1.

Question :

(TCO A) Risk management is

 

Student Answer:

 

[removed] exposure to the consequences of uncertainty

 

 

CORRECT

 culture, processes and structures directed towards the management of potential opportunities

 

  

[removed] determining if risk is tolerable

 

  

[removed] all of the above

 

  

[removed] none of the above

 

 

 
 

 

 2.

Question :

(TCO A) The objective of risk management is to

 

Student Answer:

 

[removed] reduce organizational costs

 

  

[removed] increase organizational costs

 

  

[removed] transfer organizational costs

 

 

CORRECT

[removed] identify and manage significant risks

 

 

INCORRECT

identify and manage all risks

 

 

 
 

 

 3.

Question :

(TCO B) The qualitative risk analysis step assigns

 

Student Answer:

 

[removed] each risk a list

 

 

CORRECT

[removed] each risk a priority

 

  

[removed] each project action a priority

 

 

INCORRECT

all of the above

 

  

[removed] none of the above

 

\

 
 

 

 4.

Question :

(TCO C) Risk treatment strategies should include

 

Student Answer:

 

[removed] risk prevention

 

  

[removed] impact mitigation

 

  

[removed] risk sharing

 

 

CORRECT

all of the above

 

  

[removed] none of the above

 

 

 

 

 5.

Question :

(TCO C) Insurance is commonly used as a ___________ strategy.

 

Student Answer:

 

[removed] well known risk deferment

 

 

INCORRECT

risk elimination

 

  

[removed] cost

 

  

[removed] all of the above

 

 

CORRECT

[removed] none of the above

 

 

 

 

 

 6.

Question :

(TCO C) Insurance is a ____ sharing strategy.

 

Student Answer:

CORRECT

well known risk

 

  

[removed] little used risk

 

  

[removed] cost

 

  

[removed] all of the above

 

  

[removed] none of the above

 

I

 8.

Question :

(TCO A) Project risk management is a topic of major current interest. Identify at least two organizations that are currently addressing project risk management and explain how they are addressing project management?

Question :

(TCO B) Explain the purpose of the semi-quantitative risk assessment process.

TCO B) Explain the method of the semi-quantitative risk assessment process.

 