Hr operations

profilemiabai
TaskPredecessorNormal TimeCrash TimeCrash Cost Slope
ANone77NA
BA33NA
CA84600
DA44NA
EB65600
FC, D22NA
GE, F66NA
HF53400
IG, H44NA
JI22NA

In a 3- to 4-page Microsoft Word document, address the following:

  • Draw the AON project network using Microsoft Project, Microsoft Visio, or some other tool capable of creating such a network. Perform a critical path analysis for the network and calculate the ES, EF, LS, and LF times.
  • Calculate the slack time for each activity.
  • Identify the critical path.
  • Assume that the organization will receive a $400 bonus for each day the duration of the project is shortened. The organization is also responsible for paying the crash cost associated with shortening the schedule. To maximize the net profit, identify which task you should crash and by how much.

Support your responses with examples.

Cite any sources in APA format.

 
    • 12 years ago
    • 10
    Answer(3)

    Purchase the answer to view it

    blurred-text
    NOT RATED
    • attachment
      scheduling.operations_management.doc

    Purchase the answer to view it

    blurred-text
    NOT RATED
    • attachment
      mgt_3059_week_2_assignment_2.docx
    • attachment
      mgt_3059_week_2_assignment_2.xlsx

    Purchase the answer to view it

    blurred-text
    NOT RATED
    • attachment
      mgt_3059_week_2_assignment_2_project_network_activity_with_bonus_1000.mpp
    • attachment
      mgt_3059_week_2_assignment_2_project_network_activity_with_bonus_1000.xlsx
    • attachment
      mgt_3059_week_2_assignment_2_project_network_activity_with_bonus_400.docx
    Bids(0)