PM 592 Week 6 Quiz
(Not rated)
(Not rated)
1. Using the network below and the additional information provided, find:
(a) the crash cost per day per activity
(b) which activities should be crashed to meet a project deadline of 12 days at minimum cost; and
(c) what the extra cost is to crash the project.
Activity | Normal Time | Crash Time | Normal Cost | Crash Cost |
A | 5 | 3 | $300 | $600 |
B | 3 | 2 | $250 | $450 |
C | 6 | 4 | $400 | $500 |
D | 5 | 3 | $150 | $400 |