UOP OPS 571 Week 4 Quiz
• 1
Which of the following would be the result of subdividing a project?
•
Work events
•
Tasks
•
Job categories
•
Job orders
Correct
• 2
A Responsibility Chart specifically identifies which of the following?
•
Customer satisfaction
•
Planning the tasks for a project
•
Commitment to quality
•
Level of inventory
Correct
• 3
A work breakdown structure is
•
a Cost and Performance tracking schedule
•
a hierarchy of tasks, subtasks, and work packages
•
a structure that is incompatible with the Critical Path Method
•
a simple list of the activities making up a project
Correct
• 4
The vertical axis on a Gantt chart is usually which of the following?
•
Cost
•
Time
•
Profit
•
Activities
Correct
• 5
Which of the following identifies a key principle of Reengineering?
•
Merge information-processing work into the real work that produces the information.
•
Downsize (lay-off) workers and do the same amount of work as before.
•
Organize around tasks.
•
Capture information both at the source and where it is interpreted.
Correct
• 6
Which project progress technique includes the essential features of a project plan, budgeted cost of work scheduled and budgeted cost of work performed?
•
Critical path method
•
Gantt chart
•
Cost analysis
•
Earned value management
Correct
• 7
An example of a graphic project report utilized within project management is:
•
Equipment and supplies chart
•
Humphrey chart
•
Project proposal
•
Cost and performance tracking schedule
Correct
• 8
Consulting firms typically use which of the following techniques to plan and monitor the engagements of the firm or specific projects?
•
Quantitative layout
•
Qualitative forecasting
•
CPM/PERT
•
Materials requirements planning (MRP)
Correct
• 9
At the onset, a project originates as which of the following?
•
A series of milestones
•
A statement of work (SOW
•
A Gantt chart
•
Critical path method (CPM)