In a 1-page Word document, consider the following activities and their durations. The original project schedule, using early activity starts, is shown below.
Activity | Task | Predecessors | Duration | Activity Cost |
A | Sign Contract | None | 5 days | $5,000 |
B | Design Survey | A | 3 days | $1,500 |
C | Identify Audience | A | 7 days | $1,000 |
D | Run Survey | B, C | 30 days | $6,000 |
E | Analyze Results | D | 5 days | $3,000 |
F | Create Presentation | E | 5 days | $1,000 |
G | Present to Client | E, F | 2 days | $3,000 |
- Reconfigure the chart above into a critical path diagram for project scheduling similar to the diagram shown in this module's lecture.
- What is the duration of the project?
- How much slack is currently available in the non-critical path?
- How long are the project and feeder buffers?
10 years ago
15
Answer(1)![blurred-text]()
![]()
Purchase the answer to view it

- written_assignment_on_citical_path.doc
Bids(1)
other Questions(10)
1-page Word document Review a Project Schedule and Evaluate for Potential Issues
NOT RATED9 years ago