maths assignment due i 2 hours
To formulate the linear model, we first need to find out the crash costs per week. This is calculated using the formula (Crash cost - Normal Cost) / (Normal time - Crash time). This is calculated for each of the activities as shown below
The variables that considered for are below
Let xi (i = 1 to 8) be the earliest start time of each activity andyi (i = 1 to 8) be the crash times for each activity. xs and xf are the start and finish time.
The objective function is to minimize the total crash cost. This can be represented as
Minimize : 6y1 + 12y2 + 4y3 + 6.67y4 + 10y5 + 7.3y6 + 5.75y7 + 8y8
subject to constraints
y1 < 2 (2 is the maximum time activity 1 can be crashed = 5-3 =2. similarly for all activities)
y2 < 1
y3 < 2
y4 < 3
y5 < 1
y6 < 3
y7 < 4
y8 < 2
xf < 15 (The constraint for finish time after crashing)
xs = 0 (Constraint for start time = 0)
The constraint of crashing can be represented as
x1 - xs + y1 >= 5
x2 - xs + y2 >= 3
x3 - x1 + y3 >= 4
x4 - x1 + y4 >= 6
x5 - x2 + y5 >= 5
x6 - x2 + y6 >= 7
x7 - x3 + y7 >= 9
x7 - x5 + y7 >= 9
x8 - x4 + y8 >= 9
x8 - x6 + y8 >= 8
9 years ago
5
- Religion
- In an essay (750-1,000 words), explain how the change in social values in American society in the last 50 years or so has changed the face of education in the United States. Include a description of the social issues that schools face and offer an explana
- stats homework 4 - three tutors could not do these assignments. Please only do them if you really can.
- PHI445 Personal & Organizational Ethics Week 2 DQ 1 & 2
- PHI445 Week 3, 4 & 5- Ashford University
- Python 3 Programming
- i need it in 3 hours matrix algebra
- For Prof. Nicholas
- Event Planing week5
- Mechanics of Materials