MGT417 Midterm Exam New (2017)
Question 1 (2 points)
Savings in the supply chain are mostly the result of:
Question 1 options:
cutting cost after the design phase.
members in the chain sharing information.
members having clout with suppliers.
being able to ship in larger quantities.
sticking with local competition.
Question 2 (2 points)
If the manufacturing lead time of an item is reduced by 50%, the work in process inventory:
Question 2 options:
does not change.
is reduced by approximately 50%.
More information is needed for this problem.
is reduced by approximately 70%.
Question 3 (2 points)
Performance measures in a supply:
Question 3 options:
should be objective.
concentrate on cost only.
are viewed mostly by finance.
are not used once a process is automated.
must be measurements of one parameter only.
Question 4 (2 points)
Which of the following is/are primary activities of manufacturing planning and control?
I. Production planning
II. Implementation and control
III. Inventory management
Question 4 options:
I and III only
II and III only
I and II only
All of the above are primary activities.
Question 5 (2 points)
Making a pizza at a fast-food restaurant would be considered a form of:
Question 5 options:
assembling to order.
making to order.
making to stock.
none of the above.
engineering to order.
Question 6 (2 points)
Which of the following is (are) input(s) to manufacturing planning and control?
Question 6 options:
product description
available facilities
quantities to be produced
process description
all of the above
Save
Question 7 (2 points)
Which of the following is a complete closed-loop planning system that develops plans for all materials and operations?
Question 7 options:
Capacity Requirements Planning
Supply Chain Management
Enterprise Resource Planning
Material Requirements Planning
Question 8 (2 points)
Which of the following are characteristics of an MRPII system?
I. It incorporates the plans of marketing, production, and finance.
II. It is a fully integrated planning and control system.
III. It has feedback from the bottom up.
Question 8 options:
III only
I only
II only
I, II, and III
Question 9 (2 points)
Which of the following is a basic strategy in developing a production plan?
Question 9 options:
chase strategy
hybrid strategy
production leveling
production leveling and chase strategy
hybrid strategy and production leveling
Question 10 (2 points)
Which of the following information is needed to develop a make-to-stock production plan?
I. Forecast by time period for the production plan
II. Opening inventory
III. Opening backlog of customer orders
IV. Desired ending inventory
Question 10 options:
I, II, and IV
II, III, and IV
I, III, and IV
None of the above
I, II, and III
Question 11 (2 points)
Priority in production planning relates to:
Question 11 options:
none of the above
an objective of the firm.
how much of what is needed and when.
capacity.
what should come first.
Question 12 (2 points)
Over a 10-week period the cumulative sales are forecast at 10,000 units, the opening inventory is 200 units, and the closing inventory is to be 100 units. What should be the weekly planned production for level production?
Question 12 options:
1,010
1,000
990
none of the above
1,030
Question 13 (2 points)
Given the following table, calculate the ATP. There are 50 units on hand.
Week 1 2 3 4 5
Customer orders 20 20 15 30 10
Scheduled receipts 50
ATP
Question 13 options:
The ATP in week 1 is 30.
The ATP in week 1 is 5.
The ATP in week 2 is 10.
The ATP in week 1 is 10.
The ATP in week 3 is 35.
Question 14 (2 points)
The portion of inventory or production not committed to customer orders is called:
Question 14 options:
waste.
available to promise.
excess capacity.
excess production.
free stock.
Question 15 (2 points)
Which of the following modules follows the sales and operations plan?
Question 15 options:
Production planning
Material requirements planning
Master scheduling
Business planning
Question 16 (2 points)
The final assembly schedule is used:
Question 16 options:
in none of the above.
in a make-to-stock environment.
in an assemble-to-order environment.
in a make-to-order environment.
in any of the above.
Question 17 (2 points)
Which of the following is the term applied to a master schedule for a purchased item?
Question 17 options:
Supplier scheduling
Master scheduling
Purchase order
Material scheduling
Question 18 (2 points)
Master scheduling is a balancing act between which of the following?
