Question 1

Description: http://edugen.wileyplus.com/edugen/art2/common/pixel.gif

A CD player has 3 components that all must function for the player to work. The average reliability of each component is 0.88. What is the reliability of the CD player? (Round answer to 4 decimal places, e.g. 15.2500.)

Reliability of CD player

 

Description: http://edugen.wileyplus.com/edugen/art2/common/pixel.gif[removed]

 

Question 2

Description: http://edugen.wileyplus.com/edugen/art2/common/pixel.gif

An office copier has four main components in a series with the following reliabilities: 0.95, 0.81, 0.88, and 0.90. Determine the reliability of the copier. (Round answer to 4 decimal places, e.g. 15.2500.)

Reliability of copier

 

Description: http://edugen.wileyplus.com/edugen/art2/common/pixel.gif[removed]

 

Question 3

Description: http://edugen.wileyplus.com/edugen/art2/common/pixel.gif

A bank loan processing system has three components with individual reliabilities as shown:

Description: http://edugen.wileyplus.com/edugen/courses/crs6904/art/qb/qu/ch0/EAT_1352982480517_0_0604806841316793960.jpg

R1 = 0.98
R2 = 0.96
R3 = 0.88

What is the reliability of the bank loan processing system? (Round answer to 4 decimal places, e.g. 15.2500.)

Reliability of bank loan processing system

 

Description: http://edugen.wileyplus.com/edugen/art2/common/pixel.gif[removed]

 


 

 

Question 4

Description: http://edugen.wileyplus.com/edugen/art2/common/pixel.gif

An LCD projector in an office has a main light bulb with a reliability of 0.87 (R1) and a backup bulb, the reliability of which is 0.82 (R2). The system looks as follows:

Description: http://edugen.wileyplus.com/edugen/courses/crs6904/art/qb/qu/ch0/EAT_1352982480876_0_82690614666045890.jpg

What is the reliability of the system? (Round answer to 4 decimal places, e.g. 15.2500.)

Reliability of system

 

Description: http://edugen.wileyplus.com/edugen/art2/common/pixel.gif[removed]

 

Question 5

Description: http://edugen.wileyplus.com/edugen/art2/common/pixel.gif

BioTech Research Center is working to develop a new vaccine for the West Nile Virus. The project is so important that the firm has created three teams of experts to work on the project from different perspectives. Team 1 has a 83 percent chance of success, team 2 an 80 percent chance of success, and team 3 a 94 percent chance. What is the probability that BioTech will develop the vaccine? (Round answer to 4 decimal places, e.g. 15.2500.)

Probability of developing vaccine

 

Description: http://edugen.wileyplus.com/edugen/art2/common/pixel.gif[removed]

 

Question 6

Description: http://edugen.wileyplus.com/edugen/art2/common/pixel.gif

The following system of components has been proposed for a new product. Determine the reliability of the system. (Round answer to 4 decimal places, e.g. 15.2500.)

Description: http://edugen.wileyplus.com/edugen/courses/crs6904/art/qb/qu/ch0/EAT_1352982481500_0_63454816076851480.gif

Reliability of the system

 

Description: http://edugen.wileyplus.com/edugen/art2/common/pixel.gif[removed]

 

 

 

    • 10 years ago
    OPERATIONS MANAGEMENT - PROBLEMS IN Total Quality Management A+ Tutorial use as Guide
    NOT RATED

    Purchase the answer to view it

    blurred-text
    • attachment
      operations_management_-_problems_in_total_quality_management.docx