Using the information provided in the Gantt chart below, construct the project activity network using the activity-on-node (AON) methodology, and label each node. Identify the critical path and other paths through the network.

 

Activity

 

 

Duration

 

Predecessors

A

 

 

3

 

--

B

 

 

5

 

A          

C

 

 

7

 

A

D

 

 

3

 

B, C

E

 

 

5

 

B

F

 

 

4

 

D

G

 

 

2

 

C

H

 

 

5

 

E, F, G

Activity 

Duration

ES

EF

LS

 

LF

Slack

A

3

0

3

0

 

0

--

B

5

3

8

8

 

13

5

C

7

3

10

3

 

10

--

D

3

10

13

13

 

13

--

E

5

8

12

13

 

17

5

F

4

13

17

13

 

17

 

G

2

10

12

15

 

17

5

H

5

17

22

17

 

22

--

         

 