1. (TCO G) Estimate At Completion forecast (EAC) A project has been estimated to take eight weeks and cost $65,000. The critical path is A - D. Cost and earned value data are provided below: | | EV | PV | | | AC | | | | Budget | BCWP | - BCWS | SV | SPI | - ACWP | CV | CPI | A | $8,500 | $8,500 | $8,500 | $ - | 1.00 | $7,500 | $1,000 | 1.13 | B | $15,000 | $15,000 | $15,000 | $ - | 1.00 | $13,000 | $2,000 | 1.15 | C | $6,800 | $2,530 | $2,700 | ($170) | 0.94 | $4,000 | ($1,470) | 0.63 | D | $18,000 | $900 | $3,000 | ($2,100) | 0.30 | $1,200 | ($300) | 0.75 | E | $16,000 | $0 | $0 | $ - | | $0 | $ - | | Project: | $64,300 | 26,930 | 29,200 | ($2,270) | 0.92 | $25,700 | $730 | 1.05 |
(i) Calculate the Estimate At Completion (EAC) considering future performance will be back on schedule and budget. (ii) Calculate EAC considering that the project will continue to perform as it has to date. (iii) Using either of these two numbers discuss the status of the project and if the project manager needs to take corrective actions. Justify your comments. (Points : 30) Answer – |
2. (TCO D) PMIS and cost accounting Monitoring of projects and especially using an earned value system will give a project manager the ability to exercise proper project control. The Earned Value process requires detail data which we can obtain from proper Project Cost Accounting System (PCAS). (a) What are the primary types of data we require for Earned Value Analysis? (b) What are some of the benefits of PCAS? (Points : 30) |
3. (TCO F) Earned Value The following data were obtained from a project to design a new software package: Activity | Duration | Predecessors | Budgeted Cost | A | 3 Days | -- | $8,320 | B | 6 Days | -- | $11,740 | C | 4 Days | A | $11,550 | D | 2 Days | C, B | $7,850 | E | 3 Days | A | $10,750 | F | 2 Days | D, E | $8,600 |
At the end of day 5, the status of the project is as follows:
Activity | % Complete | Actual Cost | A | 100% | $7,200 | B | 50% | $6,370 | C | 25% | $8,250 | D | 0% | $0 | E | 80% | $8,560 | F | 0% | $0 |
(a) Calculate the Cost and Schedule Variances and Indexes (CV, SV, CPI, SPI) for tasks A, B, C, D, and E. (b) Write a brief analysis of the status of the project at this time, including task level, project level, and critical path. (Points : 30) |
|