Earthwork
Earthwork
A pit, 750' long, 80' wide, and 2' deep, needs to be filled and compacted with select structural fill in Seattle, WA. The swell factor is 20 percent, and the shrinkage factor is 15 percent. The soil is to be retrieved from a location 5 miles away. It will be compacted using sheepsfoot compactors.
Source: Modified from the textbook, Mubarak, S. (2012). How to estimate with RSMeans data: Basic skills for building construction (4th ed.). Hoboken, NJ: John Wiley.
Using the provided data and CostWorks, estimate:
- The total volume of soil to be retrieved
- The total number of 12-cubic-yard dump trucks needed, each loaded at 110 percent capacity
- The total bare cost and the total cost, including overhead & profit (O&P) for the entire operation
Submission Requirements:
Submit the CostWorks format, including all the data and calculations used to estimate the cost of the structural fill.
10 years ago
5
Answer(0)
Bids(0)
other Questions(10)
- Use the following information to answer questions 5-8. Kaufmann, Inc. is a textile firm specializing in linen tablecloths
- The readership of a certain magazine has the following characteristics : 30% are younger than 26, 20% are
- Treating Test Anxiety. Relaxation Training (RT) and Physical Fitness Training (PFT) were compared as methods for treating test anxiety among male
- Study the following Excel regression output for an analysis attempting to predict the number of union members in the
- 4 paragraph
- Finance
- All ammonium compounds, which contain an ammonium ion (NH4+) and a negative ion, are thermally unstable. A. Discuss two ways that ammonium compounds decompose when they are heated. What chemical reaction is involved in the thermal decomposition of ammon
- SEC 280 Week 3 Case Study-Asymmetric_and_Symmetric_Encryption
- When two lines are graphed on a coordinate grid and the equatiowns graph the same line, how many coordinate pairs...
- Humanities unit 6 Discussion