Stadium Builders RS are preparing a bid to build a new 50,000 seat baseball stadium in Delaware. The construction must start on June 1, 2013 and be completed in time for the 2016 season. A penalty clause of $90,000 per day of delay beyond April 20, 2016 is written into the contract.
Willie Robertson, the president of the company could net as much as $1.9MM on the project. He also said if they are successful, the prospects for future projects are very good since there is a projected interest in building new ball parks with modern luxury boxes.
Given the information provided below for the stadium project. answer the following questions:
Assignment A
- Will the project be completed by the April 20th deadline?
- How long will it take?
- What is the critical path for the project?
- Based on the schedule, would you recommend that the new owner pursue this construction contract? Why or Why not?
Assignment B
- Include a one page Gantt chart for the stadium schedule.
ID | Activity | Duration | Predecessor(s) |
1 | Baseball Stadium |
|
|
2 | Get permits | 10 days | --- |
3 | Clear stadium site | 70 days | --- |
4 | Demolish building | 30 days | 3 |
5 | Set up construction site | 70 days | 4 |
6 | Drive support piling | 120 days | 3 |
7 | Pour lower concrete bowl | 120 days | 6 |
8 | Pour main concourse | 120 days | 4,7 |
9 | Install playing field | 90 days | 4,7 |
10 | Construct upper steel bowl | 120 days | 4,7 |
11 | Install seats | 140 days | 8, 10 |
12 | Build luxury boxes | 90 days | 8, 10 |
13 | Install jumbotron | 30 days | 8, 10 |
14 | Stadium infrastructure | 120 days | 8, 10 |
15 | Construct steel canopy | 75 days | 11 |
16 | Light installation | 30 days | 15 |
17 | Build roof supports | 90 days | 7 |
18 | Construct roof | 180 days | 17 |
19 | Install roof tracks | 90 days | 17 |
20 | Install roof | 90 days | 18, 19 |
21 | Inspection | 20 days | 9,12,14,16,20 |
|
|
|
|
|
|
|
|