Question 18 options:
Inventory and customer service
Supply and demand
Forecast and inventory
Forecasts and orders
Question 19 (2 points)
Which of the following comes directly from external customers?
Question 19 options:
Order quantity
Independent demand
Bill of materials
Dependent demand
Question 20 (2 points)
A set of priority planning techniques for planning component items below the end item level is called:
Question 20 options:
production control.
material requirements planning.
capacity planning.
none of the above
master scheduling.
Question 21 (2 points)
In material requirements planning, the process of placing the exploded requirements in the proper time periods, based on the assembly lead times involved, is known as:
Question 21 options:
netting.
offsetting.
none of the above
exploding.
all of the above
Question 22 (2 points)
Given the following parents and components, how many B’s are required to make an X? (Quantities are shown in parentheses.)
Parent X A
Component A(2) B(2)
B(1) D(1)
Question 22 options:
3
2
5
4
1
Question 23 (2 points)
A multilevel bill of materials:
I. Reflects the way the product will be manufactured.
II. Is produced by the engineering department.
III. Is a parts list only and does not contain subassemblies.
Question 23 options:
Only I is true.
I, II, and III are true.
Only II is true.
Only III is true.
I and II are true.
Question 24 (2 points)
The document that shows the component parts and the number of parts needed to make an assembly or subassembly is called:
Question 24 options:
none of the above
a material requisition.
a material requirements plan.
a bill of materials.
a route sheet.
Question 25 (2 points)
A report that shows the future capacity requirements based on released and planned orders for each time period of the plan is called:
Question 25 options:
dispatch list.
order report.
capacity report.
load report.
none of the above
Question 26 (2 points)
A work center was available for work 80 hours, produced 74 standard hours of work, and actually worked 67 hours. What is the efficiency of the work center?
Question 26 options:
119.4%
108.1%
92.5%
110.4%
Question 27 (2 points)
Rated capacity is calculated taking into account work center:
I. Historical data
II. Utilization
III. Efficiency
Question 27 options:
I and II.
None of the above.
II and III.
I and III.
Question 28 (2 points)
Available capacity in production planning is:
Question 28 options:
a measure of the ability of a plant to consume raw materials.
none of the above.
the quantity of work that can be performed in a given period of time.
all of the above.
the amount of inventory that can be held in a warehouse.
Question 29 (2 points)
The ratio of standard hours of work produced to hours actually worked is called:
Question 29 options:
efficiency.
effectiveness.
Murphy's factor.
up-time.
utilization.
Question 30 (2 points)
In one week, a work center produced 130 standard hours of work. The actual hours worked was 114. The efficiency is:
Question 30 options:
92.3%
80.8%
114.0%
87.7%
Question 31 (2 points)
The activities of production activity control can be classified as:
I. planning.
II. implementation.
III. control.
IV. process control.
Question 31 options:
I, III, and IV
II, III, and IV
All of the above
I, II, and III
I, II, and IV
Question 32 (2 points)
Planning the flow of work requires production activity control to:
I. be sure the material needed is available.
II. be sure the tooling needed is available.
III. schedule the start and stop dates at each work center.
IV. advise the plant supervisor of future orders.
Question 32 options:
I, III, and IV
II, III, and IV
I, II, and IV
All of the above
I, II, and III
Question 33 (2 points)
Which of the following files is used by PAC for planning?
I. Shop order master file
II. Shop order detail file
III. Item master file
IV. Routing file
Question 33 options:
I and II
II and III
III and IV
I and III
All of the above
Question 34 (2 points)
Which file contains information on the efficiency and utilization of a work center?
Question 34 options:
Utilization file
Efficiency file
Routing file
Efficiency file or utilization file
Work center file
Question 35 (2 points)
Which of the following dispatching rules ignore(s) due dates?
