  Using High-Low to Calculate Fixed Cost, Calculate the Variable Rate, and Construct a Cost Function


Pizza Vesuvio makes specialty pizzas. Vesuvio's controller wants to calculate the fixed and variable costs associated with labor used in the restaurant. Data for the past eight months were collected:

Month                                     Labor Cost($)              Employee Hours
January                        6,900                                       350
February                      8,040                                       540
March                          9,799                                       640
April                            9,687                                       600
May                             8,390                                       470
June                             7,350                                       340
July                              9,390                                       560
August                        7,431                                       300

In your calculations, round the variable rate per employee to the nearest cent. If required, round your final answers to the nearest cent.

1. Using the high-low method, calculate the fixed cost of labor.
                        $ 

2. Using the high-low method, calculate the variable rate.
$ per employee hour

3. Using the high-low method, construct the cost formula for total labor cost.
Total labor cost = $ + ($ × Employee hours)