Elias Corporation has the following cost records for February 2013.
(Not rated)
(Not rated)
Elias Corporation has the following cost records for February 2013.
Indirect factory labor | $ 4,612 | Factory utilities | $ 401 | |
Direct materials used | 22,361 | Depreciation, factory equipment | 1,585 | |
Work in process, 6/1/12 | 2,769 | Direct labor | 31,084 | |
Work in process, 6/30/12 | 3,633 | Maintenance, factory equipment | 1,792 | |
Finished goods, 6/1/12 | 4,609 | Indirect materials | 2,268 | |
Finished goods, 6/30/12 | 7,429 | Factory manager's salary | 3,315 |
Instructions: Prepare a cost of goods manufactured schedule for February 2013.