Finance

profileswthny007
a.

Calculate the net present value of the following project for discount rates of 0, 50, and 100%: (Leave no cells blank - be certain to enter "0" wherever required. Do not round intermediate calculations. Round your answers to 2 decimal places.)

 

C0C1C2
−$7,376.25+$4,740.00+$20,025.00

 

Discount RateNPV         
0%          $ [removed]  
50%          [removed]  
100%          [removed]  

 

b.What is the IRR of the project?

 

  IRR[removed] %  