ A schedule table reporting ES, LS, EF, LF, and slack for each activity. Hints: Change the timescale to months and weeks. The estimated duration of the project is 135 days.

Remember: Save your files for future exercises!

The following information has been derived from the WBS. Note that the activity number is what appears in the software with the complete WBS entered.

#* Activity Duration Predecessor(s)

  3 Need survey 20 None   4 Set product specs 15   3   5 Shelf life report 10   4   6 Nutrition report   5   4   7 Select fruit suppliers 20   5, 6   9 Equipment rehab 30   4 10 Production trials 15   7, 9 11 Quality trials 20 10 12 Quality metrics   5 11 13 Quality training 15 12 15 Market testing 30   5, 6 16 Package design 15 15 17 Select distributors 25   5, 6 19 Complete FDA certification 15   7, 15 20 Register trademark   5   7, 15 21 Prepare product launch 15 13, 16, 17, 19FS + 25

days, 20FS + 15 days

FS = Finish to Start lag

Part 2 Remember the old saying, “A project plan is not a schedule until resources are com- mitted.” This exercise illustrates this sometime subtle, but important point. Using your files from Part 1, input resources and their costs if you have not already done so. All information is found in Tables A2.1 and A2.2. Prepare a memo that addresses the following questions: 1. Which if any of the resources are overallocated? 2. Assume that the project is time constrained and try to resolve any overallocation

problems by leveling within slack. What happens? 3. What is the impact of leveling within slack on the sensitivity of the network? Include a Gantt chart with the schedule table after leveling within slack. 4. Assume the project is resource constrained and resolve any overallocation problems

by leveling outside of slack. What happens?

Appendix 2 Computer Project Exercises 619

TABLE A2.1 Resource Assignments

Activity Resources

Need survey MRKT (500%) Set product specs R&D (400%), MRKT (200%) Shelf life report R&D (300%) Nutrition report R&D (300%) Select fruit suppliers PURCH (100%) Equipment rehab ENG (1,000%), PROD (2,000%) Production trials PROD (1,500%), PURCH (100%), ENG (1,000%) Quality trials QUAL (300%), PROD (500%) Quality metrics QUAL (300%), PROD (100%) Quality training QUAL (300%), PROD (1,500%) Market testing MRKT (500%) Package design DESIGN (300%), MRKT (100%) Select distributors MRKT (500%) Complete FDA certification LEGAL (300%) Register trademark LEGAL (300%) Prepare product launch QUAL (300%), PURCH (200%), PROD (1,500%),

MRKT (500%), ENG (500%), R&D (100%)

TABLE A2.2 Resources Availability and Pay Rates

Resource Abbrev Available Hourly rate

Marketing staff MRKT   5 $ 80/hr R&D R&D   5 $ 80/hr Engineering ENG 10 $100/hr Purchasing PURCH   2 $ 60/hr Quality engineers QUAL   3 $ 80/hr Designers DESIGN   3 $ 60/hr Legal staff LEGAL   3 $120/hr Production PROD 20 $ 60/hr

Include a Gantt chart with the schedule table after leveling outside of slack. Note: No splitting of activities is allowed. Note: No partial assignments (e.g., 50 percent). All resources must be assigned 100 percent.

Part 3 Top management has accepted the July 19th completion schedule created at the end of Part 2. Prepare a brief memo that addresses the following questions: 1. How much will the project cost? What is the most expensive activity? 2. What does the cash flow statement tell you about how costs are distributed over the

life span of the project? Include a monthly cash flow for the project. Once you are confident that you have the final schedule, save the file as a baseline. Hint: Save a backup file just in case without baseline!

620 Appendix 2 Computer Project Exercises

Activity Actual Start Actual Finish Actual Duration Remaining Duration

Need survey 1/3/12    2/2/12   22   0 Set product specs 2/3/12    2/28/12 18   0 Shelf life report 2/29/12 3/13/12 10   0 Nutrition report 3/14/12 3/19/12   4   0 Equipment rehab 2/29/12 23 12

TABLE A2.3 Status Report March 31, 2012

Part 4 A Assume that today is March 31, 2012, and Table A2.3 contains the tracking informa- tion for the project up till now. Enter this information into your saved baseline file and prepare a status report for the first three months of the POM+ project. Your status report should also address the following questions: 1. How is the project progressing in terms of cost and schedule? 2. What activities have gone well? What activities have not gone well? 3. What do the PCIB and PCIC indicate in terms of how much of the project has been

accomplished to date? 4. What is the forecasted cost at completion (EACf)? What is the predicted VACf? 5. Report and interpret the TCPI for the project at this point in time. 6. What is the estimated date of completion? 7. How well is the project doing in terms of its priorities? Try to present the above information in a form worthy of consideration by top management. Include an Earned Value table and a Tracking Gantt Chart. Note: Insert March 31, 2012, as the status date in the Project Information box.

Part 4 B Assume that today is May 31, 2012, and Table A2.4 contains the tracking information for the project up till now. Enter this information into your saved baseline file and pre- pare a status report for the POM+ project. Your status report should address the following questions: 1. How is the project progressing in terms of cost and schedule? 2. What activities have gone well? What activities have not gone well? 3. What do the PCIB and PCIC indicate in terms of how much of the project has been

accomplished to date? 4. What is the forecasted cost at completion (EACf)? What is the predicted VACf? 5. Report and interpret the TCPI for the project at this point in time. 6. What is the estimated date of completion? 7. How well is the project doing in terms of its priorities? Try to present the above information in a form worthy of consideration by top management. Include an Earned Value table and a Tracking Gantt Chart. Note: Insert May 31, 2012, as the status date in the Project Information box.

Appendix 2 Computer Project Exercises 621

Red Zuma Project The ARC Company specializes in developing and selling a wide range of high- quality scooters. Sales representatives report that there is a growing demand for racing scooters. ARC’s president, Robin Lane, is excited about the possibilities and predicts that one day these kinds of razor scooters will be featured in X-Game events. ARC is a small company and uses a strong matrix to optimally utilize lim- ited manpower. The Project Priority Matrix for the Red Zuma Project is:

Time Scope Cost

Constrain X Enhance X Accept X

Part 1 You are a member of a project team assigned to develop the new razor scooter code named “Red Zuma.” Table A2.5 contains the information necessary to create a project schedule. For the purpose of this case assume the following: 1. The project begins January 2, 2015. 2. The following holidays are observed: January 1, Martin Luther King Day (third

Monday in January), Memorial Day (last Monday in May), July 4th, Labor Day (first Monday in September), Thanksgiving Day (4th Thursday in November), December 25.

3. If a holiday falls on a Saturday, then Friday will be given as an extra day off, and if it falls on a Sunday, then Monday will be given as a day off. If December 25th falls on a Friday then Monday will not be given a day off.

4. The project team works eight-hour days, Monday through Friday.

Activity Actual Start Actual Finish Actual Duration Remaining Duration

Need survey 1/3/12    2/2/12   22  0 Set product specs 2/3/12    2/28/12 18  0 Shelf life report 2/29/12 3/13/12 10  0 Nutrition report 3/14/12 3/19/12   4  0 Select fruit suppliers 4/3/12    4/30/12 20  0 Equipment rehab 2/29/12 4/11/12 31  0 Production trials 4/17/12 5/4/12 14  0 Quality trials 5/7/12    5/31/12 18  0 Market testing 4/4/12    5/9/12    26  0 Package design 5/10/12 5/25/12 12  0 Select distributors 5/28/12   4 18 Complete FDA certification 5/11/12 5/31/12 14  0

TABLE A2.4 Status Report May 31, 2012

622 Appendix 2 Computer Project Exercises

Note: FS refers to a Finish-to-Start lag.

ID Task Name Duration Predecessors

  1 1 Red Zuma Project 260 days   2 1.1 Market Analysis   25 days   3 1.2 Product Design   30 days 2   4 1.3 Manufacturing Study   20 days 2   5 1.4 Product Design Selection   10 days 3, 4   6 1.5 Detailed Marketing Plan   15 days 5   7 1.6 Manufacturing Process   30 days 5   8 1.7 Detailed Product Design   45 days 5   9 1.8 Build Prototypes   25 days 8 10 1.9 Lab Test Prototypes   10 days 9 11 1.10 Field Test Prototypes   15 days 9 12 1.11 Finalized Product Design   20 days 7,10,11 13 1.12 Final Manufacturing Process   10 days 12 14 1.13 Order Components     7 days 12 15 1.14 Order Production Equipment   14 days 13 16 1.15 Install Production Equipment   35 days 14FS+20 days,15FS+30 days 17 1.16 Celebrate     1 days 6, 16

TABLE A2.5 Red Zuma: Project Schedule

Construct a network schedule for this project and prepare a memo that answers the following questions: 1. When is the project estimated to be completed? How long will the project take? 2. What is the critical path for the project? 3. Which activity has the greatest amount of slack? 4. How sensitive is this network? 5. Identify two sensible milestones and explain your choices. Include the following printouts: ∙ A Gantt chart. ∙ A network diagram highlighting the critical path. ∙ A schedule table reporting ES, LS, EF, LF, and slack for each activity.

Part 2 The following personnel have been assigned full-time to the Red Zuma project team:

4 marketing specialists 4 design engineers 4 development engineers 4 industrial engineers 4 test riders 2 purchasing agents

Use the file from Part 1 and the information contained in Tables A2.6 and A2.7 to assign resources to the project schedule.

Appendix 2 Computer Project Exercises 623

Part A Prepare a memo that addresses the following questions: 1. Which if any of the resources are overallocated? 2. Assume that the project is time constrained and try to resolve any overallocation

problems by leveling within slack. What happens? 3. What is the impact of leveling within slack on the sensitivity of the network? Include a Gantt chart with the schedule table after leveling within slack.

TABLE A2.7 Red Zuma Resource Assignments

$ Number available

Marketing specialist $80,000/yr    4 Design engineer $125,000/yr  4 Development engineer $110,000/yr  4 Industrial engineer $100,000/yr 4 Purchasing agent $75,000/yr    2 Test rider $70/hr           4

Note: MS Project considers resources in terms of percentages with one full-time worker being 100%.

TABLE A2.6 Red Zuma Project Resources

Task Name Resource Names

Red Zuma Project Market Analysis Marketing Specialist [400%] Product Design Marketing Specialist, Design Engineer [400%], Development Engineer [200%], Industrial

Engineer, Purchasing Agent Manufacturing Study Industrial Engineer [400%], Development Engineer [200%] Product Design Selection Marketing Specialist [200%], Design Engineer [300%], Development Engineer [200%], Industrial

Engineer [200%], Purchasing Agent [25%] Detailed Marketing Plan Marketing Specialist [400%] Manufacturing Process Design Engineer, Development Engineer [200%], Industrial Engineer [300%] Detailed Product Design Marketing Specialist [200%], Design Engineer [400%], Development Engineer [200%], Industrial

Engineer [200%], Purchasing Agent [25%] Build Prototypes Design Engineer [200%], Development Engineer [200%], Industrial Engineer [400%] Lab Test Prototypes Design Engineer [200%], Development Engineer [200%], Test Rider Field Tests Marketing Specialist, Design Engineer [200%], Development Engineer, Industrial Engineer, Test

Rider [300%] Finalized Product Design Marketing Specialist [200%], Design Engineer [300%], Development Engineer [300%], Industrial

Engineer [200%], Purchasing Agent [25%] Final Manufacturing Process Industrial Engineer [300%], Design Engineer, Purchasing Agent [25%] Order Components Purchasing Agent Order Production Equipment Purchasing Agent Install Production Equipment Design Engineer, Development Engineer [300%], Industrial Engineer [400%] Celebration Design Engineer [400%], Development Engineer [400%], Industrial Engineer [400%], Marketing

Specialist [400%], Purchasing Agent [200%]

Note: Resource assignments without brackets are 100%.

624 Appendix 2 Computer Project Exercises

4. Assume that the project is resource constrained and no additional personnel are available. How long will the project take given the resources assigned? (Hint: Undo leveling performed in Part A before answering this question.)

Note: No splitting of activities is allowed. 5. How does the new duration compare with the estimated completion date generated

from Part 1? What does this tell you about the impact resources can have on a schedule?

Include a Gantt chart with a schedule table displaying free and total slack depicting the resource-constrained schedule.

Part B Top management is not happy with the resource-constrained schedule. Robin Lane, the president, has promised retailers that ARC will begin production in time for the major trade show in Las Vegas on January 22, 2016, which means the project needs to be completed by January 17, 2016. She has authorized working the first available Satur- day of each month to help the project get completed sooner. She realizes that this will only reduce the project duration by 12–13 days. After talking to the engineers, everyone agrees that they do not have to wait for the Detailed Product Design to be 100% completed before starting to build the prototype. The consensus is that Building the Prototype can start 30 days after the start of the Detailed Product Design. Likewise the Final Manufacturing Process can start 15 days after the start of Finalized Product Design. Dewey Martin, director of product development, is also willing to add personnel to the project. He is willing to make available at least one more Development, Design, and/or Industrial Engineer to the project as well as Marketing Specialist. Since there is an acute shortage of personnel at ARC he requests that you only use additional man- power that will help meet the deadline. Your objective is to develop a schedule which will satisfy the deadline with minimum additional resource usage. Prepare a memo that addresses the following questions: 1. What was the impact of introducing Start-to-Start lags to the schedule and budget? 2. Which, if any additional personnel assignments, would you choose to complete the

project before the January 17th deadline? Explain your choices as well as the rea- sons for not choosing other options.

3. How have these changes affected the sensitivity of the network and the critical path?

Include a Gantt chart with a schedule table displaying free and total slack for the new schedule. Note: Do not assign new personnel to specific tasks, simply add them to the Resource Sheet. All new personnel are available full time (100%).

At first glance—this appears to be a very complicated, difficult assignment, but if you enter the information correctly, the computer is able to generate the answers with a few simple clicks.

Appendix 2 Computer Project Exercises 625

Part 3 Top management has accepted the schedule created at the end of Part 2. Prepare a brief memo that addresses the following questions: 1. How much will the project cost? What is the most expensive activity? 2. What does the cash flow statement tell you about how costs are distributed over the

life span of the project? Include a monthly cash flow for the project. Once you are confident that you have the final schedule, save the file as a baseline. Hint: Save a backup file just in case without baseline!

Part 4 Part A Today’s date is July 8, 2015, the milestone date for the completion of the Prototype. You are charged with preparing a status report for top management. Table A2.8 summarizes progress on the Red Zuma project. Submit a professional status report to Robin Lane that addresses the following questions: 1. How is the project progressing in terms of cost and schedule? 2. What activities have gone well? What activities have not gone well? 3. How much of the project has been accomplished (PCIB)? 4. What is the forecasted cost at completion (EACf)? 5. What is the estimated completion date? 6. How is the project doing in terms of priorities (see Part 1)? Report and interpret relevant Earned Value metrics in your report. Include a Tracking Gantt chart as well as an Earned Value Table with your memo.

TABLE A2.8 Red Zuma Project Update

Task Name Act. Start Act. Finish % Comp. Phys. % Comp. Act. Dur. Rem. Dur.

  1 1 Red Zuma Fri 1/9/15 NA 46% 0% 125.85 days 146.4 days   2 1.1 Market Analysis Fri 1/9/15 Thu 2/12/15 100% 0% 25 days 0 days   3 1.2 Product Design Fri 2/13/15 Wed 4/1/15 100% 0% 35 days 0 days   4 1.3 Manufacturing Study Fri 2/13/15 Fri 3/6/15 100% 0% 16 days 0 days   5 1.4 Product Design Selection Thu 4/2/15 Fri 4/17/15 100% 0% 13 days 0 days   6 1.5 Detailed Marketing Plan NA NA 0% 0% 0 days 15 days   7 1.6 Manufacturing Process NA NA 0% 0% 0 days 30 days   8 1.7 Detailed Product Design Mon 4/20/15 Wed 6/24/15 100% 0% 49 days 0 days   9 1.8 Build Prototypes Wed 6/10/15 NA 39% 0% 9 days 14 days 10 1.9 Lab Test Prototypes NA NA 0% 0% 0 days 10 days 11 1.10 Field Test Prototypes NA NA 0% 0% 0 days 15 days 12 1.11 Finalized Product Design NA NA 0% 0% 0 days 20 days 13 1.12 Final Manufacturing Process NA NA 0% 0% 0 days 10 days 14 1.13 Order Components NA NA 0% 0% 0 days 7 days 15 1.14 Order Production Equipment NA NA 0% 0% 0 days 14 days 16 1.15 Install Production Equipment NA NA 0% 0% 0 days 35 days 17 1.16 Celebrate NA NA 0% 0% 0 days 1 days

626 Appendix 2 Computer Project Exercises

Part B You have told Robin Lane that based on what you know now you need to revise the estimates for some of the remaining activities. Detailed Product Design is expected to take 3 days longer than planned. Build Prototypes is expected to take 2 days less than planned and Finalized Product Design is expected to take 3 days longer than planned. Final Manufacturing Process is expected to take 2 days less than planned, while Install Production Equipment is now expected to take only 30 days. You also report that Detailed Marketing plan will be completed before the end of the New Year. She is insisting that the project be completed by January 17th in order to be ready for the Las Vegas show. She is willing to spend $50,000 from Management Reserves to expedite shipping if necessary. $25,000 would reduce the shipping of components by 5 days and/or $25,000 would reduce the shipping of manufacturing parts by 5 days (Hint: Adjust lag). Prepare a memo to Robin that addresses the following questions: 1. What is the impact of the revised estimates for Finalized Product Design and Install

Production Equipment on the project schedule and cost? 2. Would you recommend authorizing the expenditure of $50,000? Explain. 3. What, if any other recommendations, would you make so that the project can

achieve Robin’s deadline? Justify your recommendations. Include a Tracking Gantt chart with variance schedule that depicts your final recom- mendations and revised schedule. Hint: After adjusting the Installation of Production Equipment and Finalized Product Design, level outside of slack to eliminate any resource over allocation problems.

