) A project to remodel a bathroom has the following activities. Build this in MS Project (or Excel) showing predecessors and paste your answer here (20 points). ActivityDurationPredecessors A2 months--- B4 months--- C4 months--- D1 monthA E5 monthsB F2 mo

profileklbclaughuxn83

Urgent!

A project to remodel a bathroom has the following activities. Build in Excel showing prdecessors (20 points).
Activity   Duration   Predecessors
A          2 months---
B         4 months---
C          4 months---
D         1 month               A
E          5 months             B
F         2 months            B, C
G        1 month                C
H        3 months          E, F, G
I         2 months            D, E
J         2 months            G, H