Problem 17-19
Create a risk matrix for this project: |
Event | Cost ($000) | Probability |
1. Equipment breakdown | 40 | .20 |
2. Vendor is late with key segment | 200 | .60 |
3. Subcontractor has labor issues | 140 | .30 |
4. Weather problems | 15 | Unknown |
5. Funding delays | 50 | .40 to .60 |
6. Testing delays | 20 | .40 |