Project 2-6: Don Funk Music Video Problems
A student who is interning with your company made some updates to the music video project schedule. Unfortunately, he is still learning about Microsoft Project and has entered some information incorrectly. You need to correct the problems with the project schedule before distributing it to your team.
OPEN Don Funk Incorrect 2-6 from the data files for this lesson. 1. Review the Resource Sheet for this project schedule.
2. Based on what you have learned in this lesson about Resource Types, Maximum Units, and Standard Rates, find the resource errors in this project schedule and make corrections to them. (Hint: There are three resource errors in the project schedule.)
3. Study the last three resources on the sheet. If dry ice is a work resource and bottled water is a cost resource, make corrections to the information given for these resources (estimate the rate if necessary).
4. SAVE the project schedule as Don Funk Corrected and then CLOSE the file. CLOSE Project.
NEED IT IN 1 HOUR!!!!!!
9 years ago
3
- forensic Science
- HOMEWORK HELP!!!!
- China has been growing at a phenomenal rate and recently became the second largest economy in the world. Discuss economic reasons why trade with China (both in terms of importing and exporting) is beneficial to the United States.
- Twelve Angry Men: Stages of Group Development
- HRM533 WEEK 6 ASSIGNMENT 3
- 1. What purpose does a mission statement play in the success or failure of a strategic vision? Present your position, and defend your posture with strategic management theory. How does a company mission statement differ with a personal mission statement
- weekly discussion post apa format with references less than 5 years old
- For Prof.MacQueen only
- Are laws related to oil and gas development sufficient? Do they protect the environment? Do they encourage industry? Include any personal or work experience that you have related to oil and gas laws.
- quick mutiple choice and short answer