CP-3 Indoor Theme Park Project

profilecarine3

For CP3 you will set your CP2 project and document deliverable aside and start fresh. This is a new project. Your task is to use this document and the data provided to create a project file using Microsoft Project. The data below will establish a project budget and schedule baseline with Budget = $4,449,920.00 and a highly desired completion date of 12/17/08.

 

Next we will create a scenario for a time that is 'out in the future' here. We are fast forwarding the project and loading some fictional information to create a scenario for you to analyze using Earned Value and then provide course corrections to the project.

The project at this future date shows that our project is not performing very well. However, you are given the opportunity to make some changes to the project to still complete it on the desired date of 12/17/08.