Project Management

profilejamscu

 

Question 1 text  Question 1

1 points  

Save  

 

Which of the following is an example of a project?

    

Question 1 answers

[removed]

 

a. Maintaining e-mail addresses

[removed]

 

b. Capacity planning

[removed]

 

c. Submitting travel and expense reports

[removed]

 

d. Sending monthly reports to top management

    

 

 

 

Question 2 text  Question 2

1 points  

Save  

 

An effective project manager must:

    

Question 2 answers

[removed]

 

a. Tell his team members what to do

[removed]

 

b. Be the most capable person on the team technically

[removed]

 

c. Be focused on achieving results

[removed]

 

d. Not trust his team members to achieve results without his personal attention to detail

    

 

 

 

Question 3 text  Question 3

1 points  

Save  

 

A key characteristic of an effective project team is that:

    

Question 3 answers

[removed]

 

a. Members have graduate degrees in project management

[removed]

 

b. Members come from the same professional background

[removed]

 

c. Members see themselves as stakeholders in the project

[removed]

 

d. Members adhere to a prescribed pecking order

    

 

 

 

Question 4 text  Question 4

1 points  

Save  

 

A challenge of the matrix project organization is that:

    

Question 4 answers

[removed]

 

a. Team members are full of ego

[removed]

 

b. Team members are selected from the same functional area

[removed]

 

c. Team members have divided loyalties

[removed]

 

d. It enables functional managers to provide career guidance to their workers

    

 

 

 

Question 5 text  Question 5

1 points  

Save  

 

A key weakness of the Benefit-Cost ratio project selection mechanism is that:

    

Question 5 answers

[removed]

 

a. It only focuses on things that can be measured

[removed]

 

b. It takes time frame into consideration

[removed]

 

c. It is too much based on subjective judgment

[removed]

 

d. It does not entail prioritizing

    

 

 

 

Question 6 text  Question 6

1 points  

Save  

 

A major strength of task Gantt charts is that they can:

    

Question 6 answers

[removed]

 

a. Offer a sophisticated model of a project

[removed]

 

b. Show how many resources will be used on the project

[removed]

 

c. Show the interdependencies of tasks

[removed]

 

d. Show actual versus planned schedule status

    

 

 

 

Question 7 text  Question 7

1 points  

Save  

 

If you want to shorten the length of a project, you must:

    

Question 7 answers

[removed]

 

a. Shorten the critical path

[removed]

 

b. Shorten the free float

[removed]

 

c. Spend more money

[removed]

 

d. Cut back on the features you plan to deliver

    

 

 

 

Question 8 text  Question 8

1 points  

Save  

 

The critical path:

    

Question 8 answers

[removed]

 

a. Provides the duration of a project

[removed]

 

b. Has the shortest duration on a project

[removed]

 

c. Is the most expensive path to implement

[removed]

 

d. Contains the project's most significant tasks

    

 

 

 

Question 9 text  Question 9

1 points  

Save  

 

A tool that graphically shows cost variance is:

    

Question 9 answers

[removed]

 

a. A chart of accounts

[removed]

 

b. A code of accounts

[removed]

 

c. A histogram (also called a resource loading chart)

[removed]

 

d. A cumulative cost curve (also called S-curve)

    

 

 

 

Question 10 text  Question 10

1 points  

Save  

 

Which of the following methods involves performing tasks in parallel?

    

Question 10 answers

[removed]

 

a. Crashing

[removed]

 

b. Fast tracking

[removed]

 

c. Leveling

[removed]

 

d. Hammocking

    

 

 

 

Question 11 text  Question 11

1 points  

Save  

 

Top-down estimates (also called parametric estimates):

    

Question 11 answers

[removed]

 

a. Are based on historical trends

[removed]

 

b. Can be derived from the WBS

[removed]

 

c. Can be determined by analyzing work packages

[removed]

 

d. Provide accurate assessments of project costs

    

 

 

 

Question 12 text  Question 12

1 points  

Save  

 

Bottom-up estimates:

    

Question 12 answers

[removed]

 

a. Are based on historical trends

[removed]

 

b. Can be derived from the WBS

[removed]

 

c. Must employ Monte Carlo simulation

[removed]

 

d. a and c

    

 

 

 

Question 13 text  Question 13

1 points  

Save  

 

Definitive estimates are generally derived from:

    

Question 13 answers

[removed]

 

a. Bottom-up estimates

[removed]

 

b. Top-down estimates

[removed]

 

c. Expert judgment cost estimates

[removed]

 

d. Order of magnitude estimates

    

 

 

 

Question 14 text  Question 14

1 points  

Save  

 

The resource planning tool that enables us to identify who we need to carry out what tasks is called:

    

Question 14 answers

[removed]

 

a. A resource Gantt chart

[removed]

 

b. A resource matrix (also called the responsibility chart)

[removed]

 

c. A resource ogive

[removed]

 

d. A resource loading chart (also called a resource histogram)

    

 

 

 

Question 15 text  Question 15

1 points  

Save  

 

Which of the following shows resource allocation over time?

