Problem 14-7

Compute the takt time for a system where the total time per shift is 500 minutes, there is one shift, and workers are given two 20-minute breaks and 40 minutes for lunch. Daily demand is 310 units. (Round your answer to 2 decimal places.)


  Takt time[removed] minutes per cycle  

 

Problem 14-8

What cycle time would match capacity and demand if demand is 187 units a day, there are two shifts of 397 minutes each, and workers are given three half-hour breaks during each shift, one of which is for lunch or dinner? (Round your answer to 2 decimal places.)


  Cycle time[removed] minutes per cycle  