12-1 Using the information in Table 12-7, construct a PERT network and answer each of the following questions:

  • a. What is the expected project completion data?
  • b. What is the scheduled start and completion date for each activity?
  • c. Which activities are on the critical path?
  • d. How long can noncritical path activities be delayed without jeopardizing the overall completion date for this project?
  • 12-2 Assess the impact of the following changes to the time estimates provided in question 12-1. Individually, what is the impact if:

    Activity

    Predecessor

    New Time Estimate

    O. Advertise for new staff

    N

    4

    P. Interview for new staff

    O

    6

    Q. Select new staff

    P

    1

    Collectively, what is the impact of these changes?

  • 12-3 As project manager for the example included in question 12-1, what would you recommend to preserve the original project completion date if activity A was reestimated to take 8 weeks, not the original 4 weeks? Provide details.
  • 12-4 Develop a WBS and PERT network with no more than 20 activities for each of the following projects.
    • a. Buying a car
    • b. Screening 1000 school-age children for high blood pressure and reporting the results to the child’s physician
    • Table 12-7 Project to Convert a 20-Bed Unit in a Nursing Home to Accommodate Patients with Dementia

      Activity

       

      Predecessor

      Time estimate (weeks)

      A

      Secure state approval

      4

      B

      Identify 20-bed unit to be used

      A

      1

      C

      Move existing residents

      B

      1

      D

      Clean space

      C

      2

      E

      Develop architectural plans

      A

      9

      F

      Install new heating and ventilation systems

      E

      4

      G

      Install security systems

      E

      2

      H

      Move walls; renovate

      F

      4

      I

      Identify new equipment

      A

      1

      J

      Order new equipment

      I

      1

      K

      Unpack and inspect new equipment

      J

      1

      L

      Install new equipment

      D, K, H

      3

      M

      Reassign staff

      A

      1

      N

      Identify new staffing needs

      M

      1

      O

      Advertise for new staff

      N

      3

      P

      Interview for new staff

      O

      2

      Q

      Select new hires

      P

      3

      R

      Develop care plan protocols

      M

      1

      S

      Train staff

      R, Q, M, L

      1

      T

      Modify quality assurance plans

      S

      2

      U

      Coordinate with hospital discharge planners

      T

      4

      V

      Complete internal audit

      U, G

      1