Question 35 options:
Shortest processing time
Earliest operation due date
First come, first served, and shortest processing time
First come, first served, and earliest operation due date
First come, first served
Question 36 (2 points)
A scheduling system that assumes that the required capacity will always be available is called:
Question 36 options:
finite scheduling.
infinite scheduling.
none of the above
forward scheduling.
backward scheduling.
Question 37 (2 points)
In which of the following situations would a company probably specify by brand?
Question 37 options:
When the item to be bought is made to an industry standard
When the item to be bought is patented
When the item to be bought is patented, and when the item to be bought is made to an industry standard
When buying small quantities
When buying small quantities, and when the item to be bought is patented
Question 38 (2 points)
Purchasing departments usually have the responsibility and authority to:
Question 38 options:
none of the above
satisfy the needs of the user department.
legally commit the company to a contract.
determine price and source.
all of the above
Question 39 (2 points)
Verifying shipments for quantity and no damage is the responsibility of:
Question 39 options:
the shipping department.
the receiving department.
accounts payable.
the purchasing department.
the quality department.
Question 40 (2 points)
Which of the following statements is true about planner/buyers?
I. Planner/buyers handle more components than planners do.
II. Planner/buyers issue material releases to suppliers.
III. Planner/buyers establish supplier delivery priorities.
IV. Planner/buyers negotiate prices with suppliers.
Question 40 options:
I, II, and III are true.
II and III are true.
II, III, and IV are true.
I and II are true.
III and IV are true.
Question 41 (2 points)
Special items will generally be purchased on the basis of a quotation. The purchasing agent will select on the basis of:
Question 41 options:
the most reliable bidder.
the preference of the department that will use the item.
all of the above
none of the above
the lowest price.
Question 42 (2 points
From the buyer's point of view the best quality is:
Question 42 options:
none of the above
the least expensive.
the most expensive.
that which technically does the best job.
that which is best adapted to a particular use.
Question 43 (2 points)
Products should be specified by brand because:
Question 43 options:
price levels of brand items are low, and the number of potential suppliers is restricted.
all of the above
it is difficult to develop accurate specifications for an item.
the number of potential suppliers is restricted.
price levels of brand items are low.
Question 44 (2 points)
Which of the following departments is most likely to be familiar with waste products, the legislation governing their handling, and other uses in the company?
Question 44 options:
Maintenance.
Direct Customer Sales.
Purchasing.
Human Resources
Engineering.
Question 45 (2 points)
Which of the following is an advantage of specifying by company-developed specification?
Question 45 options:
Unless a performance specification is used, the buyer takes responsibility for performance.
None of the above is an advantage.
All of the above are advantages.
It is always possible to draw up specifications for any product.
The cost of establishing specifications is low.
Question 46 (2 points)
Forecasts are far more accurate for which of the following?
Question 46 options:
End-use components
Individual items
Short term
Product families
Question 47 (2 points)
If the February demand for a product is 5,000 units and the seasonal index for February is 0.75, what is the deseasonalized February demand?
Question 47 options:
8,750
10,000
6,667
15,000
3,750
Save
Question 48 (2 points)
Select the best statement from the following:
Question 48 options:
All of the above are true.
Usually forecast error is distributed normally about the average demand.
In a normal distribution the error will be within 1 MAD of the average about 60% of the time.
None of the above is true.
The mean absolute deviation can be used as a measure of forecast error.
Question 49 (2 points)
Which of the following methods can be used to forecast the demand for a NEW product?
Question 49 options:
Qualitative techniques
All of the above
Equation fitting
Moving averages
None of the above
Question 50 (2 points)
Which of the following statements is (are) best regarding forecasting techniques?
Question 50 options:
Intrinsic techniques use historical data.
Qualitative techniques are based on judgment.
Techniques that use external economic indicators are classified as extrinsic.
All of the above are true.
None of the above is true.
9 years ago
Purchase the answer to view it

- mgt417_midterm_-_may_2017.docx