q3
Question 3
Lewitt PLC has asked for your help in designing their new costing system. You have
ascertained that they have two direct production departments: manufacturing and finishing,
and two production overhead departments: stores and canteen.
The allocated costs in the period are budgeted to be:
Manufacturing £360,000 Stores £120,000
Finishing £320,000 Canteen £30,000
Costs to be apportioned:
Rent on basis of floor area £26,000
Machine depreciation on basis of original cost of machinery £60,000
Management time on basis of time spent in each dept. £120,000
Floor Area Machinery Management
Sq mtrs Original cost Time
Manufacturing 300 £450,000 48%
Finishing 100 £30,000 32%
Stores 50 £5,000 5%
Canteen 70 £15,000 15%
Stores Number of
Requisitions Employees
Manufacturing 150 35
Finishing 10 25
Stores N/A N/A
Canteen 40 N/A
Budgeted machine hours in manufacturing department is 25,183
Budgeted direct labour hours in finishing department is 27,095
Required:
Calculate the overhead absorption rate for the manufacturing and finishing departments.
14 years ago
10
Answer(1)![blurred-text]()
![]()
Purchase the answer to view it

NOT RATED
- q3_1.xlsx
Bids(0)
other Questions(10)
- how is a virus different from a bacterium?
- list all positive factors of 56
- pH
- how do you solve -5a+4=29
- write down the gradient of each line and coordinates of y-intercept a)y=2x-8
- Keisha and Honey jog together.In one week, they ran 1 3/4 miles, 1 2/5 miles,1/2 mile,1 mile,and 1 1/4 miles.About...
- Economics of Health and Health Care Chapter 4-6 summaries
- given a force of 100 N and an acceleration of 10 m/s^2, what is the mass?
- Evaluate. Please show all of your work. -5 ÷ m2 – 2(m – 2), for m = 1
- How much is 400 parts 921 twice 4000000