Conveyor Belt Project

Part 1 Project Description The new computer-controlled conveyor belt is an exciting project that moves and positions items on the conveyor belt within <1 millimeter. The project will produce a new system for future installations, and for replacement of those in the field, at a low cost. The computer- controlled conveyor belt has the potential to be a critical unit in 30 percent of the systems installed in factories. The new system is also easier to update with future technologies. The Project Priority Matrix for the Conveyor Belt Project (CBP) is:

Time Scope Cost

Constrain X Enhance X Accept X

Table A2.9 has been developed for you to use in completing the project exercises.

Assignment Develop the WBS outline using the software available to you. Question Does this information (WBS) allow you to define any milestones of the project? Why or why not? What are they? Remember: Save your file for future exercises!

Appendix 2 Computer Project Exercises 627

TABLE A2.9 Conveyor Belt Project; WBS

Conveyor Belt Project

Hardware Hardware specifications Hardware design Hardware documentation Prototypes Order circuit boards Assemble preproduction models

Operating system Kernel specifications Drivers     Disk drivers     Serial I/O drivers Memory management Operating system documentation Network interface

Utilities Utilities specifications Routine utilities Complex utilities Utilities documentation Shell

System integration Architectural decisions Integration first phase System hard/software test Project documentation Integration acceptance testing

Part 2 Use your file from Part 1 and the information provided below to complete this exercise. (See Table A2.10.) 1. Each work package will represent an activity. 2. The project begins January 4, 2010. 3. The following holidays are observed: January 1, Memorial Day (last Monday in

May), July 4th, Labor Day (first Monday in September), Thanksgiving Day (4th Thursday in November), December 25 and 26.

4. If a holiday falls on a Saturday then Friday will be given as an extra day off, and if it falls on a Sunday, then Monday will be given as a day off.

5. The project teams work eight-hour days, Monday through Friday. Warning: Experience has taught students to frequently make separate backup files for each exercise. The software is never as friendly as users expect! Construct a network schedule for the conveyor belt project and prepare a memo that addresses the following questions: 1. When is the project estimated to be completed? How long will the project take? 2. What is the critical path(s) for the project? 3. Which activity has the greatest amount of slack? 4. How sensitive is this network? 5. Identify two sensible milestones and explain your choices. 6. Compare the advantages/disadvantages of displaying the schedule as a network

versus a Gantt chart.

628 Appendix 2 Computer Project Exercises

Include the following printouts: ∙ A Gantt chart. ∙ A network diagram highlighting the critical path. ∙ A schedule table reporting ES, LS, EF, LF, and slack for each activity. Hint: the project should be completed in 530 days. Remember: Save your file for future exercises!

Part 3 Remember the old saying, “A project plan is not a schedule until resources are com- mitted.” This exercise illustrates this subtle, but very important, difference.

Part A Using your files from Part 2 input resources and their costs if you have not already done so. All information is found in Tables A2.10 and A2.11.

TABLE A2.10 Conveyor Belt Project; Schedule

Activity Description Resource Duration (days) Preceding Activity

  1 Architectural decisions Design   25 —   2 Hardware specifications Development, design   50 1   3 Kernel specifications Design   20 1   4 Utilities specifications Development, design    15 1   5 Hardware design Design, development 70 2   6 Disk drivers Assembly, development 100 3   7 Memory management Development   90 3   8 Operating system documentation Design, documentation   25 3   9 Routine utilities Development   60 4 10 Complex utilities Development   80 4 11 Utilities documentation Documentation, design   20 4 12 Hardware documentation Documentation, design   30 5 13 Integration first phase Assembly, development   50 6,7,8,9,10,11,12 14 Prototypes Assembly, development   80 13 15 Serial I/O drivers Development 130 13 16 System hard/software test Assembly   25 14,15 17 Order circuit boards Purchasing     5 16 18 Network interface Development   90 16 19 Shell Development   60 16 20 Project documentation Documentation, development   50 16 21 Assemble preproduction models Assembly, development   30 17F-S, lag 50 days 22 Integrated acceptance testing Assembly, development   60 18,19,20,21

Note: F-S refers to a Finish-to-Start lag.

TABLE A2.11 Organization Resources

Name Group Cost ($/hr)

Design R&D (2 teams) $100 Development R&D (2 teams)     70 Documentation R&D (1 team)     60 Assembly/test R&D (1 team)     70 Purchasing Procurement (1 team)     40

Appendix 2 Computer Project Exercises 629

Prepare a memo that addresses the following questions:

1. Which if any of the resources are overallocated? 2. Assume that the project is time constrained and try to resolve any overallocation

problems by leveling within slack. What happens? 3. What is the impact of leveling within slack on the sensitivity of the network?

Include a Gantt chart with the schedule table after leveling within slack.

4. Assume the project is resource constrained and resolve any overallocation problems by leveling outside of slack. What happens? What are the managerial implications?

5. What options are available at this point in time?

Include a Gantt chart with the schedule table after leveling outside of slack.

Note: No splitting of activities is allowed. Note: No partial assignments (e.g., 50 percent). All resources must be assigned 100 percent.

Part B When you show the resource-constrained network to top management, they are visibly shaken. After some explanation and negotiation they make the following compromise with you:

∙ The project must be completed no later than February 2, 2012 (530 days). ∙ You may assign two additional development teams. ∙ If this does not suffice, you may hire other development teams from the outside.

Hire as few external teams as possible because they cost $50 more per hour than your inside development people.

Internal Development Add as many development units (teams) as needed to stay within the 530 days. If you need more than two internal development units, then hire as few external teams as necessary. Select the cheapest possibility! Change as few activities as possible. It is recommended you keep work packages which require cooperation of several organiza- tional units inside your company. You decide how best to do this.

Hint: Undo leveling prior to adding new resources.

Once you have obtained a schedule that meets the time and resource constraints, prepare a memo that addresses the following questions:

1. What changes did you make and why? 2. How long will the project take? 3. How did these changes affect the sensitivity of the network?

Include a Gantt chart with a schedule table presenting the new schedule.

630 Appendix 2 Computer Project Exercises

Part 4 Based on the file created at the end of Part 3, prepare a memo that addresses the fol- lowing questions: 1. How much will the project cost? 2. What does the cash flow statement tell you about how costs are distributed over the

life span of the project? Include a monthly cash flow and a cost table for the project. Once you are confident that you have the final schedule, save the file as a baseline. Hint: Save a backup file just in case without baseline!

Part 5 Prepare status reports for each of the first four quarters of the project given the infor- mation provided here. This requires saving your resource schedule as a baseline and inserting the appropriate status report date in the program. Assume that no work has been completed on the day of the status report. Your status report should include a table containing the PV, EV, AC, BAC, EAC, SV, CV, and CPI for each activity and the whole project. The report should also address the following questions: 1. How is the project progressing in terms of cost and schedule? 2. What activities have gone well? What activities have not gone well? 3. What do the PCIB and PCIC indicate in terms of how much of the project has been

accomplished to date? 4. What is the forecasted cost at completion (EACf)? What is the predicted VACf? 5. Report and interpret the TCPI for the project at this point in time. 6. What is the estimated date of completion? 7. How well is the project doing in terms of its priorities? Try to present the above information in a form worthy of consideration by top management. Include a Tracking Gantt chart with each report.

First Quarter, April 1, 2010 Table A2.12 summarizes the information regarding activities accomplished to date. Be sure to save your file after each quarterly report and use it to build the next report!

Actual Remaining Activity Start Date Finish Date Duration Duration

Hardware specifications 2/9/10    37   8 Kernel specifications 2/8/10   3/12/10 25   0 Disk drivers 3/15/10 13 87 Memory management 3/15/10 13 77 Op. systems documentation 3/15/10 13   7 Utilities specifications 3/8/10  3/29/10 16   0 Complex utilities 3/30/10   2 85 Architectural decisions 1/4/10    2/5/10   25   0

TABLE A2.12 April 1, 2010

Appendix 2 Computer Project Exercises 631

Second Quarter, July 1, 2010 Table A2.13 summarizes the information regarding activities accomplished since the last report.

Third Quarter, October 1, 2010 Table A2.14 summarizes the information regarding activities accomplished since the last report.

Fourth Quarter, January 1, 2011 Table A2.15 summarizes the information regarding activities accomplished since the last report.

Part 6 You have received revised estimates for the remaining activities at the end of the fourth quarter: ∙ Prototypes will be completed on 3/8/11. ∙ Serial I/O drivers will be completed on 6/30/11.

Actual Remaining Activity Start Date Finish Date Duration Duration

Hardware specifications 2/9/10   4/12/10 45   0 Hardware design 4/13/10 56 11 Kernel specifications 2/8/10   3/12/10 25   0 Disk drivers 3/15/10 77 33 Memory management 3/15/10 77 19 Op. systems documentation 3/15/10 4/16/10 25   0 Utilities specifications 3/8/10   3/29/10 16   0 Routine utilities* 4/26/10 47 18 Complex utilities 3/30/10 66 25 Utilities documentation 5/3/10   6/2/10    22   0 Architectural decisions 1/4/10    2/5/10   25   0

TABLE A2.13 July 1, 2010

* The project manager for the external development team that was hired to perform routine utilities reported that due to commitments to other clients they would be able to start on that activity 4/26/10.

Actual Remaining Activity Start Date Finish Date Duration Duration

Hardware specifications 2/9/10   4/12/10   45  0 Hardware design 4/13/10 7/16/10   67  0 Hardware documentation 7/19/10 8/24/10   27  0 Kernel specifications 2/8/10   3/12/10   25  0 Disk drivers 3/15/10 8/17/10 110  0 Memory management 3/15/10 7/30/10   98  0 Op. systems documentation 3/15/10 4/16/10   25  0 Utilities specifications 3/8/10   3/29/10   16  0 Routine utilities 4/26/10 7/27/10   65  0 Complex utilities 3/30/10 8/11/10   95  0 Utilities documentation 5/3/10   6/2/10     22  0 Architectural decisions 1/4/10   2/5/10     25  0 Integration 1st phase 8/25/10   26 24

TABLE A2.14 October 1, 2010

632 Appendix 2 Computer Project Exercises

∙ System hardware/software test will start on 7/1/11 and take 25 days. ∙ Order circuit boards will start on 8/8/11 and take 5 days. ∙ Assemble preproduction model will begin on 10/14/11 and take 18 days. ∙ Project documentation is expected to start on 8/8/11 and will take 55 days. ∙ Network interface is expected to start on 8/8/11 and will take 99 days. ∙ Shell is expected to start on 8/8/11 and will take 55 days. ∙ Integrated acceptance testing is expected to start on 12/29/11 and will take 54 days. Prepare a memo that addresses the following questions: 1. What is the new EAC for the project? How long should the project take given these

revised estimates? 2. How happy will top management be with these forecasts given the priorities of the

project? 3. What recommendations would you make? Include a revised schedule, a Tracking Gantt chart, and cost table with your memo.

Actual Remaining Activity Start Date Finish Date Duration Duration

Hardware specifications 2/9/10    4/12/10    45    0 Hardware design 4/13/10  7/16/10    67    0 Hardware documentation 7/19/10  8/24/10    27    0 Prototypes 11/11/10   34   44 Kernel specifications 2/8/10    3/12/10    25    0 Disk drivers 3/15/10  8/17/10  110    0 Serial I/O drivers 11/11/10   34 119 Memory management 3/15/10  7/30/10    98    0 Op. systems documentation 3/15/10   4/16/10    25    0 Utilities specifications 3/8/10    3/29/10    16    0 Routine utilities 4/26/10  7/27/10    65    0 Complex utilities 3/30/10  8/11/10    95    0 Utilities documentation 5/3/10    6/2/10      22    0 Architectural decisions 1/4/10     2/5/10      25    0 Integration 1st phase 8/25/10   11/10/10   55    0

TABLE A2.15 January 1, 2011

G L O S S A R Y

A 360-degree feedback A multirater appraisal system based on performance information that is gathered from multiple sources (superiors, peers, subordinates, customers).

accept risk When a conscious decision is made to accept the risk of an event occurring (i.e., if risk is too large, if chance of occurring is slim, or if the budget reserve can simply absorb the risk if it materializes).

activity Task(s) of the project that consumes time while people/equipment either work or wait.

Agile Project Management (Agile PM) A family of incremental, iterative development methods for completing projects.

AOA Activity-on-arrow method for drawing project networks. The activity is shown as an arrow.

AON Activity-on-node method for drawing project networks. The activity is on the node (rectangle).

apportionment method Costs allocated to a specific segment of a project by using a percentage of planned total cost—for example, framing a house might use 25 percent of the total cost, or coding a teaching module 40 percent of total cost.

avoiding risk Elimination of the risk cause before the project begins.

B balanced matrix A matrix structure in which the project manager and functional managers share roughly equal authority over the project. The project manager decides what needs to be done; functional managers are concerned with how it will be accomplished.

baseline A concrete document and commitment; it represents the first real plan with cost, schedule, and resource allocation. The planned cost and schedule performance are used to measure actual cost and schedule performance. Serves as an anchor point for measuring performance.

BATNA Best alternative to a negotiated agreement. Strong or weak BATNA indicates your power to negotiate with the other party.

bottom-up estimates Detailed estimates of work packages usually made by those who are most familiar with the task (also called micro estimates).

brainstorming Generating as many ideas/solutions as possible without critical judgment.

budget at completion (BAC) Budgeted cost at completion. The total budgeted cost of the baseline or project cost accounts.

budget reserve Reserve setup to cover identified risks that may occur and influence baseline tasks or costs. These reserves are typically controlled by the project manager and the project team. See management reserve.

burst activity An activity that has more than one activity immediately following it.

C change management systems A defined process for au- thorizing and documenting changes in the scope of a project.

co-location A situation in which project members including those from different organizations work together in the same location.

concurrent engineering Cross-functional teamwork in new-product development projects that provides product design, quality engineering, and manufacturing process engineering all at the same time.

contingency plan A plan that covers possible identified project risks that may materialize over the life of the project.

control chart A chart used to monitor past project schedule performance and current performance as well as estimate future schedule trends.

cost account A control point of one or more work packages used to plan, schedule, and control the project. The sum of all the project cost accounts represents the total cost of the project.

cost performance index (CPI) The ratio of work performed to actual costs (EV/AC).

cost variance (CV) The difference between EV and AC (CV = EV – AC). Tells if the work accomplished cost more or less than was planned at any point over the life of the project.

crash point The most a project activity time can realisti- cally be compressed with the resources available to the organization.

crash time The shortest time an activity can be completed (assuming a reasonable level of resources).

crashing Shortening an activity or project. 633

634 Glossary

critical path The longest activity path(s) through the network. The critical path can be distinguished by identifying the collection of activities that all have the same minimum slack.

cross-cultural orientations A framework which describes and/or explains cultural differences.

culture The totality of socially transmitted behavior patterns, beliefs, institutions, and all other products of human work and thought characteristic of a community or country.

culture shock A natural psychological disorientation that most people suffer when they move to a culture different from their own.

D dedicated project team An organizational structure in which all of the resources needed to accomplish a project are assigned full time to the project.

Delphi technique A group method to predict future events—e.g., time, cost.

direct costs Costs that are clearly charged to a specific work package—usually labor, materials, or equipment.

dysfunctional conflict Disagreement that does not improve project performance.

E early time The earliest an activity can start or finish based on network logic, the data date, and any schedule constraints.

earned value (EV) The physical work accomplished plus the authorized budget for this work. Previously this was called the budgeted cost of work performed (BCWP).

emotional intelligence (EQ) The ability or skill to perceive, assess, and manage the emotions of one’s self and others.

escalation A control mechanism for resolving problems in which people at the lowest appropriate level attempt to resolve a problem within a set time limit or the problem is “escalated” to the next level of management.

estimated cost at completion (EAC) The sum of actual costs to date plus revised estimated costs for the work remaining in the WBS. The text uses EACre to represent revisions made by experts and practitioners associated with the project. A second method is used in large projects where the original budget is less reliable. This method uses the actual costs to date plus an efficiency index (CPI = EV/AC) applied to the remaining proj- ect work. When the estimate for completion uses the CPI as the basis for forecasting cost at completion, we use the acronym

EACf, where EACf = estimated costs at completion. Includes costs to date plus revised estimated costs for the work remain- ing. (Uses formula to compute EAC.)

F fast-tracking Accelerating project completion typically by rearranging the network schedule and using start-to-start lags.

feature A piece of a product that delivers some useful functionality to a customer.

Forecasted total cost at completion (EACf). The expected total cost of the project expressed as the sum of actual costs to date and forecasted estimate of the cost of remaining work based on the current CPI.

free slack The maximum amount of time an activity can be delayed from its early start (ES) without affecting the early start (ES) of any activity immediately following it.

function points Points derived from past software projects to estimate project time and cost, given specific features of the project.

functional conflict Disagreement that contributes to the objectives of the project.

G Gantt chart See bar chart.

groupthink A tendency of members in highly cohesive groups to lose their critical evaluative capabilities.

H hammock activity A special-purpose, aggregate activity that identifies the use of fixed resources or costs over a segment of the project—e.g., a consultant. Derives its duration from the time span between other activities.

heuristics A rule of thumb used to make decisions. Frequently found in scheduling projects. For example, schedule critical activities first, then schedule activities with the shortest duration.

I implementation gap The lack of consensus between the goals set by top management and those independently set by lower levels of management. This lack of consensus leads to confusion and poor allocation of organization resources.

incremental, iterative development (IID) A cyclical development process in which a project gradually evolves over time.

Glossary 635

indirect costs Costs that cannot be traced to a particular project or work package.

infrastructure Basic services (i.e., communication, transportation, power) needed to support project completion.

inspiration-related currencies Influence based on inspiration (opportunity to do good, be the best, etc.).

