it project management
Question 1: [2 marks]
Give examples of when you would prepare rough order of magnitude (ROM), budgetary, and definitive cost estimates for a project providing 100 new laptops for students to borrow on campus. Use the following techniques for creating a cost estimate for the laptop project:
a) analogous, b) parametric, and c) bottom-up.
Question 2: [3 marks]
Assume you have completed three months of the project. The BAC was $200 000 for this six month project. Also assume the following:
PV = $120,000
EV = $100,000
AC = $90,000
a) What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?
b) How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget?
c) Use the CPI to calculate the estimate at completion (EAC) for this project. Is the project performing better or worse than planned?
11 years ago
3
- PSY 1001
- please help
- 1. which two political act during the reconstruction Era recognized the centrality of slavery to the civil war? 2. what were the origins and meaning of the fourteenth amendment of the 1860? how did the reconstruction " reconstruct" the nation for the ?
- SCI 230 Week 4 CheckPoint Mendel on Patterns of Inheritance
- PSYCH 540 Week 2 Individual Assignment Ethics In Psychological Research
- PSY 450 Week 2 Team Assignment Traditional and Nontraditional Culture Paper
- BUS 475 Integrated Business Topics Week 2 DQ
- Describe the various factors that contribute to attitude (affects, behaviors, and cognitions). •Explain the role of prejudice, aggression, and attraction
- What percent of 86 is 50 to the nearest whole percent?
- MGT 350 Week 2 Thinking Styles