The Holden Company uses a job-costing system at its Sydney, Ashfield plant. The plant has a machining department and a finishing department. Holden uses normal costing with two direct-cost categories (direct materials and direct manufacturing labor) and two manufacturing overhead cost pools (the machining department with machine hours as the allocation base, and the finishing department with direct manufacturing labor costs as the allocation base). The 2013 budget for the plant is as follows:

 

 

Machining Department

Finishing Department

Manufacturing overhead costs

$9,750,000

$6,296,000

Direct manufacturing labor costs

$920,000

$3,330,000

Direct manufacturing labor-hours

42000

145000

Machine-hours

215000

53000

 

 

Required:

 

1. Prepare an overview diagram of Holden’s job-costing system. (8 Marks)Required

2. What is the budgeted manufacturing overhead rate in the machining department? In the finishingdepartment?(4 Marks)

3. During the month of January, the job-cost record for Job 369 shows the following:

 

Machining Department

Finishing Department

Manufacturing overhead costs

                               17,300

                              5,200

Direct manufacturing labor costs

                                     380

                              1,600

Direct manufacturing labor-hours

60

60

Machine-hours

142

40

 

Compute the total manufacturing overhead cost allocated to Job 369.(4 Marks)

4. Assuming that Job 369 consisted of 600 units of product, what is the cost per unit?(10 Marks)

5. Amounts at the end of 2013 are as follows:

 

Machining Department

Finishing Department

Manufacturing overhead costs

                       13,100,000

                      9,360,000

Direct manufacturing labor costs

                             950,000

                      6,450,000

Machine-hours

235000

41000

 

Compute the under-or over allocated manufacturing overhead for each department and for the Sydney plant as a whole.(10 Marks)

 

6. Why might Holden use two different manufacturing overhead cost pools in its job-costing system?(4 Marks)

 

 

    • 11 years ago