Durkee Corporation keeps careful track of the time required to fill orders
1. Durkee Corporation keeps careful track of the time required to fill orders. The times required for a particular order appear below:
Wait time........ Hours: 10.7
Process time......Hours: 0.9
Inspection time...... Hours: 0.4
Move time ...... Hours: 2.3
Queue time ...... Hours: 4.5
Required:
A.) Determine the throughput time.
B.) Determine the manufacture cycle efficiency (MCE),
C.) Determine the delivery cycle time.
2. Jane, Inc., is considering the purchase of a machine that would cost $430,000 and would last for 6 years, at the end of which, the machine would have a salvage value of $47,000 The machine would reduce labor and other costs by $109,000 per year. Additional working capital of $4,000 would be needed immediately, all of which would be recovered at the end of 6 years. The company requires a minimum pretax return of 17% on all investment projects.
Required:
Determine the net present value of the project.