L lag relationship The relationship between the start and/or finish of a project activity and the start and/or finish of another activity. The most common lag relationships are (1) finish-to-start, (2) finish-to-finish, (3) start-to-start, and (4) start-to-finish.

late time The latest an activity can start or finish without delaying the completion of the project.

law of reciprocity People are obligated to grant a favor comparable to the one they received.

leading by example Exhibiting the behaviors you want to see in others.

learning curve A mathematical curve used to predict a pattern of time reduction as a task is performed over and over.

lessons learned An analysis carried out during and shortly after the project life cycle; they attempt to capture positive and negative project learning.

leveling Techniques used to examine a project for an unbalanced use of resources, and for resolving resource overallocations.

M management by wandering around (MBWA) A management style in which managers spend the majority of their time outside their offices interacting with key people.

management reserve A percentage of the total project budget reserved for contingencies. The fund exists to cover unforeseen, new problems—not unnecessary overruns. The reserve is designed to reduce the risk of project delays. Management reserves are typically controlled by the project owner or project manager. See budget reserve.

management reserve index The percentage of the management reserve that has been used to date.

matrix Any organizational structure in which the project manager shares responsibility with the functional managers

for assigning priorities and for directing the work of individuals assigned to the project.

mentor Typically a more experienced manager who acts as a personal coach and champions a person’s ambitions.

merge activity An activity that has more than one activity immediately preceding it.

met expectations Customer satisfaction is a function of the extent to which perceived performance exceeds expectations.

milestone An event that represents significant, identifiable accomplishment toward the project’s completion.

mitigating risk Action taken to either reduce the likelihood that a risk will occur and/or the impact the risk will have on the project.

N net present value (NPV) A minimum desired rate of return discount (e.g., 15 percent) is used to compute present value of all future cash inflows and outflows.

nominal group technique (NGT) A structured problem- solving process in which members privately rank-order preferred solutions.

O opportunity An event that can have a positive impact on project objectives.

organization breakdown structure (OBS) A structure used to assign responsibility for work packages.

organizational culture A system of shared norms, beliefs, values, and assumptions held by an organization’s members.

organizational politics Actions by individuals or groups of individuals to acquire, develop, and use power and other resources to obtain preferred outcomes when there is uncertainty or disagreement over choices.

outsourcing Contracting for the use of external sources (skills) to assist in implementing a project.

overhead costs Typically organization costs that are not directly linked to a specific project. These costs cover general expenses such as upper management, legal, market promotion, and accounting. Overhead costs are usually charged per unit of time or as a percentage of labor or material costs.

oversight A set of principles and processes to guide and improve the management of projects. The intent is to ensure projects meet the needs of the organization through

636 Glossary

standards, procedures, accountability, efficient allocation of resources, and continuous improvement in the management of projects.

P parallel activity One or more activities that can be carried on concurrently or simultaneously.

partnering charter A formal document that states common goals as well as cooperative procedures used to achieved these goals which is signed by all parties working on a project.

path A sequence of connected activities.

payback method The time it takes to pay back the project investment (investment/net annual savings). The method does not consider the time value of money or the life of the investment.

percent complete index actual costs The amount of work accomplished based on actual costs and revised estimates (AC/EAC).

percent complete index budgeted costs The amount of work accomplished based on project budget (EV/BAC).

percent complete index—actual costs (pcic) The amount of work accomplished based on actual costs and revised esti- mates (AC/EAC).

performance review In general, all review methods of individual performance center on the technical and social skills brought to the project and team. These reviews stress personal improvement and are frequently used for salary and promotion decisions.

personal integrity Adherence to moral and ethical principles.

personal-related currencies Influence based on enhancing another person’s self-esteem.

phase estimating This estimating method begins with a macro estimate for the project and then refines estimates for phases of the project as it is implemented.

phase gating A structured process to review, evaluate, and document outcomes at each project phase and to provide management with information to guide resource deployment toward strategic goals.

planned value (PV) The planned time-phased baseline of the value of the work scheduled. Previously this was called budgeted cost of work scheduled (BCWS).

portfolio management Centralized selection and management of a portfolio of projects to ensure that

allocation of resources is directed and balanced toward the strategic focus of the organization.

position-related currencies Influence based on the ability to enhance someone else’s position within an organization.

positive synergy A characteristic of high-performance teams in which group performance is greater than the sum of individual contributions.

principled negotiation A process of negotiation that aims to achieve win/win results.

priority matrix A matrix that is set up before the project begins that establishes which criterion among cost, time, and scope will be enhanced, constrained, or accepted.

priority system The process used to select projects. The sys- tem uses selected criteria for evaluating and selecting projects that are strongly linked to higher-level strategies and objectives.

priority team The group (sometimes the project office) responsible for selecting, overseeing, and updating project priority selection criteria.

proactive Working within your sphere of influence to accomplish something.

process breakdown structure (PBS) A phase-oriented grouping of project activities that defines the total scope of the project. Each descending level represents an increasingly detailed description of project work.

product backlog A prioritized list of project requirements with estimated time to turn them into complete product functionality.

product owner The person responsible for managing the product backlog in Scrum so as to maximize the value of the project. The product owner represents all stakeholders.

Program A group of related projects designed to accom- plish a common goal over an extended period of time.

project A temporary endeavor undertaken to create a unique product, service, or result.

project charter A document that authorizes the project manager to initiate and lead a project.

project closure All of the activities of shutting down a project. The major activities are evaluation of project goals and performance, developing lessons learned, releasing resources, and preparing a final report.

project cost—duration graph A graph that plots project cost against time; it includes direct, indirect, and total cost for a project over a relevant range of time.

project evaluation The process of assessing, verifying, and documenting project results.

Glossary 637

project facilitator A guide who leads the project team through an analysis of project activities that went well, what needs improvement, and development of a follow-up action plan with goals and accountability. project kick off meeting Typically the first meeting of the project team.

project life cycle The stages found in all projects— definition, planning, execution, and delivery.

Project Management Professional (PMP) An individual who has met specific education and experience requirements set forth by the Project Management Institute, has agreed to adhere to a code of professional conduct, and has passed an examination designed to objectively assess and measure project management knowledge. In addition, a PMP must satisfy continuing certification requirements or lose the certification.

project office (po) A centralized unit within an organization or department that oversees and improves the management of projects.

project portfolio Group of projects that have been selected for implementation balanced by project type, risk, and ranking by selected criteria.

project sponsor Typically a high-ranking manager who champions and supports a project.

project vision An image of what the project will accomplish.

projectitis A condition in which team members become strongly attached to their project and disconnected from the larger organization.

projectized organization A multi-project organization in which project managers have full authority to assign priorities and direct the work of persons assigned to their project.

R range estimating An estimating technique in which multiple estimating points are given based on some logic (i.e., high vs. low or best case, worst case, and most likely case).

ratio (parametric) methods Uses the ratio of past actual costs for similar work to estimate the cost for a potential project. This macro method of forecasting cost does not provide a sound basis for project cost control since it does not recognize differences among projects.

reference class forecasting A sophisticated forecasting method in which you take an external view and forecast project costs based on actual outcomes of similar projects.

relationship-related currencies Influence based on friendship.

release burndown chart The trend of work remaining across time. In a release or product, the source of data is the product backlog with work remaining tracked on the vertical axis and number of sprints on the horizontal axis.

resource smoothing A technique that uses slack to reduce peak resource demand to increase resource utilization.

resource-constrained project A project that assumes resources are limited (fixed) and therefore time is variable.

responsibility matrix A matrix whose intersection point shows the relationship between an activity (work package) and the person/group responsible for its completion.

retrospective A methodology that analyzes a past project event to determine what worked and what didn’t, develops lessons learned, and creates an action plan that ensures lessons learned are used to improve management of future projects.

Revised estimated cost at completion (EACre). The expected total cost of the project expressed as the sum of actual costs to date and revised estimates of the cost of remaining work based on the judgment of those doing the work.

risk The chance that an undesirable project event will occur and the consequences of all its possible outcomes.

risk breakdown structure (RBS) A hierarchical depiction of the identified project risks arranged by risk category and subcategory that identifies the various areas and causes of potential risks.

risk profile A list of questions that addresses traditional areas of uncertainty on a project.

risk register A register detailing all identified risks, including descriptions, category, and probability of occurring, impact, responses, contingency plans, owners, and current status.

risk severity matrix A tool used to assess the impact of risks on a project.

S “sacred cow” A project that is a favorite of a powerful man- agement figure who is usually the champion for the project.

scaling Adapting Agile PM to large, multi-team projects.

scenario analysis Technique for analyzing risks where team members assess the significance of each risk event in terms of probability and impact of the event.

638 Glossary

schedule performance index (SPI) The ratio of work performed to work scheduled (EV/PV).

schedule variance (SV) The difference between the planned dollar value of the work actually completed and the value of the work scheduled to be completed at a given point in time (SV = EV – PV). Schedule variance contains no critical path information.

scope creep The tendency for the scope of a project to expand once it has started.

scope statement A definition of the end result or mission of a project. Scope statements typically include project objectives, deliverables, milestones, specifications, and limits and exclusions.

Scrum master The person responsible for the Scrum process and its correct application.

self-organizing team A semi-autonomous team that manages itself.

sensitivity A function of the number of critical or near-critical paths.

social network building The process of identifying and building cooperative relationships with key people.

splitting A scheduling technique in which work is interrupted on one activity and the resource is assigned to another activity for a period of time, then reassigned to work on the original activity.

sprint backlog A list of tasks that defines a Scrum team’s work for a sprint. Each task identifies those responsible for doing the work and the estimated amount of work remaining on the task on any given day during the sprint.

sprint burndown chart The trend of work remaining across time in a sprint. The source of data is the sprint backlog with work remaining tracked on the vertical axis and days of a sprint on the horizontal axis.

stakeholders Individuals and organizations that are actively involved in the project, or whose interests may be positively or negatively affected as a result of project execution or completion. They may also exert influence over the project and its results.

strategic management process The process of assessing “what we are” and deciding and implementing “what we intend to be and how we are going to get there.” Strategy describes how an organization intends to compete with the resources available in the existing and perceived future environment.

strong matrix A matrix structure in which the project manager has primary control over project activities and functional managers support project work.

systems thinking A holistic approach to viewing problems that emphasizes understanding the interactions among different problem factors.

T task-related currencies Influence based, helping someone else do their work.

team evaluation Evaluating the performance of the project team using a minimum core of conditions in place before the project began. Evaluation practices should emphasize the team as a whole, while minimizing individual performance.

team rituals Ceremonial actions that reinforce team identity and values.

team-building A process designed to improve the performance of a team.

template method Use of a prepared form to develop project networks, costs, and time estimates.

time and cost databases Collection of actual versus estimated times and costs of work packages over many projects that are used for estimating new project tasks and their expected possible error.

time buffer A contingency amount of time for an activity to cover uncertainty—for example, availability of a key resource or merge event.

time-constrained project A project that assumes time is fixed and, if resources are needed, they will be added.

time-phased budget baseline A cost baseline that is derived from the WBS and project schedule. The budgeted costs are distributed to mirror the project schedule.

to complete performance index (tcpi) The calculated cost performance index that must be achieved on the remaining work in order to meet the project budget (BAC-EV)/ (BAC-AC).

top-down estimates Rough estimates that use surrogates to estimate project time and cost (also called macro estimates).

total slack (TS) The amount of time an activity can be delayed and not affect the project duration (TS = LS – ES or LF – EF).

tracking Gantt A Gantt chart that compares planned versus actual schedule information.

transferring risk Shifting responsibility for a risk to another party.

Glossary 639

V variance at completion (VAC) Indicates expected actual cost over- or underrun at completion (VAC = BAC – EAC).

virtual project team Spatially separated project team whose members are unable to communicate face to face. Communication is usually by electronic means.

W weak matrix A matrix structure in which functional managers have primary control over project activities and the project manager coordinates project work.

white elephant A burdensome possession which is not easily disposed of and whose cost (particulary upkeep) is out of proportion with its usefulness.

work breakdown dictionary Provides detailed information about each element in the WBS. The dictionary typically includes the work package level (code), name, and functional description.

work breakdown structure (WBS) A hierarchical method that successively subdivides the work of the project into smaller detail.

work package A task at the lowest level of the WBS. Responsibility for the package should be assigned to one person and, if possible, limited to 80 hours of work.

640

AC Actual cost of work completed ACWP Actual cost of work performed AOA Activity-on-arrow AON Activity-on-node BAC Budget at completion BATNA Best alternative to a negotiated agreement BCWP Budgeted cost of work performed BCWS Budgeted cost of work scheduled BOOT Build-own-operate-transfer CAPM Certified Associate in Project

Management CCPM Critical-chain approach to project

planning and management CPI Cost performance index CPM Critical path method CV Cost variance DUR Duration EAC Estimate at completion (with revised cost

estimates) EF Early finish EQ Emotional intelligence ES Early start ETC Estimate to complete EV Earned value FAC Forecast at completion FF Free float

IFB Invitation for bid KISS Keep it simple, stupid LF Late finish LS Late start MRI Management reserve index MBWA Management by wandering around NIH Not invented here NPV Net present value OBS Organization breakdown structure PCI Percent complete index PCIB Percent complete index—budget costs PCIC Percent complete index—actual costs PDM Precedence diagramming method PERT Project evaluation review technique PMP Project Management Professional PO Project office PV Planned value of work scheduled RBS Risk breakdown structure RM Responsibility matrix SL Slack SPI Schedule performance index SV Schedule variance TCPI To complete performance index VAC Variance at completion WBS Work breakdown structure

A C R O N Y M S

641

PCIB = EVBAC CV = EV − AC

CPI = EVAC

EACf = (BAC − EV )

( EVAC) + AC

EACre = AC + ETCre

MRI = CVMR

te = a + 4m + b

6

σte = ( b − a6 ) TCPI = (BAC − EV)(BAC − AC)

PCIC = ACEAC SV = EV − PV

SPI = EVPV VACf = BAC − EACf VACre = BAC − EACre σTE =

√Σσ2te

Z = TS − TE √Σσ2te

P R O J E C T M A N A G E M E N T E Q U A T I O N S

Chapter 1 Modern Project Management 1.2 Project defined 1.7.1 Project manager 1.3 Project management defined 1.4 Projects and programs (.1) 1.7 Role of the project manager 2.4 The project life cycle (.1.2) (Fig 2.13) 4.1 Integration of project management processes [.2.3.4.5.6] Chapter 2 Organization Strategy and Project Selection 1.4.1 Projects and programs (.2) 1.4.2 Managing the portfolio 1.4.3 Strategy and projects 13.1 Stakeholders (.2.3.4)(2.2.1) (A1.4.2) (A1.5.24)(A1.6.8) 12.1 RFP’s and vendor selection (.3.4) (A1.6.7) (12.2) 11.2.2.6 SWOT analysis Chapter 3 Organization: Structure and Culture 2.1.1 Organization cultures 2.1. Organization structures (.2.3.4.5) 9.1.2.1 Organization charts 1.4.4 Project offices Chapter 4 Defining the Project 5.3.1.2 Project charter (A1.4.1) 5.2 Gather requirements 5.3 Defining scope (A1.5.2) 5.4 Creating a WBS 5.4.2 Tools and techniques 6.2 Define activities 9.1.2.1 Responsibility matrix 10.1 Communication planning (.2.3) (A1.7.8) (X3.4) Chapter 5 Estimating Times and Costs 6.5 Activity duration estimates (.3.1) 6.5.2 Estimating tools (.1.2.3.4) 6.4 Identifying resources 6.4.2.4 Bottom-up estimates 7.2 Activity cost estimates (.1) 5.2.2.5 Delphi method (11.2.2.2) (6.5.2.5) Chapter 6 Developing a Project Plan 4.2.2 Planning tools 6.3.2.1 Precidence diagramming 6.3 Sequence activities (.2) (Fig. 6-11) (Fig. 6-18) 6.6.3.2.1 Bar and milestone charts (8.1.2.3) 6.6.2.2 Critical path method 6.3.2.3 Lead and lag activities Chapter 7 Managing Risk 11.1 Risk management process 11.2 Identifying risks 11.3.2.5 Impact matrix (11.3.2.2) 11.3.2.5 Risk assessment 11.5 Risk responses (.2–.1.2) (A1.5.22) 11.2.31 Risk register (11.5.12) 11.4.2.2 Contingency reserves 4.5.2.3 Change control management (A1.7.)

