Material Planning
The forecasting department, traditionally reporting to the sale manager, has historically seen a forecast accuracy of about 60%, and this in turn causes problems for the following departments:
- Purchasing: What should we buy and how much?
- Production: What should we really build?
- Inventory management: We keep building the wrong thing.
The sales manager asked you to write her a memo, specifically addressing the following:
- How could you suggest that your new system would achieve any better levels of forecast accuracy?
- Why is forecast accuracy itself not as important under traditional methods?
- Create a chart or timeline that includes all of the following:
- Which purchase orders have to be placed, and when
- When manufacturing needs to begin, to have products delivered to a customer
- Approximate dates for all of the following:
- When the product must be shipped to meet the customer's due date
- When the application of the cover and packaging must take place to meet the customer's due date
- When the manufacturing of the widget must begin and end
- When the raw material for the widget must be ordered
- When the plastic cover must be ordered
- When the cardboard box must be ordered
- Includes notes explain your timing calculation
- Assumes all of the following conditions:
- The factory has two departments: manufacturing and packaging
- Product X consists of 3 components
- a widget manufactured in the factory with a total manufacturing lead time of 1 week
- a plastic cover purchased from vendor A with a procurement lead time of 3 weeks
- a cardboard shipping box purchased from vendor B with a procurement lead time of 4 weeks
- The widget itself is made from steel (whose lead time from vendor C is 4 weeks).
- It takes 1 day for the cover to be applied to the product and for the product to be inserted in the box in the packaging department.
- The shipping time to this customer is in 3 weeks, and you do not want it to be late or early.
- Assume you received the customer order on 1/1/20XX.
- Ignore any holidays
- Assume a 5-day work week
- The customer requires the product to arrive at his location on 3/31/2011
9 years ago
20
Answer(1)![blurred-text]()
![]()
Purchase the answer to view it

NOT RATED
- material_planning_draft.docx
Bids(1)
other Questions(10)
- FIN-534-quiz-10-week-11
- Three Assignments Due.
- information security
- BUS 401 Final Exam Rating A
- in at least 200 words answer the following
- CJA 364 Week 3 Learning Team Assignment Search and Seizure Paper
- Declaration of independence
- BUS340
- Subject: International Trade 1. Compare and contrast earnings of labor and earnings of capital and land in the specific-factors model. (75 words)
- need soc2000 help