    

Question 15 answers

[removed]

 

a. Resource Gantt chart

[removed]

 

b. Resource matrix

[removed]

 

c. S-Curve

[removed]

 

d. Resource leveling

    

 

 

 

Question 16 text  Question 16

1 points  

Save  

 

What is the function of a change control board (CCB) in configuration management?

    

Question 16 answers

[removed]

 

a. To assess the management impacts of change requests

[removed]

 

b. To initiate changes needed on the project

[removed]

 

c. To focus on the technical implication of change requests

[removed]

 

d. To approve change requests coming from senior management

    

 

 

 

Question 17 text  Question 17

1 points  

Save  

 

Good functional requirements

    

Question 17 answers

[removed]

 

a. Describe how the deliverable should be developed

[removed]

 

b. Provide detailed technical insights into what the deliverable will do

[removed]

 

c. Describe what the deliverable looks like and what it should do

[removed]

 

d. Are created after development of the technical specifications

    

 

 

 

Question 18 text  Question 18

1 points  

Save  

 

The type of management whose focus is on activities whose variances lie outside the acceptable range is:

    

Question 18 answers

[removed]

 

a. Management by Objectives

[removed]

 

b. Management by Exception

[removed]

 

c. Management by Walking Around

[removed]

 

d. Management by Control Limits

    

 

 

 

Question 19 text  Question 19

1 points  

Save  

 

Which of the following is a characteristic of an effective reporting system?

    

Question 19 answers

[removed]

 

a. SMART

[removed]

 

b. KISS

[removed]

 

c. MBO

[removed]

 

d. LOWBALLING

    

 

 

 

Question 20 text  Question 20

1 points  

Save  

 

Which of the following is an elapsed time task?

    

Question 20 answers

[removed]

 

a. Paint is drying

[removed]

 

b. A painter paints the wall

[removed]

 

c. Software is being written

[removed]

 

d. A sandwich is being made

    

 

 

 

Question 21 text  Question 21

1 points  

Save  

 

An autocratic management style:

    

Question 21 answers

[removed]

 

a. Is effective in most project management situations

[removed]

 

b. Is effective in highly routine efforts

[removed]

 

c. Is effective in high flux, state-of-the-art projects

[removed]

 

d. Will lead to the tyranny of the majority

    

 

 

 

Question 22 text  Question 22

1 points  

Save  

 

A project team structure that closely reflects the physical structure of the deliverable is known as:

    

Question 22 answers

[removed]

 

a. Egoless

[removed]

 

b. Specialty

[removed]

 

c. Surgical

[removed]

 

d. Isomorphic

    

 

 

 

Question 23 text  Question 23

1 points  

Save  

 

The purpose of mid-project evaluation is:

    

Question 23 answers

[removed]

 

a. Continual monitoring of budget and estimates

[removed]

 

b. To focus on achievement of individual element of the project plan

[removed]

 

c. To determine whether the original objectives are still relevant

[removed]

 

d. To re-baseline the project budget

    

 

 

 

Question 24 text  Question 24

1 points  

Save  

 

If the latest time you can start a task is five hours into the project, and the earliest time is three and a half hours into the project, how much slack (also called float) does the task have?

    

Question 24 answers

[removed]

 

a. 0.5 hours

[removed]

 

b. 1.5 hours

[removed]

 

c. 2.5 hours

[removed]

 

d. 8.5 hours

    

 

 

 

Question 25 text  Question 25

1 points  

Save  

 

In risk management, insurance is an example of:

    

Question 25 answers

[removed]

 

a. Risk avoidance

[removed]

 

b. Risk deflection

[removed]

 

c. Risk acceptance

[removed]

 

d. Contingency planning

    

 

 

 

Question 26 text  Question 26

1 points  

Save  

 

A four step risk assessment process reflecting standard risk management good practice consists of:

    

Question 26 answers

[removed]

 

a. Risk identification, Risk deflection, Risk impact analysis, Risk monitoring and control

[removed]

 

b.  Risk acceptance, Risk impact analysis, Risk response planning, Risk monitoring and control

[removed]

 

c. Risk deflection, Contingency planning, Risk impact analysis, Risk monitoring and control

[removed]

 

d. Risk identification, Risk impact analysis, Risk response planning, Risk monitoring and control

    

 

 

 

Question 27 text  Question 27

1 points  

Save  

 

Structured Walk-Through is a methodology used in:

    

Question 27 answers

[removed]

