Task Successor Duration Start A, B 0 A C, D 3 B D 5 C E 4 D G 8 E F +1 d lag, G 7 F H 2 G H 4 H End 3 Draw the PDM and calculate Critical Path How many paths are there? What is the individual floats for each task?

profileFin-Acc-Boss
 (Not rated)
 (Not rated)
Chat

 

Task Successor Duration   
Start A, B 0  
A C, D 3  
B D 5  
C E 4  
D G 8  
E F +1 d lag, G 7  
F H 2  
G H 4  
H End 3  
     
     
     
Draw the PDM and calculate Critical Path 
     
How many paths are there?  
     
What is the individual floats for each task?
     
Does the lag matter in this project? 
 
 
 
 
    • 11 years ago
    Task Successor Duration Start A, B 0 A C, D 3 B D 5 C E 4 D G 8 E F +1 d lag, G 7 F H 2 G H 4 H End 3 Draw the PDM and calculate Critical Path How many paths are there? What is the individual floats for each task?
    NOT RATED