Chapter 8 Scheduling Resources and Cost 6.6.3.1 Setting a schedule baseline (7.2.1.4(6.5.1.4) 6.6.3.2 Setting a resource schedule 6.6.2.4 Resource leveling 7.3.3.1 Cost baseline development 6.6.2.3 Critical chain method 4.0 Change control (A1.7.2) Chapter 9 Reducing Project Duration 6.6.2.7 Schedule compression Chapter 10 Leadership 1.72 Leadership skills (A1.72) (X3.1) (X3.3) 13.0 Stakeholder management (13.1.2.3.) Chapter 11 Teams 9.2 Building the team (.1.2.3) (A1.6.4) (X3.2) 9.4 Managing the team (A1.6.5) 9.3.2.3 Team building activities 9.2.4 Virtual teams 9.3.3.1 Team performance (9.4.2.2) 9.4.2.3 Conflict management 9.3.2.6 Recognition and awards Chapter 12 Outsourcing 12.1 Procurement requirements (.3.2) (12.2.1.7) 12.1.3.3 Contract types 9.4.2.3 Conflict management (X3.8) 12.2.7 The art of negotiating 12.1.3.6 Change requests (12.2.4) Chapter 13 Monitoring Progress 7.4.2.1 Cost/schedule system 6.0 Time performance 7.4.2.1 Earned value system 7.4.2.4 E.V., performance status report 7.4.2.2 E.V., forecasts 7.4.2. EV., to complete index (EAC) 7.4.2.1 Schedule and cost variance (Fig 7-12) Chapter 14 Project Closure 10.2.2.5 Closure report (8.3.3.8) 8.2.2.) 4.5.1.5 Organization processes (12.1.1.9) (11.6.3.5) 4.6 Administrative tasks (A1.8.) 12.4.1.2 Lessons learned 9.4.2.2 Individual performance appraisals Chapter 15 International Projects 4.1.1.4 Culture awareness Chapter 16 Agile PM 1.5.22 Project management and governance 1.4.4 Project offices (PMO)(4.1) (4.5.2) (10.3.2.2) (2.2.2) 8.1.3.2 Continuous improvement 5.2 Requirements vs. actual (.1) (5.2.2) (5.2.3.1) 6.7 Schedule control 2.4.2.4 Adaptive life cycle 6.2.2.2 Rolling wave

Cross Reference of Project Management Body of Knowledge (PMBOK, 6th ed) Concepts to Text Topics A Socio-Technical Approach to Project Management

A Socio-Technical Approach to Project Management

Le ve

l o f e

ffo rt

1. Goals 2. Specifications 3. Tasks 4. Responsibilities

1. Schedules 2. Budgets 3. Resources 4. Risks 5. Staffing

1. Status reports 2. Changes 3. Quality 4. Forecasts

1. Train customer 2. Transfer documents 3. Release resources 4. Evaluation 5. Lessons learned

Defining

Defining

Start Time End

Planning

Planning

Executing

Executing

Closing

Closing

Project Life Cycle

The Technical and Sociocultural Dimensions of the Project Management Process

Technical

Scope WBS Schedules Resource allocation Baseline budgets Status reports

Sociocultural

Leadership Problem solving Teamwork Negotiation Politics Customer expectations

644

Index A Abdel-Hamid, T., 328 Abdelshafi, I., 598 Abramovici, A., 501 Abrashoff, D. M., 365 acceleration options, 307–312 accounting services, 357, 438 Acer Predator 6, 306 Ackoff, Russell L., 545, 572 activity

basic relationships, 168–170 burst, 166, 169, 174 defined, 164, 166, 168 hammock, 188 level of detail, 178 merge, 166, 169, 172–173 numbering, 179 parallel, 166, 169 in project networks, 164–170 splitting, 255, 269, 295–296, 300

activity-on-arrow (AOA), 167–170 activity-on-node (AON), 167–170

versus activity-on-arrow (AOA), 167–168

automated warehouses, 169, 170, 171–177, 179–181

backward pass, 173–175 basic relationships, 168–170 computers in developing, 179–182 forward pass, 171–173 fundamentals, 167–168 laddering, 182, 183 lag relationship, 182–187

combinations, 183, 186 finish-to-finish, 186 finish-to-start, 183 start-to-finish, 186 start-to-start, 183–184 use in forward and backward

pass, 186–187 activity orientation, 557 actual cost (AC)

defined, 466 variance analysis, 468–469

Adams, A. M., 232 Adams, J. R., 395, 407 Adaptive Software Development, 593 adjourning stage of team development, 378 Adler, N., 551, 568, 572 Adler, P. S., 55 administrative support, dependencies

of, 342

Aerial Transportation, Inc., 135 aerospace industry, 72, 383 Agile Alliance, 593 Agile Manifesto, 593 Agile PM (Agile Project Management),

221n, 579–595 examples of, 584, 585 iterative incremental development

processes (IIDs), 582–584 with large projects, 592–593 limitations and concerns, 593–595 nature of, 579–580 process break-down structure (PBS), 584 scrum, 585–592 traditional methods versus, 580–582

AgileZen, 590 Ahmadi, R., 328 Air France (Concorde), 150 airlines, 150, 438 airplane production, 297, 422–423 Albaugh, Jim (Boeing), 423 Alexander, R. C., 35n6, 57 Allen, Roger E., 101n Allen, Stephen D., 101n all-or-nothing projects, 222 alternatives, in group decision making, 394 AMRDEC Maintenance Engineering

Division, 434 Anand, V., 365 Anbari, F. T., 501 Ancona, D. G., 365 Andersen, Arthur E., 357 Andersen, Erling S., 366 Angola, 548 Angus, R. B., 456 Aniftos, S., 539 Apocalypse Now (film), 549 Apple, 15, 32, 36, 49, 74, 306, 420, 423 Applebaum, Jeffrey, 431 apportionment, for estimating project times

and costs, 137 Arenas, Gilbert, 520 Arms, P. B., 555, 572 Arrow, K. J., 258, 291 Arthur Andersen, 356, 357 artificial intelligence, 30 Ashforth, B. E., 365 Ashley, D. B., 102, 124 Atkinson, W., 232 AT&T, 27, 67–68, 138, 535 audit. See project audit automated warehouses, 169, 170, 171–177,

179–181

automotive industry, 13, 387 Avatar (film), 404n avoiding risk, 217

B backward pass-latest times, 173–175

lag relationships, 186–187 using backward pass information,

177–178 Badaracco, J. L. Jr., 365 Baker, B. M., 328 Baker, B., 232, 365 Baker, W. E., 365 balanced matrix, 76 Bangalore (India), 420. See also India Bank of America, 138 Bard, J. F., 367 Barnes, M., 154 Barnes, R., 301, 302 baseline budget, 470–471 baselines

changes in, 483–484 developing, 273–278, 470–471 project cost, 251, 273–278 project monitoring information system,

461, 467, 470–471, 483–484 time-phased budget, 251, 273–278,

465, 467 basic nature of people, 557 BATNA (best alternative to a negotiated

agreement), 438 Baxter, Jerry B., 308n Bay of Pigs invasion (Cuba), 403 Bedeian, A. G., 232 behavior, in organizational culture, 85 Beijing Olympics (2008), 150 BellAircraft, 222 Benko, C., 20, 55 Bennis, W., 360, 365 Benson, S., 408 Berkun, S., 389n6, 407 Bertsche, R., 365 best alternative to a negotiated agreement

(BATNA), 438 best practices in outsourcing, 426–434

co-location, 432 conflict management processes 429, 431 fair and incentive-laden contracts, 433 frequent review and status updates,

431–432 long-term outsourcing relationships,

433–434

Index 645

Hector Gaming Company, 57–58 The Hokies Lunch Group, 22–25 The Home Improvement Project,

126–127 Horizon Consulting, 97–99 International Capital, Inc.—Part A,

245–246 International Capital, Inc.—Part B, 329 Introducing Scrum at P2P, 599–602 Kerzner Office Equipment, 410–412 Manchester United Soccer Club,

125–126 Maximum Megahertz Project, 542 Moss and McAdams Accounting Firm,

94–96 Nightingale Project—A, 332–333 Nightingale Project—B, 333–334 The “Now” Wedding—Part A,

334–336 The “Now” Wedding—Part B, 336 Phuket A, 576 Post Graduation Adventure, 156–157 Power Train, Ltd., 292–294 Scanner Project, 504 Sharp Printing, AG, 155–156 Shell Case Fabricators, 444–446 Shoreline Stadium Case, 204–205 Shoreline Stadium Status Report Case,

502–503 Silver Fiddle Construction. 234–235 Sustaining Project Risk management

during Implementation, 238–240 Tom Bray, 371–372 Trans LAN Project, 235–236 Tree Trimming Project, 502 Whitbread World Sailboat Race,

329–331 XSU Spring Concert, 237–238

Casey, W., 80, 80n, 92 Castro, Edson de, 389 Cavendish, J., 456 C. C. Myers, Inc., 308 CCPM. See critical-chain project

management (CCPM) celebration in closing stage, 521 certification programs, 4 Certified Associate in Project Management

(CAPM), 4 change management systems, 227–229

change request forms and logs, 227–229 integration of, 228–229

changed priority closure, 518 Chaparral Steel, 80–81, 88 Charnes, A., 291 Chatman, J., 82n, 93 checklists

closing stage, 516, 518, 519 project scope, 103, 105–106 in project selection, 41

time-phased budget baselines, 251, 273–278, 465

Buehler, R., 147, 154 buffers

feeder, 296 project, 296 resource, 296 time, 225

Build-Own-Operate-Transfer (BOOT) provisions, 217

bureaucratic bypass syndrome, 404 Burgess, A. R., 291 burst activities, 166, 169, 174 Button, S., 301, 302

C Cabanis, J., 356n6, 365 Cabanis-Brewin, J., 361n, 365 Cahill, T., 547, 572 Caldwell, D., 365 Caldwell, D. F., 82n, 93 calendar dates, for project activities, 182 Calhoun, Chad, 312 California Department of Transportation

(CalTrans), 308 Callaway Golf, 104 Cameron, K. S., 92 Canan, Cystal, 431 Capability Maturity Model (CMM), 529 CAPM (Certified Associate in Project

Management), 4 career paths. See project management

career paths Carlton, J., 74n, 92 Carr, M. J., 232 Carrier Transicold, 220 cases

The Accounting Software Installation Project, 446–447

A Day in the Life, 20–22 Advantage Energy Technology Data

Center Migration—Part A, 202–204

Advantage Energy Technology Data Center Migration—Part B, 246–249

Ajax Project, 412–413 Fly-Fishing Expedition, 233–234 AMEX, Hungary, 574–576 Blue Mountain Cabin, 292 The Blue Sky Project, 367–371 Buxton Hall, 447–450 The CCPM Dilemma, 303 Cerberus Corporation, 372–373 Film Prioritization, 58–59 Franklin Equipment, Ltd., 414–416 Fund Raising Project Selection, 62–63 Goldrush Electronics Negotiation

Exercise, 450–451

training and team-building activities, 428– 429

well-defined requirement and procedures, 426–427

beta distribution, PERT, 240–241 beverage industry, 13 Beyer, J. M., 82n, 92 Biesenthal, C., 366 Big Bertha, 104 “Big Dig” (Boston), 106 Bigelow, D., 55 bio-tech industry, 309 Bird’s Nest (Beijing), 150 Block, T. R., 92, 523n Bloom, Howard, 520n Bloomberg Business Week, 547 Boeing, 148, 301, 422 Boeing 787 Dreamliner, 422 Bogart, Humphrey, 420 bottom-up estimates, 134–144

nature of, 134–135 parametric procedures, 140 range estimating, 140 template methods, 140

Bolman, D. G., 385n, 407 Bonar, Robert, 14 Boulter, M., 598 Bourne, Lynda, 119n, 344n, 365 Borsuk, R., 572 Bowen, D., 560n, 573 Bowen, H. K., 88, 92, 389, 407 Bowles, M., 501 Boyer, C., 55 Bradberry, T., 361n, 365 Bradford, D. L., 345, 346n, 365 brainstorming

of cost saving options, 322–323 in generating alternatives, 394

Brandon, D. M. Jr., 501 Brandt, S. E., 395, 407 bread-and-butter projects, 50 bribery, 555, 562, 565 Brin, Sergey, 84 Brooks, Frederick P. Jr., 309, 309n1,

328, 459 Brown, S., 92 Brown, Tim, 583, 583n Brucker, P., 291 Bruzelius, N., 149, 154 Bryant, Kobe, 376 Budd, C. S., 302 Bucharest (Romania), 420 budget at completion (BAC), 466 budget reserves, 224 budgets

budget reserves, 224 percent complete index—budgeted

costs (PCIB), 477 Project Baseline Budget, 470–471

646 Index

Coppola, Francis Ford, 549 core project team, in accelerating project

completion, 310 Corning Bio, 309 cost account, 113 Cost and Optimization Engineering (Jelen

and Black), 159 cost estimates, 130–148

apportion methods, 137 consensus methods, 136 factors influencing quality of, 130–132 forecasting final project cost,

479–481 function point methods, 138–139 guidelines for, 132–133 learning curves, 139, 157–161 level of detail, 143–144 mega projects, for, 149–150, 152 parametric procedures, 140 phase estimating, 141–143 range estimating, 140 ratio methods, 137 refining, 146–148 template methods, 140 time and cost databases, 148 top-down versus bottom-up, 134–143 types of costs, 144–146

cost performance index (CPI), 476 cost-plus contracts, 454–455 cost risks, in contingency planning, 222 cost saving options, brainstorming of,

322–323 cost-sharing ratio (CSR), 454 cost/schedule graph, 468, 469 cost variance (CV)

computing, 466, 478 defined, 466 variance analysis, 468–469

Coutu, D. L., 401, 407 Covance, 309 Covey, Stephen R., 358, 360n9, 365, 437,

437n, 443 Cowan, C., 426n, 443 crashing, 314–321 crash point, 315–316 crash times, 314–316, 319 Crawford, Lynn, 20, 38, 55 critical-chain project management

(CCPM), 294–302 accelerating project completion,

311, 312 in action, 296–297, 301 impact on project schedule, 298 methodology, 296 monitoring project performance,

300–301 splitting tasks, 300 time estimates, 295–296 traditional scheduling approach versus,

297–298

conflict management, 394–398 dedicated project teams and, 73–75 dysfunctional conflict, 396, 397–398 functional conflict, 396–397 low-priority projects, 395 matrix management and, 78 in outsourcing, 429–431 resource conflicts, 36–37 virtual project teams and, 402–403

Confucius, 562 Conrad, Joseph, 549 consensus methods

consensus testing in group decision making, 393

for estimating project times and cost, 136–137

construction/demolition agencies, 254 consultants, external

as independent project facilitators, 525–526

in rejuvenating the project team, 398–399 contingencies, in project estimation, 133 contingency funding, 223–225 contingency planning, 219–223

cost risks, 222 funding risks, 222–223 schedule risks, 222 technical risks, 220–221

Contingency Planning and Management. com, 548n, 572

contract change control system, 455–456 contract management, 451–456

contract change control system, 455–456 cost-plus contracts, 454–455 fixed-price contracts, 453–454 nature of contracts, 452 in outsourcing, 452–456 in perspective, 456 procurement management and, 452

contractors. See also outsourcing dependencies of, 343 incentive contracts, 307, 308, 433 selection from bid proposals, 425–426

control. See also project monitoring information system

in conflict management, 397 contract change control, 455–456 defined, 459, 461 project control process, 461–462 risk response control, 225–226

control charts, in project monitoring information system, 462, 463–464

control tower project office, 80 Controlled Demolition Inc., 218 Cooke-Davies, T., 538 Cooper, M. J., 302 Cooper, W. W., 291 cooperation. See also project teams

in leading by example, 355 in negotiations for outsourcing, 433, 435

Chen, M., 555, 572 Chermack, T. J., 56 Chetty, T., 149, 155 Chilmeran, A. H., 124 China

cross-cultural factors in, 562–563 guanxi, 562 legal/political factors in, 562–563

Christensen, D. S., 480, 501 Chudoba, K. M., 408 Chunnel project, 149, 420 Cigna, 134 Citibank Global Corporate Bank, 523 Citigroup, 547 Clark, J., 390, 409 Clark, K. B., 92, 407 clean air industry, 13 Cleland, D. I., 407 Cleveland Cavaliers, 520 closing stage, 8–9, 515–536

adjourning stage of team development, 378

dedicated project teams and, 75 evaluation, 516, 532–536 post-implementation evaluation, 516,

532–536 project closeout checklists, 516, 518,

539–541 of project life cycle, 8, 395–396 retrospectives, 516, 525–529 sources of conflict in, 395–396 types, 516–518 wrap-up activities, 516, 518–521

Coady, Gerry (Frontier Airlines), 42 Coca-Cola Co., 13 Cochran, Dick, 535n, 536, 538 CogniToys, 13 Cohen, A. R., 345, 346n, 365 Cohen, D. J., 20, 55 Colangelo, Jerry (Phoenix Suns), 376 Collins, J. C., 88, 92, 572 co-location

in outsourcing, 432 team identity and, 387–388

combination of lag relationships, 186 communication

cultural factors in, 551–552, 570. See also cultural factors

in international projects, 551, 570 in outsourcing, 427, 428, 431, 433, 437 project communication plan, 119–121 virtual project teams and, 400,

402–403 compadre system, 556 computer industry, 29, 30, 35, 271 Conaway, W. A., 560n, 573 concurrent engineering, 184–186 conductor metaphor, 344 conference calls, virtual project teams

and, 402

Index 647

documentation. See also reports and reporting in outsourcing, 428 public documents in organizational

culture, 85 Doh, J. P., 572 doing it twice, in accelerating project

completion, 310 Dooley, K. J., 382, 409 Doran, G. T., 33, 33n, 55 Drexl, A., 291 Drexler, John A., 414n, 443, 444 dropped baton, 295 Drummond, Erin, 312n Duffey, M. R., 501 Dunbar, E., 573 Duncan, David (Arthur Andersen), 357 Duncan, J., 232 DuPont, 138 duration of project. See project duration Dvir, D., 80n, 94, 301, 302 Dworatschek, S., 92 Dyer, L., 408 Dyer, S., 443 Dyle, Dov, 28 dysfunctional conflict, 396–398

E EACf (estimated cost at completion,

forecast), 479 EACre (estimated cost at completion,

revised), 479 Earley, Kristin, 532 early times and late times, 166 earned value (EV)

additional earned value rules, 478–479, 505–511

defined, 462, 466 development of earned value cost/

schedule system, 464–469, 505–511 50/50 rule, 478 percent complete rule, 467 percent complete with weighted moni-

toring gates, 478 pseudo-earned value percent complete

approach, 485 in status report, 471 in time-phased budgets, 276 variance analysis, 468–469 0/100 rule, 478

economic factors, 549–550 Economy, P., 443 Eden, L., 572 EDS, 464 Edward, K. A., 444 Einsiedel, A. A., 366 Eisenhardt, K. R., 92 Eiteman, D. K., 573 electronic bulletin boards, virtual project

teams and, 402

Davis, E. W., 258, 291 deadlines

imposed, 307 in outsourcing, 428

Deal, T. E., 81, 92, 385n, 407 Decarlo, D., 598 decision-making process, 393–394

facilitating, 393–394 importance of, 392–393 nominal group technique (NGT) in, 405 in project meetings, 383–385

dedicated project teams, 71–75 advantages and disadvantages, 72–75 examples of, 72, 74 nature of, 71 projectitis, 74 we–they syndrome, 74

defining stage, 8, 101–121 coding WBS for information system,

113–115 establishing project priorities, 106–108 organization breakdown structure

