critical path and the overall project completion time
(Not rated)
(Not rated)
The following table lists seven different activities that need to be performed to complete the
project. Also listed are the immediate predecessors for each activity and the optimistic, most
likely, and pessimistic time estimates for each activity
Activity: A, B, C, D, E, F, G
Predecessor: none, none, A, A, C, D, B,
Optimistic: 3, 2, 5, 6, 3, 1, 8
Most likely: 5, 3, 7, 6, 4, 8, 9
Pessimistic: 7, 4, 15, 6, 5, 9, 10
Sketch and analyze the network associated with this problem. That is, determine the earliest and
the latest start and finish and the slack for each activity. Also determine the critical path and the
overall project completion time.