Task Successor Duration Start A, B 0 A C, D 3 B D 5 C E 4 D G 8 E F +1 d lag, G 7 F H 2 G H 4 H End 3 Draw the PDM and calculate Critical Path How many paths are there? What is the individual floats for each task?
Fin-Acc-Boss (Not rated)
(Not rated)
| Task | Successor | Duration | ||
| Start | A, B | 0 | ||
| A | C, D | 3 | ||
| B | D | 5 | ||
| C | E | 4 | ||
| D | G | 8 | ||
| E | F +1 d lag, G | 7 | ||
| F | H | 2 | ||
| G | H | 4 | ||
| H | End | 3 | ||
| Draw the PDM and calculate Critical Path | ||||
| How many paths are there? | ||||
| What is the individual floats for each task? | ||||
| Does the lag matter in this project? | ||||