 

a. PERT

[removed]

 

b. GERT

[removed]

 

c. VERT

[removed]

 

d. Project Evaluation

    

 

 

 

Question 28 text  Question 28

1 points  

Save  

 

If review of a project's status indicates that EV = $400, AC = $400, and PV = $500, the project is:

    

Question 28 answers

[removed]

 

a. On budget, behind schedule

[removed]

 

b. On budget, ahead of schedule

[removed]

 

c. Over budget, behind schedule

[removed]

 

d. Over budget, ahead of schedule

    

 

 

 

Question 29 text  Question 29

1 points  

Save  

 

The poor man's hierarchy is a method for:

    

Question 29 answers

[removed]

 

a. Project estimation

[removed]

 

b. Project scheduling

[removed]

 

c. WBS construction

[removed]

 

d. Project selection

    

 

 

 

Question 30 text  Question 30

1 points  

Save  

 

According to PMI, a WBS should focus on

    

Question 30 answers

[removed]

 

a. Tasks

[removed]

 

b. Deliverables

[removed]

 

c. Interrelationships among activities

[removed]

 

d. Cost of the project

    

 

 

 

Question 31 text  Question 31

1 points  

Save  

 

If EV = $300, AC = $400, and the project budget is $1,000, what is the estimated final cost of the project (this is known as EAC, estimate at complete)?

    

Question 31 answers

[removed]

 

a. $750

[removed]

 

b. $1,000

[removed]

 

c. $1,250

[removed]

 

d. $1,333

    

 

 

 

Question 32 text  Question 32

1 points  

Save  

 

Which of the following is a scope planning tool?

    

Question 32 answers

[removed]

 

a. Benefit/cost analysis

[removed]

 

b. WBS

[removed]

 

c. Earned Value analysis

[removed]

 

d. Fast tracking

    

 

 

 

Question 33 text  Question 33

1 points  

Save  

 

In resource planning, one of the issues that needs to be considered is:

    

Question 33 answers

[removed]

 

a. Staff empowerment

[removed]

 

b. Technical requirements of the project

[removed]

 

c. Theory X management principles

[removed]

 

d. Theory Y management principles

    

 

 

 

Question 34 text  Question 34

1 points  

Save  

 

The bottom-most level of the WBS -- the level at which project budget and schedule data are captured -- is called:

    

Question 34 answers

[removed]

 

a. Work package

[removed]

 

b. Code of accounts

[removed]

 

c. Budget baseline

[removed]

 

d. Change control level

    

 

 

 

Question 35 text  Question 35

1 points  

Save  

 

Scope creep means:

    

Question 35 answers

[removed]

 

a. Needs emergence and identification

[removed]

 

b. Uncontrolled changes to a project's requirements during project execution

[removed]

 

c. Migration of project needs to requirements

[removed]

 

d. Imprecise scope statement

    

 

 

 

Question 36 text  Question 36

1 points  

Save  

 

Configuration management is a:

    

Question 36 answers

[removed]

 

a. Methodology for working closely with customers by developing and updating requirements for faster response to changing customer needs

[removed]

 

b. Methodology for ensuring that requirements evolve with evolving customer requirements

[removed]

 

c. Methodology for specifying requirements at the outset and for controlling very tightly any changes to them

[removed]

 

d. Methodology for specifying requirements at the outset and for facilitating any changes to them with minimum customer input

    

 

 

 

Question 37 text  Question 37

1 points  

Save  

 

Rapid prototyping is a methodology for:

    

Question 37 answers

[removed]

 

a. Specifying requirements at the outset and for controlling very tightly any changes to them

[removed]

 

b. Specifying requirements at the outset and for facilitating later changes to them with minimum customer in put

[removed]

 

c. Triggering early warning of unauthorized changes to the original prototype to enable project management to take remedial actions

[removed]

 

d. Working closely with customers by creating and updating prototypes that respond to customer input

    

 

 

 

Question 38 text  Question 38

1 points  

Save  

 

Ensuring a one-to-one correspondence between specification items and general design items is a feature of:

    

Question 38 answers

[removed]

 

a. Scope statement definition

[removed]

 

b. WBS construction

[removed]

 

c. Rapid prototyping

[removed]

 

d. Configuration management

    

 

 

 

Question 39 text  Question 39

1 points  

Save  

 

Under what conditions may a project manager accept a change request?

    

Question 39 answers

[removed]

 

a. If the request has no effect on project objectives, deadlines, or resources

[removed]

 

b. If the request has no effect on project objectives, although it has effects on deadlines and resources

[removed]

 

c. If the request is coming from a valued customer

[removed]

 

d. If the request is from the Chief Executive Officer

    

 

 

 

Question 40 text  Question 40

1 points  

Save  

 

Which of the following is not an activity carried out during project closeout?

