You are working with your team leads to create the project schedule. You are very concerned about the intersections between the teams, so you all are starting with the major milestones and working backward from the new product launch.
Sales of the new product are going to start in 9 months and the new CRM system needs to be in place 6 weeks prior so the sales force can get their customer and prospect information entered in time for the big marketing mailing going out 3 weeks prior to the product being available. You have one team working on the marketing program (and the mailing is just one of their deliverables); this team is being led by Jennifer from marketing. You also have another team working on the CRM implementation being led by Ben from IT. The two teams will intersect at the sales force training on the new system, the new product, and the new marketing program. After talking with the sponsor and customers, it was determined that the training approach would be holistic; the marketing process would be taught using the new system–not two separate classes, but one integrated class. Instructors will come from both the IT and the marketing teams. You are unsure which team leader should be responsible for training; it will depend upon the resources and dependencies.
Using the list of tasks below as a starting point, create a schedule by adding tasks, dependencies, efforts, and descriptions of the skills required to complete each task. Also, determine the start and end dates based on the dependencies and effort (assume your resources have 50% availability to the project). The schedule should contain between 30 and 60 tasks/subtasks. Use Microsoft Project, Excel, Word, or any other appropriate tool to document your schedule. You will also need to define the team members you will need. For each team member you will need, create a bulleted list of skills and expertise that he or she must have to complete the assigned tasks. For the effort, describe your rationale for your estimate.
- Determine training objectives.
- Create training outline (objectives, phases, topics, and content).
- Define activities.
- Create instructor guide.
- Create participant materials.
- Create activity guide.
- Review training materials.
- Conduct pilot training class/test training materials.
- Deliver training to all of sales force.
Please refer to the following multimedia course material(s):
- Unit 1: Work Breakdown Structure
- Unit 1: Foundations for Effective Project
- Unit 1: Project Schedule Defined
- Unit 1: FAQ: Activities & PM
- Unit 2: Structure of the Project Schedule
- Unit 2: Project Scheduling and Resource Allocation
- Unit 2: Project Planning & Scheduling Review
- Unit 2: Resource Planning in the Project
12 years ago
10
Purchase the answer to view it

- project_schedule_on_marketing_program.doc
- one cell phone company charges $0.10 per minute with no activation fee. Another cell phone service charges $0.05 per minute...
- Identify the subject of the sentence. The rain and wind caused the planners to postpone the concert.
- what were the major features of roman government and society during the republic
- Post a 150-200-word response to the following discussion question by clicking on Reply. Ask question(s) at the...
- should obsidian be classified as a mineral? Explain why or why not.
- How large is a mass if a force of 100 N is required to accelerate it by 1m/sec/sec?
- when did canada become a country
- 4x-7(3x-4)=-2(2x-4)
- 1. Using the descriptions of the attributes given in the figure, convert the ERD shown in P6.1 into a dependency that...
- What was general washington's greatest strength?