Project Time Management
SuperClassLab 7 - Chapter 8: Project Time Management Name: Chapter 8, Section 1 Exercises 1. A _________ schedule identifies major types of activities and approximate start and end dates for use in decision making about the scope of the project. 2. A schedule of activities that is prepared every two weeks is the _______ schedule. 3. How does a conceptual schedule differ from a master schedule? Chapter 8, Section 2 Exercises 1. What is work breakdown structure? 2. If two activities are concurrent and they have the same completion date, they have a _______-_______ relationship. 3. A calendar that shows when a person, facility, or key piece of equipment is available is a __________ calendar. 4. What is the advantage of a network diagram over a bar chart for illustrating the critical path? Chapter 8, Section 3 Exercises 1. The path through the network diagram that has the longest total duration is the __________ path. 2. The difference between the sum of the activity durations along the critical path and the project completion date is the project _______. 3. If two sequential activities overlap and the successor activity can begin three days before the predecessor begins, those three days are called _________ time. 4. If the last activity in the critical path has a completion date that is five days later than the project completion date, the project has a _______ _________ (two words) of five days. 5. What is the difference between free float and project float? 6. If an activity has a duration of three days, how do you calculate the finish date in a way that considers availability of the resources for that activity? 7. What would be an example of lag time between two activities? Chapter 8, Section 4 Exercises 1. Accelerating the project schedule is also known as ________ the project. 2. Extra amounts of time and money that are built into the schedule to buffer against delays and extra costs are called...
10 years ago
Purchase the answer to view it

- project_time_management.doc