(OBS), 113 process breakdown structure (PBS),

116–117 project communication plan, 119–121 of project life cycle, 8, 396 project scope, 102–106 responsibility matrices (RM), 117–119 sources of conflict, 396–397 work breakdown structure (WBS),

108–112 Dehler, G. E., 366 De Laat, P. B., 92 Delbeeq, Andrew, 405n Dell Children’s Medical Center, 14 Deloitte Consulting, 35 Delphi Method, 136, 212n DeMarco, T., 310, 328, 407 Demeulemeester, E. L., 291, 302 Deneire, M., 572 Denver Airport, 106, 149, 484 dependencies,

mapping, 348–349 stakeholder, 341–343

Derby, Charles, 20 DeRosa, D., 401, 408 Descamps, J.P., 55 Developing Products in Half the Time

(Smith and Reinertsen), 220 Dexter, Susan, 309 DiDonato, L. S., 443 DiStefano, J. J., 555n, 573 Dinsmore, P. C., 365 direct costs, 145

project, 314 project overhead, 145

Disney, 464 Doctors Without Borders (Médecins Sans

Frontières), 547, 547n

critical path method (CPM), 163, 166, 167, 171, 175–177, 178, 187. See also PERT (program evaluation and review technique)

cross-cultural orientations, 557 Crystal Clear, 593 Cullinane, T. P., 456 cultural factors, 551–553. See also commu-

nication; organizational culture adjustments, 555–556 in China, 562–563 cross-cultural orientations, 557 culture, defined, 554 culture shock, 565–567 in France, 559–560 Hofstede framewok, 558 in Hong Kong, 563 in international projects, 551–553,

554–568 Kluckhohn-Strodthbeck cross-cultural

framework, 557 in Mexico, 556, 558–559 in Namibia (Africa), 568 in outsourcing, 428 in Saudi Arabia, 560–561 summary comments, 565 in the United States, 563–564

culture shock, 565–568 coping with, 567–568 culture shock cycle, four stages of, 566 nature of, 565–566 stress-related, 567

Culver, Irvin, 72 currency fluctuations, 549–550 customer relations

increased customer focus and, 12–14 met expectations, 439–441 project managers as client account

executives, 441 customers

assumption of project responsibilities, 322

dependencies of, 343 scope checklist review with, 105

D Dahlgren, G., 443 daily scrum, 588 DaimlerChrysler, 420 Dalkey, N. C., 154 dangler paths, 182 Daniel, Tim, 547 Darnell, R., 20 databases

project monitoring information system, 460–461, 485

time and cost, 148 Data General Corporation, 389

648 Index

with slack times, 175 using forward pass information,

177–178 Foti, R., 37, 40, 56 Frame, J. D., 92, 387, 408, 523n France, cross-cultural factors in, 559–560 Frank, L., 56 Frankel, Rob, 520 Fraser, J., 457 free float, 177 free slack (FS), 177 Fretty, Peter, 297n, 538 Friedman, Thomas L., 56 Fritz, Robert, 388 Frontier Airlines Holdings, 42 functional conflict, 396–397 functional managers

dependencies of, 343 project managers versus, 7

functional organization, 68–71 advantages and disadvantages, 69–71 nature of, 68–69

“function points,” for estimating project times and cost, 138–139

funding risks, in contingency planning, 222–223

Fusco, Joseph C., 35, 35n4, 56, 533, 533n

G Gabarro, S. J., 366 Gale, S. F., 598 Gallagher, R. S., 92 Gamble, J. E., 104n Gantt, H. L., 179n, 202 Gantt chart, 179

baseline, 462–463 in critical-chain project management

(CCPM), 298, 300 in project monitoring information

system, 462–463 tracking, 462–463, 473–474

Gantz, J., 532n Gardner, D., 523n Gary, L., 124 GE Appliances, 405 Geary, L. K., 93 Gene Codes, 585 general and administrative (G&A)

overhead costs, 145 General Electric (GE), 15, 27, 138,

405, 535 General Motors (GM), 301 geographical factors, 548 Gersick, Connie J., 380, 380n Giangreco, D. M., 527n Gibson, C. B., 408 Ginter, P. M., 232 global project office (GPO), 523 Globerson, S., 125, 367

F Facebook, 13 facilitators. See project facilitators Faerman, S. R., 444 failed projects, 517

The Wake, 517 Failure Mode and Effects Analysis

(FMEA), 215 Faris, R., 598 fast-tracking, 185, 310–311 Federal Deposit Insurance Corporation

(FDIC), 526 feeder buffers, 296 Fendly, L. G., 258, 291 Ferrazzi, K., 366 Ferrucci, D., 30n FHA (Federal Housing Authority), 137 FIFA (Federation Internationale de Foot-

ball Association), 149 Filipczak, B. 92 film industry, 549 final project report, 516, 518, 524–525

analysis, 525 appendix, 525 classification, 525 lessons learned, 516, 525, 526, 527,

529, 532 recommendations, 525

Financial Accounting Standards Board, 438 financial selection models, 38–40

net present value (NPV), 38–40 payback, 38–40

Financial Solutions Group of Mynd, 351 finish-to-finish lag relationship, 186 finish-to-start lag relationship, 183 Fischer, Randy, 431, 435n Fisher, R., 435, 435n, 438, 439, 443 fixed-price contracts, 453–454 Fleming, Q. W., 457, 465n, 476n, 480, 501 float, 175–177

free, 177 total, 175–177

Floyd, S. W., 55 Flyvbjerg, Bent, 149, 150, 151, 154 FMEA (Failure Mode and Effects

Analysis), 215 folklore, in organizational culture, 85 follow-on contracts, 159 follow-up, in group decision making, 394 Ford, E. C., 232 Ford, Henry, 375 Ford Motors, 138, 387 forecasting

of final project cost, 479–480 reference class forecasting (RFC), 151

forming stage of team development, 378 Fortune 500, 34 forward pass-earliest times, 171–173

lag relationships, 186–187

electronics industry, 13 Eliyahu Goldratt Institute, 301, 301n e-mail, virtual project teams and, 402 Emerson, Ralph Waldo, 305 Emhjellenm, K., 155 emotional intelligence (EQ), 361 Emotional Intelligence (Goleman), 361 empathy, 361 Endurance Antarctic expedition, 354 energy conservation, 14 energy efficiency, 14 Englund, R. L., 92 Enron, 356, 357 environmental factors, 546–553

culture, 551–553 economy, 549–550 geography, 548 infrastructure, 550–551 legal/political, 546–547 security, 547–548

environmental sustainability, 12 Dell Children’s Medical Center, 14 London Olympics (2012), 150 Studio Roosegaarde, 13

equipment factor, as resource constraint, 255

Ericksen, J., 408 Ernst, H., 409 errors

as acceptable, 226 network logic, 178 project estimation, 134 reporting, 226

escalation, 429 estimated cost at completion (EAC)

defined, 466, 479 EACf (forecast), 479 EACre (revised), 479

estimated cost to complete (ETC), 466 estimation. See project estimation ethics, 355–357

bribery, 555, 562, 565 code of conduct, 356 collapse of Arthur Andersen, 357 in leading by example, 355 top management and, 356

evaluation. See project evaluation Evans, J., 269, 291 Everest (film), 221 exchange rate fluctuations, 549–550 excessive multitasking, 295–296 executing stage, 8. See also implementation

of project life cycle, 8, 396 sources of conflict, 395–396

expectancy theory of motivation, 320, 320n

expectations managing, 351 met expectations, 439–441

Extreme Programming (XP), 584, 593

Index 649

performance indexes, 476 project percent complete indexes, 477 software for project cost/schedule

systems, 477–478, 511–513 technical performance

measurement, 481 India

infrastructure factors in, 550 outsourcing in, 428

indirect costs, project, 313–314 individual reviews, 536–536 inflation, 550 “influence currencies.” See law of

reciprocity information system. See also project

monitoring information system coding work breakdown structure for,

113–115 in project communication plan,

120–121 infrastructure factors, 550–551 Ingebretsen, M., 124, 232 inspiration-related currencies, 346, 347 integrity, 360 Intel, 27, 301 internal staff specialists, in rejuvenating the

project team, 398 International Business Machines (IBM),

88, 138, 148, 300, 558 international projects, 545–571

cross-cultural factors, 554–568 environmental factors, 546–553 personnel selection and training,

568–570 project site selection, 553–554 virtual project teams in, 399, 400

International SOS Assistance, Inc., 547 Into Thin Air (Krakauer), 221 invitation for bid (IFB), 453 IPC Media, 595 iPhone 7, 306 Irix Pharmaceuticals, 309 iterative incremental development

processes (IIDs), 582–584

J Jackson, M. B., 598 Jago, A. G., 393, 409 Jakarta (Indonesia), 548 James, LeBron, 376, 520 James, M., 598 Jamieson, A., 56 Janis, I. L., 403, 408 Jassawalla, A. R., 93 Jedd, Marcia, 538 Jeffery, R., 154 Jensen, M. C., 377, 409 Jet Propulsion Laboratory, 383 Jobs, Steve, 74

Head, 583 health care industry, 14 Heart of Darkness (Joseph Conrad), 549 Hearts of Darkness: A Filmmaker’s

Apocalypse (film), 549n Hedberg, B., 443 Heise, S., 501 Helm, J., 56 Helpdesk Automated Site (HASS), 389 Henricks, Paul, 309 Hendrickson, Chet, 579 Hendrix, K., 125 Henry, R. A., 210, 232 Herroelen, W. S., 291, 302 heuristics, 258, 259 Hewlett-Packard (HP), 67–68, 399, 405, 535 Highsmith, J., 598 high-tech toy industry, 13 Hildebrand, C., 598 Hill, L. A., 366 Hirschman, A. O., 149, 154 Hoang, H., 443 Hobbs, B., 38, 55, 79, 93 Hobday, M., 93 Hodgetts, R. M., 573 Hoegl, M., 409 Hoffman, R., 535n, 538 Hofstede framewok, 558 Hofstede, Geert, 558, 558n, 573 Holloway, C. A., 92, 407 Hollywood, 3, 13, 320 Homans, G. C., 379n, 408 Homeland Security, 526 Hong Kong, cross-cultural factors in, 563 Hooker, J., 560n, 562n, 573 Hulett, D. T., 232 Hurowicz, L., 258, 291 Hurricane Katrina, 526 Hutchens, G., 56

I IBM, 88, 138, 148, 300, 558 IBM System/360, 309 IBM Watson’s Jeopardy Project, 13, 29, 30 Ibbs, C. W., 328, 538 IDEO, 583 implementation implementation gap in project portfolio

system, 34–35, 36–37 projects in organization strategy, 33 incentives, 320

incentive contracts, 307, 308 project reward systems, 391–392

independence in project estimation, 133 project facilitators, 523

indexes to monitor progress, 475–479 additional earned value rules, 478–479,

505–511

Goal, The (Goldratt), 294–301 Gobeli, D. H., 77, 79, 92, 93, 102, 124, 538 Godfather movies, 549 Gold, Dan, 309 Goldberg, Aaron, 74 Goldberg, A. I., 93 Golden Gate Bridge (San Francisco), 255 Goldratt, Eliyahu, 269, 291, 294–296,

301, 302 Goldsman, L. P., 457 Goleman, Daniel, 361, 361n going native, 545 Goo, S. K., 84n Google, 13, 15, 84 Gordon, R. I., 309n2, 328 governance. See project governance government agencies. See also names of

specific government agencies dependencies of, 343

Governor’s Office of Planning and Research (California), 308

Gradante, W., 523n Graham, J. L., 562n, 572 Graham, R. J., 20, 55, 92 Grant, Adam, 345, 345n, 366 Graves, J., 361n, 365 Gray, Clifford, 8, 20, 79, 92, 232, 426n,

443, 616n Gray, N. S., 154 Green, S. G., 366 Greenland, 548 Griffin, D., 147, 154 Griffiths, M., 598 Gringo, 556 Griswold, T. A., 527n groupthink, 403–404 Gryglak, Adam, 387 guanxi, 562 Gudergan, S., 366 Gundersen, A., 551, 568, 572 Gundersen, N. A., 456 Gustafson, D. H., 405n

H Habitat for Humanity, 312, 312n Hackman, J. R., 408 Haliburton, 519 Hall, C., 306n Hallowell, R., 560n, 573 Hamburger, D. H., 232 hammock activities, 188 Hansson, J., 443 Harris Semiconductor, 301 Harris, P. R., 561n, 573 Harrison, M. T., 82n, 92 Hartman, Frances, 388n Harvard Business School, 584 Hawkins, K., 434 HBO, 583

650 Index

Leading at the Edge (Perkins), 354 leading by example, 353–355 learning curves, for estimating project

times and costs, 139, 157–161 leave-takings, 561 Leavitt, H. J., 404, 408 Lechler, T., 94 LEED (Leadership in Energy &

Environmental Design), 14 Lee, S. A., 328 legal/political factors, 546–547. See also

organization politics Leifer, R., 56 Lerner, Matthew, 309n lessons learned

final project report, 516–518 from Hurricane Katrina, 526 from Operation Eagle Claw, 527

letters of recommendation, 392 Leus, R., 302 leveling, 253, 256–257 level of detail

for project activities, 178 in project estimation, 143–144 for project networks, 178

Levine, H. A., 302 Levi Strauss, 464 Levy, F. K., 202 Levy, S. L., 392, 392n, 409 Lewis, J. P., 124 Lewis, M. W., 366 Lewis, R., 154 Li, M. I., 328 Lieberthal, G., 573 Lieberthal, K., 573 Likert, R., 377n, 408 Lilly, Bonnie, 312 Lincoln, Abraham, 345 Lindberg, Mike, 135 linearity assumption, 319 Linetz, B. P., 408 Lipman-Blumen, J., 404, 408 Lipsinger, R., 401, 408 Lister, T., 407 Loch, C. H., 232 The Lodge at Snowbird (Utah), 593 Logitech, 583 Loizeaux, Mark, 218 London Olympics (2012), 150 Lone Ranger analogy, 352 long-term relationships, in outsourcing,

433–434 Lonza Biologics, 309 Lockheed Aerospace Corporation, 72 Lockheed Martin, 72, 208 looping, 166, 178 Lorsch, J. W., 93 Lovallo, D., 147, 155 Low, G. C., 154 Lowe, D., 457

Krause, Melissa, 585n Kruchten, P., 598 Krupp, Goran, 221 Kryzewski, Mike, 376 Kurtulus, I., 291 Kuruppuarachchi, P., 408 Kvalnes, Ø., 366 Kwak, Y. H., 538

L Lackey, Michael B. (Trojan Nuclear Plant),

482n laddering, 182, 183 Ladika, S., 538 lags, 182–187

in forward and backward pass procedures, 186–187

to reduce schedule detail, 182–184 Lam, N. M., 562n, 572 Lamb, J. C., 309n2, 328 Landau, F., 209n Lane, H. W., 555n, 573 Lange, Merete, 568 Lansing, Alfred, 354, 354n Larman, C., 598 large projects. See also mega projects,

149–151 Larson, Erik W., 69, 72, 77, 79, 92, 93,

102, 124, 355n, 366, 367n, 426n, 443, 538, 616n

Larsson, U., 93 Laslo, Z., 93 Latham, G. P., 535, 538 Lavell, Debra, 538 law of reciprocity, 345–348

inspiration-related currencies, 346, 347

personal-related currencies, 346, 348 position-related currencies, 346–347 relationship-related currencies,

346, 347 styles of social interaction, 545 task-related currencies, 345–346

Lawrence of Arabia (film), 404n Lawrence, P. R., 94 Leach, L. P., 296n, 302 leadership, 339–362. See also project

managers ethics and, 355–356 law of reciprocity and, 345–348 leading at the edge, 354 leading by example, 353–355 managing versus leading a project,

340–341 project stakeholders and, 341–343 qualities of effective project managers,

359–362 social network building, 348–355 trust and, 357–359

Johansen, R., 404, 408 Johnson, Clarence L. “Kelly,” 72, 93 Johnson, Magic, 376 Johnson, R. E., 56 Joint Chiefs of Staff, 527 Jonas, D., 20 Jonasson, Hans, 598 Jones, C., 154 Jordan, Michael, 376 Joshi, M., 365

K Kahneman, D., 147, 155 Kalaritis, Panos, 309 Kanban, 590 Kanter, Rosabeth Moss, 358, 366, 419, 443 Kaplan, R. E., 345, 366 Kaplan, R. S., 56 Karif, O., 13n Katz, D. M., 124 Katz, Ralph, 385n, 388, 408 Katzenbach, J. R., 385n, 408 Keifer, S., 483n Kellebrew, J. B., 291 Kelly, J. E., 202 Kendrick, Tom, 538 Kennedy, A. A., 81, 92 Kenny, J., 56 Kerth, Norman L., 538 Kerzner, Harold, 81n, 93, 124, 501 Kezsbom, D. S., 444 Khang, D. B., 328 Kharbanda, O. P., 56, 129n, 130n, 154 Kidd, Jason, 376 Kidder, Tracy, 389, 389n, 390, 390n, 408 Kim, E. H., 501 King, J. B., 355n, 366 Kipling, Rudyard, 163 Kirk, Dorothy, 351, 351n, 366 Kirkman, B. L., 408 Kluckhohn, F., 557, 557n, 573 Kluckhohn-Strodthbeck cross-cultural

framework, 557 Knoepfel, H., 92 Knoop, C. I., 560n, 573 knowledge explosion, 12 Koh, Aileen, 20 Kokkla (Finland), 548 Kolawa, Adam Dr., 428, 428n Konda, S. L., 232 Koppelman, Joel M., 465n, 476n,

480, 501 Korto, R. F., 56 Kotter, J. P., 340, 366 Kouzes, J. M., 353, 366 Krakauer, Jon, 221n Kraków (Poland), 567 Krane, J., 573 Kras, E., 559n, 573

