Question 1
Which of the following is NOT true regarding bottom-up budgeting?
A. The method tends to be inaccurate in the detailed tasks.
B. The WBS is used to identify the elemental tasks.
C. It is rarely used.
D. It is a good managerial training technique.
Question 2
A task is expected to take 20 hours of labor at $25 per hour. The required material cost is $500, and the organization charges 30% of direct labor for overhead. The total task cost is:
A. $500
B. $1,150
C. $1,250
D. $1,500
Question 3
There is a 30 percent chance that a new product development project will result in sales of $500,000 and a 70 percent chance that the project will result in sales of $100,000. What is the expected value of this project?
A. $220,000
B. $240,000
C. $300,000
D. $320,000
Question 4
Which of the following is most closely associated with FMEA?
A. Risk priority number
B. Game theory
C. Expected value
D. Simulation