•Your Microsoft® Project file

 

◦A schedule table reporting ES, LS, EF, LF, and slack for each activity

 

Change the timescale to months and weeks. The estimated duration of the project is 135 days.

 

 

 

Activity

Description

Preceding Activity

Activity Time

1

POM+Project

None

1 day

2

R&D Product Development

None

44 Days

3

Need survey

None

20 days

4

Set product specs

3

15 days

5

Shelf life report

4

10 days

6

Nutrition report

4

5 days

7

Secure fruit suppliers

5,6

20 days

8

Initial production

None

83 days

9

Equipment rehab

4

30 days

10

Production trials

7,9

15 days

11

Quality trials

10

20 days

12

Quality metrics

11

5 days

13

Quality training

12

15 days

14

Distribution

None

45 days

15

Market testing

5,6

30 days

16

Packet design

15

15 days

17

Select distributors

5,6

25 days

18

Legal

None

14 days

19

Complete FDA certification

7,15

15 days

20

Register trademark

7,15

5 days

21

Prepare product launch

13,16,17,19,20

15 days

 

  • 10 years ago