Index 651

Morigeau, Stuart, 233n Morris, P. W., 56 Morrison, T. 560n, 573 Morton, Danelle, 383, 383n motivation

for extraordinary performance, 320 incentives in, 307, 308, 320

Motorola, 420 Motta, Silva, 56 Müller, R., 356, 360, 366, 367 multi-criteria selection models, 40–43 multiproject environments

project networks in, 182 resource scheduling in, 272–273

multiproject resource schedules, 272–273 multitasking, 36–37, 295–296 multi-weighted scoring models, 41–43 Murch, R., 124 Murphy, C., 390, 409

N Nabisco, 535 Naeni, L., 501 NAFTA, 559 Nambisan, S., 444 Namibia, Africa, cross-cultural factors

in, 568 NASA Mars Climate Orbiter, 208–209 Nash, Steve, 520 National Basketball Association (NBA),

376, 520 National Guard, 526 Navistar, 387 Navy Federal Credit Union, 532 NCR, 464 NEC, 27 negotiation

components of principled, 435–439

in outsourcing, 434–439 Nelson, K. A., 356n7, 367 Nelson, Ryan R., 538 net present value model (NPV)

in project selection, 38, 39 in risk assessment, 215

Netflix, 13 network logic errors, 178 Newbold, R. C., 269, 291, 302 Newmann, L., 291 new products, concurrent engineering

in, 184–186 NIH (not invented here), 379 Nike, 583 Nissen, M. E., 444 Nobel Peace Prize, 547 Nofziner, B., 360, 367 Nokia, 583 nominal group technique (NGT) in, 405 Nonaka, Ikujiro, 585, 598

McDougall, Lorna, 357n McFarlan, F. W., 20, 55 McGrath, M. R., 444 McNerney, Jim, 423 McPherson, S. O., 408 Médecins Sans Frontières (Doctors With-

out Borders), 547, 547n mediating conflict, 397 meetings. See project meetings mega projects, estimation for, 149–151 Melnyk, Les A., 526n Ménard, 79, 93 Mendenhall, M. E., 569n, 573 Menon, R., 232 merge activities, 166, 169, 172–173 Merritt, G. M., 232 met-expectations model, 439 Meyer, A. D., 232 Meyer, D., 269, 291 Meyer, E., 573 Mexico, cross-cultural factors in, 556,

558–559 MGM, 320 Miami Heat, 520 Microsoft Project, 385, 478, 511–513 middle management. See also top

management implementation gap in project portfolio

management, 34–35, 36–37 level of detail in project estimates,

143–144 managing versus leading a project,

340–341 milestones

guidelines for setting, 465 in project scope, 103 schedules, 463–464

Millard, Candice, 552, 552n Miller, D., 555, 572 Miller, J., 72n, 93 Mills, E., 84n Milosevic, D. Z., 56, 155, 564n, 573 mission of organization

project manager, understanding of, 28 in strategic management process, 30

Mitchel, Russ, 271n mitigating risk, 216–217 Mittman, R., 408 Mobil Oil, 535 Moffett, M. H., 550, 573 Mohring, R., 291 Molinski, D., 13n Molloy, E., 149, 155 Monarch, I., 232 Monroe, Marilyn, 420 Montreal Olympics (1976), 150 Moran, James, 202n Moran, R. T., 561n, 573 Moran, S. V., 561n, 564n, 573 Morgan, Pat, 387

loyalty, 352 Luby, R. E., 124 Lucas, E., 555, 572 Lucas George, 549 Lucent Technologies, 301 Luthans, F., 573

M MacCormack, Alan, 584, 584n MacIntyre, Jeff, 35, 35n3, 56 Mackey, J., 302 MacLeod, G., 155 Madnick, S., 328 Magenau, J. M., 444 Magne, E., 155 Magretta, Joan, 56 Maier, N. R. F., 393n, 408 Majchrzak, A., 93, 408 Malhotra, A. A., 408 “management by wandering around”

(MBWA), 350–351, 393 Management Reserve index (MRI), 477 management reserves, 224–225 managing expectations, 351 Managing Martians (Shirley and

Morton), 383 managing upward relations, 351–353 mañana syndrome, 556 Mannakau (New Zealand), 312 Mantel, S. K., 351n3, 367 Marlin, Mark, 538 Marriott Corp., 405 Mars Exploration Program (JPL), 383 Martin, A., 408 Martinelli, Russ, 538 Martin, M., 456 Mass Fatality Identification System

(M-FISys), 585 materials factor, as resource constraint, 254 Matheson, David, 50–51, 50n, 56 Matheson, Jim, 50–51, 50n, 56 matrix management, 75–81

advantages and disadvantages, 77–78 balanced matrix, 76 example of, 89 nature of, 75 performance reviews, 534–535 project versus functional manager

responsibilities, 7, 75 recruiting project members, 381–382 strong matrix, 77 weak matrix, 76–78, 81

maturity models, 529–532 growth levels, 529–532

Maurer, I., 444 MBWA (“management by wandering

around”), 350–351 McConnel, S., 598 McDermott, C. M., 56

652 Index

overhead costs, 145 direct, 145 general and administrative (G&A), 145

oversight. See project audit; project offices (POs)

overtime in accelerating project completion,

308, 310 cross-cultural attitudes toward, 560

ownership, in team building, 399 oyster projects, 50

P pace of life, 555 padding estimates, 131 Panama Canal expansion project, 13 parametric procedures, for estimating

project times and costs, 140 parallel activities, 166, 169 Parker, Ron, 10–11 Pakinson’s law, 295 Parsi, N., 13n partnering charters, 429, 430 Pascoe, T. L., 258, 291 past experience, in project estimation,

130, 157 path, 166 Patheon Inc., 309 Patterson, J. H., 258, 291 Patterson, J., 258, 291 Patzelt, A. H., 538 Paulus, P. B., 379n, 409 Pavlik, A., 232 payback, model, 38 PBS (process breakdown structure), 102,

116–117 pearl projects, 50 Peck, W., 80, 80n, 92 Peel, D., 124 people factor

in assigning project work, 271 dealing with unreasonable people,

438–439 in negotiation process, 434–439 in project estimation, 131 as resource constraint, 254 separating people from problem,

435–436 People’s Republic of China (PRC).

See China Pepsi-Cola, 583 percent complete index—actual costs

(PCIC), 477 percent complete index—budgeted costs

(PCIB), 477 percent complete rule, 467 percent complete with weighted monitoring

gates, 478 performance-based contracts, 433

implications for organizing projects, 86–88

nature of, 81–83 in project estimation, 131 relationship with project structure, 88

organizational culture review questionnaire, 528

Organizational Project Management Maturity Model (OPM3), 529

organization breakdown structure (OBS), 109, 110, 113

integrating with organization, 113, 114

time-phased budget and, 274–276 organization politics

project managers and, 361 in project portfolio system, 35–36 in recruiting project members, 382 trust and, 357–359

organization strategy, 28–51 implementation through projects, 33 managing portfolio system, 48–51 project alignment with, 28 project manager understanding of, 28 project portfolio management system,

37–38 project priority system, 34–37 project selection criteria, 38–43 project selection models, 44 selection model application, 43–48 strategic management process

overview, 29–34 strategy, defined, 27

Orlando Sentinel, 209, 232 Osmundsen, P., 155 outdoor experiences/retreats, 399 outsourcing, 419–441

in accelerating project completion, 309, 322

advantages and disadvantages, 421–424 best practices, 426–434 co-location, 432 communication in, 427–428, 433 conflict management processes,

429–431 contract management, 433, 451–456 customer relations, 439–441 defined, 420 examples of, 422–423, 428, 431 long-term relationships, 433–434 negotiation in, 434–439 in resource allocation, 272–273 review and status updates, 431–432 team-building activities, 426,

428–429 traditional approach versus partnered

approach, 426–427 training activities, 428–429 well-defined requirements and proce-

dures, 426–427

nonfinancial selection models, 40–43 checklist models, 40–41 multi-weighted scoring models, 41–43

nonproject factors, in project estimation, 131 Noreen, E., 302 normal closure, 516–517 normal conditions in project estimation,

132–133 norming stage of team development, 378 Nortel Networks Corp., 547 Northridge earthquake (California), 308 Norton, D. P., 56 not invented here (NIH), 379 Novell, Inc., 271 numbering activities, 179

O objectives

characteristics of, 33 in project scope, 102–103 strategy formulation to meet, 32–34 in supporting organization strategy, 33

O’Boyle, B., 306n OBS (organization breakdown structure),

109, 110, 113 O’Connor, G. C., 56 Oculus Rift, 13 Oddou, G. R., 573 Office of the Chief Medical Examiner

(New York), 585 Ohio School Facilities Commission, 431 Olson, E. M., 93 Olve, N., 443 Olympic Forest, 270 Olympic games, 376 O’Neal, Shaquille, 520 operational projects, 37–38 Operation Eagle Claw, 527 Operations and Technology for Global

Cash Management, 523 OPM3 (Organizational Project

Management Maturity Model), 529

opportunity management, 223 opportunity, defined, 223 responses to opportunity, 223

optimism, 361 Oregon Health Sciences University

(OHSU), 135 O’Reilly, Brian, 535n O’Reilly, C. A., 82n, 93 organizational culture, 68, 81–89. See also

cultural factors characteristics of, 83–86 countercultures and, 83, 86, 88 diagnosis worksheet, 85 ethics in, 355–357 example of, 84 functions of, 82–83

Index 653

classification of, 37–38, 43, 50 defined, 6–7 everyday work versus, 7 examples of for college students, 5 implementing organization through,

33–34 program versus, 7 size, 15

project audits, 516, 521–532 bigger picture of, 529–532 data collection and analysis, 524 external consultants in, 525–526 guidelines for conducting, 522–525 importance of, 521 in-process, 521 initiating and staffing, 522–523 nature of, 521–522 postproject, 521 project maturity models in, 529–532 project offices (POs) and, 522, 523 reporting, 524–525 retrospectives, 525–529 senior management in, 522

Project Baseline Budget, 470–471 project buffers, 296 project charters, 11–12, 105–106, project classification

in project selection, 43 types of projects, 37–38, 50

project closure, 516. See also closing stage wrap-up closure activities, 516,

518–521 project code names, 49 project communication plan, 119–121 project control process, 461–462 project complexity, in project

estimation, 130 project cost baselines, 273–278 Project Cost–Duration Graph, 313–321

crashing, 314–321 determining activities to shorten,

314–316 project direct costs, 314 project indirect costs, 313–314 simplified example, 316–318 time reduction decisions, 320–321 using, 318–319

project definition. See defining stage project duration, 305–323

acceleration options when resources are constrained, 310–312

acceleration options when resources are not constrained, 308–310

cost as issue in, 321–323 lags and, 183–186 practical considerations, 318–321 Project Cost–Duration Graph,

313–321 in project estimation, 131 rationale for reducing, 306–307

position-related currencies, 346–347 positive synergy, 375–377 Posner, B. Z., 125, 353, 360, 366, 367,

395, 409 post-implementation evaluation, 532–536

individual reviews, 535–536 performance reviews, 534–536 team evaluation, 532–534 360-degree reviews, 534–535, 536

postproject retrospectives, 525–529 Powell, M., 93 premature closure, 517 Pressman, R. S., 155 Price, M., 56 PricewaterhouseCoopers, 547 Primavera, 385 principled negotiation, 435 priorities

changed priority closing stage, 518 leading by example, 353 low-priority projects, 395 priority matrix, 107 priority system in project selection,

34, 36–37 project reward systems, 391–392 responsibility for prioritizing projects,

47–48, 50 priority matrix, 107–108 priority system, 34, 36–37, 47–48, 50 priority team, 42 proactive approach, 360 probability analysis, in risk assessment,

215–216 problem identification, in group decision

making, 393 problem solving

in leading by example, 355 in recruiting project members, 382

process breakdown structure (PBS), 102, 116–117

procrastination (student syndrome), 296 Procter and Gamble, 27, 583 procurement management

components of, 452 Request for Proposal (RFP), 44, 45,

63–64, 452 product backlog, 588–589 product life cycle, compression of, 12, 27 product owner, 586–587 program(s)

defined, 7–8 project versus, 7

program evaluation and review technique (PERT), 140, 216, 240–244

program goals, 8 program management, 8 progress measurement. See project

monitoring information system project(s), 6–12

characteristics of, 7

performance indexes, 476 performance measurement. See project

monitoring information system performance reviews, 534–536

individual, 535–536 project manager, 534 team member, 532–534 360-degree reviews, 535, 536

performing stage of team development, 378 Perkins, Dennis N. T., 354, 354n perpetual closure, 517 Perrow, L. A., 328 personal integrity, 360 personal-related currencies, 347, 348 PERT (program evaluation and review

technique), 140, 216, 240–244 development of, 240 hypothetical example of, 242–244

Pesch, E., 291 Peters, J. F., 538 Peters, Lawrence H., 366, 389, 389n Peters, L. S., 56 Peters, T., 20, 353, 366, 409 Pethokoukis, J. M., 583n Pettegrew, A. M., 93 phase estimating, for project times and

costs, 141–143 Philippines, 547, 549, 553 physical characteristics, in organizational

culture, 84–85 Pich, M. T., 232 Pinto, J. K., 56, 102, 124, 129n, 130n, 154.

232, 301, 302, 351n3, 367, 444 Pippett, D. D., 538 Pitagorsky, G., 124 planned value (PV)

costs included in, 467–468 defined, 276, 466 in time-phased budgets, 276 variance analysis, 468–469

planning decisions, 384 planning horizon, in project

estimation, 130 planning stage, 8. See also project estima-

tion; resource scheduling of project life cycle, 8, 396 sources of conflict, 395–396

PMBOK (Project Management Body of Knowledge), 223n, 232

PM Network, 538 PMI. See Project Management

Institute (PMI) PMI Standards Committee, 124 PMI Today, 4n Poli, M., 94 Porras, J. I., 88, 92 portfolio management, 37–38

senior management input to, 48–49 portfolio risks, balancing, 50–51 Portland General Electric Company, 480

654 Index

understanding strategy, 28 work breakdown structure (WBS) and,

108–109 working in a multicultural environment,

555, 565–568 project measurement. See project monitor-

ing information system project meetings, 383–387

establishing ground rules, 384–385 project kick-off meeting, 383 scrum, 587–589 subsequent meetings, 386–387 team identity and, 387–388

project monitoring information system, 459–486

baseline changes, 483–484 costs and problems of data acquisition,

485–486 critical-chain project management

(CCPM) in, 300–301 data collected in, 460–461, 485 earned value (EV) cost/schedule

system, 462, 464–469, 505–511 examples of use, 464, 480 forecasting final project cost, 479–481 indexes to monitor progress, 475–479 Microsoft Project and, 478, 511–513 process overview, 467 project control process, 461–462 reports and reporting in, 460–461,

470–475 scope creep, 483 status report, 470–475, 478, 481 structure of, 460–461 time performance, 462–464

tracking Gantt, 462–463 project networks, 163–189

activities in, 163–164, 166–170 activity numbering, 179 activity-on-arrow (AOA), 167–170 activity-on-node (AON), 167–170

activity-on-arrow (AOA) versus, 167–168

backward pass, 173–175 forward pass, 171–173

backward pass-latest times in, 173–175 basic rules for developing, 166 calendar dates, 182 computers in developing, 179–182 concurrent engineering, 184–186 critical activities in, 176, 184 critical path method (CPM), 163, 166,

167, 171, 175–177, 178, 187, 317 development

basic rules, 166 computer use in, 179–182 from work breakdown structure

(WBS), 164–166 yellow sticky approach to, 167

extended network techniques, 182–188

Project Management Body of Knowledge (PMBOK), 223n, 232, 342, 594

project management career paths, 3–5 certification and training, 4 examples of, 4–5, 10–11 projects given to recent college

graduates, 5 Project Management Consultants, 431 Project Management Institute (PMI), 4, 6,

20, 35, 35n5, 367, 465, 480, 529, 532, 594

project management maturity, 529–532 project management office (PMO), 532 Project Management Professional (PMP),

4, 594 project management software

Microsoft Project, 385, 478, 511–513 Primavera, 385

project management structures, 68–81 dedicated teams, 71–72, 79, 88 functional organization, 68–70

advantages and disadvantages, 69–70 matrix arrangement, 75–81, 88–89 organization considerations, 79 project considerations, 79–81 relationship with organizational

culture, 88 project managers, 339–362. See also

leadership; project teams building trust, 357–359 career paths. See project management

career paths certification and training, 4 as client account executives, 441 conductor metaphor and, 344 dependencies of, 342–344 developing high-performance project

teams, 381–399 ethics and, 356 functional manager versus, 9 law of reciprocity and, 345–348 leading at the edge, 354 leading by example, 353–355 “management by wandering around”

(MBWA), 350–351 managing expectations, 351 managing upward relations, 351–353 motivating for extraordinary

performance, 320 nature of, 9–10 performance reviews, 534–536 professional training and certification, 4 project leadership versus, 340–341 project teams, 9, 11–12, 342 qualities of effective, 359–362 role of, 9–10 scrum masters as, 587 skill set, 5 social network building, 348–355 stakeholders and, 341–344

project estimation, 129–151. See also cost estimates; resource estimates; time estimates

accuracy, 142 adjusting estimates of specific tasks,

146–148 error reduction, 134 factors influencing quality estimates,

130–132 guidelines for times, costs, and

resources, 132–133 importance of, 130 learning curves in, 139, 157–161 level of detail, 143–144 mega projects, 149–150, 152 refining estimates, 146–148 time and cost databases, 148 top-down versus bottom-up, 134–143 types of costs, 144–146

project evaluation, 532–536 in closing stage, 532–534 statement of criteria,

project facilitators, 515, 525–529 roles, 525–529 selecting, 525–526

project governance, 15–16 alignment of projects and

organizational strategy, 16 governance team in portfolio system,

49–50 nature of, 15–16

projectitis, 74 projectized organization, 72–73, 79 project kick-off meeting, 383 project life cycle, 8–9

defined, 8 project cycle times, 8 sources of conflict over, 395–396 stages of, 8–9. See also closing stage;

defining stage; executing stage; planning stage

project management. See also project teams

critical-chain project management (CCPM) and, 301

current drivers of, 12–15 current examples of, 5, 13–14 impact of, 4 importance of, 3–5 integration of, 15–16 leadership versus, 339–341 new-school thinking of, 28 old-fashioned view of, 344 old-school thinking if, 28 project size and, 15, 144, 147 socio-technical approach to, 17–18 sustainable practices and, 12–14

