Machine shop

profilemarlas
13.
 
 
 

The following table shows orders to be processed at a machine shop as of 8:00 a.m. Monday. The jobs have different operations they must go through. Processing times are in days. Jobs are listed in order of arrival.


 

JobProcessing
Time (Days)
Due Date
(Days)
Remaining Number
of Operations
A8        202
B10        184
C5        255
D11        173
E9        354


 

a.Determine the processing sequence at the first work center using each of these rules: (1) First come, first served, (2) Slack per operation.


 

  
  Sequence for First come, first served  
  Sequence for Slack per operation  


 

b.Compute the effectiveness of each rule using each of these measures: (1) average completion time, (2) average number of jobs at the work center. (Round your answers to 2 decimal places.)


 

 First Come, First ServedSlack per Operation
  Average completion time[removed]         [removed]         
  Average number of jobs[removed]         [removed]         

    • 11 years ago
    • 7
    Answer(6)

    Purchase the answer to view it

    blurred-text
    • attachment
      answer_marlas.docx

    Purchase the answer to view it

    blurred-text
    NOT RATED
    • attachment
      workings.xlsx

    Purchase the answer to view it

    blurred-text
    NOT RATED
    • attachment
      workings.xlsx
    • attachment
      answer_marlas.docx

    Purchase the answer to view it

    blurred-text
    NOT RATED
    • attachment
      answer_changes.docx

    Purchase the answer to view it

    blurred-text
    NOT RATED
    • attachment
      workings.xlsx

    Purchase the answer to view it

    blurred-text
    NOT RATED
    • attachment
      problem_16.8.docx