MS Project 2
John_mattPredecessors and Successors I
Please write all your response in a single MS Word document covering all questions and exercises, and paste (do not attach) the screen shots into the document in-line with your text. It makes it much easier to read -- and grade. Please include screen shots of each step, not just one screen shot before or one after.
Note: These are not trick questions, though (as with many of the MS Project exercises) you need to read them carefully. Some people seem to misread the question and do the wrong thing.
These questions are based on the First Project (MS Project 1)
1. You've seen how to enter the predecessors for a task. What is one method to enter successors (that's right, successors, not predecessors) for an MS project task? (Note: This is not asking how to display the Successors column; that's the next question. This asks how to enter successors for a task.) Describe AND provide a screen shot of the steps.
2. What is one method to show the successors field (column)? Describe AND provide a screen shot of the steps.
3. What is one method to enter the project start date? Not the start date of a task (that's a different question, below) -- not even of the first task -- but the start date of the entire project. Describe AND provide a screen shot of the steps.
4. What version of MS Project did you use for this?
Due JUNE 17th
- 8 years ago
- 18
Purchase the answer to view it
- reply.docx
Purchase the answer to view it
- ms_project_questions2.docx
- ENG125-Assignment WK3
- OPS/571 Final Exam
- NEED PPT AND REFERENCING TO BE DONE
- prompt 2
- What is the importance of stakeholders to effective leadership
- PERT and Gantt
- BUS610 Assignment III - Motivational Problem Assignment 3
- Assignment 2 Sales Force Compensation
- Cognitive review of computer networks
- Research the Internet about a problem