Job 101_Cost Allocation
Job 101 was started in December 2014 and finished in January 2015. It was the only unfinished job at the end of December 2014
It is estimated that total overhead costs (MOH) for 2015 will be $120,000
The activity base used to apply MOH are the estimated direct labor costs of $150,000
JOB 101 (200 units)
Direct Materials Direct Labor Manufacturing Overhead
Jan 1 Beg Balance $ 10,000 $ 8,000 4,000
Jan 10 2,000 2,000
Jan 25 1,000 8,000 _________
TOTAL 13,000 18,000
Using the information above, answer the following questions:
1. What was the balance in work in process inventory Jan 1, 2015?
what numbers are you using?
2. What is the MOH application rate used last year?
How did you find this number?
3. What is the MOH application rate that will be used in 2015?
How did you find this number?
4. The total cost of Job 101 after MOH is applied for work done in 2015: __________
5. Make the journal entry for the materials requisitioned to job 101 this period:
6. Make the journal entry for the labor for job 101 this period.
7. Make the journal entry to apply overhead to job 101 this period.
8. Make the journal entry when the job was completed.
9. The job was sold for $55,000 on account. Record the journal entries required for the sale
and to record cost of goods sold.
This is the only job in 2015. Do the cost of manufacturing schedule and a partial income statement for 2015
(down to gross profit) below:
11 years ago
Purchase the answer to view it

- job_101_cost_allocation.xlsx