Operations Management 2 Discussion questions

profilemisbra

Discussion # 1:

How is process selection related to product design and capacity determination? Your initial post should be 200-250 words.

 

Discussion #2:

 

Read Problem 6: The “Monique Food Processing Company” in Chapter 8 of your text.

Monique Food Processing Company produces light snacks that can be heated in a microwave. The following steps are included in the process:

Steps

Description

Capacity (Units/Hour)

1

Prepare food

200

2

Measure and place in plastic pouch

175

3

Prepare cardboard box

200

4

Insert pouch into box

300

5

Shrink-wrap box

200

 

  1. What is the system capacity, and which is the bottleneck department?
  2. How much slack (unused capacity) is available in other departments?
  3. How much system capacity can be gained by adding capacity to the bottleneck?
  4. What are the key factors that determine when to add capacity?
  5. Why would an organization want to reduce its capacity?

Make and include calculations. Answer questions “a” through “e.” Your response should be 200-250 words.

  • 10 years ago
  • 20
Answer(3)

Purchase the answer to view it

blurred-text
NOT RATED
  • attachment
    monique_food_processing_company_and_capacity.doc

Purchase the answer to view it

blurred-text
NOT RATED
  • attachment
    operations_management_2_discussion_questions.edited.docx

Purchase the answer to view it

blurred-text
NOT RATED
  • attachment
    bus-644-week-4-dq-2-monique-food-processing-company-and-capacity-859004937.doc
Bids(1)