Activity | Description | Preceding Activity | Activity Time |
1 | POM+Project | None | 1 day |
2 | R&D Product Development | None | 44 Days |
3 | Need survey | None | 20 days |
4 | Set product specs | 3 | 15 days |
5 | Shelf life report | 4 | 10 days |
6 | Nutrition report | 4 | 5 days |
7 | Secure fruit suppliers | 5,6 | 20 days |
8 | Initial production | None | 83 days |
9 | Equipment rehab | 4 | 30 days |
10 | Production trials | 7,9 | 15 days |
11 | Quality trials | 10 | 20 days |
12 | Quality metrics | 11 | 5 days |
13 | Quality training | 12 | 15 days |
14 | Distribution | None | 45 days |
15 | Market testing | 5,6 | 30 days |
16 | Packet design | 15 | 15 days |
17 | Select distributors | 5,6 | 25 days |
18 | Legal | None | 14 days |
19 | Complete FDA certification | 7,15 | 15 days |
20 | Register trademark | 7,15 | 5 days |
21 | Prepare product launch | 13,16,17,19,20 | 15 days |
10 years ago
20
Purchase the answer to view it

- information_systems_homework.rar
- Roles and Responsibilities of Industrial Safety and Security Officers
- Assignment due in 5 hours
- This is for Prof Xavier ONLY.
- Business Law in the Workplace
- Ashford University: Performance and Racism Assignment
- external financing
- Research Paper Due 1/30
- PHI103 Informal Logic WEEK 3 ASSIGNMENT STEREOTYPES
- Econ hw help
- QUESTION 1 Define and describe the general environment and the industry environment and how competitive forces influence the firm. What is the external environment affecting Dr. Pepper?