    

Question 40 answers

[removed]

 

a. Reassignment of project staff

[removed]

 

b. Preparation of the project's baseline

[removed]

 

c. Reassignment of material resources

[removed]

 

d. Preparation of user manuals

    

 

 

 

Question 41 text  Question 41

1 points  

Save  

 

When crashing a project, we typically choose critical path tasks whose costs of crashing are highest.

    

Question 41 answers

[removed]

True

[removed]

False

    

 

 

 

Question 42 text  Question 42

1 points  

Save  

 

The astute project manager typically uses only one management style in order not to confuse his/her teammates.

    

Question 42 answers

[removed]

True

[removed]

False

    

 

 

 

Question 43 text  Question 43

1 points  

Save  

 

Concurrent engineering involves overlapping tasks and phases to accelerate a project's schedule.

    

Question 43 answers

[removed]

True

[removed]

False

    

 

 

 

Question 44 text  Question 44

1 points  

Save  

 

A work package is to be found at the summary level of the WBS.

    

Question 44 answers

[removed]

True

[removed]

False

    

 

 

 

Question 45 text  Question 45

1 points  

Save  

 

Milestones, like tasks, consume resources.

    

Question 45 answers

[removed]

True

[removed]

False

    

 

 

 

Question 46 text  Question 46

1 points  

Save  

 

In project management, the level of uncertainty plays a major role in determining the adequacy of a project plan.

    

Question 46 answers

[removed]

True

[removed]

False

    

 

 

 

Question 47 text  Question 47

1 points  

Save  

 

Using working time or elapsed time to calculate the time it will take to complete a task produces the same results.

    

Question 47 answers

[removed]

True

[removed]

False

    

 

 

 

Question 48 text  Question 48

1 points  

Save  

 

Needs recognition is the first stage of the needs-requirement life cycle.

    

Question 48 answers

[removed]

True

[removed]

False

    

 

 

 

Question 49 text  Question 49

1 points  

Save  

 

Functional requirements provide us with detailed technical specifications.

    

Question 49 answers

[removed]

True

[removed]

False

    

 

 

 

Question 50 text  Question 50

1 points  

Save  

 

A key objective of change control in configuration management is to keep track of actions taken in response to change requests.

    

Question 50 answers

[removed]

True

[removed]

False

    

 

 

 

Question 51 text  Question 51

1 points  

Save  

 

Under rapid prototyping (also called application prototyping), the customer actually sees and works with the deliverable as it evolves.

    

Question 51 answers

[removed]

True

[removed]

False

    

 

 

 

Question 52 text  Question 52

1 points  

Save  

 

There is a definite link between the level of risk an enterprise encounters and project time frame.

    

Question 52 answers

[removed]

True

[removed]

False

    

 

 

 

Question 53 text  Question 53

1 points  

Save  

 

When we have objective data on the probability of an event, we are involved with decision making under certainty.

    

Question 53 answers

[removed]

True

[removed]

False

    

 

 

 

Question 54 text  Question 54

1 points  

Save  

 

The Theory X approach to managing workers is a classic example of a top-down view of how people should be managed.

    

Question 54 answers

[removed]

True

[removed]

False

    

 

 

 

Question 55 text  Question 55

1 points  

Save  

 

A laissez-faire management style may lead to a ship without rudder syndrome.

    

Question 55 answers

[removed]

True

[removed]

False

    

 

 

 

Question 56 text  Question 56

1 points  

Save  

 

An objective of prototyping is to minimize life-cycle cost.

    

Question 56 answers

[removed]

True

[removed]

False

    

 

 

 

Question 57 text  Question 57

1 points  

Save  

 

A modern view in Human Resource Management is that positive motivation results from an opportunity to achieve and experience self-actualization.

    

Question 57 answers

[removed]

True

[removed]

False

    

 

 

 

Question 58 text  Question 58

1 points  

Save  

 

Confidence in the accuracy of a cost estimate increases when top-down and bottom-up estimates converge.

    

Question 58 answers

[removed]

True

[removed]

False

    

 

 

 

Question 59 text  Question 59

1 points  

Save  

 

Internal Rate of Return (IRR) is the discount rate that sets the present value of cash outflow equal to the present value of cash inflow.

    

Question 59 answers

[removed]

True

[removed]

False

    

 

 

 

Question 60 text  Question 60

1 points  

Save  

 

A project can be terminated prematurely because the original objectives may no longer be valid.

    

Question 60 answers

[removed]

True

[removed]

False

    

 

Bottom of Form

 

 

 

  • 12 years ago
  • 40
Answer(1)

Purchase the answer to view it

blurred-text
NOT RATED
  • attachment
    management.docx
  • attachment
    project_management_multiple.docx