Suppose a project costs $1,000 and produces cash flows of $200 over each of the next three years and a cash flow of $250 for each of the years four to six.
Use the following information for this and the next question.
Suppose a project costs $1,000 and produces cash flows of $200 over each of the next three years and a
cash flow of $250 for each of the years four to six.
What is the IRR of the project?
a. 15.2%
b. 10.0%
c. 24.3%
d. 8.8%
What is the NPV of the project if the required rate of return is 8 percent?
a. $350
b. $160
c. $27
d. $0
The following information is for this and the following two questions.
X and Y, LLC has two mutually exclusive projects available. The cash flows from these projects are
shown below.
What is the IRR of Project A and Project B, respectively?
a. 17.48% and 17.03%
b. 14.71% and 16.09%
c. 16.09% and 14.71%
d. 19.84% and 18.31%
If the required rate of return is 12%, what is the NPV of Project A and Project B, respectively?
a. $3,568 and $3,974
b. $3,568 and $7,051
c. $5,735 and $3,974
d. $5,735 and $7,051
What is the crossover rate between Project A and Project B?a. 18.31%
b. 14.17%
c. 16.09%
d. 19.84%
What is the Net Future Value (Terminal Value) of the following set of cash flows at 10% rate? (Hint: To
calculate terminal values, calculate the future value of all cash flows at the end of the project, and add
them together, that is, NFV = FV of Cash Inflows – FV of Cash Outflows) (Answers are rounded.)
a. $ 0.00
b. –$500
c. –$770
d. –$1,360
Your required return is 12%. Should you accept a project with the following cash flows?
a. No, because the IRR is 13.9%.
b. No, because the IRR is 8.0%.
c. Yes, because the IRR is 13.9%.
d. Yes, because the IRR is 8.0%.
Use the following information for this and the next two question.
Suppose a project costs $222,000 at start up, generates a cash flows of $560,000 in year one, and costs
$350,000 in year 2. There are no cash flows after year 2.
What is the first (lowest) IRR of the project?
a. 14.2083%
b. 10.0000%
c. 24.3125%
d. 38.0439%
What is the second IRR of the project?
a. 14.2083%
b. 10.0000%
c. 24.3125%
d. 38.0439%
What is the NPV of the project at 25 percent required rate of return?
a. 306.24
b. 1,611.11
c. 2,000.00
d. 1,668.64
12 years ago
Purchase the answer to view it

- solution-4039.xls