Dell Children’s Medical Center, 14 London Olympics (2012), 150 Studio Roosegaarde, 13

Index 655

rejuvenating, 398–399 reward systems, 391–392 shared vision, 388–391, 396 situational factors in team development,

379, 381 team identity, 386–387 virtual project teams, 399–403

project vision, 388–391, 396 proposals

contractor selection from, 64 ranking, 46–48 Request for Proposal (RFP), 44, 45, 452 sources of, 44, 45

prototypes, in outsourcing, 428 pseudo-earned value percent complete

approach, 485 public documents, in organizational

culture, 85 public recognition, 392 Public Utilities Commission, 480 punctuality, 555, 560 punctuated equilibrium, 380

Q Quality

options for accelerating projects, 311–312

in project estimation, 130–132 total quality management (TQM), 38

Quintella, Hermida, 56 Quinn, R. E., 92, 444

R Raja, V. T., 367n Randall, Doug, 57 RAND Corporation, 136 range estimating, for project times and

costs, 140–141 Raskin, P., 57 ratio methods, for estimating project times

and costs, 137 Raz, T., 125, 301, 302 Rea, K. P., 408 Rebello, K., 93 recruitment process, 381–382

considerations in, 382 international projects, 568–570 in matrix management, 381–382

Red Cross, 526 Rees, Kevin, 434 reference class forecasting (RCF), 151 refining estimates, 146–148 Reinertsen, D. G., 88, 94, 220, 232, 291,

328, 391, 409 Reinman, R., 232 relationship nature, 557 relationship-related currencies, 346, 347 release burndown charts, 590

deadlines, 307 development of earned value cost/

schedule system, 464–469, 505–511 early times and late times, 166 project networks and, 164 schedule variance (SV), 466, 468–469 slippage in, 272 time buffers, 225

project scope, 102–106 changes in, 147, 311, 322 checklist, 103–105 reducing, 311, 322 scope creep, 106, 483 scope statement, 11–12, 17, 19,

105–106 project screening

financial selection models, 38–40 multi-criteria selection models, 40–43 nonfinancial criteria, 40–43 overview of project screening

process, 47 project screening matrix, 42–43 project screening matrix, 42–43 project selection, 38–48

financial criteria, 38–40 in international projects, 568–570 multi-criteria selection models, 40–43 nonfinancial criteria, 40–43 prioritizing proposals, 28, 41, 47 project classification, 43 ranking proposals, 46–47 selecting a model, 44 solicitation of project proposals, 44–45 sources of project proposals, 44–45

project site selection, 549, 553–554 project-specific risk. See risk management

process project sponsor, 35

dependencies of, 343 managing upward relations, 352

project structure organizational culture and, 88 in project estimation, 131

project teams, 11, 375–405 building high-performance, 381–399 conflict management, 394–398 decision-making process, 393–394 dedicated. See dedicated project team dependencies of, 342–344 five-stage team development model,

377–379 importance of teamwork, 17 improving the efficiency of, 310–311 international project, 558, 568 low-priority project, 395 meetings, 383–387 pitfalls, 403–405 project synergy, 375–377 punctuated equilibrium, 380 recruitment process, 381–382

forward pass-earliest times in, 171–173 hammock activities, 188 laddering, 182, 183 lags, 182–187

in forward and backward pass procedures, 186–187

to reduce schedule detail, 182–184 level of detail for activities, 178 multiple starts/multiple projects, 182 nature of, 163–164 network computation process, 171–177

backward pass-latest times, 173–175 forward pass-earliest times, 171–173

network logic errors, 178 practical considerations, 178–182 project schedules and, 164 sensitivity, 176–177, 320–321 slack/float in, 175–177

free, 177 total, 175–177

terminology, 166 project offices (POs), 80, 523

benefits of, 523 defined, 80 project audits and, 522, 523 services provided by, 523 types of, 80

projected organization, 72 project plans. See project networks project portfolio management system,

34–51 benefits of, 37 classification of project, 37–38, 50 implementation gap, 34–35, 36–37 managing the system, 48–51 organization politics, 35–36 priority system in, 36–37, 47, 48, 50 project portfolio in, 34 project selection, 35–48 resource conflicts and multitasking,

36–37 project priority system, 34–37. See also

priorities implementation gap, 34–35 organizational politics, 35–36 resource conflicts and multitasking,

36–37 project process review questionnaire, 528 project proposals. See proposals project queue systems, 272 project reward systems, 391–392 project rollup, 466, 474–475 project schedules. See also time estimates

acceleration options, 307–312 constrained resources, 310–312 unconstrained resources, 308–310

in critical-chain project management (CCPM), 297–298. See also critical-chain project management (CCPM)

656 Index

risk response control, 225–226 change control management, 226–229 risk register, 225–226

risk response development, 216–219 avoiding risk, 217 contingency funding, 223–225 contingency planning, 219 mitigating risk, 216–217 opportunity management, 223 retaining risk, 218 time buffers, 225 transferring risk, 217–218

risk response matrix, 220 risk retention, 218 risk severity matrix, 214 risk transfer, 217–218 Ritti, R. R., 392, 392n, 409 River of Doubt (Millard), 552 Rizova, Polly S., 89, 89n, 94 Robb, D. J., 367 Rodriguez, P., 572 Roemer, T. R., 328 Rogers, Will, 207 Romanoff, T. K., 535, 538 Rondon, Candido Mariano da Silva, 552 Roosevelt, Theodore “Teddy,” 552 Rosen, B., 408 Rosenblatt, A., 202 Ross, Jerry, 539 Ross, M., 147, 154 Rothaermel, F. T., 443 Rothengatter, W., 149, 154 Rourke, D. L., 154 Rousculp, M. D., 232 Royer, I., 538 Rubinstein, J., 269, 291 Ruekert, R. W., 93 Russia, legal/political factors, 547 Ryan, Frank, 135n

S “sacred cow,” 35, 42, 44 Saffo, P., 408 Salehipour, A., 501 Samsung, 306 Samsung Galaxy 7, 306 Sankaran, S., 366 Santayana, George, 515 Sashittal, H. C., 93 Saudi Arabia, cross-cultural factors in,

560–561 Saunders, C., 573 Sayles, Leonard R., 351n2, 352n, 360, 367 scaling, 592–593 scenario analysis, 213–214 schedule. See project schedules schedule performance index (SPI), 476 schedule risks. See also resource scheduling

in contingency planning, 222

time-phased budget baseline, 251, 273–278

types of resource constraints, 254–255 resource smoothing, 252, 256–257 responsibilities

client assumption of, 322 governance team, 49 in project estimation, 132 in risk response control, 226 top management, 47

responsibility matrix (RM), 117–119 retaining risk, 218 retrospectives in closing stage, 525–529.

See also project audits archiving, 529 independent facilitators, 525 lessons learned, 526, 527 methodology, 526–529

reviews, in outsourcing, 431–432 reward systems, 391–392. See also

incentives; project reward systems RFP (Request for Proposal), 44, 45, 63–64,

424–426, 452 Ricks, D. A., 573 RIM, 306 risk

avoiding, 217 defined, 207 retaining, 218 sources of project, 209 transferring, 217–218

risk assessment, 210, 212–216 Failure Mode and Effects Analysis

(FMEA), 215 probability analysis, 215–216 in project estimation, 133 risk severity matrix, 214 scenario analysis, 213–214

risk avoidance, 217 risk breakdown structure (RBS), 210–211 risk event graph, 209 risk identification, 210–212 risk management process, 208–230

balancing portfolio risks, 50–51 components of, 209–210 cost of mismanaged risk, 207–209 examples of, 207–209, 218, 221 international projects and, 548 proactive approach, 209 process overview, 210 risk, defined, 207 risk assessment, 210, 212–216 risk identification, 210–212 risk response control, 210, 225–226 risk response development, 210,

216–219 sources of project risk, 209

risk mitigation, 216–217 risk profile, 211 risk register, 225–226

release planning, 587 religious factors, 551 Relyea, Dave, 585 Remington, K., 56 reports and reporting

change request forms and logs, 227–229

errors, 226 final project report, 516–518 in outsourcing, 428 project monitoring information system,

460–461, 470–475 by project offices (POs), 523 status report, 470–475, 478, 481

Request for Proposal (RFP), 44, 45, 63–64, 424–426, 452

reserves, 224–225 budget, 224 management, 224–225

resource bottlenecks, 272, 296 resource buffers, 296 resource conflicts, 36–37 resource-constrained projects, 252–253,

255, 257–269 computer demonstration, 262–269 EMR project example, 262–269 examples of, 254 impacts of, 266 nature of, 255, 257–258 parallel method of applying heuristics,

258, 259 resource allocation methods, 255–262 resource conflicts and multitasking,

36–37 resource estimates, 130–148

factors influencing quality of, 130–132

guidelines for, 132–133 level of detail, 143–144 phase estimating, 141–143 refining, 146–148 top-down versus bottom-up, 134–143

resource pool project office, 80 resource scheduling, 250–279

assessing resource allocation, 262 assigning project work, 271 benefits of, 270 critical-chain project management

(CCPM), 294–303 to develop project cost baseline, 251,

273–278 multiproject resource schedules,

272–273 process overview, 252–254 resource-constrained projects, 252–253,

255, 257–269 resource smoothing in, 252, 256–257 splitting activities, 269 time-constrained projects, 255,

256–257

Index 657

critical-chain project management (CCPM) and, 300

in resource scheduling, 269 sports and recreation, 150, 376, 520 sprint backlogs, 589 sprint burndown charts, 589 sprint planning, 587–588 sprint retrospective, 588 sprint review, 588 Squires, Susan E., 357, 357n Srivannaboon, S., 56 stakeholders, 341–344

defined, 342 dependencies of, 342–343 stakeholder analysis in project

communication plan, 119–120 types of, 342–343

standards of performance in leading by example, 355

Standish Group, 20, 102, 125 start-to-finish lag relationship, 186 start-to-start lag relationship, 183–184 Star Wars (film), 549 statement of work (SOW), 105, 424 status report, 470–475

assumptions, 470 baseline development, 470–471 development of, 471–475 example of monthly, 481

status updates, in outsourcing, 431–432 Staw, Berry M., 539 Sten, Erik, 135 Stern, David (NBA), 376, 520 Stewart, T. A., 20 Steyn, H., 302 Stonehill, I., 573 storming stage of team development, 378 strategic management process, 29–51

analyze and formulate strategies, 32 defined, 29 dimensions of, 28 implementing strategies through

projects, 33–34 objectives support strategy, 33 process overview, 29 project portfolio management system,

34–38 project selection, 38–48 review and define organizational

mission, 31 strategic projects, 37–38 strategy

defined, 27 understanding, 28

stress-related culture shock, 566–567 Strickland, A. J., 104n Strodtbeck, F. L., 557, 557n, 573 Strohl Systems Group, 548 strong matrix, 77–78, 81 Stubbs, David, 150

Shell, G. R., 444 Shenhar, Aaron J., 28, 57, 80n, 94, 360, 367 Sheperd, D. A., 538 Sherif, M., 379n, 409 Shirley, Donna, 383, 383n Shtub, A., 367 Sibbett, D., 408 Siebdrat, F., 409 Siemens Medical Systems, 594 Sieminski, G. C., 49n, 57 Singer, Carl A., 400, 400n Sirisomboonsuk, Pinyarat, 616n Shawshank Redemption, The (movie), 398 Skelton, T., 232 Skilton, P. F., 382, 409 Skunk Works, 72. See also dedicated

project teams situational factors in team development,

379–381 slack, 175–177

free, 177 total, 175–177

Sleeping Dictionary, The (film), 404n Slevin, D. P., 102, 124, 367 slippage, 272 Sloan, John, 372n small projects, 15 smartphone industry, 306 Smith, B. J., 390, 409 Smith, Cynthia J., 357n Smith, D., 155, 302 Smith, D. K., 35n6, 57, 385n, 408 Smith, M., 93 Smith, P. G., 88, 94, 220, 232, 328, 391, 409 Snapple Company, 208 Snizek, J. A., 210, 232 Snyder, D., 154 social network building, 348–355

leading by example, 353–355 “management by wandering around”

(MBWA), 350–351 managing upward relations, 351–353 mapping dependencies, 348–349 social network, defined, 348

social skills, 361 Sochi Winter Olympics, 106 Software Engineering Institute (SEI),

529, 531 Somalia, 547 South Africa 2010 World Cup, 149 socio-technical approach to project

management, 17–18 Sojourner (Martian rover), 383 Sony, 15 Sood, S., 302 Soul of a New Machine, The (Kidder),

389, 389n Spalding, 520 Spirit Aero Systems, 297 splitting activities,

schedule variance (SV) computing, 466 defined, 466 variance analysis, 468–469

Schein, E., 82n, 94, 377n Schilling, D. L., 444 Schkade, J., 379n, 409 Schmidt, Eric, 271 Schuler, J. R., 232 Schultzel, H. J., 444 Schur, M., 594, 598 Schwaber, K., 579, 598 Schwalbe, K., 457 Schwartz, Peter, 57 scope creep, 106, 483 scope statement, 11–12, 17, 19, 105–106 Scown, M. J., 547, 573 scrum, 585–592

features, 585–586 meetings, 587–588 origins, of, 585 process overview, 586 product and sprint backlogs, 588–589 roles and responsibilities, 586–587 sprint and release burndown charts,

589–592 scrum master, 587 scrum meeting, 587–588 Sculley, John, 74, 74n, 94 Sears Roebuck, 138 Seattle Kingdome, 218 Secret of Success, The (Rizova), 89 Securities and Exchange Commission

(SEC), 357 security factors, 547–548 Segalla, M., 572 selection. See project selection self-awareness, 361 self-motivation, 361 self-organizing teams, 587 self-protection, 295 self-regulation, 361 Senge, P. M., 360, 360n8, 367, 389n5,

409, 538 senior management. See top management sensitivity, of project network, 176–177,

320–321 September 11, 2001 terrorist attacks, 547, 587 Seta, J. J., 379n, 409 Seven Habits of Highly Effective People

(Covey), 358, 360n Shackleton, Ernest, 354 Shadrokh, S., 501 Shanahan, S., 258, 291 Shao, J., 366 shared vision, 388–391, 396 Shaw, L., 13n Sheen, Martin, 549 Shelby County Habitat for Humanity

( Alabama), 312

658 Index

tracking decisions, 384 tracking Gantt charts, 462–463, 473–474 training

certification and, 4 in outsourcing, 428 in international projects, 568–570

transferring risk, 217–218 transportation services, 135, 308 Trevino, L. K., 356n7, 367 triple bottom line, 11–12 Trojan Nuclear Plant decommission, 480 trust

leadership and, 357–359 in negotiations for outsourcing, 433 virtual project teams and, 401–402

Tuchman, B. W., 377, 409 Tuller, L. W., 559n Tung, R. L., 562n, 567, 573 Turne, J. R., 38, 55, 366 Turner, J. R., 360, 367 Turner, R., 366 Turtle, Q. C., 186, 202 20th Century–Fox, 320 2008 Olympic Redeem Team, 376

U “Ugly American,” 554 U.S Green Building Council, 14 U.S. Air Force, 301 U.S. Army, 222 U.S. Department of Agriculture, 270 U.S. Department of Defense, 3, 222, 433,

434, 464 U.S. Department of Defense’s Value

Engineering Awards, 434 U.S. Federal housing Authority (FHA), 137 U.S. Food and Drug Administration

(FDA), 343 U.S. Forest Service, 270, 485 U.S. Navy, 301, 424 U.S. West, 405 Uhlenbruck, K., 572 Ulrich, F. C., 232 United States Golf Association

(USGA), 104 United States, cross-cultural factors in,

563–564 Unruh, V. P., 444 urgency, in leading by example, 355 Ury, W., 435, 435n, 438, 439, 443 Uzbekistan, 548

V Value Engineering Awards (U.S.

