1. Balance the assembly line for the tasks contained in the table. The desired output is 240 units per day. Available production time per day is 480 minutes.
Work Element | Time (Sec.) | Immediate Predecessor(s) |
A | 40 | --- |
B | 45 | --- |
C | 55 | A |
D | 55 | B |
E | 65 | B |
F | 40 | C,D |
G | 25 | D,E |
a) What is the desired Cycle time in seconds?
b) What is the theoretical minimum number of stations?
c) Use trial and error to work out a solution in the table below. Your efficiency should be at least 90%.
Station | Candidates | Choice | Work-Element Time (Sec) | Cumulative Time (Sec) | Idle Time |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
d) Calculate the efficiency of your solution. (2 points)
- 12 years ago
- 5
Answer(0)
Bids(0)
other Questions(10)
- Two lines are represented by the equations x+2y=4 and 4y-2x=12. Determine whether these lines are parallel, perpendicular, or neither. Justify...
- I dont understand what is the problem
- marketing
- what is 6457 divided by 27?
- How did max's and freak's families act toward them after killer Kane was returned to jail
- the selective advantage linked to the high frequency of the cystic fibrosis allele in caucasians is
- need help
- 3m+5=35
- Where is cotton found in Louisiana?
- Use pseudocode to design a program to read 10 integers and put these integers into two arrays. One array...