Department of Defense), 434 Van de Ven, Andrew H., 405n Van Slyke, C., 573 Vanderjack, B., 598

scheduling interval in applying heuristics, 258–262

smoothing resource demand, 252, 256–257

time estimates, 130–148. See also project schedules

apportion methods, 137 consensus methods, 136 in critical-chain project management

(CCPM), 295 factors influencing quality of, 130–132 function point methods, 138–139 guidelines for, 132–133 learning curves, 139, 157–161 level of detail, 143–144 parametric procedures, 140 phase estimating, 141–143 range estimating, 140 ratio methods, 137 refining, 146–148 template methods, 140 time and cost databases, 148 top-down versus bottom-up, 134–143

Time Inc., 595 580, time management, 361 time performance, in project monitoring

information, 462–464 time-phased budget baselines, 251,

273–278 creating, 274–276 need for, 276–278

To Complete Performance Index (TCPI), 480

top-down estimates, 134–144 apportion methods, 137 consensus methods, 136 “function points,” 138–139 learning curves, 139, 157–161 nature of, 134 ratio methods, 137

top management. See also middle management

dependencies of, 343 ethics and, 356 functional organization and, 68–69 implementation gap in project portfolio

system, 34–35, 36–37 level of detail in project estimates,

143–144 managing upward relations, 351–353 in portfolio system, 48–49 in project audits, 522 in project portfolio management, 48–49 responsibility for prioritizing

projects, 47 time orientation, 557

Torti, M. T., 441, 441n Total quality management (TQM), 38, 347 total slack/float, 175–177 Toyota, 27, 420, 433

Stuckenbruck, L. C., 94 student syndrome (procrastination), 296 Studio Roosegaarde, 13 Sullivan, Stacy Savides, 84 Sun Microsystems, 271 Swahl, W., 124 Swanson, S., 57, 134n Sweden, 548 SWOT (strengths, weaknesses, opportunities,

and threats) analysis, 32 Symons, C. R., 155 synergy, 375–377 systems thinking, 360

T Takeuchi, Hirotaka, 585, 598 Talbot, B. F., 258, 291 Tanzania, 550 Tarne, R., 590, 598 task-related currencies, 345–346 Tate, K., 125 team building, 381–399

five-stage team development model, 377–379

in outsourcing, 428–429 punctuated equilibrium, 380 recruiting project members, 381–382 rejuvenating the project team, 398–399 team-building techniques in, 399

team charter, 385 team evaluation, 532–534 team identity, 381, 387–388, 395 team rituals, 387–388 team spirit, 404 technical performance measurement, 481 technical requirements, in project

scope, 103 technical risks, in contingency planning,

220–221 technological expertise

outsourcing and, 421 in recruiting project members, 382

template methods, for estimating project times and costs, 140

terrorist attacks of 2001, 547, 587 Tesluk, P. E., 408 Tektronics, 464 Thamhain, H., 221, 226, 232, 395, 409 Thompson, A. A., 104n Thompson, G. L., 202 Thompson, Hine & Flory, 431 Thompson, M. P., 444 Thoms, P., 409 360-degree review, 534, 535, 536 3M, 40, 87, 301, 402, 402n, 409, 583 time and cost databases, 148 time buffers, 225 time-constrained projects, 255, 256–257

nature of, 255

Index 659

groupings found in, 108–109 in helping project manager, 108 integrating with organization,

113, 114 level of detail in, 143–144 process overview, 110 simplified WBS development, 109–112 time-phased budget and, 273–278

work package, 111 World Cup (2010), 149 World Trade Center terrorist attacks

(2001), 585 Worldcom, 356 Worthen B., 42n, 598 Worthington, M. M., 457 wrap-up closure activities, 516, 518–521

closedown activities, 518 partial administrative closure

checklist, 519

X Xerox, 35–36, 86 Yates, J. K., 539 Yazici, H., 81n, 94 Yeak, William R., 357n Yeung, I., 562n, 573 Yin, M., 328 Yovocich, B. G., 568n Youker, R., 94 Young, Bruce, 320 Young, J., 93

Z Zaitz, Les, 539 Zalmanson, E., 301, 302 Zander, A., 379n, 409 Zaphiropoulos, Renn (Versatec), 86 Zenisek, Joseph, 297 z values, PERT, 242–244 Zwikael, Ofer, 20 Zyliss, 583

Watson, G., 202 Watson’s Jeopardy Project (IBM), 13, 29, 30 WBS dictionary, 115 WBS. See work breakdown structure (WBS) weak matrix, 76–78, 81 weather station project office, 80 Webb, A. P., 365, 501 Webber, S. S., 441, 441n Weiler, Ed, 209 Wells, W. G., 501 Welsh, M. A., 366 West, J. D., 202 West, Tom, 389, 389n Wexley, K. N., 535, 538 Wheatly, M., 539 Wheelwright, S. C., 92, 407 white elephants, 50, 149 Whitten, Danny, 320 Whybark, D. Clay, 334n Wiest, J. D., 291 Wilemon, D. L., 395, 409 Willie, C. J., 252, 291 Willis, Kerry, 134 Wilson, Pete, 308 Windows 10, 452 Windows 11, 213–214 Wisneiski, Mary, 431n Wolfe, M., 538 Wolff, Alexander, 376n Woodward, H., 57 Woodworth, B. M., 252, 258, 291 Woolridge, B., 55 work assignment

as incentive, 391–392 in resource scheduling, 271

work breakdown structure (WBS), 102, 108–117

baseline development in project monitoring information system, 461, 470, 474, 483–484

coding for information systems, 113–115 creating, 112 development of project network from,

164–166

variance analysis actual cost (AC), 466 cost variance (CV), 466 earned value (EV), 466 methods of, 468–469 planned value (PV), 466 schedule variance (SV), 466, 468–469

variance at completion (VAC) defined, 466, 468 variance analysis, 468–469

Varkonyi, Greg, 376n Vecta, 583 Versatec, 86 Veryzer, R. W., 56 Verzuh, E., 328 videoconferencing, virtual project teams

and, 402 virtual project teams, 399–403

communication patterns and, 402 in global environment, 399–400 outsourcing and, 421 trust and, 401–402

virtual reality technology, 13 vision, 388–391, 396 Vogel, D. R., 573 Vroom, V. H., 320n, 328, 393, 409

W Wake, William, 585 Walker, C. F., 232 Walker, D., 366 Walker, O. C., Jr., 93 Walmart, 8 Walt Disney World, 391 Walters, H., 84n Wang, Q., 93 Wang, R., 328 Warner Brothers, 320 Warner-Lambert, 535 Washington Wizards, 520 waterfall method, 116, 116n, 580–581, 584,

595. See also process breakdown structure (PBS)

  • Cover
  • Title Page
  • Copyright Page
  • About the Authors
  • Dedication
  • Preface
  • Acknowledgments
  • Brief Contents
  • Contents
  • Chapter 1 Modern Project Management
    • 1.1 What Is a Project?
      • What a Project Is Not
      • Program versus Project
      • The Project Life Cycle
      • The Project Manager
      • Being Part of a Project Team
    • 1.2 Current Drivers of Project Management
      • Compression of the Product Life Cycle
      • Knowledge Explosion
      • Triple Bottom Line (Planet, People, Profit)
      • Increased Customer Focus
      • Small Projects Represent Big Problems
    • 1.3 Project Governance
      • Alignment of Projects with Organizational Strategy
    • 1.4 Project Management Today: A Socio-Technical Approach
    • Summary
  • Chapter 2 Organization Strategy and Project Selection
    • 2.1 The Strategic Management Process: An Overview
      • Four Activities of the Strategic Management Process
    • 2.2 The Need for a Project Priority System
      • Problem 1: The Implementation Gap
      • Problem 2: Organization Politics
      • Problem 3: Resource Conflicts and Multitasking
    • 2.3 A Portfolio Management System
      • Classification of the Project
    • 2.4 Selection Criteria
      • Financial Criteria
      • Nonfinancial Criteria
    • 2.5 Applying a Selection Model
      • Project Classification
      • Sources and Solicitation of Project Proposals
      • Ranking Proposals and Selection of Projects
    • 2.6 Managing the Portfolio System
      • Senior Management Input
      • The Governance Team Responsibilities
      • Balancing the Portfolio for Risks and Types of Projects
    • Summary
  • Chapter 3 Organization: Structure and Culture
    • 3.1 Project Management Structures
      • Organizing Projects within the Functional Organization
      • Organizing Projects as Dedicated Teams
      • Organizing Projects within a Matrix Arrangement
      • Different Matrix Forms
    • 3.2 What Is the Right Project Management Structure?
      • Organization Considerations
      • Project Considerations
    • 3.3 Organizational Culture
      • What Is Organizational Culture?
      • Identifying Cultural Characteristics
    • 3.4 Implications of Organizational Culture for Organizing Projects
    • Summary
  • Chapter 4 Defining the Project
    • 4.1 Step 1: Defining the Project Scope
      • Employing a Project Scope Checklist
    • 4.2 Step 2: Establishing Project Priorities
    • 4.3 Step 3: Creating the Work Breakdown Structure
      • Major Groupings Found in a WBS
      • How WBS Helps the Project Manager
      • A Simple WBS Development
    • 4.4 Step 4: Integrating the WBS with the Organization
    • 4.5 Step 5: Coding the WBS for the Information System
    • 4.6 Process Breakdown Structure
    • 4.7 Responsibility Matrices
    • 4.8 Project Communication Plan
    • Summary
  • Chapter 5 Estimating Project Times and Costs
    • 5.1 Factors Influencing the Quality of Estimates
      • Planning Horizon
      • Project Complexity
      • People
      • Project Structure and Organization
      • Padding Estimates
      • Organization Culture
      • Other Factors
    • 5.2 Estimating Guidelines for Times, Costs, and Resources
    • 5.3 Top-Down versus Bottom-Up Estimating
    • 5.4 Methods for Estimating Project Times and Costs
      • Top-Down Approaches for Estimating Project Times and Costs
      • Bottom-Up Approaches for Estimating Project Times and Costs
      • A Hybrid: Phase Estimating
    • 5.5 Level of Detail
    • 5.6 Types of Costs
      • Direct Costs
      • Direct Project Overhead Costs
      • General and Administrative (G&A) Overhead Costs
    • 5.7 Refining Estimates
    • 5.8 Creating a Database for Estimating
    • 5.9 Mega Projects: A Special Case
    • Summary
    • Appendix 5.1: Learning Curves for Estimating
  • Chapter 6 Developing a Project Plan
    • 6.1 Developing the Project Network
    • 6.2 From Work Package to Network
    • 6.3 Constructing a Project Network
      • Terminology
      • Basic Rules to Follow in Developing Project Networks
    • 6.4 Activity-on-Node (AON) Fundamentals
    • 6.5 Network Computation Process
      • Forward Pass-Earliest Times
      • Backward Pass-Latest Times
      • Determining Slack (or Float)
    • 6.6 Using the Forward and Backward Pass Information
    • 6.7 Level of Detail for Activities
    • 6.8 Practical Considerations
      • Network Logic Errors
      • Activity Numbering
      • Use of Computers to Develop Networks
      • Calendar Dates
      • Multiple Starts and Multiple Projects
    • 6.9 Extended Network Techniques to Come Closer to Reality
      • Laddering
      • Use of Lags to Reduce Schedule Detail and Project Duration
      • An Example Using Lag Relationships-The Forward and Backward Pass
      • Hammock Activities
    • Summary
  • Chapter 7 Managing Risk
    • 7.1 Risk Management Process
    • 7.2 Step 1: Risk Identification
    • 7.3 Step 2: Risk Assessment
      • Probability Analysis
    • 7.4 Step 3: Risk Response Development
      • Mitigating Risk
      • Avoiding Risk
      • Transferring Risk
      • Accept Risk
    • 7.5 Contingency Planning
      • Technical Risks
      • Schedule Risks
      • Cost Risks
      • Funding Risks
    • 7.6 Opportunity Management
    • 7.7 Contingency Funding and Time Buffers
      • Budget Reserves
      • Management Reserves
      • Time Buffers
    • 7.8 Step 4: Risk Response Control
    • 7.9 Change Control Management
    • Summary
    • Appendix 7.1: PERT and PERT Simulation
  • Chapter 8 Scheduling Resources and Costs
    • 8.1 Overview of the Resource Scheduling Problem
    • 8.2 Types of Resource Constraints
    • 8.3 Classification of a Scheduling Problem
    • 8.4 Resource Allocation Methods
      • Assumptions
      • Time-Constrained Project: Smoothing Resource Demand
      • Resource-Constrained Projects
    • 8.5 Computer Demonstration of Resource-Constrained Scheduling
      • The Impacts of Resource-Constrained Scheduling
    • 8.6 Splitting Activities
    • 8.7 Benefits of Scheduling Resources
    • 8.8 Assigning Project Work
    • 8.9 Multiproject Resource Schedules
    • 8.10 Using the Resource Schedule to Develop a Project Cost Baseline
      • Why a Time-Phased Budget Baseline Is Needed
      • Creating a Time-Phased Budget
    • Summary
    • Appendix 8.1: The Critical-Chain Approach
  • Chapter 9 Reducing Project Duration
    • 9.1 Rationale for Reducing Project Duration
    • 9.2 Options for Accelerating Project Completion
      • Options When Resources Are Not Constrained
      • Options When Resources Are Constrained
    • 9.3 Project Cost-Duration Graph
      • Explanation of Project Costs
    • 9.4 Constructing a Project Cost-Duration Graph
      • Determining the Activities to Shorten
      • A Simplified Example
    • 9.5 Practical Considerations
      • Using the Project Cost-Duration Graph
      • Crash Times
      • Linearity Assumption
      • Choice of Activities to Crash Revisited
      • Time Reduction Decisions and Sensitivity
    • ?9.6 What If Cost, Not Time, Is the Issue?
      • Reduce Project Scope
      • Have Owner Take on More Responsibility
      • Outsourcing Project Activities or Even the Entire Project
      • Brainstorming Cost Savings Options
    • Summary
  • Chapter 10 Being an Effective Project Manager
    • 10.1 Managing versus Leading a Project
    • 10.2 Managing Project Stakeholders
    • 10.3 Influence as Exchange
      • Task-Related Currencies
      • Position-Related Currencies
      • Inspiration-Related Currencies
      • Relationship-Related Currencies
      • Personal-Related Currencies
    • 10.4 Social Network Building
      • Mapping Stakeholder Dependencies
      • Management by Wandering Around (MBWA)
      • Managing Upward Relations
      • Leading by Example
    • 10.5 Ethics and Project Management
    • 10.6 Building Trust: The Key to Exercising Influence
    • 10.7 Qualities of an Effective Project Manager
    • Summary
  • Chapter 11 Managing Project Teams
    • 11.1 The Five-Stage Team Development Model
    • 11.2 Situational Factors Affecting Team Development
    • 11.3 Building High-Performance Project Teams
      • Recruiting Project Members
      • Conducting Project Meetings
      • Establishing Team Norms
      • Establishing a Team Identity
      • Creating a Shared Vision
      • Managing Project Reward Systems
      • Orchestrating the Decision-Making Process
      • Managing Conflict within the Project
      • Rejuvenating the Project Team
    • 11.4 Managing Virtual Project Teams
    • 11.5 Project Team Pitfalls
      • Groupthink
      • Bureaucratic Bypass Syndrome
      • Team Spirit Becomes Team Infatuation
      • Going Native
    • Summary
  • Chapter 12 Outsourcing: Managing Interorganizational Relations
    • 12.1 Outsourcing Project Work
    • 12.2 Request for Proposal (RFP)
      • Selection of Contractor from Bid Proposals
    • 12.3 Best Practices in Outsourcing Project Work
      • Well-Defined Requirements and Procedures
      • Extensive Training and Team-Building Activities
      • Well-Established Conflict Management Processes in Place
      • Frequent Review and Status Updates
      • Co-Location When Needed
      • Fair and Incentive-Laden Contracts
      • Long-Term Outsourcing Relationships
    • 12.4 The Art of Negotiating
      • 1. Separate the People from the Problem
      • 2. Focus on Interests, Not Positions
      • 3. Invent Options for Mutual Gain
      • 4. When Possible, Use Objective Criteria
      • Dealing with Unreasonable People
    • 12.5 A Note on Managing Customer Relations
    • Summary
    • Appendix 12.1: Contract Management
  • Chapter 13 Progress and Performance Measurement and Evaluation
    • 13.1 Structure of a Project Monitoring Information System
      • What Data Are Collected?
      • Collecting Data and Analysis
      • Reports and Reporting
    • 13.2 The Project Control Process
      • Step 1: Setting a Baseline Plan
      • Step 2: Measuring Progress and Performance
      • Step 3: Comparing Plan against Actual
      • Step 4: Taking Action
    • 13.3 Monitoring Time Performance
      • Tracking Gantt Chart
      • Control Chart
      • Milestone Schedules
    • 13.4 Development of an Earned Value Cost/Schedule System
      • Percent Complete Rule
      • What Costs Are Included in Baselines?
      • Methods of Variance Analysis
    • 13.5 Developing a Status Report: A Hypothetical Example
      • Assumptions
      • Baseline Development
      • Development of the Status Report
    • 13.6 Indexes to Monitor Progress
      • Performance Indexes
      • Project Percent Complete Indexes
      • Software for Project Cost/Schedule Systems
      • Additional Earned Value Rules
    • 13.7 Forecasting Final Project Cost
    • 13.8 Other Control Issues
      • Technical Performance Measurement
      • Scope Creep
      • Baseline Changes
      • The Costs and Problems of Data Acquisition
    • Summary
    • Appendix 13.1: The Application of Additional Earned Value Rules
    • Appendix 13.2: Obtaining Project Performance Information from MS Project 2010 or 2015
  • Chapter 14 Project Closure
    • 14.1 Types of Project Closure
    • 14.2 Wrap-up Closure Activities
    • 14.3 Project Audits
      • The Project Audit Process
      • Project Retrospectives
      • Project Audits: The Bigger Picture
    • 14.4 Post-Implementation Evaluation
      • Team Evaluation
      • Individual, Team Member, and Project Manager Performance Reviews
    • Summary
    • Appendix 14.1: Project Closeout Checklist
    • Appendix 14.2: Euro Conversion-Project Closure Checklist
  • Chapter 15 International Projects
    • 15.1 Environmental Factors
      • Legal/Political
      • Security
      • Geography
      • Economic
      • Infrastructure
      • Culture
    • 15.2 Project Site Selection
    • 15.3 Cross-Cultural Considerations: A Closer Look
      • Adjustments
      • Working in Mexico
      • Working in France
      • Working in Saudi Arabia
      • Working in China
      • Working in the United States
      • Summary Comments about Working in Different Cultures
      • Culture Shock
      • Coping with Culture Shock
    • 15.4 Selection and Training for International Projects
    • Summary
  • Chapter 16 An Introduction to Agile Project Management
    • 16.1 Traditional versus Agile Methods
    • 16.2 Agile PM
    • 16.3 Agile PM in Action: Scrum
      • Roles and Responsibilities
      • Scrum Meetings
      • Product and Sprint Backlogs
      • Sprint and Release Burndown Charts
    • 16.4 Applying Agile PM to Large Projects
    • 16.5 Limitations and Concerns
    • Summary
  • Appendix One: Solutions to Selected Exercise
  • Appendix Two: Computer Pro-ject Exercises
  • Glossary
  • Acronyms
  • Project Management Equations
  • Cross Reference of Project Management
  • Socio-Technical Approach to Project Management
  • Index